irwin/mcgraw-hill 2 chapter 16 inventory systems for dependent demand u master production schedule u...
TRANSCRIPT
Irwin/McGraw-Hill 2
Chapter 16
Inventory Systems for Dependent Demand
Master production schedule
Material Requirements Planning (MRP)– System structure– Example
MRP II
MRP/JIT
Irwin/McGraw-Hill 3
Material Requirements Planning
How much of an item is needed?
When is an item needed to complete– a specified number of units...– in a specified period of time?
Dependent demand drives MRP
Irwin/McGraw-Hill 4
Introductory Example - Dependent Demand
B(4)
E(1)D(2)
C(2)
F(2)D(3)
A
Product Structure Tree for Assembly A Lead Times
A 1 dayB 2 daysC 1 dayD 3 daysE 4 daysF 1 day
Demand
Day 10 50 ADay 8 20 B (Spares)Day 6 15 D (Spares)
Create a schedule to satisfy demand.
LT = 1 day
Day: 1 2 3 4 5 6 7 8 9 10A Required 50
Order Placement 50
5© The McGraw-Hill Companies, Inc., 1998Irwin/McGraw-Hill
Day: 1 2 3 4 5 6 7 8 9 10A Required 50
Order Placement 50B Required 20 200
Order Placement 20 200
SparesLT = 2
B(4)
E(1)D(2)
C(2)
F(2)D(3)
A
6© The McGraw-Hill Companies, Inc., 1998Irwin/McGraw-Hill
Day: 1 2 3 4 5 6 7 8 9 10A Required 50
LT=1 Order Placement 50B Required 20 200
LT=2 Order Placement 20 200C Required 100
LT=1 Order Placement 100D Required 55 400 300
LT=3 Order Placement 55 400 300E Required 20 200
LT=4 Order Placement 20 200F Required 200
LT=1 Order Placement 200
B(4)
E(1)D(2)
C(2)
F(2)D(3)
A
40 + 15 spares
Part D: Day 6
7©The McGraw-Hill Companies, Inc., 1998Irwin/McGraw-Hill
Irwin/McGraw-Hill 8
Master Production Schedule (MPS)
Time-phased plan specifying how many and when the firm plans to build each end item
Aggregate Plan(Product Groups)
MPS(Specific End Items)
Irwin/McGraw-Hill 9
Time Fences
Frozen– No schedule changes allowed within this window
Moderately Firm– Specific changes allowed within product groups as
long as parts are available Flexible
– Significant variation allowed as long as overall capacity requirements remain at the same levels
Irwin/McGraw-Hill 10
Time Fences
8 15 26
Weeks
FrozenModerately
Firm Flexible
Firm Customer Orders
Forecast and availablecapacity
Capacity
Irwin/McGraw-Hill 11
Material Requirements Planning
Based on a master production schedule, a material requirements planning system:– Creates schedules identifying the specific
parts and materials required to produce end items
– Determines exact numbers needed
– Determines the dates when orders for those materials should be released, based on lead times
Firm orders from knowncustomers
Forecastsof demand
from randomcustomers
Aggregateproduct
plan
Masterproductionschedule(MPS)
Materialplanning(MRP)
Engineeringdesign
changes
Bill ofmaterial
file
Inventorytransactions
Inventoryrecord
file
Reports
12© The McGraw-Hill Companies, Inc., 1998
Irwin/McGraw-Hill
Irwin/McGraw-Hill 13
Bill of Materials (BOM) FileA Complete Product Description
Materials Parts Components Production sequence Modular BOM
– Subassemblies Planning BOM
– Fractional options
Irwin/McGraw-Hill 14
Inventory Records File
Each inventory item carried as a separate file– See, for example, Exhibit 16.15– Status according to “time buckets”
Pegging– Identify each parent item that created demand
Irwin/McGraw-Hill 15
Primary MRP Reports
Planned orders – to be released at a future time
Order release notices – to execute the planned orders
Changes in due dates of open orders due to rescheduling
Irwin/McGraw-Hill 16
Primary MRP Reports
Cancellations or suspensions of open orders – due to cancellation or suspension of orders on the
master production schedule.
Inventory status data
Irwin/McGraw-Hill 17
Net Change System
Activity driven Net change schedules Potential for system nervousness
Irwin/McGraw-Hill 18
Another MRP Example
A(2) B(1)
D(5)C(2)
X
C(3)
Item On-Hand Lead Time (Weeks)X 50 2A 75 3B 25 1C 10 2D 20 2
Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10plus the following spares:
Spares 1 2 3 4 5 6 7 8 9 10A 12B 7C 10D 15
Irwin/McGraw-Hill 19
Adding some more terminology
Gross Requirements
On-hand
Net requirements
Planned order receipt
Planned order release
C Gross Requirements 45 36 64LT=2 On-Hand=10 10
Net Requirements 35 36 64Planned Order Receipt 35 36 64Planner Order Release 35 36 64
D Gross Requirements 15 135LT=2 On-Hand=20 15 5
Net Requirements 130Planned Order Receipt 130Planner Order Release 130
A(2) B(1)
D(5)C(2)
X
C(3)
20Irwin/McGraw-Hill
Day: 1 2 3 4 5 6 7 8 9 10X Gross Requirements 95
LT=2 On-Hand=50 50Net Requirements 45Planned Order Receipt 45Planner Order Release 45
A Gross Requirements 90 12LT=3 On-Hand=75 75
Net Requirements 15 12Planned Order Receipt 15 12Planner Order Release 15 12
B Gross Requirements 7 45LT=1 On-Hand=25 7 18
Net Requirements 27Planned Order Receipt 27Planner Order Release 27
C Gross Requirements 45 36 54 10LT=2 On-Hand=10 10
Net Requirements 35 36 54 10Planned Order Receipt 35 36 54 10Planner Order Release 35 36 54 10
D Gross Requirements 15 135LT=2 On-Hand=20 15 5
Net Requirements 130Planned Order Receipt 130Planner Order Release 130
21Irwin/McGraw-Hill
Irwin/McGraw-Hill 23
Manufacturing Resource Planning (MRP II)
Goal: Plan and monitor all resources of a manufacturing firm (closed loop):– manufacturing– marketing– finance– engineering
Simulate the manufacturing system