  • Appendix B - Capital Project Details

    cambridge.ca/budget

    KNOWTHENUMBERS.

    KNOW YOUR CITY.

  • City of Cambridge 2019 Budget Details Page 93

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00389-30 INFRASTRUCTURE DESIGN (19C014)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2020Department Reference #

    Project Type Design Division/Section Infrastructure Engineering

    Estimation Method Expert JudgementStrategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Project Details

    Project Description

    Project is to complete infrastructure/road designs for subsequent years. The purpose of the program is to have designs completed well in advance of construction schedule in order to ensure spring start-up.

    Project Justification

    Infrastructure design work is part of the process to deliver road and underground infrastructure renewal projects. A ‘Shovel ready’ project improves accessibility to any future grant programs, ensure spring start-up and receive early competitive quotes. This is the first of four phases which will transition this activity from capital to operating budgets in the future.

    Expenditure / Revenue Allocation 2019

    Financing401028.800000001 Contribution from 150,000401028.800000004 Contribution from 175,000401028.800000006 Contribution from 175,000501026 Professional Serv (500,000)

    $0Total Financing

    Project Milestones25% 50% 75% 90% 100%Percent Complete

    Expected Completion Date Jan 2020 Feb 2020 Mar 2020 May 2020 Dec 2020

    Staffing ImpactProject Manager Michael McGannOther Staffing Resources Required

  • City of Cambridge 2019 Budget DetailsPage 94

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00389-30 INFRASTRUCTURE DESIGN (19C014)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2020Department Reference #

    Project Type Design Division/Section Infrastructure Engineering

    Estimation Method Expert JudgementStrategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Category Score CommentsDescriptionPriority Ranking

    1. Project Category 180 Infrastructure design is part process for construction of infrastructure renewal projects

    Critical Projects

    2. Alignment with Corporate Strategic Direction 75 Infrastructure design is part of process to deliver projects identified within council Approved Long range Financial Plan

    Aligned with Strategic Plan goals and objectives

    3. Operating Budget Impact 50 N/ALittle or no decrease / increase in operating costs

    4. Risk Assessment 75 Will mitigate corporate risk defined as "medium"

    5. Cost/Benefit (Payback) 50 Timely infrastructure designs provides an access to infrastructure grants and competitive quotes early in the spring

    ROI difficult to measure in financial terms

    6. Service Levels 100 This is required in order to proceed with addressing the current infrastructure gap that is affecting service standards to customers.

    Address a current service level deficiency so level of service standard is achieved

    7. Infrastructure Impact 75 Ten year capital budget includes number of project addressing water and waste water system backlog. Infrastructure designs are part of process to delivery these projects.

    Indirect impact in reducing the City's total infrastructure gap

    8. Community Impact 50 Has moderate indirect impact to projects improving customer service

    Has no direct community impact

    9. Economic Impact 50 Improved/sustainable infrastructure provides moderate benefits to businesses and residents. Advanced infrastructure design work enables earlier engagement with property owners and businesses to improve co-ordination and mitigate impacts at a much earlier stage.

    Limited, minimal or no economic benefit for the local economy

    Total Score 705

  • City of Cambridge 2019 Budget Details Page 95

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00390-40 Main Street Streetscaping (19C023)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 30 December 2020Department Reference #

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Project Details

    Project DescriptionPart of the Back to the Rivers project. Focus of this project is core area beautification and enhancement of existing or new amenities through improved access to the river for residents and visitors. Streetscaping of Main Street from Ainslie Street to Shade Street. Project includes replacement of watermain and services from Wellington Street to Shade Street, replacement of water services from Ainslie Street to Wellington Street, replacement of some storm sewer from Wellington Street to Shade Street due to deterioration. Also includes replacement of sidewalk, curb, traffic signs, streetlights, benches, street trees, garbage receptacles and bike rings.

    Project JustificationPart of the Back to the Rivers project. Project addresses water and sewer backlog as per long range financial plan along with storm and road infrastructure needs. Project also includes streetscaping improvements.

    Expenditure / Revenue Allocation 2019

    Financing401039 Debenture 2,920,000501010 Salaries and Wages (30,000)501013 Other Staffing Costs (20,000)501026 Professional Serv (220,000)501051 Construction - Roads (2,000,000)501052 Construction - Storm (290,000)501053 Construction - Water (360,000)

    $0Total Financing

    Operating Impact2022202120202019Total

    Estimated Operating Costs10141-0501015 Debt Charges - Prin 174,300 174,300348,600

    Total Estimated Operating Costs 174,300174,300348,600Estimated Revenue

    10141-0401028.80 Contribution from RF-Hydro Dividend Stabiliztn R.F.

    174,300 174,300348,600

    Total Net Expenditures / (Revenues)

    Page No. : 3

  • City of Cambridge 2019 Budget DetailsPage 96

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00390-40 Main Street Streetscaping (19C023)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 30 December 2020Department Reference #

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Project Milestones25% 50% 75% 90% 100%Percent Complete

    Expected Completion Date Jul 2019 Aug 2019 Sep 2019 Oct 2019 Nov 2019

    Staffing ImpactProject Manager Jeff NyenhuisOther Staffing Resources Required

    Operating Impact2022202120202019Total

    Estimated RevenueTotal Estimated Revenue 174,300174,300348,600

    Total Net Expenditures / (Revenues)

  • City of Cambridge 2019 Budget Details Page 97

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00390-40 Main Street Streetscaping (19C023)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 30 December 2020Department Reference #

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Category Score CommentsDescriptionPriority Ranking

    1. Project Category 140 Part of the Back to the Rivers project. Focus of this project is core area beautification and enhancement of existing or new amenities through improved access to the river for residents and visitors.

    Strategic Projects

    2. Alignment with Corporate Strategic Direction 100 Part of the Back to the Rivers project. Key component of Mayor’s 2014 state of the City address and supported in principle by Council.

    Council Priority

    3. Operating Budget Impact 50 Part of the Back to the Rivers project. There will be on-going operating budget requirements to address components of the overall Back to the Rivers project.

    Little or no decrease / increase in operating costs

    4. Risk Assessment 50 Part of the Back to the Rivers project. This project is fundamental to helping Cambridge Downtowns remain competitive and vibrant while attracting new development and embracing the valuable asset we have in the downtown.

    Will mitigate corporate risk defined as "low" or little or no impact

    5. Cost/Benefit (Payback) 50 Part of the Back to the Rivers project. Benefits of new development should be able to be measured in a 5+ year timeframe through increased private investment. There will be some elements of the projects that are hard to measure in financial terms.

    ROI difficult to measure in financial terms

    6. Service Levels 75 Part of the Back to the Rivers project. Increasing level of service by providing amenities that will benefit residents and visitors.

