introduction to vibration problems at compressor stations

Upload: satyachaganti

Post on 04-Jun-2018

255 views

Category:

Documents


4 download

TRANSCRIPT

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    1/113

    Introduction to Vibration Problemsat Compressor Stations

    Presented by:

    Gary Maxwell, Chris Harper, Shelley Greenfield(Beta Machinery Analysis)

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    2/113

    Welcome

    Purpose: Introduction to compressor vibration(for more detail, recommend the 2.5 day GMRC Course in May)

    Focus on practical issues.

    Audience participationdemos, case studies,questions, etc.

    (We cant take you to the field, so we are bringing the field to the classroom)

    Presenters introductions

    Questions for the parking lot?

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    3/113

    Vibration Induced Pipe Fatigue Failure

    /

    , , ,

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    4/113

    Todays Topics

    1. Vibration Overview

    2. Sources of Vibration

    3. Pulsation Control4. Mechanical Resonance

    5. Torsional Analysis

    6. Pipe Strain7. Small Bore Piping

    8. Start-up Vibration Survey

    9. Summary

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    5/113

    1. Vibration Overview

    Presented by: Chris Harper

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    6/113

    How Equipment Fails

    Vibration is the leading cause of mechanicalproblems

    Equipment and piping fail due to excessiveSTRESS (fatigue failure)

    Pulsation Forces Vibration Stress Failure

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    7/113

    What is vibration?

    Vibration = periodic motion about anequilibrium position

    Vibration can be described with: Amplitude and

    Frequency (number of

    cycles per time) or Period (time to

    complete one cycle)

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    8/113

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    9/113

    Vibration amplitude

    Three related units

    Displacement

    (m, mils) Velocity

    (mm/s, in/s or

    ips) Acceleration

    (mm/s2, in/s2,gs)

    Only related whenvibration is simple,like in a spring-

    mass system

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    10/113

    Two Ways to Look at Vibration

    Frequency-domain

    Individual vibration

    Time-domain

    Overall vibrationUnits = seconds

    Units = Hz

    Time domain amplitudetypically higher

    than frequencydomain amplitude

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    11/113

    Time domain frequency domain

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    12/113

    Another way to visualize it

    Time domain and frequency domain show thesame information, just in different ways

    Frequency domain breaks out thecomponents of the time domain

    Time domain is

    measured Frequency domain

    is calculated

    O ll ti d i ib ti

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    13/113

    Overall time-domain vibration -terminology

    pe

    ak

    Peak-to-peak

    RMS p

    eak

    Peak-to-peak

    RMS

    Peak (measure of deflection) is used more

    often than RMS (measure of energy) Frequency domain is either peak or RMS (not

    peak-to-peak)

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    14/113

    Vibration Directions (common terminology)

    Axial: along crankshaft

    Horizontal: direction

    of piston motion

    Vertical

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    15/113

    Video #1 Vibration Equation

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    16/113

    Demo #1 Scrubber Vibration

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    17/113

    BETA guidelines - velocity

    Dashed linesadapted from

    SwRI Piping guideline

    also applicable forvessels, and forsmall borepiping ( 2 NPS)

    At individual

    frequencies, notoverall (time-domain) vibration

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    18/113

    Comparison

    Many differentvibration guidelines

    Remember thanvibrations overguideline mean

    moreinvestigationneeded

    Use 1 ips (FD) or1.5 ips (TD) as ascreening guideline

    for piping18

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    19/113

    2. Sources of Vibration

    Presented by: Shelley Greenfield

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    20/113

    Vibration Risk Areas

    TorsionalPulsation(Acoustics)

    Mechanical

    Skid & Foundation (Dynamics)

    Small Bore

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    21/113

    Risk Areas and Design Considerations

    Off-skid Pulsations

    Thermal Expansion:Piping Layout and

    Supports

    InteractionBetween Other Units

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    22/113

    Risk Areas and Design Considerations

    Off-skidPulsations

    Thermal Expansion;Piping Layout and Supports

    System PressureDrop (performanceissue, losses)

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    23/113

    Responsibility

    Pulsations and thermal growth crossboundaries of responsibility

    Vibration consultant hired by packager

    may be acceptable for small gatheringsystems

    good specificationsand communication

    Owner

    Engineering firm

    Packager

    Vibration consultant

    Large critical pipeline,storage, oroffshore units -recommend vibrationconsultant hired byowner

