kevin dare - why do floors fail part 1

40
Why do floors go wrong and what are we going to do about it ? Kevin Dare Managing Director Face Consultants

Upload: thomas-rochford

Post on 20-Aug-2015

152 views

Category:

Engineering


0 download

TRANSCRIPT

Page 1: Kevin Dare - Why Do Floors Fail Part 1

Why do floors go wrong and what are we going to do about it ?

Kevin DareManaging Director

Face Consultants

Page 2: Kevin Dare - Why Do Floors Fail Part 1
Page 3: Kevin Dare - Why Do Floors Fail Part 1

UK

• Mesh reinforced – 1 layer mesh, bottom (50mm)• Jointless Steel fibre (35 Kg) – Ground supported• Jointless Steel Fibre (45 Kg) – Pile supported

• All on 1 layer 300 micron slip membrane• On 150 to 250 road base +0 / - 15mm• 35 – 40 MPa cube concrete (28 – 33 cylinder)

Page 4: Kevin Dare - Why Do Floors Fail Part 1

Mainland Europe

• Jointed Steel fibre (25 Kg) – Ground supported• Jointless Steel Fibre (35 Kg) – Ground supported

• On 2 layers 300 micron slip membrane• On 150 to 250 road base +0 / - 15mm• 28 MPa Concrete (cylinder)• Dry shake topping

Page 5: Kevin Dare - Why Do Floors Fail Part 1

Middle East

• Jointed mesh, two layers – Ground supported• Jointless Steel Fibre (35 Kg) – Ground supported

• All on 1 layer 300 micron slip membrane• On 150 to 250 road base +0 / - 15mm• 35 – 40 MPa cube concrete (28 – 33 cylinder)

Page 6: Kevin Dare - Why Do Floors Fail Part 1

South Africa

• Jointed (approx 3 to 4 metres) No reinforcement.• Rough sub-base• No slip membrane• Thicker slabs

• Jointless Steel Fibre (35 Kg) – Ground supported

• 1 layer 300 micron slip membrane (Jointless)• On 150 to 250 road base +0 / - 15mm• 35 – 40 MPa cube concrete (28 – 33 cylinder)

Page 7: Kevin Dare - Why Do Floors Fail Part 1

Asia

• A real mixture.• Invariably poor ground leads to traditional reinforced slab

on piles.• Lack of specialist flooring contractors. Supervised labour• Multi level warehouses with topping slabs.• Mesh reinforced – 1 layer mesh, bottom (50mm)• Jointless Steel Fibre (45 Kg) – Pile supported

• 35 – 40 MPa cube concrete (28 – 33 cylinder)

Page 8: Kevin Dare - Why Do Floors Fail Part 1

Australia

• Mesh reinforced – 1 layer mesh, top (50mm)• Jointed steel fibres (20Kg) – Ground supported• Jointless Steel fibre (30 Kg) – Ground supported• PT – Ground supported

• All on 1 layer 200 micron slip membrane• On sand blinding • 40 MPa concrete (cylinder)

Page 9: Kevin Dare - Why Do Floors Fail Part 1

Why do floors fail ?

• We give too much importance on designing for imposed loads and not how the floor will be used or change with time. (race to the bottom)

• We fail to grasp that floors crack not because of drying shrinkage but restraint to drying shrinkage.

• We fail to understand the requirements or the impact of MHE that operate on the floor.

• We are driven to reduce price and blindly accept proprietary designs by material suppliers

Page 10: Kevin Dare - Why Do Floors Fail Part 1

Why do floors fail ?

• A floor is the table top on which the tenant runs his business.

Page 11: Kevin Dare - Why Do Floors Fail Part 1

What goes wrong ?

• Geotechnical reporting (Deep Layer)• Top layer ground or Sub Grade• Sub base / sand blinding• Mesh in the top• Steel fibre (jointed)• Steel fibre (jointless)• Un planned cracking should not be the norm.• Design methods• Concrete strength (shrinkage)• Detailing

Page 12: Kevin Dare - Why Do Floors Fail Part 1

Ground (Deep Layer)

• Geotechnical reports are generally carried out.

• Settlement modeling is rarely carried out or considered.

Page 13: Kevin Dare - Why Do Floors Fail Part 1

Ground (Deep Layer)

• We do not need this information to determine the slab thickness. Only knowledge of the top metre or so of the ground (plate tests).

