irwin/mcgraw-hill 2 chapter 16 inventory systems for dependent demand u master production schedule u...

21
Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand Master production schedule Material Requirements Planning (MRP) System structure Example MRP II MRP/JIT

Upload: tyler-daniels

Post on 12-Jan-2016

212 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Irwin/McGraw-Hill 2

Chapter 16

Inventory Systems for Dependent Demand

Master production schedule

Material Requirements Planning (MRP)– System structure– Example

MRP II

MRP/JIT

Page 2: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Irwin/McGraw-Hill 3

Material Requirements Planning

How much of an item is needed?

When is an item needed to complete– a specified number of units...– in a specified period of time?

Dependent demand drives MRP

Page 3: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Irwin/McGraw-Hill 4

Introductory Example - Dependent Demand

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A

Product Structure Tree for Assembly A Lead Times

A 1 dayB 2 daysC 1 dayD 3 daysE 4 daysF 1 day

Demand

Day 10 50 ADay 8 20 B (Spares)Day 6 15 D (Spares)

Create a schedule to satisfy demand.

Page 4: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

LT = 1 day

Day: 1 2 3 4 5 6 7 8 9 10A Required 50

Order Placement 50

5© The McGraw-Hill Companies, Inc., 1998Irwin/McGraw-Hill

Page 5: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Day: 1 2 3 4 5 6 7 8 9 10A Required 50

Order Placement 50B Required 20 200

Order Placement 20 200

SparesLT = 2

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A

6© The McGraw-Hill Companies, Inc., 1998Irwin/McGraw-Hill

Page 6: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Day: 1 2 3 4 5 6 7 8 9 10A Required 50

LT=1 Order Placement 50B Required 20 200

LT=2 Order Placement 20 200C Required 100

LT=1 Order Placement 100D Required 55 400 300

LT=3 Order Placement 55 400 300E Required 20 200

LT=4 Order Placement 20 200F Required 200

LT=1 Order Placement 200

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A

40 + 15 spares

Part D: Day 6

7©The McGraw-Hill Companies, Inc., 1998Irwin/McGraw-Hill

Page 7: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Irwin/McGraw-Hill 8

Master Production Schedule (MPS)

Time-phased plan specifying how many and when the firm plans to build each end item

Aggregate Plan(Product Groups)

MPS(Specific End Items)

Page 8: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Irwin/McGraw-Hill 9

Time Fences

Frozen– No schedule changes allowed within this window

Moderately Firm– Specific changes allowed within product groups as

long as parts are available Flexible

– Significant variation allowed as long as overall capacity requirements remain at the same levels

Page 9: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Irwin/McGraw-Hill 10

Time Fences

8 15 26

Weeks

FrozenModerately

Firm Flexible

Firm Customer Orders

Forecast and availablecapacity

Capacity

Page 10: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Irwin/McGraw-Hill 11

Material Requirements Planning

Based on a master production schedule, a material requirements planning system:– Creates schedules identifying the specific

parts and materials required to produce end items

– Determines exact numbers needed

– Determines the dates when orders for those materials should be released, based on lead times

Page 11: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Firm orders from knowncustomers

Forecastsof demand

from randomcustomers

Aggregateproduct

plan

Masterproductionschedule(MPS)

Materialplanning(MRP)

Engineeringdesign

changes

Bill ofmaterial

file

Inventorytransactions

Inventoryrecord

file

Reports

12© The McGraw-Hill Companies, Inc., 1998

Irwin/McGraw-Hill

Page 12: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Irwin/McGraw-Hill 13

Bill of Materials (BOM) FileA Complete Product Description

Materials Parts Components Production sequence Modular BOM

– Subassemblies Planning BOM

– Fractional options

Page 13: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Irwin/McGraw-Hill 14

Inventory Records File

Each inventory item carried as a separate file– See, for example, Exhibit 16.15– Status according to “time buckets”

Pegging– Identify each parent item that created demand

Page 14: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Irwin/McGraw-Hill 15

Primary MRP Reports

Planned orders – to be released at a future time

Order release notices – to execute the planned orders

Changes in due dates of open orders due to rescheduling

Page 15: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Irwin/McGraw-Hill 16

Primary MRP Reports

Cancellations or suspensions of open orders – due to cancellation or suspension of orders on the

master production schedule.

Inventory status data

Page 16: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Irwin/McGraw-Hill 17

Net Change System

Activity driven Net change schedules Potential for system nervousness

Page 17: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Irwin/McGraw-Hill 18

Another MRP Example

A(2) B(1)

D(5)C(2)

X

C(3)

Item On-Hand Lead Time (Weeks)X 50 2A 75 3B 25 1C 10 2D 20 2

Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10plus the following spares:

Spares 1 2 3 4 5 6 7 8 9 10A 12B 7C 10D 15

Page 18: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Irwin/McGraw-Hill 19

Adding some more terminology

Gross Requirements

On-hand

Net requirements

Planned order receipt

Planned order release

Page 19: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

C Gross Requirements 45 36 64LT=2 On-Hand=10 10

Net Requirements 35 36 64Planned Order Receipt 35 36 64Planner Order Release 35 36 64

D Gross Requirements 15 135LT=2 On-Hand=20 15 5

Net Requirements 130Planned Order Receipt 130Planner Order Release 130

A(2) B(1)

D(5)C(2)

X

C(3)

20Irwin/McGraw-Hill

Page 20: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Day: 1 2 3 4 5 6 7 8 9 10X Gross Requirements 95

LT=2 On-Hand=50 50Net Requirements 45Planned Order Receipt 45Planner Order Release 45

A Gross Requirements 90 12LT=3 On-Hand=75 75

Net Requirements 15 12Planned Order Receipt 15 12Planner Order Release 15 12

B Gross Requirements 7 45LT=1 On-Hand=25 7 18

Net Requirements 27Planned Order Receipt 27Planner Order Release 27

C Gross Requirements 45 36 54 10LT=2 On-Hand=10 10

Net Requirements 35 36 54 10Planned Order Receipt 35 36 54 10Planner Order Release 35 36 54 10

D Gross Requirements 15 135LT=2 On-Hand=20 15 5

Net Requirements 130Planned Order Receipt 130Planner Order Release 130

21Irwin/McGraw-Hill

Page 21: Irwin/McGraw-Hill 2 Chapter 16 Inventory Systems for Dependent Demand u Master production schedule u Material Requirements Planning (MRP) – System structure

Irwin/McGraw-Hill 23

Manufacturing Resource Planning (MRP II)

Goal: Plan and monitor all resources of a manufacturing firm (closed loop):– manufacturing– marketing– finance– engineering

Simulate the manufacturing system