    Dynamic force on

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    24/113

    Dynamic force onreciprocating compressor

    Unbalanced Forces and Moments

    due to Reciprocating MotionPulsation Shaking

    Forces in Piping

    Gas Forces

    (Cylinder

    Stretch)

    Crosshead Guide

    Forces

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    25/113

    Forces occur at multiples of runspeed

    1x Compressor primary forces & moments

    Cylinder gas forces (rod load)

    Pulsation shaking forces (single-acting)

    2x Compressor secondary forces & moment

    Crosshead guide forcesCylinder gas forces

    Pulsation shaking forces (double-acting)

    3x Cylinder gas forces

    Pulsation shaking forces

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    26/113

    /2

    (0.605 ) 7042 (7001200

    )

    880 1000 , 1058

    1270

    , , 1

    How High Can Pulsation Forces Get?

    Cooler Nozzle Failure

    Pulsation Shaking Forces Can Be Very

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    27/113

    Pulsation Shaking Forces Can Be VeryHigh

    Original

    Bottles

    Guesses as to how high forcecould be in this run of piping?

    No acoustical study had been performed

    To solve problem, Beta conducted acoustical studyand recommended new bottles

    6 pipe - area = 26 in2

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    28/113

    As Found Unbalanced Forces

    11000 lbf pk-pk at 38 Hz

    What speed?

    Vertical

    Riser toCooler

    38 Hz x 60 s/min 2

    = 1140 RPM

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    29/113

    Gas Forces Cause Cylinder Motion

    Act on cylinder, bottles, scrubber and piping

    Create high vibrations around compressor

    :

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    30/113

    Vibration Risk: Compressor APPLICATION

    Lower Risk Vib. Risk Factors Higher Risk

    1 # of Units Online Many

    Convenient LocationOffshore or

    Remote

    Not Unit CriticalityCritical to the

    Process

    NotImportant

    Efficiency Important

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    31/113

    Vibration Risk: Compressor CONFIGURATION

    Lower Risk Vib. Risk Factors Higher Risk

    Sweet Gas Composition Sour, Heavy

    1 Step, DA Load Steps DA + SA(>50% turndown)

    Fixed Suct./Disc. Pressure Wide range;

    Fixed Speed Wide Range

    2 stg (4 or6 cylinder)

    Compressor Stages 1 stg (manycylinders)

    CR > 1.7 Compression Ratio < 1.3

    < 150 HP/ Cylinder > 750

    Vibration Study Scope

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    32/113

    CompressorPackage

    Vibration Study Scope

    /

    ,

    Small Bore

    Piping

    Foundation& Structure

    Off-Skid PipingVibration

    & ()

    /

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    33/113

    3. Pulsation Control

    Presented by: Shelley Greenfield

    l i i i

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    34/113

    Pulsation animation

    Pulsations in non-flowing gas

    Notice change in pressure and velocity

    Vid #2 P l ti d Oth F

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    35/113

    Video #2 - Pulsations and Other Forces

    P l ti F I Pi i S t

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    36/113

    Pulsation Forces In Piping System

    Example: Interstage System

    Discharge

    Piping

    Suction

    Piping

    Cooler

    P l ti F DA SA

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    37/113

    Pulsation Forces DA vs. SA

    Cylinder vertical forces

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    38/113

    Cylinder vertical forces

    Can be significant

    Pulsations controlled

    with orificeplates

    Vibration controlled

    with outboardsupports

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    39/113

    Compressor Vibration

    Case Study:

    C I t ll d Vib ti P bl

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    40/113

    Compressors Installed Vibration Problem

    6 1700

    Vibration Problems

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    41/113

    ( )

    Customer tried to fix problem no success

    Units not fully operational very expensive

    called BETA for help

    Vibration Problems

    Example: Piping to Cooler (Riser)

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    42/113

    Example: Piping to Cooler (Riser)

    :

    > 3

    ( )

    ( )

    Other Problem Locations(U b l d F lbf k k)

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    43/113

    (Unbalanced Forces, lbf pk-pk)

    &

    Recommendations

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    44/113

    New Bottles(Suction; Discharge)

    Modify Piping andSupports (includingoff-skid)

    Recommendations Implemented

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    45/113

    :

    Case Summary

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    46/113

    Case Summary

    Vibration problems are expensive

    Small errors during design stage are avoidable

    Illustrates how vibration analysis techniquesused to solve or prevent problems (comparedto trial and error fixes)

    What Happens to Pulsations ifOperating Envelope Changes?

