kingston bridge 2005 rev1
TRANSCRIPT
![Page 1: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/1.jpg)
Kingston Bridge ComplexKINGSTON BRIDGE COMPLEXKINGSTON BRIDGE COMPLEX
11stst JUNE 2005 JUNE 2005
Glasgow City CouncilGlasgow City Council
Land Services
![Page 2: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/2.jpg)
Kingston Bridge Complex
Complex consists of Main Bridge & Approaches
Opened 26 June 1970
Two adjacent structures 20.8 m wide
5 No. lanes of Motorway on each bridge
Main Span - 143m long
Two End Spans - 62.5m long
4,500m of Elevated Approach Structures
Designer - W A Fairhurst & Partners
Contractors - Logan, Marples Ridgeway
![Page 3: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/3.jpg)
Kingston Bridge Complex
Heart of M8 Motorway System, spans over River Clyde & carries 180,000 vehicles per day
M8 carries East West traffic between Greenock and Glasgow Airport to Edinburgh
It connects to the M80 & M77, the M74 to South and England & Clydeside Expressway & North West
![Page 4: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/4.jpg)
Kingston Bridge Complex
North Approaches - early 1967
![Page 5: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/5.jpg)
Kingston Bridge Complex
Construction of Cantilever End Span over the Broomielaw
![Page 6: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/6.jpg)
Kingston Bridge Complex
Two Bridges - 3 voids in each bridge
![Page 7: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/7.jpg)
Kingston Bridge Complex
Construction nearing Mid Span
![Page 8: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/8.jpg)
Kingston Bridge Complex
Cladding Panels on Bridge - Client Requirement
![Page 9: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/9.jpg)
Kingston Bridge Complex
Kingston Bridge Complex in 1970 - 30,000 vehicles a day
![Page 10: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/10.jpg)
Kingston Bridge Complex
Exp a nsio n J o int Exp a nsio n J o int
62.484 m 143 .256 m 62.484 m
268 .224 m
Rive r C lyd ePinne dPinne dPinne d
General Arrangement
North Pier connected to Deck By 6 Rocker Bearings
South Pier cast into Deck
Both Piers connected to Foundations by 12 Pin Bearings
Piles connect Foundations to Bedrock 30 metres below
![Page 11: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/11.jpg)
Kingston Bridge Complex
Pin Bearings at Bottom of Piers
![Page 12: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/12.jpg)
Kingston Bridge Complex
200mm bulge of North Quay Wall
In late 1980’s a number of Defects were found :-
![Page 13: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/13.jpg)
Kingston Bridge Complex
The North Pier tilted by 165mm
![Page 14: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/14.jpg)
Kingston Bridge Complex
Spalling of Concrete at base of North Pier
![Page 15: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/15.jpg)
Kingston Bridge Complex
North Comb Movement Joint remained closed
![Page 16: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/16.jpg)
Kingston Bridge Complex
South Comb Movement Joint remained open
![Page 17: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/17.jpg)
Kingston Bridge Complex
Cracks in Concrete at Midspan - Midspan dropped 300mm
![Page 18: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/18.jpg)
Kingston Bridge Complex
Combination of these factor prompted Strathclyde Regional Council to carry out:-
Quay Wall Stabilisation Works
A Design Check of the Bridge
Inspection & Assessment of the Bridge
Monitoring System on Bridge
![Page 19: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/19.jpg)
Kingston Bridge Complex
26 Prisms, 32 LVDT’s, 89 Temperature Sensors, 2 Wind Anometers & 1 Tide Gauge
![Page 20: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/20.jpg)
Kingston Bridge Complex
QUAY WALL STABILISATION CONTRACT
Concerns :-
1 If Quay Wall collapsed, rapid washout of the sands & gravels below the footing could occur
2 Also, with the horizontal load on the Pier Footing from the Tilt of the North Pier, the Pier could be unstable
Contract Awarded to Keller Concrete in May 1991
Completed July 1992 - Cost £4 million
![Page 21: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/21.jpg)
Kingston Bridge Complex
1st Major Contract Awarded
Phased strengthening of Quay Wall
![Page 22: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/22.jpg)
Kingston Bridge Complex
4,000 tonnes of Jet Grouting carried out
![Page 23: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/23.jpg)
Kingston Bridge Complex
16,000 tonnes of Rock placed infront of Quay Wall to add stability
![Page 24: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/24.jpg)
Kingston Bridge Complex
Engineers Inspecting soffit of bridge from Inspection vehicle
![Page 25: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/25.jpg)
Kingston Bridge Complex
1 Under extreme loading condition of Maximum Load on
the main span and with the end spans unloaded, there is insufficient holding down capacity of the end bearings
2 The bending capacity of the centre section of main span is inadequate
1994 ASSESSMENT
![Page 26: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/26.jpg)
Kingston Bridge Complex
INTERIM MEASURES
As a result of these findings the following Interim Measures were undertaken:-
A Traffic Management Scheme was Implemented consisting of;-
3 unrestricted lanes on each bridge 1 lane closed on each bridge
1 lane on each bridge restricted to 7.5 tonnes
Also 100 tonne of concrete blocks placed at each end of bridge
![Page 27: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/27.jpg)
Kingston Bridge Complex
DEFECTS TO BE ADDRESSED IN DESIGN
Understrength Deck - Bending Capacity midspan inadequate
Understrength Pier Shafts & Pile Caps- insufficient reinforcement in pier and pile caps
![Page 28: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/28.jpg)
Kingston Bridge Complex
165 mm Tilt of the North Pier
Lean on the North Approaches- due to sway on bridge
Riverward Load on North Pier foundations
Slipped Rocker Bearing at top of North Pier
Excess travel of South End Bearings
![Page 29: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/29.jpg)
Kingston Bridge Complex
Successful Contractor
Main Contractor Balfour Beatty
Prestressing Balvac
Jacking VSL (France)
![Page 30: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/30.jpg)
Kingston Bridge Complex
Four Phases of the Contract
1 Deck Strengthening External Prestress
2 Bridge JackingVertical and Horizontal
3 Demolition and Reconstruction of SubstructureKeeping bridge open
4 Installation of the New Bridge Bearings
![Page 31: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/31.jpg)
Kingston Bridge Complex
Four Phases of the Contract
1 Deck Strengthening External Prestress
![Page 32: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/32.jpg)
Kingston Bridge Complex
DECK CROSS SECTION AT PIERS
ExistingOpenings
8.5Mapp.