    Increase level of service

    7. Infrastructure Impact 75 Part of the Back to the Rivers project. Projects to be funded through debenture financing.

    Indirect impact in reducing the City's total infrastructure gap

    8. Community Impact 75 Part of the Back to the Rivers project. Phased implementation of individual projects will help achieve a significant impact in improving and enhancing amenities for residents and visitors.

    Has moderate impact by improving or enhancing amenities available to the community

    9. Economic Impact 75 Part of the Back to the Rivers project. Aim of the Back to the Rivers plan is to significantly benefit the Cambridge community through private sector investment, new development, current business retention and expansion, increased tourism and broader recognition beyond the City.

    Generates a moderate economic benefit for the local economy

  • City of Cambridge 2019 Budget DetailsPage 98

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00390-40 Main Street Streetscaping (19C023)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 30 December 2020Department Reference #

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Category Score CommentsDescriptionPriority Ranking

    Total Score 690

    Maps/Attachments

  • City of Cambridge 2019 Budget Details Page 99

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00390-40 Main Street Streetscaping (19C023)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 30 December 2020Department Reference #

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Maps/AttachmentsG:\DI\ENG\Engineering Services\Capital Projects\2019\2019 Budget Process\Asset Management Maps\3230.jpg

  • City of Cambridge 2019 Budget DetailsPage 100

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00391-40 Reg Prj / King St Phase 1 & 2 (Dover to Bishop) (19C028)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2021Department Reference # AM#1553

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Project Details

    Project DescriptionPhase 1 of Preston Streetscaping. King Street East from Dover Street to Laurel Street. Project includes replacement of sanitary sewer, storm sewer, watermain including services due to deterioration. Also includes replacement of sidewalk, curb, traffic signs, streetlights, benches, street trees, garbage receptacles and bike rings. Focus of this project is core area beautification and enhancement of existing or new amenities through improved access to the river for residents and visitors.

    Project JustificationUnderground infrastructure will be replaced along with road reconstruction to avoid social, traffic disruption and to gain cost efficiency. Project scope includes street scape improvement work on King Street from Dover St to Bishop St. Key component of Mayor’s 2014 state of the City address and supported in principle by Council. Project addresses water and sewer backlog as per long range financial plan along with storm and road infrastructure needs.

    Expenditure / Revenue Allocation 2019

    Financing401028.800000004 Contribution from 1,560,000401028.800000006 Contribution from 2,150,000401039 Debenture 1,990,000501041 Funding to Ext Agenc (5,700,000)

    $0Total Financing

    Operating Impact2022202120202019Total

    Estimated Operating Costs10141-0501015 Debt Charges - Prin 118,800 118,800237,600 Debt cost for $1.79M only as $200k

    debt covered by savings in 16C032 (operating impacts already built in)

    10169-0501023 Program Suppl & Mat 5,0005,000 Streetscaping upgrades will require aditional work for snow removal.

    Total Estimated Operating Costs 123,800118,800242,600Estimated Revenue

    10141-0401028.80 Contribution from RF-Hydro Dividend Stabiliztn R.F.

    118,800 118,800237,600

    $5,000 $5,000Total Net Expenditures / (Revenues)

    Page No. : 8

  • City of Cambridge 2019 Budget Details Page 101

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00391-40 Reg Prj / King St Phase 1 & 2 (Dover to Bishop) (19C028)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2021Department Reference # AM#1553

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Project Milestones25% 50% 75% 90% 100%Percent Complete

    Expected Completion Date Aug 2019 Dec 2019 Aug 2020 Sep 2020 Dec 2020

    Staffing ImpactProject Manager Jeff NyenhuisOther Staffing Resources Required

    Operating Impact2022202120202019Total

    Estimated RevenueTotal Estimated Revenue 118,800118,800237,600

    $5,000 $5,000Total Net Expenditures / (Revenues)

  • City of Cambridge 2019 Budget DetailsPage 102

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00391-40 Reg Prj / King St Phase 1 & 2 (Dover to Bishop) (19C028)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2021Department Reference # AM#1553

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Category Score CommentsDescriptionPriority Ranking

    1. Project Category 200 Cost contribution to Regional project for road reconstruction and underground infrastructure replacement. Project is also part of the Back to the Rivers project. Focus of this project is core area beautification and enhancement of existing or new amenities through improved access to the river for residents and visitors.

    Mandatory Projects

    2. Alignment with Corporate Strategic Direction 100 Part of the Back to the Rivers project. Key component of Mayor’s 2014 state of the City address and supported in principle by Council.

    Council Priority

    3. Operating Budget Impact 50 Part of the Back to the Rivers project. There will be on-going operating budget requirements to address components of the overall Back to the Rivers project.

    Little or no decrease / increase in operating costs

    4. Risk Assessment 50 Part of the Back to the Rivers project. This project is fundamental to helping Cambridge Downtowns remain competitive and vibrant while attracting new development and embracing the valuable asset we have in the downtown.

    Will mitigate corporate risk defined as "low" or little or no impact

    5. Cost/Benefit (Payback) 50 Benefits of new development should be able to be measured in a 5+ year timeframe through increased private investment. There will be some elements of the projects that are hard to measure in financial terms. Long term ROI due to reduced water losses, I&I and improved traffic safety.

    ROI difficult to measure in financial terms

    6. Service Levels 100 Address service level deficiency by replaceing shared thin walled CI watermain and sanitary sewer. Part of the Back to the Rivers project. Increasing level of service by providing amenities that will benefit residents and visitors.

    Address a current service level deficiency so level of service standard is achieved

    7. Infrastructure Impact 100 Direct impact to water and sanitary infrastructure gap. Part of the Back to the Rivers project. Projects to be funded through debenture financing.

    Direct impact in reducing the City's total infrastructure gap

    8. Community Impact 75 Part of the Back to the Rivers project. Phased implementation of individual projects will help achieve a significant impact in improving and enhancing amenities for residents and visitors.

    Has moderate impact by improving or enhancing amenities available to the community

  • City of Cambridge 2019 Budget Details Page 103

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00391-40 Reg Prj / King St Phase 1 & 2 (Dover to Bishop) (19C028)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2021Department Reference # AM#1553

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Category Score CommentsDescriptionPriority Ranking

    9. Economic Impact 75 Part of the Back to the Rivers project. Aim of the Back to the Rivers plan is to significantly benefit the Cambridge community through private sector investment, new development, current business retention and expansion, increased tourism and broader recognition beyond the City.

    Generates a moderate economic benefit for the local economy

    Total Score 800

  • City of Cambridge 2019 Budget DetailsPage 104

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00391-40 Reg Prj / King St Phase 1 & 2 (Dover to Bishop) (19C028)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2021Department Reference # AM#1553

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Maps/AttachmentsG:\DI\ENG\Engineering Services\Capital Projects\2019\2019 Budget Process\Asset Management Maps\3628.jpg

  • City of Cambridge 2019 Budget Details Page 105

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00392-40 Regional Poject - Franklin Blvd Improvements Year 2 North (19C033)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2021Department Reference # AM1620

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Project Details

    Project Description

    Reconstruction of Franklin Blvd from North of Avenue Road to North of Clyde Road. Project includes replacement of water, sanitary, storm and road infrastructure due to deterioration. Also includes new multi-use trails, curb, traffic signs, and utility relocations.