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    47/113

    Operating Envelope Changes?

    ACCEPTABLE BottleShaking Forces

    Design Change: Increased #of Load Steps and Ps Range

    Bottle Shaking Forces >200% of

    Guideline. High Risk of VibrationProblem

    Initial Operating Points

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    48/113

    Pulsation mitigation

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    49/113

    g

    Surge volumes and resistive elements (orificeplates) are simple but can be costly (capital

    and pressure drop)

    Acoustic filtering offers much more pulsationcontrol with some capital cost but very littlepressure drop

    Factors affecting pulsation mitigation

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    50/113

    g p g

    Speedrange

    Valveunloaders

    Difficultycontrollingpulsations

    Difficultycontrolledvibration

    Fixed Very low Low

    Narrow Low Medium

    Wide Medium High

    Fixed Medium Low

    Narrow High Medium

    Wide Very high High

    For example, fixed speed =1200rpm, narrow speed range = 900 - 1200rpm,wide speed range = 600 - 1200rpm

    Optimizing Pulsation Control

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    51/113

    p g

    Case study - Impact of off-skid piping

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    52/113

    y p p p g

    Case study:

    One stage, two-throw Dresser-Rand 5BVIP2

    1200 RPM, gas speed of sound 1200 ft/s

    Both single-acting (SA) and double-acting (DA)

    Off-skid piping comes several weeks after pulsationstudy was completed - two units with two coolers

    Stages of analysis:

    Bottle sizing with a damper check

    On-skid design with infinite pipe termination

    Off-skid piping added

    On-skid design is volume-choke filter

    Piping layout

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    53/113

    Damper Check Piping LayoutOn-Skid Piping Layout

    Off-Skid Piping Layout

    Pulsations:

    - Cylinder nozzle

    - Bottle outlet nozzle

    - Skid edge

    Shaking Forces:

    - Cylinder

    - Bottle

    - Crossover piping

    Pulsations - discharge nozzle

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    54/113

    0

    5

    10

    15

    20

    25

    Pulsations

    ,psipk-pk

    1x, SA 1x, DA 2x, SA 2x, DA

    Damper Check

    On-SkidOff-Skid

    Shaking force - crossover piping

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    55/113

    0

    50100

    150

    200

    250

    300

    350

    400

    450

    Sha

    king

    Forc

    es,

    lbfpk-pk

    2x, SA 2x, DA

    On-Skid

    Off-Skid

    What was the difference?

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    56/113

    Hint: the length betweenthe discharge bottle and thecooler header is 15 feet

    Half-wave between bottleand cooler header box

    volume amplified pulsations

    Multiple compressors beat frequency

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    57/113

    Animation courtesy of Dr. Dan Russell, Kettering University

    Unit A

    Unit B

    Unit A

    Unit B

    Combined Pulsations

    Unit A and B run at slightly different speeds

    Because of this, the pulsations go in andout of phase

    Total pulsation amplitude is sumof pulsations from each unit

    Beat frequency is related to thespeed differential between Unit A

    and B

    Summary

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    58/113

    Shaking forces are more important to controlthan pulsations

    Acoustic filters are more effective than orificeplates for controlling pulsations

    More pressure drop is required to filter

    pulsations when wider speed ranges are usedor unit single-acting

    The more information included in a pulsation

    study improves accuracy and reduces risk

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    59/113

    4. Mechanical Resonance

    Presented by: Chris Harper

    Summary

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    60/113

    Example of Mechanical Analysis Model

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    61/113

    Mechanical Analysis - MNFs

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    62/113

    Frequencies wheresmall forces result

    in large vibrationresponse ofstructure

    Modal Analysis

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    63/113

    Finite Element Analysis(FEA) used to calculateMechanical Natural

    Frequencies (MNFs) Elastic Modulus

    Geometry

    Density

    Measure MNFs with Bump

    Test

    Demo #2 Mechanical Natural Frequency

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    64/113

    Mechanical Resonance

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    65/113

    |

    6x

    |

    1x

    |

    2x

    |

    3x

    |

    4x

    |

    5x

    Frequency

    Forces

    MNFs

    We define resonance when force frequency is +/- 10% of MNFAt resonance, displacement can be magnified by 40 times can cause fatigue

    failure

    What happens at 3X? What about 4X? 6X? Potential resonance,but insufficient forceto cause problems

