Food and Nutrition Technical Assistance II Project (FANTA-2) Academy for Educational Development 1825 Connecticut Ave., NW Washington, DC 20009 Tel: 202-884-8000 Fax: 202-884-8432 E-mail: [email protected] Website: www.fanta-2.org Layers: Layers: Adaptations for DP’s Adaptations for DP’s M&E needs M&E needs Food and Nutrition Technical Assistance II Project (FANTA-2) Academy for Educational Development 1825 Connecticut Ave., NW Washington, DC 20009 Tel: 202-884-8000 Fax: 202-884-8432 E-mail: [email protected] Website: www.fanta-2.org

Upload: jeroen

Post on 13-Jan-2016

26 views

Category:

Documents


0 download

DESCRIPTION

Layers: Adaptations for DP’s M&E needs. Food and Nutrition Technical Assistance II Project (FANTA-2) Academy for Educational Development 1825 Connecticut Ave., NW Washington, DC 20009 Tel: 202-884-8000 Fax: 202-884-8432 E-mail: [email protected] Website: www.fanta-2.org. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Layers: Adaptations for DP’s M&E needs

Food and Nutrition Technical Assistance II Project (FANTA-2)Academy for Educational Development 1825 Connecticut Ave., NW Washington, DC 20009Tel: 202-884-8000 Fax: 202-884-8432 E-mail: [email protected] Website: www.fanta-2.org

Layers:Layers:Adaptations for DP’s Adaptations for DP’s

M&E needsM&E needs

Food and Nutrition Technical Assistance II Project (FANTA-2)Academy for Educational Development 1825 Connecticut Ave., NW Washington, DC 20009Tel: 202-884-8000 Fax: 202-884-8432 E-mail: [email protected] Website: www.fanta-2.org

Page 2: Layers: Adaptations for DP’s M&E needs

Goal of session

• Discussed in this session: – What Layers is – Types of questions asked in Layers– Where Layers is currently being implemented

• Also :– Is Layers adaptable to MYAPs’ M&E systems?

• Highly structured to address Mission needs• Can it help PVO needs?• What issues may be addressed? Outcomes? MTEs?

Page 3: Layers: Adaptations for DP’s M&E needs

Session format

• Part 1:– Presentation – Q&As

• Part 2:– Working group session: potential for use of

Layers by MYAPs

• Part 3:– Plenary wrap up

Page 4: Layers: Adaptations for DP’s M&E needs

4

What is Layers?

• Layers is a monitoring system developed to help USAID Missions fulfill their responsibilities to monitor Food for Peace Act, Title II Programs.

• According to DCHA/FFP enabling regulation:

“USAID Missions are expected to monitor CS's management of the commodities and use of grant funds. (…) Oversight and monitoring should include regularly scheduled visits to distribution centers and warehouses…”

Page 5: Layers: Adaptations for DP’s M&E needs

5

Typical (pre-Layers) Title II monitoring• Title II sites are periodically visited by USAID staff to verify

compliance on commodity storage, disposal and distribution.

• If discrepancies are found, the partner is notified.

Weaknesses of this approach:

• Only commodities monitored, not program activities.

• Site selection based on convenience--no systematic sampling.

• Only sites visited are assessed; no program-wide monitoring.

• Designed for USAID’s use; little helpful feedback to partners.

• No methodological guidance to field monitors (sampling, indicators).

Page 6: Layers: Adaptations for DP’s M&E needs

6

What Layers brings:• Allows monitoring of program activities as

well as commodity management

• Draws from a random sample of sites: results are representative of the entire program

• Uses standardized indicators

• Shares findings with partners to improve program performance

Page 7: Layers: Adaptations for DP’s M&E needs

7

What is LQAS (Lot Quality Assurance Sampling)?

• LQAS is a sampling method developed to control the quality of manufactured goods produced in ‘lots.’

• LQAS takes a small random sample and tests the sample for quality.

