Sub:- Quotation for Shell Structure works of Residential Building
(Ground + 1 Podium + 13 Upper Floors) Sub Structure & Super Structure
Work (RCC, Block work, Int. Plaster, Ext. Plaster & Waterproofing) at
proposed Bldg. No. 153 on Plot bearing survey No. 236/A, CTS No. 194 Pt. ofGhatkopar Village, Pantnagar, Ghatkopar (East), Mumbai.
Respected Sir,
We thank you for inviting us to quote for work under subject matter above. We are pleased to submit herewith
the quotation complete in all respect with. The rates have been quoted for in respect to the scope of works
mentioned hereafter.
The Construction of abovementioned residential building shall be carried out complete in all respect for the
scope of work described hereunder-
Rate excluding Piling
Approximate Built-up Area : 39983 Sq. Ft.(to be ascertained with final VFC Drawing)
Rate per Sq. Ft. Built-up Area : Rs. 621/- NoteThe Built up Area are subjected to change as per final drawings (Cement, Concrete and Steel will be provided by the developer free of cost at site.)
Basic rate of Steel Rs. 45,000 / M.T.
Basic rate of Cement Rs. 260 / Bag of 50kg
Basic rate of Sand Rs. 6,000 / Brass
Basic rate of Aggregate Rs. 2,400 / Brass
Basic rate of Block Rs. 4,200 / Cu. M.
The total final amount shall be evaluated on basis of actual total built-up area constructed on site on the basis of
the mode measurement describe hereunder and duly certified by the Architect. The rates shall be calculated on
basis of the mode of measurement defined hereunder to arrive at the total contract value.
-
7/27/2019 KUL NEST, 153 Pantnagar,G'par(E) - Qtn - 29.6.13
2/8
Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai
Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]
Rose Group Company
Built-up AREA Calculation
Built up area shall be calculated on following table & before start of work & accordingly payment scheduleshall be decided.
BUILTUP AREA STATEMENT FOR BUILDING
(Ground +1 Podiums + 13 Upper Floors)
Sr.No Details Area in sqft.
1. Ground Floor
2. 1st
Podium
3. 1st Floor
4. 2nd Floor
5. 3rd Floor
6. 4th Floor
7. 5th Floor
8. 6th Floor
9. 7th Floor
10. 8th Floor
11. 9th Floor
12. 10th Floor
13. 11th Floor
14. 12th Floor15. 13th Floor
Total:
Note : - The above area is approx. Actual area for payment shall be ascertained a per final VFCdrawings.
Measurement of Construction Area shall be on the following basis:
1. F.S.I. area statement including staircase, Lift Lobby 100%
2. Lift Shaft 100%
3. Ground floor (staircase, lift lobby + lifts + society room etc. ) 100%
4.Terrace at Lower floors
- Created due to top of Flat- Created additional terrace by cantilever 0%50%
5.
Balcony / Service corridor / Service Slab
- Up to 600mm- More than 600mm 50%100%
6. Staircase Room 100%
7. Lift Machine Room Nil
8. Overhead Tank Nil
9. Terrace at Roof level Nil
10.Refuge Area (a) inside bldg
(b) outside bldg
50%
50%
11. Podium & stilt 50%
12. Service ducts ( if enclosed and with slab ) 50%
-
7/27/2019 KUL NEST, 153 Pantnagar,G'par(E) - Qtn - 29.6.13
3/8
Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai
Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]
Rose Group Company
Measurements:
The site In-charge will jointly measure all the works in progress with the contractors authorized agent. Suchmeasurement will be recorded in the measurement sheets by the contractor and will be signed by representative
of Site In-charge. For the purpose of taking joint measurement, the contractors representative shall be bound to
be present whenever required by the Engineer In-Charge.
Payment Schedule to the contractor: The contractor will be paid as per the payment schedule.
