kingston bridge 2005 rev1

85
Kingston Bridge Complex KINGSTON BRIDGE COMPLEX KINGSTON BRIDGE COMPLEX 1 1 st st JUNE 2005 JUNE 2005 Glasgow Glasgow City Council City Council Land Services

Upload: andrew-orr

Post on 08-Aug-2015

84 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Kingston Bridge 2005 Rev1

Kingston Bridge ComplexKINGSTON BRIDGE COMPLEXKINGSTON BRIDGE COMPLEX

11stst JUNE 2005 JUNE 2005

Glasgow City CouncilGlasgow City Council

Land Services

Page 2: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Complex consists of Main Bridge & Approaches

Opened 26 June 1970

Two adjacent structures 20.8 m wide

5 No. lanes of Motorway on each bridge

Main Span - 143m long

Two End Spans - 62.5m long

4,500m of Elevated Approach Structures

Designer - W A Fairhurst & Partners

Contractors - Logan, Marples Ridgeway

Page 3: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Heart of M8 Motorway System, spans over River Clyde & carries 180,000 vehicles per day

M8 carries East West traffic between Greenock and Glasgow Airport to Edinburgh

It connects to the M80 & M77, the M74 to South and England & Clydeside Expressway & North West

Page 4: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

North Approaches - early 1967

Page 5: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Construction of Cantilever End Span over the Broomielaw

Page 6: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Two Bridges - 3 voids in each bridge

Page 7: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Construction nearing Mid Span

Page 8: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Cladding Panels on Bridge - Client Requirement

Page 9: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Kingston Bridge Complex in 1970 - 30,000 vehicles a day

Page 10: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Exp a nsio n J o int Exp a nsio n J o int

62.484 m 143 .256 m 62.484 m

268 .224 m

Rive r C lyd ePinne dPinne dPinne d

General Arrangement

North Pier connected to Deck By 6 Rocker Bearings

South Pier cast into Deck

Both Piers connected to Foundations by 12 Pin Bearings

Piles connect Foundations to Bedrock 30 metres below

Page 11: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Pin Bearings at Bottom of Piers

Page 12: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

200mm bulge of North Quay Wall

In late 1980’s a number of Defects were found :-

Page 13: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

The North Pier tilted by 165mm

Page 14: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Spalling of Concrete at base of North Pier

Page 15: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

North Comb Movement Joint remained closed

Page 16: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

South Comb Movement Joint remained open

Page 17: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Cracks in Concrete at Midspan - Midspan dropped 300mm

Page 18: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Combination of these factor prompted Strathclyde Regional Council to carry out:-

Quay Wall Stabilisation Works

A Design Check of the Bridge

Inspection & Assessment of the Bridge

Monitoring System on Bridge

Page 19: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

26 Prisms, 32 LVDT’s, 89 Temperature Sensors, 2 Wind Anometers & 1 Tide Gauge

Page 20: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

QUAY WALL STABILISATION CONTRACT

Concerns :-

1 If Quay Wall collapsed, rapid washout of the sands & gravels below the footing could occur

2 Also, with the horizontal load on the Pier Footing from the Tilt of the North Pier, the Pier could be unstable

Contract Awarded to Keller Concrete in May 1991

Completed July 1992 - Cost £4 million

Page 21: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

1st Major Contract Awarded

Phased strengthening of Quay Wall

Page 22: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

4,000 tonnes of Jet Grouting carried out

Page 23: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

16,000 tonnes of Rock placed infront of Quay Wall to add stability

Page 24: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Engineers Inspecting soffit of bridge from Inspection vehicle

Page 25: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

1 Under extreme loading condition of Maximum Load on

the main span and with the end spans unloaded, there is insufficient holding down capacity of the end bearings

2 The bending capacity of the centre section of main span is inadequate

1994 ASSESSMENT

Page 26: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

INTERIM MEASURES

As a result of these findings the following Interim Measures were undertaken:-

A Traffic Management Scheme was Implemented consisting of;-

3 unrestricted lanes on each bridge 1 lane closed on each bridge

1 lane on each bridge restricted to 7.5 tonnes

Also 100 tonne of concrete blocks placed at each end of bridge

Page 27: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

DEFECTS TO BE ADDRESSED IN DESIGN

Understrength Deck - Bending Capacity midspan inadequate

Understrength Pier Shafts & Pile Caps- insufficient reinforcement in pier and pile caps

Page 28: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

165 mm Tilt of the North Pier

Lean on the North Approaches- due to sway on bridge

Riverward Load on North Pier foundations

Slipped Rocker Bearing at top of North Pier

Excess travel of South End Bearings

Page 29: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Successful Contractor

Main Contractor Balfour Beatty

Prestressing Balvac

Jacking VSL (France)

Page 30: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Four Phases of the Contract

1 Deck Strengthening External Prestress

2 Bridge JackingVertical and Horizontal

3 Demolition and Reconstruction of SubstructureKeeping bridge open

4 Installation of the New Bridge Bearings

Page 31: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Four Phases of the Contract

1 Deck Strengthening External Prestress

Page 32: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

DECK CROSS SECTION AT PIERS

ExistingOpenings

8.5Mapp.