• As racking gets higher and materials handling equipment becomes more sophisticated. Settlement and more importantly differential settlement becomes essential.

Page 14: Kevin Dare - Why Do Floors Fail Part 1

Ground (Deep Layer)

Page 15: Kevin Dare - Why Do Floors Fail Part 1

Ground (Deep Layer)

Page 16: Kevin Dare - Why Do Floors Fail Part 1

Top Layer Ground

• Sub Grade• Plate tests• Determines slab thickness

Page 17: Kevin Dare - Why Do Floors Fail Part 1

Top Layer Ground

Heave

Page 18: Kevin Dare - Why Do Floors Fail Part 1

Top Layer Ground

• Expansive clays• Moisture content• Heave

Page 19: Kevin Dare - Why Do Floors Fail Part 1

Sub Base / Sand Blinding

A sub base should:

1. Transmit the floor load to the sub grade thus improving the quality of support from soil under.

2. Provide a level formation

3. To provide a firm working platform for construction (without rutting)

Page 20: Kevin Dare - Why Do Floors Fail Part 1

Sub Base / Sand Blinding

Sub Base

Road base graded material, well compacted

Should not rut under load

+0 / -15mm

Page 21: Kevin Dare - Why Do Floors Fail Part 1

Sub Base / Sand BlindingSand Blinding:

Moves

Ruts under load

Causes restraint

Variable slab depths

Page 22: Kevin Dare - Why Do Floors Fail Part 1

Sub Base / Sand Blinding

Page 23: Kevin Dare - Why Do Floors Fail Part 1

Mesh in the top

• Has no structural benefit• Maintaining cover • Bends down dowel sleeves• Risk of being saw cut

Page 24: Kevin Dare - Why Do Floors Fail Part 1

Mesh in the top

Page 25: Kevin Dare - Why Do Floors Fail Part 1

Mesh in the top

Page 26: Kevin Dare - Why Do Floors Fail Part 1

Steel Fibre (Jointed)

Method not used in the UK and is not recommended in TR34 because of issues of dominant joints and loss of load transfer

Page 27: Kevin Dare - Why Do Floors Fail Part 1

Steel Fibre (Jointless)

Benefits:• No induced sawn joints.

Disadvantages:• Wider joint openings• Increased risk of cracking• Panel sizes – aspect ratio• Wire guidance issues• Fibres at the surface

Page 28: Kevin Dare - Why Do Floors Fail Part 1

Steel Fibre (Jointless)

Recommendations:• 1000 sq metre panels• Aspect 1:1.2 max• Min 35Kg steel fibres• 35 MPa concrete max.• 300 micron slip membrane• No sand blinding• Good isolation• As long as possible before loading• No wire guidance

Page 29: Kevin Dare - Why Do Floors Fail Part 1

Un planned cracking should not be the norm.

Page 30: Kevin Dare - Why Do Floors Fail Part 1

Design Methods

There are two parts to a floor design:

1. Slab thickness and reinforcement.

2. Detail design:– understanding how the floor will shrink– Understanding the performance requirements of the MHE that

will operate on it.

Page 31: Kevin Dare - Why Do Floors Fail Part 1

Design Methods

• TR34 unravels proprietary designs issued by material suppliers and makes it easier for design engineers to do to their job in checking them.

Page 32: Kevin Dare - Why Do Floors Fail Part 1

Detailing

Shrinkage

Page 33: Kevin Dare - Why Do Floors Fail Part 1

Detailing

Shrinkage

Page 34: Kevin Dare - Why Do Floors Fail Part 1

Detailing

Shrinkage

Page 35: Kevin Dare - Why Do Floors Fail Part 1

Detailing

Shrinkage

Page 36: Kevin Dare - Why Do Floors Fail Part 1

Detailing

Shrinkage

Page 37: Kevin Dare - Why Do Floors Fail Part 1

Detailing

Restraint:• Sub-base• Reinforcement• Columns• Services• Door openings• Joints• Racking too early

Page 38: Kevin Dare - Why Do Floors Fail Part 1

Concrete Strength

Reduce shrinkage:• Reduce strength. 40 MPa not required for abrasion• Reduce cement• Reduce water• Sands and aggregates???• Water reducing admixtures.

Page 39: Kevin Dare - Why Do Floors Fail Part 1

What do we do about it ?

Page 40: Kevin Dare - Why Do Floors Fail Part 1

Thank you!

Kevin DareFace Consultants