• The sample will tell if program activities (agriculture, health, etc.) are meeting/not a performance benchmark

• The sample size is chosen so that there is a high probability of determining what indicators in a given activity are meeting or not meeting the performance benchmark.

• A MYAP may get a “No” on some indicators and a “Yes” on others within the same activity type.

Page 8: Layers: Adaptations for DP’s M&E needs

8

Limitations and words of cautions about LQAS and Layers

• Layers only shows whether a CS has met the benchmark for an indicator or not (e.g. does it meet 95% “fail free” standard?). It does not provide point estimates (i.e. “% of sites where standard is met”)

• LQAS is good at accurately identifying a CS that is above the upper benchmark or below the lower benchmark. Classification errors are unfrequent but may occur when CS results are “borderline” (fall between UT & LT).

• Planned sample size must be met—else, error rates increase which may lead to erroneous conclusion that the CS performs below the benchmark).

Page 9: Layers: Adaptations for DP’s M&E needs

9

• A popular sample size is n=19. This does not have to be so: what sets the final n is: benchmark level, UT/LT, error rate

• Calculating the right sample size for a LQAS survey is done with easy-to-use tools found on the FANTA-2 website, athttp://www.fantaproject.org/layers/reference.shtml

• The tool tells us:

– How many sites to sample (e.g., 25)

– How many of those sites must receive a “yes” (e.g., 21) in order to meet the benchmark for that indicator (called the “decision rule”).

– Alpha and beta error rates based on sample size and upper and lower thresholds

Sampling for LQAS

Page 10: Layers: Adaptations for DP’s M&E needs

10

Page 11: Layers: Adaptations for DP’s M&E needs

11

Indicators Used by Layers

• Layers can monitor many aspects of a program to ensure the overall success of the CS in delivering services.

• Several modules of indicators/questionnaires already exist. Those are modified and adapted to each country/program.

• New indicators can also be created.

Page 12: Layers: Adaptations for DP’s M&E needs

12

Examples of Common Layers Indicators by Type of Activity

Commodity Mgt MCHN FFW Education

Commodity movements

–Ledger/physical inventories agree?

–Tracking system in place and adequate?

Immunization services

–Cold chain OK?

–Any vaccines stock-outs, past due?

Infrastructures

–Structure respects EIA, engineering standards?

Education

–Attendance as expected?

–Kitchen adequate?

Storage conditions

- Commodities clean and secure?

Nutrition intervention

–Staff knowledgeable?

–Posters present?

–Scales calibrated?

Irrigation, water systems

–Maintenance ensured?

Teaching quality

–Teachers present, equipped?

–School building meets standards?

Page 13: Layers: Adaptations for DP’s M&E needs

Data entry using PDAs Use of PDAs facilitates the work of enumerators

• PDAs reduce the likelihood of error– Automatically selects form/module/question to ask– Verify coherence with earlier responses– Minimizes coding error, poor transcript – Data entry errors eliminated

• PDAs are economical– No need to print paper forms– Changes to the questionnaires easily made mid course– Data entry is eliminated, & info is immediately usable

• PDAs are flexible:– GPS and other electronic equipment can be adapted– Reference tools can be included (manuals, calculators, etc)– Decision making tools can be included (drill down,

decision/diagnosis trees)BUT

• PDAs require programming, specialized training and IT support

Page 14: Layers: Adaptations for DP’s M&E needs

14

Page 15: Layers: Adaptations for DP’s M&E needs

15

Page 16: Layers: Adaptations for DP’s M&E needs

16

Page 17: Layers: Adaptations for DP’s M&E needs

17

Layers Data Analysis

• Analysis with LQAS is simple:

– Count the number of “yes” responses for each indicator.

– Apply the decision rule in each case.

# of “Yes” responses ≥ decision rule: YES – this indicator meets the benchmark

# of “Yes” responses < decision rule: NO - this indicator does not meet the benchmark

Page 18: Layers: Adaptations for DP’s M&E needs

Setting up Layers: what’s involved?