    Project Justification

    Project addresses water and sewer backlog as per long range financial plan along with storm and road infrastructure needs. Project includes a proposed roundabout at Avenue Road and Multi use trails.

    Expenditure / Revenue Allocation 2019

    Financing401028.800000006 Contribution from 1,300,000401028.800000044 Contribution from 568,000501030 Regional Services (1,868,000)

    $0Total Financing

    Project Milestones25% 50% 75% 90% 100%Percent Complete

    Expected Completion Date Aug 2019 Dec 2019 Aug 2019 Dec 2019 Dec 2021

    Operating Impact2022202120202019Total

    Estimated Operating Costs10173-0501023 Program Suppl & Mat 5,0005,000 Incremental maintenance cost for new

    watermainTotal Estimated Operating Costs 5,0005,000

    $5,000 $5,000Total Net Expenditures / (Revenues)

  • City of Cambridge 2019 Budget DetailsPage 106

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00392-40 Regional Poject - Franklin Blvd Improvements Year 2 North (19C033)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2021Department Reference # AM1620

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Staffing ImpactProject Manager Jeff NyenhuisOther Staffing Resources Required

  • City of Cambridge 2019 Budget Details Page 107

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00392-40 Regional Poject - Franklin Blvd Improvements Year 2 North (19C033)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2021Department Reference # AM1620

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Category Score CommentsDescriptionPriority Ranking

    1. Project Category 120 Cost contribution to Regional project for road widening and underground infrastructure replacement

    Enhance / Growth Related Projects

    2. Alignment with Corporate Strategic Direction 75 Approved cost contribution by council as per DC By-Laws 2014

    Aligned with Strategic Plan goals and objectives

    3. Operating Budget Impact 50 Reduced number of potholes, road patrolling cost and associated operating and maintenance cost

    Little or no decrease / increase in operating costs

    4. Risk Assessment 75 Significant risk due to increased number of potholes and hindrance to growth due to traffic chaos

    Will mitigate corporate risk defined as "medium"

    5. Cost/Benefit (Payback) 50 Long term ROI due to reduced water losses and I&I

    ROI difficult to measure in financial terms

    6. Service Levels 75 Addresses substandard roadway in terms of condition and capacity

    Increase level of service

    7. Infrastructure Impact 100 Addresses water and sanitary infrastructure gap

    Direct impact in reducing the City's total infrastructure gap

    8. Community Impact 50 Reduces traffic chaos to accommodate future growth along with improved water quality

    Has no direct community impact

    9. Economic Impact 50 Improves transportation system with City of Cambridge to generate growth potential resulting assessment growth and jobs

    Limited, minimal or no economic benefit for the local economy

    Total Score 645

  • City of Cambridge 2019 Budget DetailsPage 108

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00392-40 Regional Poject - Franklin Blvd Improvements Year 2 North (19C033)

    Prepared By Yogesh ShahApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2021Department Reference # AM1620

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Maps/AttachmentsG:\DI\ENG\Engineering Services\Capital Projects\2019\2019 Budget Process\Asset Management Maps\3450.jpg

  • City of Cambridge 2019 Budget Details Page 109

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00396-40 Melrose St and Frederick St Reconstruction (19C038)

    Prepared By Michael McGannApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 01 December 2020Department Reference # AM3322

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Project Details

    Project Description

    Reconstruction of Melrose St from Eagle St to North St and Frederick St from Sherring St to Vine St. Project includes replacement of watermain, sanitary sewers, storm sewers and road infrastructure due to deterioration. Also includes replacement of sidewalk, curb, traffic signs, streetlight relocation and utility relocation.

    Project Justification

    Project addresses water and sewer backlog as per long range financial plan along with storm and road infrastructure needs.

    Expenditure / Revenue Allocation 2019

    Financing401027.800000039 Contribution from 540,000401028.800000001 Contribution from 70,000401028.800000004 Contribution from 370,000401028.800000006 Contribution from 440,000501010 Salaries and Wages (90,000)501026 Professional Serv (10,000)501027 General Maint Contr (50,000)501051 Construction - Roads (240,000)501052 Construction - Storm (305,000)501053 Construction - Water (395,000)501054 Construction - Sewer (330,000)

    $0Total Financing

    Project Milestones25% 50% 75% 90% 100%Percent Complete

    Expected Completion Date May 2019 Jul 2019 Sep 2019 Oct 2019 Dec 2020

  • City of Cambridge 2019 Budget DetailsPage 110

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00396-40 Melrose St and Frederick St Reconstruction (19C038)

    Prepared By Michael McGannApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 01 December 2020Department Reference # AM3322

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Staffing ImpactProject Manager Scott MacDonaldOther Staffing Resources Required Project Engineer (110hrs), Construction Inspector (0.5 FTE),

    Manager of Field Services (40 hrs), Water Operator(40 hrs)

  • City of Cambridge 2019 Budget Details Page 111

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00396-40 Melrose St and Frederick St Reconstruction (19C038)

    Prepared By Michael McGannApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 01 December 2020Department Reference # AM3322

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Category Score CommentsDescriptionPriority Ranking

    1. Project Category 180 Critical project to address Water and sewer backlog

    Critical Projects

    2. Alignment with Corporate Strategic Direction 75 Addresses Water and sewer backlog as per council approved long range financial plan. Provide new sidewalks for AODA compliance

    Aligned with Strategic Plan goals and objectives

    3. Operating Budget Impact 50 Reduces ongoing operation and maintenance cost for periodic flushing of sanitary sewer, WM breaks, Water losses, Pothole repairs

    Little or no decrease / increase in operating costs

    4. Risk Assessment 75 Improves water quality. Reduces claims due to potholes, sidewalk trip and fall, sewer blocks etc. Provide pedestrian safety with additional sidewalks

    Will mitigate corporate risk defined as "medium"

    5. Cost/Benefit (Payback) 50 Long term ROI due to reduced water losses and I&I

    ROI difficult to measure in financial terms

    6. Service Levels 100 Improves water quality in the area. Provides improved pedestrian access

    Address a current service level deficiency so level of service standard is achieved

    7. Infrastructure Impact 100 Water and Sewer backlog reductionDirect impact in reducing the City's total infrastructure gap

    8. Community Impact 50 Pedestrian access and AODA compliance. Improved water quality. Improved service reliability due to reduced water main breaks and sewer blockages

    Has no direct community impact

    9. Economic Impact 50 N/ALimited, minimal or no economic benefit for the local economy

    Total Score 730

  • City of Cambridge 2019 Budget DetailsPage 112

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00396-40 Melrose St and Frederick St Reconstruction (19C038)

    Prepared By Michael McGannApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 01 December 2020Department Reference # AM3322

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Maps/AttachmentsG:\DI\ENG\Common\Scott MacDonald\2019 Budget\3322.jpg

  • City of Cambridge 2019 Budget Details Page 113

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00397-40 Elliott St and Burrows St Reconstruction (19C040)

    Prepared By Michael McGannApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2020Department Reference # AM2628

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Project Details

    Project Description

    Reconstruction of Elliott Street from Henry Street to East Street and Burrows Street from Elliott Street to end. Project includes replacement of water, sanitary, storm and road infrastructure due to deterioration. Also includes replacement of sidewalk, curb, traffic signs and utility relocation.

