intro to pm oil and gas industry rev 03

Upload: agung-prima-aprim

Post on 30-Oct-2015

70 views

Category:

Documents


0 download

DESCRIPTION

Intro to PM Oil and Gas Industry Rev 03

TRANSCRIPT

  • Introduction to Project & Interface Management in Deep Offshore Oil & Gas Industry

    Public Lecture ISTN 15 June 2013

    Antonius Yunianto Offshore Project & Interface Management Professional Offshore-skills.com

    1

    offshore-skills.com

  • Agenda 2

    I

    II

    Introduction to Project Interface Management in Oil and Gas Industry

    III

    Introduction to Project Management in Oil and Gas Industry

    IV

    Case Study : Concept Selection Phase in Field Offshore Deepwater Development

    Project Management Certification

  • PART I INTRODUCTION TO PROJECT MANAGEMENT IN OIL AND GAS

    INDUSTRY

    3

  • I.1 Project Definition 4

    Temporary endeavor with a beginning and an end Creates unique product, service or result Is progressively elaborated Distinguishing characteristics of each unique project will be progressively detailed as the project is better understood Progressively means proceeding in steps, continuing steadily by increments, while elaborated means worked out with care and detail, developed thoroughly

    Reference : PMBOK

  • I.1 Project Definition 5

    Temporary endeavor with a beginning and an end Creates unique product, service or result Is progressively elaborated Distinguishing characteristics of each unique project will be progressively detailed as the project is better understood Progressively means proceeding in steps, continuing steadily by increments, while elaborated means worked out with care and detail, developed thoroughly

    Reference : PMBOK

  • I.2 Project Attributes 6

    A Project : Has a unique purpose Is temporary Is developed using progressive elaboration Requires resources, often from various areas Should have a primary customer or sponsor The project sponsor usually provides the direction and funding the project Involves uncertainty

    Reference : PMBOK

  • I.3 Project vs Operational Work 7

    Reference : PMBOK

    Projects Operations

    To attain its objectives and terminate Create own charter, organization and goals Catalyst for change Unique product or services Heterogeneous teams Start and end dates

    To sustain the business Semi permanent charter, organization and goals Maintain status quo Standard product or services Homogenous teams On going

    Examples Build LNG Plant Geotechnical Investigation Ground water well construction Opening a new shop Arrange for a conference

    Examples LNG Plant Production Writing a progress update memo Attending a conference Meeting with an employee Opening the shop

  • I.4a Project Management, Program Management & Portfolio Management

    8

    Ref.: PMBOK

  • I.4 Project Management, Program Management & Portfolio Management

    9

  • I.5 What is Project Management? 10

    Reference : PMBOK

    The Application of knowledge, skills, techniques and tools to project activities to meet project requirements. Project management is accomplished through the application and integration of the process such as: 1. Initiating

    2. Planning

    3. Executing

    4. Monitoring and Controlling

    5. Closing

  • I.6 Project Constraint 11

    Reference : PMBOK

    Scope What work will be done as part of the project? What unique product, service, or result does the customer or sponsor expect from the project as its deliverables?

    Cost

    What is the cost to complete the project? What is the project budget?

    Time

    How long it takes to complete the project? What is the project schedule?

  • I.7 Managing the Project 12

    Ref. : PMBOK

    Project managers are assigned by the performing organization to achieve the project objectives.

    A project manager is in charge of all aspects of the project including, but not limited to: Developing the project management plan and all related component plans, Keeping the project on track in terms of schedule and budget, Identifying, monitoring, and responding to risk, and Providing accurate and timely reporting of project metrics.

    The project manager is the lead person responsible for communicating with all stakeholders, particularly the project sponsor, project team, and other key stakeholders.

    The project manager occupies the center of the interactions between stakeholders and the project itself.

