ladotd construction specifications: parts ii, iii & iv
TRANSCRIPT
MARK MORVANT, P.E. ASSOCIATE DIRECTOR, RESEARCH
LADOTD Construction
Specifications: Parts II, III & IV
Presentation Outline
General Introduction
Part II Site Preparation & Earthwork
Part III Base Courses
Part IV Surface Courses
Questions
Committee Members
Member Affiliation
Mark Morvant LTRC
John Wells Contracts and Specifications
Danny Smith Construction Section
Gavin Gautreau LTRC
Neal West District 58
Matthew Ziecker District 05
Jeff Lambert Pavement & Geotechnical Design Section
Bernard Sincavage Construction Section
Bert Wintz Materials
Scott Nelson FHWA
B.J. Carlin W.E. McDonald & Son
Dale Willis Gilchrist Construction
Part II: Site Preparation and Earthwork
201 Clearing and Grubbing
202 Removing or Relocating Structures and Obstructions
203 Excavation and Embankment
204 Temporary Erosion Control
Part II: Site Preparation and Earthwork
201 Clearing and Grubbing
201.04 Clearing and Grubbing
Redefined clearing and grubbing areas to limits of right-of-way or construction limits (whichever is greater) or as defined in the plans.
Requires contractor to submit an operations plan for burning operations to the engineer for review and comment.
Part II: Site Preparation and Earthwork
202 Removing or Relocating Structures and Obstructions 202.01 – Clarifies that removal of structures and obstructions
visible at the time of bid, including all related structures or as designated in the plans.
202.05.1 - Asbestos: Updated in accordance with DEQ policy and forms
202.05.5 - Allows contractor to retain steel members when lead paint is removed
202.05.8 Other Regulated Materials (ORM): Allows material not specifically defined to be disposed of as a solid waste in the appropriate solid waste landfill. i.e asphalt shingles, noninfectious medical waste, and etc. not
covered in other items.
Part II: Site Preparation and Earthwork
203 Excavation and Embankment 203.02 – Clarifies that the bidder shall determine the suitability of
the on-site soils to meet specifications of Section 203.
203.03 – Hydraulic Excavation (new title): Distinguishes Drainage Excavation from Cleaning Existing Ditches. Establishes a bid item for cleaning of existing ditches in order to
reestablish flow lines on the existing alignment
203.06.1 Deleted Selected Soil: Moved definition of soil type to Pipe Backfill specification
203.14.2.1 – Plan Quantity: Added clarification that quantity revisions will not be considered without advanced notice to both parties and unless original cross-sections have been taken.
Part II: Site Preparation and Earthwork
204 Temporary Erosion Control 204.01 Description – Develop and comply with a Storm
Water Pollution Prevention Plan (SWPPP) approved by the Department in accordance with the department’s Notice of Intent (NOI).
204.03.5.2 Other Retention Systems Other silt retention systems may be used if approved by the Materials Engineer Administrator.
204.06 Construction Requirements - When temporary erosion and pollution control measures are
required due to the contractor's negligence or failure to install permanent controls, such work shall be performed at the contractor’s expense.
When erosion control devices have been properly maintained and exceeded their useful life, they may be replaced with approval and paid for under appropriate pay items as directed.
Part III: Base Courses
301 Class I Base Course
302 Class II Base Course
303 In-Place Cement Stabilized and Treated Base Courses
304 Lime Treatment
305 Subgrade Layer
306 Scarifying and Compacting Roadbed
307 Permeable Bases
308 In-Place Cement Treated Base Courses
309 In-Place Cement Treated Subgrade
Part III: Base Courses
301 – Class I Base Course – Maintained due to references
301.01 Description
Soil Cement
Crushed Stone or Crushed Slag
Cement Stabilized Sand Clay Gravel
Asphaltic Concrete Base Course on Treated Layer
Recycled Portland Cement Concrete
Blended Calcium Sulfate
Part III: Base Courses
301 – Class I Base Course – Maintained due to references
301.01 Description
Submit a dust control plan to address weather, sight clearance, operational procedures, traffic control and any other project specific concerns. Failure to maintain sight clearance will result in the Engineer stopping contractor operations.