    Change design to shiftMNF away from resonance

    Mechanical Analysis Design Goal

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    66/113

    MNF

    |

    1x

    |

    2x

    |

    3x

    |

    4x

    Forces

    API 618 Design GoalMNF > 2.4 x

    Wide speed range

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    67/113

    MNF

    Frequency avoidance becomes challenging asspeed range is increased

    Blocking out speeds may help avoidresonance

    |

    1x

    |

    2xFrequency (orders of run speed)

    Speed of

    driver

    Magnitude

    of Force

    1200 rpm

    700 rpm

    No room forMNF to hide

    MNFs of Main Components in Relation toCompressor Harmonics

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    68/113

    60 Hz40 Hz 50 Hz

    ScrubberMNFs:

    15-30 Hz Typ.

    Cylinder MNFs:

    30-50 Hz Typ.

    Bottle MNFs:40-70 Hz Typ.

    70 Hz20 Hz

    Example: Scrubber Design

    Move MNF to Higher Frequency

    = Extra costs; design modification

    2.4 X 900 RPM 2.4 X 1200 RPM

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    69/113

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    70/113

    Case Study 3rd Stage MNF (API 618 Step3a)

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    71/113

    Case Study 3rd Stage MNF

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    72/113

    Case Study Cylinder Gas Loads at 3x?

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    73/113

    TABLE L.2 - Cylinder Gas Forces (kips,0-Pk) in Horizontal direction

    Unit: Ariel KBZ/6

    STAGE#3 CYLINDER# 2

    COND# 01X 02X 03X 04X 05X 06X 07X 08X 09X 10X

    1 75.0 5.7 4.3 0.7 3.4 1.2 0.7 0.8 0.9 0.8

    2 69.6 5.5 6.5 1.1 2.9 1.2 0.7 0.9 0.9 0.8

    3 67.8 5.4 7.0 1.2 2.7 1.2 0.9 0.9 0.8 0.8

    4 65.8 5.3 7.5 1.3 2.5 1.1 1.0 1.0 0.7 0.8

    5 49.1 4.5 5.2 4.1 1.6 1.1 0.4 0.4 0.2 0.6

    6 48.4 4.3 5.5 4.1 1.6 1.2 0.4 0.3 0.3 0.5

    Therefore 7500 lbs (0-pk) at 3x compressor run speed.

    (Weight of large SUV fully reversing 43.5 times per second!)

    Causes cylinder stretch

    Case Study Forced Response Analysis(API 618 Step 3b1)

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    74/113

    Case Study 3rd Stage MNF, with LWN

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    75/113

    Case Study 3rd Stage MNF, with LWN

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    76/113

    Case Study Cylinder Gas Loads at 4x?

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    77/113

    TABLE L.2 - Cylinder Gas Forces (kips,0-Pk) in Horizontal direction

    Unit: Ariel KBZ/6

    STAGE#3 CYLINDER# 2

    COND# 01X 02X 03X 04X 05X 06X 07X 08X 09X 10X

    1 75.0 5.7 4.3 0.7 3.4 1.2 0.7 0.8 0.9 0.8

    2 69.6 5.5 6.5 1.1 2.9 1.2 0.7 0.9 0.9 0.8

    3 67.8 5.4 7.0 1.2 2.7 1.2 0.9 0.9 0.8 0.8

    4 65.8 5.3 7.5 1.3 2.5 1.1 1.0 1.0 0.7 0.8

    5 49.1 4.5 5.2 4.1 1.6 1.1 0.4 0.4 0.2 0.66 48.4 4.3 5.5 4.1 1.6 1.2 0.4 0.3 0.3 0.5

    Gas Loads are less at 4x compressor run speed than at 3x

    Case Study Forced Response Analysis

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    78/113

    Conflict Between Thermal and Dynamic Study

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    79/113

    Thermal solution has large distance betweenclamps, thermal loops, and resting supports