Page 33: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

CROSS SECTION AT QUARTER SPAN

CROSS SECTION AT MIDSPAN

Existing Opening

Existing OpeningVoid Height 1.5m App

Void Height 2.5m App

Page 34: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

C/L PIER

WEB ANCHORAGE

BOTTOM SLAB ANCHORAGE

BOTTOM SLAB STRENGTHENING

Page 35: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Typical Void before Strengthening

Page 36: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Typical Void after Strengthening

Page 37: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

In each Void the Tendons consisted of:-

5 web Tendons in pairs with 12 strands per Tendon

2 Bottom Slab Tendons with 43 strands per Tendon

Page 38: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

View of Anchor Blocks inside Bridge

Page 39: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

View of Bottom Slab Beams on Bridge Soffit

Page 40: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Four Phases of the Contract

2 Bridge JackingVertical and Horizontal

Total Closure of Bridge during these operations - 17 Hour duration

Weight of Bridge - 52,000 tonnes

Page 41: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Elevation showing Supplementary Piers & Jacking Systems

Page 42: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

JACKING SYSTEM B - NORTH PIER

Page 43: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

JACKING SYSTEMS A, B & C AT SOUTH PIER

Page 44: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Vertical & Horizontal Jacking Systems

Page 45: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Page 46: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Kingston Bridge Complex - “Closed”

Page 47: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

NADICS Control Centre

Page 48: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

After lift 20mm gap between bottom bearing pin & upper casting

Page 49: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Removal of Bearing Pins

Page 50: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

After longitudinal jacking of bridge top & bottom casting offset

Page 51: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Four Phases of the Contract

3 Demolition and Reconstruction of SubstructureKeeping bridge open

Page 52: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Pier Slide Out with Traffic on Bridge

Page 53: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Demolition of North Pier after pier slide out

Page 54: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Demolition of South Pier

Page 55: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Rebuilding of North Pier

Page 56: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Four Phases of the Contract

4 Installation of the New Bridge Bearings

Page 57: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

1250mm x 1250mm x 500mm deep Laminated rubber bearing

Page 58: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Bearing in position on North Pier

Page 59: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

New Pier - South of River

Page 60: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Works complete - 5 Lanes of Traffic on each Bridge

Cost of Works - £30 Million

Page 61: Kingston Bridge 2005 Rev1

Land Services

Land Services

Kingston Bridge Complex

Page 62: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

OTHER WORKS ON THE COMPLEX

Routine Maintenance of Complex

Monitoring Works

Special Inspections

Concrete Repairs to soffit of Approach Structures

Half Joint Bearing Replacement

Cope & Parapet Refurbishment - Phases 1 & 2

Cope & Parapet Refurbishment (Central Reserve) - Phase 3

Stobcross Off & On Ramps Replacement & Associated Works

Page 63: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

MAINTENANCE OF COMPLEX

Cleaning of Traffic Management Scheme

Cleaning of Gullies

Cleaning of Carriageway Channels

Cope and Parapet Repairs

Page 64: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

MONITORING & ASSOCIATED WORKS

Calibration of Monitoring Equipment

Maintenance of Monitoring Equipment

Page 65: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

SPECIAL INSPECTIONS

Precast Cope cladding panels

Half Joint Inspections

Inspection of concrete deterioration

Page 66: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

CONCRETE REPAIRS TO NORTH AND SOUTH APPROACHES

Concrete repairs to Half Joints

Concrete repairs to SoffitGully refurbishment

Contract Awarded to Makers - 2002

Cost of Works - £700,000

Page 67: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

HALF JOINT BEARING REPLACEMENT

Contractor - Morrison Construction Limited -2001 / 2002

Page 68: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

HALF JOINT BEARING REPLACEMENT

Existing Holding Down Bearing in Poor Condition

Page 69: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

HALF JOINT BEARING REPLACEMENT

Existing Sliding Bearing in Poor Condition

Page 70: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

HALF JOINT BEARING REPLACEMENT

Bearing Replacement at North - New Bearings in position

Page 71: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

HALF JOINT BEARING REPLACEMENT

Replacement of Expansion Joint Units

Page 72: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

COPE & PARAPET REFURBISHMENT

Phase 1 - Morrison Construction1992

Phase 2 - Nuttall1993

Page 73: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Hydrodemolition of Cope Edge

Page 74: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

COPE AND PARAPET REFURBISHMENT

EXISTING

NEW

Page 75: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

STOBCROSS OFF RAMP REPLACEMENT & ASSOCIATED WORKS

Morgan Est - Works Started 24 February 2003 for 26 weeks

Page 76: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

STOBCROSS OFF RAMP REPLACEMENT & ASSOCIATED WORKS

Demolition & Replacement of Stobcross Off Ramp

Page 77: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

STOBCROSS OFF RAMP REPLACEMENT & ASSOCIATED WORKS

Cope & Parapet Refurbishment (Full Cantilever Replacement)

of the West Face of Bridge & Approach Structures

Page 78: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Temporary Demolition and Construction Gantries on West Face of Bridge

Page 79: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

STOBCROSS OFF RAMP REPLACEMENT & ASSOCIATED WORKS

Replacement of 2 No. Overhead Sign Gantries

Page 80: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

STOBCROSS ON RAMP REFURBISHMENT & ASSOCIATED WORKS

Graham construction - Works Started January 2005 for 52 weeks

Page 81: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Aerial View of Stobcross On Ramp

Page 82: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Temporary Demolition & Construction Gantries

Page 83: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Stobcross On Ramp construction work

Page 84: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Replacement of 2 No. Overhead Sign Gantries

Page 85: Kingston Bridge 2005 Rev1

Kingston Bridge Complex

Land Services

KINGSTON BRIDGE COMPLEXKINGSTON BRIDGE COMPLEX1st JUNE 20051st JUNE 2005

Glasgow City CouncilGlasgow City Council