lcls injector commissioning dates (2006 - 2007)

1
1 LCLS LCLS Injector Commissioning Dates (2006 - Injector Commissioning Dates (2006 - 2007) 2007) Dec 22: Dec 22: PPS Certified PPS Certified Dec 20-Jan 1: Dec 20-Jan 1: Holidays Holidays Jan 2: Jan 2: VVS’s switched on for PEP-II (RF power VVS’s switched on for PEP-II (RF power available) available) Jan 15: Jan 15: L0a, L0b, L1 RF processing begins L0a, L0b, L1 RF processing begins Feb. 1: Feb. 1: X-band RF X-band RF processing begins processing begins Feb 20: Feb 20: GTL beamline installation complete GTL beamline installation complete Mar 6: Mar 6: Virtual cathode fully characterized (ready to Virtual cathode fully characterized (ready to install gun) install gun) Mar 7: Mar 7: RG gun installation begins – laser rate to 30 RG gun installation begins – laser rate to 30 Hz Hz Mar 16: Mar 16: First laser UV-light on cathode! First laser UV-light on cathode! Mar 17: Mar 17: Electrons in GTL and gun-spectrometer Electrons in GTL and gun-spectrometer Apr 9: Apr 9: Beam through L0a, L0b and down to 135-MeV Beam through L0a, L0b and down to 135-MeV spectrometer spectrometer Apr 24: Apr 24: Beam into main linac (to TD11 dump) Beam into main linac (to TD11 dump) Nov. 4, 2006 Nov. 4, 2006

Upload: camille-vaughn

Post on 31-Dec-2015

11 views

Category:

Documents


1 download

DESCRIPTION

LCLS Injector Commissioning Dates (2006 - 2007). Dec 22: PPS Certified Dec 20-Jan 1: Holidays Jan 2: VVS’s switched on for PEP-II (RF power available) Jan 15: L0a, L0b, L1 RF processing begins Feb. 1: X-band RF processing begins Feb 20: GTL beamline installation complete - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: LCLS  Injector Commissioning Dates (2006 - 2007)

1

LCLSLCLS Injector Commissioning Dates (2006 - 2007) Injector Commissioning Dates (2006 - 2007)Dec 22:Dec 22: PPS CertifiedPPS Certified

Dec 20-Jan 1:Dec 20-Jan 1: HolidaysHolidays

Jan 2:Jan 2: VVS’s switched on for PEP-II (RF power available)VVS’s switched on for PEP-II (RF power available)

Jan 15:Jan 15: L0a, L0b, L1 RF processing beginsL0a, L0b, L1 RF processing begins

Feb. 1:Feb. 1: X-band RF X-band RF processing beginsprocessing begins

Feb 20:Feb 20: GTL beamline installation completeGTL beamline installation complete

Mar 6:Mar 6: Virtual cathode fully characterized (ready to install gun)Virtual cathode fully characterized (ready to install gun)

Mar 7:Mar 7: RG gun installation begins – laser rate to 30 HzRG gun installation begins – laser rate to 30 Hz

Mar 16:Mar 16: First laser UV-light on cathode!First laser UV-light on cathode!

Mar 17:Mar 17: Electrons in GTL and gun-spectrometerElectrons in GTL and gun-spectrometer

Apr 9:Apr 9: Beam through L0a, L0b and down to 135-MeV spectrometerBeam through L0a, L0b and down to 135-MeV spectrometer

Apr 24:Apr 24: Beam into main linac (to TD11 dump)Beam into main linac (to TD11 dump)

~July:~July: Take beam down full linac (to BSY SL2 stopper)Take beam down full linac (to BSY SL2 stopper)

Aug 31:Aug 31: ShutdownShutdown Nov. 4, 2006Nov. 4, 2006