JdVVNL/TNTW- /P-1 TENDER SPECIFICATION Supply, Erection, Testing and Commissioning of 11 KV XLPE cable 26.8 KM in order to bypass existing line which has undergone to sand dunes area under Sub-Division Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key Basis”.(TNTW-473) TENDER No. JU/SE/TN/TW- 473 NAME OF CIRCLE:- SE(BFL),Jaisalmer, JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity Number (CIN) U40109RJ2000SGC016483 Regd. Office: New Power House, Jodhpur- 342003 OFFICE OF THE SUPERINTENDING ENGINEER (TW) Phone No: 0291-2742336, Fax No: 0291-2745259 E-mail: [email protected], Web site: www.jdvvnl.com PART - I Cost of tender specification: Rs. 2950/- Contact Details Contact Person Superintending Engineer (TW) Telephone: (0291) 2742336 :Fax (0291) 2745259 :Email [email protected]

Upload: others

Post on 21-Aug-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-1

TENDER SPECIFICATION

“Supply, Erection, Testing and Commissioning of 11 KV XLPE cable 26.8 KM in order to

bypass existing line which has undergone to sand dunes area under Sub-Division Moomal

and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per

governing specification on Turn-Key Basis”.(TNTW-473)

TENDER No. JU/SE/TN/TW- 473

NAME OF CIRCLE:- SE(BFL),Jaisalmer,

JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity Number (CIN) –U40109RJ2000SGC016483

Regd. Office: New Power House, Jodhpur- 342003

OFFICE OF THE SUPERINTENDING ENGINEER (TW)

Phone No: 0291-2742336, Fax No: 0291-2745259

E-mail: [email protected], Web site: www.jdvvnl.com

PART - I

Cost of tender specification: Rs. 2950/-

Contact Details

Contact Person Superintending Engineer (TW)

Telephone: (0291) 2742336

:Fax (0291) 2745259

:Email [email protected]

Page 2: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-2

Office of the Superintending Engineer (TW)

New Power Industrial Area, Jodhpur -342003 (Rajasthan)

INDEX

S. No Particulars Pages No.

(A) Part-I

1 E-tender notice Web Page (Annexure-I) 3

2 Important Dates & Notes (Annexure-II) 4-7

3 Qualification requirement (Annexure-III) 8-12

4 Bid proposal form and schedules (Schedule-1 to 8) 13-22

(B) Part-II

5 Broad Scope of Work 24

6 Requirement of System 25-27

7 Technical Requirement of System 28

8 General Information 29-33

(C) Part-III

(Section-I)

9 Instructions to bidders (ITB) 34-53

(Section-II)

10 General Conditions of Contract (GCC) 54-117

(Section-III)

11 Erection Conditions of Contract (ECC) 118-185

Page 3: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-3

ANNEXURE-I

JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity Number (CIN) –U40109RJ2000SGC016483

Regd. Office: New Power House, Jodhpur- 342003

OFFICE OF THE SUPERINTENDING ENGINEER (TW)

Phone No: 0291-2742336, Fax No: 0291-2745259

E-mail: [email protected], Web site: www.jdvvnl.com

No. Jd.VVNL/SE (TW)/XEN (TW)/JU/ /D- Dated

E-PROCUREMENT SHORT TERM TENDER NOTICE Techno-commercial and Price short term e-Bids are invited from eligible bidders

for following works:

Sr.

No.

Tender

No.

Name of work Estimated cost

in Lakh Rs.

1 TNTW-

473 “Supply, Erection, Testing and Commissioning of 11 KV

XLPE cable 26.8 KM in order to bypass existing line which

has undergone to sand dunes area under Sub-Division

Moomal and Dhanana for deposit work for F.Y. 2019-20

under SE( BFL) ,Jaisalmer as per governing specification on

Turn-Key Basis.”

534.01/-

1. EMD could be furnished in Bankers cheque / D.D. or 20% in Bankers cheque / D.D. in the

name of Sr. Accounts Officer ( CPC), JdVVNL, Jodhpur and balance 80% in the form of

bank guarantee in the name of Superintending Engineer (TW), JdVVNL, Jodhpur.

2. The copy of the tender documents / specifications are available on Jodhpur Discom website

http://energy.rajasthan.gov.in /jdvvnl and the same can be downloaded and uploaded on the

website www.eproc.rajasthan.gov.in by the bidder. The bidders, in their own interest are

requested to read very carefully the tender documents before submitting the bid only through

on line on website www.eproc.rajasthan.gov.in

3. The cost of tender specification (non-refundable) Rs. 2950/- and EMD as above shall be

payable in demand draft/Bankers cheque in favour of the Sr. Accounts Officer ( CPC),

JdVVNL, Jodhpur and tender processing fees of Rs. 1180.00/- (non-refundable) shall be

payable in favour of the Managing Director, RISL payable at Jaipur. The bidders are

required to furnish the proof of depositing all these payment in the office of the undersigned

up to 01:00 P.M. of last date of bid submission for respective tender otherwise the bids are

liable to be rejected.

4. Eligible bidders should submit their bid well in advance instead of waiting till last date

JdVVNL will not be responsible for non-submission of Bid due to any website related

problems.

Note: - All eligible interested bidders are required to get enrolled on e-tendering portal

www.eproc.rajasthan.gov.in

-Sd-

SUPERINTENDING ENGINEER (TW)

JODHPUR DISCOM, JODHPUR

Part-I 1. E-PROCUMENT TENDER NOTICE

Page 4: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-4

Annexure-II

Office of the Superintending Engineer (TW)

New Power Industrial Area, Jodhpur -342003 (Rajasthan)

Tel. No.: 0291-2742336, 2742260 Fax No. 0291-2745259 E Mail: [email protected]

Specification No. JdVVNL/SE(TW)/TNTW-473

“Supply, Erection, Testing and Commissioning of Laying of 11 KV XLPE cable &

Maintenance works in shifting sand dunes area under Sub-Division Moomal and

Dhanana for deposit work for F.Y. 2019-20 (TNTW-473) under ,SE( BFL) ,Jaisalmer,

as per governing specification on Turn-Key Basis”.

TENDER PROCESSING FEES (NON-REFUNDABLE): Rs. 1180.00

COST OF SPECIFICATION (NON-REFUNDABLE) : Rs. 2950.00

Sr.

No. Name of Works

Estimated

cost of the

work (Rs.

In Lacs)

Tender

processi

ng fees

in Rs.

Cost of

tender

(In Rs.)

Earnest

Money

02%

(Rs. In

Lacs)

Last date of

bid

submission

Date of

opening

Tender

Completi

on Period

1

Supply, Erection, Testing and

Commissioning of Laying of 11

KV XLPE cable & Maintenance

works in shifting sand dunes area

under Sub-Division Moomal and

Dhanana for deposit work for F.Y.

2019-20 (TNTW-473) under ,SE(

BFL) ,Jaisalmer, as per governing

specification on Turn-Key Basis

534.01 1180/-

2950/-

10.68

04000004000

0404.12.2019

00004

05.12.2019 3 months

Note:- Work completion period and contract period shall govern as per clause No. 26. of

“GCC”

SPPP Portal PUBLISHING DATE

/UBN No.

EPROC Portal PUBLISHING DATE

DOCUMENT DOWNLOAD / SALE

START DATE

From -------- onwards

at http://eproc.rajasthan.gov.in

Part-I 2.IMPORTANT DATES AND TIME FOR BID INVITATION

Page 5: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-5

PLACE OF SUBMISSION OF BIDS at http://eproc.rajasthan.gov.in

SUBMISSION OF BANKERS

CHEQUE

DEMAND Draft and Bank Guarantee

3:00 P.M. on the scheduled date 04.12.2019 for submission

of respective bid at office of Sr. A.O (CPC) New Power

House, Industrial Area, Basni, Jodhpur

OPENING OF TECHNICAL BIDS http://eproc.rajasthan.gov.in

in office of S.E. (TW), Jodhpur

DATE & TIME OF OPENING OF

FINANCIAL BIDS

Will be intimated later to the Technically qualified bidder

WEBSITE FOR DOWNLOADING

TENDER DOCUMENT,

CORRIGENDUMS, ADDENDUMS

ETC DRAFT FOR TENDER FEE,

EMD AND PROCESSING FEE

http://energy.rajasthan.gov.in /jdvvnl ,

www.eproc.rajasthan.gov.in, http://sppp.raj.nic.in

VALIDITY OF TENDERS

REQUIRED UPTO

120 days from the date of opening of techno-commercial bids.

TENTATIVE QUANTUM OF

WORK

As per G-Schedule & Annexure -‘S’

CONTACT PERSON

(AUTHORIZED BID SIGNATORY)

Superintending Engineer (TW) JdVVNL, Jodhpur

CORRESPONDENCE ADDRESS Superintending Engineer (TW) JdVVNL, Jodhpur, New

Power House, Jodhpur

MOBILE NO. 9413359104

TELEPHONE NO. 0291-2742336

FAX NO. 0291-2745259

WEBSITE 1. http://energy.rajasthan.gov.in /jdvvnl

2. http://risl.rajasthan.gov.in

3. http://sppp.raj.nic.in

E-MAIL [email protected] [email protected]

Address of RISL Rajcomp Info Services Limited (RISL) 1st floor, Yojna

Bhawan, Tilak Marg, C-Scheme, Jaipur (Raj.)

Phone: 0141-5103902, 4031900, Fax: 0141-2228701

Web:http://risl.rajasthan.gov.in,Email:[email protected]

.in

Page 6: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-6

1.IMPORTANT NOTES

Note:

1.EMD could be furnished in Bankers cheque/D.D. or 20% in Bankers cheque/D.D. and

balance 80% in the form of bank guarantee

2. The tender/bid shall only be submitted through online tendering system of

www.eproc.rajasthan.gov.in.

3. Bidders who wish to participate in this tender will have to register on

http://eproc.rajasthan.gov.in (bidders registered on eproc.rajasthan.gov.in before

30.09.2011 needs to register again). To participate in online tenders, Bidders will have to

procure Digital Signature Certificate (Type – II or Type – III) as per Information Technology

Act-2000 using which they can sign their electronic bids. Bidders can procure the same from

any CCA approved certifying agency i.e TCS, Safecrypt, Ncode etc. or they may contact e-

Procurement Cell, Department of IT & C, Government of Rajasthan for future assistance.

Bidders who already have a valid Digital Certificate need not to procure a new Digital

Certificate.

Contact No. 0141 – 4022868 (Help desk of RISL - 10.00 AM to 6.00 PM on all working

days)

E-mail: [email protected]

Address: e-Procurement Cell, RISL, Yojana Bhawan, Tilak Marg, C-Scheme, Jaipur.

4. Bidders should go through the website http://eproc.rajasthan.gov.in, should refer to the

website and go through the link “Help For Contractors”, “Information About DSC”, “FAQ”

and “Bidders Manual Kit” and clause no. 5 of Section-I to know the process for submitting

the electronic bids at the website.

5. The ‘Instructions to bidders’ and other terms and conditions of this tender pertaining to the

bidding process generally follow the guidelines of e-tendering system of the government of

Rajasthan, available at URL http://eproc.rajasthan.gov.in. However, wherever there is any

anomaly between the conditions referred to in this document and the GoR e-tendering

system, the later shall be final.

6. The complete bid document has been published on the websites, www.jodhpurdiscom.in

and http://www.eproc.rajasthan.gov.in for the purpose of downloading.

7. The downloaded bid document shall be considered valid for participation in the bid process

subject to submission of required Bid document fee of Rs. 2950/- only (Rupees Two

thousand five Hundred only) and e-Tender Processing Fee: Rs. 1180/- (Rupees One thousand

only) in Cash/ Demand Draft in favour of M.D, RISL payable at Jaipur.. A copy of the bid

document fees receipt must be enclosed along with the Technical bid/proposal failing which

the bid will be summarily rejected.

8. All the communication/ correspondence including the bid document (Technical and

Financial Bid) should be signed digitally and stamped on each page by the designated

authorized representative of the bidder.

Page 7: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-7

9. No contractual obligation whatsoever shall arise from the RFP/ bidding process unless and

until a formal contract is signed and executed between the tendering authority and the

successful bidder(s).

10. JdVVNL disclaims any factual/ or any other errors in this document (the onus is purely

on the individual bidders to verify such information) and the information provided herein are

intended only to help the bidders to prepare a logical bid-proposal.

11. Bids will be considered only in the prescribed form/ document. Bids not submitted in the

prescribed format will be summarily rejected and EMD submitted along with the bids shall be

forfeited. Also, bidders should refrain from providing the information which is not relevant.

12. Copies of various documents to be enclosed along with the bid-proposals must be legible

and be self-attested by the authorized signatory with official seal. Claims made by bidder

related to the project experience and other requirements shall be considered only when

appropriate supporting documents are provided.

13. All the communication/correspondence including the bid document (Technical and

Financial Bid) must be signed and stamped on each page by the designated authorized

representative of the bidder failing which the bid will be summarily rejected.

14. The Bids can be submitted up to date and time given as specified in the NIT.

15. The complete bidding process is defined in Vol.-II Part-I of this RFP document.

16. In case, a bidder imposes conditions which are in addition or at variance or in conflict

with the terms and conditions as specified in this RFP document, all such bid-proposals will

be summarily rejected and EMD submitted along with the bids will be forfeited.

17. Tendering Authority reserves the complete right to accept or reject in part or full any or

all the offers without assigning any reasons whatsoever. No further discussion/ interaction

will be held with the bidders whose bids have been disqualified/ rejected by the purchaser/

tendering authority.

18. In case, a dispute arises with regard to interpretation/ omission/ error in the RFP

document, bid submitted, other documents; the decision SE (TW), JdVVNL, Jodhpur will be

final and binding upon the bidders.

19. Interested bidders may obtain further information from the office of the Superintending

Engineer (TW), JdVVNL, New Power House, Industrial Area, Jodhpur on any working day

from 10 am to 6pm.

20. Other terms and conditions which are not mentioned here shall be applicable as per

provisions and Rules mentioned in RTPP Act 2012 and RTPP Rules 2013 and amended from

time to time.

Superintending Engineer (TW)

Jodhpur Vidyut Vitran Nigam Limited

Page 8: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-8

JODHPUR VIDYUT VITRAN NIGAM LIMITED

1.0 GENERAL: The Bidders shall become eligible to Bid, on satisfying the following

‘Bid Qualification Requirements’ and on production of the required documentary evidences

along with the Tender. The tender may be filed by a single bidder or by making a

consortium. The bidder should possess class “A / B” Electrical License issued by Electrical

Inspectorate of any state Govt. or Central Govt. of India or undertaking shall be given on NJS

Rs.100/- that after awarding the contract the successful bidder should possess Electrical

license of above category issued by Govt. of Rajasthan within one month from the date of

issue of order.

2.0 ELIGIBILTY: The Bidder should be a reputed Infrastructure contractor who

regularly undertakes electrical turnkey projects and has adequate technical knowledge and

practical experience. The bidder should be in the business of heavy electrical goods for

Supply, Erection / Construction, Commissioning, Testing and Operation of various mega

projects.

3.0 EXPERIENCE: Bidders having good experience of successfully completing various

EPC Electrical Infra projects in India since last 5 years(i.e. F.Y. 2014-15 to F.Y.2018-19).

4.0 WORK EXPERIENCE:

4.1 For single bidder:-

The bidder should have experience of having executed the similar nature of the

turnkey projects (as specified below) during last five financial years (i.e. F.Y. 2014-15 to

F.Y.2018-19)and the total value of such executed works should at least be 25% of the

estimated project value.

4.2 For Joint venture:-

The Lead Partner should be an Electrical Contractor possessing class “A / B”

Electrical License issued by Electrical Inspectorate of any state Govt. or Central Govt. of

India. The lead partner should have executed one or more type of works/projects as specified

below. The other partner(s) should either be electrical contractor(s) for the above specified

works / projects or any financial enterprise. The value of such executed works by the lead

partner and the value against the such works by the other partner (s) added together should at

least be 25% of the estimated project value during last five financial years (i.e. F.Y. 2014-15

to F.Y.2018-19)

The value of such type of works / projects executed by the lead partner should at

least be 40% of the qualifying criteria.

For participating in project/ all lots of project, if any or some of the lots of

the project the total amount of work executed during last five financial years should be 25%

the total estimated cost of project/ LOT(s) be added together.

If bidder have any past work experience in JV then sharing ratio of work experience

shall be given in form of undertaking if sharing ratio is not mentioned anywhere in work

experience document.

Part-I 3. PRE QUALIFICATION REQUIREMENT (Annexure-III)

Page 9: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-9

The type of electrical projects executed should be as under for Power

Utilities / State Electricity Boards / Other Govt. agencies like Housing Board, Development

Authorities, RIICO etc. :-

(i) Supply & Erection / Construction of EHV / MV 33 KV, 11 KV and LT over head lines.

(ii) Supply & Erection / Construction of EHV / MV 33 KV, 11 KV and LT underground

cables.

(iii) Supply & Erection / Construction of EHV / MV 33 / 11 KV, 11 / 0.433 KV sub-

stations complete with all equipments.

(iv) Supply & Erection / Construction of 11 / 0.433 KV Packaged sub- stations.

(v) Supply & Erection / Construction of 11KV Ring Man Units in underground cable

network.

(vi) Supply & Erection works for Electric Traction for Indian Railways.

NOTE:- Please note that out of these above projects, the orders executed of only

SUPPLY of material shall not be considered. Only execution of Turn-key

works shall be considered.

In support of the works executed as stated above, the bidder is required to

furnish a list of work orders executed during last five financial years in the prescribed format

given at Schedule –3(B) duly supported by the following documents attested in respect of

each work executed:-

(i) Detailed work order(s) i.e W.O. No., W.O. date, Dispatch No., ( F.Y. 2014-15 to

F.Y.2018-19).

(ii) Satisfactorily work completion certificate issued by concerned officer not below the

rank of Executive Engineer in case of orders of Power Utilities / State Electricity Boards

/ Other Govt. agencies like Housing Board, Development Authorities, and RIICO etc.

(iii) The Bidder should also furnish documentary evidences about their professional

competence with details of various orders contracts placed and executed by them with

testimonials on the satisfactory performance of the contracts.

5.0 REQUIREMENTS FOR JOINT VENTURE/ CONSORTIUM: In case of Joint Venture / Consortium the requirement of experience as per 4.0 should

be meeting out in totality by both the members. The Consortium can be made with the

following:-

(A) Electrical Contractors who have executed projects as under for Power Utilities /

State Electricity Boards / Other Govt. agencies like Housing Board, Development

Authorities, RIICO etc. :-

(i) Supply & Erection / Construction of EHV / MV 33 KV, 11 KV and LT over head

lines.

(ii) Supply & Erection/ Construction of EHV / MV 33 KV, 11 KV and LT underground

cables.

(iii) Supply & Erection/ Construction of EHV / MV 33/11 KV, 11/0.433 KV sub- stations

complete with all equipments.

(iv) Supply & Erection/ Construction of 11/0.433 KV Packaged sub- stations.

(v) Supply & Erection/ Construction of 11KV Ring Man Units in underground cable

network.

(vi) Supply & Erection works for Electric Traction for Indian Railways.

Page 10: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-10

Financial Enterprises.

6.0 TURN OVER:

(i) For single bidder:-

The turnover for last five financial years ( F.Y. 2014-15 to F.Y.2018-19)should be at least

25% of the estimated project value.

(ii) For Joint Venture /Consortium:-

In case of joint venture, the figures for each of the partners of the Joint Venture

shall be added together to determine the bidder’s compliance with the minimum qualifying

criteria set out as above (turnover of last five financial years should be at least 25% of the

estimated project value, subject to the condition that turnover of lead partner of joint venture

should not be less than 40% of the minimum qualifying criteria.

7.0 BID CAPACITY:-

The bidders who meet the minimum qualification requirements / criteria specified

above are to be evaluated further for their bid capacity as under:-

A- Maximum annual turnover out of immediate preceding five financial years (ie.

F.Y. 2014-15 to F.Y.2018-19)

B- Value of existing commitments against various contracts awarded upto the tender

publication of this bid.

Hence bid capacity = 2XA –B, which should be in excess of the estimated value

of this project.

Bidders are required to furnish the year wise turnover in the prescribed format for

immediate preceding five financial years duly certified by a Chartered Accountant along with

his/her membership and UDIN i.e. Unique Document Identification Number with the

Institute of Chartered Accountants of India (ICAI)

Note: - In case of Joint Venture the maximum turnover is to be worked out by summation of

the annual turnover of last five financial years of each bidder.

For example: -

PARTICIPANT YEAR-1 YEAR-2 YEAR-3 YEAR-4 YEAR-5

LEAD

PARTNER

5 3 2 4 1

OTHER

PARTNER

3 5 7 4 5

TOTAL 8 8 9 8 6

Maximum Annual Turnover of the Joint Venture would be taken as (2+7) = 9 (for the year 3

in above example )

Page 11: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-11

8.0 OTHER CONDITIONS:

8.1 In case of non-furnishing of requisite undertaking along with the bid, the bid will be

considered as non responsive proposal.

8.2 Jd.VVNL reserve the right to waive deviations, if they do not materially affect the

capability of an applicant.

8.3 If the bidder forms a Joint Venture / Consortium, the qualification requirement

mentioned above should be met in totality.

8.4 Original consortium agreement on Non – Judicial stamp paper of Rs. 500/- stamp value

must be submitted along with the proposal.

The JV agreement / consortium agreement must have the following:

(a) Names of all partners

(b) Name of the lead member

(c) Authorization in favour of the lead member from all the members. (A separate power

of attorney signed by legally authorized signatories of all the partners is required)

(d) The lead member is authorized to incur liabilities and receive instructions for and on

behalf of any and all partner of the Joint Venture / Consortium and the entire

execution of the contract including payment shall be done exclusively with the lead

member

(e) All partners of the Joint Venture / Consortium shall be liable jointly and severally for

the execution of the contract in accordance with the contract terms

(f) In the event of any default by any partner / partners of Joint Venture / Consortium, the

other partner / partners shall accept the liability and execute the contract in full.

(g) The agreement must provide details of roles and responsibilities of each member of

the consortium. Overall responsibility in respect of execution of tendered work is

with the lead member.

(h) The Joint Venture / Consortium agreement shall not be cancelled or amended

unilaterally without consent of the purchaser after opening of the bid and a

statement to this effect should appear in the JV agreement.

(i) A firm can submit only one bid in the same bidding process, either individually

as a bidder or as a partner of a Joint Venture / Consortium. A bidder who

submits or participates in more than one bid will cause all the bids in which the

bidder has participated to be disqualified.

(j) Bids from agents are not acceptable in the case of Joint Venture / Consortium, and

such bids will be treated as non-responsive.

(k) The change in consortium /JV after opening / submission of tender shall not be

entertained, in the event the consortium / JV is altered then such proposals shall be

treated as rejected.

(l) The above stated requirements are a minimum and the owner reserves the right to

request for any additional requirement and also reserve the right to reject the

Page 12: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-12

proposal of any bidder, if in the opinion of the owner, the qualification data is

incomplete or the bidder is found not qualified to satisfactorily perform the works.

NOTE:

I. In case of non-furnishing of original Consortium / JV agreement along with the

bid the bid will be considered as bid without consortium and evaluation shall be

made on the basis of credentials of lead member only.

II. The JV / Consortium agreement should be tender specific i.e. signed specifically for

this tender.

III. The JV and Consortium shall be considered at par.

IV. THE OFFERS OF BIDDERS NOT SATISFYING THE ABOVE “BID

QUALIFICATION REQUIREMENTS” SHALL BE REJECTED.

Page 13: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-13

SCHEDULE-1

BID PROPOSAL FORM

Specification No. JdVVNL/SE(TW)/TNTW-__________

“Supply, Erection, Testing and Commissioning of Laying of 11 KV XLPE cable &

Maintenance works in shifting sand dunes area under Sub-Division Moomal and

Dhanana for deposit work for F.Y. 2019-20 (TNTW-473 ) under ,SE( BFL)

,Jaisalmer, as per governing specification on Turn-Key Basis”.

The Superintending Engineer (TW),

Jodhpur VidyutVitran Nigam Limited,

Jodhpur.

Dear Sir,

With reference to your invitation for bids against specification No.JU/SE/TW/TNTW-______ we

agree for execution of tendered work including survey, supply of material, erection & commissioning on

turnkey basis as per bidding documents downloaded by us on prices, terms & conditions mentioned hereunder:

1. The prices as mentioned in Schedule-2 (G-schedule of prices/Rates) being furnished in accordance with

clause 4.0 of Volume-II, Part-I[Instructions to Bidders(INB)], are on FIRM price basis in all respect.

2. The prices quoted are valid for a period of 120 days from the date of opening of techno-

commercial bids.

3. The quoted /agreed prices are inclusive of all the statutory DUTY/CESS/TAXES & GST etc. as

applicable at the time of opening of the bid, such as following charges:

4. We here by certify that the quoted / agreed prices are inclusive of all taxes, duties and cess on the date of

opening of bids and shall not be charged extra.

5. Any statutory variation in existing rates of taxes/duties/levies/charges during the contracted completion

period shall be to Nigam’s account. However, for claiming any such statutory variation, the contractor is

required to furnish the documentary evidence/proof in support of the same for scrutiny and approval.

Any downward variation in above rates of taxes/duties/levies shall have to be passed on to the Nigam.

6. It is noted that the quantum of work as mentioned in the specification are tentative and we agree to

execute any quantum of work as per your requirement.

7. We have noted the standard terms of payment and undertake to abide by the same.

8. We also note that conditional offers are likely to be rejected.

9. The supply of material / equipments shall be strictly as per latest ISS / BS and technical specification of

JU/SE/TN/TW-_____ and as per GTP provided by bidder and accepted by the Nigam.

10. The erection work shall strictly be in accordance with work completion schedule as given in the

schedule-5. In case we fail to complete the work as indicated in therein we shall pay penalty as per

“Delay in completion” clause of the specification.

11. The supply of material/ equipments shall be strictly as per latest ISS/ BS & technical specification No

JU/SE/TN/TW-_______and as per GTP provided by bidder and accepted by Nigam.

Part-I Bid Proposal form & Schedules

Page 14: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-14

12. We confirm that we agree to adhere to all the commercial terms & conditions as well as the technical

stipulation of your specification No.JU/SE/TN/TW-_______ and there is no deviation. Such

acceptance has also been confirmed in prescribed schedule 3 & 4 enclosed herewith.

13. We confirm that we are qualified for bidding in terms of Qualification Requirements specified in the

bidding documents and have submitted the requisite qualification Certificate & data/ documents with the

bid.

14. Until a formal contract is prepared and executed, this document together with your written acceptance

thereof in your notification of award shall constitute a binding contract between us.

15. We understand that price quoted by us are firm and no price variation will be allowed.

16. We understand that you are not bound to accept the lowest or any bid you may receive.

17. The checklist have been completely filled and signed.

18. We have mentioned respective tender No. wherever required in schedules and documents, in which we

are participated.

Encl: -Schedule-3 to 8 along with supporting documents.

Yours faithfully,

(Signature)

Name &Designation

(with seal of the firm) Place:

Date:

Page 15: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-15

SCHEDULE-2

Duly Prepared BOQ (Price Bid) in

XLS Format uploaded separately on

www.eproc.rajasthan.gov.in Bidders

are requested to fill the rates

separately in each BOQ i.e. for

supply and erection.

Page 16: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-16

SCHEDULE-3

Commercial Terms & Conditions

Bidder's Name & Address:

To

The Superintending Engineer (TW),

Jodhpur VidyutVitran Nigam Limited,

New Power House, Industrial Area,

Jodhpur – 342003.

Sub: Confirmation for “NIL Deviation” in Commercial terms & conditions for tender No. JU/SE/TN/TW-

_____

Dear Sirs,

We hereby confirm that there is NIL deviation in commercial terms & conditions stipulated in the bidding

documents and we are agreed to adhere the same strictly.

(Signature)...............................

(Name)...............................

(Designation)…………………….

(Common Seal)..............................

Place:

Date:

Page 17: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-17

SCHEDULE-4

Technical Terms & Conditions

Bidder's Name & Address:

To

The Superintending Engineer (TW),

Jodhpur VidyutVitran Nigam Limited,

New Power House, Industrial Area, Jodhpur – 342003.

Sub:Confirmation for “NIL Deviation” in Technical terms & conditions for tender No. JU/SE/TN/TW

______

Dear Sirs,

We hereby confirm that there is NIL deviation in technical terms & conditions stipulated in the bidding

documents and we are agreed to adhere the same strictly.

We also confirm that tendered material shall be procured in line with clause no. 8.0 of General Conditions of

Contract.

(Signature)...............................

(Name)...............................

(Designation)…………………….

(Common Seal)..............................

Place:

Date:

Page 18: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-18

SCHEDULE-5

Work Completion Schedule

Bidder's Name & Address:

To

The Superintending Engineer (TW),

Jodhpur VidyutVitran Nigam Limited,

New Power House, Industrial Area,

Jodhpur – 342003

Dear Sirs,

We hereby declare that the following Work Completion Schedule, including submission of Joint Survey Report

& Work Plan shall be followed by us in supply, erection, testing and commissioning of the equipments and

completion of works as detailed in the G-schedule of tender No. JU/SE/TN/TW-________ shall be as per

clause No. 26 of general Condition of Contract (GCC).

(Signature)...............................

(Name)...............................

(Designation)…………………..

Place:

Date: (Common Seal)..............................

Page 19: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-19

SCHEDULE-6(A)

Qualification Requirements Details

(Tender No. JU/SE/TN/TW-________)

Bidder's Name & Address:

To

The Superintending Engineer (TW),

Jodhpur VidyutVitran Nigam Limited,

New Power House, Industrial Area,

Jodhpur – 342003

Dear Sirs,

We hereby declare that we are qualified for bidding in reference to “Qualification Requirements” indicated in

“Annexure – III, Part-I, Vol-I” of the bidding documents as per details given here under:

S.No

.

PARTICULARS DETAILS

1 Turn Over (As

defined in cl. No.

2(i) of annexure-‘III’

of Volume-I)

( In Crores of Rs. only)

2014-15

2015-16

2016-17

2017-18

2018-19

2 Net Profit After Int.

& Dep.

( In Crores of Rs. only)

2014-15

2015-16

2016-17

2017-18

2018-19

3 Net Worth ( In Lacs of Rs. only)

2014-15

2015-16

2016-17

2017-18

2018-19

and submit the following certificate(s) /documents in support of the above: -

1. Copy of Valid Contractor License.

2. Copy of registration with Jodhpur-Discom, if registered.

3. Copies of Audited Balance Sheet pertaining to last five years ( i.e. F.Y. 2014-15 to F.Y. 2018-19)

4. Furnishing of a certificate issued by a registered Chartered Accountant certifying of specified

qualification requirements is essential. The name, stamp and the registration no. of the Chartered

Accountant are necessary of the certificate with UDIN.

Date: Name & Designation

Place: (with seal of the firm)

Page 20: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-20

Schedule-6(B)

Qualification Requirements

(Tender No. JU/SE/TN/TW-______)

Details of Works Executed during last three financial years (, 2014-15, 2015-16, 2016-17 , 2017-18 & 2018-

19)

Ord

er

Aw

ard

ing

Au

tho

rity

Des

crip

tio

n

of

Work

Work

order S

tip

ula

ted

com

ple

tio

n

Per

iod

Da

te o

f co

mm

ence

men

t

Da

te o

f a

ctu

al

com

ple

tio

n Value of work actually

executed (as per

completion certificate)

during five years

(Amt. in Rs. Lacs) Remarks

No

.&

Da

te

Am

ou

nt

(Rs.

in l

acs

)

20

14-1

5

20

15-1

6

20

16-1

7

20

17-1

8

20

18-1

9

To

tal

TOTAL:

Note:

(1) Copy of each work order, G-schedule & completion report be enclosed.

(2) Completion report must be certified by a technical officer only, as per cl. No. 1 (c) (iii) of

Qualification Requirement and should also be duly attested by Notary Public.

(3) Furnishing of the completion report of each of work executed specially indicating the amount

thereof, is essential as the qualification of the bidder shall be determined on this basis. The

Work experience shall not be counted on account of non-furnishing of such documents.

(4) Work Experience certificate should also be duly attested by Notary public.

(Signature)...............................

Date:

(Name)...............................

Place:

(Designation)..............................

(Common Seal)..............................

Page 21: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-21

SCHEDULE-7

List of Previous Experience of Work Executed

(Tender No. JU/SE/TN/TW-________)

Bidder's Name & Address:

To

The Superintending Engineer (TW),

Jodhpur VidyutVitran Nigam Limited,

New Power House, Industrial Area,

Jodhpur – 342003

Dear Sirs,

We have completed /executed the orders of Turn-key package successfully as per details given hereunder:-

S.No. Details of

ordered work

Order No. & Date Name & details of

ordering utility Date of

commencement 1 2 3 4 5

Date of

completion

Contract value of

ordered/executed work

Whether order executed as per

stipulated work completion

schedule or not

Remarks

6 7 8 9

(Signature)...............................

Date:

(Name)...............................

Place:

(Designation)..............................

(Common Seal)..............................

Page 22: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-22

SCHEDULE-8

List of Equipments and Technical Hands

(Tender No. JU/SE/TN/TW-_____________)

Bidder's Name & Address:

To

The Superintending Engineer (TW),

Jodhpur VidyutVitran Nigam Limited,

New Power House, Industrial Area,

Jodhpur – 342003

Dear Sirs,

We hereby declare that we have sufficient men & machinery for successful execution of work against this tender

enquiry, the details of which are given as under:-

---------------------------------------------------------------------------------------------- -----------------------------

(Signature)...............................

Date:

(Name)...............................

Place:

(Designation)..............................

(Common Seal)..............................

Page 23: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-23

Office of the Superintending Engineer (TW)

New Power Industrial Area, Jodhpur -342003 (Rajasthan)

TENDER SPECIFICATION FOR

“Supply, Erection, Testing and Commissioning of 11 KV XLPE cable 26.8 KM in order to

bypass existing line which has undergone to sand dunes area under Sub-Division Moomal

and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per

governing specification on Turn-Key Basis”.(TNTW-473)

TENDER No. JU/SE/TN/TW- 473

NAME OF CIRCLE:- SE(BFL),JAISALMER

VOLUME - I

Part : II

Page 24: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-24

Jodhpur Vidyut Vitran Nigam Limited is one of the Electricity Distribution Companies in

Rajasthan State.

This specification covers the execution of work “Supply, Erection, Testing and

Commissioning of 11 KV XLPE cable 26.8 KM in order to bypass existing line which has

undergone to sand dunes area under Sub-Division Moomal and Dhanana for deposit work

for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

Basis”.(TNTW-473)

Following main works are to be carried out:

i. Joint Survey of site with GPS coordinate and SLD.

ii. Transportation/ freight and Insurance of material

iii. Supply and Erection/Installation of various material/equipments

iv. Testing & Commissioning of various material/ equipments

---XXX---

Part-II BROAD SCOPE OF WORK

Page 25: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-25

TECHNICAL SPECIFICATIONS

1. Introduction

Jodhpur Vidyut Vitran NIGAM Ltd herein after to be referred to as JdVVNL is a

distribution Utility entrusted with the distribution of power. It caters power to more than

22 Lacs consumers.

2. Objectives of this bid

Jodhpur Vidhyut Vitran Nigam Ltd. is one of the electricity distributing company in

Rajasthan State intents to install appropriate system and provide contract on Turnkey basis

for carry out the works covered in the scope of work and shall be increased or decreased as

per requirement of field condition/ Nigam.

3. Detailed scope of work

The following main works are to be carried out for erection/ installation & commissioning

of various material along with its associated equipments:

Joint Survey of site with GPS coordinate and SLD.

Transportation/ freight and Insurance of material

Supply and Erection/Installation of various material/equipments

Testing & Commissioning of various material/ equipments

3.1 WORKMANSHIP/TECHNICAL RESOURCES:

i. The contractor should be a Class A/B Electrical Contractor who possess valid license

and experience of such type of erection and commissioning work for 33/11KV and above

works on turnkey or contract basis. The contractor shall give a list of such turnkey projects

or contract executed by them in past including civil foundation work.

ii. The contractor shall furnish full details, of Engineers, skilled, semi-skilled persons

and unskilled labour along-with supervisory staff with their experience who would be

employed by him to carry out the proposed erection work. The qualification and

experience of such manpower shall be furnished in relevant schedule. The contractor shall

assign only qualified and senior supervisor Engineers and provide adequate number of

competent labour for the work.

iii. Payment in part or whole may be withheld against contract work claimed by contractor

which in opinion of the Nigam, is necessary to protect himself from loss on the

account of :-

a. Defective work not remedied or guarantees not met.

b. Claims filed against contractor.

c. Failure by contractor to make due payment for materials supplied or labour employed

by him.

d. Damage to Nigam’s or other’s property.

e. Failure to meet the mutually agreed schedules to works.

Part-II REQUIREMENT OF SYSTEM

Page 26: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-26

iv. Whenever any information or clarifications in respect of construction of work have to

be obtained from various authorities the contractor shall be responsible for taking

action well in time, so that there are no delays on this account. The completion period

offered in the tender shall be deemed to include the time taken for such incidental

works.

3.2 MANUFACTURER’S DRAWINGS & INSTRUCTION MANUALS:

Manufacturer’s drawings, instructions and recommendations shall be correctly

followed in handling and setting of equipment and extreme came shall be exercised in

handling equipment to avoid distortion to stationary structures, the marking of surface finish,

damage to delicate instruments and electrical parts.

In accordance with the specific installation instructions as indicated on manufacturer’s

drawings or catalogues, or as directed by the Nigam, the contractor shall handle, assemble,

install, wire, test and put into commercial use all equipment and works included in this

contracts. The equipment shall be installed in a neat manner, so that it is level plums, square

and properly aligned and oriented. Tolerance shall be as establishes in manufacturer’s

drawing or a stipulated by the Nigam. No equipment shall be grouted or permanently bolted

down to the foundation or structure until the alignment has been checked and found

acceptable to the Nigam.

In case of any doubt/mis-understanding as to the correct. Interpretation of

manufacturer’s drawings or instructions, necessary clarifications shall be obtained from the

manufacturer. The contractor shall be held responsible for any damage to the equipment

consequent to the non-following of manufacturer’s instructions correctly.

4 PRICE/CHARGES:

(i) The contract price shall remain FIRM throughout the period of contract and no

increase in these rates shall be allowed under any circumstances.

(ii) The following charges, if any, shall be borne by the tenderer:-

(a) All traveling expenses to and fro the site, allowances, living expenses,

wages, salaries, overtime benefits and all compensations for skilled and

unskilled workmen, supervisors, engineers, clerical staff, watch and ward staff,

storekeepers etc. engaged for the work.

(b) Insurance for workers engaged for installation work, workmen’s

compensation, third party liability and any other insurance required as per the

specification, cost of all licenses and permits, loading, transport and unloading

of all his material, tools and tackles instruments and construction sides to and

from the site, cost of providing office, tool rooms, quarters, required under the

contract and for satisfactorily executing the complete work under the contract.

(iii) No idle charges shall be payable for any reason whatsoever to the contractor for

stoppage of works.

(iv) Contract price included all taxes, duties and cess as applicable time being in force.

Page 27: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-27

5 INSPECTION FEES:

Any fee to be paid to statutory authorities including electrical inspector for testing and

inspection shall be borne by the Nigam.

6 COMPLETENESS OF TENDER:

Each section of the tender should be complete and include all associated works not

specifically mentioned in the Schedule/Specification etc., but essential for the completeness

of the work. The contractor shall not be eligible for any extra charges in respect of such

minor works though not specifically included in the tender or contract.

7 DEPARTURE FROM SPECIFICAITON:

Should the tender wish to depart from the specification in any respect, he should

clearly state such departures indicating the reasons there of, unless this is done, the

departmental specification will hold good and shall be binding on the supplier unless the

departures have been approved in writing by the purchaser.

Tender not supported by the information desired in the specification or not complying

with the specification is liable for rejection.

8 COMPLIANCE WITH REGULATIONS:

Unless otherwise specified, all works shall be carried out in accordance with the

Indian Electricity Act 1910, Indian Electricity Rules, 1956 with any amendments or revision

thereof which may be issued during the currency of the contract and the requirement of any

other regulations and Acts in India which the Nigam may be subjected to.

9 LAY-OUT OF SUB-STATION/DRAWINGS:

The contractor will be supplied two copies of all relevant necessary layout drawings

required for installation commissioning of 33KV lines.

The Nigam reserves the right to make minor additions/deletions or modifications to

the particulars and details given on the drawing depending on actual site requirement as and

when necessary. Contractor shall carry-out the installation work in accordance with such

requirement.

All specialized equipments/services necessary for proper installation of all equipment

covered in this contract shall be provided by the contractor.

Page 28: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-28

SUPPLY OF TOOLS, TACKELS AND OTHER MATERIALS:

For completion of the work, contractor shall, at his own expense ensure availability of

all necessary erection tools, machine tools, power tools, Tackles, hoists, Cranes, Derricks,

Cables, Slings, Skids, Scaffolding, work benches, tools for rigging, cribbing & blocking,

welding machine and all associated protective equipment, instruments, appliances, materials

and supplies required for unloading, transporting, storing, erection testing and

commissioning that may be required to accomplish the work under contract unless

otherwise provided for. Adequacy of such tools will be subject to final determination of the

Nigam.