Payment Schedule:
Consider following assumptions for:
a. Concrete - 1.6 Cft / Sft BUAb. Steel - 6 Kg / Sft BUA
Item
No.Item Description Quantity Unit
1 Cement Concrete 1586 Cu. M.
2 Steel Reinforcement @ 6 kg / Sq. ft. BUA 239.89 MT
3 Labour Charges 39982.99 Sq. ft. BUA
4 Formwork / Shuttering Material Charges 39982.99 Sq. ft. BUA
5 Machinery and Equipments Charges 39982.99 Sq. ft. BUA
6 Excavation 39982.99 Sq. ft. BUA
7 Masonry - Block Work (AAC Blocks)
Masonry - Block Work (AAC Blocks) - External - 6"thk. 29194 Sq. ft.
Masonry - Block Work (AAC Blocks) - Internal - 4"thk. 14085 Sq. ft.
8 Water Proofing 39982.99 Sq. ft. BUA
Plaster
9 Internal Gypsum PlasterInternal Gypsum Plaster - Ceiling 31986 Sq. ft.
Internal Gypsum Plaster - Wall 63973 Sq. ft.
10 External Plaster 76718 Sq. ft.
11 Water & Electricity Charges 39982.99 Sq. ft.
12 Anti Termite Treatment 39982.99 Sq. ft. BUA
-
7/27/2019 KUL NEST, 153 Pantnagar,G'par(E) - Qtn - 29.6.13
4/8
Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai
Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]
Rose Group Company
SCOPE OF WORK
(R.C.C., Block Masonry, Plaster & Waterproofing)
a) The specified work shall consist of Sub Structure & Super Structure Work (RCC, Block work, Int.Plaster in Kitchen, toilet & Common area and Ext. Plaster) Contract on Sq. ft. basis with Part Material
(Only cement and steel shall be supplied by Developer at Site at Free of Cost) in accordance with the
plan given by the Developer to the Contractor with specification, rates etc. given in Bill of quantities
appearing hereunder and as described more particularly herein.
b) The Developer shallprovide drawings approved by Architects/ Structural consultants to the contractorto execute the work at Site.
1. CONCRETEProving Beams, Columns, Slabs, Chajjas, Lifts Machines Room, Lift Well, Lintels, Copings, UG &OH Water Storage Tanks, R.C.C. Staircase & other Walls in Site machine mixed concrete complete
with the grade of concrete as per detailed specifications of R.C.C. Consultant including all formworks,
reinforcement and inserts required to carry on the said works. Formwork for slabs shall be 12mm ply
form.
2. MASONRYAll masonry woks shall be Block masonry as per Architectural drawings and specifications.
External masonry shall be of block 150mm thick constructed in C:M 1:5.
Internal partition wall and elevation masonry shall be constructed in half brick walls in C:M 1:5.
R.C.C. runners with required reinforcement shall be provided at mid-depth of the half brick walls.
All masonry works will be carried out in proper line, level & plumb.
3. PLASTERAll Internal walls & Ceilings shall be rendered with Gypsum Plaster.
External plaster shall be finished with 5-10mm thick plaster in C.M. 1:4 with a thickness of 6-10mm
over the backing coat.
4. WATER PROOFINGAll Toilets and terrace water proofing shall be of Brickbat / Chemical Water Proofing
-
7/27/2019 KUL NEST, 153 Pantnagar,G'par(E) - Qtn - 29.6.13
5/8
Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai
Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]
Rose Group Company
Terms and Conditions
1) The basic rate shall include all transportation, loading VAT or any other taxes applicable.2) Services tax and VAT applicable shall be paid by the owner.3) WATER AND ELECTRICITY (Free of Cost at Site)
a) Construction Water: Water required for construction purpose shall be arranged at one sourceonly by the Developer at free of cost at Site. The Contractor shall make the arrangement forstorage of the construction water and distribution, including the piping, pumping and its
distribution up to the place of works.
b) Electricity: Electricity required for construction purpose, labour hutments and generalillumination in and around the work place shall be arranged and borne by the Developer at one
source only at free of cost at site.
General common area lighting arrangement to be in scope of main contractor.
Water and Electricity as available for the work will be supplied at one point at free of cost at site
c) Water supply shall be provided free of cost at point for the labour hutments and drinking purpose.4) Bills shall be made as per the mode of the payment attached herewith. Payments against R.A. Bills
shall be paid within 7-10 days from the date of submission of the R.A. Bill.