![Page 33: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/33.jpg)
Kingston Bridge Complex
CROSS SECTION AT QUARTER SPAN
CROSS SECTION AT MIDSPAN
Existing Opening
Existing OpeningVoid Height 1.5m App
Void Height 2.5m App
![Page 34: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/34.jpg)
Kingston Bridge Complex
C/L PIER
WEB ANCHORAGE
BOTTOM SLAB ANCHORAGE
BOTTOM SLAB STRENGTHENING
![Page 35: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/35.jpg)
Kingston Bridge Complex
Typical Void before Strengthening
![Page 36: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/36.jpg)
Kingston Bridge Complex
Typical Void after Strengthening
![Page 37: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/37.jpg)
Kingston Bridge Complex
In each Void the Tendons consisted of:-
5 web Tendons in pairs with 12 strands per Tendon
2 Bottom Slab Tendons with 43 strands per Tendon
![Page 38: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/38.jpg)
Kingston Bridge Complex
View of Anchor Blocks inside Bridge
![Page 39: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/39.jpg)
Kingston Bridge Complex
View of Bottom Slab Beams on Bridge Soffit
![Page 40: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/40.jpg)
Kingston Bridge Complex
Four Phases of the Contract
2 Bridge JackingVertical and Horizontal
Total Closure of Bridge during these operations - 17 Hour duration
Weight of Bridge - 52,000 tonnes
![Page 41: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/41.jpg)
Kingston Bridge Complex
Elevation showing Supplementary Piers & Jacking Systems
![Page 42: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/42.jpg)
Kingston Bridge Complex
JACKING SYSTEM B - NORTH PIER
![Page 43: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/43.jpg)
Kingston Bridge Complex
JACKING SYSTEMS A, B & C AT SOUTH PIER
![Page 44: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/44.jpg)
Kingston Bridge Complex
Vertical & Horizontal Jacking Systems
![Page 45: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/45.jpg)
Kingston Bridge Complex
![Page 46: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/46.jpg)
Kingston Bridge Complex
Kingston Bridge Complex - “Closed”
![Page 47: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/47.jpg)
Kingston Bridge Complex
NADICS Control Centre
![Page 48: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/48.jpg)
Kingston Bridge Complex
After lift 20mm gap between bottom bearing pin & upper casting
![Page 49: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/49.jpg)
Kingston Bridge Complex
Removal of Bearing Pins
![Page 50: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/50.jpg)
Kingston Bridge Complex
After longitudinal jacking of bridge top & bottom casting offset
![Page 51: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/51.jpg)
Kingston Bridge Complex
Four Phases of the Contract
3 Demolition and Reconstruction of SubstructureKeeping bridge open
![Page 52: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/52.jpg)
Kingston Bridge Complex
Pier Slide Out with Traffic on Bridge
![Page 53: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/53.jpg)
Kingston Bridge Complex
Demolition of North Pier after pier slide out
![Page 54: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/54.jpg)
Kingston Bridge Complex
Demolition of South Pier
![Page 55: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/55.jpg)
Kingston Bridge Complex
Rebuilding of North Pier
![Page 56: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/56.jpg)
Kingston Bridge Complex
Four Phases of the Contract
4 Installation of the New Bridge Bearings
![Page 57: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/57.jpg)
Kingston Bridge Complex
1250mm x 1250mm x 500mm deep Laminated rubber bearing
![Page 58: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/58.jpg)
Kingston Bridge Complex
Bearing in position on North Pier
![Page 59: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/59.jpg)
Kingston Bridge Complex
New Pier - South of River
![Page 60: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/60.jpg)
Kingston Bridge Complex
Works complete - 5 Lanes of Traffic on each Bridge
Cost of Works - £30 Million
![Page 61: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/61.jpg)
Land Services
Land Services
Kingston Bridge Complex
![Page 62: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/62.jpg)
Kingston Bridge Complex
OTHER WORKS ON THE COMPLEX
Routine Maintenance of Complex
Monitoring Works
Special Inspections
