k barrage 2014 - pm world library...the existing barrage remained safe, but the overflow of banks...
TRANSCRIPT
PM World Journal Flood at Khanki Barrage 2014 Vol. III, Issue XII – December 2014 by Zafar Ahmed www.pmworldjournal.net Personal Story
© 2014 Zafar Ahmed www.pmworldlibrary.net Page 1 of 7
FLOOD AT KHANKI BARRAGE 20141
By Zafar Ahmed
The River Chenab is one of the largest rivers of the Indus basin. The river Chenab basin measures
about 67,500 km² of area. The River originates at 77°-30°E and 32°-50°N in Lahul and Spite
district in Himachal Pradesh India. It flows through the Baralcha pass at an elevation of 5,000 M
and enters the State of Jammu and Kashmir (India). Many streams join on both sides of the river in
high mountainous region of about 500 kms long and flows out into the plains and enter Pakistan
near Marala Barrage, in district Sialkot. After flowing through 600 km it joins the river Indus and
then falls into the Indian Ocean near Karachi after a further 600 km.
The Khanki Headworks is the Oldest Barrage on River Chenab and was completed in 1892 with a
most economical design. It was shuttered type weir comprising 8 Spans of 500 ft and Rope Bridge
for controlling staff to move across the river. It is 56km downstream from Marala Barrage and is
one of the oldest weirs in the Indian sub-continent. The water is diverted to a canal at left bank,
irrigating 1.2 million hectors of land in 7 districts of central Punjab in Pakistan.
The existing Khanki Headworks has the capacity to pass the flood of 800,000 cusecs and in case of
higher floods, some discharge is passed through breaches of u/s guide banks towards an
unpopulated area to avoid any damage to the weir structure.
The average annual rainfall in the area is 950 mm and mean annual temperature is 30c°. The main
weather system which causes heavy rainfall is due to monsoon incursion from Arabian Sea and Bay
of Bengal during July to September. The floods in River Chenab result from heavy rainfall in upper 1 This story describes events that affected the project on which the author is current working.
PM World Journal Flood at Khanki Barrage 2014 Vol. III, Issue XII – December 2014 by Zafar Ahmed www.pmworldjournal.net Personal Story
© 2014 Zafar Ahmed www.pmworldlibrary.net Page 2 of 7
drainage basin which falls under the most active monsoon belt. The snow melt contributes on the
average 40% of the total flow in July, and peak values occurring in months of August and
September are due to monsoon rains. The history of past 92 years’ floods is shown in table.
`
Due to the ageing effects of old barrage, a new 4400 ft long barrage having 65 bays with
controlling gates and bridge is being constructed downstream of existing barrage at the cost of
about $ 200 million. The works at new barrage started in October 2013 and is planned to be
completed in 42 months. As per schedule, the Contractor M/S Descon Engineering Limited
completed 30% of sub-structures including protection works in the first working season (October
2013 – June 2014) before the start of first flood season (July-September 2014) and cleared the river
bed from temporary structures and coffer dam to pass the monsoon floods.
160
257
203 26
6.8
225 26
175
074
7.3
249
352.
425
627
8.1
208 27
3.8
189.
112
3.4
264.
518
4.8
145.
628
7.4
288.
422
0.6
173.
215
2.6 22
9.6
251.
243
8.5
225
1011
.721
7.9 31
5.3
315
806.
734
0.7
261.
510
86.4
401.
710
2170
9.5
354
345.
318
6.7
406.
220
0.7
631.
624
0.7
235.
436
227
5.1
311.
528
1.7
856.
319
7.9
666.
261
547
2.1
433.
124
6.9
194.
856
3.9
261.
930
3.9
167.
430
9.1
341
109.
486
4.2
512.
234
5.7
314.
691
0.5
439.
442
5.2
630.
585
1.3
847.
722
0.3
177.
830
9.3
162.
8 244.
437
1.8
151.
134
368.
078
422.
7430
2.19
721
5.41
210
5.35
833
4.43
716
6.38
3
947.
099
0
200
400
600
800
1000
1200
1922
1924
1926
1928
1930
1932
1934
1936
1938
1940
1942
1944
1946
1948
1950
1952
1954
1956
1958
1960
1962
1964
1966
1968
1970
1972
1974
1976
1978
1980
1982
1984
1986
1988
1990
1992
1994
1996
1998
2000
2002
2004
2006
2008
2010
2012
2014
Peak
Dis
char
ge (
thou
sand
s of
cus
ec)
Years
ANNUAL PEAK DISCHARGES AT KHANKI HEAD
WORKS (1922-2014) IN thousands of cusecs
PM World Journal Flood at Khanki Barrage 2014 Vol. III, Issue XII – December 2014 by Zafar Ahmed www.pmworldjournal.net Personal Story
© 2014 Zafar Ahmed www.pmworldlibrary.net Page 3 of 7
Works in Progress to Complete before July 2014
The working Contractor encircled about 15 % of the river bed through coffer dams to continue the
works during flood season to complete the Head Regulator structure, Silt Excluder, Guide Bank,
Divide Wall and other protection works. They planned to pass about 600,000 cusecs in the
remaining river width.