The Nigam may furnish to contractor for use on the project, such equipment, tools and

Tackles that could be spared by him at the time of request for the same by contractor, at

standard rental charges. Such rental charges shall be deducted by the Nigam from

contractor’s bill and net payment shall be made.

Contractor shall also furnish al necessary expendable devices like Anchors, Grinding, and

abrasive wheels, raw Plugs, Hacksaw, Blades, Tags Dies, Drills, Reamers, Chisels, Files,

capbroundum, Wire, Brushes, necessary Bamboo scalffolding, Ladders, wooden blanks,

timbers, Sleepers and consumable material like oxygen, actilylene, Argon, lubricating, oils,

greases, cleaning Plugs, cylinder oil, graphite power and flakes, fasteners, baskets,

temporary supports, stainless Steels Shims of various thickness as required, Cotton wastes,

cheese cloth and all other miscellaneous supplies of every kind required for carrying out the

work under the contract.

Contractor shall be responsible to provide all reasonable facilities including tools,

personnel etc. and ensure co-ordination with the Nigam and equipment supplier’s erection

supervisors to enable them to carry-out all supervision, measurements, checks etc., in a

satisfactory manner, entirely at contractor’s cost.

Contractor shall not dispose off, transport or withdraw any tools, tackles, equipment and

material provided by him for the contract without taking prior written approval from Nigam

and Nigam at all times shall have right to refuse permission for disposal, transport or

withdrawal of tools/tackles, equipments and material if in his opinion, the same will

adversely affect the efficient and expeditious of the project.

Note:- All the material supplied by the contractor shall comply the relevant ISS and

shall be in accordance with the requirement mentioned in clause No.-8 of GCC.

Part-II TECHNICAL REQUIREMENT OF SYSTEM

Page 29: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-29

1.0 WAY LEAVE, TREE CUTTING AND OTHER OBSTRUCTIONS:

The Nigam will arrange for way leave and for tree clearance, proposals in this

connection will have to be prepared and submitted by the contractor well in time. It will also

be necessary on the part of contractor to instruct his labour and staff to use minimum area

while doing the work where there are standing crops. No person of the Contractor should pick

any items from standing crops of fruits. The Contractor should take all possible steps to avoid

or minimize damage to standing crops, etc. Tree cutting required, shall be arranged by the

contractor.

The contractor should immediately notify any obstructions or hindrance from local

villagers or the local authorities in the execution of the work, to the concerned Engineer/In-

charge but should not deal directly in the matter. The Engineer/in-charge will arrange to

remove the obstacles as soon as possible.

For the clearance, permissions, removal of obstructions in way leave, etc. the

contractor shall not remain contended by simply informing the Nigam but shall invariably

assist and arrange for personal follow up to overcome the difficulties in the interest of

progress of the work.

2.0 ACCESS TO LOCATION:

It will be the contractor’s sole responsibility to take the material up to the location and

shall have to arrange transportation at his cost.

The contractor will be deemed to be very well familiar with the work to be executed

before giving the offer. Notwithstanding, the difficulties of terrain, location

approaches, way leave and other obstructions the price quoted for all the items of

erection in the ‘G’ schedule shall not undergo any change at any stage of work

including the time limit extension.

Only Indian Original persons having valid police clearance will be allowed to

work as per time specified by BFL authorities.

3.0 SHUT DOWN OF EXISTING LINES:

The contractor or his authorized representative shall intimate in advance along-with

complete programme of erection where ever shunt down of existing line is required to the

Engineer In charge of the site for arranging shut downs. The contractor shall have to plan the

work in such a way that in minimum duration of shut down maximum work is carried out to

avoid repeated and/or longer duration shut downs.

4.0 GENERAL TECHNICAL CONDITIONS

The following provisions shall supplement all the detailed technical Specification and

requirements. The Bidder’s proposal shall be based on the use of equipment and materials

complying fully with the requirements, specified herein.

Part-II GENERAL INFORMATION

Page 30: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-30

The Bidder shall furnish clause – by – clause commentary (with detailed technical data

as required) on the Technical Specification demonstrating the goods substantial

responsiveness to the Specification or deviation and exceptions to the provisions of the

Technical Specification unless and until advised contrary to this in the bidding document.

4.1 Reference Standards & Improvements

The Codes and/or Standards referred to in Specification shall govern, in all cases

wherever such references are made. In case of a conflict between such Codes and / or

Standards and the specification, latter shall govern. Such Codes and / or Standards,

referred to shall mean the latest revisions, amendments / changes adopted and published

by the relevant agencies.

Other internationally acceptable Standards that ensure equivalent or better performance

than those specified shall also be accepted.

The Owner or the Contractor may propose changes in the Specification of the

equipment or quality thereof and if the parties agree upon any such changes, the

Specification shall be modified accordingly.

If any such agreed upon change is such that it affects the price and schedule of

completion, the parties shall agree in writing as to the extent of any change in the price

and / or schedule of completion before the Contractor proceeds with the change.

Following such agreement, the provision thereof shall be deemed to have been amended

accordingly.

4.2 Quality Assurance

A Quality Assurance Programme of the Contractor shall generally cover but not

limited to the following:

(a) His organization structure for the management and implementation of the proposed

Quality Assurance Programme.

(b) Documentation control system.

(c) Qualification data for key personnel.

(d) The procedure for purchases of materials. Parts/ components and selection of sub-

Contractor’s services including vendor analysis, source inspection, incoming raw

material inspection, verification of material purchases etc.

(e) System for shop manufacturing including process controls.

(f) Control of non-conforming items and system for corrective action.

(g) Control of calibration and testing of measuring and testing equipments.

(h) Inspection and test procedure for manufacture.

(i) System for indication and appraisal of inspection status.

(j) System for quality audits.

(k) System for authorizing release of manufactured product to the Purchaser.

Page 31: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-31

(l) System for maintenance of records.

(m) System for handling storage and delivery and

A Quality Plan detailing out the specific quality control procedure adopted for

controlling the quality characteristics of the product. The Quality Plan shall be mutually

discussed and approved by the Owner after incorporating necessary corrections by the

Contractor as may be required.

4.3 Quality Assurance Documents

The Contractor shall be required to submit all the Quality Assurance Documents as

stipulated in the Quality Plan at the time of Owner’s inspection of equipment / material.

The owner or his duly authorized representatives reserves the right to carry out Quality

Audit and Quality surveillance of the systems and procedures of the Contractor’s / his

vendor’s Quality Management and Control Activities.

4.4 Owner’s Supervision

To eliminate delays and avoid disputes and litigation it is agreed between the parties

to the Contract that all matters and questions shall be resolved in accordance with the

provisions of this document.

The manufacturing of the product shall be carried out in accordance with the

specification. The scope of the duties of the Owner’s pursuant to the contract will include but

not be limited to the following:

(a) Interpretation of all the terms and conditions of these Documents and Specification.

(b) Review and interpretation of all the Contractor’s drawings, engineering data etc.

(c) Witness or authorize his representative to witness tests at the manufacturer’s works or

at site, or at any place where work is performed under the Contract.

(d) Inspect, accept or reject any equipment, material and work under the Contract, in

accordance with the Specification.

(e) Issue certificate of acceptance and / or progressive payment and final payment

certificate.

(f) Review and suggest modification and improvement in completion schedules from

time to time; and

Supervise the Quality Assurance Programme implementation at all stages of the Works.

4.5 MANDATORY TEST CHECKING OF MATERIAL ON RECEIPT IN

THE STORES:

(i) NO Material shall be allowed to use against the awarded works without successful

testing as per provisions of Technical Specifications for which testing facility is available at

JdVVNL’s CTL Lab, Jodhpur. The due payment against supplies & erection, whenever it

falls due, shall be released only after receipt of successful test reports for the samples

selected at stores by the NODAL or the nominated officers of the JDVVNL.

Page 32: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-32

(ii) In case material/equipments do not pass the test and contractor request for re-testing

of second sample and if it is accepted by the Discom, the testing fees will be charged as per

item wise prevailing rates of CTL testing charges of material and the amount will be payable

by the contractor on this account to the Sr. Accounts Officer ( CPC), JdVVNL, Jodhpur.

4.0 SERVICE CONDITIONS

All out door Equipment / material to be supplied/erected against this specification

shall be suitable for satisfactory continuous operation under tropical conditions as specified

below:

1. Maximum ambient air temperature in shade 500C

2. Minimum ambient temperature in shade -2.50C

3. Maximum Relative humidity 90%

4. Minimum Relative humidity 10%

5. Average Annual rainfall 10-100 Cm.

6. Maximum wind pressure (Kg. Per sq. m.) 45

7. Height above mean sea level Less Than 1000 meter

8. Dust storms are liable to occur during the period March to July

9. Average number of rainy days per annum 100

10. Isoceraunic level (days / year) 40

11. Moderately hot and humid tropical Yes

12. Seismic level (horizontal acceleration) 0.08 g

6.0 STATUTORY REGULATIONS & STANDARDS: -

6.1 Statutory Regulations: -

The contractor is required to follow Indian Electricity Act 2003, Indian Electricity

Rules, 1956, as amended and other local rules and regulation referred in this specification.

6.2 Reference Standards: -

The codes and/ or standards referred to in the specification shall govern, in all cases

wherever such references are made. In case of a conflict between such codes and/or standards

and the specification, latter shall prevail. Such codes and/or standards referred to shall mean

the latest revisions, amendments/changes adopted and published by the relevant agencies

unless otherwise indicated.

7.0 EARTHING

Page 33: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-33

Earthing shall generally be carried out in accordance with the requirements of Indian Electricity Rules, 1956 and the relevant regulations of the Electricity Supply Authority concerned and as indicated below

1. All metallic supports shall be properly connected to the earth wire.

2. For lattice structure the metal cross-arms and insulator pins shall be bonded and properly connected to the earth wire. Ground earthing is to be provided at every 4/5 structure support.

3. The supports on either side of the road, railway or river crossing should be

earthed.

4. All supports passing through inhabited areas, road crossings and along such other places, where earthing of all structure(s) is considered desirable from safety considerations should be earthed.

In special locations, railway and telegraph line crossings, special structures, etc., rod earthing should be done.

8 .0 TESTING AND COMMISSIONING

When the line/SS is ready for energisation, it should be thoroughly inspected in

respect of the following:-

1. Earthing System: To check whether the earthing connections of supports and fitting are intact. Measure earth resistance with earth tester.

2. After the visual inspection is over and satisfied, the conductor is tested for continuity/ground, by means of magger. At the time of testing through magger, person should not climb on the structure or touch the guarding, conductor, guy wire etc.

3. Before charging any new line, cable, substation it should be ensured that the required inspection fee for the new line, cable, and substation is paid to the Electrical Inspector and approval obtained from him for charging the line.

4. The line, cable, substation should be energized before the officer who has been authorized by the Nigam in this regard.

5. Before energizing any new line, cable, substation the officer-in-charge of the line, cable, and substation shall notify to the workmen that the line is being energized and that it will no longer be safe to work on line. Acknowledgement of all the workmen in writing should be taken in token of having intimated them.

6. Wide publicity by Tom-toming should be arranged in all the localities through which the line, that is to be energized passes, intimating the time and date of energizing and warning public against the risk in meddling with the line.

7. The Officer-in-charge of the line, cable, substation shall personally satisfy himself that the same is in a fit state to be energized.

9. WASTAGES:

This being a total turnkey contract, no wastage shall be allowed in any material except

3% of length in case of conductor and 1% of length in earth wire towards sag &

jumpering etc. Wastage if any shall be born by the Contractor.

Page 34: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-34

1 GENERAL INSTRUCTIONS

1.1 The JODHPUR Vidyut Vitran Nigam Ltd, or any authority designated herein after

called 'OWNER' will receive bids in respect of services as set forth in the

accompanying specification. All bids shall be prepared and submitted in accordance

with these instructions. The Bidder, in his own interest is requested to read very

carefully these instructions and the terms and conditions as incorporated in General

Conditions of Contract and Technical specification before filling the Bid proposal

form. If he has any doubt as to the meaning of this specification or any portion

thereof, he shall before submitting the Bid, refer the same to the Superintending

Engineer (TW), Jodhpur in writing well in time before the specified date of opening

of Bids so that such doubts may be clarified. Submission of the Bid shall be deemed

to be the conclusive proof of the fact that the Bidder has acquainted himself and is in

agreement with all the instructions, terms and conditions governing the specification,

unless otherwise specifically indicated / commented by him in his Bid.

1.2 Bids submitted after the time and date fixed for receipt of bids as set out in the

invitation to Bid may be rejected.

1.3 The works referred herein shall cover the entire scope of the proposal which include

commissioning and erection & commissioning of equipment including the successful

completion of performance and guarantee tests which the owner desires to get

executed.

2 INTRODUCTION OF WORK:

JODHPUR Vidyut Vitran Nigam Limited intends for Route Survey, Design,

Supply of Material, Erection, Testing and Commissioning, of proposed work on

Turnkey basis against TN-TN-.

2.1 The job involves as detailed in Part-II “Scope of Work”, however any work if

specifically not mentioned but reasonably implied for the successful implementation

and good performance of the proposed work are deemed to be included and are to be

executed.

2.2 The Agency is advised in its own interest to examine the bid documents, instructions,

forms, terms and general information. Failure to provide information, which is

essential to evaluate the bid or to provide timely clarification or substantiation of the

information supplied or submission of bid not substantially responsive to the bid

document may result in disqualification.

2.3 FIELD CONDITIONS: The bidder may in its own interest, before submitting the bid,

inspect and examine the area involved and satisfy him regarding the field conditions

and present supply system of "Area covered in scope of work". For ascertaining the

field condition the Agency may contact the concerned XEN (O&M) / Concerned

Assistant Engineer. No claim for change in the bid or terms & conditions of the

contract shall be entertained on the ground that the conditions are different than what

were contemplated.

Part : III Section-I INSTRUCTION TO BIDDERS (ITB)

Page 35: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-35

2.4 The scope of the proposal shall be on the basis of a single bidder's responsibility,

completely covering all the material supply and erection activities specified under the

accompanying technical specification. It will include the following:

2.5 Detailed of the equipment

2.5.1 (a) Complete manufacture including shop testing prior to dispatch at

manufacturer’s premises as per contract specifications by the representative of

owner.

2.6 Providing Engineering drawings, data, operation manual, etc. for the owner's

approval.

2.7 Packing and transportation from the manufacturer’s works to the site, receipt,

storage, preservation and conservation of equipment at the site, pre-

assembly, if any, erection, testing and commissioning of all the equipments,

Reliability tests and performance and guarantee tests on completion of

Commissioning.

2.8 Bids not covering the above entire scope of works shall be treated as

incomplete and shall be rejected.

3 QUALIFICATION REQUIREMENTS

The qualification requirements of the bidders are mentioned in Section-III Part-II

of the bidding documents. The bids of bidders fulfilling these requirements only

would be considered for evaluation & award of contract.

4.0 SUBMISSION OF BIDS:

The bidders, in their own interest, are requested to read very carefully Section-I

(Instruction to bidders), Section-II (General Condition of Contract), Section-III Part-

IA & IB (Erection Condition of Contract) & Section-III part-III (Technical

Specification) before filling the bid. The Bid documents be downloaded from

J d V V N L website http://energy.rajasthan.gov.in /jdvvnl , or

http://eproc.rajasthan.gov.in and upload the tender on website of RISL

www.http://eproc.rajasthan.gov.in. No hard copy of the bidding documents will

be provided to the bidders through this office. In case of any discrepancy found in

bidding documents downloaded from the website and appended with the bid (as a

bid document) and original copy of such document available in the office of

Superintending Engineer (TW), JdVVNL, Jodhpur will be considered as final

document for all purpose. The cost of Bid document as published in NIT shall be

furnished along with EMD before opening of bid and scan copy be upload on

website of RISL. The document shall be downloaded/ uploaded in the manner

prescribed in bid document.

• Tenders shall be submitted online in the electronic format attached here to and all

blanks in the tender and the schedule to the specification shall be duly filled in. The

completed forms, schedule(s) shall be considered as part of the contract documents

in the case of successful bidder (s).

Page 36: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-36

• No alteration should be made to the format of the tender specification and

schedules. The bidder must comply entirely with specification.

• The tender and all accompanying documents shall be in Hindi/English Language

and shall be signed digitally by a responsible and authorized person. The name,

designation and authority of the signatory shall be stated in the tender.

• Tender should be filled in only with ink or typed and must be submitted online after

signing digitally.

• All additions, alterations and over-writing in the bid must be clearly signed by the

signatory of the bidder otherwise bid will be summarily rejected.

• The bidder must quote the prices strictly in the manner as indicated herein, failing

which bid is liable for rejection. The rate/prices shall be entered in words as well as in

figures. These must not contain any additions, alterations, over-writing, cuttings or

corrections and any other marking which leave any room for doubt.

• The Purchase Authority will not be responsible to accept any cost involved in the

preparation or submission of bids.

• Any printed conditions of sale on the bid shall not be accepted by the purchase

Authority.

• The tender offer shall be submitted in time specified on http://eproc.rajasthan.gov.in

in electronic format in the following manner:

• COVER – I for details of EMD, Tender processing fee and Cost of Tender

document (to be filed in pdf format).

• COVER – II for Techno- Commercial Bid (to be filed in pdf format):

In this part of bid, bidder will have to furnish Guaranteed Technical Particulars in

regard to all requirement details of Technical Specification (Section-III part-III) and

confirmation of commercial terms and conditions of GCC (General Conditions of

Contract) and its addendum/corrigendum, if any, along with details required in

various/schedules “EXCEPT THE PRICE SCHEDULE” so that the purchaser may be

able to examine whether the offer submitted is technically acceptable and also confirm

to our commercial terms and conditions or not.

• COVER – III for Financial/Price Bid/BOQ (to be filed in xls format).

This price bid shall include submission of details of prices as per Schedule of the

specification. The price bid will be opened only after being satisfied with Technical

and Commercial Bid as per qualifying requirement stipulated in the Specification

and bid of such qualified bidders will only be opened. The date of opening of such

price Bids will be intimated in due course of time.

Page 37: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-37

• Bidders shall indicate in their bid the name and complete address of Excise

authorities under whose jurisdiction is their works / offices falls.

• All bids and accompanying documents shall be addressed to the S.E. (TW)

JODHPUR Vidyut Vitran Nigam Limited, JODHPUR.

• The bidder should sign the tender documents digitally and stamped on each page.

• The tenders given in the form other than prescribed form will not be considered.

• Only one representative, on submission of valid authorization of the signatory of

the bid, will be allowed to be present during the opening of the bid.

• The conditional bids shall not be accepted.

• The bidder must clearly fill up each and every particular of Guaranteed

Technical Particulars annexed with Technical specification otherwise he will be

responsible for Technical non-responsiveness.

5. DOCUMENTS TO BE UPLOADED WITH THE TENDER:

The tender shall be accompanied with the following schedules, documents. The tender

who is not accompanied by any or all the following mentioned schedules, documents or

is accompanied by incomplete annexure/ schedules is liable for rejection.

• Cover I for details of EMD / Tender processing fee and Cost of Tender document as detailed

below:

• Proof of depositing EMD (DD/Banker’s Cheque)/ Scan copy of BG for EMD

• Proof of depositing DD/Banker’s Cheque towards e- tender processing fee.

• Proof of depositing cost of tender documents (DD/Banker’s Cheque).

• Cover II for Techno- Commercial Bid as detailed below duly signed and stamped:

• Schedule-1 Bid Proposal Form.

• Schedule-2 Price Bid

• Schedule-3 for confirmation with regard to “ NIL DEVIATION” in respect of

commercial terms & conditions of the specifications.

• Schedule-4 for confirmation with regard to “NIL DEVIATION” in respect

of Technical terms & conditions of the specifications. Confirmation of

required guarantee technical particulars of material to be supplied / used

and purchase of same from Approved vendors by MM wing of Jd.VVNL or

TW wing of respective Nigam.

• Schedule-5 Work Completion schedule .

• Schedule-6 (A) Check List for Qualification Requirements

• Schedule-6(B) Check List for Qualification Requirements

• Schedule-7 List of Previous Experience of Work Executed

• Schedule-8 List of Equipments and Technical Hands

• Copy of class “A/B” Electrical contractor license.

• Copy of registration with labour department, insurance certificate,

undertaking in respect of registration of building and construction, Act-1996

and other supporting documents required as per specifications.(as applicable)

• Other details/information in the schedule(s) or Annexure(s), wherever

specified in Section I & II.

Page 38: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-38

• Power of Attorney on NJS Rs. 500/- for authorized signatory to sign the

tender document digitally.

• Name & Complete address of excise authority under whose jurisdiction their

works/office falls.

• Copy of latest Audited Account for last 5 years.( F.Y. 2014-15 to 2018-19)

• Name & correspondence address of the bidder along with phone /Fax No. &

email address.

• Confirmation of firm Not-blacklisted and no pending litigation.

• PF/ESI Registration.

• GSTIN, PAN, Bank A/C No. with IFSC code and Branch Address

• Cover-III For financial / price bid / BOQ (to be filled in Excel format) in

prescribed schedule.

6. INFORMATION REQUIRED WITH THE PROPOSAL

• The bids must clearly indicate the name of the manufacturer, the type of model of

each principal item of equipment proposed to be furnished and erected. The bid

should also contain drawings and descriptive materials indicating general

dimensions, material from which the parts are manufactured, principles of operation,

the extent of pre-assembly involved, major construction equipment proposed to be

deployed, method of erection and the proposed erection Organizational structure.

• The Bidder in the form of separate sheets, drawings, catalogues, etc. in two copies

shall provide the above information.

• Any bid not containing sufficient descriptive material to describe accurately the

equipment proposed may be treated as incomplete and shall be rejected. The Owner

will retain such descriptive materials and drawings submitted by the Bidder. Any

major departure from these drawings and descriptive material submitted will not be

permitted during the execution of the Contract without specific written permission/

approval of the owner.

• Oral statements made by the Bidder at any time regarding quality, quantity or

arrangement of the equipment or any other matter will not be considered.

• The bidder may use in the bid Standard catalogue pages and other documents to

provide additional information and data as deemed necessary.

• The Bidder, along with its proposal, shall submit a list of recommended erection

equipments and materials, which may be required for the purpose of erection of

equipment and materials supplied under the contract.

• In case the 'Proposal' information contradicts the specification requirements, the

specification requirements will govern, unless otherwise brought out clearly in the

technical/ commercial deviation schedule.

• The bidder shall furnish the guaranteed technical particulars in the schedule(s)

provided in this document for various materials.

7.0 RECEIPT AND OPENING OF BIDS.

• Bidder shall submit their bid in electronic format, digitally signed and

stamped on each page. Bidder shall procure Digital Signature Certificate

(DSC) as per IT act - 2000.

Page 39: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-39

• The electronically received bids will be opened in the office of the

Superintending Engineer (TW), JODHPUR on stipulated date & time in the

presence of such bidders or their authorized representative, who choose to be

present. The system does not permit electronic submission of late tenders after the

due date & time.

• In case, the date fixed for opening of the tenders be declared as a public holiday, the

bid shall be opened on the next date on which office re-opens after such holiday(s).

8. FORMAT AND SIGNING OF BID:

• The tender must contain the name, designation and place of business of the person

or persons making the tender and must submit online & signing digitally with

his DSC (Digital Signature). Tender by a partnership firm must be furnished with

full names of all the partners and should be signed digitally by one of the

member of partnership firm or by a authorized representative indicating the

designation of the person or persons, with authority letter signed by the

Chairman/ Secretary other person authorized to bind the Corporation / Company in

the matter.

• Bid by a partnership must be furnished with full names of all partners and be

signed with the partnership firm name, followed by the signature (s) and

designation (s) of the authorized partner (s) or other authorized representative (s).

• Bids by corporation/ company must be signed with the legal name of the

corporation/ company by the President, Managing Director or by the Secretary or

other person or persons authorized to bid on behalf of such corporation/ company in

the matter.

• A bid by a person who affixes to his signature the word 'President',

'Managing Director' 'Secretary', 'Agent' or other designation without disclosing his

principal will be liable to be summarily rejected.

• Satisfactory evidence of authority of the person signing on behalf of the Bidder

shall be furnished with the bid.

• The Bidder's name stated on the proposal shall be exact legal name of the firm.

• Erasures or other changes in the bid documents shall bear the initials of the person

signing the bid.

• Bids not conforming to the above requirements of signing shall be disqualified.

9. EFFECT AND VALIDITY OF BID :

• The submission of any bid connected with these documents and specification shall

constitute an agreement that the bidder shall have no cause of action or claim, against

the owner for rejection of his bid. The owner shall always be at liberty to reject or

Page 40: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-40

accept any bid or bids at his sole discretion and any such action will not be called

into question and the bidder shall have no claim in that regard against the owner.

• The bids shall be valid for a minimum period of 120 days (One hundred twenty)

days from the date of opening of t e c h o - c o m m e r c i a l bids. Bids mentioning a

shorter validity period than specified are likely to be summarily rejected /ignored.

• Owner may ask for extension in validity period. The bidder will be at liberty to

accept it or not. In case bidder agrees to extend the validity period without changing

his original offer, he will be required to extend validity period of the Bank Guarantee

(Submitted against the EMD) suitably.

10.0 EARNEST MONEY:

• The bidder shall furnish bid guarantee (Earnest Money Deposit) as mentioned in

“Invitation for bids”/Tender Notice by crossed bank draft payable in the name of

Senior Accounts Officer ( CPC ), Jd.VVNL, Jodhpur. The Demand draft shall be

accompanied with the bid in an envelope as per instructions given in these bidding

documents. No other mode of deposit shall be accepted.

Or

The bidder shall furnish 20% amount of earnest money deposit by crossed bank draft

payable in the name of Senior Accounts Officer ( CPC ), Jd.VVNL, Jodhpur along

with irrevocable bid bank guarantee of balance 80% amount on non-judicial stamp

papers of Rajasthan state worth 0.25 % of BG value & max. upto Rs. 25,000/-

whichever is less duly authenticated either by a first class Magistrate or Notary Public

or directly confirmed by the issuing Bankers furnished valid initially upto the bid

validity period plus 30 day grace period and further extendable till finalization of bid.

(Bid bank guarantee format is enclosed at Annexure-A). The demand draft of 20%

amount of EMD and bank guarantee for balance 80 % amount shall accompany with

the bid in an envelope as per instructions given in these bidding documents. “In case

of invocation of Bank guarantee issuing Bank must authorize for entertaining the case

at the sister branch located in Rajasthan”. The Bank guarantee must be from any

Nationalized / Scheduled Bank. (Bid-bank guarantee form for EMD is enclosed with

this doc.) • Any other mode except as specified under clause (i) above such as Postal orders/

cheques/ other forms of instruments are not acceptable. Any tender not accompanied

with Crossed Bank Demand Draft against 20% amount of EMD along with proper

BG against balance 80% amount of EMD or crossed Bank Draft against full

amount of Earnest Money shall be rejected and the tender will not be accepted.

• In case of unsuccessful bidder, the Earnest money will be refundable on

production of the original receipt within a fortnight after finalization of the tender. In

case of successful bidder(s) the Earnest Money will be taken into account in arriving

at the amount of the security cum performance guarantee if vendor(s) desires to

furnish cash security deposit. However if the security cum performance guarantee is

Page 41: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-41

furnished through bank guarantee (BG) the EMD will be released consequent to

acceptance of such BG.

• Request for adjustments/proposals for acceptance of Earnest Money deposits, if

any, already lying with the Discom’s in connection with some other tenders/orders

shall not be entertained.

• No interest shall be payable on such Deposits.

• The Nigam reserves the right to forfeit Earnest Money Deposit or a part thereof in

circumstances, which according to it indicate that the bidder is not earnest in

accepting/executing order placed under the specification.

11.0 COST OF SPECIFICATION:

The cost of Bid document as published in NIT shall be furnished along with

EMD prior to opening of bid and scan copy be upload on website of RISL. The

document shall be downloaded / uploaded in the manner prescribed in bid

document. The cost of bid and EMD shall be furnished through Bank Draft

payable to Senior Accounts Officer ( CPC), Jd.VVNL, Jodhpur.

12.0 LATE BIDS:

The system does not permit electronic submission of late tenders after the due

date & time.

13 CLARIFICATION OR MODIFICATION OF BIDS:

To assist in the examination, evaluation and comparison of bids, Nigam may ask

Bidders individually for clarification, in writing. No change in the substance of

the bid shall be permitted except as required to confirm the correction of any

typographical error. Jd.VVNL may modify ‘Financial bid’ based on discussions

with individual Bidders short-listed even after opening of ‘Technical bid’.

14 REJECTION OF BIDS

14.1 Any action on the part of the Bidder to revise the rates / prices and modification in the

substance of original tender. Submission of any supplementary information unless &

otherwise asked for at his own instance after the opening of the Bid may result in

rejection of the Bid and also debar him from submission of Bid to the NIGAM at

least for one year.

14.2 The owner reserves the right to accept or reject any bid, and to annul the bidding

process and reject all bids at any time prior to award of contract, without thereby

incurring any liability to the affected bidder or bidders or any obligation to inform the

affected bidder or bidders of the grounds for the owner's action.

Page 42: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-42

15.0 OPENING OF FINANCIAL BID:

The date and time for opening “Financial bid” will be intimated to the short-listed

Bidders by Nigam in due course through ‘e’-procurement web portal. ‘Financial

Bid’ of the Bidders, not short-listed shall not be opened.

16. SIGNING OF AGREEMENT:

The successful bidder shall, on receipt of Letter of Award from SE(TW),

JdVVNL, Jodhpur enter into a contract with SE(TW), JdVVNL, Jodhpur by

jointly signing an agreement. The draft of the agreement based on the terms

sheet, detailed in Section-II shall be forwarded to the successful bidder for

execution. The agreement shall be executed within fifteen days thereafter. The

person to sign the agreement shall be duly authorized by the Bidder. Amount of

stamp duty for execution of Contract Agreement shall be borne by Contractor.

17.0 UNDERSTANDING & CLARIFICATIONS ON DOCUMENTS &

SPECIFICATIONS.

17.1. The Bidder is required to carefully examine the specifications and documents and

fully inform himself as to all the conditions and terms matters which may in any way

affect the Work or the cost thereof. If any Bidder finds discrepancies or omissions in

the specifications and documents or is in doubt as to the true meaning of any part, he

shall at once request in writing for an interpretation / clarification by the owner. The

Owner, then, will issue interpretation and clarifications as he may think fit in writing.

After receipt of such interpretations and clarifications, the Bidder may submit his bid

but within the time and date as specified in the Invitation to Bid. All such

interpretations and clarifications shall form a part of the specifications and

documents, and accompany the bidder's proposal.

17.2. Verbal clarifications and information given by the owner or his employee(s) or his

representative(s) shall not in any way be binding on the owner.

18.0 DUTIES AND TAXES

18.1 GST as applicable and other taxes /duties/cess as applicable / leviable shall be

included in the bid price. Price break up shall be submitted by the bidder after award

of work order.

18.2 Any income tax, surcharge on income tax and other corporate taxes as attracted under

the law, shall be deducted at source, as per the prevailing Govt. rules by payment

making authority from each bill. Necessary TDS certificate shall be issued by

payment making authority.

18.2Nigam is registered dealer under Rajasthan Sales tax (VAT) and Central Sales tax Act

and is entitled to concessional rate of Central / State sales tax as per rules in force. In

accordance to above, the present applicable concessional rate of CST is @ 2 % and

VAT is @ 5 % to Nigam, and therefore for supply of material, the CST / VAT shall

be payable at actual subject to maximum of concessional rate of 2% / 5 % (as the case

may be). Necessary declaration Form ‘C’ or prescribed certificate for availing

Page 43: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-43

supply of material on concessional sales tax shall be issued by the Nigam on

completion of ordered work.

18.3 Deduction of labour cess at source @ 1% from the each running bills of all

running projects of the suppliers/contractors on account of the building and other

construction workers (regulation of employment and conditions of service) act, 1996 &

the building and other construction workers welfare cess act 1996 and deposit the same

under the following budget head through challan under intimation to the cess collector

and assessing officer of the respective jurisdiction within 30 days from the deduction of

cess:-

The Cess will be deducted as applicable on the contract. Any statutory variation /

upward variation in existing rates of taxes / duties / levies / charges during contracted

completion period shall be to Nigam’s account. However, for claiming any such

statutory variation, the contractor is required to furnish the documentary evidence /

proof in support of the same for scrutiny and approval. Any downward variation in the

GST rate if occurred in future then the effect of same will be taken into account in the

contract amount and the benefit of same will be taken by Nigam.

POLICY FOR BIDS UNDER CONSIDERATION

19.1 Bids shall be deemed to be under consideration immediately after they are opened

and until such time official intimation of award / rejection is made by the owner to

the bidders. While the bids are under consideration, bidders and / or their

representatives or other interested parties are advised to refrain from contacting by

any means, the owner and / or his employees / representatives on matters related to

the bids under consideration. The owner, if necessary, will obtain clarifications on the

bids by requesting for such information from any or all the bidders, either in writing

or through personal contact, as may be necessary. Bidder will not be permitted to

change the substance of the bid after the bid has been opened.

20.0 SCOPE OF WORK / QUANTITIES

20.1 The scope of work and quantities indicated for each item in the G-Schedule are

tentative, Nigam reserves right to delete or add any scope of work.

(a) The quantities indicated in the accompanied schedule are only provisional

and owner reserves the right of revising the same at the time of placing the

order.

(b) However the actual quantity of material and quantum of work involved

shall be based on the final survey report duly authenticated by the

concerned Superintending Engineer (O&M). The revised survey report

along with BOQ shall be approved as per Clause No. 6.0 of Section-II

(GCC).

(c) The owner reserves the right to split the quantities and to entrust the order

for the line to one or more bidders. The bidder shall agree to execute

part quantities order on him at the rates/ prices mentioned in his bid and/or

accepted by the owner.

(d) The owner may provide part or full quantity of some items to the

contractor as per his discretion depending upon the prevailing

Page 44: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-44

circumstances ,required in erection/execution of related work activity. No payment

towards the cost of such material as indicated in ‘G’ Schedule of prices shall be

payable to the contractor.

20.2 The variation in awarded quantity/ value shall be allowed subject to

provisions mentioned under RTPP Act -2012 and rule -2013 mentioned thereof

and amended from time to time which shall be based on the joint survey with

Nigam Officers during commencement period and submitted with inception

report.

LOCAL CONDITIONS

21.1 It will be imperative on each bidder to fully inform himself of all local conditions and

factors which may have any effect on the execution of the works covered under these

documents a n d s p e c i f i c a t i o n s . The owner shall not entertain any request for

clarifications from the bidders, regarding such local conditions.

21.2 It must be understood and agreed that such factors have properly been investigated

and considered while submitting the proposals. No claim for financial adjustment to

the contract awarded under these specifications and documents will be entertained by

the owner. Neither any change in the time schedule of the contract nor any financial

adjustments arising thereof shall be permitted by the owner, which are based on the

lack of such clear information or its effect on the cost of the works to the bidder.

21.0 BRAND NAMES:

The specific reference in this specification and documents to any material by trade

name, make or catalogue number shall be construed as establishing standard of

quality and performance and not as limiting competition. However bidders may offer

other similar equipment provided it meets the specified standard, and performance

requirements. The bidder shall furnish technical information about the alternative

equipment to enable the owner to determine the acceptability of equipment. The

owner shall be the sole judge of the acceptability of the alternative equipment.

22.0 PRELIMINARY EXAMINATION AND EVALUATION:

23.1 The Owner will examine the bids to determine whether they are complete, whether

any computational errors have been made, whether required sureties have been

furnished, whether the documents have been properly signed, and whether the bids

are generally in order.

23.2 Prior to the detailed evaluation, the owner will determine the substantial

responsiveness of each bid to the bidding document. For purpose of these clauses, a

substantially responsive bid is one which conforms to all the terms and conditions of

the bidding document without material deviations. A material deviation is one which

affects in any way the prices, quality, quantity or delivery period of the equipment or

which limits in any way to the responsibilities or liabilities of the bidder of any right

of the owner as required in these specifications and documents. The Owner's

determination of a bid's responsiveness shall be based on the contents of the bid itself

without recourse to extrinsic evidence.

23.3 A bid determined as not substantially responsive will be rejected by the owner and

shall not subsequently be treated responsive by the bidder by correction of the non

conformity by the bidder.

Page 45: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-45

23.4 The “Price bids” of the bidders whose “Techno- commercial bid” found in order &

responsive and meets, the qualification requirements as specified in the bidding

documents, only shall be opened.

23.5 Bid price shall mean the price evaluated on the basis of premium quoted on basic

price by each bidder in his proposal for the complete scope of works.

23.6 The owner may waive any minor infirmity or non-conformity or irregularity in a bid

which does not constitute a material deviation, provided such waiver does not

prejudice or affect the relative ranking of any bidder.

23.7 The owner will evaluate and compare the bids previously determined to be

substantially responsive, pursuant to manner specified above, for each package

separately. No bid will be considered if the complete requirements covered in the

package is not included in the bid.

23.0 AWARD OF CONTRACT

24.1 Notification of award of contract will be made in writing to the successful bidder(s)

by the owner.

24.2 The contract will be awarded to the best qualified and the substantially responsive

bidder offering the lowest evaluated bid in conformity with requirements of these

specifications and documents and the owner shall be the sole judge in this regard and

subject to the provisions of these instructions to bidders and other terms and

conditions detailed out in these documents and specifications. A responsive bid is one

which accepts all terms and conditions of these specifications and documents without

any major modifications. A major modification is one which affects in any way the

prices, quality, quantity or delivery period of the equipment or which limits in any

way the responsibilities or liabilities of the bidder or any rights of the owner as

required in these specifications and documents. However, the owner may waive any

minor formalities or irregularities in the bid.

24.3 The contract will be awarded to first lowest responsive bidder after having

discussions & negotiations with him, for ascertaining the reasonable price for

tendered work. However where the prices quoted / agreed by such first lowest bidder,

even after negotiation is considered higher, the competent purchase committee /

authority may offer a still lower price, considered reasonable to all qualified

participating bidders including first lowest one. On acceptance of such price by one

or more bidders, the contract would be awarded to bidder standing lowest among

those counter offer prices) as per original comparative statement.

24.4 Orders for supply of material and erection work contracts shall be placed separately

on the successful bidders .The contractor shall be fully responsible for the works to be

executed under both the contracts and it should be expressly understood by him that

any breach under any one of contract shall automatically be deemed as a breach of

another contract and any such breach or occurrence giving the owner a right to

terminate a contract and or recover the damages under that contract shall give owner

a right to terminate the another contract and or recover the damages under such

contract as well. However such breach or occurrence in any contract shall not

automatically relieve the contractor of any of his obligations under another contract.

25.0 CONTRACT QUALITY ASSURANCE

25.1. The bidder shall include in his proposal the quality assurance program containing the

Overall quality management and procedure which he proposes to follow in the

Page 46: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-46

performance of the works during various phases as detailed in relevant clause of the

General Technical Conditions and Specification.

25.2. At the time of award of contract, the detailed quality assurance program to

be followed for the execution of the contract will be mutually discussed and

agreed to and such agreed program shall form a part of the contract.

26.0 INSURANCE

The bidder's insurance liabilities pertaining to the scope of works are detailed out

in clause titled “Insurance” in clause No. 13.0 of “General Conditions of Contract

and clause No. 25.0 of Erection Conditions of contract. Bidder's attention is

specifically invited to these clauses. Bid price shall include all the cost in pursuance

of fulfilling all the insurance liabilities under the contract.

27.0 MAINTENANCE TOOLS AND TACKLES

The proposal shall include all special tools and tackles required for the operation

and maintenance of the equipment in each equipment package. The bidder shall

indicate all the above items in the proposal sheets in the form of a schedule giving

therein the description and the quantity of each item. The price to be quoted in “G”

schedule by the bidder shall include prices of these tools and tackles. These tools and

tackles shall be delivered at site along with the last consignment of equipment

and in no case earlier than this unless otherwise specified in the Technical

Specification.

28.0 DRAWINGS, TEST CERTIFICATES & GUARANTEED

TECHNICAL PARTICULARS (TO BE FURNISHED BY SUCCESSFUL

BIDDER IN CASE OF WORK ORDER)

28.1 Dimensional drawings indicating the general and/or detailed constructional

features/cross sectional views/ assembling, Schematic arrangement and lay out for

the material/ equipment and its erection and commissioning and use wherever

specially required under Section –III Part -I of this specification.

28.2 Notwithstanding anything contained in sub para (26.1) above, the Bidder may also

furnish such drawings which according to him are desirable for the material /

equipment offered.

28.3 The purchaser may require the drawings as furnished by the Bidder to be modified

to suit the requirements of the specification. The approval of final drawings shall be

necessary and binding and the supplies shall conform to the same.

28.4 In case of any specific alternative requirement of type tests the same shall

be furnished as per Volume-I of this specification.

28.5 The Bidder/supplier shall be required to furnish the routine/manufacturer(s)

factory test certificate(s) for the tests carried out during manufacture in accordance

with the latest standard specifications.