• Staff infolved:– Mission FFPO– PVO (IT Manager, M&E manager, COP)– FANTA/2, TANGO

• Steps:– Initial planning– Sampling (create TUS, chose sites)– Adapt model (questionnaire by sector, etc)– Train data collectors – Collect, tabulate and analyze data– Communicate results, recommendations to Awardees

• Entire process: 7 mo (first run); shorter afterward

18

Page 19: Layers: Adaptations for DP’s M&E needs

19

Timeline for setting up Layers in a new Country*

Assumes 1mo data collection via external contractor

Page 20: Layers: Adaptations for DP’s M&E needs

Final Step: Sample LAYERS Report Letter

1. Findings for commodity warehouses (documentation, management and storage)

Successes:• Routine documentation procedures at MCHN sites are followed

appropriately. • Storage management is appropriate: storage sites are clean,

weatherproof and safe; and the food stored in those sites is kept correctly.

Challenges:• The ledgers did not concur with existing inventories in many sites.

This is most serious and needs urgent attention.• Minor problems related to ventilation, rodent infestation and use of

the warehouse for other purposes were detected in a few sites.

Letter ends with a Summary of Recommendations. PVOs expected to reply and state how they will address the recommendations.

Page 21: Layers: Adaptations for DP’s M&E needs

Where is Layers used?

• Currently used in Haiti, Guatemala, Madagascar, Ethiopia

• Currently undergoing preparation in Chad, Mali, Uganda, Malawi, Bangladesh

• Will be progressively implemented in all FFP focus countries, as they turn over to new Development Programs

21

Page 22: Layers: Adaptations for DP’s M&E needs

Extensions of Layers

• Outcome Monitoring– Same general approach as Layers– Adds the following dimensions:

• Focuses on Outcome level indicators (random sample of target population, not sites)

• Implemented in several “supervision areas”– parametric results possible (means, etc) – Identifies areas that need reinforcement

• Can feed into other activities (Mid Term Evaluations? Operations Research? Etc)

22

Page 23: Layers: Adaptations for DP’s M&E needs

Focuses on Outcome Indicators

EXTERNAL PROCESSES

Human resourcesFinancial resources Physical facilities Equipment, etc

INPUTS

Training Setting up systems Supervision of activitiesNetworking

PROCESSES

N of mothers trained N of working cold chains FP methods distributed

OUTPUTS OUTCOMES

EBF, ORS, etcImmunization rateCPR

IMPACTS

Better nutritionReduced morbiditySmaller families

Monitoring indicators(yearly measurements)

Evaluation indicators(BL, MTE, Final Eval)

Rainfaill, prices, policies, etc.

Program-level info Beneficiary-level info

Page 24: Layers: Adaptations for DP’s M&E needs

Why outcome and not impact? Relates to expected size of change bt/years

Page 25: Layers: Adaptations for DP’s M&E needs

OM Indicators are highly streamlinedMalaria

1. % HHs with child< 5 having at least one ITN2. % children <5y in malaria-risk areas who selpt under ITN the previous night3. % women who received 2+ doses of SP for malaria during last pregnancy4. % children <5y w/fever in last 2w who received AMT w/in 24hrs from onset of fever

Maternal and Child Health (MCH)5. % women who gave birth who had a PP visit w/in 3 days6. % newborns receiving essential newborn care7. % women seen at ANC 4+ times during last pregnancy8. % births attended by a doctor, nurse or trained midwife9. % children 12-23mo who received 3rd dose of DTP by 12mo 10. % children 12-23mo who received vit A supplement in last 6 months11. % children <5yr who are > -2 SD of median W/A12. % infants <6mo exclusively breastfed in past 24hrs 13. % children 0-59mon w/diarrhea in last 2 weeks treated with ORS14. % children 0-59 mo w/ARI in last 2 weeks taken to appropriate health provider15. % children 12-23mo fed a MAD

