Kennewick School DistrictDaily Report: Eastgate Elementary
Specializing in Projects that Make a Difference®
PROJECT TEAM
Kennewick School District 1000 4th Ave.
Kennewick, WA 99336 (509) 222-7667
www.ksd.org Doug Carl
Director of Capital Projects
Madsen Mitchell Evenson and Conrad, PLLC
8905 West Gage, Ste 200 Kennewick, WA 99336
(509) 396-7278 www.madmitch.com
Doug Mitchell, AIA, LEED AP Project Architect
Joe Hampton Project Manager
Leone & Kebble Contractor
108 West Boone Spokane, WA 99201
(509) 327-4451 www.leone-keeble.com
Tom Mercer Project Manager
Carl Clausen Superintendent
Strategic Construction Management, Inc.
3601 North 20th Pasco, WA 99301 (509) 737-0072
www.strategic-cm.com David L. Robison, CCM, LEED AP
Owner’s Representative
CONSTRUCTION ACTIVITY OBSERVED Report No.: 040114-01
SEPTEMBER 11, 2014 VOL. 1 n ISSUE 77
Kennewick Elementary Improvement ProgramPrepared By: V. Guzman
Weather: 73° SunnyWind Speed: 10 mph
Humidity: 19%Precipitation: 0.00 in.
Interior demolition of all the walls and spaces within the existing school continues; the demolition of the exterior walls will soon begin. Only the exterior walls remain at the old principle’s office
Grinding of the existing organics is part of the process required for ongoing site development.
Electrical conduits are neatly placed and encased in the new concrete floor.
The placement of masonry block continues at all available locations.