5) Advance (5% of Contract Amount) against mobilization shall be paid to the Contractor and may berecovered from 2
ndR.A. Bill onwards @ 5% of the bill amount.
6) No retention for the value of the works executed shall be deducted from R.A. Bills on the generalcompletion of works. No Balance shall be held by the builder after the completion of work.
7) Cement and Steel shall be supplied by Developer at site free of Cost.RMC shall be supplied by the Developer with Rs.150/- pumping charges.
8) The period of completion of the works shall be 12 months (plus 3 months Grace Period), Subject toAvailability of VFC Drawing & Front.
9) Delay in execution of works due to a delay from our end either in terms of elements etc. shall beadmitted by us for a period of 30 days in all. A delay beyond shall be claimed as idle charges at the rate
of Rs. 50,000/week against idle labour, equipment, machinery etc. Also in case of unexpected delay therates shall be liable for a escalation.
10) The Site In Charge or his Senior officer appointed by the Developer shall lookafter Co-ordination ofwork and shall be authorized to inspect the work of Contractor, in way and manner as may be desired
by the Developer.
-
7/27/2019 KUL NEST, 153 Pantnagar,G'par(E) - Qtn - 29.6.13
6/8
Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai
Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]
Rose Group Company
11) In case of work for which no such specification is supplied by the Developer, such work shall becarried out in accordance to with the instructions of the Developers Site in charge and General
ManagerTechnical.
12) Insurance by the Contractor:a) The contractor shall take the appropriate insurance policies to cover all risks involved in
course of execution of work related to labour, personnel, Machinery or otherwise.
b) The contractor shall be liable for any liability, loss, claim arising in respect of any damage toproperty or in respect of personal injury or death of any person appointed by the contractor orany sub contractor engaged by the Contractor or for any loss caused on account of any act of
Contractor to any other Person or Property.
c) Contractor shall cover insurance, which he may be required under any law from time to timeor otherwise to secure himself against risk of accident etc. The Developer may ask the
Contractor to take any other specific policy provided always that Developer shall not be liablefor any peril which can be insured or otherwise.
The contractor shall comply with conditions and observe all acts, rules and Regulations
including the following:-a) Employees state Insurance Act, 1948: As applicable to himself, his employees or any other
persons engaged or employed in course of work or in work related to Contract. The Contractor
shall maintain all cards and records as required under the act in respect of employees and
payments and the contractor shall secure the agreement of the sub-contract to maintain such
records. Any expenses incurred for the contributions making contributions or maintaining
records shall be in the contractors account.
b) Workman Compensation and employees Liability Insurance: - The Contractor alone shall be
liable for compensation payable under workman compensation Act or any other law in force.
The Contractor shall take insurance policy for all the contractors employees engaged in the
performance of this contract to cover all risks. If any of the work is given on Sub-Contract, the
contractor shall require the sub-contractor to provide for compensation of workmen and also
to provide Developers liability insurance for the latters employees if such employees are notcovered under the contractors insurance.
c) Minimum wages Act:- Wages shall be paid as per the prevailing Government Rules and
records must be maintained as required.
13) Labour Laws:-a) The contractor shall comply with all rules and regulations, obligations and restrictions
imposed under the labour laws or any other law in force. The contractor will also ensure
compliance with all the regulations for all his subcontractor as regards to applicable Central,
State, Municipal and local laws. The Contractor further agrees to indemnify the Developer
from any liability or penalty which may be imposed by the Central, State, Municipal or local
authorities and also from all claims, suits or proceedings in respect thereof.
b) Notwithstanding anything contained herein, the relationship between Developer andContractor is on principal to principal basis and Developer shall not be liable for acts of
Contractor in any way whatsoever and Contractor is not agent of the Developer.
c) The Contractor further agrees and undertake as under:-
-
7/27/2019 KUL NEST, 153 Pantnagar,G'par(E) - Qtn - 29.6.13
7/8
-
7/27/2019 KUL NEST, 153 Pantnagar,G'par(E) - Qtn - 29.6.13
8/8
Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai
Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]
Rose Group Company
ForPHEENIX CONSTRUCTIONS
Partner