    Project Justification

    Project addresses water and sewer backlog as per long range financial plan along with storm and road infrastructure needs. Project includes upsizing of existing 100mm watermain.

    Expenditure / Revenue Allocation 2019

    Financing401027.800000039 Contribution from 850,000401028.800000001 Contribution from 80,000401028.800000004 Contribution from 660,000401028.800000006 Contribution from 745,000501010 Salaries and Wages (135,000)501026 Professional Serv (15,000)501027 General Maint Contr (80,000)501051 Construction - Roads (315,000)501052 Construction - Storm (520,000)501053 Construction - Water (670,000)501054 Construction - Sewer (600,000)

    $0Total Financing

    Project Milestones25% 50% 75% 90% 100%Percent Complete

    Expected Completion Date Jun 2019 Jul 2019 Aug 2019 Sep 2019 Dec 2019

  • City of Cambridge 2019 Budget DetailsPage 114

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00397-40 Elliott St and Burrows St Reconstruction (19C040)

    Prepared By Michael McGannApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2020Department Reference # AM2628

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Category Score CommentsDescriptionPriority Ranking

    1. Project Category 180 Critical project to address Water and sewer backlog

    Critical Projects

    2. Alignment with Corporate Strategic Direction 75 Addresses Water and sewer backlog as per council approved long range financial plan. Provide new sidewalks for AODA compliance

    Aligned with Strategic Plan goals and objectives

    3. Operating Budget Impact 50 Reduces ongoing operation and maintenance cost for periodic flushing of sanitary sewer, WM breaks, Water losses, Pothole repairs

    Little or no decrease / increase in operating costs

    4. Risk Assessment 100 Watermain is undersized. Improves water quality. Reduces claims due to potholes, sidewalk trip and fall, sewer blocks etc. Provide pedestrian safety with additional sidewalks

    Will mitigate corporate risk defined as "significant"

    5. Cost/Benefit (Payback) 50 Long term ROI due to reduced water losses and I&I

    ROI difficult to measure in financial terms

    6. Service Levels 100 Improves water quality in the area. Provides improved pedestrian access

    Address a current service level deficiency so level of service standard is achieved

    7. Infrastructure Impact 100 Water and Sewer backlog reductionDirect impact in reducing the City's total infrastructure gap

    8. Community Impact 50 Pedestrian access and AODA compliance. Improved water quality. Improved service reliability due to reduced water main breaks and sewer blockages

    Has no direct community impact

    9. Economic Impact 50 N/ALimited, minimal or no economic benefit for the local economy

    Total Score 755

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00397-40 Elliott St and Burrows St Reconstruction (19C040)

    Prepared By Michael McGannApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2020Department Reference # AM2628

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Category Score CommentsDescriptionPriority Ranking

    1. Project Category 180 Critical project to address Water and sewer backlog

    Critical Projects

    2. Alignment with Corporate Strategic Direction 75 Addresses Water and sewer backlog as per council approved long range financial plan. Provide new sidewalks for AODA compliance

    Aligned with Strategic Plan goals and objectives

    3. Operating Budget Impact 50 Reduces ongoing operation and maintenance cost for periodic flushing of sanitary sewer, WM breaks, Water losses, Pothole repairs

    Little or no decrease / increase in operating costs

    4. Risk Assessment 100 Watermain is undersized. Improves water quality. Reduces claims due to potholes, sidewalk trip and fall, sewer blocks etc. Provide pedestrian safety with additional sidewalks

    Will mitigate corporate risk defined as "significant"

    5. Cost/Benefit (Payback) 50 Long term ROI due to reduced water losses and I&I

    ROI difficult to measure in financial terms

    6. Service Levels 100 Improves water quality in the area. Provides improved pedestrian access

    Address a current service level deficiency so level of service standard is achieved

    7. Infrastructure Impact 100 Water and Sewer backlog reductionDirect impact in reducing the City's total infrastructure gap

    8. Community Impact 50 Pedestrian access and AODA compliance. Improved water quality. Improved service reliability due to reduced water main breaks and sewer blockages

    Has no direct community impact

    9. Economic Impact 50 N/ALimited, minimal or no economic benefit for the local economy

    Total Score 755

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00397-40 Elliott St and Burrows St Reconstruction (19C040)

    Prepared By Michael McGannApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2020Department Reference # AM2628

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Staffing ImpactProject Manager Jamie CroftOther Staffing Resources Required Project Engineer (150hrs), Construction Inspector (0.5 FTE),

    Manager of Field Services (50 hrs), Water Operator (50 Hours)

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00397-40 Elliott St and Burrows St Reconstruction (19C040)

    Prepared By Michael McGannApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2020Department Reference # AM2628

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Staffing ImpactProject Manager Jamie CroftOther Staffing Resources Required Project Engineer (150hrs), Construction Inspector (0.5 FTE),

    Manager of Field Services (50 hrs), Water Operator (50 Hours)

  • City of Cambridge 2019 Budget Details Page 115

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00397-40 Elliott St and Burrows St Reconstruction (19C040)

    Prepared By Michael McGannApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 31 December 2020Department Reference # AM2628

    Project Type Reconstruction Division/Section Infrastructure Engineering

    Estimation Method Unit Rates (Based on Design)Strategic Alignment 1 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain

    city assets in a sustainable way.

    Strategic Alignment 2

    Strategic Alignment 3

    Maps/AttachmentsG:\DI\ENG\Engineering Services\Capital Projects\2019\2019 Budget Process\Asset Management Maps\2628.jpg

  • City of Cambridge 2019 Budget DetailsPage 116

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00400-10 General Technology Enhancements (19F001)

    Prepared By Francis VillamilApproved By Dave Bush

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 01 February 2020Department Reference #

    Project Type Technology Upgrades Division/Section Technology Services

    Estimation Method OtherStrategic Alignment 1 2.5 Focus on the responsible management of financial resources, ensuring transparency and

    accountability.