Page 47: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-47

29.0 GENERAL

• Specification/ Tender document may be downloaded by any of the interested bidder

from http://eproc.rajasthan.gov.in for the consideration of his tender up to

stipulated date & time. However, online tenders will only be considered if the

bidder have deposited requisite fee.

• The supplier shall treat the details of the specification and other bid documents

as private and confidential and they shall not be reproduced without the written

authorization of the purchaser.

• The purchaser does not bind him to accept the lowest or any bid or any part of the

bid and shall not assign any reason(s) for the rejection of any bid or a part thereof.

• The fact of submission of bid to the purchaser shall be deemed to constitute a

contract between the bidder and purchaser whereby such bid shall remain open for

acceptance by the purchaser within the validity period and bidder shall not have any

option to withdraw their offer or impair/ derogate the same. Where the bidder is

notified about acceptance of their bid by the purchaser during the validity period,

they shall be bound by the terms and conditions of various contract documents as

per specifications of the bid documents in question until formal contract in this

regard, has been executed between them and the purchaser.

• The Successful bidder shall have to execute contract documents for the

proper fulfillment of the same.

• Any action on the part of the bidder to revise the rates/prices on their own after

the opening of the bid may result in rejection of the bid and also debar them

from submission of bids to the Nigam upto three years or next bid whichever is later

and action shall be taken as per provisions mentioned in RTPP Act 2012 and Rules

2013 and amended from time to time.

30.0 SPECIAL CONDITIONS OF CONTRACT

Following points are to be given personal attention by the bidder as these play vital

role in the contract: -

• The contractor shall quote only percentage above or below of prices given in ‘G’

schedules for material and erection component separately. The quantities indicated

in ‘G’ schedule are only provisional. The actual quantity of material and quantum of

work involved shall be based on detailed survey to be conducted by the contractor

with Nigam’s authorized representative before commencement of the ordered work.

• “Time is the essence of agreement”. To honour this no time extension will be given

in normal condition as the work is to be finished within scheduled time. However

extension in work completion time will be considered /granted under force majeure

conditions and on account of unforeseen or unavoidable circumstances beyond the

control of owner/contractor as specified in this specification. Progress of the work

will be examined on pro-rata basis. Priority/ Procedure of the work will be decided

by Engineer in-charge.

• It is assumed that item and work of minor nature are included in the price quoted.

However major item and work if not included in the bid, and if is the demand of

work, then contractor will have to provide it. The payment for supply erection of

such items/works shall be made in accordance with the prevailing market rates/

Standard issue rate list of the Nigam and erection charges shall be paid on CLRC

basis with quoted premium by the bidder.

Page 48: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-48

• Since this is a work on “Turnkey basis”, so price should include supply, installation,

testing, commissioning and proper maintenance and replacement of item till Security

cum Performance guarantee period is over. No matter if all above is not narrated with

the item, it is presumed that price given by bidder includes all of above work.

• Guaranteed technical particulars of each item have been indicated in the technical

specification which are to accepted /confirmed and are to be submitted after award of

contract. No deviation will be accepted in this respect. Any other document, which

may deem fit will also be included in the document of agreement even if it is not

included in the bidding document.

31.0 NOTE: 31.1 The bidders are requested to submit their bids prior to last date of submission to avoid

Non- submission of their bids up to prescribed date & time due to non-availability /

hanging of website at last moments or any reason whatsoever. The last date of

submission of bids will not be extended on such accounts.

31.2. Furnishing of Earnest Money/Exemption certificate & proof for deposit of Earnest

Money, e-tender processing fees & cost of tender documents before techno-

commercial bid opening is essential otherwise the techno-commercial bid in

electronic form (cover II and III) will not be opened.

31.3 (i) The bidder will have to deposit prescribed cost of tender specification by

DD/Banker’s Cheque payable in favour of Senior Accounts Officer ( CPC)),

Jd.VVNL , Jodhpur up to stipulated date & time in the office of the SE(TW),

Jd.VVNL, Jodhpur.

(ii) The bidder will have to deposit prescribed EMD by DD/Banker’s Cheque

payable in favour of Senior Accounts Officer ( CPC), Jd.VVNL, Jodhpur up to

stipulated date & time in the office of the SE(TW), Jd.VVNL, Jodhpur.

• The bidder will have to deposit prescribed Processing Fee by

DD/Banker’s Cheque in favour of Managing Director, RISL, payable at

Jaipur with the SE (TW), JdVVNL, Jodhpur up to stipulated date & time in

in the office of the SE(TW), JdVVNL, Jodhpur.

• The bidder will furnish bank guarantee in favour of SE (TW), JdVVNL,

Jodhpur if required as per qualifying requirement in the office of the SE

(TW), JdVVNL, Jodhpur .

31.4. Deviations, from technical and commercial terms & conditions, if any, shall

invariably be stated in schedule 1 & 2. Mentioning of such deviations elsewhere will

not be considered. The standard printed conditions of sales and other if any attached

with the tender will not be considered.

31.5. Discom’s reserve the right to accept minor deviation(s) in qualifying

requirement and techno - commercial conditions on its merits.

31.6. The purchaser will respond in writing to any request for clarification on tender

documents which it receives not later than 15 days prior to deadline for submission

of tender, after which no correspondence shall be entertained.

Page 49: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-49

31.7. The bidders should provide complete information at the time of submission of bid.

However, if the bidders are asked to furnish some

clarification/confirmation/documents, the bidders are required to furnish the same

within specified time failing which; the case shall be finalized /decided on the basis

of available information. The responsibility of their bid being ignored on account of

delay in furnishing of desired information/documents shall be of the bidder.

31.8 All tender documents shall essentially be signed digitally and submitted on

http://eproc.rajasthan.gov.in in time as per checklist provided with the tender

document. The checklist along with relevant page nos. shall also be submitted with

the tender.

31.9 The tender documents can be downloaded from web site

http://eproc.rajasthan.gov.in. Details of this tender notification can also be seen

in NIT exhibited on web site , www.jodhpurdiscom.in, and are to be submitted

online in electronic format only on website http://eproc.rajasthan.gov.in.

31.10 The bidders who are interested in bidding can download tender documents

from http://eproc.rajasthan.gov.in up to the stipulated date & time.

31.11 Bidders who wish to participate in this tender enquiry will have to register

on http://eproc.rajasthan.gov.in (bidders registered on eproc.rajasthan.gov.in

before 30.09.2011 needs to be registered again). To participate in online tenders,

Bidders will have to procure Digital Signature Certificate (Type – II or Type –

III) as per Information Technology Act-2000 using which they can sign their

electronic bids. Bidders can procure the same from any CCA approved certifying

agency or they may contact e-Procurement Cell, Department of IT & C,

Government of Rajasthan for further assistance. Bidders who already have a valid

Digital Certificate need not procure a new Digital Certificate. Contact No. 0141 –

4022868 (Help desk 10.00 AM to 6.00 PM on all working days) E-mail

[email protected] Address: e-Procurement Cell, RISL, Yojana Bhawan, Tilak

Marg, C-Scheme, Jaipur.

31.12 Bidder shall submit their offer online in electronic formats both for technical

and financial proposals. However, cost of specification and EMD in favour of

Senior Accounts Officer ( CPC), Jd.VVNL, Jodhpur up to stipulated date & time in

the office of the SE (TW), JdVVNL, Jodhpur and processing fees in the office

of SE (TW), JdVVNL, Jodhpur, up to stipulated date & time. The bidder shall

upload scanned copies of DDs / acknowledgement of above fee documents along

with their online bid.

31.13 Bidders are also advised to refer “Bidders Manual” available under

“Downloads”section for further details about the e-tendering process.

31.14 All the required information shall be furnished strictly in prescribed

Schedules/Formats only. Any information indicated other than the prescribed

schedules/formats shall not be entertained. The bid shall be evaluated on the basis of

information furnished in the prescribed Schedules/Formats.

32.0 GENERAL:

Page 50: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-50

32.1 Purchase of a copy of this specification by the bidder is essential for the consideration

of his Bid. Only one Bid will be accepted against each copy of the specification

purchased. This specification is not transferable. The cost of specification will not be

refunded under any circumstances.

32.2 The bidder shall treat the details of the specification and other Bid documents as

private and confidential and shall not reproduce without the written authorization of

the NIGAM.

32.3 The NIGAM does not bind itself to accept the lowest or any Bid or any part of the

Bid and shall not assign any reason(s) for the rejection of any Bid or a part thereof.

32.4 The fact of submission of Bid to the NIGAM shall be deemed to constitute an

agreement between the Bidder and NIGAM whereby such Bid shall remain open for

acceptance by the NIGAM and Bidder shall not have option to withdraw his offer,

impair or derogate the same. If the Bidder is notified during the period of validity of

Bid that his Bid is accepted by the NIGAM, he shall be bound by the terms of

agreement constituted by his Bid and such acceptance thereof by the NIGAM, until

formal contract of the same Bid has been executed between him and the NIGAM in

replacement of such agreement.

32.5 The successful Bidder shall have to execute the contract agreement for the proper

fulfillment of the contract. In case of ambiguous or contradictory terms and

conditions mentioned in the bid, interpretations as may be advantageous to NIGAM

may be taken, if satisfactory clarification is not furnished within the prescribed

period. NIGAM will not be responsible for any cost or expenses incurred by the

bidder in connection with preparation or submission of bids. Telex, Telegraphic, or

mailed, Fax, bids shall not be acceptable.

32.6 SE(TW), JdVVNL, Jodhpur shall be the authority for closure of the tender.

33.0 Nigam reserves the right to:

• Amend the scope of the proposed contract.

• Reject or accept any bid.

• Cancel the bid process and reject all applications.

• Vary the area.

• Nigam shall neither be liable for any action nor be under any obligation

to inform the bidders of the grounds for any of the above actions.

Page 51: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-51

ANNEXURE–A (ITB-Section-I)

Bid Bank Guarantee (FOR EARNEST MONEY)

(Bank Guarantee in lieu of 80% of earnest money on non-judicial stamp papers of Rajasthan State

worth 0.25 % of BG value & max. upto Rs. 25,000/- whichever is less.

Ref : Bank Guarantee No. .................... Dated: ........

Superintending Engineer (TW)

Jodhpur Vidyut Vitran Nigam Limited,

Jodhpur

1. Whereas .............................[name of the Bidder] (hereinafter called “the Bidder”) has submitted

its bid dated .............................[date of submission of bid] for the construction of.........................

[name of contract] (hereinafter called “the Bid”).

2. KNOW ALL PEOPLE by these presents that we.......................... [name of bank] of

.....................[name of country], having our registered office at................................ [Address of

bank] (hereinafter called “the Bank”), are bound unto.................................... [name of Purchaser]

(hereinafter called “the Purchaser”) in the sum of Rs.*________________ for which payment

well and truly to be made to the said Purchaser, the Bank binds itself, its successors, and assigns

by these presents. Sealed with the Common Seal of the said Bank this ___ day of ________

200___.

3. THE CONDITIONS of this obligation are:

i. If the Bidder withdraws its Bid during the period of bid validity specified by the Bidder in the

Bid Form; or

ii. If the bidder refuses to accept the correction of error in his Bid ; or

iii. If the Bidder, having been notified of the acceptance of its Bid by the Purchaser during the

period of bid validity:

(a) fails or refuses to execute the Contract agreement, if required; or

(b) fails or refuses to furnish the performance security, in accordance with the General Conditions of

Contract;

4. we undertake and authorize our branch situated at Ajmer (Rajasthan) address:

_____________________________________to pay to the Purchaser up to the above amount

upon receipt of its first written demand, without the Purchaser having to substantiate its demand,

provided that in its demand the Purchaser will note that the amount claimed by it is due to it

owing to the occurrence of one or all of the three conditions, specifying the occurred condition or

conditions.

5. The decision of the SUPERINTENDING ENGINEER (TW), JODHPUR VIDYUT VITRAN

NIGAM LIMITED, JODHPUR shall be final whether breach has been committed on the right to

demand the amount of guarantee from us which has accrued to the purchaser.

6. This guarantee shall not cease or determine, if the purchaser grants time or indulgence or vary the

terms of the contract with the contractor or without our consent or knowledge.

7. The guarantee herein contained shall not be affected by any change in the constitution of the

contractor.

8. We, _____________________ further undertake not to evoke this guarantee during its currency

except with the previous consent of the SUPERINTENDING ENGINEER (TW), JODHPUR

VIDYUT VITRAN NIGAM LIMITED, JODHPUR.

9. All disputes arising under the said guarantee between the Bank and the Nigam or between the

Contractor and the Nigam pertaining to the guarantee, shall be subject to the jurisdiction of

Courts in Jodhpur, Rajasthan alone.

Page 52: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-52

10. This guarantee will remain in force up to the bid validity period initially plus 30 day

grace period and further extendable till finalization of bid.

Yours faithfully,

Bankers (EXECUTANT)

Witness:-1.

2.

• The Bidder should insert the amount of the guarantee in words and figures denominated

in the currency of bid.

Page 53: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-53

Annexure – B (ITB-Section-I)

Bank Guarantee verification checklist

CHECK – LIST Yes No

1. Does the bank guarantee compare verbatim with standard

Performa for BG

2.(a) Has the executing Officer of BG indicated his name designation

& power of Attorney No. / Signing power Number etc. on BG.

(b) Is each page of BG duly Signed/ initialed by the executants and

last page is signed with full particulars as required in the standard

Performa of BG and under the seal of the bank.

© Does the last page of the BG carry the signatures of two witnesses

alongside the signature of the executing Bank Manager

3. (a) Is the BG on non-judicial stamp paper of appropriate value

(b) Is the date of sale of non-judicial stamp paper shown on the BG

and the stamp paper is issued not more than Six months prior to

the date of execution of BG.

4.(a) Are the factual details such as Bid specification No., LOA NO.

Contract price, etc, correct.

(b) Whether Overwriting /cutting, if any on the BG, authenticated

under signature & seal of executants

5. Is the amount and validity of BG is inline with contract

provisions

6. Whether the BG has been issued by a Nationalized bank / Non-

Nationalized Bank acceptable to Buyer /Scheduled Bank in India

(the applicability of the bank should be in line with the provisions

of bidding documents)

7. In case of Joint Venture bid, whether the B.G. is in the name of

Joint Venture as per provisions of bidding documents.

Yours faithfully,

(Signature)……...........................

(Name)........................................

Date :

(Designation)..............................

Place : (Common Seal)..........................

Page 54: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-54

GENERAL CONDITIONS OF CONTRACT & COMMERCIAL

TERMS & CONDITIONS

The Terms and Conditions of the contract shall prevail and shall be binding on the Agency

and any change or variation expressed or impressed howsoever made shall be in operative

unless expressly sanction by the Nigam. The Agency shall be deemed to have fully informed

himself and to have specific knowledge of the provisions under terms and Conditions of this

specification mentioned hereunder:

1.0 DEFINITION OF TERMS:

1.1 In constructing these general conditions and the annexed specification, the

following words shall have the meaning herein assigned to them unless there is

anything in the subject or context inconsistent with such construction.

1.2 The “Purchaser” shall mean t h e JODHPUR VIDYUT VITRAN

NIGAM LTD represented by Managing Director and shall include their legal

personnel, representative, successors and assignees. The “Nigam” or “Customer” or

“Owner” shall mean the “Purchaser”.

1.3 The "Bidder" shall mean and include one or more persons or any firm

or any Company or Body incorporate who has submitted the Bid in response to

"Invitation To Bid" / ”Tender Notice”.

1.4 The "Contractor" or “Supplier” shall mean the Bidder / Tenderer whose Bid /

Tender has been accepted by the NIGAM and shall include the Bidder's heirs, legal

representative, successors and assignees approved by the NIGAM.

1.5 The "Sub-contractor" shall mean the firm or the persons named in the contract

for any part of the work or any person to whom any part of the contract has been

sublet with the consent in writing of the NIGAM and shall include his heirs,

legal representative, successors and assignees approved by the NIGAM.

1.6 The "Chairman" shall mean the Chairman, DISCOM`s and “MD” shall

mean Managing Director, JODHPUR VIDYUT VITRAN NIGAM LTD, Jodhpur.

1.7 The "Engineer" shall mean the Chief Engineer or other Engineer or officer for

the time being or from time to time duly authorized and appointed in writing by the

NIGAM to act as Engineer or Inspector for the purpose of the contract. In case where

no such Engineer has been so appointed, the word "Engineer" shall mean the NIGAM

Part : III Section-II GENERAL CONDITIONS OF CONTRACT (GCC)

Page 55: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-55

or his duly authorized representative.

1.8 "Plant ", "Equipment", "Materials, "Stores", "Works", shall mean and include

the plant and materials to be provided and work or works to be done by the Contractor

under the Contract.

1.9 The contract shall mean and include the following:

1. Invitation of Bid.

2. Instructions to Bidders. 3. Bid Form including schedule of prices. 4. Cost of Tender Specification and Earnest money receipt/security guarantee.

5. Letter of Intent and its acknowledgement.

6. Composite Bank Guarantee for security and performance /obligations.

7. Formal work order. 8. Guaranteed test performance and Warranty. 9. General Conditions of Contract.

10. Erection Conditions of Contract.

11. Special instructions.

12. General Technical Conditions and specification.

13. Site conditions. 14. Specification, specific conditions, schedules and drawings. 15. Addenda which may hereafter be issued by the NIGAM, to the

Contractor in the form of letter and covering letters and schedule of

prices as agreed between the Contractor and the NIGAM.

16. The Agreement to be entered into under Clause 5 of this section.

1.10 The "Specification' shall mean the specification, specific conditions annexed to

the General Conditions of Contract and the schedules thereto, if any.

1.11 The month shall mean, English calendar month i.e. period of 30 days and week shall

mean a period of 7 days.

1.12 The "Site" shall mean the place or places named in the Contract and include, where

applicable, the lands and buildings upon or in which the works are to be executed.

1.13 The "Place of delivery" shall mean the place of delivery at which the Contractor/

Supplier is responsible to deliver the materials at the contract price.

1.14 The "Test of completion" shall mean such tests as are prescribed in the contract to be

made by the Contractor before the Plant is taken over by the NIGAM as per the General

Conditions.

1.15 "Commissioning" shall mean the satisfactory operation of the plant or equipment

specified herein, after all necessary initials checks, adjustments, trials, cleaning and re-

assembly required at site, if any, have been completed and the plant has been in continuous

and unrestricted commercial use specified for at least thirty (30) days or as otherwise.

1.16 "Letter of Intent" shall mean the NIGAM's letter conveying his acceptance of the

Page 56: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-56

Bid subject to such reservations as may have been stated therein.

1.17 The "Contract price" shall mean the sum named in or calculated in accordance with

the provisions of the Contract/purchase or any amendments thereto.

1.18 "Formal work order' shall mean the Owner's letter which may be issued in the way of

letter of intent containing detailed terms and conditions of the work/supply and such

other particulars which the owner may like to convey the Contractor/supplier pending

execution of a formal written agreement in accordance with clause 5.0 of this section.

1.19 The Consignee shall mean and include the Assistant Controller of Stores /

Store Superintendents and or any other officer / official of the JODHPUR VIDYUT

VITRAN NIGAM LTD all over jurisdiction of Jd.VVNL, performing the duties of the

consignee.

1.20 “Commercial Use” shall mean that use of the work which contract contemplates or

which it is to be commercially capable.

1.21 "Writing” Shall include any manuscript, type written or printed statement under or

over signature or seal as the case may be.

1.22 The Word "Codes" shall mean the Indian Boiler Regulation and rules made there

under with such special modifications which may be agreed upon by the Chief

Inspector of Boilers, Rajasthan from time to time which shall also include the Indian

Electricity Rules, IS Code of practice and Factory Rules and Regulations applicable in

the State of Rajasthan on the date of issue of the letter of intent or such modifications

thereof as may be specially stipulated by competent State authorities i.e. Electrical

Inspector and Chief Inspector of Factories, Rajasthan.

1.23 Words importing "PERSON" shall include firms, companies, corporation and other

bodies whether incorporated or not.

1.24 Words importing the singular only shall also include the plural and vice versa where

the context requires.

1.25 Terms and expressions not herein defined shall have the same meaning as one

assigned to them in the Indian Sale of Goods Act (No.III of 1930), fulfilling that in the

Indian Contract Act (Act IX of 1872) and falling that in the General clauses Act

1897 including amendments thereto.

1.26 When the words “approved”, “subject to approval”, “satisfactory”, “Equal to”,

“proper”, “Requested”, “as directed”, “where directed”, “when directed”, “determined

by”, “accepted”, “permitted” or words and phrases of like importance are used, the

approval, judgment, direction etc. is understood to be a function of the owner/engineer.

1.27 ' Works', shall mean and include the supplying of equipment, labour and services, as

per the technical specifications and complete erection, testing and commissioning of the

Page 57: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-57

equipment including all transportation, handling, unloading and storage at the site as

defined in the contract, intended to be executed on a supply and erection basis.

1.28 The term 'Equipment Portion' of the contract price shall mean the all adjusted F.O.R.

destination value of the equipment.

1.29 The term 'Erection Portion' of the Contract Price shall mean the value of field

activities of the Contract including erection, testing and commissioning to be performed

at site by the Contractor

1.30 ‘Inspector' shall mean the Owner or any person nominated by the Owner from time to

time, to inspect the equipment, stores or works under the Contract, and/or the duly

authorized representative of the Owner.

1.31 'Date of Contract' shall mean the date on which both the parties have signed the

Contract Agreement.

1.32 ' Start-Up' shall mean the time period required to bring the equipment covered under the

Contract from an inactive condition, when construction is essentially complete, to the state

ready for trial operation. The start-up period shall include preliminary inspection and

checkout of equipment and supporting sub-systems; initial operation of the

complete equipment covered under the Contract to obtain necessary pre trial operation

data, perform calibration and corrective action; shut down, inspection and adjustment prior

to the trial operation period.

1.33 'Initial Operation' shall mean the first integral operation of the complete equipment

covered under the Contract with sub systems and supporting equipment in service

or available for service.

1.34 'Trial Operation' "Reliability Test', "Trial run', “Completion Test”, shall mean the

extended period of time after the start-up period. During this trial operation period

the equipment shall be operated over the full load range. The length of trial operation

shall be as determined by the engineer, unless otherwise specified elsewhere in the

contract.

1.35 Performance and Guarantee Test', shall mean all operational checks and tests

required to determine and demonstrate capacity, efficiency, and operating

characteristic as specified in the contract documents.

1.36 The term 'Final acceptance' shall mean the owner’s written acceptance of the works

performed under the contract, after successful completion of performance and

guarantee Tests.

1.37 'Guarantee Period/ Maintenance period' shall mean the period during which the

contractor shall remain liable for repair or replacement of any defective part of the works

performed under the contract.

1.38 ‘Drawings'/ 'Plans’ shall mean all:

Drawing furnished by the owner/ consultant as a basis for proposals. Supplementary

drawings furnished by the owner/consultant to clarify and to define in greater detail

intent of the contract.

Page 58: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-58

Drawing submitted by the contractor with his proposal provided such drawings are

acceptable to the owner/consultant. Drawings furnished by the Owner/Consultant to

the Contractor during the progress of the work ; and Engineering data and drawings

submitted by the contractor during the progress of the work provided such drawings

are acceptable to the engineer.

2.0 CONTRACT: The Contractor and the Nigam shall as soon as possible, unless

otherwise agreed upon enter into a signed agreement for the proper fulfillment of the

contract. The expenses of completing and stamping the agreement shall be paid by the

contractor and the Nigam shall be furnished free of charge with an executed stamped

counterpart of the agreement with three copies after the tender / bid has been accepted by

the purchaser / owner. All orders/instructions to the contractor shall except as herein

otherwise provided, be given by the engineer on behalf of the purchaser/owner.

2.1 VENDOR REGISTRATION SCHEME:-

A. Registration (Enlistment) Fee and required Security Deposits:-

S.NO

CLASS OF CONTRACTOR

AMOUNT OF REGISTRATION FEES IN CASH/THROUGH BANKER’S CHEQUE/DEMAND DRAFT(NON-REFUNDABLE)

AMOUNT OF SECURITY DEPOSIT (NON INTREST BEARING)

BANK GUARANTEE REQURIED

PAST EXPERIENCE REQURIED

1 2 3 4 5 6

1 E-I RS. 10,000/- RS. 5.00 LACS

RS. 10.00 LACS

Satisfactorily completed electrical / erection work on labour contract valuing atleast Rs. 100 Lacs & minimum period of 3 months is satisfactorily over from the last completed work of similar nature.

2 E-II RS. 5,000/- RS. 1.25 LACS

RS. 2.50 LACS

Satisfactorily completed electrical / erection work on labour contract valuing atleast Rs. 50 Lacs & minimum period of 3 months is satisfactorily over from the last completed work of similar nature.

3 E-III RS. 2,500/- RS. 0.50 LACS

RS. 1.00 LACS

Satisfactorily completed electrical / erection work on labour contract valuing atleast Rs. 25 Lacs &

Page 59: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-59

S.NO

CLASS OF CONTRACTOR

AMOUNT OF REGISTRATION FEES IN CASH/THROUGH BANKER’S CHEQUE/DEMAND DRAFT(NON-REFUNDABLE)

AMOUNT OF SECURITY DEPOSIT (NON INTREST BEARING)

BANK GUARANTEE REQURIED

PAST EXPERIENCE REQURIED

1 2 3 4 5 6

minimum period of 3 months is satisfactorily over from the last completed work of similar nature.

4 E-IV RS. 1,000/- RS. 0.20 LACS

RS. 0.40 LACS

Any individual person, firm or entity having ITI/Diploma/Degree in Electrical or Mechanical branch/retired technical personnel or state power utilities/any other person having Electrical license Govt. of Raj.

B. Class of Registration, Competent Authority & Extent of Participation:-

CLASS COMPETENT

AUTHORITY TO REGISTER

LIMIT OF SINGLE CONTRACT ( In Rs.)

LIMIT OF ALL IN HAND CONTRACT OF A GIVEN POINT OF TIME (In Rs.)

E-I CE(O&M) 100 Lacs 500 Lacs

E-II CE(O&M) 25 Lacs 125 Lacs

E-III Circle SE’s 10 Lacs 50 Lacs

E-IV Circle SE’s 5 Lacs 20 Lacs

Note :- Class E-I to E-III registration procedure shall be complied as per provisions of the

office of the SE (MM&C), JdVVNL, Jodhpur

2.2 PERFORMANCE PERIOD:

2.2.1 The performance period of the contract shall be 12 months from the date of

Commission of the project in totality. The guarantee period of material used & the

Page 60: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-60

performance of workmanship of work done shall be safeguard through BG’s detailed

in clause 3.0 hereunder.

2.2.2 The contract for awarded work may be rescinded at any time if the

performance regarding achievement of the objective and scope of works as illustrated

under Part-III of this specification is not found satisfactory [no compensation will be

paid] or the agency breach any of the terms and conditions, or the agency will be advised

for improvement.

2.3 SCOPE OF CONTRACT:

2.3.1 The scope of the contract including the design manufacture, supply and

erection inter-alia including testing & commissioning of the work / equipment in

accordance with the specification and documents at the proposed site of the work.

2.3.2 The General terms and conditions mentioned herein shall form a part of the

specification and documents.

2.3.3 All the works covered by the contract shall be in accordance with the Indian

Electricity Act 2003 with the latest amendments and the Indian Electricity rules 1956

made there under.

3.0 SECURITY AND PERFORMANCE BANK GUARANTEE /DEPOSIT:

3.1 SECURITY BANK GUARANTEE / DEPOSIT:

3.1.1 In order to secure / assure due fulfillment of the contract, the successful

Bidder(s) upon receipt of preliminary acceptance letter / detailed work order as the case

may be shall furnish within a period of 15 days a security deposit equivalent to 2%

(two percent) of the contract value (material cost and erection cost including associated

civil works) in cash or by crossed Bank Draft or by way of Bank Guarantee from any

scheduled Bank in the prescribed Performa (Annexure-B of GCC) acceptable to

the owner on non-judicial stamp papers of Rajasthan State worth 0.25 % of BG value &

max. upto Rs. 25,000/- whichever is less duly authenticated by a Ist Class

Magistrate or notary public or directly confirmed by the issuing Banker. Such Bank

Guarantee is to remain valid for a period of Work Completion period including

commencement period + 3 Months initially in the first instance and may have to be

extended if desired. The B.G. is to be furnished in whole Rupees with validity up to

Page 61: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-61

last day of required calendar month. Bank commission charges or any other charges,

if any, shall be to the Contractor's account. “In case of invocation of Bank guarantee

issuing Bank must authorize for entertaining the case at the sister Branch located in

Rajasthan”. The Bank guarantee must be from any Nationalized / Scheduled Bank.

3.1.2 Unless otherwise specifically required to be retained/forfeited by the

NIGAM, the Security deposit shall be refundable on request of the contractor after

three months on completion of the entire work to the satisfaction of the NIGAM.

3.1.3 If the contractor fails or neglect to observe or perform any of his obligations

under the contract, it will be lawful for the NIGAM to forfeit either in whole or in part

at his absolute discretion, the Security deposit furnished by the contractor.

3.1.4 No interest shall be payable on such deposits.

3.1.5 If the contractor fails to provide the Security within the period specified, such

failure shall constitute a breach of the Contract and the NIGAM shall be entitled to

make other arrangements at the risk and expenses of the contractor and the Earnest

money deposited by the Contractor shall stand forfeited by the NIGAM.

This bank guarantee shall be released after 3 months of successful installation and

handing over of entire system to nodal officers assigned by Jd.VVNL.

3.2 SECURITY CUM PERFORMANCE BANK GUARANTEE :

A. Security cum Performance Bank Guarantee of Work Order:

A performance deposit / Guarantee equivalent to 10 % of contract value shall be

deposited by the successful bidder either in the form of Bank Guarantee from scheduled

Bank on non-judicial stamp papers of Rajasthan State worth 0.25 % of BG value & max.

upto Rs. 25,000/- whichever is less in the prescribed format addressed to the

Superintending Engineer [TW], Jd.VVNL, Jodhpur for satisfactory work performance

within 15 days of receipt of the Detailed Purchase Order. The Bank Guarantee is to be

remained valid for a period of commencement & completion period + 12 Months

(Performance Period) + 6 months (grace period for lodging any claims as

admissible) from the date of commencement of contract in the first instant and may have

to be extended if desired. It will be the sole duty of vendor to get the BG extended

Page 62: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-62

well in time to maintain its validity as desired. Nigam may invoke the BG without

giving any information if validity of BG expires.

(b) The Security cum Performance guarantee shall cover additionally the

following guarantee to the owner:

(i) The successful bidder guarantees the successful and satisfactory operation of the

equipment supplied and erected under the contract, as per the specifications and

documents.

(ii) The successful bidder further guarantees that the equipment provided and

installed by him shall be free from all defects in design, material and workmanship and

shall upon written notice from the owner fully remedy, free of expenses to the owner,

such defects as developed under the normal use of the said equipment within the period

of guarantee specified in the relevant clause of the General Conditions of Contract.

(c) The Security cum Performance guarantee is intended to secure the performance

of the entire contract. However, it is not to be constructed as limiting the damages under

clause entitled " Security cum Performance " in section General Technical Conditions

and damages stipulated in other clauses in the bid documents.

(d) The above BGs are to be furnished in whole Rupees with validity up-to last day

of required calendar month. Bank commission charges or any other charges, if any, shall

be to the Contractor's account.

(e) The Bank guarantee must be from any Nationalized / Scheduled Bank having a

branch at Jodhpur. The vendor may furnish Bank Guarantee on stamp paper of native

state provided the vendor shall furnish a certificate of Banker that the stamp duty has

been paid as per prevailing rules of that state.

(f) Unless otherwise specifically required to be retained/forfeited by the NIGAM,

the Security deposit shall be refundable on request of the contractor after three months on

completion of the entire work to the satisfaction of the NIGAM.

(g) If the contractor fails or neglect to observe or perform any of his obligation under

the contract, it will be lawful for the NIGAM to forfeit either in whole or in part at his

absolute discretion, the Security deposit furnished by the contractor.

(h) If the contractor fails to provide the Security within the period specified, such

failure shall constitute a breach of the Contract and the NIGAM shall be entitled to make

Page 63: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-63

other arrangements at the risk and expenses of the contractor and the Earnest money

deposited by the Contractor shall stand forfeited by the NIGAM.

B. GUARANTEE OF MAJOR EQUIPMENTS:

(a) The contractor shall guarantee amongst other things, the following:

(i) Quality and strength of the material(s) used together with the workmanship and finish

corresponding to the most modern practice(s).

(ii) Safe electrical and mechanical stresses on all parts of the equipment under all

specified conditions of operation.

(iii) Performance figures in respect of the guaranteed technical particulars as finally

agreed upon.

(iv) Satisfactory performance of materials/Equipment during the Guarantee period.

(b) Performance guarantee of major items such as Power Transformers / Distribution

Transformers / 11 KV RMU`s / 33 KV & 11 KV VCB / Kiosk for 33 KV & 11 KV

feeders / sub-stations shall be given / furnished by Manufacturers & shall be arranged by

the contractor directly in favour of the Nigam for the period equivalent to the period for

which the guarantees are given to MM wing of Discom (s) against the P.O. placed

directly by Nigam. For this purpose Tripartite agreement shall be executed between

contractor, firm & Nigam (If supply of these items is in the scope of Contractor).

Should the factory test(s) carried out at site or test(s) arranged by the owner in

exercising his option under the clause No.33.0 on the material / Equipment / Plant or part

thereof or its / their operation under service conditions for a period for which the

guarantees are given to MM wing of Discom(s) against the P.O. placed directly by

Nigam for all material /equipment. From the date of taking over work(s) that the material

/plant/ equipment does not meet the guarantee(s) as aforesaid, it shall be optional for the

owner to reject material(s), Plant(s), Equipment(s), or a part thereof and direct the

contractor to rectify/ replace the material/Plant/Equipment so rejected within a

reasonable period so as to make it meet the guarantees and requirements to the

satisfaction of the owner. All expenses whatsoever in this connection shall be borne by

the supplier/contractor.

Page 64: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-64

( c ) A manufacturer's Warrantee on the Rajasthan State Non judicial stamp paper of Rs.

100.00 in the Performa prescribed Annexure-C (GCC). Such warrantee shall be attested

either by a first class Magistrate or by Notary Public.

B. (d) All cable joints are guaranteed for min. 2 years period and should be

repaired/replaced within 7 days of failure of cable joints free of cost. Penalty on

non-performance shall be recovered at Rs. 5000/- per day after seven days upto Rs.

25000/- from the Contractor.

4.0 CONTRACTOR TO INFORM HIMSELF FULLY

The Contract shall be considered to have come into force from the date of the issue of

Letter of Intent / Letter of Award. The contractor shall be deemed to have carefully

examined the General Conditions, specifications, schedules and drawings also to have

satisfied himself as the nature and character of the work to be executed and where

necessary, of the site conditions and other relevant matters and details. Any

information thus had or otherwise obtained from the owner or the Engineer shall not

be in any way relieve the contractor from his responsibility for the supplying of the

plant and equipment and executing the work in terms of the contract including all

details and incidental works and supply all accessories or apparatus which may not

have been specifically mentioned in the contract but necessary for ensuring complete

erection & commissioning and safe and efficient working of the plant and equipment

if he has any doubt as to the meaning of any portion of the general and any special

conditions of contract and specifications, he shall before offering his bid proposal, set-

forth the particulars thereof and submit them to the Engineer in writing in order that

such doubt, misunderstanding, misconceptions, whatsoever could be allied.

5.0 CONTRACT DOCUMENTS AND AGREEMENTS

5.1 The order placed under this specification shall be governed by the terms and conditions

as incorporated in this Specification and as given in the detailed work order and its

annexure(s). The terms and conditions as specified in this section if differ from the

terms indicated in the detailed work order and its annexure(s) the latter shall prevail.

The contract shall for all purposes be construed according to the Laws of India and

subject to jurisdiction of Rajasthan Courts only. For the due fulfillment of the

contract, the contractor shall execute an agreement in the prescribed form Annexure-

“B of GCC” on Rajasthan State Non- judicial stamp paper worth 0.25% of the

contract value as per latest notification issued by GOR. The expenses of completing

and stamping the contract agreement shall be borne by the Contractor. Such

agreement shall be executed and signed by the authorized representative of the

Page 65: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-65

contractor on each page thereof. The original copy is only to be executed on the stamp

paper. The remaining two copies may be executed on simple paper. Such complete

agreement form along-with the contract documents together with a 'Power of

Attorney" in favour of the Executants shall be required to be returned to the owner

within a period of 15 days from the receipt date of work order duly signed on each

page. One copy of the executed agreement duly signed by the purchaser/owner shall

be sent to the contractor for his reference. The contract documents shall mean and

include the following:

1. Contract agreement along with letter of Intent.

2. Work order and its Annexure.

3. Instructions to bidders (SECTION-I)

4. General Conditions of Contract & other Terms & conditions (Section-II)

5. Erection Conditions of Contract -SECTION-III (PART-IA&IB)

6. Pre-Qualification Requirement- SECTION-III (PART-II)

7. Technical Specification- SECTION-III (PART-III)

8. Bid proposal form and its schedules including price schedule and completion

schedules.

9. Power of Attorney in favour of the signatory.

5.2 ACCEPTANCE OF CONTRACT:

The successful bidder will be forwarded three sets of letter of award, two of which

will be signed (each page) by him/his authorized representative in token of his

accepting the contract and returned to the authority placing the order within 15 days

of its issue, failing which, his EMD is liable to be forfeited.

5.3 FAILURE TO EXECUTE THE CONTRACT:

Contractor failing to execute the order placed on them to the satisfaction of the

NIGAM under terms and conditions set forth therein, will be liable to make good the

loss sustained by the NIGAM. This is without prejudice to the imposition of penalty

and forfeiture of any available financial holds.Other terms and conditions regarding

this shall applicable as per provisions and rules mentioned in RTPP Act 2012 and

Rules 2013.

5.4 EFFECTING RECOVERIES:

Any loss, arising due to non-fulfilment of this contract or any other contract, will be

recovered from the Security Deposit held and or any other amount due to the agency

from this Contract as well as from other contracts.

Page 66: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-66

6.0 CHANGE OF QUANTITY:

a. The SE (O&M) will approve the bill of quantity in case the variation between the

ordered value and finally surveyed amount for the ordered work is 10% after recording

reasons thereof.

b. In case where the variation between the ordered value and finally surveyed amount

or the ordered work is beyond 10% but up to 40%, the committee comprising the following

members will approve the same after recording reasons thereof. –

(i) The CE (O&M) / ZCE,

(ii)The CE (MM / TW),

(iii) The SE (TW),

(iv)The SE (O&M),

(v)The Sr.AO (TW),JdVVNL.

c. If the variation between ordered value and finally surveyed amount for the ordered

work exceeds 40% such cases should be re-studied & be referred to CLPC for approval.

7.0 GRAFTS AND COMMISSIONS ETC:

Any graft, commission, gift or advantage given, promised or offered by or on behalf

of the contractor or his partner, agent, officers, director, employee or servant or any

one on his or their behalf in relation to the obtaining or to the execution of this or any

other contract with the owner, shall be, in addition to any criminal liability which it

may incur, subject of any loss or damage to the owner resulting from any cancellation.

The owner shall then be entitled to deduct the amount so payable from any moneys

otherwise due to the contractor under the contract.

8.0 PROCUREMENT FROM MANUFACTURERS / VENDORS:

The Contractor shall be permitted to procure materials from the manufactures /

vendors who have following qualified requirements:

(i) The vendor should be a established / reputed manufacture / supplier who

should have supplied the material to erstwhile RSEB or any present

distribution company, RVVPNL or any other power utility and the contractor /

bidder are required to indicate the names & address of the manufactures of

various items from which he proposes to buy the same.

(ii) The manufacturing units shall have all facilities for conducting acceptance &

routine tests of equipment / materials.

(iii) The vendor must have supplied materials as per specifications laid down in the

bid- documents of erstwhile RSEB / NIGAMS and have arranged their type

testing not before last Five Years,

Page 67: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-67

(iv) The vendors approvals shall be obtained for supply of the equipment /

materials from the Engineer well in advance.

9.0 RULES & REGULATIONS:

9.1 The job shall be carried out as per the rules, regulations and other details as prevailed

in Nigam. These rules and regulations may be modified by Nigam from time to time

and would be intimated to the Agency.

9.2 The Agency will also follow the labour regulations and the directions of Government

and other authorities enforcing the regulations and comply with any other relevant

legislation in force from time to time.

10.0 COMPLIANCE OF LABOUR LAGISLATION:

The bidder shall discharge its liability of employer/ contractor in respect of personnel

to be engaged for service, as said out in EPF and MP Act, 1952 ESI Act, 1948 (in ESI

implemented area), workmen’s compensation act, 1923 (in non ESI implemented

area) contract labour (R&A) Act, 1970, Payment of Wages Act, 1936, Minimum

Wags Act, 1948 etc. The bidder is required to get separate code under the provision of

EPF and ESI Acts, if not already taken and deposit the employer’s contribution along

with employee subscription, as per rule and submit copy of challans at the time of

claiming payment, as per clause 28, failing which an amount equivalent to employer’s

contribution and employees subscription shall be deducted from his each bill and

deposited with the concerned authorities. The bidder shall be solely responsible for

any consequences arising out of breach of any legislation.