    Dynamic solution has short distance betweenclamps and avoids elbows

    Balanced solution has clamps

    and thermal loops API 618 recommends same

    company conduct

    both studies

    Solutions - Scrubber Bracing

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    80/113

    Increase MNF of scrubbersto guideline levels, orinter-tune if possible

    May be required on somehigh RPM compressors

    Scrubber attachmentsmore likely to fail

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    81/113

    5. Torsional Vibration

    Presented by: Chris Harper

    Torsional Vibration Crank Failures

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    82/113

    Torsional Vibration Coupling Failures

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    83/113

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    84/113

    Purpose of Torsional Analysis

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    85/113

    To predict excessive vibratory stress or amplitudeproblems in driveline of driver / coupling /compressor

    Potential Torsional Problems Compressor/Engine Crankshaft failure Motor Shaft Failures or Spider Failure (welded joints) Coupling Failure (Disk Pack, Rubber, Other) Damper/Coupling Heat Loads Compressor auxiliary drive amplitudes Engine Free End Amplitudes (Gear Problems) Motor Free End Amplitudes (Fan) Current Pulsation

    Torsional Vibration - Applications

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    86/113

    A TVA should be done for: Any new driver or compressor combination Any change in compressor configuration (different cylinders) Different motor (same frame rarely means same rotor inside) Different operating conditions (than what was originally studied) Drive trains experiencing failures VFD applications Critical applications

    Risk Chart May help to determine if a Study is requiredhttp://www.betamachinery.com/uploadedFiles/001_-_Design_Services/001_-_Reciprocating_Compressors/Recip_RISK_Chart_Vibration_Control_3.

    1.xls

    Thorough Checks Required

    A l f ll i PLUS di i

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    87/113

    Analyze full operating map PLUS upset conditions Include tolerance band to consider fabrication and

    installation uncertainty

    Motor stub shaft to be thesame diameter as thecompressor stub

    Risk of Failureat somepressures andspeeds

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    88/113

    6. Pipe Strain

    Presented by: Chris Harper

    Pipe Strain

    S l t j b h

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    89/113

    Several recent jobs wherewe encountered unexplainedhigh frequency vibrations

    and failures

    Isolated the cause as pipestrain

    Effects

    Pi t i

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    90/113

    Pipe strain can:

    Increase natural frequencies (like aguitar string)

    Reduce damping (high frequencyvibrations increase)

    Increase mean stress in system (makingit more likely to fail due to vibrations)

    Contributing Factors

    Mi li d fl

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    91/113

    Misaligned flanges

    Gaps between pipe and support

    Flange Misalignment

    ASME B31 3 offers guidance for flange

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    92/113

    ASME B31.3 offers guidance for flangealignment

    Solutions

    Custom or modified spool pieces orifice

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    93/113

    Custom or modified spool pieces, orificeplates, etc.

    Shim between piping and supports, ratherthan just tightening clamp bolts

    Post-weld heat treating (e.g., vessel nozzles)

    Designing more flexibility into system

    Small details are

    important!

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    94/113

    7. Small Bore Piping Vibration

    Presented by: Chris Harper

    Small Bore Piping - Introduction

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    95/113

    2 (50)

    (, , ),

    , , , .

    , , .

    Demo #3 Small Bore Piping

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    96/113

    Video #4 Small Bore Piping Vibration

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    97/113

    Why is SBP a High Risk Problem?

    Small bore piping is often overlooked:

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    98/113

    Small bore piping is often overlooked:

    May not be explicitly designed - fieldinstalled

    Not shown on compressor package GAs

    Not included in typical pulsation/vibration

    study Difficult to measure properly in the field

    Failure can lead to significant downtime

    Field Measurements

    Measure Relative Vibration

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    99/113

    Measure Relative Vibration,if required

    Steady State (Running)

    Transient (Start-up)

    Further check/investigation ifexceeds screening guideline

    Assessment Methods

    Energy Institute

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    100/113

    Energy Institute

    Need dynamic force &poor design & poorlocation = high likelihood of failure

    GMRC

    Tables of lengths

    and weights FEA

    Calculate allowable

    vibration before failure

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    101/113

    8. Start-up Vibration Survey

    Presented by: Chris Harper

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    102/113

    Typical vibration measurement points

    Scrubber: Top seam

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    103/113

    Bottle:Both ends of bottle (seam); sometimesmiddle

    Cylinder: Cylinder head end

    Compressor frame& engine:

    Crank height drive andnon-drive ends

    Pipe: Elbows, between supports

    PSV: Top of valve body

    Main skid: Front and rear corners

    Small Bore Piping: End of cantilever; between supports

    Plus other points if vibrations at above points are suspect!