Concrete Repairs to soffit of Approach Structures
Half Joint Bearing Replacement
Cope & Parapet Refurbishment - Phases 1 & 2
Cope & Parapet Refurbishment (Central Reserve) - Phase 3
Stobcross Off & On Ramps Replacement & Associated Works
![Page 63: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/63.jpg)
Kingston Bridge Complex
MAINTENANCE OF COMPLEX
Cleaning of Traffic Management Scheme
Cleaning of Gullies
Cleaning of Carriageway Channels
Cope and Parapet Repairs
![Page 64: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/64.jpg)
Kingston Bridge Complex
MONITORING & ASSOCIATED WORKS
Calibration of Monitoring Equipment
Maintenance of Monitoring Equipment
![Page 65: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/65.jpg)
Kingston Bridge Complex
SPECIAL INSPECTIONS
Precast Cope cladding panels
Half Joint Inspections
Inspection of concrete deterioration
![Page 66: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/66.jpg)
Kingston Bridge Complex
CONCRETE REPAIRS TO NORTH AND SOUTH APPROACHES
Concrete repairs to Half Joints
Concrete repairs to SoffitGully refurbishment
Contract Awarded to Makers - 2002
Cost of Works - £700,000
![Page 67: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/67.jpg)
Kingston Bridge Complex
HALF JOINT BEARING REPLACEMENT
Contractor - Morrison Construction Limited -2001 / 2002
![Page 68: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/68.jpg)
Kingston Bridge Complex
HALF JOINT BEARING REPLACEMENT
Existing Holding Down Bearing in Poor Condition
![Page 69: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/69.jpg)
Kingston Bridge Complex
HALF JOINT BEARING REPLACEMENT
Existing Sliding Bearing in Poor Condition
![Page 70: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/70.jpg)
Kingston Bridge Complex
HALF JOINT BEARING REPLACEMENT
Bearing Replacement at North - New Bearings in position
![Page 71: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/71.jpg)
Kingston Bridge Complex
HALF JOINT BEARING REPLACEMENT
Replacement of Expansion Joint Units
![Page 72: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/72.jpg)
Kingston Bridge Complex
COPE & PARAPET REFURBISHMENT
Phase 1 - Morrison Construction1992
Phase 2 - Nuttall1993
![Page 73: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/73.jpg)
Kingston Bridge Complex
Hydrodemolition of Cope Edge
![Page 74: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/74.jpg)
Kingston Bridge Complex
COPE AND PARAPET REFURBISHMENT
EXISTING
NEW
![Page 75: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/75.jpg)
Kingston Bridge Complex
STOBCROSS OFF RAMP REPLACEMENT & ASSOCIATED WORKS
Morgan Est - Works Started 24 February 2003 for 26 weeks
![Page 76: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/76.jpg)
Kingston Bridge Complex
STOBCROSS OFF RAMP REPLACEMENT & ASSOCIATED WORKS
Demolition & Replacement of Stobcross Off Ramp
![Page 77: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/77.jpg)
Kingston Bridge Complex
STOBCROSS OFF RAMP REPLACEMENT & ASSOCIATED WORKS
Cope & Parapet Refurbishment (Full Cantilever Replacement)
of the West Face of Bridge & Approach Structures
![Page 78: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/78.jpg)
Kingston Bridge Complex
Temporary Demolition and Construction Gantries on West Face of Bridge
![Page 79: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/79.jpg)
Kingston Bridge Complex
STOBCROSS OFF RAMP REPLACEMENT & ASSOCIATED WORKS
Replacement of 2 No. Overhead Sign Gantries
![Page 80: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/80.jpg)
Kingston Bridge Complex
STOBCROSS ON RAMP REFURBISHMENT & ASSOCIATED WORKS
Graham construction - Works Started January 2005 for 52 weeks
![Page 81: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/81.jpg)
Kingston Bridge Complex
Aerial View of Stobcross On Ramp
![Page 82: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/82.jpg)
Kingston Bridge Complex
Temporary Demolition & Construction Gantries
![Page 83: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/83.jpg)
Kingston Bridge Complex
Stobcross On Ramp construction work
![Page 84: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/84.jpg)
Kingston Bridge Complex
Replacement of 2 No. Overhead Sign Gantries
![Page 85: Kingston Bridge 2005 Rev1](https://reader037.vdocuments.us/reader037/viewer/2022102516/55c4e6a6bb61ebe5348b45be/html5/thumbnails/85.jpg)
Kingston Bridge Complex
Land Services
KINGSTON BRIDGE COMPLEXKINGSTON BRIDGE COMPLEX1st JUNE 20051st JUNE 2005
Glasgow City CouncilGlasgow City Council