11.0 ELECTRICITY RULES AND REGISTRATION:

11.1 All works shall be carried out in accordance with the latest provisions of the Indian

Electricity Act/Electricity Supply act and Indian Electricity Rules and the rules made

there under applicable in the State of Rajasthan on the date of letter of intent with

such special modification thereof as may be specially stipulated by competent State

Authorities i.e. The Chief Electrical Inspector of Rajasthan.

Page 68: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-68

11.2 Bidder (in case of consortium, the lead partner) should be registered as class-A

electrical contractor in any state and/or in union territory of India. Adequate

documentary evidence of the same shall have to be furnished.

However, for successful Bidder (in case of consortium, the lead partner), it shall be

mandatory to get registered as class-A electrical contractor in State of Rajasthan

before commencing the work. The registration should be valid from the date of start

of work and shall remain valid up to 30 days from the date of handing over of the

work to Engineer In charge. Agency shall also furnish the adequate documentary

evidence of the same before commencing the work.

12.0 SAFETY OF SYSTEM:

The Agency shall be fully responsible for upkeep and safety of existing electric

system. Agency shall make well aware to NIGAM any loss suffered due to default of

the agency in this respect.

13.0 INSURANCE:

(i) The agency at his cost shall arrange, secure and maintain all insurance as may be

pertinent to the works and obligatory in terms of law to protect its interest and interest

of the NIGAM against all perils detailed herein. The form and the limit of such

insurance as defined herein together with the under-writer in each case shall be

acceptable to the NIGAM. However, irrespective of such acceptance, the

responsibility to maintain adequate insurance coverage at all time during the period of

contract shall be of agency alone. The agency’s failure in this regard shall not relieve

him of any of his contractual responsibilities and obligations. The insurance covers to

be taken by the agency shall be in a joint name of the NIGAM and the agency. The

agency shall, however, be authorized to deal directly with Insurance Company or

companies and shall be responsible in regard to maintain of all insurance covers.

Further the insurance should be in freely convertible currency.

(ii) The agency shall obtain accident liability insurance for its employees for payment of

compensation on account of injury, fatal or otherwise due to accident during course of

operation carried out by him for the purpose of complying with his contractual

obligations thereof. It shall indemnify NIGAM against any claim from such

Page 69: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-69

employees or damage to property what- so- ever while these arise out of or in

consequences of the execution of works, operation and all activities to be performed

till the successful completion of contract shall be to the account of the agency. The

agency shall be responsible for preference of all claims and make good the damages

or loss by way of repairs and/or replacement of the equipment, damaged or lost. The

transfer to title shall not in any way relieve the agency of the above responsibilities

during the period of contract. The agency shall provide the NIGAM with copy of all

insurance policies and documents taken out by him in pursuance of the contract. Such

copies of documents shall be submitted to the NIGAM immediately after such

insurance coverage. The agency shall also inform the NIGAM in writing at least sixty

(60) days in advance regarding the expiry/cancellation and/or change in any of such

documents and ensure revalidation, renewal etc., as may be necessary well in time.

(iii) All costs on account of insurance liabilities covered under the contract will be on

agency’s account and will be included in contract price. However, the NIGAM may

from time to time during the pending of the contract, ask the agency in writing to limit

the insurance coverage, risks and in such cases, the parties to the contract will agree

for a mutual settlement, for reduction in contract price to the extent of reduced

premium amount. The agency, while arranging the insurance, shall ensure to obtain

all discounts on premium, which may be available for higher volume or for reasons of

financing arrangement of the project.

(iv) The Clause entitled ‘Insurance’ under this section covers the additional insurance

requirements for the portion of the works to be performed at the site.

(v) The agency shall take necessary insurance against loss, damage, fire, accidents and

damages occasioned by the agency in the course of operation carried out by him for

the purpose of complying with his contractual obligations thereof.

(vi) The insurance as per clause 13.1 & 13.2 shall be in the joint names of the NIGAM

and the agency so that the NIGAM and the agency are covered for the entire period of

contract from the commencement of the contract and shall remain valid up to 30 days

from the date of handing over all the works completed in all respects to the

Superintending Engineer (TW).

Page 70: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-70

(vii) It will be the responsibility of the agency to lodge, pursue and settle all claims (for all

the equipment and materials including items provided by NIGAM) with the insurance

company in case of any damage, loss, or fire and the JDVVNL shall be kept informed

about it. The losses, if any, will have to be borne by the agency if the claims are not

lodged and pursued properly in time or if the insurance company does not settle the

same.

(viii) The agency shall replace the lost/-damaged materials promptly irrespective of

settlement of the claims by the underwriters and ensure the work progresses as per the

agreed schedule(s).

(ix) The agency shall also ensure the following: -

The insurance premium should be one time paid basis.

Deductible franchise should be minimum as per insurance rules. In case of any

loss to the extent of deductible franchise, the same shall be borne by the agency.

The insurance should be valid from the date of start of work and shall remain

valid up to 30 days from the date of handing over of the work to the Engineer in

charge.

Insurance policy shall be in joint name of NIGAM and agency.

The agency shall furnish computerized and stamped insurance policy. Insurance

cover shall not be acceptable.

A copy of insurance policy shall invariably be furnished to the Superintending

Engineer (TW), Jd.VVNL Jodhpur.

(x) THIRD PARTY INSURANCE:

The agency shall if and so far as the contract provides indemnify the Nigam against

all losses and claims in respect of injury or damage to property what- so- ever while

these arise out of or in consequences of the execution of works and against all claims

proceedings, damages, costs, charges, expenses what- so- ever in respect of or in

relation thereto. Accordingly the agency shall before commencement of execution of

the works insure against his liability for material or physical damage, loss or injury

which may occur to property including that of the Nigam, or to any person including

any employee of the Nigam, by or arising.

(xi) REMEDY ON AGENCIES FAILURE TO INSURANCE:

Page 71: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-71

If the Agency shall fail to effect and keep in force insurance referred to in clause 13

(i) to 13 (ii) hereof or any other insurance which he may be required to effect under

the terms of contract then the Nigam may effect and keep in force any such insurance

and pay such premium(s) as may be necessary for that purpose and from time to time

deduct the amount so paid by the Nigam as aforesaid from any money due or which

may become due to the Agency or recover the same as debt from the Agency.

14. 0 LIABILITY FOR ACCIDENTS AND DAMAGES:

(i) The Agency shall be liable for and shall indemnify the NIGAM in respect of all injury

to person or damage to property resulting from the negligence of the Agency or his

workman or from defective work but not from any other cause.

(ii) Provided that the Agency shall not be liable for any loss or profit or loss of Contract

or any other claim made against the NIGAM not already provided for in the contract,

not for any injury or damage caused by or arising from the acts of the NIGAM or of

any other person or due to circumstances over which the agency has no control, not

shall his total liability for loss, damage or injury under this clause exceed the total

value of the Contract.

(iii) The Agency will indemnify and save harmless the NIGAM against all actions, suits,

claims, demands, costs, or expenses arising in connection with injuries (other than

such as may be attributable to the NIGAM or his employees) suffered prior to the date

when the work shall have been taken over hereof by persons employed by the agency

on the work, whether at common law or under the workman's compensation Act-1923

or any other statute in force at the date of contract relating to the question of the

liability of employees for injuries suffered by employees and will if called upon to do

so take out the necessary policy or policies of insurances to over such indemnity.

(v) The agency shall insure against such liabilities with an insurer approved by the

Engineer and shall continue such insurance, during the whole of the time that any

person(s) are employed by him on the works and shall when required produce to

the Superintending Engineer (TW), Jd.VVNLJodhpur. Such policy of insurance

and the receipt for payment of the current premium.

15.0 MAINTENANCE OF FACILITIES AND PERSONNEL:

15.1 FACILITY:

Page 72: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-72

15.1.0 The Agency shall maintain all requisite facilities, T&P etc. of its own as required to

carry out the work as per the specification.

15.1.1 The Agency shall provide and maintain a controlling office in the town for which

work has been awarded for early execution of work.

15.1.2 The agency shall also maintain communication equipments like telephone with fax,

mobile phone, Internet etc. for interaction with NIGAM and others.

15.2 PERSONNEL:

15.2.0 The Agency shall maintain supervisory and other personnel for efficient management

of the work under contract.

Officer-In-

Charge

To have adequate experience and vision to take charge of the entire

project and resolve problems so as to evolve an ideal system.

Skilled & un-

skilled workers

Sufficient manpower to achieve the targeted work in the time frame

allowed with proper safety.

Office Staff Sufficient manpower to achieve minimum guaranteed performance.

15.2.1 Person in-charge or an alternate shall be available for communication during all

business hours.

15.2.2 Agency shall not change the office in charge / nodal officer, frequently.

15.2.3 The Agency shall furnish documents regarding the experience of the key personnel

proposed to be employed by him. NIGAM has right to verify the above at any time.

15.3 NODAL OFFICER: To interact between the field offices and agency, the concerned Superintending

Engineer (O&M), Jd.VVNL will be the Nodal Officer of the project work.

16 ENGINEER INCHARGE & SUPERVISORY OFFICERS:

16.1 The Executive Engineer / Assistant Engineer as appointed by concerned Circle

Superintending Engineer will be the Engineer In charge / Supervisory officer for

execution of the contract and the officers under their Division / Sub-division shall

be authorised to inspect the work carried out by the agency.

16.2 ENGINEER'S SUPERVISION AND DECISION:

Page 73: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-73

16.2.1 All the work shall be carried out under the direction and to the reasonable

satisfaction of the Engineer. The contractor shall be responsible for the

correctness of the positions, levels and dimensions of the works according to the

drawings not withstanding that he may have assisted by the Engineer in setting

out the same.

16.2.2 In respect of all matters which are left to the decision of the Engineer

including the granting or with-holding of the certificate, the engineer shall, if

required to do so by the contractor, give in writing a decision thereon.

16.2.3 If in the opinion of the contractor, a decision made by the engineer

is not in accordance with the meaning and intent of the contract, the contractor

may file with the engineer within fifteen (15) days after receipt of the decision, a

written objection to the decision. Failure to file an objection within the aforesaid

allotted time will be considered as acceptance of the engineer's decision and the

decision shall be final and binding.

16.2.4 The engineer's decision and the filling of the written objection thereto shall

be t h e right to request arbitration. It is the intent of the agreement that there

shall be no delay in the execution of the works and the decision of the engineer as

passed shall be promptly adhered to.

17.0 GUARANTEE OF MATERIAL USED: In case of any defects is observed in the material used by the contractor during the

guarantee period, then he has to replace the defective material free of cost within a

period of 72 hrs., in case if contractor fails to replace the defective material then the

work shall be got done by the NIGAM & the available financial holds shall be

withhold / fore-fitted without any further notice / correspondences.

18.0 AGENCIES RIGHTS:

The agency will be given rights to work in the area during the agreement period for

carrying out the project work.

19.0 FALL BACK ARRANGMENT:

Provision shall be made in the agreement that in the event of failure of the Agency to

fulfil its obligations, duties and responsibilities as per the agreement terms, NIGAM

shall inter-alia have the right, at any time to resort to fall back arrangement. Under

Page 74: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-74

this plan, NIGAM shall take charge of all facilities and systems whether in operation

or under execution after giving suitable notice as provided in the agreement and can

recover from the security deposit the losses suffered due to such failure. If the security

deposit is insufficient, the Agency shall pay the difference to NIGAM failing which

NIGAM shall have right to recover the sum through legal or other means.

The NIGAM shall have the right in such circumstances to manage the system itself

after taking charge of the facilities as above or through any other agency as it may

deem fit and no claim of Agency for compensation in this respect shall be entered.

20.0 WCT is applicable only on erection part.

21.0 GOVERNING LAWS AND JURISDICTION:

The Indian Law shall govern the agreement. Only appropriate courts in Jodhpur shall

have exclusive Court Jurisdiction to deal with any matter arising out of or relating to

the agreement or otherwise.

22.0 JURISDICTION FOR LEGAL PROCEEDINGS:

The contract shall be governed by the laws of India for the time being in force and be

subject to the court of competent jurisdiction at JODHPUR (RAJASTHAN). All

disputes, differences questions whatsoever arising between the NIGAM and the

agency upon or in relation to or in connection with the contracts shall be deemed to

have arisen at JODHPUR only and no court other than the court of Jodhpur

(Rajasthan) shall have jurisdiction to entertain or try the same.

23.0 SETTLEMENT OF DISPUTES:

All dispute / difference / question what so ever which may arise between the NIGAM

and the agency, the same shall be decided by the Chairman Discom`s / Managing

Director, Jd.VVNL Jodhpur or by the settlement committee constituted by him and

shall be final and binding on both the parties.

The NIGAM has constituted settlement committee to settle the disputed cases. For the

disputed amount up to Rs. 2.5 Lac the case may be referred to the CE level settlement

Page 75: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-75

committee and if the disputed amount is more than Rs. 2.5 Lac the case shall be

referred to the corporate level settlement committee. The non refundable fees for

referring the case to the settlement committee are as given below:

i) Reference fee for CE level settlement committee - Rs.1000/-*

ii) Reference fee for Nigam level settlement committee -Rs.3000/-*

and Appeal against CE level committee

iii) Fee for review of Decision of Nigam level settlement committee - Rs.5000/-*

by BOD

*GST shall be extra charged as applicable.

The settlement committee fees as shown above or prevailing at that time shall be

deposited in cash with the respective circle Accounts Officer (O&M), Jd.VVNL and

shall furnish receipt thereof with a request for referring their disputes to the settlement

committee for decision.

24. CONDUCT OF AGENCIES STAFF:

If any of the Agency’s employees shall in the opinion of NIGAM is guilty of any

misconduct or incompetence or negligence, and then if so directed by NIGAM, the

Agency shall at once remove such employee and replace him by a qualified and

competent substitute.

25. LIEN:

In case of any lien or claim pertaining to the work and responsibility of the agency for

which NIGAM might become liable, it shall have right to recover such claim amount

from the agency.

26. COMPLETION OF WORK:

The material / equipments for construction of such ordered work shall be supplied in

such a manner so that the entire work of construction, commissioning and its handing

over to Nigam is completed within Three months (TNTW- 473) from the date of

issue of the work order. Accordingly, the ordered work shall be commenced within 15

days period from the date of issue of the work order and supply, erection, testing and

commissioning of total ordered work is to be completed within Two and half months

period thereafter at the rate specified in work completion Schedule-5 of the bidding

documents and as mentioned hereunder:-

Page 76: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-76

S. No. Stage Period in months

1 Commencement The execution of line work shall commence within 15 days

from the date of issue of work order.

2 Completion of

supply, erection,

testing and

commissioning of

ordered work

Within Two and half months (TNTW- 473 ) thereafter at

the following rate

Time Progressive quantum of

work exceed in terms of

awarded work

In 50 % of completion time

period

40% of total work awarded.

In 75 % of completion time

period

70% of total work awarded.

In 100 % of completion time

period

100 % of the ordered work.

27.0 DELAY IN EXECUTION / COMPLETION OF WORK AFTER THE

SCHEDULE DATE:

27.1 The time and the date of delivery / completion period specified in the work order

shall be deemed to be the essence of the contract and the works shall have to be

completed not later than the period specified therein. Should the contractor fail to

complete the work on order or any part thereof within the specified completion period,

the owner shall be entitled at his option.

27.1.2 To affect recovery for delay in execution of works in the prescribed time limits as

above, a penalty shall be imposed 0.25% for 1st 4 weeks & 0.5% thereof. Max. 10%

of Balance Contract Value (Supply + Erection). The Balance Contract Value shall be

determined by the following formula:-

Total Contract Value – Value of Total Bills submitted to Sr. A.O ( CPC)

JdVVNL on the date of contractual stipulated completion Period.

27.1.3 To cancel the contract or part thereof and if so desired, to get the work

completed/ executed at the risk and cost of contractor.

27.2 Any financial liability arising from and consequent upon the failure of the contractor

to adhere to the stipulated completion schedule shall be to the contractor's account.

27.3 Adjustment in regard to the amount recoverable if any shall be made from the cash

deposits or from the firms dues of by operating the bank guarantee(s) as may be

Page 77: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-77

available with Nigam and/or in any other manner as may be deemed appropriate by the

purchaser.

28. FORCE MAJURE:

28.1 If at any time during the continuance of the contract the progress in whole or in

part is prevented or delayed by reason of any war, hostility, acts of public enemy, civil

commotion, sabotage, fire, floods, explosion, epidemics, quarantine restrictions, strikes,

lockouts or any acts of Gods (herein after referred to as events), then provided, a notice

and adequate proof of production/ dispatch/ execution having suffered on account of

these events, is given within 21 days from the day of occurrence thereof, the provisions

of sub-para of this clause shall not be invoked by the owner, provided further that the

execution under the contract shall be resumed, as soon as practicable after such

event(s) has/ have ceased to exist and the decision of the owner as to whether execution

so resumed or not, shall be final and conclusive, provided further that in case the

strike/lockout prolongs beyond a period of 30 days the contractor shall immediately

inform about it to the owner, in which case the owner reserves the right to procure the

material /equipment/ get the work on order or part thereof executed from any other

source at the risk and cost of the contractor.

28.2 Non availability/ scarcity/ non-allocation of raw material shall not constitute as a

force majeure condition ' in any case and it will be sole responsibility of the

contractor to arrange the raw material for timely execution of the order.

28.3 The delay in execution due to unforeseen and unavoidable reasons and the

circumstances beyond the control of contractor/owner leading to delay in execution

may also form force majeure conditions.

29.0 INSPECTIONS AND TESTING:

29.1 Inspection & testing of material:

29.1.1 The material as per final BOQ approved after joint survey with inception report

shall be offered for inspection. The inspection offer is to be given to SE (TW). The

inspection shall be carried by officer nominated by Nigam at the manufacturing Firm’s

work / Nigam’s store as per details at clause No.5 of Sec. III Part III. The firms work

shall be intimated by the contractor in the final BOQ to be submitted with the inception

report after joint survey conducted within commencement period after awarding the

contract.

Page 78: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-78

(a) It is clarified that the Samples from the material received in stores shall be selected

by the Nodal/Nominated officer within a period of 3 days and the same shall be tested

within a weeks’ time in the CTL thereafter.

(b)The Bidder shall state in his Bid the places of manufacture, testing and inspection of

various equipments offered by him. Unless specifically provided otherwise all tests shall

be carried out at the Contractor's works before shipment.

(c) The contractor shall intimate at-least 15 days in advance through notice(s) about the

readiness of material for dispatch commensurate with specific delivery schedule, so as to

enable the owner to depute his representative for Inspection, Testing & Checking of the

material / equipment. For this purpose the date of receipt of the letter in the office of the

work order placing authority shall be deemed as the date of call for inspection and not

the date mentioned in the letter or the date of dispatch. In case material / equipment is

not found ready by the representative of the owner deputed for inspection to the extent of

the quantity indicated in the inspection call with tolerance of (-) 10% or if the inspection

is not got carried out by any reason(s ) attributed to the contractor an amount of

Rs.7500/- plus applicable GST only for the contractor's work located in the State of

Rajasthan and an amount of Rs.15,000/- plus applicable GST for the contractor's works

located outside the State of Rajasthan will become payable by the contractor on this

account to the Accounts Officer (CPC), Jd.VVNL , Jodhpur. Further, in cases where

traveling by air is involved the inspection charges will be recovered on actual basis. The

contractor will deposit the amount with the Sr.Accounts Officer ( CPC ), Jd.VVNL

Jodhpur immediately under intimation to the work order placing authority, failing which

the subsequent call for inspection shall not be entertained.

(d) Packing:- The material/equipment shall be offered duly packed so as to enable the

inspecting Officer to seal the inspected / cleared material for identification. The

supplier / contractor shall provide such packing of the goods as is required to

prevent their damages or deterioration during transit to their final destination as

indicated in the contract. The packing shall be sufficient to withstand without

limitation rough handling during transit to their final destination as indicated in

the contract. The packing shall be sufficient to withstand without limitation rough

handling during transit and exposure to extreme temperature, salt and

precipitation during transport and open storage. Packing

Page 79: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-79

case size and weights shall be taken into consideration where appropriate

keeping in view, remoteness of the good’s final destination and absence of heavy

mechanized handling facilities at all points in transit as well as at the destination.

The packing, marking and documentation within and outside the packages shall

comply strictly with such special requirements as shall be expressly provided for

in the contract or in any subsequent instructions imparted by the owner.

(e) The Owner reserves to himself the right of having any inspection or special

test of a reasonable nature at contractor's premises or at sites, in addition to those

prescribed in applicable standards and the enclosed technical specification.

(f) When the tests have been satisfactorily completed at the Contractor's or sub-

contractors works the Engineer shall issue a certificate to that effect but if the tests were

not witnessed by the Engineer or his representative, the certificate would be issued after

the receipt of test certificate by the Engineer, No equipment shall be shipped / dispatched

before such a certificate has been issued.

(g) The authorized representative of the owner shall have at all reasonable times

access to the works and premises of the contractor and / or his associates, if any, and

shall be free to inspect the works, examine & test the product(s) including raw materials

used and the workmanship employed during / after manufacture.

(h) The contractor shall also furnish the latest calibration certificate(s) of the

testing instruments / equipments used for the testing of the materials / equipments as

covered in the owner order, to the inspecting Officer. The testing instruments / machines

should be got calibrated by the contractor from time to time from the Manufacturer of the

testing instruments or any Govt. recognized testing laboratory. The calibration

certificate(s) should not, in any case, be older than one year at the time of presenting the

same to the inspecting Officer. In case the contractor fails to comply with the conditions

as aforesaid, a certificate in writing of the inspector / representative of the Owner that the

contractor has failed to provide the facilities shall be conclusive.

(i) Unless the inspection is specifically waived, no material shall be dispatched

without inspection and clearance for dispatch by the owner's representative.

(j) The owner reserves the right to reject all or any part of the material being

manufactured or awaiting dispatch, due to any defect or deviations from the standard

specifications prescribed, as observed during the inspection. In case of any dispute /

difference in this regard the decision of the Superintending Engineer (TW) shall be final

and binding.

Page 80: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-80

(k) The owner also reserves the right to get the material / equipment tested in any

recognized Government Laboratory & claiming any compensation or rejecting the

material/ equipment, if not found in accordance with the specification. All charges

whatsoever consequent to such rejection and replacement / rectification shall be borne by

the contractor.

29.1.2 TYPE TEST CERTIFICATES:-

(a) Original / attested photocopies of the latest Type test certificate(s) not older

than Five Years from any recognized Government Laboratory / NABL Accredited

Laboratory, for all type tests wherever prescribed in the relevant latest edition of ISS (as

applicable) as mentioned in technical specification shall be furnished after award of

Work order. However, the owner reserves the right to get type tests conducted afresh by

the contractor.

(b) In case of any specific alternative requirement of type tests, the same shall be

furnished as per Technical specification.

(c) The Bid not accompanied with the type test certificates in terms of para(a)

above, are liable to be ignored.

(d) The contractor shall be required to furnish the routine/manufacturer(s) factory

test certificate(s) for the tests carried out during manufacture in accordance with the

relevant standard specifications.

29.2 Random checking of material at site:

In addition of material testing in CTL and after issuing the material from ACOS for

further use at site. The owner or his representative may take random sample of material

from site in presence of contractor representative available at site and to get it tested in

CTL, failure of material in testing shall lead to rejection of balance material with

contractor and same should not be allowed for further used and have to be replaced by

fresh material after successful testing in CTL.

29.2.1 Random checking of workmanship of work going on:-

The owner or his representative shall on giving seven days notice in writing to the

agency setting out any grounds of objections which he may have in respect of the work,

be at liberty to reject all or any part of the remaining work and all or any workmanship

connected with such work which in his opinion are not in accordance with the contract or

are in his opinion defective with reasons. In case of any dispute / difference in this regard

Page 81: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-81

the decision of the concerned Engineer In Charge i.e. Circle Superintending Engineer &

Superintending Engineer (TW), Jd.VVNL shall be final and binding.

30.0 CONTRACTOR'S DEFAULT:-

30.1 If the contractor shall neglect to execute the works with the diligence and

expedition or shall refuse or neglect to comply with any reasonable orders given to him,

in writing by the engineer in connection with the works or shall contravenes the

provisions of the contract, the owner may give notice in writing to the contractor make

good the failure, neglect or contravention complained of. Should the contractor fail to

comply with the notice within thirty (30) days from the date of service thereof, then and

in such case the owner shall be at liberty to employ other workmen and forthwith execute

such part of the works as the contractor may have neglected to do or if the owner shall

think fit, it shall be lawful for him without prejudice to any other right he may have

under the contract, to take the works wholly or in part out of the contractor's hands and

re-contract with any other person or persons complete the works or any part thereof and

in that event the owner shall have free use of all contractor's equipment that may have

been at the time on the site in connection with the works without being responsible to the

contractor over the same, and the owner shall be entitled to retain and apply any balance

which may be necessary, the payment of the cost of executing the said part of the works

or of completing the works as the case may be. If the cost of completing the works or

executing a part thereof as aforesaid shall exceed the balance due to the contractor, the

contractor shall pay such excess. Such payment of excess amount shall be independent of

the liquidated damages for delay, which the contractor shall have to pay if the

completion of works is delayed.

30.2 In addition, such action by the owner as aforesaid shall not relieve the

contractor of his liability to pay liquidated damages for delay in completion of works as

defined in clause 27.2 (a) of this section.

30.3 The termination of the contract under this clause shall not entitle the contractor

to reduce the value of the Security cum performance bank guarantee nor the time thereof.

The Security cum performance guarantee shall be valid for the full value and for the full

period of the contract including guarantee period.

30.4 HANDING OVER ON TERMINATION:

Page 82: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-82

30.4.1 The contract agreement shall require the parties to cooperate in handing back

the system in good working order to NIGAM after termination of agreement. Upon

termination of the agreement, the agency’s authority to act in the area shall immediately

cease.

30.4.2 The taking over certificate on the renovated system shall be issued by

concerned Assistant Engineer and certificate issued should be counter signed by

Executive Engineer as appointed by the Circle Superintending Engineer after due

checking & finally by Nodal officer i.e. SE (O&M),JdVVNL

30.4.3 The contractor shall hand over the complete layout drawing of renovated

distribution system in three (3) sets at the time of handing over the work to the Engineer

for reference and records.

31.0 DELAYS BY OWNER OR HIS AUTHORISED AGENT:-

In case the contractor's performance is delayed due to any act of omission on

the part of the owner or his authorized agents, then the contractor shall be given due

extension of time for the completion of the works, to the extent such omission on the part

of the owner has caused delay in the contractor's performance of his work. Regarding

reasonableness or otherwise of the extension of time, the decision of the

SUPERINTENDING ENGINEER (TW), Jd.VVNL Jodhpur shall be final.

32.0 TERMINATION OF CONTRACT ON OWNER'S INITIATIVE:-

32.1 The owner reserves the right to terminate the contract either in part or in full

due to reasons other than those mentioned under clause entitled contractor's default. The

owner shall in such an event give fifteen days (15 days) notice in writing to the

contractor of his decision to do so.

32.2 The contractor upon receipt of such notice shall discontinue the work on the

date and to the extent specified in the notice, make all reasonable efforts to obtain

cancellation of all orders and contracts to the extent they are related to the work

terminated and terms satisfactory to the owner, stop all further sub-contracting or

purchasing activity related to the work terminated, and assist the owner on maintenance

protection and disposition of the work acquired under the contract by the owner.

32.3 In the event of such a termination the contract shall be cancelled without any

liability on either side.

Page 83: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-83

32.4 If the contractor is an individual or a proprietary concern and the individual or

the proprietor dies and if the contractor is a partnership concern and one of the

partners dies, then unless the owner is satisfied that the legal representatives of the

individual contractor or of the proprietor of the proprietary concern and in the case of

partnership, the surviving partners, are capable of carrying out and completing the

contract the owner shall be entitled to cancel the contract as to its incomplete part

without being in any way liable to payment of any compensation to the estate of

deceased contractor of the contract, The decision of the owner that the legal

representatives of the deceased contractor or surviving partners of the contractor's firm

cannot carry out and complete, the owner shall not hold the estate of the deceased

contractor and / or the surviving partners of the estate of the deceased contractor and /or

the surviving partners of the contractor's firm liable to damages for not completing the

contract.

33.0 CHANGE OF NAME OF THE BIDDER / CONTRACTOR:-

33.1 At any stage after Biding, the Owner shall deal with the Contractor only in the

name and at the address under which he has submitted Bid. All the liabilities /

responsibilities for due execution of the Contract shall be that of the Contractor and in no

circumstance, he shall be relieved of any obligations under the Contract. The Owner

may, however, at his discretion deal with the, Agents / Representatives / Distributors /

Manufacturers / Associates / Principals / Sister concerns and such dealings shall not

absolve the Contractor(s) from his responsibilities / obligations / liabilities to the Owner

under the contract.

33.2 Any change / Alteration of name / Constitution / Organization of the

Contractor shall be duly notified to the Owner and the Owner reserves the right to

determine the Contract, in case of any such Notification. In the event of such

determination, the Owner may affect the purchase of material not supplied from

elsewhere at the risk and cost of the Bidder / Contractor.

34.0 CERTIFICATE NOT TO AFFECT RIGHT OF OWNER AND

LIABILITY OF CONTRACTOR:-

No interim payment certificate of the engineer nor any sum paid on account by the

owner nor any extension of time for execution of the works granted by the engineer shall

affect or prejudice the rights of the owner against the contractor or relieve the contractor of

Page 84: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-84

his obligations for the due performance of the contract, or be interpreted as approval of the

works done or of the equipment furnished and no certificate shall create liability for the

owner to pay for alterations, amendments, variations or additional works not ordered, in

writing by the engineer or discharge the liability of the contractor for the payment of

which he is bound to indemnify the owner nor shall any such certificate nor the acceptance

by him of any sum paid on account or otherwise affect or prejudice the rights of the

contractor against the owner.

35.0 CONTRACT PRICE:

The lump sum price with details of price of each item for equipment & erection portion as

mentioned in ‘G’ schedule of the bid with additions & deletions as may be agreed before

signing of the contract for the entire scope of the work shall be treated as the contract

price. Prices agreed by the bidder and subsequently termed as contract price shall remain

firm and no price variation shall be allowed.

(i) The bidder(s) are requested to quote FIRM Price in Indian Rupees only.

(ii) The prices quoted should be Unit all inclusive price including all local taxes, cess,

GST, other taxes and freight & insurance etc.

(iii) It is the responsibility of the bidder to make sure about the correct rates of duty / tax

if any levyable on the work / service at the time of tendering. If the rates assumed by the

Bidder(s) are less than the current rates prevailing at the time of tendering, the Nigam

will not be responsible for the mistake.

(iv)The Total cost of tender as received (material cost / erection & commissioning cost /

dismantling charges of retrieved material) shall be considered for deciding lowest (L-1)

rates. The unit cost quoted shall be the indicative for calculating actual charges for

making payments.

36.0 DEDUCTION FROM CONTRACT PRICE:-

All costs, damages or expenses which the owner may have paid, for which under the

contract the contractor is liable, will be claimed by the owner. All such claims shall be

billed by the owner to the contractor regularly as and when they fall due. Such bills shall

be supported by appropriate and certified vouchers or explanations, to enable the

contractor to properly identify such claims. Such claims shall be paid by the contractor

within fifteen (15) days of the receipt of the corresponding bills and if not paid by the

Page 85: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-85

contractor within the said period, the owner may then deduct the amount, from any

payment due or becoming due by him to the contractor under the contract or may be

recovered by actions of law or otherwise, if the contractor fails to satisfy the owner of

such claims.

37.0 REPLACEMENT OF DEFECTIVE PARTS AND MATERIALS:-

37.1 If during the progress of the works the engineers finds/ decides and inform in

writing to the contractor, that the contractor has procured any equipment or part of the

equipment unsound or imperfect or has used any equipment and or carried out the work

inferior than the quality specified, the contractor on receiving details of such defects or

deficiencies shall at his own expense within seven(7) days of his receiving the notice,

otherwise, within such time as may be reasonably necessary for making it good, proceed

to alter, re-construct or remove such work and furnish fresh, equipment and or re-do the

work meeting with the standards of the specifications. In case the contractor fails to do

so, the engineer may on giving the contractor seven (7) days notice in writing of his

intentions to do so, proceed to remove the portion of the works so complained of and, at

the cost of the contractor, perform all such work or furnish all such equipment provided

that nothing in this clause shall be deemed to deprive the owner of invoking any rights

under the contract which the owner may otherwise have in respect of such defects and

deficiencies.

37.2 The contractor's full and extreme liability under this clause shall be satisfied

by the payments to the owner of the extra cost, of such replacement procured, including

erection, as provided for in the contract, such extra cost being the ascertained difference

between the price paid by the owner for such replacement and the contract-price portion

for such defective Equipment and repayments of any sum paid by the owner to the

contractor in respect of such defective Equipment. The contractor's extreme liability

under this clause shall be limited to repayment of all sums paid by the owner under the

contract for such defective Equipment.

38.0 CONSIGNEE:

The material after clearance of Inspection shall be consigned to Contractor Store and the

Inventory of Material should route through the Nodal Officer / Engineer Incharge

nominated by Nigam for carrying out the work.

Page 86: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-86

39.0 TERMS OF PAYMENT:

39.1 The terms of payment for the equipment / material and its erection /

dismantling charges are as detailed herein. The payment to the contractor for the material

/ equipment, erection & dismantling charges shall be made by the Sr. Accounts Officer (

CPC) of the Nigam after fulfillment of the following contractual formalities:

(a) Acceptance of letter of award and signing of Contract Agreement.

(b) Submission of an unconditional bank guarantee from a scheduled bank towards

contract Security cum Performance Guarantee valid for a period of commencement &

completion period + 12 Months (Performance Period) + 6 months (grace period for lodging any

claims as admissible) from date of issue of award of contract in accordance with clause

No.3.2 of this SECTION-II and in the format given at Annexure ‘E’-GCC.

(c) Submission of Security Deposit bank guarantee as per clause No. 3.1 above of this

section and in the format given at Annexure ‘D’ GCC.

(d) Submission of a detailed PERT Network based on the Work-Schedule stipulated

in the letter of award and the approval by owner.

(e) Submission of copy of GST registration certificate.

(f) Submission of copy of PAN.

(g) Submission of copy of CPF / PF / ESI registration certificate.

(h) Payment shall be arranged on receipt of verified bills containing the details of the

length of line work to be carried out as per the “GPRS” coordinates already got approved

from the concerned project in-charge.

(i) Contractor will submit the MAS A/c with every running/final bill duly verified by

the Junior Engineer, Assistant Engineer, Executive Engineer concerned.

39.2 The payment shall be made as under:-

A. No Payment shall be made against supply of material / equipment’s.

B. Up to 70% Cost of Awarded Contract (Supply + Erection).

i) The bills against supplied material and its erection / dismantling having 10% value

or more / having a value of 25.0 Lacs or more, whichever is less of the ordered cost of

the project shall be entertained on regular basis as running bills.

ii) 95% payment of the above bills be released.

Page 87: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-87

C. Balance 30% Cost of Awarded Contract (Supply + Erection).

i) The payment of balance 30% cost of material along with erection /dismantling

shall be made only after 100% successful erection of material / equipment and its

commissioning and after handing over the project.

ii) 95% payment of the above bills is released.

D. Balance 5% (RMD) payment of supplied material along with erection and

dismantling Charges shall be made after 12 months of handing over the system after

successful Completion, commissioning and charging in all respect.

E. All the above payments shall be released by the Sr. Accounts Officer (

CPC),through RTGS on or after 45 days of the receipt / submission of bills and

completion of other contractual formalities.

Following formalities / documents are also to be completed while delivery of the

material in the store.

a) After delivering of material in store & after passing of material in CTL testing the

contractor shall furnish receipted challans of material duly verified by the officer

designated to accept the material in triplicate as per approved BOQ of the ordered work

to the Nodal Officer / Engineer In-charge of the project. In this regard a certificate that

the material has passed in CTL testing along with CTL report for such verification shall

also be submitted for further issue of material to contractor as per requirement of on-

going work.

39.3 CURRENCY OF PAYMENTS:

All payments under the contract shall be made in Indian Rupees only.

39.4 MODE OF PAYMENT:-

i. The payment shall be made by Sr. Accounts Officer (CPC), JdVVNL, Jodhpur at the

certificate of the Engineer-in charge in accordance with the conditions set out herein, for

supply of material and erection work so measured.

ii. The contractor shall submit running bills of material supplied for the completed work

along with erection & dismantling charges as per provisions of above clause, for interim

payment in 2 (two) copies to the concerned Executive Engineer for checking and

verification by him. Thereafter, it should be submitted to Nigam Sr. A.O. (CPC) for

arranging due payment.

Page 88: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-88

39.5 APPLICATION FOR PAYMENTS: -

(i) The contractor shall submit application for the payment in the prescribed

proforma enclosed as Annexure -A (GCC) of this Sections.

(ii) Each such application shall state the amount claimed and shall set forth in

detail, in the order of the payment schedule, particulars of the works including the works

executed at site and of the equipment shipped/ brought on to the site pursuant to the

contract up to the date mentioned in the application and for the period covered since the

last preceding certificate, if any.

(iii) Every interim payment certificate shall certify the contract value of the works

executed/completed up to the date mentioned in the application for the payment

certificate, provided that no sum shall be included in any interim payment certificate in

respect of the works that, according to the decision of the engineer, does not comply with

the contract, or has been performed, at the date of certificate prematurely.

39.6 CORRECTIONS:-

The Engineer may by any Interim payment certificate make any corrections or

modifications in any previous certificate (other than the one purporting to be a final

payment certificate) which shall have been issued by him and shall have power to modify

or withhold any interim payment certificate if the works or any part thereof are not being

carried out to his satisfaction.

39.7 For the delayed payments, if any, the Nigam will not pay any interest.

39.8 FOR CLAIMING BALANCE 5% PAYMENT OF MATERIAL &

ERECTION COST AFTER HANDING OVER .

Balance 5% (RMD) payment of material cost , erection & dismantling charges shall be

made after 12 months of handing over the system after successful completion,

commissioning & charging of the system in all respect. The RMD of 5% may be released

before 12 month of entire completion of project as mentioned above subject to furnished

equivalent amount of Bank Guarantee with remaining period with additional 30 days

grace period for lodging the claim.

NOTE: -The commencement of payment shall be effective only after completion of

all contractual formalities and acceptance of BGs.

39.9 RETRIEVAL OF MATERIAL:-

Page 89: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-89

(i) The old/damaged PCC poles retrieved from site shall be deposited as per

direction of the Engineer-in-charge.

(ii) The concreted M.S. Rails / R.S. Joists to be removed from site which are not

possible to be retrieved as it is shall be cut after digging the same up to one feet in

ground.

(iii). It is also clarified that during execution of work the retrieved material have

to be deposited in Nigam store i.e. concerned ACOS. The contractor firm have to obtain

clear and readable copy of the MCNs (Material credit note) indicating quantities of the

material/equipment deposited in the stores with rating/sizes, if any, clearly legible and

duly signed & stamped by the ACOS concerned. No invoices / bills regarding material

supplied and work carried out shall be entertained by Nigam Sr.AO(CPC) for

payment without such clear and readable MCNs.

(iv). The existing service lines, if required to be replaced then such removed service

lines are to be deposited in Nigam stores as retrieved material thus the contractor firm are

advised to remain careful and conscious for removal of old service lines from the

consumer premises while execution of the work and ensure to deposit the same with the

circle stores without any failure. It may also be noted that recovery shall be effected as

per provisions of Nigam in respect of non-deposition / short deposition of such service

lines required to be retrieved as applicable in case of other retrievable material /

equipment.

40.0 FREE ISSUE ITEMS:-

(i) The NIGAM shall provide Power Transformer, Distribution Transformer, RMU,

33KV / 12 KV Breakers, & Energy meters etc.

(ii) The departmental material / item ( to be provided by the Nigam) up to the quantity

likely to be utilized during next two months shall be provided by the purchaser to the

contractor within a period of one month from the date of requisition made with the

Engineer In-charge subject to the condition that erection of all other allied material ( to

be supplied by the contractor) is ready or likely to be ready for utilization of the “Free

issue items”.

(iii) Further above mentioned item Nigam may provide any item as free issue for smooth

and accelerated execution of the work with due approval of competent authority.

41.0 BALANCE MATERIAL:-

Page 90: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-90

It is clarified that the payment shall be made based on unit prices of work order for the

executed work at site and the balance material in excess of executed work shall be

returned to the contractor through the same channel through which it was issued for site

work. However, Nigam may accept certain items which are required on such prices as

may be mutually agreed based on the comparative unit prices of the items as per work

order / Latest MM Wing price for same specifications/latest stores Issue rate etc.

whichever is lower subject to clearance of CTL testing.

42.0 EXTRA ITEMS:-

(i) In case if successful bidder at the time of joint survey feels that some additional items

are required and which are essential for completion of project work and has not been

covered in the list of items may be included in the revised BOQ with detailed

justification of such items with due approval of Nodal officer.