    Not all vibrations are alike

    Be clear what is being measured and what

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    104/113

    gguideline is being applied

    Overall vs. individual frequencies

    Units: mm/s vs. inches/second

    Peak or RMS (or pseudo RMS)

    Frequency range Apply appropriate guidelines (time-domain

    vs. frequency domain guidelines)

    When do I call an expert?

    Basic repairs/modifications do not work

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    105/113

    p /

    Try temporary bracing first

    Very high vibration levels

    Vibrations are high in multiple areas

    Vibrations are high for multiple operating

    conditions Suspect pulsations are high

    High vibrations away from compressor

    Need help measuring or interpreting data

    Solutions

    Vibration = Dynamic Force x Dynamic Flexibility

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    106/113

    y y y

    Control forces

    Pulsation control devices like orifice plates

    Moving acoustic natural frequencies

    Control flexibility Gussets

    Bracing

    Modified or additional clamping

    Moving mechanical natural frequencies

    Braces Test temporary brace

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    107/113

    Add wooden braceas field test

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    108/113

    9. Summary

    Presented by: Shelley Greenfield

    Video #5 - Summary

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    109/113

    Summary - Vibration

    Vibration = Dynamic Force x Dynamic Flexibility

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    110/113

    Vibration cannot be eliminated, but can becontrolled through a balance between cost,

    performance and reliability

    The earlier vibration risk is identified, theeasier (and cheaper) it is to deal with

    Draft Vibration Specification (GMRC)

    Study Analysis Step Description

    A. Preliminary Design Review &

    Preliminary Pulsation Bottle Sizing

    Project Planning Stage:

    Assess operating range, unloading plan, piping

    layout options.

    Provide preliminary pulsation control scheme and estimated vessel sizing.

    Scope of Work for Compressor System (Pipeline, Gas Injection/Withdrawal, Critical Application)

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    111/113

    B. Torsional Vibration Analysis (TVA) Assess stress and vibration on crankshaft(s) (driver and compressor system), and coupling dynamic torque

    effects.

    C Pulsation Analysis Pulsation study of compressor and piping system (including package and station piping). Provide final

    recommendations on pulsation control solution.

    D Pressure Drop and Performance

    Report

    Evaluate pressure drop of pulsation control devices and piping system concurrently. Evaluate impact on

    compressor performance.

    E Mechanical

    Analysis

    Mechanical dynamic analysis of on-skid piping, supports, and vessels. FEA modelling can be applied where

    necessary.

    Provide recommendations for small bore piping support and vibration control.

    Optional: Forced Response Analysis of the Compressor Manifold and Vessels when necessary.

    (Proper design practices using resonance avoidance can eliminate the need for this task.)

    Optional: Forced Response Analysis of Off-Skid Piping System when necessary.

    (Proper design practices using resonance avoidance can eliminate the need for this task.)

    F Piping Flexibility (Thermal Stress)

    Analysis

    Static Analysis of piping and vessels to evaluate stress and equipment loads due to weight, pressure and

    temperature changes.

    G Skid Dynamic and Static Analysis Evaluate vibration of the skid and equipment mounted on the skid due to dynamic loads from the compressor

    and driver. The foundation and the geotechnical properties should be considered. Evaluate skid design relative

    to lifting.

    H Commission Testing Evaluate vibration of compressor, piping, skid, foundation and small bore piping. Evaluate pulsation, pressure

    drop, performance, and torsional vibration.

    Key Take-Aways

    Properly specify vibration studies (scope, etc.)

    b k d d ff k d (

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    112/113

    Assess vibrations on-skid and off-skid (acrossoperating envelope)

    Thermal/Mechanical: performed by same group

    Consider small bore vibration survey

    Attention to details (alignment, installation, etc.)

    Start vibration study early

    Attend GMRCs 2.5 day course, Compressor StationVibration, for more training.

    Questions?

  • 8/13/2019 Introduction to Vibration Problems at Compressor Stations

    113/113

    Chris Harper ([email protected])

    Shelley Greenfield

    Gary Maxwell