joint ciwem engineers ireland presentation 12th november 2014
TRANSCRIPT
Joint CIWEM Engineers Ireland Presentation
12TH November 2014
PRESENTERS / PRESENTATION CONTENTS
Thomas Cooney
Supervisor
Part 1
Scheme Overview
Part 4
Conclusion
Paul McSparran
Contracts Manager
Part 2
Construction
Alan McWatters
CEEQUAL Assessor
Part 3
CEEQUAL Process
Part 1 Catchment
Flooding History
Scheme Overview
Catchment
Catchment Size – 55km²
Main Stream length – 22km
Q100 – 63m³/s
History of Flooding October 1987 –
highest on record
December 2000
August 2008
October 2011
Q100 Flooded Area
St Ciaran’s School
Ballygawley Village
Scheme Objectives Provide Q100 protection to
St. Ciaran’s High School (Site 1)
No.’s 8, 9 and 11 Tullybryan Rd (Site 1)
No. 28 Tullybryan Rd (Site 2)
Residential & Commercial Properties within Ballygawley Village (Site 3)
Enhance the river environment
Undertake the works in a sustainable manner
Scheme Overview
Site 3 Site 1
Site 2
Site 1 – St.Ciarans School • 700m of sheet
piled & reinforced
concrete wall
• 60m of flood
embankment
• 600m of back
drainage
• Installation of
fishery enhancement
measures
Site 1
Site 1
Site 2 – Tullybyran Rd • 160m of reinforced
concrete wall
• 150m of culvert
upgrade
• 115m of back
drainage
• Reinstatement of garden area
Site 2
Site 3 – Ballygawley Village • Removal of
existing
embankment
• 240m of kingpost
concrete floodwall
• 50m of
landscaped flood
embankment
• 250m of back drainage
Site 3
Bridge Replacement • Upgrade of
Tullybyran Rd
Bridge
• Partnership with
Roads Service
• Works completed
prior to flood
alleviation scheme
Culvert Upgrade • Upgrade of
Feddan Drain
Culvert
• Partnership with
Roads Service
• 1200mm Ø pipe to
twin 900mm Ø pipe
Part 2 - Construction
Management
Options
PAUL MCSPARRAN – CONTRACTS MANAGER BSG
Value Engineering
Savings Delivered:
• Use of vacant
offices
• Sheet pile trials
and redesign
• Use of precast
walls
Value Engineering
Savings Delivered:
• Use of 100 pour liner and review
of layout to
maximise shutter
use
• Rationalisation of
rebar design to
minimise
wastage
• Alternative coping detail
Programme
Time Savings:
• Good relationship
with adjacent
landowners
• Flexible
subcontractors
• Early engagement
with utilies, DCAL,
client etc.
• Programming to
provide a fall back
option
• Completion
achieved 4 months
ahead of schedule
Challenges
• King Post Piling
• Maintaining existing
flood protection
• Existing Services
• Reducing noise and
vibration from sheet
piling
Challenges
• Working close to a
school and nursery
• Maintaining access
for people and
animals
• Poor weather
conditions during
reinstatement
Sustainability
Reuse of excavated
material
Reuse of temporary
roads
All works completed
from the river banks
Sustainability Channel
Improvements
Fishery Measures
Project submitted
for Considerate
Constructors &
CEEQUAL Scheme
Health & Safety Works completed
successfully in
sensitive location
10749 man hours
completed with no
accidents
Regular contact
with school, nursery
and locals reduced
risks to all
Part 3 - CEEQUAL
Management
Options
ALAN McWATTERS – CEEQUAL ASSESSOR RIVERS AGENCY
CEEQUAL – a Brief Introduction Sustainability assessment and
awards scheme for civil engineering projects.
Celebrates the achievement of high environmental and social performance.
Aims to deliver improved project specification, design and construction of civil engineering works.
Encourages performance above legal, environmental and social minima.