(ii) Use of G.I pipe / conduit pipe / DWC pipe for cable laying of U/G 2 core & 4

core XLPE cable for consumer service line where it is open near consumer premises or

for crossing of “Nalis / Drainage” shall be exercised & cost of this extra item shall also

be paid by NIGAM, if not covered in G-Schedule.

(iii) Provision for route marking for cable work may also be included at the time of joint

survey.

The prices shall be allowed as per prevailing SIR/ CLRC rates ( with applicable

premium of the work order) for extra items required in survey report at the time of

submission for approval of revised BOQ with due recommendations of Nodal

officer.

Maximum quantity of extra items as well as value of extra items shall be allowed as

per RTPP Act- 2012 & Rules- 2013 made there under.

43.0 FINAL ACCOUNT:-

(a) Not later than three (3) months after the handing over of the new electrical system

complete in all respects i.e. after successful testing and commissioning of all the

equipments with necessary take off terminal units for future automations and dismantling

of existing over head lines and associated items as per final BOQ and transporting &

depositing the dismantled items to the Nigam stores and on obtaining proper receipt of

Page 91: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-91

material against MCN’s etc. The contractor shall submit a draft statement of “final

account” and supporting document to the Engineer/Engineer’s Representative showing in

detail the value of the work done in accordance with the contract (hereinafter called for

“Contractor’s Draft Final Account).

(b) Within three (3) months after receipt of the contractor’s Draft Final Account and all

information reasonably required for its verification, the Engineer/Engineer’s

representative shall determine the value of all matters to which the contractor is entitled

for payment under the contract. The Engineer/Engineer’s representative shall then issue

to the Contractor a statement (hereinafter called “Engineer’s Draft Final Account)

showing the final amount to which the contractor is entitled for completion of contract.

The Contractor shall sign the Engineer’s Draft Final Account as an acknowledgement of

the full and final value of the work performed under the contract and shall promptly

submit a signed copy. (hereinafter called “Final Account”) to the Engineer/Engineer’s

representative)

44.0 FINAL CERTIFICATE:

On receipt of Final Account, the Engineer / Engineer’s representative shall promptly

prepare and issue to the Employer and the contractor a “Final Payment Certificate”

certifying any further amounts due to the contractor in respect of the contract.

45.0 ENHANCEMENT OF RATES:

No representation for enhancement of rates once accepted will be considered during the

currency of the contract.

46.0 SUB-LETTING OF CONTRACT

46.1 The Contractor shall not, without the consent in writing of the DISCOM, assign or

sublet his contract including supply of material or any substantial part thereof, provided

that any such consent shall not relieve him from any obligation, duty or responsibility,

liability under the Contract. If the Contractor sublets or changes the sub-contractor

without notification to the DISCOM, then DISCOM shall not make payments for such

works/materials, if any defects/damages in works or materials is noticed in such

authorized sublet portion within the expiry of guarantee period/DISCOM reserves the

right to rectify/redo the defective goods/works at its own cost and such cost damages will

be recovered from contractor.

46.2 The bidder should furnish an Undertaking that he is responsible for any portion of

works if carried out by the sub-contractor and he is jointly and severally accountable to

the Nigam, in the event of defective design or defaults in the performance.

Page 92: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-92

46.3 Approval of sub-contractor shall be obtained before commencement of work.

47.0 INCIDENTAL SERVICES:

The Supplier / contractor is required to provide any or all the services broadly outlined in

the scope of the work. Detailed design, fabrication, supply, erection, testing and

commissioning of VCBs , erection of Distribution Transformers, detailed surveying,

check surveying, design, testing, fabrication, earth wire, accessories, bolts and nuts, etc.

and making foundations for erection of VCBs , Distribution Transformers under turnkey

basis. Any other minor incidental service whether specifically mentioned or not must be

done by the Contractor at his own cost. All tools, Tackles, Plant etc., required for

completion of above works shall be brought by the Contractor.

48.0 EXAMINATION OF WORK BEFORE COVERING UP/THIRD PARTY

INSPECTION :-

(i) No work shall be covered up or out of view without the approval of the Engineer

or the Engineer’s representative and the contractor shall afford full opportunity for the

Engineer or the Engineer’s representative to Examine and measure any work, which is

about to be covered up or put out of view and to examine foundations before permanent

work is placed thereon. The contractor shall give due notice to the Engineer’s

representative whenever any such work or foundation is ready or about to be ready for

examination and the Engineer’s representative shall without delay act accordingly and

attend for the purpose of examining and measuring such work or of examining such

foundations.

(ii) The Nigam shall have the right to get the executed works verified/inspected

either by the third party inspecting agency or through departmental inspecting officers

(or both) during execution as well as on completion for quality and for the quantity both.

The discrepancies / shortcomings / omissions observed shall immediately be got rectified

by the contractor and on completion of rectification work the contractor shall intimate to

the Nigam through Nodal officer so that such rectifications shall be got verified. The

contractor shall also ensure that the discrepancies / shortcomings / omissions so observed

shall not be repeated in the execution of remaining work.

49.0 UNCOVERING AND MAKING OPENINGS:

Page 93: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-93

The contractor shall uncover any part of the works or make openings in or through the

same as the Engineer may from time to time direct and shall reinstate and make good

such part or parts to the satisfaction of the Engineer. If any such part or parts have been

covered up or put out of view after compliance with the requirement of clause 50.0

supra, and or found to be executed in accordance with the contract, the expenses of

uncovering, making opening in or through, reinstating and making good of the same

shall be borne by the Employer, but in all other cases, these costs shall be borne by the

contractor.

50.0 REMOVAL OF IMPROPER WORK AND MATERIALS :

i) The Engineer / Engineer’s representative shall during the progress of the works have

power to order in writing from time to time for the removal from the site within one

week of receipt of notice, of any materials which in their opinion are not in accordance

with the contract.

(ii) In case of default on the part of the contractor in carrying out such an order, the

employer shall be entitled to employ and pay other persons to carry out the same and all

expenses consequent therein or incidental thereto shall be recoverable from the

contractor by the employer from any money due or which may become due to the

contractor.

51.0 GENERAL RESPONSIBILITIES OF THE CONTRACTOR:

51.1 WORKS EXECUTIONS:

The contractor shall, subject to provisions of the contract and with due care and elegance

execute the works and provide all labour including the supervision thereof, materials,

constructional plant and all other things, whether of a temporary or permanent nature,

required in and for such execution, so far as the necessity for providing the same is

specified in or is reasonably to be inferred from the contract.

51.2 WORKS SAFETY:

The contractor shall take full responsibility for the adequacy and safety of all site

operations and methods of construction

51.3 SUPERVISION BY THE CONTRACTOR:

The contractor shall provide all necessary supervision during the execution of the works

and as thereafter as the Engineer may consider necessary for the proper fulfillment of

contractor’s obligations under the contract.

Page 94: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-94

51.4 SETTING OUT OF WORKS:

The contractor / supplier shall be responsible for the true and proper setting out of

works in relation to the supply, installation, erection, testing & commissioning. And for

any corrections of the design position, levels, dimensions and alignment of all parts of

the works and for the provision of all necessary instruments, appliances, equipments,

tools and plants and labour in connection there with and erection of steel structure

support for provision of Transformer and dismantling of existing Nigam outdo or

11KV structures and transporting & devaluating the dismantled items to the Nigam

stores also supply and installation of Termination for the Incoming line , Outgoing line

& Transformer cable under turnkey basis at different locations. If at any time during the

progress of the works any error shall appear for arise in the design, positions levels,

dimensions or alignment of any part of the works, the contractor on being required so to

do by the Engineer / Engineer’s representative shall at his own cost, rectify such error to

the satisfaction of the Engineer / Engineer’s representative shall not in any way relieve

the contractor of his responsibility for the correctness thereof land the contractor shall

carefully protect and preserve all bench marks, sight rails, pegs and such other things

used in setting out of the works.

51.5 CARE OF THE WORK :

From the date of commencement of the works until the date stated in the certificate of

completion for the whole of the works, the contractor shall take full responsibility for the

care thereof. In case any damage, loss or injury shall happen to the works, or any part

thereof, from any cause whatsoever, the contractor shall at his own cost, repair and make

good at the same, so that at the completion, the permanent works shall be in good order

and in condition and in conformity in every respect with the requirements of the contract.

In the event of any such damage, loss or injury happening from any of the expected risks,

the contractor shall, to the extent required repair/make good the same at the cost of the

employer.

The expected risks are war hostilities (whether war be declared or not), invasion, attack

of foreign enemies, rebellion, revolution, insurrection of military or usurped power, civil

war for any such operations of the forces of nature.

51.6 WATCHING AND LIGHTING :

Page 95: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-95

The contractor shall in connection with the works provide and maintain at his own cost

all lights, guards, fencing and watching when and where necessary or as required by the

Engineer/Engineer’s representative or by any duly constituted authority for the protection

of the works or for the safety and convenience of the Public and others.

51.7 CONTRACTOR TO KEEP SITE CLEAR:

During the progress of the works, the contractor shall keep the site free from all

unnecessary obstruction and shall dispose of any construction plants, surplus materials

and clear away and remove from the site any wreckage, rubbish or temporary works no

longer required. If any permanent works on pathway such as tiles etc damaged or broken

during the work that’s all be made permanent

51.8 CLEARANCE OF SITE BEFORE AND AFTER COMPLETION :

On the Commencement and the completion of the works, the contractor shall clear away

and remove from the site all constructional plants, surplus materials, rubbish and

temporary works of every kind and leave the whole of the site and works clear and in

workman like condition to the satisfaction of the Engineer. If the site is not cleared, the

same will be done by the Employer and the cost will be recovered from the contractor.

Any materials/tools etc., at the site will become the property of the employer and

contractor shall have no claim over it.

51.9 WORK TO BE DONE TO THE SATISFACTION OF ENGINEER/

ENGINEER’S REPRESENTATIVE:

Save in so far as it legally or physically impossible, the contractor shall execute and

maintain the works in strict accordance with the contract to the satisfaction of the

Engineer/Engineer’s representative and shall comply with and adhere strictly to their

instructions and directions on any matter whether mentioned in the contract or not,

touching or concerning the works. The Engineer may from time to time delegate in

writing to the Engineer’s representative any of the powers, authorities vested in the

Engineer and furnish to the contractor a copy of all such written delegation of power and

authorities. Any written instruction or approval given by the Engineer’s representative to

the contractor within the terms of such delegation, but not otherwise shall bind the

contractor and employer as though it had been given by the Engineer provided always as

follows:

(a) Failure of the Engineer’s representative to disapprove any work or materials shall not

prejudice the power of the Engineer thereafter to disapprove such work or materials and

to order the pulling down, removal or breaking thereof.

Page 96: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-96

If the contractor shall be dissatisfied by reason of any decision of the Engineer’s

representative, he shall be entitled to refer the matter to the Engineer who shall there

upon confirm, reverse or vary such decisions.

51.10 PLANT, TEMPORARY WORKS AND MATERIALS :

All constructional plant, temporary works and materials provided by the contractor shall

when brought to the site, be deemed to be exclusively intended for the execution of the

works and the contractor shall not remove the same or any part thereof except for the

purpose of moving it from one part of the site to another part.

51.11 REMOVAL OF PLANT, ETC :

Upon completion of work, the contractor shall remove from the site all the said

constructional plant and temporary works remaining thereon and any unused materials

provided by the contractor.

51.12 EMPLOYMENT NOT LIABLE FOR DAMAGE TO PLANT ETC :

The contractor shall note that employer shall not at any time be liable for the loss of or

damage to any of aforesaid constructional plant, temporary works or materials.

52.0 COMMENCEMENT OF WORKS, PROGRAMME, & TIME FOR

COMPLETION ETC:-

52.1 COMMENCEMENT & PROGRAMME OF WORKS :

(i) The contractor shall on award of the contract submit to the Engineer In-charge an

inception report of joint survey carried out for supply, erection & retrieval of material for

approval of final BOQ during commencement period.

(ii) After joint survey, a programme showing the order or procedure in which he

proposes to carry out and complete the works as stipulated in clause 52.2 The contractor

shall whenever required by the Engineer/Engineer’s representative also provide in

writing for his information a general description of the arrangements and methods which

the contractor proposes to adopt for the execution of works.

(i) At the time of submission of joint survey report, necessary proposal for forest,

railway, highway and river crossing be submitted within the commencement period,

otherwise delay in submission shall be on the part of contractor. However, wherever such

approvals are required from the concerned authorities the delay in receipt of approval

from the date of submission of proposal by contractor through Engineer In-charge (to the

statuary agency) shall not be on the part of contractor.

Page 97: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-97

(ii) If any time it should appear to the Engineer that actual progress of works does not

conform to the approved programme 52.1(ii) Supra, the contractor shall produce at the

request of the Engineer a revised programme showing the modifications to the approved

programme necessary to ensure completion of the works within the time for completion

as defined in Clause-52.2 thereof.

(iii) The submission to and approval by the Engineer / Engineer’s representative of such

programme or furnishing of such particulars shall not relieve the contractor of any of his

duties or responsibilities under the contract.

(iv) It is to clarify that Guarantee / Warranty for the material supplied by the purchaser

shall not be applicable for contractor. The material to be supplied by the purchaser shall

be provided to the contractor within a period of one month from the date of requisition

from the contractor to the Engineer-in charge.

(v) The departmental material/ item (to be provided by the Nigam) up to the quantity

likely to be utilized during next two months shall be provided by the purchaser to the

contractor within a period of one month from the date of requisition made with the

Engineer In-charge subject to the condition that erection of all other allied material (to be

supplied by the contractor) is ready or likely to be ready for utilization of the “Free issue

items”.

(vi) It shall be the prime responsibility of the contractor. However, JVVNL shall depute

concerned field officers for necessary support in case of restrictions/resistance from local

people.

(vii) It is clarified that the Samples from the material received in stores shall be selected

by the Nodal/Nominated officer within a period of 3 days and the same shall be tested

within a weeks’ time in the CTL thereafter.

52.2 ADHERENCE TO COMPLETION PERIOD:

On receipt of the Purchase Order, the contractor shall take over the site and commence

the preliminary civil works. Entire works including testing and commissioning and

dismantling of existing Nigam outdoor 11KV structures, transporting & devaluating the

dismantled items to the Nigam stores in “as is and where is” condition the entire

work shall be completed as per Clause No. 26.0 “ Completion of Work”.

Page 98: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-98

Any delay in completion of works would attract Liquidated damages as specified in the

specification.

52.3 EXTENSION OF TIME FOR COMPLETION:

No extension of time for services to be rendered including procurement of necessary

materials granted to the contractor should affect or prejudice the right of the DISCOM

against the contractor or relieve the contractor of his obligations for the duel payment of

damage whether duly ascertained or certified or not any sum against the payment of

which he is bound to indemnify to the DISCOM.

Extension of time will be given if the delay is on the account of DISCOM.

Should the amount of extra or additional work of any kind or any cause of delay referred

to in these conditions or special circumstances of any kind whatsoever which may occur,

other than through a default of the contractor, be such as fairly to entitle the contractor, to

an extension of time for the completion of the works, the Engineer shall determine the

amount of such an extension and shall notify the employer and contractor accordingly

provided that the Engineer is bound to take into account any extra or additional work or

other special circumstances unless the contractor has within 28 days after such work has

commenced, or such circumstances have arisen, or as soon thereafter as is practicable,

submitted to the Engineer/Engineer’s representative full and detailed particulars of any

extension of time to which he may consider himself entitled in order that such

submission may be investigated at the time.

52.4 RATE OF PROGRESS:

If for any reason, which does not entitle the contractor to an extension of time, the rate of

progress of the works or any erection is at any time in the opinion of the Engineer, too

slow to ensure completion by the prescribed time or extended time for completion, the

Engineer shall so notify the contractor in writing and the contractor shall thereupon take

such steps as are necessary and the Engineer may approve to expedite progress so as to

complete the work or such section by the prescribed time or extended time. The

contractor shall not be entitled to take additional payment for taking such steps, if

necessary, as a result of any notice given by the Engineer under this clause, the

contractor shall seek Engineer’s permission to do any work on Sundays or other

Holiday’s or other locally recognized days of rest.

Page 99: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-99

52.5 DISRUPTION OF PROGRESS:

(i) The contractor shall give written notice to the Engineer whenever planning or

progress of the works is likely to be delayed or disrupted unless any further drawings or

order including a direction, instruction or approval is issued by the Engineer within a

reasonable time. The notice shall include the details of drawings or order required and

any delay or disruption likely to be suffered if it is late.

ii) If by reason of any failure or inability of the Engineer to issue within a reasonable

time in all circumstances any drawing or order requested for by the contractor in

accordance with Clause 52.7 (i), the contractor suffers delay and/or incurs cost, then the

Engineer shall take such delay into account in determining any extensions of time to

which the contractor is entitled under Clause 52.3 thereof and the contractor shall be paid

the amount of such costs as shall be reasonable.

52.7 SUSPENSION OF WORKS :

(i) The contractor shall on the written order of the Engineer, suspend the progress of

the works or any part thereof for such time or times and in such manner as the Engineer

may consider necessary and shall during such suspension properly protect and secure the

work, so far as is necessary in the opinion of the Engineer. The extra cost incurred by

the contractor in giving effect to the Engineer’s instructions under this clause shall be

paid the amount of such costs as shall be reasonable.

a. Otherwise not provided for in the contract or

b. Necessary by reason of some default on the part of the contractor, or

c. Necessary by reason of climatic conditions on the site, or

d. Necessary for the proper execution of works or for the safety of the works or

any part thereof in so far as such necessity does not arise from any act or default by the

Engineer/Engineer’s representative or from any of the expected risks defined in this

specification. Provided that the contractor shall not be entitled to recover any such extra

cost unless he gives written notice of his intention of claim to the Engineer within twenty

eight days of the Engineer’s order. The Engineer shall settle and determine such extra

payment and/or extension of time under clause 52.3 hereof to be made to the contractor

in respect of such claim as shall in the opinion of the Engineer be fair and reasonable.

52.8. SUSPENSION LASTING MORE THAN NINETY DAYS:

If the progress of the works or any part thereof is suspended on the written order of the

Engineer and if permission to resume work is not given by the Engineer within a period

Page 100: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-100

of ninety days from the date of suspension then, unless such suspension is within

paragraph (a), (b), (c) or (d) of Clause-52.7 the contractor may serve a written notice on

the Engineer requiring permission within twenty eight days (28) from the receipt thereof

to proceed with the works, or that part thereof in regard to which progress is suspended

and if such permission is not granted within that time, the contractor by a further written

notice so served may but is not bound to elect or treat the suspension where it affects part

only of the works as an omission of such part or where it affects the whole works as an

abandonment of the contract by the employer.

53.0 MEASUREMENT : It is clarified that the maximum 10% quantity variation of

particular item of final BOQ based on joint survey with NIGAM officers during

commencement period submitted with inception report shall be allowed with no change

in total contract value of particular lot.

53.1 QUANTITIES:

The quantities set out in the bill of quantities are only tentative and estimated quantities

of work. They are not to be taken as the actual and correct quantities of the work to be

executed by the contract or in fulfillment of his obligations under the contract.

53.2 WORKS TO BE MEASURED:

The Engineer shall, except as otherwise stated ascertain and determine by measurement

the value in terms of the contract of work done in accordance with the contractor. He

shall, when he requires any part or parts of the works to be measured, give notice to the

contractor, authorized agent or representative, who shall forthwith attend to or send a

qualified agent to assist the Engineer/Engineer’s representative in making such

measurement and shall furnish all particulars such measurement and shall furnish all

particulars required by either of them. Should the contractor not attend or neglect or

omit to send a such agents, then the measurement made by the correct measurement of

the works and any claim later on by the contractor will not be accepted.

53.3 METHOD OF MEASUREMENT OF WORK:

The works shall not be measured except where otherwise specifically described

henceforth:

The above measurements are purely for the purpose of progressive payments. The

erection of Distribution Transformers will be taken simultaneously with the erection of

RMUs. The erections works done by the contractor should be in complete in all respect

and has satisfactory withstand all the tests mentioned in the appropriate sections. The

Page 101: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-101

responsibility of the contractor does not cease until a certificate is issued by the

DISCOM, for having taken over RMUs and associated equipments, accessories, T&Ps,

devolution of retrieved materials to the DISCOM stores etc. from the contractor and will

cease only on expiry of the guarantee period of work.

54.0 CERTIFICATION OF COMPLETION OF WORKS :

When the whole of the works have been substantially completed and have satisfactorily

passed any final test that is prescribed in the contract, the contractor may give a notice to

that effect to the Engineer/Engineer’s representative. Such notice shall be in writing and

shall be deemed to be a request by the contractor for the Engineer to issue a certificate of

completion in respect of the works. The Engineer shall, within twenty one (21) days of

the date if delivery of such notice, either issue to the contractor with a copy to the

Employer, a certificate of completion stating the date on which, in the Engineer’s

opinion, requires to be done by the contractor of any defects in the works affecting

substantial completion that may appear after such instructions and before the completion

of the works specified therein. The contractor shall be bound to receive such certificate

of completion within twenty one (21) days of completion to the satisfaction of the

Engineer of the works specified and making good any defect so noticed.

55.0 NOTICES:

55.1 All notices given by one party to the other including written orders given by the

Employer, Engineer’s representative to the contractor under the terms of the contract

shall be in writing or if by Telegram/Telex/Fax/E-Mail be confirmed in writing. Period

of notice shall be 14 days unless otherwise stated.

55.2 For the purpose of issuing notices to the purchaser in respect of works and

supply of goods, the following is the address of the Purchaser.

The Superintending Engineer (TW)

Jd.VVNL

New Power House, Jodhpur

55.3. For the purpose of issuing notices for the works concerned to them to the

Engineer’s Representative, the addresses of the Superintending Engineer is as follows:

THE SUPREINTENDING ENGINEER (O&M), Jodhpur Discom, _______

Page 102: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-102

56.0 DETAILS CONFIDENTIAL:

56.1 The contractor shall treat the specifications, contract document etc. as confidential.

56.2 The materials and services covered under these specifications shall be performed

as per requirements of the relevant standards refereed hereinafter against each of

equipment and services.

56.3 No extension of time for services to be rendered including procurement of

necessary materials granted to the contractor shall affect or prejudice the right of the

DISCOM against the payment of which he is bound to indemnify to the DISCOM.

Extension of time will be given if the delay is on the account of the DISCOM.

********

Page 103: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-103

ANNEXURE – A (GCC)

PROFORMA OF APPLICATION FOR PAYMENTS

__________________________________________________________________________

Project :

Equipment : Date :

Name of Contractor : Contract No. :

Contract Value: Contract Name :

Until reference: Application :

Serial number :

To,

The Superintending Engineer (O&M )

Jd.VVNL

Dear Sir,

Sub: Application for Payment *

Pursuant to the above referred contract dated ..................... the undersigned hereby applies for

payment of the sum of ................................................................................................

(Specify amount)

1.1.1 Material supplied in the store/ site.

1. The above amount is on account of : (Check whichever applicable)

2.Completed works including supply & erection against running bills

3.Final payment (Schedule **)

as detailed in the attached schedule(s) which form an integral part of this application.

4. The payment claimed is as per item(s) No.(s) .................... of the payment schedule

annexed to the above mentioned contract.

5. This application consists of this page, a summary of claim statement (Schedule**) and the

following signed schedule:

1. _____________________ 2. _____________________ 3. _____________________

The following documents are also enclosed:

1. _____________________ 2. _____________________ 3. _____________________

Signature of Contractor/authorized signatory

* Applications for payment will be made to 'Engineer' as to be designated for this purpose at

the time of award of the contract.

** Proforma for the schedules will be mutually discussed and agreed to during the

finalisation of the contract agreement.

Proforma:

__________________________________________________________________

S.no. Name of Make Qty. Date of Date of Amount Remark

Material Supply Erection

Page 104: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-104

ANNEXURE-B (GCC)

JODHPUR VIDYUT VITRAN NIGAM LTD.

AGREEMENT

(On non-judicial stamp paper worth 0.25% of contract value of Govt. of Rajasthan)

This indenture made at ________ on ______ this _____ day of the Month of

________________ of the year ____________ between the ________________Jodhpur

Vidyut Vitran Nigam Ltd. (hereinafter referred to as the Owner) which expression unless the

context does not permit includes successors and assigns) of the one part and

(I) To be used in case of Limited Companies

M/s____________________________________ a private/ Public Limited Company

incorporated _____________________ under the ____________________________

companies act and having its Registered office at _____________________ (hereinafter

referred to as Contractor which expression unless the context does not permit includes their

successors and permitted assigns).

(2) To be used in case of Partnership concerns

M/s ________________________________ a Partnership Firm consisting of the following

Partners namely:

(Name) (Age) (Residence) (Occupation)

1.

2.

3.

4.

(hereinafter referred to as Contractor which expression unless the context does not permit

includes their respective heirs, executors, administrators, legal representatives, permitted

assigns) of the second part, witness the as follows:-

(1) The contractor, does by these presents agree to supply and execute/complete the erection

work of _______________ (Name of line) to the Owner and the Owner does agree to

purchase and execute/complete the erection work from the Contractor, the

material/equipment and erection work as specified in the work order No. ___________ dated

__________ and amendment letter No. __________ dated __________ appended and on the

terms & conditions constrained in the said order and amendment letter. The General terms

and conditions of the contract appended hereto are considered a part of this agreement.

(2) The Contractor has deposited Rs. _____________________ (In words

Rs._______________________)

*(a) In cash, or

*(b) by furnishing a Demand Draft No._______ dated ________ drawn in favour of

__________ or

*(c) by furnishing a Bank Guarantee equivalent to _______% of the Contract value,

towards security deposit with the Owner for the performance of this agreement by the

Contractor. The security deposit Receipt duly endorsed in favour of the Owner

should be lodged to his safe custody.

(* delete which is not applicable)

(3) The contractor is also bound to fulfill all the conditions mentioned in the above work

order.

Page 105: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-105

(4) The work to be executed under this agreement shall be as per terms and conditions

mentioned in the above work order.

(5) In case of dispute as to whether any materials supplied are or are not in accordance with

specifications set forth in the schedule, the decision of the Superintending (TW), JVVNL,

Jaipur shall be final and binding on both the parties.

(6) The delivery shall be effected and completed as per clause No. ________ of the work

order from the date of this Work Order and amendment letter No. ________ dt. ________.

The first installment of supplies will begin as per clause No. _________ of the work order

and amendment letter No. __________ dt. _______ to the work order.

(7) Payment of the work executed under this agreement shall as under :

As per clause No. ____________ of the Work Order and amendment letter No.

___________ dt ______ to the work order.

(8) If the Contractor fails wholly or in part to fulfill this agreement, the Owner shall be

entitled at his discretion to retain the whole or any part of the deposit made by the Contractor

under clause (2) and if the loss suffered by the Owner exceeds the amount of said deposit, he

will be entitled to recover the said loss from the Contractor.

(9) If any sum remains due or becomes recoverable from the Contractor on account of the

non-fulfillment of this agreement or on account of any other reason, the Contractor shall pay

the same immediately on demand, the Owner shall be entitled to recover the same from the

Contractor as arrears of Land Revenue.

(10) In witness of the due execution of this agreement the parties have hereunder set their

hands the day and the year first above written.

Signed and delivered by

In case of Limited/Partnership Shri_____________ (1)Signature ______________

Companies & Firms Designation (2)Signature ______________

For and on behalf of _______________________ (1) Signature _____________

In presence of witnesses (2) Signature _____________

Signed and delivered by

In case of individuals Shri________________ (1) Signature _____________

Signed and delivered by

In case of Individuals Shri_________________ (1) Signature _____________

In the presence of witness:

(1) Shri_____________ Designation ___________ (1) Signature _____________

(2) Shri _____________ Designation ___________ (2) Signature _____________

Signed and delivered by the ___________________ JDVVNL

by order and on behalf of the MD of the Nigam. Jodhpur Vidyut Vitran Nigam Ltd.

(Seal to be affixed)

Page 106: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-106

ANNEXURE-C (GCC)

MANUFACTURER’S WARRANTEE FORM

(Warrantee to be furnished on non-judicial stamp paper of Government of Rajasthan

worth Rs. 500/-)

To,

The SUPERINTENDING ENGINEER (TW),

Jaipur Vidyut Vitran Nigam Limited,

Old Powerhouse, Bani Park,

Jaipur-302006

Dear Sir,

THIS DEED OF GUARANTEE is made this day ___________of_____________of the

year_____

Between the SUPERINTENDING ENGINEER (TW), Jodhpur Vidyut Vitran

Nigam Limited (which expression shall unless excluded by or repugnant to the

context includes his successors and assignees) of the one part and

_________________________________________hereinafter called “The Contractor”

(which expression shall unless excluded by or repugnant to the context includes its

successors and assignees) of the other part.

WHEREAS MESSERS __________________________________(hereinafter called the

contractor) agreed to supply the material for erection of -------- on turnkey basis from

_______________ (Name of line) to the Superintending Engineer, Jodhpur Vidyut

Vitran Nigam Ltd., against Work Order No._____________________dated_______

(hereinafter referred to as the contract).

AND WHEREAS as per the terms of the contract it was provided that the contractor

should furnish a Warrantee for supplying any material free of cost that may be required

due to defects arising from faulty materials, design and workmanship, so as to make it

meet the guarantees and requirements of the contract.

AND WHEREAS at the request of the Superintending Engineer (TW) Jd.VVNL ,

Jodhpur , the contractor M/s_________________ has agreed to execute these presents.

NOW THIS INDENTURE WITNESS AND IT IS HEREBY AGREED AND

DECLARED by the and between the parties hereto as follows:

1. The Contractor hereby guarantees to the SUPERINTENDING ENGINEER (TW),

/ Jd.VVNL Jodhpur , the fulfillment by the contractor of the various obligations

imposed on him under the aforesaid contract including the obligations of the

contractor to supply materials of the good quality, design and workmanship and the

Contractor further guarantees to the Jaipur / Jodhpur / Ajmer Vidyut Vitran Nigam

Ltd. that they (M/s ________________) shall substitute and supply any material free

of cost that may be required due to defects arising from faulty material design and

workmanship and the Contractor undertakes to indemnify and keep the

SUPERINTENDING ENGINEER (TW), Jd.VVNL / Jodhpur indemnified to the

extent of full value of contract ( Rs. ______) (in words Rupees

___________________________) against any loss or damage that may be caused to

or suffered by the Jaipur / Jodhpur / Ajmer Vidyut Vitran Nigam Ltd. by reason of

any failure by the contractor to supply materials of good quality, design and

workmanship as aforesaid.

The decision of SUPERINTENDING ENGINEER (TW), Jd.VVNL Jodhpur as to

whether the contractor (M/s ______________) have failed or neglected to perform or

discharge their duties and obligations as aforesaid shall be final and binding on the

Contractor.

Page 107: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-107

2. The Warrantee herein contained shall remain in full force and effect during the period

that would be taken in the performance of the said contract and it shall continue to be

valid till all the obligations to the Jodhpur Vidyut Vitran Nigam Ltd. under or by

force of the contract have been fully and properly discharged by the said contractor,

subject however, to the conditions that the Jodhpur Vidyut Vitran Nigam Ltd. will

have no right under this Warrantee after 60 months from the date of

commissioning/taking over of the line provided further that if any claim arises by

virtue of this Warrantee before the aforesaid date, the same shall be enforceable

against the Contractor notwithstanding the fact that the same is enforced after the

aforesaid date.

3. The Warrantee herein contained shall not be affected by any change in the

constitution of the Contractor.

4. The Contractor further undertake not to revoke, this Warrantee during its currency

except with the previous consent of the SUPERINTENDING ENGINEER (TW),

Jd.VVNL Jodhpur , in writing.

5. All disputes arising under the said Warrantee, between the Contractor and the Jodhpur

Vidyut Vitran Nigam Ltd. shall be subject to the jurisdiction of Courts, only at

Jodhpur in Rajas than alone.

IN WITNESS WHEREOF THE CONTRACTOR HAS executed these presents the

day and year written above.

Yours faithfully,

(EXECUTANT)

Signed by the above named Contractor in presence of:-

(Signature with full Name and Address)

SUPERINTENDING ENGINEER (TW),

Witness:-

1.

2.

(Attested by Notary Public or First Class Magistrate or directly confirmed by the

executing Contractor)

Page 108: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-108

ANNEXURE-D(GCC)

SECURITY BANK GUARANTEE

(On non-judicial stamp paper of Govt. of Rajasthan worth 0.25% of BG value or Maximum

Rs.25000/- whichever is less)

The Superintending Engineer(TW)

Jodhpur Vidyut Vitran Nigam Limited

Jodhpur

Jodhpur (hereinafter called the Owner or his assigns) having agreed that in respect of order

No.______ dated ______ (hereinafter referred to as contract) placed with M/s.

______________________ having their registered office at _________________________

(hereinafter called the contractor), the contractor need not to furnish security deposit in cash and/or

bank draft, We the _____________________ having its head office at _____________________

(hereinafter called the Bank) undertake to pay the owner on demand the sum or sums of money

payable as security deposit by the contractor in respect of Order No. ___________ dated _________

placed by the Nigam with the contractor subject to the following terms & conditions.

(1) Payment pursuant in this undertaking will be demanded by the owner from the Bank and will be

met by the Bank without question in the case in which the Contractor, on receipt of the order and/or

after the acceptance of this tender has been communicated to him by the owner ,make default in

entering into an agreement or having entered into such Agreement or otherwise the contractor makes

default in carrying out the contract thereof. As to whether the occasion or ground is arisen for such

demand the decision of the SUPERINTENDING ENGINEER (TW) or any other officer exercising

the powers of SUPERINTENDING ENGINEER (TW), JdVVNL shall be final.

(2) The liability of the Bank shall not at any time exceed to Rs. _________ (Rupees

__________________________________)

(3) The undertaking will be determined on ___________ but will, notwithstanding such

determination, continue to be in force till the expiry of 3 months from the date of completion of line

against the aforesaid order.

(4) No variation in the terms of tender, acceptance or agreement as between the contractor and the

owner made without the owner's consent shall discharge this undertaking.

(5) No indulgence or grant of time by the owner to the contractor without the acknowledgement of

the Bank will discharge the liabilities of the Bank under this guarantee.

(6) The guarantee herein contained shall not be affected by any change in the constitution of the

contractor.

(7) Notwithstanding anything contained herein before, the Bank's liability under this guarantee is

restricted to Rs. __________ (Rupees ___________________________) and the guarantee shall

remain in force up to _______________ unless demand or claim in writing is presented on the Bank

within 3 months from that date, the Bank shall be released and discharged from all liabilities there

under. However the validity of the bank guarantee shall be extended as and when required by the

Nigam.

(8) All disputes arising under the said guarantee between the Bank and the NIGAM or between the

contractor and the Nigam pertaining to the guarantee shall be subject to the jurisdiction of Courts only

at Jaipur / Jodhpur / Ajmer in Rajasthan.

(9) The Bank further undertakes not to revoke this guarantee during its currency except with the

previous consent of the SUPERINTENDING ENGINEER (TW), JdVVNL IN WITNESS

WHEREOF the Bank has executed these presents the day __________ and year _________________.

Yours faithfully,

Bankers (EXECUTANT)

Witness:

1. 2.

Page 109: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-109

ANNEXURE-E (GCC)

PERFORMA FOR SECURITY CUM PERFORMANCE BANK GUARANTEE FORM

(On non-judicial stamp paper of Govt. of Rajasthan worth 0.25% of BG value or Maximum

Rs.25000/- whichever is less)

To,

The SUPERINTENDING ENGINEER (TW),

Jodhpur Vidyut Vitran Nigam Ltd.. ),

Jodhpur .

Dear Sir,

THIS DEED OF GUARANTEE is made this day __________ of __________________

of the year _________ between the SUPERINTENDING ENGINEER (TW), Jodhpur

Vidyut Vitran Nigam Ltd. (which expression shall unless excluded by or repugnant to the

context includes his successors and assignees) of the one part and the

_______________________________, having its head office at _______________________

hereinafter _______________________________ hereinafter called "The Bank" (which

expression shall unless excluded by or repugnant to the context includes its successors and

assignees) of the other part.

WHEREAS MESSERS ________________________ (hereinafter called contractor)

agreed for ---------------------------------------------------turnkey basis to the

SUPERINTENDING ENGINEER (TW), JODHPUR VIDYUT VITRAN NIGAM LTD.

against Work order No. __________________ dated _____ (hereinafter referred to as the

contract).

AND WHEREAS as per the terms of the contract it was provided that the contractor

should furnish a Bank Guarantee ________% ___________ of the total contract

value(material & erection) by way of security for supplying any material and erection

executing/completing free of cost any erection work that may be required due to defect

arising from faulty design and workmanship, so as to make it meet the guarantee and

requirements of the contract.

AND WHEREAS at the request of the contractor the Bank has agreed to execute these

present.

NOW THIS INDENTURE WITNESS AND IT IS HEREBY AGREED AND

DECLARED by the and between the parties hereto as follows:

1. The Bank hereby guarantees to the SUPERINTENDING ENGINEER

(TW), JODHPUR VIDYUT VITRAN NIGAM LIMITED, the fulfillment by the contractor

Page 110: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-110

of the various obligations imposed on him under the aforesaid contract including the

obligations of the contractor to supply material and to timely execute /complete erection work

of good quality and workmanship and the bank further guarantees to the JODHPUR

VIDYUT VITRAN NIGAM LTD. that the contractor shall substitute and supply any material

and execute /complete free of cost, any additional work that may be required due to defects

arising from faulty design and workmanship and the Bank undertakes to indemnity and keep

the SUPERINTENDING ENGINEER (TW), JODHPUR VIDYUT VITRAN NIGAM

LTD. indemnified to the extent of Rs. _________ (in words Rupees ______________)

against any loss or damage that may be caused to or suffered by the JODHPUR VIDYUT

VITRAN NIGAM LTD. by reason of any failure by the contractor to timely supply material

and executing/completing erection work of good quality and workmanship as aforesaid and

further undertake to pay to the SUPERINTENDING ENGINEER (TW), JODHPUR

VIDYUT VITRAN NIGAM LTD. on demand a sum not exceeding Rs. ________ (Rupees

__________________) in the event of the contractor failing or neglecting to perform and

discharge the aforesaid duties and obligations on their part to be observed and performed

under the said contract.

The decision of the SUPERINTENDING ENGINEER (TW), JODHPUR VIDYUT

VITRAN NIGAM LTD. as to whether the contractor has failed or neglected to perform or

discharge their duties and obligations as aforesaid and as to the amount payable to the

SUPERINTENDING ENGINEER (TW), JODHPUR VIDYUT VITRAN NIGAM LTD.

by the Bank herein shall be final and binding on the Bank.

2. The guarantee herein contained shall remain in full force and effect during the period

that would be taken for the Security cum performance of the said contract and it shall

continue to be enforceable till all the obligations to the JODHPUR VIDYUT VITRAN

NIGAM LTD. under or by force of the contract have been fully and properly discharged by

the said contractor, subject however, to the conditions that the JODHPUR VIDYUT

VITRAN NIGAM LTD. will have no right under this guarantee after 12 Months + 6

Months grace period from the date of completion / commissioning / taking over of the line,

provided further that if any, claim arises by virtue of this guarantee before the aforesaid date,

the same shall be enforceable against this bank not withstanding the fact that the same is

enforced after the aforesaid date.

3. The guarantee herein contained shall not be affected by any change in the constitution of

the contractor or Bank.

Page 111: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-111

4. The SUPERINTENDING ENGINEER (TW), JODHPUR VIDYUT VITRAN

NIGAM LTD. shall have the fullest liberty without affecting the guarantee to postpone for

any time and from time to time any of the powers exercisable by the NIGAM against

contractor and either to enforce or forebear from enforcing any of terms and conditions of the

said contract and the Bank shall not be released from its liability under this guarantee and

exercise of JODHPUR VIDYUT VITRAN NIGAM LTD. of the liberty with reference to

the matter aforesaid or by the reasons time being given to the contractor or any other

forbearance, act or omission on the part of the JODHPUR VIDYUT VITRAN NIGAM

LTD. to the contractor or by any other matter or thing whatsoever which under the law

relating to the sureties shall but for this provision have the effect of so releasing the bank

from such liability.

5. The decision of the SUPERINTENDING ENGINEER (TW), or any other officer

exercising the powers of SUPERINTENDING ENGINEER (TW), JODHPUR Vidyut

Vitran Nigam Ltd. shall be the final.

6. The Bank further undertake not to revoke the guarantee during its currency except with

the previous consent of the, SUPERINTENDING ENGINEER (TW), JODHPUR Vidyut

Vitran Nigam Ltd. in writing.

7. All disputes arising under the said guarantee, between the Bank and the Nigam or

between the contractor and the Nigam pertaining to the guarantee, shall be subject to the

jurisdiction of Courts, only at JODHPUR in Rajasthan alone.

8. Notwithstanding anything contained herein before, the Bank's liability under this guarantee

is restricted to Rs. _________ (Rupees _____________ and the guarantee shall remain in

force up to __________________________________ unless demand or claim in writing is

presented on the Bank within six months from that date, the Bank shall be released and

discharged from all liabilities there under. However the validity of the bank guarantee shall

be extended as and when required by the Nigam.