For dust sensitive areas designated on plans, the plan must also include environmental requirements.
In inaccessible areas, PCC or Asphalt may be used at three-quarters of the base thickness
Part III: Base Courses
301.03.4 Automatic Finishing Machine– The approved automatic finishing machine shall be capable of operating from an erected stringline or Global Positioning System (GPS) and laser system …
301.16.2 Thickness Tolerances - When crushed stone base or recycled concrete base is used over soil cement base, the individual base layer tolerances shall be as noted above, and the total base course under-thickness shall not exceed 3/4 inch (20mm).
Part III: Base Courses
302 Class II Base Courses
Allowable base types same as 301
Dust plan requirements same as 301
Asphalt and Portland cement thicknesses same as 301
Thickness Tolerances same as 301
Part III: Base Courses
302.02.1 Soils for Soil Cement - Acceptance of soils with organic contents between 2 to 5 percent may be allowed determination of increased cement percentages based on
lab testing.
Maximum cement rate allowed will be 14 percent by volume.
Perform the laboratory testing specified above at the contractor’s expense.
The laboratory used must be approved by the Materials Engineer Administrator .
Part III: Base Courses
Section 303 In-Place Cement Stabilized & Treated Base Courses – Combined 308 into this section
Cement Stabilization – existing roadbed materials
typically 8.5 inches thick
design compressive strength:300 psi
Cement Treatment – existing roadbed materials
typically 12 inches thick
Design compressive strength: 150 psi
Part III: Base Courses
Section 303 In-Place Cement Stabilized & Treated Base Courses
303.02.1 Determination of Cement Rate
303.02.1.1 Predetermined (Plan Specified) –cement
percentage as shown on the plans
303.02.1.2 Non-Predetermined- District Laboratory will determine the percent of cement from job samples
303.02.1.3 - Contractor Selected Cement Type - If Type IP or IS is selected at the option of the contractor, lab testing will be by independent lab at expense of contactor to also include durability testing.
Part III: Base Courses
Section 303 In-Place Cement Stabilized & Treated Base Courses
303.11.2 Thickness Requirements - When approved, corrections may be made by re-stabilizing or retreatment the existing material in accordance with this section and the cement content may be reduced from design contents with approval of the District Laboratory Engineer.
Part III: Base Courses
Section 304 Lime Treatment
304.07.2 Type C Compact to 93.0 percent of maximum dry density. When conditions, such as a yielding subgrade, make this impractical or
detrimental, establish an optimum rolling pattern to the satisfaction of the engineer.
304.07. 4 Type E Compact to 95 percent of maximum dry density. When traffic conditions warrant
When an adequate rolling pattern has been established that has demonstrated that density is being achieved, the engineer may reduce density frequency testing requirements to expedite construction.
A change in subgrade materials will require testing at the original frequency until a new rolling pattern is established.
Added for safety issue for two lane roadways.
Part III: Base Courses
Section 304 Lime Treatment
304-01 Lime Ton (Mg)
304-02 Lime Treatment (Type B) Square Yard
304-03 Lime Treatment (Type C) Square Yard
304-04 Lime Treatment (Type D) Square Yard
304-05 Lime Treatment (Type E) Ton
304-06 Lime Treatment (Type E) Square Yard
Part III: Base Courses
Section 305 Subgrade Layer
305.04.1.2 Treatment
When the contractor elects to use Portland-Pozzolan Cement the rate of cement shall be determined at the contractor’s expense.
The design compressive strength criteria - 100 psi.
P.I. Percent by Volume
0-15 9 6 % cement
16-25 6 % lime and 9 6 % cement
26-35 9 % lime and 9 6 % cement
Part III: Base Courses
Section 306 Scarifying and Compacting Roadbed
No major changes
Section 307 Permeable Bases
No major changes
Section 308 In-Place Cement Treated Base Courses
Deleted and combined with 303
Part III: Base Courses
Section 309 In-Place Cement Treated Subgrade (new) 309.02.1 Description
primarily used for existing roadway reconstruction
typically for subgrade soils with a PI < 20
design compressive strength criteria: 100 psi
309.02.1 Determination of Cement Rate
303.02.1.1 Predetermined - Plan Specified
303.02.1.2 Non-Predetermined - District Laboratory
303.02.1.3 Contractor Selected Cement Type – Contractor expense
If the contract documents do not specify a percent cement, 6 percent will be used for treated subgrades for bid purposes.