  • I.8 Project Life Cycle 13

    Reference : PMBOK

  • I.9 Product vs Project Life Cycle Relationships 14

    Reference : PMBOK

  • I.9 Product vs Project Life Cycle Relationships 15

  • I.10 Stakeholder 16

    Reference : PMBOK

    A Stakeholder are individuals and organizations that are actively involved in the Project, or whose interest may be positively or negatively affected as a result of project execution or project completion

    External Stakeholders Internal Stakeholders

  • I.11 Impact of Stakeholder Based on Project Time 17

    Reference : PMBOK

  • I.12 Organizational Structure 18

    Reference : PMBOK

    Organizational structures range from functional to projectized, with a variety of matrix structures between them

  • I.13 Functional Organization 19

    Reference : PMBOK

    Key Points: The organization is grouped by areas of specialization within different functional areas Projects generally occur within a single department Information required from other department will be routed through departmental heads Team members complete project work in addition to normal department work

    Advantages: Easier management of specialists Team member reports to only one supervisor Similar resources are centralized, the company is grouped by specialties Clearly defined career paths in areas of work specialization

    Disadvantages: People are more emphasis on their functional specialty to the detriment of the project No career path in project management Project Manager has little or no authority

  • I.14 Projectized Organization 20

    Reference : PMBOK

    Key Points: The Project Manager has control of projects Personnel are assigned and reports to a Project Manager Team members complete only project work and when it is over they dont have home Communication generally occurs only within project

    Advantages: Efficient project organization Loyalty to project More effective communications than functional

    Disadvantages: No home when project is completed Lack of professionalism in discipline Duplication of facilities and job functions Less efficient use of resources

  • I.14 Weak Matrix Organization 21

    Reference : PMBOK

    Key Points: Team members report to Functional Manager Team members do project work in addition to normal departmental work Power rest with the Functional Manager Project Manager plays a role of: Project Expeditor: Can not make any decision. Staff assistant and Communication Coordinator Project Coordinator: Similar to Project Expeditor except has some power to make decision.

  • I.15 Balanced Matrix Organization 22

    Reference : PMBOK

    Key Points: Two Bosses Team members report to Project Manager and Functional Manager Team members do project work in addition to normal departmental work Power is shared between the functional and project manager

  • I.16 Strong Matrix Organization 23

    Reference : PMBOK

    Key Point: Power rest with the Project Manager

  • I.17 Project Management Process 24

    Reference : PMBOK

    The project processes are performed by the project team and generally fall into one of two major categories: Project management processes ensure the effective flow of the project throughout its existence. These processes encompass the tools and techniques involved in applying the skills and capabilities described in the Knowledge Areas. Product-oriented processes specify and create the projects product. Product-oriented processes are typically defined by the project life cycle (as discussed in Section 1.9) and vary by application area.

  • I.18 Five Project Management Process Group 25

    Reference : PMBOK

    The process flow diagram provides an overall summary of the basic flow and interactions among Process Groups and specific stakeholders. A Process Group includes the constituent project management processes that are linked by the respective inputs and outputs where the result or outcome of one process becomes the input to another. The Process Groups are not project phases.

  • I.19 Project Management Process Groups and Knowledge Areas Mapping

    26

    Reference : PMBOK

  • I.20 Team Management 27

  • I.21 Project Development Management Phase 28

  • I.22 Earn Value Management

    29

    Link : EVM

  • I.23 Oil and Gas Industry Regulation

    30

    1. PTK-037 POD 2. PTK-038 WP&B 3. PTK-039 AFE 4. All procurement activities are bound by BPMIGAS Regulation on Supply Chain Management for

    PSC No. 007-REVISI-2/PTK/I/2011 - Providing guideline on supply chain management, procurement of goods and services, asset management, custom, and project management in BPMIGAS/PSC/JOBTAC. In general, all purchases of goods and services are done by either tender or direct selection/direct appointment (with certain requirements) and with only suppliers which are registered locally. Highlights in the procurement (goods & services) regulation guidelines :

    - Tender Plan and Contract Award > $5M needs BPMIGAS approval

    Non compliance to the procurement regulation will result to non-cost recovery and may lead to disciplinary action to the PSCs personnel.

    Link : POD, WP&B dan AFE http://www.skspmigas-esdm.go.id/

  • PART II INTRODUCTION TO PROJECT INTERFACE MANAGEMENT

    IN OIL AND GAS INDUSTRY

    31

  • II.1 Subsea Interface Management Overview 32

    Typical Subsea Interfaces:

  • II.3 Interface Management Overview 33

    Definition of Interface : An interface is the place at which independent systems meet or communicate with each other. It is an interaction of crossproject Delivery Team members necessary to exploit the synergy that is possible by having the right people engaged in communication. This dialogue is focused on ensuring that project identifies and implements the best solutions effectively.