9. IN WITNESS WHEREOF THE BANK HAS executed these presents the day and year

written above.

Yours faithfully,

Bankers (Executants)

Signed by the above named Bank in presence (Name and Address)

Witness 1.

Witness 2.

Page 112: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-112

Attested by Notary Public or First Class Magistrate or directly confirmed by the executing

bank.

Note: In case the contract is awarded to a joint venture, the contract Security cum

performance bank guarantee shall be in the name of the joint venture covering all partners of

the joint venture, not in the name of the lead partner or any partner(s) of the Joint Venture

alone.

Page 113: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-113

APPENDIX-1(GCC)

(A )DETAILS OF PROGRESS

1. Details of progress achieved during I/II fortnight of month _______________

2. Order No. and Date ______________________________

3. Name of Line : ________________________________

Sl.No. Erection

activity

(All)

Unit Total

work

involved

Work

done up to

last

fortnight

Work

done

during

fortnight

Total

work

done

up to

this

report

Bala

nce

work

to be

done

Remarks

1. 2. 3. 4. 5. 6. 7. 8 . 9.

(B) Details of work done (activity-wise)

SIGNATURE OF THE CONTRACTOR

Page 114: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-114

APPENDIX-2 (GCC)

CHECK LIST

CONTRACT AGREEMENT

1) Required stamp paper 0.25% of the contract value (Non judicial stamp paper of

Rajasthan Government).

2) Stamp paper should be in the name of firm

3) Stamp paper should be valid (should not be old more than six month)

4) Should be in triplicate

5) Contract agreement should be according to our prescribed format

6) The enclosures should be attached as required by Work Order

7) All the pages of agreement along with its enclosures should be signed by the

authorized signatory

8) The clause Number of work order should be recorded in the blank space wherever

required alongwith other information like work order No., details of firms, details of

deposit etc.

9) The agreement should be witnessed by the two persons along with their name and

address

10) The Power of Attorney in respect of authorized signatory should be attached

with the contract agreement duly attested by first class magistrate or Notary Public on

Non judicial stamp paper of Rs. 100/- or as provided in stamp and registration Act,

bearing the seal of stamp paper issuing authority to firm along with seal and signature of

issuing authority.

11) The power of attorney should be witnessed by two persons along with their

name and address

12) The Power of Attorney should be in triplicate

13) The Manufacturer’s Warranty should be enclosed with the contract agreement

in triplicate if required as per work order.

Page 115: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-115

ANNEXURE–A(INB)

Bid Bank Guarantee

(FOR EARNEST MONEY)

(Bank Guarantee in lieu of 80% of earnest money on non-judicial stamp paper of Govt.

of Rajasthan worth Rs.25000/- Maximum or 0.25% of BG Value whichever is less)

Ref : Bank Guarantee No. ................................

Dated: ..........................................

The Superintending Engineer (TW)

Jodhpur Vidyut Vitran Nigam Limited,

Industrial Area,New Power House

Jodhpur – 342001.

1.Whereas .............................[name of the Bidder] (hereinafter called “the Bidder”)

has submitted its bid dated .............................[date of submission of bid] for the

construction of......................... [name of contract] (hereinafter called “the Bid”).

2.KNOW ALL PEOPLE by these presents that WE..........................[name of bank] of

.....................[name of country], having our registered office at................................

[address of bank] (hereinafter called “the Bank”), are bound

unto.................................... [name of Purchaser] (hereinafter called “the Purchaser”)

in the sum of Rs.*________________ for which payment well and truly to be made to

the said Purchaser, the Bank binds itself, its successors, and assigns by these presents.

Sealed with the Common Seal of the said Bank this _____ day of ____________

200__________.

3. THE CONDITIONS of this obligation are:

1. If the Bidder withdraws its Bid during the period of bid validity specified by the

Bidder in the Bid Form; or

2. If the bidder refuses to accept the correction of error in his Bid ; or

3.. If the Bidder, having been notified of the acceptance of its Bid by the Purchaser

During the period of bid validity:

(a) Fails or refuses to execute the Contract agreement, if required; or

(b) Fails or refuses to furnish the Security cum performance security, in accordance with the

General Conditions of Contract;

4. We undertake and authorize our branch situated at Jaipur (Rajasthan)

address:_______________________________________________________to pay to

the Purchaser up to the above amount upon receipt of its first written demand, without

the Purchaser having to substantiate its demand, provided that in its demand the

Purchaser will note that the amount claimed by it is due to it owing to the occurrence

of one or all of the three conditions, specifying the occurred condition or conditions.

5. The decision of the SUPERINTENDING ENGINEER (TW),

JODHPUR VIDYU VITRAN NIGAM LIMITED, Jodhpur shall be final whether breach

has been committed

on the right to demand the amount of guarantee from us which has accrued to the

Purchaser.

6. This guarantee shall not cease or determine, if the purchaser grants time or

indulgence or vary the terms of the contract with the contractor or without our consent

or knowledge.

7. The guarantee herein contained shall not be affected by any change in the

constitution of the contractor.

8. We, _____________________ further undertake not to evoke this guarantee during

its currency except with the previous consent of the SUPERINTENDING ENGINEER(TW),

Page 116: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-116

JODHPUR VIDYUT VITRAN NIGAM LIMITED, JODHPUR.

9. All disputes arising under the said guarantee between the Bank and the Nigam or

Between the Contractor and the Nigam pertaining to the guarantee, shall be subject to

the jurisdiction of Courts in Jaipur, Rajasthan alone.

10. This guarantee will remain in force up to the bid validity period initially plus 30 day grace

period. Further extended till finalization of bid.

Yours faithfully,

Bankers (EXECUTANT)

Witness:-

1.

2.

_______________________________________________________________

*The Bidder should insert the amount of the guarantee in words and figures

Denominated in the currency of bid. This figure should be same as shown in clause No.

13.0 of the “instructions to bidders”.

Page 117: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-117

Annexure - B (INB)

Bank Guarantee verification checklist

S.No. CHECK - LIST

1. Does the bank guarantee compare verbatim with standard Performa for BG Yes/NO

2. (a)Has the executing Officer of BG indicated his name designation &power of Attorney

No. Signing power Number etc. on BG. Yes/NO

(b) Is each page of BG duly Signed/ initialed by the executants and last page is signed with

full particulars as required in the standard Performa of BG and under the seal of the bank.

Yes/NO

(c) Does the last page of the BG carry the signatures of two witnesses alongside the signature

of the executing Bank Manager Yes/NO

3.(a)Is the BG on non-judicial stamp paper of appropriate value Yes/NO

(b)Is the date of sale of non-judicial stamp paper shown on the BGand the stamp paper is

issued not more than Six months prior to the date of execution of BG. Yes/NO

4. (a)Are the factual details such as Bid specification No., LOA NO.Contract price, etc ,

correct Yes/NO

(b) Whether Overwriting /cutting, if any on the BG, authenticated under signature & seal of

executants Yes/NO

5. Is the amount and validity of BG is in line with contract provisions. Yes/NO

6.Whether the BG has been issued by a Nationalized bank / Non-Nationalized Bank

acceptable to Buyer /Scheduled Bank in India(the applicability of the bank should be in line

with the provisions

of bidding documents) Yes/NO

Date:

Signature………………..

Place:

Name……………………

Designation………………

Company Seal…………….

Page 118: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-118

1.0 GENERAL

1.1 The following shall supplement the conditions already contained in the other

parts of the Specification and documents and shall govern the Portion of the work of

this Contract to be performed at Site.

1.2 The Contractor upon signing of the Contract shall, in addition to a Project

Coordinator, nominate another responsible officer as his representative a t Site

suitably acted for the purpose of overall responsibility and co-ordination of the

works to be performed at Site. Such person shall function from the Site Office of the

Contractor during the pendency of Contract.

2.0 REGULATION OF LOCAL AUTHORITIES AND STATUTES

2.1 The Contractor shall comply with all the rules and regulations of local

authorities during the performance of his field activities. He shall also comply with the

Minimum Wages Act, 1948 and the Payment of Wages Act (both of the Government of

India) and the rules made there under in respect of any employee or workman employed

or engaged by him or his Sub-Contractor.

2.2 All registration and statutory inspection fees, if any, in respect of his work

pursuant to this Contract shall be to the account of the Contractor. However, any

registration, statutory inspection fees lawfully payable under any statutory laws

and its amendments from time to time during erection in respect of the equipment

ultimately to be owned by the Owner, shall be to the account of the Owner. Should

any such inspection or registration need to be rearranged due to the fault of the

Contractor or his Subcontractor, the additional fees to such inspection and/or

registration shall be borne by the Contractor.

3.0 OWNER'S LIEN ON EQUIPMENT

The Owner shall have lien on all equipments including those of the Contractor

brought to the Site for the purpose of erection, testing and commissioning of the

equipment to be supplied & erected under the Contract. The Owner shall continue to

hold the lien on all such equipment throughout the period of Contract. No material

Part : III Section-III ERECTION CONDITIONS OF CONTRACT (ECC)

Page 119: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-119

brought to the Site shall be removed from the Site by the Contractor and/or his Sub-

Contractors without the prior written approval of the Engineer.

4.0 INSPECTION, TESTING AND INSPECTION CERTIFICATES

The provisions of the clause entitled Inspection, Testing and Inspection

Certificates under General Technical Conditions and Specifications shall also be

applicable to the erection portion of the Works.The Engineer in Charge (Nodal

Officer) shall have the right to re-inspect any equipment though previously inspected

and approved by owner’s representative at the Contractor’s works, before and after the

same are erected at Site. If by the above inspection, the Engineer in Charge (Nodal

Officer) rejects any equipment, the Contractor shall make good for such rejections either

by replacement or modification / repairs as may be necessary to the satisfaction of the

Engineer in Charge (Nodal Officer). Such replacements will also include the

replacements or re- execution of such of those works of other Contractors and/or

agencies, which might have got damaged or affected by the replacements or re- work

done to the Contractor’s work.

5.0 ACCESS TO SITE AND WORKS ON SITE

5.1 Suitable access to the Site shall be afforded to the Contractor by the Owner in

reasonable time.

5.2 In the execution of the works, no person other than the Contractor

or his duly appointed representative, Sub-Contractor and workmen, shall be allowed to

do work on the Site, except by the special permission, in writing of the Engineer in

Charge (Nodal Officer) or his representative.

6.0 CONTRACTOR'S SITE OFFICE ESTABLISHMENT

The Contractor shall establish a Site Office at the Sites and keep posted an

authorized representative for the purpose of the Contract. Any written order or

instruction of the Engineer in Charge (Nodal Officer) or his duly authorized

representative shall be communicated to the said authorised resident representative of the

Contractor and the same shall be deemed to have been communicated to the

Contractor at his legal address.

Page 120: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-120

7.0 CONTRACTOR'S REPRESENTATIVE AND WORKMAN:

If supervision of erection or complete erection be included then the contractor

shall employ at least one competent representative, whose name or names shall have

previously been communicated in writing to the Engineer by the contractor to

superintend the erection of the plant and carrying out of the works. The said

representative or if more than one shall be employed then one of such representative

shall be present on the site during working hours and any written orders or instructions

which the Engineer or his duly authorized representative (whose name shall have been

previously communicated in writing to the contractor) may give to the said

representative of the contractor shall be deemed to have been given to the

contractor, and the contractor shall remove the person so objected to, upon receipt

from the Engineer a notice in writing requiring him to do so, and shall provide in

his place a competent representative at the contractor's expenses.

8.0 DISCIPLINE OF WORKMEN

The Contractor shall adhere to the disciplinary procedure set by the Engineer in

Charge (Nodal Officer) in respect of his employees and workmen at Site. The Engineer

in Charge (Nodal Officer) shall be at liberty to object to the presence of any

representative or employee of the Contractor at the Site, if in the opinion of the

Engineer in Charge (Nodal Officer) such employee has mis-conducted himself or is

incompetent or negligent or otherwise undesirable and then the Contractor shall remove

such a person objected to and provide in his place a competent replacement.

9.0 CONTRACTOR'S FIELD OPERATION

9.1 The Contractor shall keep the Engineer in Charge (Nodal Officer)

informed in advance regarding his field activity plans and schedules for carrying out

each part of the works. Any review of such plan or schedule or method of work by the

Engineer in Charge (Nodal Officer) shall not relieve the Contractor of any of

responsibilities towards the field activities. Such reviews shall also not be considered as

an assumption of any risk or liability by the Engineer in Charge (Nodal Officer) or the

Owner or any of his representatives and no claim of the Contractor will be entertained

because of the failure or inefficiency of any such plan or schedule or method of work

reviewed. The Contractor shall be solely responsible for the safety, adequacy and

efficiency of plant and equipment and his erection methods.

Page 121: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-121

9.2 The Contractor shall have the complete responsibility for the conditions

of the Work-Site including the safety of all persons employed by him or his Sub-

Contractor and all the properties under his custody during the performance of the

work.This requirement shall apply continuously till the completion of the Contract and

shall not be limited to normal working hours. The construction review by the

Engineer in Charge (Nodal Officer) is not intended to include review of Contractor's

safety measures in, or of near the Work-Site, and their adequacy or otherwise.

10.0 CHECKING OF INSPECTED MATERIAL BEFORE USE

Before use of inspected equipments/ material for erection/

commissioning, the contractor shall get verified the intactness of seals identification of

the material inspected or cleared for dispatch by our inspecting officer from our

Engineer in- charge as per inspection report of our inspecting officers. A certificate to

this effect and authorizing contractor to use the material, shall be issued by the Engineer

in-charge. Further, the material /equipments, authorized to be used without inspection in

special circumstances shall also to be got checked & verified by the Engineer In-charge

and a certificate issued from him authorizing the contractor to use the same.

11.0 MAN-POWER REPORT

11.1 The Contractor shall submit to the Engineer, on the first day of every

month, a man-hour schedule for the month, detailing the man- hours scheduled for

the month, skill-wise and area-wise.

11.2 The Contractor shall also submit to the Engineer, on the first day of every

month, a man-power report of the previous month detailing the number of persons

scheduled to have been employed and actually employed, skill-wise and the areas of

employment of such labour.

12.0 PROTECTION OF WORK

The Contractor shall have total responsibility for protecting his works till it is

finally taken over by the Engineer. No claim will be entertained by the Owner or the

Engineer in Charge (Nodal Officer) for any damage or loss to the Contractor's works

and the Contractor shall be responsible for complete restoration of the damaged works

to original conditions to comply with the specification and drawings. Should any such

damage to the Contractor's Works occur because of other party not being under his

Page 122: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-122

supervision or control, the Contractor shall make his claim directly with t h e party

concerned. If disagreement or conflict or dispute develops between the

Contractor and the other party or parties concerned regarding the responsibility

for damage to the Contractor's Works the same shall be resolved as per the

provisions of the GCC Clause entitled "Cooperation with other Contractors". The

Contractor shall not cause any delay in the repair of such damaged Works

because of any delay in the resolution of such disputes. The Contractor shall proceed to

repair the Work immediately and no cause thereof will be assigned pending resolution

of such disputes.

13.0 EMPLOYMENT OF LABOUR

13.1 The Contractor will be expected to employ on the work only his

regular skilled employees with experience of his particular work. No female

labour shall be employed after darkness. No person below the age of eighteen years

and above the age of 60 years shall be employed.

13.2 All travelling expenses including provisions of all necessary transport to and

from Site, lodging allowances and other payments to the Contractor's

employees shall be the sole responsibility of the Contractor.

13.3 The hours of work on the Site shall be decided by the Owner and the

Contractor shall adhere to it. Working hours will normally be eight (8) hours per day -

Monday to Saturday.

13.4 The Contractor's employees shall wear identification badges while on work

at Site.

13.5 In case the Owner becomes liable to pay any wages or dues to the labour

or any Government agency under any of the provisions of the Minimum Wages Act,

Workmen Compensation Act, Contract Labour Regulation Abolition Act or any other

law due to act of omission of the Contractor, the Owner may make such payments and

shall recover the same from the Contractor's Bills.

13.6 EMPLOYEES PROVIDENT FUNDS: The contractor shall have to

submit a certificate every month that he is an establishment covered under the

Employees Provident Fund and Miscellaneous provisions Act, 1952 and is having a

separate code number with the provident fund commissioner and also that the

provident fund contribution in respect of all the employees employed by him along

with employer's share of contribution etc. is being deposited with the provident fund

Page 123: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-123

authorities and shall also submit certified photo copies of the challans of deposits. In

absence of above, the contractor shall be liable to deposit employees, as well as,

Employer's contribution and other charges in respect of all the employees engaged by

him for the said work with Nigam along with details of the employees, their wages and

the amount of contribution as per Nigam CPF Rules every month. In case of failure,

Nigam shall be entitled to deduct 16% of the amount from his bills.

14.0 FACILITIES TO BE PROVIDED BY THE CONTRACTOR

14.1 Tools, tackles and scaffoldings

The Contractor shall provide all the construction equipments, tools, tackles

and scaffoldings required for pre-assembly, erection, testing and commissioning of

the equipments covered under the Contract. He shall submit a list of all such

materials to the Engineer in Charge (Nodal Officer) before the commencement of

pre-assembly at Site. These tools and tackles shall not be removed from the Site

without the written permission of the Engineer.

14.2 First-Aid

The Contractor shall provide necessary first-aid facilities for all his

employees, representatives and workmen working at the Site. Enough number of

Contractor's personnel shall be trained in administering first- aid.

14.3 Cleanliness

The Contractor shall be responsible for keeping the entire area allotted to him

clean and free from rubbish, debris etc. during the period of Contract. The Contractor

shall employ enough number of special personnel to thoroughly clean his work-area

at least once in a day. All such rubbish and scrap material shall be stacked or

disposed in a place to be identified by the Engineer. Materials and stores shall be so

arranged to permit easy cleaning of the area. In areas where equipment might

drip oil and cause damage to the floor surface, a suitable protective cover of a flame

resistant, oil proof sheet shall be provided to protect the floor from such damage.

Page 124: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-124

15.0 LINES AND GRADES

All the Works shall be performed to the lines, grades and elevations indicated

on the drawings. The Contractor shall be responsible to locate and lay-out the

Works. Basic horizontal and vertical control points will be established and got

verified by the Engineer in Charge (Nodal Officer) at Site at suitable points. These

points shall be used as datum for the works under the Contractor. The Contractor shall

inform the Engineer in Charge (Nodal Officer) well in advance of the times and places at

which he wishes to do work in the area allotted to him so that suitable datum points may

be established and checked by the Engineer in Charge to enable the Contractor to

proceed with his works. Any work done without being properly located may be

removed and/or dismantled by the Engineer in Charge at Contractor's expense.

16.0 FIRE PROTECTION

16.1 The work procedures that are to be used during the erection shall be those

which minimize fire hazards to the extent practicable. Combustible materials,

combustible waste and rubbish shall be collected and removed from the Site at least

once each day. Fuels, oils and volatile or flammable materials shall be stored away

from the construction equipment and materials storage areas in safe containers.

Untreated canvas, paper, plastic or other flammable flexible materials shall not at all be

used at Site for any other purpose unless otherwise specified. If any such materials are

received with the equipment at the Site, the same shall be removed and replaced with

acceptable material before moving into the construction or storage area.

16.2 Similarly corrugated paper fabricated cartons etc. will not be permitted in

the construction area either for storage or for handling of materials. All such materials

used shall be of water proof and flame resistant type. All the other materials such as

working drawings, plans etc. which are combustible but are essential for the works to be

executed shall be protected against combustion resulting from welding sparks, cutting

flames and other similar fire sources.

16.3 All the Contractor's supervisory personnel and sufficient number of workers

shall be trained for fire-fighting and shall be assigned specific fire protection duties.

Enough of such trained personnel must be available at the Site during the entire period of

the Contract.

Page 125: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-125

16.4 The Contractor shall provide enough fire protection equipment of the types

and number for the warehouses, office, temporary structures, labour colony area etc.

Access to such fire protection equipment, shall be easy and kept open at all time.

17.0 SECURITY

The Contractor shall have total responsibility for all equipment and materials

in his custody stores, loose, semi-assembled and/or erected by him at Site. The

Contractor shall make suitable security arrangements including employment of

security personnel to ensure the protection of all materials, equipment and works from

theft, fire, pilferage and any other damages and loss. All materials of the

Contractor shall enter and leave the project Site only with the written permission of the

Engineer in Charge (Nodal Officer) in the prescribed manner.

18.0 CONTRACTOR'S AREA LIMITS

The Engineer in Charge (Nodal Officer) will mark-out the boundary limits of

access roads, parking spaces, storage and construction areas for the Contractor and the

Contractor shall not trespass the areas not so marked out for him. The Contractor shall

be responsible to ensure that none of his personnel move out of the areas marked out for

his operations. In case of such a need for the Contractor's personnel to work out of the

areas marked out for him, the same shall be done only with the written permission of the

Engineer.

19.0 PROTECTION OF MONUMENTS AND REFERENCE POINTS

The Contractor shall ensure that any finds such as relic, antiques, coins,

fossils, etc. which he may come across during the course of performance of his Works

either during excavation or elsewhere, are properly protected and handed over to the

Engineer. Similarly the Contractor shall ensure that the bench marks, reference points,

etc., which are marked either with the help of Engineer in Charge (Nodal Officer) shall

not be disturbed in any way during the performance of his Works. If, any work is to be

performed which disturb such reference, the same shall be done only after these

are transferred to other suitable locations under the direction of the Engineer. The

Contractor shall provide all necessary materials and assistance for such relocation of

reference points etc.

Page 126: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-126

20.0 MATERIALS HANDLING AND STORAGE

20.1 All the equipment furnished under the Contract and arriving at Site shall

be promptly received, unloaded, transported and stored in the storage spaces by the

Contractor.

20.2 Contractor shall be responsible for examining all the shipment and notify the

Engineer in Charge (Nodal Officer) immediately of any damage, shortage, discrepancy,

etc. for the purpose of Engineer's information only. The Contractor shall submit to the

Engineer in Charge (Nodal Officer) every week a report detailing all the receipts during

the week. However, the Contractor shall be solely responsible for any shortages or

damage in transit, handling and/or in storage and erection of the equipment at Site.

Any demurrage, wharfage and other such charges claimed by the transporters, railways

etc. shall be to the account of the Contractor.

20.3 The Contractor shall maintain an accurate and exhaustive record

detailing out the list of all equipment received by him for the purpose of erection and

keep such record open for the inspection of the Engineer-in-Charge.

20.4 All equipment shall be handled very carefully to prevent any damage or

loss. No bare wire ropes, slings, etc. shall be used for unloading and/or handling of

the equipment without the specific written permission of the Engineer. The equipment

stored shall be properly protected to prevent damage either to the equipment or to the

floor where they are stored. The equipment from the store shall be moved to the

actual location at the appropriate time so as to avoid damage of such equipment at Site.

20.5 All electrical panels, control gears, motors and such other devices shall

be properly dried by heating before they are erected and energized. Motor bearings, slip

rings, commutators and other exposed parts shall be protected against moisture ingress

and corrosion during storage and periodically inspected.

20.6 All the electrical equipment such as motors, generators etc. shall be tested for

insulation resistance at least once in three months from the date of receipt, till the date

of commissioning and a record of such measured insulation values maintained by

the Contractor. Such records shall be open for inspection by the Engineer.

Page 127: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-127

20.7 The Contractor shall ensure that all the packing materials and protection

devices used for the various equipments during transit and storage are removed before

the equipment are erected.

20.8 The consumables and other supplies likely to deteriorate due to storage must

be thoroughly protected and stored in a suitable manner to prevent damage or

deterioration in quality during storage.

20.9 All the materials stored in the open or dusty location must be covered

with suitable weatherproof and flameproof covering materials wherever applicable.

20.10 If the materials belonging to the Contractor are stored in areas other than those

earmarked for him, the Engineer in Charge (Nodal Officer) will have the right to get it

moved to the area earmarked for the Contractor, at the Contractor's cost.

20.11 The Contractor shall be responsible for making suitable indoor storage

facilities to store all equipment which require indoor storage. Normally, all the electrical

equipments such as motors, control gear, generators, exciters and consumables like

electrodes, lubricants etc. shall be stored in the closed storage space. The Engineer, in

addition, may direct the Contractor to move certain other materials, which in his opinion

will require indoor storage, to indoor storage areas which the Contractor shall strictly

comply with.

21.0 CONSTRUCTION MANAGEMENT

21.1 The field activities of the various contractors executing different contracts

for the project will be coordinated by the Engineer in Charge (Nodal Officer) and his

decision shall be final in resolving any disputes or conflicts between the Contractor and

other Contractors and tradesmen of the Owner regarding scheduling and coordination

of work. Such decision by the Engineer in Charge (Nodal Officer) shall not be a

cause for extra compensation or extension of time for the Contractor.

21.2 The Engineer in Charge (Nodal Officer) shall hold weekly meetings

of all the Contractors working at Site, at a time and place to be ated by the Engineer.

The Contractor shall attend such meetings and take notes of discussions during the

meeting and the decisions of the Engineer in Charge (Nodal Officer) shall be strictly

adhered to in performing his Works. In addition to the above weekly meeting, the

Engineer in Charge (Nodal Officer) may call for other meeting either with individual

Page 128: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-128

contractors or with selected number of contractors and in such a case the Contractor if

called, will also attend such meetings.

21.3 Time is the essence of the Contract and the Contractor shall be responsible

for performance of his works in accordance with the specified construction schedule. If

at any time, the Contract is falling behind the schedule, he shall take necessary action to

make good for such delays by increasing his work force or by working overtime or

otherwise accelerate the progress of the work to comply with the schedule and shall

communicate such actions in writing to the Engineer, satisfying that his action will

compensate for the delay. The Contractor shall not be allowed any extra

compensation for such action.

21.4 The Engineer in Charge (Nodal Officer) shall however not be responsible

for provision of additional labour and/or materials or supply or any other services to the

Contractor except for the coordination work between various Contractors as set out

earlier.

22.0 FIELD OFFICE RECORDS

The Contractor shall maintain at his Site Office up-to-date copies of all drawings,

Specification and other Contract Documents and any other supplementary data complete

with all the latest revisions thereto. The Contractor shall also maintain in addition the

continuous record of all changes to the above Contract Documents, drawings,

Specification, supplementary data, etc. effected at the field and on completion of his

total assignment under the Contract shall incorporate all such changes on the drawings

and other Engineering data to indicate as erection conditions of the equipment furnished

and erected under the Contract. Such drawings and engineering data shall be

submitted to the Engineer in Charge (Nodal Officer) in required number of copies.

23.0 CONTRACTOR'S MATERIALS BROUGHT TO SITE

23.1 The Contractor shall bring to Site all equipments, components, parts,

materials, including construction equipments, tools and tackles for the purpose of the

Works under intimation to the Engineer. All such goods shall, from the time of their

being brought vest in the Owner, but may be used for the purpose of the Works only and

shall not on any account be removed or taken away by the Contractor without the

Page 129: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-129

written permission of the Engineer. The Contractor shall nevertheless be solely liable

and responsible for any loss or destruction thereof and damage thereto.

23.2 The Owner shall have a lien on such goods for any sum or sums which may

at any time be due or owing to him by the Contractor, under, in respect of or by reasons

of the Contract. After giving a fifteen (15) days notice in writing of his intention

to do so, the Owner shall be at liberty to sell and dispose off any such goods, in

such manner as he shall think fit including public auction or private treaty and to apply

the process in or towards the satisfaction of such sum or sums due as aforesaid.

23.3 After the completion of the Works, the Contractor shall remove from the

Site under the direction of the Engineer in Charge (Nodal Officer) the materials such as

construction equipment, erection tools and tackles, scaffolding etc. with the written

permission of the Engineer. If the Contractor fails to remove such materials,

within fifteen (15) days of issue of a notice by the Engineer in Charge (Nodal Officer) to

do so then the Engineer in Charge (Nodal Officer) shall have the liberty to dispose off

such materials as detailed under Clause 23.2 above and credit the proceeds thereto to the

account of the Contractor.

24.0 PROTECTION OF PROPERTY AND CONTRACTOR'S LIABILITY

24.1 The Contractor shall be responsible for any damage resulting from his

operations. He shall also be responsible for protection of all persons including members

of public and employees of the Owner and the employees of other Contractors and Sub-

contractors and all public and private property including structures, building, other

plants and equipments and utilities either above or below the ground.

24.2 The Contractor will ensure provision of necessary safety equipment

such as barriers, sign-boards, warning lights and alarms, etc. to provide adequate

protection to persons and property. The Contractor shall be responsible to give

reasonable notice to the Engineer in Charge (Nodal Officer) and the owners of public or

private property and utilities when such property and utilities are likely to get damaged

or injured during the performance of his works and shall make all necessary

arrangements with such owners, related to removal and/or replacement or protection of

such property and utilities.

25.0 INSURANCE

In addition to the conditions covered under the Clause entitled "Insurance' in

Page 130: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-130

General Terms and Conditions of Contract of this Volume – I, the following

provisions will also apply to the portion of works to be done beyond the Contractor's

own or his Sub-contractor's manufacturing Works.

25.1 Workmen's Compensation Insurance

This insurance shall protect the Contractor against all claims applicable under

the Workmen's Compensation Act, 1948 (Government of India). This policy shall also

cover the Contractor against claims for injury, disability, disease or death of his or his

Sub-Contractor's employees, which for any reason are not covered

under the Workmen's Compensation Act, 1948. The liabilities shall not be less than :

Workmen's Compensation : As per statutory provisions

Employee's liability : As per statutory provisions

25.2 Comprehensive Automobile Insurance

This insurance shall be in such a form to protect the Contractor against all

claims for injuries, disability, disease and death to members of public including the

Owner's men and damage to the property of others arising from the use of motor vehicles

during on or off the Site operations, irrespective of the ownership of such vehicles.

25.3 Comprehensive General Liability Insurance

25.3.1 The insurance shall protect the Contractor against all claims arising from

injuries, disabilities, disease or death of members of public or damage to property of

others, due to any act or omission on the part of the Contractor, his agents, his

employees, his representatives and Sub-contractors or from riots, strikes and civil

commotion. This insurance shall also cover all the liabilities of the Contractor arising out

of the Clause entitled Defence of Suits under General Terms and Conditions of Contract

of this Volume – I.

25.3.2 The hazards to be covered pertain to all the Works and areas where the

Contractor, his Sub-contractors, his agents and his employees have to perform work

pursuant to the Contract.

Page 131: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-131

25.3.3 The above are only illustrative list of insurance covers normally required and it

will be the responsibility of the Contractor to maintain all necessary insurance coverage

to the extent both in time and amount to take care of all his liabilities either direct or

indirect, in pursuance of the Contract.

26.0 UNFAVOURABLE WORKING CONDITIONS

The Contractor shall confine all his field operations to those works

which can be performed without subjecting the equipment and materials to adverse

effects during inclement weather conditions, like monsoon, storms, etc. and during

other unfavourable construction conditions. No field activities shall be performed by

the Contractor under conditions which might adversely affect the quality and efficiency

thereof, unless special precautions or measures are taken by the Contractor in a proper

and satisfactory manner in the performance of such Works and with the

concurrence of the Engineer. Such unfavorable construction conditions will in no

way relieve the Contractor of his responsibility to perform the Works as per the

schedule.

27.0 WORK & SAFETY REGULATIONS

27.1 The Contractor shall ensure proper safety of all the workmen, materials

plant and equipments belonging to him or to owner or to others, working at the Site. The

Contractor shall also be responsible for provision of all safety notices and safety

equipment required both by the relevant legislations and the Engineer in Charge (Nodal

Officer) as he may deem necessary.

27.2 The Contractor will notify well in advance to the Engineer in Charge

(Nodal Officer) of his intention to bring to the Site any Container filled with liquid

or gaseous fuel or explosive or petroleum substance or such chemicals which may

involve hazards. The Engineer in Charge (Nodal Officer) shall have the right to

prescribe the conditions, under which such container is to be stored, handled and used

during the performance of the works and the Contractor shall strictly adhere to and

comply with such instructions. The Engineer in Charge (Nodal Officer) shall have the

right at his sole discretion to inspect any such container or such construction

plant/equipment for which material in the container is required to be used and if in his

opinion, its use is not safe, he may forbid its use. No claim due to such prohibition shall

Page 132: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-132

be entertained by the Owner and the Owner shall not entertain any claim of the

Contractor towards additional safety provisions/conditions to be provided for/

constructed as per the Engineer's instructions. Further, any such decision of the Engineer

in Charge (Nodal Officer) shall not, in any way, absolve the Contractor of his

responsibilities and in case, use of such a container or entry thereof in to the Site area is

forbidden by the Engineer, the Contractor shall use alternative methods with the

approval of the Engineer in Charge (Nodal Officer) without any cost implication to

owner or extension of work schedule.

27.3 Where it is necessary to provide and/or store petroleum products or

petroleum mixtures and explosives, the Contractor shall be responsible for carrying-out

such provision and/or storage in accordance with the rules and regulations laid down in

Petroleum Act- 1934, Explosives Act-1948, and Petroleum and Carbide of Calcium

Manual published by the Chief Inspector of Explosives of India. All such storage

shall have prior approval of the Engineer. In case, any approvals are necessary from the

Chief Inspector (Explosives) or any statutory authorities, the Contractor shall be

responsible for obtaining the same.

27.4 All equipment used in construction and erection by the Contractor shall

meet Indian/International Standards and where such standards do not exist, the

Contractor shall ensure these to be absolutely safe. All equipments shall be strictly

operated and maintained by the Contractor in accordance with manufacturer's operation

Manual and safety instructions and as per Guidelines/Rules of JdVVNL in this regard.

27.5 Periodical Examinations and all tests for all lifting/hoisting equipment

& tackles shall be carried-out in accordance with the relevant provisions of

Factories Act-1948, Indian Electricity Act-2003 and associated Laws/Rules in force

from time to time. A register of such examinations and tests shall be properly

maintained by the Contractor and will be promptly produced as and when desired by

Engineer in Charge (Nodal Officer) or by the person authorised by him.

27.6 The Contractor shall be fully responsible for the safe storage of his and his

sub-contractor's radio-active sources in accordance with BARC/DAE Rules and other

applicable provisions. All precautionary measures stipulated by BARC/DAE in

Page 133: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-133

connection with use, storage and handling of such material shall be taken care by

Contractor.

27.7 The Contractor shall provide suitable safety equipment of prescribed

standard to all employees and workmen according to the need, as may be directed by

Engineer in Charge (Nodal Officer) who will also have right to examine these safety

equipments to determine their suitability, reliability, acceptability and adaptability.

27.8 Where explosives are to be used, the same shall be used under the direct

control and supervision of an expert, experienced, qualified and competent person

strictly in accordance with the Code of Practices/Rules framed under Indian Explosives

Act pertaining to handling, storage and use or explosives.

27.9 The Contractor shall provide safe working conditions to all workmen

and employees at the Site including safe means of access, railings, stairs, ladders,

scaffoldings etc. The scaffoldings shall be erected under the control and supervision of

an experienced and competent person. For erection, good and standard quality of

material only shall be used by the Contractor.

27.10 The Contractor shall not interfere or disturb electricity fuses, wiring and

other electrical equipment belonging to the Owner or other contractors under any

circumstances, whatsoever, unless expressly permitted in writing by Engineer in Charge

(Nodal Officer) or his authorised representative to handle such electrical equipment.

27.11 Before the Contractor connects any electrical appliances to any plug or socket

belonging to the other Contractor or Owner, he shall:

a) Satisfy the Engineer in Charge (Nodal Officer) that the appliance is in good working

condition.

b) Inform the Engineer in Charge (Nodal Officer) of the maximum current rating,

voltage and phases of the appliances.

c) Obtain permission of the Engineer in Charge (Nodal Officer)

detailing the sockets to which the appliances may be connected.

Page 134: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-134

27.12 The Engineer in Charge (Nodal Officer) will not grant permission to connect

electric load until he is satisfied that;

a) The appliance is in good condition and is fitted with suitable plug.

b) The appliance is fitted with a suitable cable having two earth conductors one of

which shall be an earthed metal sheath surrounding the cores.

27.13 No electric cable in use by the Contractor/Owner will be disturbed with

out prior permission. No weight of any description will be imposed on any cable and

no ladder or similar equipment will rest against or attached to it.

27.14 No repair work shall be carried out on any live equipment. The equipment

must be declared safe by the Engineer in Charge (Nodal Officer) and a permit to work

shall be issued by the Engineer in Charge (Nodal Officer) or his authorized

representative before any repair work is carried out by the Contractor. While

working on electric lines/equipments whether live or dead, suitable type and sufficient

quality of tools will have to be provided by Contractor to electricians/workmen/officers.

27.15 The Contractors shall employ necessary number of qualified, full time

Electricians/Electrical Supervisors to maintain his temporary electrical installations /

erections site.

27.16 The Contractor employing more than 250 workmen whether temporary,

casual, probationer, regular or permanent or on contract, shall employ atleast one full

time officer exclusively as Safety Officer to supervise safety aspects of the equipments

and workmen, who will coordinate with the Project Safety Officer. In case of work

being carried out through Sub-contractors, the Sub-contractor's workmen/employees will

also be considered as the Contractor's Employees/workmen for the above purpose. The

name and address of such Safety Officer of Contractor will be promptly informed in

writing to Engineer in Charge (Nodal Officer) with a copy to Safety Officer- in-charge

before he starts work or immediately after any change of the incumbent is made during

currency of the Contract.

27.17 In case of any accident during the construction/erection or other

associated activities undertaken by the Contractor thereby causing any minor or major or

fatal injury to his employees due to any reason whatsoever, it shall be the responsibility

Page 135: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-135

of the Contractor to promptly inform the same to the Engineer in Charge (Nodal

Officer) in prescribed form and also to all the authorities envisaged under the applicable

laws.

27.18 The Engineer in Charge (Nodal Officer) shall have the right at his sole

discretion to stop the work, if in his opinion the work is being carried out in such a way

that it may cause accidents and endanger the safety of the persons and/or property,

and/or equipments. In such cases, the Contractor shall be informed in writing about the

nature of hazards and possible injury/accident and he shall comply to remove

shortcomings promptly.The Contractor after stopping the specific work can, if felt

necessary appeal against the order of stoppage of work to the Engineer in Charge

(Nodal Officer) within 3 days of such stoppage of work and decision of the Engineer in

Charge (Nodal Officer) in this respect shall be conclusive and binding on the Contractor.

27.19 The Contractor shall not be entitled for any

damages / compensation for stoppage of work due to safety reasons as provided in para

27.18 above and the period of such stoppage of work will not be taken as an extension of

time for completion of work and will not be the ground for waiver of levy of liquidated

damages.

27.20 It is mandatory for the Contractor to observe during the execution of the

works requirements of safety rules which would generally include but not limited to

following :

27.21 The Earth Resistance is to be maintained as required under Electricity act/

Rules for transformer and line earthing.

27.22 For line (HT single phase) earthing , the earth wire provided in the pole is to

be connected at top to all steel part and at bottom to be connected to earthing provided

with Welding and Nut Bolting

Page 136: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-136

Safety Rules

Each employee shall be provided with initial instruction regarding safety by the

Contractor, so as to enable him to conduct his work in a safe manner.

a) No employee shall be given a new assignment of work unfamiliar to him

without proper introduction as to the hazards incident thereto, both to himself and his

fellow employees.

b) Under no circumstances shall an employee hurry or take unnecessary chance

when working under hazardous conditions.

c) Employees must not leave naked fires unattended. Smoking shall not be

permitted around fire prone areas and adequate fire fighting equipment shall be provided

at crucial locations.

d) Employees under the influence of any intoxicating beverage, even to the slightest

degree shall not be permitted to remain at work.

e) There shall be a suitable arrangement at every work site for rendering prompt

and sufficient first aid to the injured.

f) The staircases and passageways shall be adequately lighted.

g) The employees when working around moving machinery must not be permitted to

wear loose garments. Safety shoes are recommended when working in shops or places

where materials or tools are likely to fall. Only experienced workers shall be

permitted to go behind guard rails or to clean around energized or moving equipment.

h) The employees must use the standard protection equipment intended for each job.

Each piece of equipment shall be inspected before and after it is used.

i) Requirements of ventilation in underwater working to licensed and experienced

divers, use of gum boots for working in slushy or in undated conditions are essential

requirements to be fulfilled.

Page 137: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-137

j) In cases or rock excavation blasting shall invariably be done through licensed

blasters and other precautions during blasting and storage / transport of charge material

shall be observed strictly.

27.23 The Contractor shall follow and comply with all Safety Rules, relevant provisions

of applicable laws pertaining to the safety of workmen, employees plant and equipment

as may be prescribed from time to time without any demur, protest or contest or

reservation. In case of any in conformity between statutory requirement and Safety rules

referred above, the later shall be binding on the Contractor unless the statutory

provisions are more stringent.

27.24 If the Contractor fails in providing safe working environment as per Safety Rules

or continues the work even being instructed to stop work by the Engineer in Charge

(Nodal Officer) as provided in para 27.18 above, the Contractor shall promptly pay to

JdVVNL, on demand by the Owner compensation at the rate of Rs. 5,000/- per day or

part thereof till the instructions are complied with and so certified by the Engineer.