Family Planning Reproductive Health (FP/RH)16. % women 15-49yr (or partner) using a modern method of contraception17. % need satisfied by modern method of FP18. % women 15-49yr stating desire to space birth 36mo+ or to limit births

Page 26: Layers: Adaptations for DP’s M&E needs

Use of PMAs (Program Management Areas )

n=21 This design allows us to saywhether the region as a whole passes or fails the benchmark

Page 27: Layers: Adaptations for DP’s M&E needs

What PMAs Add

n=21

n=21

n=21

n=21

n=21

n=21 n=21 n=21 n=21 n=21n=105

Dividing the total area into PMAs allows to:(i) State whether each PMA fulfills the benchmark orients corrective action(ii) Compare PMAs to one another identify “positive deviants”(iii) Generate parameters from the total (n=105) estimate coverage (means, etc)

Page 28: Layers: Adaptations for DP’s M&E needs

Sampling design: dictated by key indicators*

Subsample Group of Indicators this Subsample will Document

Mothers of Children 0-5mo

Exclusive Breast Feeding rates

Mothers of Children 0-11mo

Pre/Postpartum Care, including Birth Attendance, Essential Newborn Care, Pre/Postpartum visits, Vit A, TT, and Iron Folate

Mothers of Children 12-23mo

Immunization and Vitamin A, Infant and Young Child Feeding

Mothers of Children 0-59mo

Malaria, Illness management (diarrhea, fever, ARI), Anthropometry

Women of Reproductive age (15-49yrs)

Family Planning, including CPR, Needs Satisfied, Birth Spacing; as well as Reproductive Health

*Recall: LQAS requires that all samples be completed

Page 29: Layers: Adaptations for DP’s M&E needs

Putting the pieces together: Example of Sampling Matrix with

5 PMAs, 5 Subsamples

SUBSAMPLES

PMAs Motherchildren

0-5m

Motherchildren 0-11m

MotherChildren

12-23

Motherschildren

0-59m

Women Reprod. age

(15-49y)

Total

Chimaltenango HZ 21 21 21 21 21 105

Quetzaltenango HZ 21 21 21 21 21 105

Quiche HZ 21 21 21 21 21 105

San Marcos HZ 21 21 21 21 21 105

Totonicapan HZ 21 21 21 21 21 105

TOTAL 105 105 105 105 105 525

Page 30: Layers: Adaptations for DP’s M&E needs

Part 2: Adapting Layers to Awardees’ needs

• How do we adapt those concepts to the needs of T-II Awardees?– Yearly monitoring of outputs? outcomes?– Use in MTE?– Use in BL/FE?– Use in special studies?

• Issues to keep in mind:– Integration between Mission and MYAP data– Why sample? (if PVOs must visit all sites)– Monitor what? (Outputs, Outcomes, Impacts?)

30

Page 31: Layers: Adaptations for DP’s M&E needs

Method for Part 2

• Breakout in working groups. • Each WG discusses a possible use of Layers.

Examples of options (others welcome): – Yearly monitoring– Mid term evaluations– Baseline/Final evaluations– Special studies

• Report in plenary after. Have audience review and critique each approach

31

Page 32: Layers: Adaptations for DP’s M&E needs

32

This presentation is made possible by the generous support of the American people through the support of the Office of Health, Infectious Disease and Nutrition, Bureau for Global Health, and the Office of Food for Peace, Bureau for Democracy, Conflict and Humanitarian Assistance, United States Agency for International Development (USAID) under terms of Cooperative Agreement No. GHN-A-00-08-00001-00, through the Food and Nutrition Technical Assistance II Project (FANTA-2), managed by the Academy for Educational Development (AED). The contents are the responsibility of AED and do not necessarily reflect the views of USAID or the United States Government.

Food and Nutrition Technical Assistance II Project (FANTA-2)Academy for Educational Development 1825 Connecticut Ave., NW Washington, DC 20009Tel: 202-884-8000 Fax: 202-884-8432 E-mail: [email protected] Website: www.fanta-2.org