Part III: Base Courses
Section 309 In-Place Cement Treated Subgrade 309.04.1 Treatment and Pulverization
When field conditions warrant: Yielding subgrade: establish an optimum rolling pattern to the
satisfaction of the engineer. Wet subgrade: The engineer has the option of increasing or
decreasing the percentages of cement. Increase the cement content by one percent by volume for
every 3 percent of moisture content above optimum. When traffic conditions warrant
When an adequate rolling pattern has been established that has demonstrated that density is being achieved, the engineer may reduce density frequency testing requirements to expedite construction.
A change in subgrade materials will require testing at the original frequency until a new rolling pattern is established.
Part IV: Surface Courses
401 Aggregate Surface Course
402 Traffic Maintenance Aggregate Surfacing
403 Aggregate Roadway Surfacing
Part IV: Surface Courses
401 Aggregate Surface Course 401.04 Shoulder Construction
On existing surfaces, where only aggregate surface course is to be placed, remove vegetation, shape and satisfactorily compact the surface prior to placing aggregate surfacing.
For new or reconstructed surfaces construct subgrade in accordance with Section 203
401.07.2 Aggregate Surfacing Stone and Recycled Portland Cement Concrete (Material specifically defined)
401.07.4 Lime Treated Materials Sand-Clay-Gravel (Material specifically defined)
Part IV: Surface Courses
Section 402 Traffic Maintenance Aggregate Surfacing 402.01 DESCRIPTION Furnish and construct surfacing for maintenance of traffic on
driveways, pipe crossings, short term traffic on raw embankment, slope corrections, or other disturbed roadway sections ….
402.02 MATERIALS Stone Recycled Portland Cement Concrete Reclaimed Asphaltic Pavement Asphalt Concrete Flowable Fill (excavatable) Other materials must be approved in advance
Part IV: Surface Courses
Section 402 Traffic Maintenance Aggregate
402.01.1 Mainline Surfacing - in accordance with Table 402-1 at the posted speed limit during construction.
Aggregate surface is allowed only when all aggregate table criteria are met.
Hard surface is required when any of hard surface table criteria is met.
Surface Type ADT Posted Speed mph
Time Surfacing to Remain in Place Under Traffic
Aggregate 5000 or Less 45 or less 4 weeks or Less1
Hard Surface
Greater than 5000
Greater than 45 Greater than 4 weeks
Part IV: Surface Courses
Section 402 Traffic Maintenance Aggregate 402.01.1 Mainline Surfacing
Hard surface Asphaltic Concrete or Flowable Fill 6 inches minimum ½” longitudinal tolerance and properly drain Asphalt Concrete :89 percent of maximum density
Should a contractor’s operation or sequence of construction extend the time an aggregate surface is to remain in place under traffic beyond four weeks, hard surfacing will be at no additional pay.
Should a contractor’s operation or sequence of construction necessitate the use of aggregate in areas requiring hard surface, place the hard surface within 48 hours. Placement of aggregate surfacing in this case will be at no direct pay.
Part IV: Surface Courses
Section 402 Traffic Maintenance Aggregate
402.01.2 Non-mainline surfacing
Use either aggregate or hard surfacing for turnout, drives, crossovers and other non-mainline segments of roadway. If hard surfacing is used it shall meet the requirements of 402.01.1.
Part IV: Surface Courses
402.06 PAYMENT Aggregate materials reused by blading to adjacent locations will be
at the contractor’s expense.
Aggregate material reloaded, hauled, and re-used will be paid at 50 percent of the contract unit price.
402-01 Mainline Traffic Maintenance Surfacing Cubic Yard (Aggregate) (Vehicular Measurement) 402-02 Mainline Traffic Maintenance Surfacing (Hard) Square Yard 402-03 Non-Mainline Traffic Maintenance Surfacing Cubic Yard (Aggregate) (Vehicular Measurement)
MARK MORVANT, P.E. ASSOCIATE DIRECTOR, RESEARCH
Questions?