    Strategic Alignment 2

    Strategic Alignment 3

    Project Details

    Project DescriptionApplication upgrades, new licenses for existing products, new devices/hardware as required for continued operations or new corporate operations

    Project JustificationWith over 80 supported applications we need to upgrade a portion of each annually. Often time operating systems or other related components will need to be upgraded. These upgrades are needed to keep the systems operational so business units can serve the public. New services often require the purchase of supported technology, not to replace existing technology but to enhance a service, a new user requires a laptop, a new pinpad is required to provide better service at a pool, a new tablet is required staff to service their clients in a way not provide before.

    Expenditure / Revenue Allocation 2019

    Financing401028.800000001 Contribution from 200,000501050 Construct/Implement (200,000)

    $0Total Financing

    Project Milestones25% 50% 75% 90% 100%Percent Complete

    Expected Completion Date Apr 2019 Jul 2019 Oct 2019 Dec 2019 Feb 2020

    Operating Impact2022202120202019Total

    Estimated Operating Costs10127-0501019 Licensing/Subcrib 10,00010,00010128-0501020 Equipment Renew/Rep 10,00010,000

    Total Estimated Operating Costs 20,00020,000

    $20,000 $20,000Total Net Expenditures / (Revenues)

    Page No. : 28

  • City of Cambridge 2019 Budget Details Page 117

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00400-10 General Technology Enhancements (19F001)

    Prepared By Francis VillamilApproved By Dave Bush

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 01 February 2020Department Reference #

    Project Type Technology Upgrades Division/Section Technology Services

    Estimation Method OtherStrategic Alignment 1 2.5 Focus on the responsible management of financial resources, ensuring transparency and

    accountability.

    Strategic Alignment 2

    Strategic Alignment 3

    Staffing ImpactProject Manager Francis VillamilOther Staffing Resources Required Various staff in IT

  • City of Cambridge 2019 Budget DetailsPage 118

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00400-10 General Technology Enhancements (19F001)

    Prepared By Francis VillamilApproved By Dave Bush

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 01 February 2020Department Reference #

    Project Type Technology Upgrades Division/Section Technology Services

    Estimation Method OtherStrategic Alignment 1 2.5 Focus on the responsible management of financial resources, ensuring transparency and

    accountability.

    Strategic Alignment 2

    Strategic Alignment 3

    Category Score CommentsDescriptionPriority Ranking

    1. Project Category 160 Impacts every business unit in the corporation. This investment in technology is critial in assisting the city to operate efficiently. Emergency repairs and replacements are inevitable and would otherwise cause productivity issues for all business units.

    Community Planning / Maintenance / Efficiency Projects

    2. Alignment with Corporate Strategic Direction 75 Investment in Technology aligns with all departmental business needs and goals.

    Aligned with Strategic Plan goals and objectives

    3. Operating Budget Impact 50 Efficiencies may be found at that Business Unit level however to sustain the purchase of new hardware and software additional ongoing support costs are required.

    Little or no decrease / increase in operating costs

    4. Risk Assessment 75 Impact would be felt by all Business units and in some cases they would not be able to meet legislative requirements without the implementation of new technology.

    Will mitigate corporate risk defined as "medium"

    5. Cost/Benefit (Payback) 50 ROI may occur within Business units that are implementing the new technology. ROI is measured in uptime and productivity time when emergency repairs occur.

    ROI difficult to measure in financial terms

    6. Service Levels 75 Emergency repairs would address a current service level deficiency that is difficult to plan for.

    Increase level of service

    7. Infrastructure Impact 50 Replacement of faulty technology infrastructure would have no direct impact. Technologies implemented for business units could be used to assist with the tracking and replacement process of other City infrastructure.

    Has no impact in reducing the City's total infrastructure gap

    8. Community Impact 50 Technology implemented could be used by Business units to enhance amenities available to the community. Emergency repairs or replacement for existing online services for the community would be critical in providing the service.

    Has no direct community impact

    9. Economic Impact 50 May improve overall level of service.Limited, minimal or no economic benefit for the local economy

    Total Score 635

  • City of Cambridge 2019 Budget Details Page 119

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00414-40 FIRE HALL INFRASTRUCTURE - FIRE STATION 2 (19G003)

    Prepared By Steve RuffiniApproved By Cheryl Zahnleiter

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 31 December 2019Department Reference #

    Project Type Facility Renovation Division/Section Sustainable Design and

    Estimation Method Expert JudgementStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 4.1 Ensure that sustainability principles are a part of city decision- making processes.

    Strategic Alignment 3 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Project Details

    Project Description

    Projects based on lifecycle analysis of safety, service deterioration, and life expectancy of building envelope, components and materials. Also addressed: inspection report recommendations on Fire Protection, Cross Connections, Electrical Safety, Air Quality and weather proofing the building boiler replacement and lights to LED at Fire Station 2.

    Project Justification

    Deterioration of building envelope allowing for weather penetration into the building. Inefficient and dated mechanical equipment.

    Expenditure / Revenue Allocation 2019

    Financing401028.800000019 Contribution from 250,000501026 Professional Serv (25,000)501050 Construct/Implement (225,000)

    $0Total Financing

    Project Milestones25% 50% 75% 90% 100%Percent Complete

    Expected Completion Date Jun 2019 Aug 2019 Sep 2019 Nov 2019 Dec 2019

    Staffing ImpactProject Manager Steve RuffiniOther Staffing Resources Required

  • City of Cambridge 2019 Budget DetailsPage 120

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00414-40 FIRE HALL INFRASTRUCTURE - FIRE STATION 2 (19G003)

    Prepared By Steve RuffiniApproved By Cheryl Zahnleiter

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 31 December 2019Department Reference #

    Project Type Facility Renovation Division/Section Sustainable Design and

    Estimation Method Expert JudgementStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 4.1 Ensure that sustainability principles are a part of city decision- making processes.

    Strategic Alignment 3 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Category Score CommentsDescriptionPriority Ranking

    1. Project Category 180 To ensure no water can penetrate into the building to damage equipment and create hazards for occupants.

    Critical Projects

    2. Alignment with Corporate Strategic Direction 75 Ensure the integrity of the building envelope to avoid building deterioration.

    Aligned with Strategic Plan goals and objectives

    3. Operating Budget Impact 50 Will stop the deterioration minimizing further expenses.

    Little or no decrease / increase in operating costs

    4. Risk Assessment 75 All Fire Stations have exceeded lifecycle renewal. Increased risk of service interruptions.

    Will mitigate corporate risk defined as "medium"

    5. Cost/Benefit (Payback) 50 Benefits will be realized through occupant comfort.

    ROI difficult to measure in financial terms

    6. Service Levels 100 Each Fire station has accumulated deficiencies that has reduced service level

    Address a current service level deficiency so level of service standard is achieved

    7. Infrastructure Impact 100 Repariing current deterioration will reduce infrastructure gap.

    Direct impact in reducing the City's total infrastructure gap

    8. Community Impact 50 The Fire Department exists to enhance the quality of life within our community by providing innovative protection and safety to life, property and the environment.