    Multidiscipline Communication

    Its Colorful

    Communication is the key in Project

    Execution

  • II.1 Interface Management Overview 34

    Interface Management Plan :

    Its builtin & integral part of overall Project Management.

    Supports Project Manager for project execution ontime & within budget.

    The responsibility is entrusted to Project Interface Engineer.

    Is developed for Client, Contractor(s) and subs (suppliers/vendors).

    Applicable for project lifecycle : PreFEED/FEED, Detailed Engineering, Procurement,

    Construction, Installation (EPCI).

    This presentation summarizes the scope of Interface Management, procedure, systems &

    processes.

    On megaprojects, how it is implemented? Across Continents in different time zones and in

    multicultural environments? And, finally the . . . .

    Key to successful interface is frequent and effective Communication.\

    Is utilized to manage the interfaces between all parties involved during project life cycle.

    Is employed to incorporate process, tools and organizational structure.

    Later in the project the interface system is developed to incorporate delivery control, status of

    equipment, fabrication, installation and finally the management of lesson learned.

  • II.2 Interface Management vs Project Management Process

    35

    Interface Management Encompasses Entire Project Process Group :

    Interface Management Encompasses Entire Project Phases:

    Interface Management Cover s Nine Knowledge Areas

    Project Integration Management Project Scope Management Project Time Management Project Cost Management Project Quality Management

    Project HR Management Project Communications Management Project Risk Management Project Procure Management

  • II.3 Interface Categories 36

    External Interfaces:

    External Interfaces Occur between Contractor & Client and their external org /entities. Outside of the Contractors responsibility (If specified by Client). Cross scope boundaries of two or more Delivery Teams and/or Development Systems, (Ex. PL contractors for Export Lines, etc.) PS : For Client and their sub-contractors these are internal interfaces.

    Internal Interfaces:

    Internal Interfaces Occur within work areas of Contractors responsibility. Allow flow of information, identify Receiving and Providing Occur between the disciplines, e.g., Engineering, Construction, Quality, Procurement, Project Services, Commissioning, etc. PS : This includes Project Controls, Document Controls and any of Contractors suppliers / vendors.

  • II.3 Interface Types 37

    Interface Types:

    Tangible or Hard Interfaces Have a physical connection such as a structural steel connection, pipe termination, or cable connection, Ex. TieIn Points.

    Intangible or soft interfaces Involve only the exchange of information such as design criteria, clearance requirements or utility needs between Delivery Teams or between a Delivery Team and an external party.

    Technical interfaces Are tangibles or hard interfaces that occur within structures, systems and equipment, Ex. TieIn Points.

    Execution interfaces Occur when different contractors conduct their scope of work in series with interfaces that are dependent on each other or simultaneous when concurrent activities impact each other. (Here Construction Manager is in lead).

    Organizational Interfaces Result in a significant loss/gain in schedule or capital to the originating Delivery Team or to the project in general.

    Critical interfaces Result in a significant loss/gain in schedule or capital, those not performing have potential to negatively impact project performance.

  • II.5 Interface Management Strategy 38

    Interface Management Strategy

    Ensures all interfaces between the various parties are identified and controlled to ensure integrity between the different elements associated with the project. Maintains uptodate Interface Registers and forms bridge between various parties involved in the execution of the Project. Defines precisely the interface requirements associated with each party involved in a particular interface. Defines the responsibilities for the parties involved with the interface so that individuals can be assigned and made accountable to followup the required actions. Monitors the transfer of information relating to interfaces between the relevant parties, including Risk Identification & Mitigation Management, and VEP (Value Engineering & Constructability) Programs. Monitors the status of the interface actions to enable active followup if necessary by the Project Management Team, including potential change requests, variation requests, etc. In short, creates an environment to minimize loss of revenue.

  • PART III

    SAMPLE CASE STUDY : CONCEPT SELECTION IN OFFSHORE DEEPWATER FIELD

    DEVELOPMENT

    39

  • 40

    40

    FPU

    Number of Wells & Plateu Rate

    Vertical type Cluster type

    None Minim.Off. Treatment

    Full Off. Treat.