CEEQUAL – How it works
Rivers Agency CEEQUAL History Moneymore Flood
Protection Scheme
Construction Only Award
Excellent (93%)
Lodge Burn Flood Alleviation Scheme
Whole Team Award
Excellent (76.4%)
Ballygawley Water Flood Alleviation Scheme
SUSTAINABILITY PERFORMANCE ASSESSMENT
Whole Team Award
Client – DARD Rivers Agency
Designer – DARD Rivers Agency
Constructor – BSG Civil Engineering
Assessor – Alan McWatters, DARD Rivers Agency
Verifier – David Fisher, The Design Environment
Ballygawley Water FAS Sustainable planning from the start
Environmental Enhancement
Fishery Enhancement
Electro Fishing Survey
Otter Holt
Environmental Protection
Green Barrier
Invasive Species
Neighbour Interactions
Community Amenity
Opportunities for the Unemployed
Minimal Construction Waste
Value Engineering
Sustainable thinking from the start Feasibility Study and Economic Appraisal considered Social, Economic
and Environmental impacts and benefits of the proposed project
Flood protection delivered to residential, commercial and social properties
Climate change fully incorporated within the design process
Overall delivering this flood alleviation scheme will provide more sustainable living to the community it serves
Fishery Enhancement Measures
• Water environment enhancement considered within all capital works schemes
• Liaison and site investigation with DCAL Inland Fisheries and RA Environment Section
• Fishery habitat units included in scheme to improve environment for UKBAP significant species
Fishery Enhancement Measures
Pool
Nursery D-Groyne
Electro Fishing Monitoring Survey
Fish are stunned with an electric current
Safely collected from a 10 metre length of channel
Species and size recorded to calculate density
Safely released back into the watercourse
Undertaken at both a control and the enhancement site
2013 – Pre Enhancement Works
2014 – Post Enhancement Works
Total Salmonid Biomass
Otter Holt Construction
Otter footprints identified
Loss of vegetation in this area
Agreed best area for artificial holt with RA Environment Section
Included Otter Holt construction with project
Environmental Protection
Green Barrier
Environmental Protection
Temporary Upstream Barrier
Mature Tree Retention
Invasive Species – Japanese Knotweed
•Followed Environment Agency JKW remediation flow chart •7 metre radius supervised excavation zone •Buried contaminated soil over 2 metres depth in root membrane •Plant tracks washed before leaving site
Neighbour Interactions
•Promoting Civil Engineering in St. Ciarans College
•Existing culvert pipes retained for reuse by landowner
•Existing fence around St. Ciarans retained for reuse
•Back drainage amended after concerns raised by local resident
Community Amenity
•Created new public amenity footway over flood wall tie in to high ground •Reckli patterned formwork finish to all exposed surfaces for reduced visual impact •Both the above points were well received from community feedback questionaire
Opportunities for the Unemployed Contract documents specified the need for provision
of work experience through the DEL Steps to Work (StW)Programme
BSG carried out 2 periods of interviews with possible StW candidates
Sam Managh was employed on a 13 week training experience placement
Sam is now a full time
employee of BSG Civil
Engineering
Minimal Construction Waste
KPI’s to monitor waste reduction and recycling
99.9% of non hazardous waste was reused on site
All excavation material re-profiled onsite
Waste segregation and recycling implemented
Materials ordered and stored appropriately
Haul road stone reused throughout project
Value Engineering
NEC3 Option C incentivises value engineering
Reduced material usage through reduction in sheet pile section – saving of 270T of steel.
Re-design of coping equated to 60m3 concrete saving
Precast embankment wall
Benefits of using CEEQUAL
Delivery of a more sustainable project
Improved public relations and perception
Environment protected and enhanced
Enhanced Team Spirit - Provided a target for the project team to deliver high performance and developed a positive attitude
Increased interest within construction workforce about environmental issues
Cost Savings through Value Engineering and reduced material wastage
Part 4 - Conclusion
Management
Options
CONCLUSIONS
• Flood protection up to 1% AEP provided
for Ballygawley
• Improvement to fisheries habitat and river environment
• Project completed ahead of schedule
• Awarded CEEQUAL Excellent award
Questions