    Has no direct community impact

    9. Economic Impact 50 There is no economic impact from the lifecycle repairs.

    Limited, minimal or no economic benefit for the local economy

    Total Score 730

  • City of Cambridge 2019 Budget Details Page 121

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00414-40 FIRE HALL INFRASTRUCTURE - FIRE STATION 2 (19G003)

    Prepared By Steve RuffiniApproved By Cheryl Zahnleiter

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 31 December 2019Department Reference #

    Project Type Facility Renovation Division/Section Sustainable Design and

    Estimation Method Expert JudgementStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 4.1 Ensure that sustainability principles are a part of city decision- making processes.

    Strategic Alignment 3 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Maps/AttachmentsG:\CFO\Sustainable Design and Development\Common\Capital Budget Info\Maps for Budget Pages\FIRE STATION 2.jpg

  • City of Cambridge 2019 Budget DetailsPage 122

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00417-40 Energy Management - Galt Arena (19G008)

    Prepared By Slobodanka LekicApproved By Cheryl Zahnleiter

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 01 June 2020Department Reference #

    Project Type Facility Renovation Division/Section Sustainable Design and

    Estimation MethodStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 3.2 Conserve and make positive contributions to our heritage districts and buildings throughout the community.

    Strategic Alignment 3 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Project Details

    Project DescriptionThis project represents the Corporate Greenhouse Gas and Energy Conservation and Demand Management Plan (Plan) for the City of Cambridge. The plan has been developed to meet the reporting requirements for O. Reg. 397/11 (the Ontario Green Energy Act (GEA)) and the voluntary Partners for Climate Protection (PCP) Program in which the City is actively participating. Replace lighting throughout (except over ice). Install low flow fixtures and toilets, replace furnace, BAS. Dolson Pool - Relamping of Dolson Pool, LED lighting installation in pool area, changerooms and common areas including lighting controls.

    Project JustificationThe City is meeting its obligations under O. Reg. 397/11 (the Ontario Green Energy Act (GEA)). In June 2018, the City completed the sixth requirement under the GEA, reporting its 2016 energy usage and GHG emissions at City-owned facilities. This Corporate Greenhouse Gas and EnergyConservation and Demand Management Plan is intended to fulfill the reporting requirements for the Green Energy Act. This project is based on Efficiency Engineering's assessment. Not doing any heritage preservation will result in an increase in deterioration of this very important heritage building.

    Expenditure / Revenue Allocation 2019

    Financing401027.800000039 Contribution from 300,000401028.800000001 Contribution from 50,000401028.800000031 Contribution from 31,000501026 Professional Serv (40,000)501050 Construct/Implement (341,000)

    $0Total Financing

    Operating Impact2022202120202019Total

    Estimated Operating Costs10140-0501038 Natural Gas (2,900) (1,300)(4,200)10140-0501039 Hydro (18,600) (8,200)(26,800)10140-0501043.80 Contribution to RF-Energy Conservation

    21,500 9,50031,000

    Total Estimated Operating Costs 0 00

    Total Net Expenditures / (Revenues)

    Page No. : 34

  • City of Cambridge 2019 Budget Details Page 123

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00417-40 Energy Management - Galt Arena (19G008)

    Prepared By Slobodanka LekicApproved By Cheryl Zahnleiter

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 01 June 2020Department Reference #

    Project Type Facility Renovation Division/Section Sustainable Design and

    Estimation MethodStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 3.2 Conserve and make positive contributions to our heritage districts and buildings throughout the community.

    Strategic Alignment 3 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Project Milestones25% 50% 75% 90% 100%Percent Complete

    Expected Completion Date Jun 2019 Oct 2019 Dec 2019 Feb 2020 Jun 2020Staffing Impact

    Project Manager Michelle VienneauOther Staffing Resources Required Manager of Construction, Facility Supervisor

  • City of Cambridge 2019 Budget DetailsPage 124

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00417-40 Energy Management - Galt Arena (19G008)

    Prepared By Slobodanka LekicApproved By Cheryl Zahnleiter

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 01 June 2020Department Reference #

    Project Type Facility Renovation Division/Section Sustainable Design and

    Estimation MethodStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 3.2 Conserve and make positive contributions to our heritage districts and buildings throughout the community.

    Strategic Alignment 3 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Category Score CommentsDescriptionPriority Ranking

    1. Project Category 160 Replace MUA, furnace, BAS, install timers on pumps. Decreases operating costs and reduces GHG.

    Community Planning / Maintenance / Efficiency Projects

    2. Alignment with Corporate Strategic Direction 75 This Energy Management Plan implementation completes Action Env9, one of the nine identified environmental actions within the CSP. Specifically, Action Env9 states: “Data gathered from 2009 to 2019 about greenhouse gas emissions are required to be reported on in annually to meet the requirements of the Green Energy Act.

    Aligned with Strategic Plan goals and objectives

    3. Operating Budget Impact 50 Best practices of energy conservation will decrease operating, maintenance and future capital costs significantly, this will be measured, monitor and tracked. The information will be reported annually.

    Little or no decrease / increase in operating costs

    4. Risk Assessment 50 Fulfills the EMP as required by the Green Energy Act.

    Will mitigate corporate risk defined as "low" or little or no impact

    5. Cost/Benefit (Payback) 75 There are lower maintenance and energy savings. If energy costs exceed trends the ROI will accelerate.

    Able to measure a positive ROI with a payback period of greater than 5 years

    6. Service Levels 50 The funding addresses mandatory planning requirements that are legislated as well as a wise investment in energy efficiencies. In energy management plan and GHG reduction program there was a planned expenditure of $750,000 per year. That program is underfunded with underfunded portions being carried as an infrastructure gap.

    Has no impact on level of service

    7. Infrastructure Impact 75 The Funding addresses and renews the energy infrastructure identified in the energy management plan.

    Indirect impact in reducing the City's total infrastructure gap

    8. Community Impact 75 The funding reduces carbon emissions and reduces energy operating costs.

    Has moderate impact by improving or enhancing amenities available to the community

    9. Economic Impact 50 A limited but a positive investment in the local green economy.

    Limited, minimal or no economic benefit for the local economy

    Total Score 660

  • City of Cambridge 2019 Budget Details Page 125

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00419-40 Outdoor Relamping - West River Walkways/Soper Park (21G006)

    Prepared By Michelle VienneauApproved By Cheryl Zahnleiter

    Project Status ApprovedYear 2019

    Project Start Date 04 January 2019Project Completion Date 31 December 2019Department Reference #

    Project Type Park Development Division/Section Sustainable Design and

    Estimation Method Expert JudgementStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 4.1 Ensure that sustainability principles are a part of city decision- making processes.

