Page 1: Italian-Thai Development - Work Progress as of December 2012

1

Work Progress as of December 2012

A. Access Road and Access Bridge

Section 1: Route to Myitta

Picture 1: Completion of Myitta office

Picture 2: Abutment of Temporary Bridge

Page 2: Italian-Thai Development - Work Progress as of December 2012

2

Picture 3: Material Covering

Picture 4: Construction of Labor House

Picture 5: Construction of Staff House at Myitta

Page 3: Italian-Thai Development - Work Progress as of December 2012

3

Section 2: Route from Myitta to Sin Byu Daing

Picture 6: Fabrication Truss for Main Base

Section 3: Route from Sin Byu Daing to Hti Khee

Picture 7: Cutting Curve and Fill at Vado

Picture 8: Staff House

Page 4: Italian-Thai Development - Work Progress as of December 2012

4

Picture 9: Office under Construction

Picture 10: Completion of temporary bridge

Page 5: Italian-Thai Development - Work Progress as of December 2012

5

B. Port

Picture 1: Temporary Access Road for North Quay Wall

Picture 2: Temporary Access Road for North Quay Wall (Cont.)

Page 6: Italian-Thai Development - Work Progress as of December 2012

6

Picture 3: Temporary Access Road for South Quay Wall

Picture 4: Site Clearing for Main Port Area Works

Page 7: Italian-Thai Development - Work Progress as of December 2012

7

C. Reservoir

Picture 1: Topographic Survey on Pa Yain Byu Catchment Area

Picture 2: Standard Penetration Test (SPT) on West Wat Chaung Pond

Page 8: Italian-Thai Development - Work Progress as of December 2012

8

Picture 3: Standard Penetration Test (SPT) on Water Treatment Plant Area

Picture 4: Area of Water Treatment Plant after Site Clearing

Page 9: Italian-Thai Development - Work Progress as of December 2012

9

Picture 5: Preparing for Wat Chaung Construction Site Office

Page 10: Italian-Thai Development - Work Progress as of December 2012

10

D. Industrial Estate Infrastructure

Road and Utility Designs for Early Industries

Figure 1: Conceptual Layout of Early Industrial Estate

Clearing and Grubbing for Pagaw Zoon Relocation Construction Project

Picture 1: Temporary Stock of Palm Trunk

Page 11: Italian-Thai Development - Work Progress as of December 2012

11

Picture 2: Temporary Stock of Palm Trunk (Cont.)

Picture 3: Clearing Pagaw Zoon Relocation Area

Page 12: Italian-Thai Development - Work Progress as of December 2012

12

Clearing and Grubbing for Early Industries and Township

Picture 4: Earth Fill

Picture 5: Clearing Areas by Excavator

Page 13: Italian-Thai Development - Work Progress as of December 2012

13

E. Corporate Social Responsibility (CSR)

CORPORATE SOCIAL RESPONSIBILITY (CSR) WORK PROGRESS

1. Social Development Program

1.1. Public Health

Disease Control

Picture 1-2: Dr. May Aung Lin (Country Program Director), URC/ USAID/CAP Had a Meeting

with CSR Team and Dr. Win Naing, CSR Doctor

2. Job Opportunity and Livelihood Development

2.1. Skill Trainings:

- Computer Training

Picture 3: Computer Training Course

Page 14: Italian-Thai Development - Work Progress as of December 2012

14

- Thai Language training

Picture 4: Thai Language Training Course

Picture 5: Thai Language Lesson Sheets

Page 15: Italian-Thai Development - Work Progress as of December 2012

15

ENVIRONMENTAL RESTORATION PROJECT

DDC Center and Environmental Restoration Complex Current Construction Process

Demonstration Plot:

A. Plantation

Picture 6-7: Coconut, Lime and Jackfruit Trees

B. Products from CSR Nursery: We’ve harvested many crops from our demonstration plot

and nursery to show the villagers the quality of the product that they can grow

themselves. Also, to let them see that it’s possible to grow them in this area.

CSR Art and Culture Center at CSR Complex

Picture 8: CSR Shop

Page 16: Italian-Thai Development - Work Progress as of December 2012

16

F. Bawah Resettlement Site

Picture 1- 4: Work Progress of Concrete Plank

Picture 5-6: Work Progress of Concrete Block

Page 17: Italian-Thai Development - Work Progress as of December 2012

17

Picture 7-8: Work Progress of Door and Window

Picture 9-10: Work Progress

Picture 11-12: Work Progress of E Plot

Page 18: Italian-Thai Development - Work Progress as of December 2012

18

G. Site Work

Picture 1: ITD Office No.1

Picture 2: ITD Office No.2

Page 19: Italian-Thai Development - Work Progress as of December 2012

19

Picture 3: ITD Office No.3

Picture 4: Furniture Factory (Extension)

Page 20: Italian-Thai Development - Work Progress as of December 2012

20

Picture 5: Water Treatment Plant (In Construction)

Picture 6: Hospital

Page 21: Italian-Thai Development - Work Progress as of December 2012

21

Picture 7: VIP Residential

Page 22: Italian-Thai Development - Work Progress as of December 2012

22

H. Small Port

Picture 1: First Pour of In-s itu Slab Topping Approach Bridge as of November 17, 2012

Picture 2: Pouring Concrete to Pile Cap West Side of Loading Platform

as of November 19, 2012

Page 23: Italian-Thai Development - Work Progress as of December 2012

23

Picture 3: Form and Rebar Work to Pile Cap East Side of Loading Platform

as of November 21, 2012

Picture 4: View of Small Port Seeing from the West on November 19, 2012