However, in case of accident taking place-causing injury to any individual, the

provisions contained in para 27.23 shall also apply in addition to compensation

mentioned in this para.

27.25 If the Contractor does not take all safely precautions and/or fails to comply with

the Safety Rules as prescribed by owner or under the applicable law for the safety of

the equipment and plant and for the safety to personnel and the Contractor does not

prevent hazardous conditions which cause injury to his own employees or employees of

other contractors, or Jd.VVNL employees or any other person who are at Site or

adjacent thereto, the Contractor shall be responsible for payment of compensation to

owner as per the following schedule :-

Page 138: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-138

a) Fatal injury or

accident

causing death

As per

Nigam

norms

:

These are

applicable for

death / injury to

any person

whosoever

b) Major injuries or

accident causing

25% or more

permanent

disablement to

workmen or

employees

As per

Nigam

norms

:

Permanent disablement shall have same meaning as indicated in Workmen's

Compensation Act. The compensation mentioned above shall be in addition to the

compensation payable to the workmen/employees under the relevant provisions of

the Workmen's Compensation Act and rules framed there under or any other

applicable laws as applicable from time to time. In case the Owner is made to pay such

Compensation, then the Contractor is liable to reimburse the Owner such amount in

addition to the compensation indicated above.

27.26 If the Contractor observes all the Safety Rules and Codes, Statutory

Laws and Rules during the currency of Contract awarded by the Owner and no accident

occurs then Nigam may consider the performance of the Contractor and award suitable

"ACCIDENT FREE SAFETY MERITORIOUS AWARD" as per scheme as may be

announced separately from time to time.

28.0 EXAMINATION OF WORK BEFORE COVERING UP

28.1 No work shall be covered up or put out of view without the approval

of the engineer or the Engineer’s representative and the contractor shall afford

full opportunity for the Engineer or the Engineer’s representative to examine and

measure any work which is about to be covered up or put out of view and to examine

foundations before permanent work is placed thereon. The contractor shall give due

notice to the Engineer’s representative whenever any such work or foundation is or

Page 139: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-139

are ready or about to be ready for examination and the Engineer’s representative shall

without delay advise the contractor accordingly, attend for the purpose of examining and

measuring such work or of examining such foundations.

28.2 Uncovering and Making Openings The contractor shall uncover any part or

parts of the works or make openings in or through the same as the Engineer may from

time to time direct and shall reinstate and make good such part or parts to the satisfaction

of the Engineer. If any such part or parts have been covered up or put out of view

after compliance of clause 28.1 above, and are found to be executed in accordance with

the contract, the expenses of covering , making openings in or through reinstating and

making good of the same shall be borne by the owner, but in all other cases, these costs

shall be borne by the contractor.

29.0 REMOVAL OF IMPROPER WORK AND MATERIALS

The Engineer/Engineer’s representative shall during the progress of the works have

the power to order in writing from time to time

a) The removal from the site within such time or times as may be specified in the

order of any materials which in their opinion are not in accordance with the contract.

b) The substitution of proper and suitable material and

c) The removal and proper re-execution, notwithstanding any previous tests

thereof or interim payment therefore, of any work which in respect of materials or

workmanship is not accordance with the contract.

In case of default on the part of the contractor in carrying out such an order, the

Owner shall be entitled to employ and pay other persons to carry out the same and all

expenses consequent thereon or incidental thereto shall be recoverable from the

contractor by the Owner or may be deducted by the Owner from any amount due

or which may become due to the contractor.

30.0 SETTING OUT OF WORKS:

The contractor shall be responsible for the true and proper setting out of the

works in relation to the original points, lines and levels of reference given by the Engineer

in writing and for the correctness, subject as mentioned above of the position, levels,

Page 140: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-140

dimensions, and alignment of all parts of the works and for the provision of all necessary

instruments, appliances and labour in connection therewith. If, at any time during the

progress of the works, any error shall appear or arise in the position levels, dimensions, or

alignment of any part of the works, the contractor on being required by the Engineer, shall

at his own cost, rectify such error to the satisfaction of the Engineer unless such error is

based on incorrect data supplied in writing by the Engineer, in which case the expense of

rectifying the same shall be borne by the owner. The checking or setting out of or any line

or level by the Engineer shall not in any way relieve the contractor of his responsibility

for the correctness thereof and the contractor shall carefully protect and preserve all

bench-marks, sight rails, pegs and such other thing used in the setting out of the works.

31.0 MINOR ACCESSORIES FOR COMPLETION OF WORKS:

Contractor shall supply all minor accessories required for the completion of

supply which have not indicated in specification or in purchase order.

Page 141: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-141

SECTION-III PART-IB

ERECTION CONDITIONS OF CONTRACT (ECC)- TECHNICAL

REQUIREMENT

1.0 SCOPE OF WORK:

1.1 The contractor’s scope of work includes but not limited to: Survey, network

design, supply, manufacturer’s quality assurance, testing, transportation, storage, erection

(including all civil /structural works), site testing, commissioning of all items &

materials, including all associated activities that though not exclusively specified here in

but are required for the completion of the entire works under this package.

1.2 The Bidder shall execute the above Action Plan works on TOTAL TURN-

KEY BASIS, which involves broadly the supply, transportation to works site, erection,

assembly, testing and commissioning of the lines & equipment and returning the

retrieved materials to concerned Nigam stores.

1.3 The details of equipment to be supplied, transported, erected, assembled,

tested & commissioned are indicated in schedule of Works. The quantities indicated in

the Schedule of Works are only approximate and may increase or decrease and prices

quoted by the bidder are deemed to be valid in spite of such variations in the quantities at

the time of award of contract.

1.4 Any other items not specifically mentioned but which are essentially required

for satisfactory performance & completeness of work, shall be deemed to be included in

the scope of specifications and works and the same shall be executed / carried out by the

bidder at no extra cost to the Nigam.

1.5 Name of feeder, distribution box No. and Consumer identification numbers

are to be marked with indelible paint on the pillar boxes and distribution boxes as

required by the concerned AEN of the Sub- Division.

2.0 CONTRACTOR RESPONSIBILITY:

2.1 All equipment / materials shall be submitted for inspection by a duly

authorized representative of the Engineer-in-charge. Inspection may be made at any stage

of manufacture, dispatch or at site or at these places at the option of the Engineer-in-

charge and the equipment dispatched / about to be dispatched, if found unsatisfactory as

to workmanship or quality, the same is liable to be rejected. The successful bidder /

Page 142: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-142

Contractor shall grant free access to the places of manufacture to the authorized

representative of the Engineer-in-charge at all times when the works related to the

manufacture are in progress.

2.2 The Contractor is fully responsible for the Equipment / Material until the same

is handed over to the NIGAM in an operating condition after commissioning. The

Contractor is responsible for the proper maintenance of equipment / material as well as

protection of the same against theft, elements of nature, damages etc., while in his

custody as well as after erection until the same is taken over by the NIGAM under due

acknowledgment in writing.

2.3 The entire works to be executed under this contract will be in stages &

requires obtaining Line Clear Permits from the Engineer-in-charges representative or his

subordinate before taking up the works by the Contractor. As such the Contractor shall

take all mandatory safety precautions for executing the works & shall obtain line clear

permits with the Operational Authorities of the area prior to commencement of works on

daily basis.

2.4 Similar parts of any equipment supplied shall be inter changeable. Danger /

Caution Boards shall be provided on Pillar & Distribution boxes.

2.5 The contractor is to supply and erect all requisite material for above works

except mentioned herein which shall be provided by the Nigam. No payment shall be

made to the contractor for the items provided by the Nigam.

3.0 GENERAL INFORMATION:-

3.1 WAY LEAVE, AND OTHER OBSTRUCTIONS:

3.1.1 The contractor will arrange for way leave proposals for carrying out the work

& the proposals are to be submitted by the contractor well in time. It will also be

necessary on the part of contractor to instruct his workers and staff to work in a manner

so that no damage of the existing underground systems of other public utility systems

shall take place.

Page 143: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-143

3.1.2 However in case, if any damage happens to be there, the responsibility of

repair of such damages shall be in the scope of contractor.

3.1.3 The contractor should immediately notify any obstructions or hindrance from

households or the local authorities in the execution of the work, to the concerned

Engineer / In-charge but should not deal directly in the matter. The Engineer / in-charge

will arrange to remove the obstacles as soon as possible.

3.1.4 For the clearance, permissions, removal of obstructions in way leave, etc. the

contractor shall not remain contended by simply informing the Nigam but shall

invariably assist and arrange for personal follow up to overcome the difficulties in the

interest of progress of the work.

3.1.5 The project may involve some obstacles from the public. In such a situation

the position should be brought out in knowledge of the Nodal officer / Engineer In-

charge of the project, for making a spot solution of the situation.

3.2 ACCESS TO LOCATION:

3.2.1 It will be the contractor’s sole responsibility to take the material up to the

location from the ACOS / store and shall have to arrange transportation at his cost.

3.2.2 The contractor will be deemed to be very well familiar with the work to be

executed before giving the offer. Notwithstanding, the difficulties of terrain, location

approaches, way leave and other obstructions the price quoted for all the items with

erection & commissioning & commissioning charges shall not undergo any change at

any stage of work including the time limit extension.

3.3 TESTING AND COMMISSIONING:

After completion of the work, as mentioned in clause no 1.0 scope, the contractor will

ensure that all works connected with the line have been completed correctly as per Indian

Electricity Rules and procedure. Any extra cost involved due to incompleteness of work

or bad workmanship found but subsequently, shall be set right forthwith by the

Contractor at his cost. The contractor shall arrange to handover the complete line.

Page 144: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-144

3.4 SHUT DOWN OF EXISTING LINES:

The contractor or his authorized representative shall intimate in advance along-

with complete programme of erection & commissioning where ever shunt down of

existing line is required, to the Nodal officer / Engineer In-charge of the site for

arranging shut downs. The contractor shall have to plan the work in such a way that in

minimum duration of shut down maximum work is carried out to avoid repeated and / or

longer duration shut downs.

3.5 Reference Standards:

The material to be utilized in execution of tendered / ordered works on turnkey

basis shall confirm to the Indian Standards (IS) which shall mean latest revisions,

Amendments / changes and published unless otherwise specified herein

Further, applicable standards are also mentioned under Technical Specification of the

each item in SECTION-III-PART-III: TECHNICAL SPECIFICATION.

4.0 GENERAL TECHNICAL CONDITIONS:

The following provisions shall supplement all the detailed technical Specification and

requirements. The Bidder’s proposal shall be based on the use of equipment and

materials complying fully with the requirements, specified herein.

4.1 The Bidder shall furnish clause – by – clause commentary (with detailed

technical data as required) on the Technical Specification demonstrating the goods

substantial responsiveness to the Specification or deviation and exceptions to the

provisions of the Technical Specification unless and until advised contrary to this in the

bidding document.

5.0 Equipment Performance Guarantee:

5.1 The performance requirements of the items are detailed separately in this

Specification. These guarantees shall supplement the general performance guarantee

provisions covered under General Conditions of Contract in clause entitled “Guarantee”.

5.2 Liquidated damages for not meeting specified performance shall be assessed

and recovered from the Contractor. Such liquidated damages shall be without any

Page 145: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-145

limitation whatsoever and shall be in addition to damages, if any payable under any other

clause of Conditions of Contract.

5.3 Engineering Data

5.3.1 The furnishing of engineering data by the Contractor shall be in accordance

with the appropriate Schedule appended to this document. The review of these data by

the Owner will cover only general conformance of the data to the Specification and

drawings. This review by the Owner may not indicate a thorough review of all

dimensions, quantities and details of the equipment, materials, any devices or items

indicated or the accuracy of the information submitted. This review and / or approval by

the Owner shall not be considered by the Contractor, as limiting any of his

responsibilities and liabilities for mistakes and deviations from the requirements,

specified under these Specification and documents.

5.3.2 All engineering data submitted by the Contractor after final process including

review and approval by the Owner shall form part of the Contract Document and the

entire works performed under this Specification shall be performed in strict conformity,

unless otherwise expressly requested by the owner in writing.

5.4 Drawings

5.4.1 All drawings submitted by the Contractor including those submitted at the

time of bid shall be in sufficient detail to indicate the type, size, arrangement,

dimensions, material description, Bill of Materials, weight of each component, break-up

for packing and shipment, required fixing arrangement, the required dimensions for

installation and any other information specifically requested in the Specification.

5.4.2 Each drawing submitted by the Contractor shall be clearly marked with the

name of the Purchaser, the unit designation, the Specification title, the Specification

number and the name of the Project. All titles, noting, markings and in writings on the

drawing shall be in English. All the dimensions should be to the scale and in metric units.

5.4.3 The drawings submitted by the Contractor shall be reviewed by the Owner as

far as practicable within one (1) week and shall be modified by the Contractor if any

modifications and / or corrections are required by the Owner in compliance with the

Page 146: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-146

Specification. The Contractor shall incorporate such modifications and or corrections and

submit the final drawings for approval. Any delays arising out of failure by the

Contractor to rectify the drawings in good time shall not alter the completion date.

5.4.4 The drawings submitted for approval to the Owner shall be in quadruplicate.

One print of such drawings shall be returned to the Contractor by the Owner marked

“approved / approved with corrections”. The Contractor shall thereupon furnish the

Owner additional print as stipulated in Technical Specification along with one

reproducible in original of the drawings after incorporating all corrections.

5.4.5 Further work by the Contractor shall be strictly in accordance with these

drawings and no deviation shall be permitted without the written approval of the

Purchaser, if so required.

5.4.6 All manufacturing and fabrication work in connection with the equipment /

material prior to the approval of the drawings shall be at the Contractor’s risk. The

Contractor may make any changes in the design which are necessary to make the

equipment conform to the provisions and intent of the Contract and such changes will

again be subject to approval by the Owner. Approval of Contractor’s drawing or work by

the Owner shall not relieve the Contractor of any of his responsibilities and liabilities

under the Contract.

5.4.7 All rights of the design / drawing shall be strictly reserved with the Owner

only and any designs / drawings / data sheets submitted by the contractor from time to

time shall become the property of the Owner. Under no circumstances, the Contractor

shall be allowed to use / offer above designs / drawings / data sheets to any other

authority without prior written permission of the Owner. Any deviation to above is not

acceptable and may be a cause of rejection of the bid.

5.5 Quality Assurance

To ensure that the equipment under the scope of this Contract whether

manufactured within the Contractor’s Works or at his Sub-Contractor’s premises is in

accordance with the Specification, the Contractor shall adopt suitable Quality Assurance

Programme to control such activities at all points necessary.

Page 147: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-147

A Quality Assurance Programme of the Contractor shall generally cover but not limited

to the following.

a) His organization structure for the management and implementation of the proposed

Quality Assurance Programme.

b) Documentation control system.

c) Qualification data for key personnel;

d) The procedure for purchases of materials. Parts/ components and selection of sub-

Contractor’s services including vendor analysis, source inspection, incoming raw

material inspection, verification of material purchases etc.

e) System for shop manufacturing including process controls.

f) Control of non-conforming items and system for corrective action.

g) Control of calibration and testing of measuring and testing equipments.

h) Inspection and test procedure for manufacture.

i) System for indication and appraisal of inspection status.

j) System for quality audits.

k) System for authorizing release of manufactured product to the Purchaser.

l) System for maintenance of records.

m) System for handling storage and delivery and

A Quality Plan detailing out the specific quality control procedure adopted for

controlling the quality characteristics of the product.

The Quality Plan shall be mutually discussed and approved by the Owner after

incorporating necessary corrections by the Contractor as may be required.

5.6 Quality Assurance Documents

5.6.1 The Contractor shall be required to submit all the Quality Assurance

Documents as stipulated in the Quality Plan at the time of Owner’s inspection of

equipment / material.

The owner or his duly authorized representatives reserves the right to carry out Quality

Audit and Quality surveillance of the systems and procedures of the Contractor’s / his

vendor’s Quality Management and Control Activities.

Page 148: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-148

5.7 Owner’s Supervision

5.7.1 To eliminate delays and avoid disputes and litigation it is agreed between the

parties to the Contract that all matters and questions shall be resolved in accordance with

the provisions of this document.

5.7.2 The manufacturing of the product shall be carried out in accordance with the

approved design & bill of Material furnished by the Contractor. However this approval

does not relieve the responsibility of contractor for safe & efficient working of the

equipments.

5.7.3 Interpretation of all the terms and conditions of these Documents and

Specification.

5.7.4 Review and interpretation of all the Contractor’s drawings, engineering data

etc.

5.7.5 Witness or authorize his representative to witness tests at the manufacturer’s

works or at site, or at any place where work is performed under the Contract.

5.7.6 Inspect, accept or reject any equipment, material and work under the Contract,

in accordance with the Specification / approved drawing & workmanship.

5.7.7 Review and suggest modification and improvement in completion schedules

from time to time; and Supervise the Quality Assurance Programme implementation at

all stages of the Works.

6.0 TESTS AND STANDARDS:

6.1 Tests: The type, acceptance and routine tests and tests during manufacture

shall be carried-out on the material as per the relevant standards.

6.1.1 The bidders shall furnish original / Photostat copies of the latest type test

certificates from any NABL accredited / Govt. laboratory for all the type tests

where ever prescribed in the relevant ISS / specification along with the bid for all

the items.

Page 149: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-149

6.1.1.1 Type Tests shall mean those tests, which are to be carried out to prove the

process of manufacture and general conformity of the material to this Specification. The

type test certificates furnished by the bidder should not be older than three years; in

that case no fresh type test shall be insisted upon. In case if the type tests are older than

Five Years, the contractor has to arrange fresh type test at his cost and no extra time shall

be allowed for arranging the type tests.

6.1.2 Acceptance Tests shall mean those tests, which are to be carried out on

samples taken from each lot offered for pre-dispatch inspection, for the purposes of

acceptance of that lot. These tests are to be conducted in the presence of owner’s

representative.

6.1.3 Routine Tests shall mean those tests, which are to be carried out on the

material to check requirements, which are likely to vary during production.

6.1.4 Tests during Manufacture shall mean those tests, which are to be carried out

during the process of manufacture and end inspection by the Contractor to ensure the

desired quality of the end product to be supplied by him.

6.1.5 The norms and procedure of sampling for these tests will be as per relevant

standards / specification wherever, sampling plan and procedure is not defined, the

procedure/practice adopted in MM wing of Nigam shall be followed.

6.1.6 For all type and acceptance tests, the acceptance values shall be the values

specified in this Specification.

6.2 Additional Tests:

6.2.1 The Owner reserves the right of having at his own expenses any other test(s)

of reasonable nature carried out at contractor’s premises, at site, or in any other place in

addition to the specified type, acceptance and routine tests to satisfy himself that the

materials / equipment comply with the Specification.

6.2.2 The Owner also reserves the right to conduct all the tests mentioned in the

specification at his own expense on the samples drawn from the site at Contractor’s

Page 150: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-150

premises or at any other test center. In case of evidence of non compliance, it shall be

binding on the part of contractor to prove the compliance of the items to the technical

Specification by repeat tests, or correction of deficiencies, or replacement of defective

item all without any extra cost to the Owner.

6.3 MANDATORY TEST CHECKING OF MATERIAL ON RECEIPT IN

THE STORES:

(i) NO Material shall be allowed to use against the awarded works without

successful testing as per provisions of Technical Specifications laid down under

Section-III,Part-III for which testing facility is available at Nigam`s CTL Lab,

Jodhpur. The due payment against supplies & erection, whenever it falls due,

shall be released only after receipt of successful test reports for the samples selected

at stores by the NODAL OFFICER or the nominated officers of the Nigam.

(ii) It is further clarified that the Samples from the material received in stores

shall be selected by the Nodal/Nominated officer within a period of 3 days and the

same shall be tested within a weeks’ time in the CTL thereafter.

7.0 GUARANTEED TECHNICAL PARTICULARS:

7.1 The Guaranteed Technical Particulars of the various items shall be confirming

to requirement of relevant Standard & the specification. The bidder shall furnish the

Guaranteed Technical Particulars of various items as required for this work failing which

the bid shall be rejected. The Bidder shall also furnish any other schedule / information

as in their opinion is needed to give full description and details to judge the item(s)

offered by them.

8.0 TYPE, DESIGN AND PARTICULARS OF MATERIAL:-

8.1. General Requirement:

8.1.1 All materials required in completing the work as per this Specification &

drawings / design approved by the Nigam etc. must be manufactured and supplied using

fresh raw materials. Re-molded, re–circulated materials are not acceptable to Nigam.

The procurement of materials must be made by the contractor directly from such

manufacturers or through their authorized dealers / distributors. Documentary

evidences to this effect are to be made available to Nigam for necessary checks /

verification of source of supply of materials. Second hand materials / partially used

Page 151: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-151

materials / used materials are not acceptable. The contractor / bidder are required to

indicate the names & address of the manufactures of various items from which he

proposes to buy the same.

8.1.2 Further, the work shall be carried out strictly as per prevailing norms design,

drawing, technical specifications, practice adopted in the Nigam for the same nature of

work. Whether mentioned or not, all the items included in the tentative list of material

shall conform to latest technical specifications adopted by MM wing of the Nigam and

latest relevant IS/IEC / B.S. / NFC or any other code as prescribed by the Nigam for its

works. In case any dispute arises, the current specifications, practice, norms, approved

design and drawings of Nigam shall prevail.

8.1.3 PROCUREMENT FROM MANUFACTURERS / VENDORS:

The Contractor shall be permitted to procure materials from the manufactures / vendors

who have following qualified requirements:

(i) The vendor should be a established / reputed manufacture / supplier who should have

supplied the material to erstwhile RSEB or any present distribution company, RVVPNL

or any other power utility and the contractor / bidder are required to indicate the names &

address of the manufactures of various items from which he proposes to buy the same.

(ii)The manufacturing units shall have all facilities for conducting acceptance & routine

tests of equipment / materials.

(iii) The vendor must have supplied materials as per specifications laid down in the

bid- documents of erstwhile RSEB / NIGAMS and have arranged their type testing not

before last Five Years,

(iv) The vendors approvals shall be obtained for supply of the equipment /

materials from the Engineer well in advance.

8.1.4 ASSIGNMENT AND SUB-LETTING OF CONTRACT:

The Contractor may, after informing the engineer and getting his written

approval assign or sublet the contract or any part thereof other than for raw materials, for

minor details of any part of the plant for which makes are identified in the contract.

Page 152: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-152

Suppliers of the equipment not identified in the contract or any change in the identified

supplier shall be subject to approval by the engineer. The experience list of the

equipment vendors under consideration by the contractor for this contract shall be

furnished to the engineer for approval prior to procurement of all such items /

equipments. Such assignment / sub letting shall not relieve the contractor from any

obligation, duty of responsibility under the contract. Any assignment as above without

prior written approval of Engineer shall be void.

For components / equipments procured by the Contractors for the purposes of the

Contract, after obtaining the written approval of the owner, the contractor’s purchase

specifications and enquiries shall call for quality plans to be submitted by the suppliers

along with their proposals. The quality plans called for from the vendors shall set out,

during the various stages of manufacture and installation, the quality practices and

procedures followed by the vendors quality control organization, the relevant reference

documents / standards used, acceptance level, inspection documentation raised, etc. such

quality plans of the successful vendor shall be discussed and finalized in consultation

with the engineer and shall form a part of the work order / contractor between the

contractor and the vendor. Within 3 weeks of the release of the same work order /

contracts for such bought out terms / components a copy of the same without price

details but together with detailed specifications, quality plans and delivery conditions

shall be furnished to the engineer by the contractor.

9.0 JOINT SURVEY:-

9.1 The bidders are presumed to have acquainted themselves with the scope

of work of this specification by doing a walk over survey of the area/feeder before

submitting their bid. The quantum of works indicated in ‘G’ Schedule is tentative.

After award of contract, a detailed survey shall however, required to be done by the

contractor along with Nigam’s authorized Engineer to assess actual quantum of

work. The contractor shall have to execute the works in accordance with the

quantities so assessed and approved by the Nigam. Further the contractor is also to

carry out the detailed survey of individual work as per work order placed on them,

to finalize route / marking of the lines, pole spotting, Sub-stations & its associated

equipments for various locations and other activities.

Page 153: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-153

9.2 Successful bidder shall carry out the joint survey and submit the

inception report for approval of final BOQ in respect of supply , erection &

retrieval of material duly signed by contractors representative & Nigam officer. He

shall also prepare the route of, 33 KV, 11 KV, LT lines, location of distribution

transformer on the town/city map. The final route map of 33 KV,11 KV & LT lines

shall be prepared and submitted by the bidder showing the proposed pole position,

ground clearance, conductor sag and various crossings i.e. railway lines,

communication lines, EHT lines, rivers, road and stream crossings on the map.

9.3 At the time of submission of joint survey report, necessary proposal for forest,

railway, highway and river crossing be submitted within the commencement period ,

otherwise delay in submission shall be on the part of contractor. However, wherever

such approvals are required from the concerned authorities the delay in receipt of

approval from the date of submission of proposal by contractor through Engineer In-

charge (To the statuary agency) shall not be on the part of contractor.

9.4 The road restoration charges wherever applicable shall be reimbursed by the

Nigam on actual basis against the documentary proof of having deposited the same with

the respective civic authority through the invoice submitted for road restoration charges

actually paid to civic authority along with receipt. However, the contractor has to submit

the estimate against road cut restoration charges issued by local civic agency to Nodal

Officer of NIGAM for pre-examination / verification for according prior approval and

only after approval these charges are to be deposited by the contractor with the respective

local civic authority which shall be reimbursed by the NIGAM on the production of

documentary proof having deposited the charges on actual basis. The permission for any

required road cut is also to be arranged by the bidder/Contractor from the concerned

civic agency. All assistance for coordinating in this regard will be provided by the Nigam

9.5 Check Survey of Pole Locations:

The check survey has to be conducted by the contractor to locate and peg marks

pole positions on ground confirming to the approved profile and pole schedule. The

Changes, if required, after detailed survey in the preliminary pole schedule shall be

carried out by the Contractor and he shall thereafter submit a final pole schedule for the

approval of employer (PM). The pole schedule shall show position of all Poles, type of

Poles, span length, type of foundation for each pole and the deviation at all angles as set

Page 154: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-154

out with other details.

(i) Details En-route: - All topographical permanent features, such as trees,

telecommunication lines, buildings etc, 5.5 meter on either side of the alignment shall be

detailed on the route plan.

(ii) Clearance from ground building, trees etc.:- Clearance from ground buildings,

trees and telephones lines shall be provided in conformity with the Electricity Act, 2003,

as amended up to date. The bidder shall select the height of the poles such that all the

electrical clearances are maintained.

(iii) The minimum planting depth of poles shall be governed by IS: 1678,

However, if due to the ground conditions e.g. water logged area etc. depth of planting of

poles shall be suitably increased, with appropriate extension arrangement in order to

maintain the required clearances the vendor will submit the details of the same on case to

case basis.

(iv) Appropriate Guarding arrangement shall be used for crossings of electric line /

telecom line / road / drain / canal crossing and at all points as per statutory requirements.

The bidder shall provide install anti climbing devise and danger plates on all poles and

DT stations.

10.0 WORK PLAN:

After completing the work of survey, the contractor shall finalize the programme

to commence and execute the work. The contractor shall also take care of the under

mentioned points in construction of various lines.

10.1 Span

The number of consecutive spans between the section points and average span

shall be as per relevant standard / instructions of engineer at site.

10.2 Road Crossing

At all important road crossings, the structure shall be fitted with Strain type insulators

but the ground clearance at the roads under maximum temperature and in still air shall be

such that even with conductor broken in adjacent span, ground clearance of the

conductor from the road surfaces will be as per Indian Electricity Rules.

Page 155: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-155

10.3 Railway Crossings

At the time of route survey, the railway crossings shall be finalized as per the

regulation laid down by the Railway Authorities. The approval for crossing railway track

shall be obtained by the Nigam from the Railway Authority. At the time of submission of

joint survey report, necessary proposal for railway crossing be submitted within the

commencement period , otherwise delay in submission shall be on the part of

contractor. However, wherever such approvals are required from the concerned

authorities the delay in receipt of approval from the date of submission of proposal by

contractor through Engineer In-charge (To the statuary agency) shall not be on the part of

contractor.

10.4 Forest Clearance

The forest clearance shall be obtained by the Nigam and same shall be conveyed to the

contractor before due date of commencement of the work. Delay in forest clearance after

the due date of commencement if any, shall not be counted towards delay in execution.

At the time of submission of joint survey report, necessary proposal for Forest

Clearance be submitted within the commencement period , otherwise delay in

submission shall be on the part of contractor. However, wherever such approvals are

required from the concerned authorities the delay in receipt of approval from the date of

submission of proposal by contractor through Engineer In-charge (To the statuary

agency) shall not be on the part of contractor.

10.5 Clearance from Electrical inspector:

Construction of the line shall be done so as to meet the requirements of Indian

Electricity Act / Indian Electricity Rules 1956 as amended from time to time. Necessary

clearance from the Electrical inspector, Govt. of Rajasthan shall be obtained by the

contractor before handing over the line to the Nigam. The necessary clearance fee paid

by the contractor shall be reimbursed by Nigam. In case some defects / observations are

pointed out & subsequent fee if any required to be paid shall not be reimbursed.

10.6 Power Line Crossings:

Where this line is to cross over another line of the same voltage or lower voltage,

provisions to prevent the possibility of its coming into contact with other overhead lines

shall be made in accordance with the Indian Electricity Rules, 1956 as amended from

Page 156: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-156

time to time. All the works related to the above proposal shall be deemed to be included

in the scope of the Contract except if modifications are required, in which case, the

conditions to be agreed upon.

10.7 Tele-communication Line Crossing:

The angle of crossing shall be as near to 90 degree as possible. However, deviation to the

extent of 30 degree may be permitted under exceptionally difficult situations. When the

angle of crossing has to be below 60 degree, the matter will be referred to the authority

in-charge of the telecommunication system in writing. On a written request from the

Contractor, the permission of the telecommunication authority may be obtained by the

Owner in writing. Also, in the crossing span, power line support will be as near the

telecommunication line as possible, to obtain increased vertical clearance between the

wires.

10.8 Clearances:

Minimum clearances to power conductors are to be maintained as per I.E Rules 1956.

These minimum clearances are statutory and shall be maintained at all times.

For the purpose of arriving at the vertical clearance, the maximum sag is to be calculated

taking into account the highest conductor temperature as specified in the sag tables.

For the purpose of arriving at the horizontal clearance, the maximum deflection of

conductor based on the maximum wind pressure in the zone is to be taken into account or

deflection up to 45o from the vertical towards the object is to be assumed and clearances

measured. The clearances apply in any direction.

Special consideration needs to be given to all clearances in the vicinity of recreation

sites.

For crossing any railway track Indian Electricity Rules and the regulations of railway

authorities are to be followed.

An additional vertical clearance of 300 mm must be allowed to compensate for long term

creep than those mentioned in the charts.

Page 157: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-157

10.8.1 Clearances to Ground and Roads

(Distance in Meters)

Sl.No Item LT 11 kV 33 kV

1. Minimum vertical clearance to over head line

conductor

a) Across the street 5.8 6.1 6.1

b) Along the street 5.5 5.8 6.1

c) At other places than mentioned in (a) and (b) 4.6 4.6 5.2

10.8.2 Maximum Span

In case of overhead lines carrying LT, 11 kV and 33 kV voltage conductors, when

erected in, over, along or across any street. The maximum span shall not exceed 45

mts.

10.8.3 Clearances to Buildings

(Distance in Meters)

Sl.N

o

Item LT 11 kV 33 kV

1. Minimum Vertical clearance to Buildings 2.44

3.66 3.66

2. Minimum Horizontal clearance to buildings 1.22 1.22 1.83

10.8.4 Clearances to communication lines

(Distance in Meters)

Sl.N

o

Item LT 11 kV 33 kV

1. Minimum Vertical clearance between power and

communication lines

1.525

1.525 1.830

2 Minimum clearance between guarding wire and

telecommunication line

1.220 1.220 1.220

Page 158: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-158

10.8.5 Clearness Between Power Lines when crossing each other (Distance in Meters)

Sl.N

o

Voltage LT 11 kV 33 kV

1. LT lines 2.44 2.44 2.44

2. 11 kV and 33 kV 2.44 2.44 2.44

3. 132 kV 3.05 3.05 3.05

4. 220 kV 4.58 4.58 4.58

5. 400 kV 5.49 5.49 5.49

6. 800 kV 7.94 7.94 7.94

10.8.6 Clearances to Railway Track

Railway crossings are classified into three categories as mentioned below:

Category ‘A’ : Tracks electrified on 1500 volts D.C.System (Eg.:

Bombay city area)

Category ‘B’ : Tracks already electrified and likely to be electrified

on 25 kV A.C.System in near future.

Category ‘C’ : Tracks not likely to be electrified in the foreseeable

future.

10.8.7 Special Note:

These are the minimum clearances to be maintained to the lowest portion of any

conductor of crossing including guarded wire under conditions of maximum sag.

Lines drawn upwards from the outer most guard wire to the center at an angle of 45o to

the vertical shall totally enclose the power conductors.

The structures are to be located in such a way that from the centre of the nearest railway

track the distance shall be height of the structures +6 meters.

The span of crossing is to be restricted to 80% of the normal span.

No jointing is permitted in the crossing span.

The crossing shall be in accordance with approved designs and drawings of Railways.

U.G. Cable pipe structure should be at 5 M away from Railway Power Support to be

located by the Railway Authorities

Spun concrete pipe encasing cable under tracks should be laid at not less than 1 meter

below

Page 159: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-159

10.8.8 Method of crossing

Sl.No Voltage Category Method of Crossing

1 LT A,B,C Cable crossing

2 11 kV A,B,C Cable crossing

10.8.9 Minimum clearance between Railway track and overhead lines

Sl.No Voltage Inside Station limits Outside station limits

1 LT Only by cable crossing Only by cable crossing

2 11 kV Only by cable crossing Only by cable crossing

10.8.10 Insulators to be used

Sl.No Category Type of Insulators

1. A,B Double set of strain insulators strings shall be used in

the crossing span in conjunction with a yoke plate

wherever necessary. In each string one strain insulator

shall be provided extra than the normal design of over

head line.

2. C Insulators as per normal design to be used.

11.0 STATUTORY REGULATIONS & STANDARDS-

11.1 Statutory Regulations:-

The contractor is required to follow local statutory regulations stipulated in Electricity

(supply) Act, 1948, Indian Electricity Rules, 1956, as amended and other local rules and

regulation referred in this specification.

11.2 Reference Standards:-

The codes and / or standards referred to in the specification shall govern, in all cases

wherever such references are made. In case of a conflict between such codes and / or

standards and the specification, latter shall prevail. Such codes and/or standards referred

to shall mean the latest revisions, amendments / changes adopted and published by the

relevant agencies unless otherwise indicated.

12.0 CONSTRUCTION PRACTICES:-

12.1 The standard construction practices as adopted by Jodhpur Vidyut Vitran Nigam

Ltd are to be followed in construction of various works activities covered in the

specification.

OVER HEAD LINES:

The construction of over head-lines may be divided into the following parts:-

a) Pit marking, pit digging.

Page 160: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-160

b) Erection of supports and concreting.

c) Providing of guys to supports.

d) Mounting cross-arms, pin and insulators,

e) Paying and stringing of the conductor.

f) Sagging and Tensioning of Conductors and pin binding.

g) Crossings.

h) Guarding.

i) Earthing.

j) Testing and Commissioning

12.2 The contractor should also follow & take care of the following points in

execution of various activities:-

i) All the material to be used shall be as per specification & drawing approved by the

JODHPUR DISCOM duly inspected and cleared for use in construction at site by the

authorized person of JODHPUR DISCOM.

ii)The pole shall be erected only after fitting of V-cross Arms, Top Hampers. Washers

shall be used with nuts and bolts.

iii)PCC poles shall be transported to the pit points through hand trolley so as to avoid

any cracks during transportation.

iv) Top Hamper should always be fixed, straight with the help of two nut, bolts and

washers on PCC poles.

v) Earthing of all steel structure like Top Hamper X-arm shall be done by 8 SWG GI

wire to connect all items to earth clamps/guard bracket PCC poles.

vi) Alignment of pit of RS Joist /PCC pole shall be along the line. Alignment of lattice

tower/PCC pole shall be along with the line and shall be erected through Ballies in the

following length below the ground, pit shall be excavated along the line.

a) 9 M Long pole : 1.5 M Deep

b) 8 M Long pole : 1.5 M Deep

c) 10/11M RS Joist : 1.8 M Deep

d) 12.8M Lattice Tower : 1.8 M Deep

vii) Erection of RS Joist/PCC pole shall be in alignment and back filling of soil

should be in consolidated form by ramming and watering each layer of 0.15

grade ( 1:3:6), 1.65 M in length.

Page 161: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-161

viii) Stay set shall be provided 2.0 M below the ground and back filling of pit by soil

shall be properly rammed. Alignment of pits for stay sets shall be across the lines. Angle

of stay set provided shall be an angle of about 45 degree from the ground level. Only one

stay set shall be provided in one pit.

ix) 8 stay set shall be provided on each double pole structure and 5 on lattice tower to

be provided for road, P&T and power line crossing.

x) Guy insulator shall be used in each stay wire at height not less than 3.0 meters from

the ground.

xi) Special nuts of self-locking type will be used in stay sets.

xii) Proper binding of stay wire shall be done. There shall be no gap between binding

coils of same wire. 100mm gap shall be maintained in the binding of two strand of stay

wire. Binding of alternate stay wire shall be in opposite direction to each other. Proper

size of stay and other clamps shall only provide.

xiii) All civil works shall be carried out strictly as per norms using proper ratio of

Cement concrete of ratio 1:3:6(M-10) 1cement3grit:6 sand with 25mm graded stone

aggregate with smooth finish may be provided.

xiv) Strut shall be provided at angle of 55 to 60 degree from the ground level. Top edge

of strut shall be just touch the horizontal base of V-cross Arm/ Cut point.

xv) Meggering value of all lines shall not be less than 2000 Mega-ohms after

completion of work of line & sub-station.

xvi) Stringing of conductor shall be done properly by using normal pullies and

chain pulley block. Over tensioning should not be there in any case and it should be

equal in all conductors having proper sag.

xvii) Binding on pin insulator shall be done 0.230 M on either side of the insulator

with one wire .

xviii) Two Nos. PG clamps of standard size as per conductor size shall be provided

on each jumper. No separate piece of conductor will be allowed in jumpering. PG clamps

for Dog conductor shall be 3 bolt type. As per Indian Electricity Act, atleast three

earthing of the line are to be done in one Km. length.

xix) For the proper earthing due care has to be given. The earth lead should be

tightened with U-Bolt on earth wire or bolted on bracket and the earth lead may pass

through bolt the hooks of poles.

Page 162: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-162

xx) The pits for all works including pole erection stay sets, earthings etc. shall be

excavated by the contractor irrespective of type of soil whether it is ordinary or hard

rock or any other type of soil.

xxi) Pole mounted 11/0.4 KV Sub-station complete with transformer, G.O. switch,

Horn gap fuse sets and lightening arrestors are to be erected as per approved drawing of

the Nigam. The location for pole mounted S/S has to be provided as per load

requirements. It should be ensured that all live parts are above 12 ft. from the ground.

Proper earthing with galvanized M. S. Rod for Sub-station as per approved drawing is

also to be ensured.

xxii) Erection of LT Distribution Pillar Boxes of 400/160/100 Amps. Capacity

Each 37”x24” base as per NIGAM standard including excavation, bricks, sand, cement,

masonry of size 4”x3”x10” and 3’ in ground and 1½’ above road level with muffing to

support and mounting the pillar. The masonry will have 4”x4” opening 2”bellow ground

level two in the rear side and one each in the remaining sides to facilitate entry & exit of

incoming and outgoing LT cable .However the exact sizes & general construction design

of the foundation shall be given by the Engineer In-charge of the contract with in three

weeks of the contract agreement .The contractor shall take into account this while

quoting the rates.

xxiii) Earthing shall generally be carried out in accordance with the requirements of

Indian Electricity Rules, 1956 and the relevant regulations of the Electricity Supply

Authority concerned and as indicated below:

(a) All metallic supports shall be earthed.

(b) For PCC poles the metal cross-arms and insulator pins shall be bonded and earthed at

every pole for HT lines.

(c) All special structures on which switches, transformers, fuses, etc., are mounted /

likely to mount should be earthed.

(d) The supports on either side of the road, railway or river crossing should be earthed.

(e) All supports (Steel & PCC) HT lines passing through inhabited areas, road crossings

and along such other places, where Earthing of all poles is considered desirable from

safety considerations should be earthed.

12.2.1 PROVIDING OF GUYS TO SUPPORTS:

In spite of careful planning and alignment of line route, certain situations arise where the

conductor tries to tilt the pole from its normal position due to abnormal wind pressure

Page 163: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-163

and deviation of alignment, etc. When these cases of strain arise, the pole is strengthened

and kept in position by guys. One or more guys will have to be provided for all supports

where there is unbalanced strain acting on the support, which may result in

tilting/uprooting or breaking of the support.

Guys are braces fastened to the pole. In this work anchor type guy sets are to be used.