    Strategic Alignment 3 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Project Details

    Project Description

    Replacement of HPC Coach Lamps with new LED lamps and shoebox HPS fixtures with new LED fixtures for public safety issues and energy savings. Capital project for the replacement of outdoor lighting fixtures along the West River Walkways and Soper Park pathway areas to energy efficient LED lighting.

    Project Justification

    Part of back to the river enhancements on the Grand River and improving public safety on the Active Transportation Network and in keeping with the mandatory Green Energy Act in developing plans to conserve energy and reduce Green House Gases. (Soper project moved up from 2021 and combined)

    Expenditure / Revenue Allocation 2019

    Financing401028.800000001 Contribution from 80,000501026 Professional Serv (10,000)501050 Construct/Implement (70,000)

    $0Total Financing

    Project Milestones25% 50% 75% 90% 100%Percent Complete

    Expected Completion Date Jun 2019 Aug 2019 Sep 2019 Oct 2019 Dec 2019

    Operating Impact2022202120202019Total

    Estimated Operating Costs10197-0501039 Hydro (800)(800)10199-0501039 Hydro (800)(800)

    Total Estimated Operating Costs (1,600)(1,600)

    ($1,600) ($1,600)Total Net Expenditures / (Revenues)

  • City of Cambridge 2019 Budget DetailsPage 126

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00419-40 Outdoor Relamping - West River Walkways/Soper Park (21G006)

    Prepared By Michelle VienneauApproved By Cheryl Zahnleiter

    Project Status ApprovedYear 2019

    Project Start Date 04 January 2019Project Completion Date 31 December 2019Department Reference #

    Project Type Park Development Division/Section Sustainable Design and

    Estimation Method Expert JudgementStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 4.1 Ensure that sustainability principles are a part of city decision- making processes.

    Strategic Alignment 3 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Staffing ImpactProject Manager Michelle VienneauOther Staffing Resources Required Supervisor

  • City of Cambridge 2019 Budget Details Page 127

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00424-40 Fire Station #3 - Roof Replacement (19H009)

    Prepared By Steve RuffiniApproved By Cheryl Zahnleiter

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 31 December 2019Department Reference #

    Project Type Facility Renovation Division/Section Sustainable Design and

    Estimation Method Expert JudgementStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 4.1 Ensure that sustainability principles are a part of city decision- making processes.

    Strategic Alignment 3 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Project Details

    Project DescriptionReplacement of the Roof at the Fire Station # 3

    Project Justification

    • Sustainable Infrastructure project in order to keep the building in good repair which supports the community as the Fire Station is here 24/7 as well as a very busy, active Community Centre for Older Adults. • 2008 Building Audit identified the roof would be at its life span in 2018. It has been patched in a number of places over the last four years. Our program objective is to maintain our services and programs with no interruption.

    Expenditure / Revenue Allocation 2019

    Financing401028.800000019 Contribution from 150,000501026 Professional Serv (12,000)501050 Construct/Implement (138,000)

    $0Total Financing

    Project Milestones25% 50% 75% 90% 100%Percent Complete

    Expected Completion Date Jun 2019 Aug 2019 Oct 2019 Nov 2019 Dec 2019

    Staffing ImpactProject Manager Steve RuffiniOther Staffing Resources Required

    Page No. : 41

  • City of Cambridge 2019 Budget DetailsPage 128

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00419-40 Outdoor Relamping - West River Walkways/Soper Park (21G006)

    Prepared By Michelle VienneauApproved By Cheryl Zahnleiter

    Project Status ApprovedYear 2019

    Project Start Date 04 January 2019Project Completion Date 31 December 2019Department Reference #

    Project Type Park Development Division/Section Sustainable Design and

    Estimation Method Expert JudgementStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 4.1 Ensure that sustainability principles are a part of city decision- making processes.

    Strategic Alignment 3 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Category Score CommentsDescriptionPriority Ranking

    5. Cost/Benefit (Payback) 75 energy costs exceed trends the ROI will accelerate.

    Able to measure a positive ROI with a payback period of greater than 5 years

    6. Service Levels 75 Current lighting service standards within other areas have been met except in these two areas.The funding addresses mandatory planning requirements that are legislated as well as and a wise investment in energy efficiencies. In energy management plan and GHG reduction program there was a planned expenditure of $750,000 per year. That program is underfunded with underfunded portions being carried as an infrastructure gap.

    Increase level of service

    7. Infrastructure Impact 50 The Funding addresses and renews the energy infrastructure identified in the energy management plan

    Has no impact in reducing the City's total infrastructure gap

    8. Community Impact 75 Current light conditions in the area are poor particularly for the volume of users.The funding also reduces carbon emissions and reduces energy operating costs.

    Has moderate impact by improving or enhancing amenities available to the community

    9. Economic Impact 50 A limited but a positive investment in the local green economy.

    Limited, minimal or no economic benefit for the local economy

    Total Score 660

  • City of Cambridge 2019 Budget Details Page 129

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00424-40 Fire Station #3 - Roof Replacement (19H009)

    Prepared By Steve RuffiniApproved By Cheryl Zahnleiter

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 31 December 2019Department Reference #

    Project Type Facility Renovation Division/Section Sustainable Design and

    Estimation Method Expert JudgementStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 4.1 Ensure that sustainability principles are a part of city decision- making processes.

    Strategic Alignment 3 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Project Details

    Project Description

    Replacement of the Roof at the Fire Station # 3

    Project Justification

    • Sustainable Infrastructure project in order to keep the building in good repair which supports thecommunity as the Fire Station is here 24/7 as well as a very busy, active Community Centre for Older Adults. • 2008 Building Audit identified the roof would be at its life span in 2018. It has been patched in a numberf l th l t f O bj ti i t i t i i d ith

    Expenditure / Revenue Allocation 2019

    Financing401028.800000019 Contribution from 150,000501026 Professional Serv (12,000)501050 Construct/Implement (138,000)

    $0Total Financing

    Project Milestones25% 50% 75% 90% 100%Percent Complete

    Expected Completion Date Jun 2019 Aug 2019 Oct 2019 Nov 2019 Dec 2019

    Staffing ImpactProject Manager Steve RuffiniOther Staffing Resources Required

  • City of Cambridge 2019 Budget DetailsPage 130

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00424-40 Fire Station #3 - Roof Replacement (19H009)

    Prepared By Steve RuffiniApproved By Cheryl Zahnleiter

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 31 December 2019Department Reference #

    Project Type Facility Renovation Division/Section Sustainable Design and

    Estimation Method Expert JudgementStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 4.1 Ensure that sustainability principles are a part of city decision- making processes.

    Strategic Alignment 3 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Category Score CommentsDescriptionPriority Ranking

    1. Project Category 160 To ensure no water can penetrate into the building to damage equipment and create hazards for occupants.

    Community Planning / Maintenance / Efficiency Projects

    2. Alignment with Corporate Strategic Direction 75 Ensure the integrity of the building envelope to avoid building deterioration.