The Contractor continued works in the enclosed 15% of river bed area without danger, as the
average flow in the River Chenab at Khanki remained less than 80,000 cusecs from July to August
2014.
With the beginning of September, heavy continuous rains started in the catchment area of river
Chenab due to a monsoon incursion from Bay of Bengal. The water in the river started to increase
on 3rd
September 2014. The discharge was 650, 000 cusecs on 5th
and 6th
September. It passed
safely in the available river bed width. It started to recede at 1200 hrs and all the stakeholders were
happy that the flood has passed and was now receding.
At 1600 hours on the 6
th September 2014, an alarming situation created a panic when it was
announced that one peak discharge of about 1 million cusecs was expected early next morning. It
was a very surprising / devastating situation for the safety of the old barrage structure and the under
construction works which were continued as per plan in the enclosed area of 15 % of the river bed.
The time was very short to take and implement important decisions in order to pass the peak flood
that was more than the capacity of existing barrage that was coming in few hours. The Punjab
Irrigation Department, The Project Director, CRE, the Consultants SMEC International and the
PM World Journal Flood at Khanki Barrage 2014 Vol. III, Issue XII – December 2014 by Zafar Ahmed www.pmworldjournal.net Personal Story
© 2014 Zafar Ahmed www.pmworldlibrary.net Page 4 of 7
Contractor M/s Descon, local representatives joined hands and heads to protect the existing Barrage
structure, already completed works, and to safely pass the flood peak when it reached the Barrage.
It was decided to remove the coffer dam immediately which encircling the working area at left
bank. Secondly, to immediately strengthen the upstream banks to protect the populated and
industrial areas, and to prepare and blast the breaching section by Army corps of Engineers at the
u/s right bank which diverts the part of flood water towards unpopulated area to pass the part of
peak flood through the breaching section. The Contractor mobilized all available resources so that
the coffer dam obstructing the flow could be removed as early as possible. As huge flood was
coming so Contractor’s camps, offices, records, computers, costly items had to be protected and
Plant and moving equipment had to be removed as soon as possible as the flooding of the adjoining
area was inevitable.
The water level started to increase at 0200 hrs and it was at its peak at 0700 hrs in the morning of
7th
September 2014. The water was overtopping from the D/S Abutment stone walls. The peak
discharge recorded was 947,099 cusecs (27,000 cubic meters per second) at the Old Khanki
Barrage. As planned, the u/s right bank breaching section was detonated before the peak discharge,
easing the pressure at the Barrage structure.
The Peak Flood Passing at U/S of Barrage
The peak flood measured as 947,099 cusecs (27,000 Cubic meters per second). It overflowed from
the Abutment wall of both banks eroding nearby areas; this also eroded the banks of the existing
canal, also eroded trees along the banks, and a few were as old as 150 years. The Contractor’s camp
was flooded as 5-6 ft water flowed through the camps.
PM World Journal Flood at Khanki Barrage 2014 Vol. III, Issue XII – December 2014 by Zafar Ahmed www.pmworldjournal.net Personal Story
© 2014 Zafar Ahmed www.pmworldlibrary.net Page 5 of 7
FLOOD DAMAGES:
The existing Barrage remained safe, but the overflow of banks eroded existing canal banks. The
Contractor M/s Descon working for the new Barrage also suffered losses due to flooding of their
offices, warehouses, slag - cement store yard, the temporary works and under construction road
along left bank. The works for new Barrage suffered about 60 days delays. The Contractor, M/s
Descon was determined to overcome the delay in the next working season from October – June
2015.
PM World Journal Flood at Khanki Barrage 2014 Vol. III, Issue XII – December 2014 by Zafar Ahmed www.pmworldjournal.net Personal Story
© 2014 Zafar Ahmed www.pmworldlibrary.net Page 6 of 7
RESTORATION WORKS:
The Punjab Irrigation Department immediately decided to restore all the works so that the Canal
which was feeding a large area could be operated as early as possible. The working Contractor was
instructed to mobilize and restore the canal banks and eroded portions. The variation works started
immediately and the canal was ready to receive water after 12 days.
The Works in Progress now for Main Barrage
PM World Journal Flood at Khanki Barrage 2014 Vol. III, Issue XII – December 2014 by Zafar Ahmed www.pmworldjournal.net Personal Story
© 2014 Zafar Ahmed www.pmworldlibrary.net Page 7 of 7
About the Author
Zafar Ahmed
Pakistan
Zafar Ahmed, by profession a Civil Engineer, has worked in Middle
East countries at planning and managing construction of heavy projects. He participated in planning
and construction of the first balanced cantilever bridge over river Indus at old and historical
crossings of invaders to India near Attock, about 35 years before. He also worked for large Hydro
power projects of 1600 MW, 1500 MW and 1000 MW in Pakistan. Zafar participated in the
rehabilitation of Adam – Salalah road, 200 km stretch and new dual carriageway from Sohar to
Buraimi in Oman. He has therefore been engaged in planning and construction of multibillion $
construction projects overseas and in Pakistan. Presently he is working as resident civil works
consultant with SMEC international at Khanki Barrage.
Zafar can be contacted at [email protected]