These guys are provided at (i) angle locations (ii) dead end locations (iii) T - off points

(iv) Steep gradient locations and (v) where the wind pressure is more than 50 kg /

Sq.mtrs.

The fixing of guys stays will involve (i) pit digging and fixing stay rod (ii) fastening guy

wire to the support (iii) Tightening guy wire and fastening to the anchor. The marking of

guy pit, digging and setting of anchor rod must be carefully carried out. The stay rod

should be placed in a position so that the angle of rod with the vertical face of the pit is

30º/45º as the case may be.

Before start of erection of Stay sets, required concreting materials like Cement, Sand,

Stone Chips and Construction water need to be made available near the pit.

GI Stay wire of size 7/4.0 mm 8.5 kg stay wire per set and 20mm stay rod for 33 KV

lines and DP whereas 7/3.15 mm 5.5 kg (10 SWG) stay wire per set and 16 mm stay rod

for 11 KV lines and DP .

For double pole structure (DP), four stays along the line, two in each direction and two

stays along the bisection of the angle of deviation or as required depending on the angle

of deviation are to be provided.

After concreting of 0.3 cmt per stay, back filling and ramming must be done well and

appropriate time / days shall be allowed for proper setting.

The free end of the guy wire/stay wire is passed through the eye of the anchor rod, bent

back parallel to the main portion of the stay/guy and bound after inserting the G.I.

thimble, where it bears on the anchor rod. If the guy wire proves to be hazardous, it

should be protected with suitable asbestos pipe filled with concrete of about 2 m length

above the ground level, painted with white and black strips so that, it may be visible at

night. The turn buckle shall be mounted at the pole end of the stay and guy wire so fixed

that the turn buckles is half way in the working position, thus giving the maximum

movement for tightening or loosening.

Page 164: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-164

12.2.2 Conductor Erection:

Conductor erection is the most important phase in construction. The main operations

are:-

(a) Transportation of Conductor to works site.

(b) Paying and Stringing of Conductor

(c) Jointing of Conductor

(d) Tensioning and Sagging of Conductor

The conductor drums are transported to the tension location. While transporting

precautions are to be taken so that the conductor does not get damaged / injured. The

drum could be mounted on cable drum support, which generally is made from crow-bar

and wooden slippers for small size conductor drums. The direction of rotation of the

drum has to be according to the mark in the drum so that the conductor could be drawn.

While drawing the conductor, it should not rub causing damage. The conductor could be

passed over poles on wooden or aluminum snatch block mounted on the poles for this

purpose.

The mid span jointing is done through compressions or if helical fittings are used

the jointing could be done manually. After completing the jointing, tensioning

operation could be commenced. The conductor is pulled through come-along clamps to

stringing the conductor between the tension locations. Sagging of conductor has to be in

accordance to the Sag Tension chart. In order to achieve it, it is preferred to pull the

conductor to a tension a little above the theoretical value so that while transferring it

from the snatch blocks to the pit insulators and to take care of temperature variation.

Proper sag could achieve. Sagging for HT line is mostly done by “Sighting”. A

horizontal strip of wood is fixed below the cross-arm on the pole at the required sag. The

lineman sees from other end and the sag is adjusted by increasing or decreasing the

tension. The tension clamps could then be finally fixed and conductor be fixed on pin-

insulators. All fittings, accessories like guys, cross-arms, etc., could be checked as they

should not have deformed.

The maximum permissible spans for all the lines of HT and 0.4 KV are prescribed

according to the design of the supports. Sag-tension charts for these conductors are to be

followed.

12.2.3 STRINGING OF CONDUCTOR:

i) The works include spreading of conductors or HT/LT cables without any

damages and stringing with proper tension without any kinks / damages including

Page 165: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-165

binding of conductor at pin points, jumper at cut points etc, and the ground and

line clearances at road crossings along roads. LT crossing and others shall be as per

the relevant I.E. rules.

ii) While transporting conductors drums to site precautions are to be taken so that the

conductor does not get damaged. The drum shall be mounted on cable drum support, The

direction of rotation o the drum shall be according to the mark in the drum so that the

conductor could be drawn, While drawing the conductor, it shall not rub causing damage,

the conductor shall be passed over poles on wooden or aluminum snatch block (pulley)

mounted on the poles for this purpose.

iii) The conductor shall be pulled through come-along clamps to stringing the conductor

between the tension locations.

iv) Conductor splices shall not crack or otherwise be susceptible to damage in the

stringing operation. The contractor shall be used only such equipment/ methods during

conductor stringing which ensures complete compliance in this regard. All the joints

including mid span joints on the conductor and earth wire shall be of the

compression type in accordance with the recommendations of the manufacturer, for

which all necessary tools and equipment like compressors dies, etc, shall be obtained by

the contractor, each part of the joint shall be cleaned by wire brush till it is free of rust or

dirt, etc, and be properly greased with anti corrosive compound, before the final

compression is carried out with the compressors. After completing the jointing,

tensioning operation shall be commenced.

v) All the joints or splices shall be made at least 15 meters away from the pole No.

joints of splices shall be made in spans crossing over main roads, railways and small

rivers, spans. Not more than one joint per sub conductor span shall be allowed. The

compression type fittings shall be of the self centering type. After compressing the joint

the aluminum sleeve shall have all corners rounded; burrs and sharp edges removed and

smoothened.

vi) During stringing of conductor to avoid any damages to the joint the contractor shall

use a suitable protector for mid span compression joints in case they are to be passed

over pulley blocks / aerial rollers. The pulley groove size shall be such that the joint

along with protection can be passed over it smoothly.

Page 166: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-166

12.2.4 TENSIONING AND SAGGING OPERATIONS:

(i) The tensioning and sagging shall be done in accordance with the approved stringing

charts or sag tables. The “initial” stringing chart shall be sued for the conductor and

“final” stringing chart for the earth wire. The conductors shall be pulled up to the desired

sag and left in running blocks for at least one hour after which the sag shall be re-

checked and adjusted, if necessary before transferring the conductor from the running

blocks to the suspension clamps. The conductor shall be clamped within 36 hours of

sagging in.

(ii) The sag will be checked in the first and the last section span for sections up to eight

spans and in one additional intermediate span for sections with more than eight spans.

The sag shall also be checked when the conductors have been drawn up and transferred

form running blocks to the insulator clamps.

(iii) At sharp vertical angles, conductor and earth wire sags and tensions shall be checked

for equality on both sides of the angel and running block. The suspension insulator

assemblies will normally assume verticality when the conductor is clamped. Tensioning

and sagging operations shall be carried out in calm whether when rapid changes in

temperature are not likely to occur.

12.2.5 TAPPING ARRANGEMENT FROM EXISTING 11 KV LINE :

Tapping of existing 11 KV line shall be taken by providing a horizontal cross arm below

the existing V cross arm of the pole and mounting disc insulators on it. The tapping

conductors may be guided by providing pin insulators as required.

A new two pole structure shall be erected within 10-15 meters of this tapping pole & the

new line will emerge from this two pole structure with disc insulators. The Tapping pole

to the double pole conductor tension should be such that it avoids looseness & sag to the

extent possible & it should avoid extra tension on the tapping pole.

Alternately, tapping of existing 11 KV line can be done by erecting two single poles with

„V‟ Cross arms & top clamps, just below the line, as such forming a Double Pole

Structure. The Horizontal cross arm shall be provided below the „V‟ cross arms on both

poles and disc insulators are mounted on it. The tapping conductors may be guided by

providing pin insulators as required.

Wherever the proposed spur line length is more than two km after the tapping an AB

switch arrangement shall be provided at the double pole for isolation of the line.

Page 167: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-167

12.2.6 FINAL CHECKING, TESTING AND COMMISSIONING:

After completion of the works, final checking of the line shall be carried out by the

Contractor to ensure that all foundation works, pole erecting and stringing have been

done strictly according to the specifications and as approved by the Owner. All the works

shall be thoroughly inspected in order to ensure that:

1 Sufficient backfilled earth covers each foundation pit and is adequately compacted.

2 All poles are used strictly according to final approved drawing and are free of any

defect or damage whatsoever.

3 The stringing of the conductors have been done as per the desired clearances.

4 All conductor accessories are properly installed.

5 All other requirements for completion of works such as fixing of danger plate and anti-

climbing device have been fulfilled.

6 The insulation of the line as a whole is tested by the Contractor through provision of

his own equipment, labor, etc. to the satisfaction of the purchaser.

7 All poles are properly grounded.

8 The line is tested satisfactorily for commissioning purpose.

12.2.7. Anchoring and Providing Guys for Supports

Guys are to be provided to counter balance the load on the supports due to pulling of the

conductors, so that the supports remain straight in vertical position without bending in

any direction.

The stays/guys shall be provided at the following locations.

1. Angle locations

2. Dead end locations

3. Tee off points

4. Steep gradient locations to avoid uplift on the poles

5. Two numbers storm guys to the central pole between two cut points perpendicular to

the line direction.

The installation of stay/guy will involve the following works:

1. Excavation of pit

2. Fixing of base plate to the stay rod and concreting and back filling of the pit.

3. Fastening guy wire to the support along with stay clamp and turn buckle, after fixing

guy insulator(s) as per the drawing.

Page 168: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-168

4. Tightening guy wire and fastening to the anchor.

The marking of the guy pit for excavation, the excavation of pits and setting of the

anchor rod must be carefully carried out. The stay rod shall be placed in a position such

that the angle of inclination of the rod with the vertical face of the pit is 45o.

The anchor plate shall be of size 450 x 450 x 75mm, made of RCC with 1:2:4 ratio and

using 20mm machine crushed granite metal. Alternatively M.S. Plate of size 450 x 450 x

10mm may also be used. The pit shall be filled with 1:3:6 cement concrete using 40mm

granite metal. The size of concrete block shall be 450x450x1265mm at the bottom

covering the anchor plate completely. The concrete shall be cured for 14 days and

balance portion of the pit back filled with earth as per the specification.

Proper form of moulds adequately braced to retain proper shape shall be used. The

moulds should be made water tight so that cement cream will not come out. After

concreting to the required height the top surface should be finished smooth, with 1:6

slope towards the outer edge to drain off water.

In wet locations, submerged locations and marshy locations the site shall be completely

dewatered during concreting and for 24 hours after completion. Moulds shall not be

removed before a lapse of 24 hours after completion of concreting. After removal of

form boxes, the concrete surfaces where ever required shall be plastered with a rich mix

of cement and sand mortar in the shortest possible time.

After the curing time of concrete is over, the free end of the guy wire is passed through

the eye of the anchor rod, bent back parallel to the main portion of the guy and bound

after inserting the G.I. Thimble. The loop is protected by G.I. Thimble where it bears on

the anchor rod. Where the existence of guy wire proves hazardous, it should be protected

with suitable asbestos pipe of 50 mm dia. and 2 mts length, filled with concrete, duly

painted with black and white stripes with enamel paint of approved quality and make, so

that it may be visible at night.

The Turn buckle shall be mounted at the pole end of the stay and guy wire so fixed that

the eye bolt is half way in the working position, thus giving the maximum movement for

tightening or loosening.

Page 169: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-169

Guy insulators shall be provided to prevent the lower part of the guy from becoming

electrically energised by contact with the upper part of the guy, when the conductor

snaps and falls on them or due to leakage. No guy insulator shall be located at less than

3.5 mts (vertical distance) from the ground. The minimum distance along the stay

between the point of contact with the pole and the top of stay insulator is 1.8 mts

Guy insulators shall comply with IS: 5300. Where stay angles of less than 45o are

unavoidable the use of stay angles from 30o to 44o or bow guys or flying stays shall only

be done with the approval of the Engineer. The anchoring and providing of guys for

supports shall be done as per the drawing. The stay wires used for anchoring shall

conform to IS: 2141. The individual wire used to form “stranded stay wire” is to be of

tensile grade 4 having minimum tensile strength of 700N /mm2.

12.2.8 Do’s and Don’t’s

For the guidance certain DO’S and DON’TS are given below while stringing the

conductor.

Do’s

1. Use proper equipment for binding aluminium conductors at all times.

2. Use skids or similar method for lowering conductor drums from transport.

3. Examine reel before unreeling for presence of nails or any other object, which

might damage conductor.

4. Rotate the reel while unwinding the conductor in the direction marked on the

reel.

5. Grip all strands while pulling out the conductor.

6. Control the unreeling speed with a suitable braking arrangement.

7. Use wooden rods for suitable braking arrangement.

8. Use long straight, parallel jaw grip with suitable liners when pulling conductor,

thus avoiding nicking or kinking of the conductor.

9. Use free running sleeves or blocks with adequate grooves for drawing / paving

conductors.

10. Use proper sag charts.

11. Mark conductors with adhesive tape which will not damage the strands.

12. Make all splicing with proper tools

Page 170: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-170

13. Chromate or graphite conducting oxide inhibiting grease, should be applied

before cleaning with wire brush, where ever jointing takes place.

Don’ts

1. Do not handle conductor without proper tools at any stage.

2. Do not pull conductors without ensuring that there are no obstructions on the

ground.

3. Do not pull out excess quantity of conductor than is required.

4. Do not make jumper connections on dirty or weathered conductor; clean the

conductor using wire brush.

5. Do not handle aluminum conductor in a rough fashion but handle it with a

care it deserves.

12.2.9 WORKMAN SHIP

The Contractor shall entirely be responsible for the correct erection of line

as per specification / approved drawings and their correct setting and alignment, as

approved by the Engineer. If the supports and DP Structures after the erection are

found to differ from approved route maps and drawings or to be out of alignment,

the Contractor shall dismantle and re-erect them correctly at his own cost without

extension of time. The supports must be truly vertical and in plumb after erection

and no straining will be permitted to bring them to vertical position. Verticality of

each support shall be checked by the Contractor and furnished to the Engineer.

Maximum permissible tolerance is 50 mm in respect of verticality.

12.3 CABLE LAYING AND INSTALLATION TECHNIQUES:

12.3.1 Cable as per scope indicated in this specification, shall be laid underground in

flat formation throughout the route as per relevant IS. However, as per requirement of the

field, the cables shall also have to be laid:

1. In Hume Pipe or GI pipe.

2. In air at terminations.

3. At varying depths due to obstructions.

4. As per approved drawings.

The final route shall however be site specific. The contractor shall prepare the final

route drawing based on the design and planning criteria provided in this document and

get the same approved from Employer/NIGAM before starting the cable laying work.

Page 171: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-171

12.3.2 TRENCHING:

The cable trench work involves earth excavation for cable trench, back

filling and removal of excess earth from site. The work site shall be left as clean as

possible.

The trench shall be excavated using manual and mechanical methods including air

compressor driven pneumatic drill as per field conditions. Most main roads are of asphalt

surface and some of the roads with cement concrete surface.

An air compressor with pneumatic drill or equivalent mechanical tool will be essential if

the road crossings are to be speedily made. Special system of laying hume pipe under

road without digging the surface may be adopted if feasible.

Where paved footpaths are encountered, the pavement slabs shall be properly stored and

reinstated. Identification markers of other services shall be properly stored and restored.

The sides of the excavated trenches shall, wherever required, be well shored up with

timber and sheeting.

Suitable wooden/ sheet steel barriers should be erected between the cable trench

and pedestrian/ motorway to prevent accidents. The barrier could be made out of

sheet steel or wood planks. These could be portable types of size 1.5 m long by 1.2

m (height). These should be painted with red and white coloured cross stripes.

Warning and caution boards should be conspicuously displayed. Red lights as

warning signal should be placed along the trench during the nights.

The excavated material shall be properly stored to avoid obstruction to public and traffic

movement.

The bottom of the excavated trench should be leveled flat and free from any object,

which would damage the cables. Any gradient encountered shall be gradual.

The depth of open trench should be as per ISS: 1255/84 according to size & voltage

ratings. For 33kv 30 cm x 120 cm and for 11kv / 1.1 kv 30 cm x100 cm.

12.3.3 TRIAL HOLES:

The bidder shall excavate trial holes, for alignment purpose at appropriate distance apart

as warranted by the local conditions, keep a record of findings and close the trial holes

properly to avoid hindrance / accidents to pedestrian traffic. The final route alignment of

cable shall be decided based on the finding of the trial hole.

Page 172: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-172

It is the responsibility of the contractor to maintain as far as possible the required

statutory clearances from other utility services.

Any damage caused, inadvertently to any utility services shall be the sole responsibility

of the contractor.

The scope also includes the Trench-less laying of H.T. Cables. The best cable laying

practices are to be adopted by using latest “HDD “ techniques with “VERMIER”

machines in specific locations such as road crossings and locations where open trench

digging is not possible. The depth of cable shall be maintained from 1.2 Mtr (Min.) to 2.0

Mtr(Max.), and a proof in the form “DEPTH GRAPH” must be produced by the

contractor.

12.3.4 CABLE HANDLING:

The inspection of cable on receipt, handling of cables, paying out, flaking,

cushioning with sand or sieved compacted native soil, back-filling, reinstatement of road

surfaces, providing and fixing joint markers, route markers , precautions of joint pits,

sump holes and all necessary precautions that are required shall be carefully planned and

in general conform to IS 1255-1984 or its equivalent. Standard practices should be

followed while handling the cable drums, The drum shall not be thrown or dropped on

the ground from the carriers such as trucks or railway wagon during unloading. The cable

drum shall be unloaded with the help of Cranes or Forklifts or using a proper ramp

having inclination 1:3 to 1:4 in order to avoid mechanical damage to the outer layer of

the cables. The cable drums shall be lifted or stored with its flanges always vertical. The

cable drum shall be rolled in the direction of arrow only, in order to avoid loosening of

cable winding. The drum shall not be rolled on rocky, uneven surface and for longer

distances, it may damage the drum and cable. While pulling the cables through ducts,

care should be taken to avoid abrasion of sheath around sharp bends. The minimum

bending radius also should be maintained as specified above and in any case, should

not be less than 10/15 times the overall diameter of cables. A suitable lubricant may be

used whenever pulling is done in longer ducts. Jerks should be avoided while pulling the

cables.

Recommended safe pulling force with stockings for HT XLPE cables:

a) For Unarmoured cable : P = 5DxD where P= pulling force

b) For Armoured cable : P = 9DxD D= dia. of cable in mm

Page 173: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-173

Recommended safe pulling force when pulled eye for HT XLPE cables:

For Aluminium conductors : 30 N/mm Sq.

For Copper Conductor : 50 N/mm Sq.

Cable shall be unwound from the drum by lifting the drum on the center shaft supported

both ends with suitable jacks/stands. Under no circumstances the cable winding shall be

lifted off a coil or drum lying flat at the flanges. This would cause serious twist and

damages.

12.3.5 DAMAGE TO PROPERTY:

The contractor shall take all precautions while excavation of trench, trial pits

etc., to protect the public and private properties and to avoid accidental damage. Any

damage so caused shall be immediately repaired by contractor at his own cost and

brought to the notice of the concerned persons and to the Employer/NIGAM.

- Contractor shall arrange third party liability insurance for the above purpose.

- The contractor shall bear all responsibilities and liabilities and shall bear all costs of

the damages so caused by him or by his workman or agents.

- At places where the cables cross private roads, gates of residential houses or

buildings, the cables shall be laid in RCC Hume pipes.

12.3.6 CABLE ROUTE MARKERS/CABLE JOINT MARKERS

Permanent means of indicating the position of joints and cable route shall

be fabricated, supplied and erected. Route Marker shall be provided at every 100

meter and at the turning points. Markers provided shall be as per the field

requirement. If the route passes through open fields, markers should be

conspicuously visible and above ground surface and particularly along the Road

turns except on road & pavements where they may interfere in the movement of

traffic or pedestrians.

The markers should incorporate the relevant information. The name of the owner,

voltage shall be marked on the route marker. The details shall be as per the drawing

enclosed.

The markers shall be of stone or tile construction. The design shall be such that it cannot

be pulled out. Tile type marker shall be used along the pavement. Stone/ PCC markers

shall be used at other locations.

Page 174: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-174

The stone/PCC markers shall be cut into proper size as per drawing, covered with cement

plaster with engraving of the information required.

12.3.7 DEPTH OF LAYING & SPACING BETWEEN CABLES:

Minimum depth of laying from ground surface to top of cable shall be as following:

33kv cable : 1.05 meter.

11 kV cable : 0.90 meter.

415 volt cable : 0.75 meter.

11kV, 415 V Cables at Road crossing : 1.0 meter.

11Kv,415V Cables at Railway crossing

(Measured from bottom of sleeper to top of pipe.) : 1.0 meter.

Whenever 2Nos. 33kV cable or 11kV Cables have common route, they can be laid in

same corridor (Trench) at the specified depth as indicated in the drawing.

Wherever the proper depth is not achievable due to presence of other services or for

other reasons, the cable shall be laid deeper or in hume pipe or GI pipe as required

depending upon the site condition.

12.3.8 PAYING OUT THE CABLE

The excavated cable trench shall be drained of all water and the bed surface

shall be smooth, uniform and fairly hard before paying out the cable. The cable shall be

rolled in the trench on cable rollers, spaced out at uniform intervals. The paying out

process must be smooth and steady without subjecting the cable to abnormal tension.

The cable on being paid out shall be smoothly and evenly transferred to the ground after

providing the sand cushion. The cables shall never be dropped. All snake bends shall be

straightened. Suitable size cable stocking pulling eye shall be used for pulling the cable.

While pulling the cable by winches or machines, the tension loading shall be by tension

indicator and shall not exceed the permissible value for the cable. The cable laying shall

be performed continuously at a speed not exceeding 600 to 1000 meter per hour.

The cable end seals shall be checked after laying and, if found damaged, shall

immediately be resealed. Sufficient number of heat shrinkable cable end sealing caps

shall be stocked at site stores for testing and jointing work. The integrity of the outer

sheath shall be checked after the cable is laid in position.

Page 175: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-175

12.3.9 SAND BEDDING and Brick

The cable shall be completely surrounded by well-compacted sand to such a

thickness and of such size that the cable is protected against damage. The thickness of

the cable sand should normally be a minimum of 7.5 cm in all directions from the cable

surface. Cable sand with a grain size less than 8 mm shall be preferred to offer good

protection to cable.

A brick layer of thickness 70 mm brick shall be provided over the sand for protection of

the cable with Two Layers of ‘A’ CLASS RED BRICKS (9x2 per meter).

12.3.10 FLAKING:

The cables shall be flaked and left with slight extra lengths at jointing bays for

expansion and flexibility.Sand Bedding shall be provided as no special thermal back

filling is required.

12.3.11 BACK FILLING

Normally back filling shall consist of the material earlier excavated. However, bigger

stones or pieces of rock should be removed.

12.3.12 PREVENTION OF DAMAGE DUE TO SHARP EDGES:

After the cables have been laid in the trench and until the cables are covered

with protective covering, no sharp metal tool shall be used in the trench or placed in such

a position that may fall into the trench. Straight and curved rollers used shall have no

sharp projecting parts liable to damage the cable. While pulling through pipes and ducts,

the cable shall be protected to avoid damage due to sharp edges. The cables shall never

be bent, beyond the specified bending radius.

12.3.13 ROAD, RAILWAY TRACKS, WATER PIPE LINE CROSSINGS:

RCC hume pipe shall be used for crossing of Road and cast iron or GI pipes

for railway track and water pipe line. One spare pipe at each location of 11 kV cable

crossing shall be laid. Cable pipe size/ laying details shall be as per IS 1255-1983. The

road cutting for cable trench, whether cement concrete, asphalt or macadam road

surface shall be undertaken after obtaining approval for cutting from the road

owning authorities, traffic police, telephone authorities and work should be planned

to be completed in the shortest possible time. Where necessary the work shall be

planned during night or light traffic periods. The railway track crossing design shall be

got approved from the railway authorities and the contractor shall do work in

coordination with them.

Page 176: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-176

In the excavated trench across the road the pipes shall be laid, excavation

backfilled compacted and surface shall be redone in the shortest possible time.

Open Drain Crossing: Where ever the cable has to cross open drains, with long

span, the cable shall be laid in suitable size G. I. pipe properly joined with suitable

collars. The GI pipe shall be firmly supported on pillars, columns, or suitable support of

RCC foundation.

The road-cut charges wherever applicable shall be reimbursed by the Nigam on

actual basis against the documentary proof of having deposited the same with the

respective civic authority through the invoice submitted for road restoration charges

actually paid to civic authority along with receipt. However, the contractor has to submit

the estimate against road cut restoration charges issued by local civic agency to Nodal

Officer of NIGAM for pre-examination / verification for according prior approval and

only after approval these charges are to be deposited by the contractor with the respective

local civic authority which shall be reimbursed by the NIGAM on the production of

documentary proof having deposited the charges on actual basis. The permission for any

required road cut is also to be arranged by the bidder/Contractor from the concerned

civic agency. All assistance for coordinating in this regard will be provided by the Nigam

12.3.14 FOOT PATH CUTTING:

The slabs, kerbstones, on the roads/ footpath shall be removed and reinstated

without damage.

12.3.15 REINSTATEMENT:

After the cables and pipes have been laid and before the trench is backfilled, all

joints and cable positions should be carefully plotted in drawing and preserved and

provided to the Engineer of Employer/NIGAM. The protective covers shall then be

provided, the excavated soil riddled, sieved and replaced. It is advisable to leave a crown

of earth not less than 50 mm and not more than 100 mm in the centre and tapering

towards the sides of the trench.

The temporary reinstatement of roadways should be inspected at regular intervals, more

frequently in rainy season and immediately after overnight rain for checking settlement

and if required, the temporary reinstatement should be redone.

12.3.16 JOINTING BAYS:

The bidder shall identify the location of the joint bays after carrying out

detailed survey of the cable route and excavation of the trial pits. The delivery lengths of

the cables shall match the location.

Page 177: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-177

The joint bay should have a flat and level surface. At the bottom in a corner, a sump pit

shall be made , if necessary, for bailing out water.

The contractor shall follow standard practice in making joint bay, jointing and back

filling after making joint and testing for the voltage class required.

All works shall be carried out in presence and supervision of the Engineer of

Employer/NIGAM.

12.3.17 TOOLS AND PLANTS:

The successful bidder shall have all necessary tools, plant and equipment to

carry out the survey and cable installation work.

The bidders are instructed to give all the details of equipment at their disposal, to carry

out the work successfully and speedily.

BENDING RADIUS:

Care shall be taken during laying to avoid sharp bending, and twisting.

Recommended minimum bending radius for LT/HT cables:

LT HT

Single Core 15xD 20xD D= Dia of cable in MM

Multicore 12xD 15xD

12.4 JOINTING AND TERMINATION OF CABLES:

General: The cable jointing personnel and his crew shall have good experience in the

type of joints and terminations that are used. The jointing work shall commence as soon

as two or three lengths of cables have been laid. All care should be taken to protect the

factory-plumbed caps/ seals on the cable ends, and the cable end shall be resealed

whenever the end is exposed for tests.

Jointing of cables in carriage ways, drive ways under costly paving, under concrete or

asphalt surfaces and in proximity to telephone cables, and water mains should be avoided

wherever possible.

Sufficient over lap of cables shall be allowed for making the joints.

The joint bay should be of sufficient dimensions to allow the jointers to work with as

much freedom of movement and comfort as possible. Sufficient space should be kept

below the cable to be jointed.

The joints of different phases shall be staggered.

All jointing shall be done by joint manufacturer’s jointers or under their supervision.

Page 178: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-178

12.4.1 TENTS / COVERS:

An enclosure or suitable protection cover shall be used in all circumstances

wherever jointing work is carried out in the open irrespective of the weather conditions.

The joint shall be made in dust free and clean atmosphere.

12.4.2 PRECAUTIONS BEFORE MAKING A JOINT/ END TERMINATION:

The cable end seals should not be opened until all arrangement have been made

for jointing and all necessary precautions have been taken to prevent circumstances

arising out of rainy/ inclement weather conditions, which might become uncontrollable.

If the cable end seals or cable ends are found to have suffered damage the cables should

not be jointed, without tests and rectification.

12.4.3 MEASUREMENT OF INSULATION RESISTANCE:

Before and after jointing, the insulation resistance of both sections of cables

shall be checked.

12.4.4 IDENTIFICATION:

The identification of each phase shall be clearly and properly noted. The cables

shall be jointed as per the design approved by the Employer/NIGAM based on the

proposal submitted by the Contractor. Each cable shall have identification for phase and

circuit at joint bays.

12.4.5 MAKING A JOINT/ END TERMINATION:

Comprehensive jointing instructions should be obtained from the manufacture

of jointing/end kits and meticulously followed.

The materials used in the joints/ end kits like ferrules, screen / armour continuity bonds,

lugs etc., shall be of good quality and conform to standards.

The jointing tools shall be appropriate and as per the requirement of jointing XLPE, PVC

cables.

12.4.6 CABLE TERMINATIONS:

The cable terminations used are to be of outdoor type.

The preparation of the cable end for installing the terminations and the precautions to be

taken before fixing the terminations shall be followed as in the case of the cable jointing

procedures.

The instructions furnished by the termination manufacturer shall be strictly followed.

All terminations shall be done by joint manufacturer’s jointers or under their supervision.

At cable terminating end, the following provisions for supply and erection are to be

included.

Page 179: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-179

(i) A terminating structure should be provided where necessary for supporting the cable

to be terminated (except at the ring main unit ends)

(ii)A sufficient length of spare cable shall be left in the ground, for future needs.

(iii) The rise of the cable immediately from the ground shall be enclosed in 150

mm dia. PVC/GI pipe to protect against direct exposure to the sun.

(iv) The cable shall be properly fastened to the support using non-metallic clamps.

(v) Appropriate labels shall be fixed identifying the phase circuit, voltage and date of

commissioning etc., on the cable supporting structure.

(vi) The sealing end shall be mounted on insulators to isolate them from their

supporting steel work.

(vii) Protection from contact with the exposed metal work at the termination shall

be provided by resin bonded glass fiber shroud.

(viii) Providing earth stations with all required materials, like leads, connectors etc for

earthing of armour and screen.

12.4.7 BONDING OF SCREEN / ARMOUR:

The screens and armour at both ends shall be brought out and solidly bonded

to the earth station.

All accessories and consumables used in the termination should be of good

quality and compatible with the cable.

In case of armoured cable It is also important to ensure that all armoured wires

and all faces of armoured clamps making contact with them thoroughly cleaned during

installation and that the clamps are adequately tightened to ensure good electrical contact.

Provision should be made for earthing the wire armour to the main earth electro at the

supply and by means of a metallic bond of adequate conductance. The bonding

connection should be as short as possible. Where long cable length are laid it is also

desirable to earth the armour wires at interval, preferably at joint positions, to earth

electrode of sufficient at low resistances to ensure safety.

12.4.8 CONNECTION OF RADIAL WATER BARRIER AND CABLE SCREEN:

If the metallic radial water barrier is insulated from the metallic wire screen a

connection suitable to carry the currents occurring during operation must be installed

between metallic radial water barrier of the cable and metallic wire screen in joints and

sealing ends.

Page 180: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-180

12.4.9 ERECTION OF CABLE TERMINATING STRUCTURES:

The terminating structure should be designed as per the requirement of the

cable end sealing, offered by bidder.

The mounting structure shall be of latticed GI suitably grouted to the ground.

After fixing the end termination, the cable shall be fixed to the support, with non-

magnetic material clamps to the required height securely.

The mounting structure includes the supports for cable end boxes, link boxes and any

other structure required for the intent of the contract.

All steel sections used shall be free from all imperfections, mill scales, slag intrusions,

laminations, fillings, rust etc., which may impair their strength, durability and

appearance. All materials shall be of tested quality only unless otherwise permitted by

the Employer/NIGAM . The Contractor shall fabricate, provide and install the structures.

12.4.10 TESTS AFTER INSTALLATION:

All tests as prescribed in Clause-6 of IEC-840 shall be performed after

installation of cable. Following minimum tests shall be carried out:

Insulation Resistance of each cable drum length after paying but before jointing.

a) Serving insulation resistance after laying each cable length shall withstand a voltage

of 5 kV DC between each reinforcement and external conducting surface for one minute.

In addition, the serving insulation resistance shall be measured and checked with the

values obtained in the routine factory test.

b) On completion of the cable laying and jointing work, the complete installation shall

be tested with a D.C. / VLF voltage (high Voltage Test) as per IS 1255.

c) Conductor resistance of each cable of each complete circuit shall be measured and

compared with the values obtained during routine factory tests.

d) Test for 5 minutes with system voltage applied between the conductor and the armour

/ screen earthed.

e) Test for 24 hours with normal operating voltage of the system.

Note:- 1) Before laying the insulation value of the cable should be checked with

megger as a preliminary check against any probable damage.

Page 181: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-181

2) After the cable is installed a D.C. voltage of 3kv passed through each core and

against armour in case of LT cable. No breakdown should occur.

12.5 CONSTRUCTION PRACTICE FOR DISTRIBUTION TRANSFORMER

SUB-STATION :

The contractor shall transport, install, test and commission 3 phase, 11 KV/433 volts

Distribution Transformers of various capacity (Although DTs will be provided by

NIGAM).

The contractor shall survey the area, fix the location of DT keeping in view that DT is

close to the centre of the area to be fed as practically possible. Contractor shall obtain the

owner’s approval for final DT location. The no. of LT feeders / service connections to be

connected to a particular DT shall be decided during detailed physical survey and owner

approval will be final.

The details of the work related to distribution transformer are given below: -

12.5.1 Erection of transformer:

Distribution Transformer structure shall have the following configurations.

For all locations three phase DTs shall be mounted on 8 mtr double H-beam structure

with DO fuse for O.H. line system and special 2/4 pole steel sub-station structures for

U.G. cable system as per construction standard details of installation of DT substation

shall be as per enclosed drawing. At angle location DP, installation of transformer is not

permitted.

12.5.2 Erection of DO fuse:

The DO fuse unit shall be installed on HT side. The equipment and accessories

shall be checked for proper alignment and tightness after installation in O.H. line

network.

12.5.3 Earthing arrangement for transformer stations:

Earthing arrangement for DT shall be as per OUR construction standard

earthing shall be used to earth LT neutral, LA and the DT body at each DT location.

Thus three such pits shall be built for each transformer, the location of earth pits and for

connections to various earth pits, the bidder shall furnish detailed earthing system

drawing for the DT stations for review and approval. The earth resistance achieved shall

be less than the stipulated value as per the relevant codes of practice and shall be

measured and recorded as per approved erection and commissioning procedures.

Page 182: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-182

12.5.4 Electrical connections

The HT side connections shall be made with Rabbit ACSR conductor. LT side

connections shall be made with LT XLPE cables. Cables glands of ISI marks shall be

used for all the cable entries in distribution box.The contractor shall properly dress all the

LT cables emanating form distribution box. The contractor shall provided all jointing

material i.e. sleeves etc and carry out all jointing works. The cable ends shall be

connected using adequate capacity aluminum lugs and shall be tightened using bimetallic

brasses.

12.5.5 Protection and isolation

(a) HT side

The DTs shall be fitted with DO fuse to protect and isolate transformer on HT side in

case of over current and earth faults, the contractors shall specify the rating of the fuse

elements in the bid for each rating of transformer.

(b) LT side

Electric power from the transformer is drawn through the incomer ISOLATOR &

MCCBs provided on LT side to protect the transformer form the faults occurring on LT

system.

12.5.6 Connection from distribution Transformer to LT Cable

For extension of supply from Distribution box to overhead AB Cable/Insulated

conductor the arrangement shall be as described below:

Bearer/Messenger wire of LT AB cable shall be anchored through dead end clamp

arrangement on master pole which is at a distance of 5 meter from transformer DP.

Extra length of continuous cable along with messenger / bearer wire shall be properly

dressed and taken in to MCCB, using bimetallic clamp of appropriate size / quality.

Connection from cable & messenger / bearer to bus bar of pole distribution box (If

any) should be done with 6 sq mm PVC wire (having specifications as per ISS) using

Insulated piercing connectors and Earthing connectors.

12.6. Distribution Line Locations:

12.6.1 The route selected for a distribution line shall be such that it will find the

lowest cost considered over a period of years, consistent with accessibility for easy

maintenance etc. This includes many considerations such as original cost, tree trimming,

freedom from vehicular damages as for as possible, availability for future service.

Page 183: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-183

The line should be routed whenever possible to avoid natural obstacles such as steep hills

or valleys, swamps, lakes, thick forests, rivers etc. Lines should be located at a safe

distance from buildings and from possible fire, proximity to traffic and other hazards,

Lines shall not cross school playgrounds, cemetery, except under special circumstances,

Lines should be away form the building containing explosives.

12.6.2 Transportation cost constitute a major portion of the construction cost, As such,

while finalizing the route alignment, it may be ensured that extra cost involved due to

additional lead for transportation of the material should be as low as possible.

12.7 Right of way:

Considering the case of maintenance and avoiding the problems of right of

way. It is always preferable to lay the distribution lines along the roads; this will not

always be possible considering the cost involved due to the extra length of lines etc, in

which case, the line will have to be run on private lands or property.

12.8 L.T. LINE CONSTRUCTION PRACTICES:

12.8.1 LT lines shall be constructed with three phase 3x50 + 1x35 sq.mm AB cable /

Insulated ACSR Rabbit conductor. Support at each of the Pole as per the final line route

to be decided based on survey. RSJ/H-beam, to be used for this purpose shall be of 8.0

meters height. Pole footing arrangement shall be identical to the other similar poles

described in this specification.

12.8.2 For LT lines with cable, poles shall have Eye hook and suspension clamp

arrangement for anchoring of bearer wire associated with ABC line.

12.8.3 For pole locations, where consumer connections are more than two (extended).

ABC conductor shall be anchored on their bearer wire with suitable clamp or hook,

arrangement. This clamp shall be similar to dead end type (anchor) clamps cable portion

shall be terminated in and out of the distribution box (If any). The anchor arrangement to

be provided on both sides of the pole to facilitate connection of AB Cable pole to the

next pole of the line.

12.8.4 Locations, where single phase LT lines have to cross important through fare

(Main road, HT line etc.) the line shall be on poles with horizontal configuration. These

shall be as per REC construction standard drawing No. B-1 (guard wire with cross

lacing) and clearances as per IE Rule. Suitable extension arrangement (pole top bracket)

shall be provided to maintain the clearances and sags

Page 184: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-184

12.8.5 For LT line, every 5th pole, starting pole, cut point pole and last pole shall be

earthed by providing Earthing coil / Rod earthing.

12.9 RENOVATION OF DAMAGED SERVICE LINE & INSTALLATION OF

METERS:

The contractor shall replace identified damaged service line of the consumers other than

Below Poverty Line (BPL consumers) & agriculture pump consumers. The service line

wire shall travel from service pole to the premises of the consumer with the provision of

i) Through distribution box (In case of L.T. line comprising of L.T. cable).

ii) XLPE Insulated Armoured 4 sq.mm. (2 core) /6 sq.mm (4 core) cable.

iii) Supporting GI wire 10 SWG.

iv) Energy meter in the consumer premises at call bell location. (Although the Energy

Meters will be provided by NIGAM)

As far as possible the service connection shall be given from the pole of the LT line

which is nearest to the consumer’s premise.

The specific arrangement of service line renovation and installation of energy meters

shall be finalized during detailed engineering.

12.10 ERECTION OF ADDITIONAL 11 KV BAY IN 33/11 KV SUB

STATION:-

The erection of additional 11 kV bay in existing 33/11 kV sub station shall be done after

finalization of route of 11 kV new feeders. The lay out for erection of gantry structure,

VCB and related accessories shall be done as per the drawing attached with the bid

document.

12.11 EARTHING OF 33/11 KV SUB-STATION

Value of earth resistance in 33/11 kv Sub-Station shall be less than 1.0 Ohm.

13.0 INCEPTION / FDS REPORT:

13.1 In order to ensure the better execution of the proposed work in a

scientific and managerial way, the vendor shall furnish an inception report within

30 days of awarding the contract. The inception / FDS report shall contain the

following:

i) Detailed methodology / project report / modus operandi to be adopted to execute the

contract.

Page 185: JODHPUR VIDYUT VITRAN NIGAM LTD. Corporate Identity …€¦ · Moomal and Dhanana for deposit work for F.Y. 2019-20 under SE( BFL) ,Jaisalmer as per governing specification on Turn-Key

JdVVNL/TNTW- /P-185

ii) Resources, T&P with list of man power to be deployed to execute the contract.

iii) Detailed list of material required for successful execution of project.

iv) Cleary spell-out the obligation to be completed for execution of the work.

v) Detailed Functional design & specification of the equipments to be installed with GTP

(Guaranteed Technical Particulars).

vi) Testing procedure as per the relevant clause of the specification.

vii) Detailed methodology of Training system to technical staff of Nigam for

further maintain the system.

viii) Break up of total time schedule allowed for completion of supply in GANTT

CHART. The GANTT CHART shall include milestone of approval of types and makes.

ix) Complete bill of material (BOQ) of existing material to be retrieved off duly

verified by the Nodal Officer / Engineer In-charge of the project.

The NIGAM on receipt of the inception report will furnish its recommendation for any

modification, if required, within 7 days of receipt the same. If no communication is

received from the NIGAM within the stipulated period of 7 days, it shall be presumed

that the inception report is in order and the contractor may go ahead to start the work

accordingly.