    Aligned with Strategic Plan goals and objectives

    3. Operating Budget Impact 50 Will insulate building and avoid water damage repairs.

    Little or no decrease / increase in operating costs

    4. Risk Assessment 75 Avoid occupant risk from water infiltration.>Will mitigate corporate risk defined as "medium"

    5. Cost/Benefit (Payback) 50 Reduced cost of damage repairs.ROI difficult to measure in financial terms6. Service Levels 50 Maintains the building envelope integrity to

    avoid program interruptionHas no impact on level of service

    7. Infrastructure Impact 100 By replacing the roof, building deterioration is avoided and maintains the integrity of the structure.

    Direct impact in reducing the City's total infrastructure gap

    8. Community Impact 50 Amenities for the community will improve.Has no direct community impact9. Economic Impact 50 Replacement of the roof will not affect the

    quality of life for City residents.Limited, minimal or no economic benefit for the local economy

    Total Score 660

  • City of Cambridge 2019 Budget Details Page 131

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00424-40 Fire Station #3 - Roof Replacement (19H009)

    Prepared By Steve RuffiniApproved By Cheryl Zahnleiter

    Project Status ApprovedYear 2019

    Project Start Date 01 February 2019Project Completion Date 31 December 2019Department Reference #

    Project Type Facility Renovation Division/Section Sustainable Design and

    Estimation Method Expert JudgementStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 4.1 Ensure that sustainability principles are a part of city decision- making processes.

    Strategic Alignment 3 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Maps/AttachmentsG:\CFO\Sustainable Design and Development\Common\Capital Budget Info\Maps for Budget Pages\ALLAN REUTER CENTRE.jpg

  • City of Cambridge 2019 Budget DetailsPage 132

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00425-40 Cemetery Improvements (19M002)

    Prepared By Corina BurnellApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 01 December 2019Department Reference #

    Project Type Community Improvement Division/Section Cemetery

    Estimation Method Expert JudgementStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Strategic Alignment 3 4.1 Ensure that sustainability principles are a part of city decision- making processes.

    Project Details

    Project DescriptionDevelopment/expansion of a new section of land in Parklawn Cemetery to accommodate 600 new grave spaces (approximately $2,000,000 in revenue) to meet community needs for interment spaces. Area is required to be developed, including installation of drainage tile, filling, leveling and grading, pinning and mapping/layout of graves, and completion of road and curbs. Repair/replace basement ramp and railing. Sealing and repair of concrete pads under existing mausoleum and columbariums. Includes other interment options such as a scattering garden and concrete pad for 3 future columbariums, a memorial wall accommodating bronze plaques, memorial path, columbarium pad to accommodate 3 future columbariums, landscaping, garden and benches.

    Project JustificationExpansion at Parklawn Cemetery is required to accommodate future community needs for interment spaces. The project is funded through the Cemetery Improvements Reserve Fund generated from previous sales of interment rights and not from tax dollars/tax base.

    Expenditure / Revenue Allocation 2019

    Financing401028.800000010 Contribution from 400,000501010 Salaries and Wages (5,000)501026 Professional Serv (100,000)501050 Construct/Implement (295,000)

    $0Total Financing

    Project Milestones25% 50% 75% 90% 100%Percent Complete

    Expected Completion Date Jun 2019 Sep 2019 Oct 2019 Nov 2019 Dec 2019

    Staffing ImpactProject Manager Shane TaylorOther Staffing Resources Required Manager of Cemeteries

    Page No. : 44

  • City of Cambridge 2019 Budget Details Page 133

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00425-40 Cemetery Improvements (19M002)

    Prepared By Corina BurnellApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 01 December 2019Department Reference #

    Project Type Community Improvement Division/Section Cemetery

    Estimation Method Expert JudgementStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Strategic Alignment 3 4.1 Ensure that sustainability principles are a part of city decision- making processes.

    Category Score CommentsDescriptionPriority Ranking

    1. Project Category 120 Well-designed cemetery sections create a space for families to commemorate their loved ones in a place of tranquility and peace. Within the design, the planning incorporates features which minimizes maintenance and ease of traffic and flow of equipment.

    Enhance / Growth Related Projects

    2. Alignment with Corporate Strategic Direction 75 Proper cemetery design meets our target of a caring community.

    Aligned with Strategic Plan goals and objectives

    3. Operating Budget Impact 50 The cemetery pricing structure of interment rights allows for the regular expansion of areas within the cemetery with no tax implications.

    Little or no decrease / increase in operating costs

    4. Risk Assessment 50 Increasing the active use of the cemetery does minimally increase the risk of liability.

    Will mitigate corporate risk defined as "low" or little or no impact

    5. Cost/Benefit (Payback) 100 Due to the cemetery pricing strategy, the sale of interment rights is cost recovery.

    Able to measure a positive ROI with a payback period of less than 5 years

    6. Service Levels 75 Interment options for families is required to maintain our service standard.

    Increase level of service

    7. Infrastructure Impact 50 Increasing the active use of the cemetery does add slightly to the city's infrastructure.

    Has no impact in reducing the City's total infrastructure gap

    8. Community Impact 75 Increasing the active use of the cemetery to provide interment spaces does add to the health and wellbeing of the community. This space allows for friends and family to gather for reflection and meditation and the interment of their loved one.

    Has moderate impact by improving or enhancing amenities available to the community

    9. Economic Impact 50 Increasing the active use of the cemetery provides opportunity for local monument companies to sell granite memorials and personalized inscriptions.

    Limited, minimal or no economic benefit for the local economy

    Total Score 645

  • City of Cambridge 2019 Budget DetailsPage 134

    Budget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028

    Project ID / Title

    Department

    A/00425-40 Cemetery Improvements (19M002)

    Prepared By Corina BurnellApproved By Hardy Bromberg

    Project Status ApprovedYear 2019

    Project Start Date 01 January 2019Project Completion Date 01 December 2019Department Reference #

    Project Type Community Improvement Division/Section Cemetery

    Estimation Method Expert JudgementStrategic Alignment 1 4.4 Manage city resources in a responsible and sustainable manner, considering future needs for

    resiliency and community adaptation.

    Strategic Alignment 2 7.3 Provide innovative leadership in the management of city assets to help plan, fund and maintain city assets in a sustainable way.

    Strategic Alignment 3 4.1 Ensure that sustainability principles are a part of city decision- making processes.

    Maps/AttachmentsG:\Facilities Management and Development\Common\Construction Admin Assistant\Budgets\Maps for Budget Pages\ParklawnCemetery.jpg

  • City of Cambridge 2019 Budget Details Page 135

    Budget DetailsAppendix B

    2019 Capital Project Detail SheetsBudget DetailsAppendix B

    2019 Capital Project Detail Sheets

    Budget Details

    City of CambridgeCapital Project Detail Sheet

    2019 - 2028