    None -Subsea tie-back

    SWP FPU SWP

    New onshore

    plant

    TLP

    Existing plant

    None -Subsea tie-back

    SWP

    New offshore

    Well type

    Offshore

    processing

    Offshore

    structure

    Final

    treatment

    location

    New onshore

    plant

    Existing plant

    None Minim.Off. Treatment

    Full Off. Treat.

    New onshore

    plant

    Existing Plant

    New offshore

    New onshore

    plant

    Existing plant

    TLP SWP

    III.1 Standard Concept Screening Methodology

  • 41

    41

    III.2 FPU/FPSO vs SWP

  • 42

    III.10 Comparison between SWP and FPU/FPSO concepts

    Characteristic SWP FPU

    Process - NO condensate storage (Layout and safety constraints)

    - High capability for condensate storage

    Flowline system - Longer infield flowline system

    - subsea layout more exposed to geohazards - More complex riser system

    Expandability - Larger deck area and load capacity permit easier expansion;

    - allows for storage of liquids

    HSE - Risks for personnel working offshore for long periods during hook up and commissioning activities (moreover possible SIMOPs)

    - Flexible risers and umbilicals not protected from dropped objects

    - Flexible risers less protected from ship impact than SWP risers

    Subsea system - Complex riser base for export line due to diameter limit on flexible riser (16 ID)

    Decommissioning - Requires heavy decommissioning activities - Residual value

    Contractual scheme

    Schedule - 1000 days

    - 800 days

    Operability/ piggability

    - Pigging of export line requires support vessel and subsea pig launcher because of complex riser base

    Constructability - Possible availability of existing FPU for reconversion

    42

  • PART IV PROJECT MANAGEMENT CERTIFICATION

    43

  • IV.1 Project Management Professional Certifications 44

    Professional Certifications in Project Management

    Professional Certifications in Project Management 1. IAMPI (Ikatan Ahli Manajemen Proyek Indonesia) IAMPI website: http://www.iampi.org/ 2. Project Management Institute (PMI)

    a. Certifies Associate in Project Management (CAPM) A secondary degree (high school diploma or the global equivalent) AND At least 1,500 hours of project experience OR 23 hours of project management education by the time you sit for the exam.

    b. Project Management Professional (PMP)

    A secondary degree (high school diploma, associates degree, or the global equivalent) with at least five years of project management experience, with 7,500 hours leading and directing projects and 35 hours of project management education. OR A four-year degree (bachelors degree or the global equivalent) and at least three years of project management experience, with 4,500 hours leading and directing projects and 35 hours of project management education.

    PMI website : http://www.pmi.org/ PMI Indonesia Chapter : http://www.pmi-indonesia.org

  • 45

    The Deep Seafloor is The New Real Surface

    Offshore-Skills.com

    Terimakasih Thank You

  • BACK UP PROCESS GROUP

    46

  • I.18-a Initiating Process Group 47

    Reference : PMBOK

  • I.18-b PlanningProcess Group 48

    Reference : PMBOK

  • I.18-c Executing Process Group 49

    Reference : PMBOK

  • I.18-d Monitoring & Controlling Process Group 50

    Reference : PMBOK

  • I.18-e Closing Process Group 51

    Reference : PMBOK

  • BACK UP TATA KELOLA MIGAS

    52

  • IV.3 Upstream Petroleum Arrangement 53

    Upstream Petroleum Arrangements

    G

    B

    G B

    B B

  • IV.4 Historical Perspective 54

    License/Concession

    Production Sharing Contract

    1960 -1970

    G

    B

  • IV.5 Upstream Petroleum Contract 55

    *) Authors illustration - Modified from Society of Petroleum Engineers (SPE)

  • IV.5 Upstream Petroleum Contract 56

    Technical Assistance

    Development Field

    Conventional E & P

    High Cost EOR

    Extra Heavy Oil

    Extra Deepwater

    Low Cost Brownfield

  • IV.6 The Role of NOC/SOC 57

    Service Contract

    Production Sharing Contract

    Concession Royalty & Tax

    Lower Risk

    Higher Risk

    Percentage of NOC/SOC

    Participation?

    Iran (Buy back)

    Iraq (Technical Service Assistance)

    Brazil

    Norway

    Indonesia Angola Canada (unconv. heavy oil)

    Nigeria

    Malaysia Libya (EPSA)

    Nigeria DW Russia

    Algeria

    Kazakhstan UK US GOM

    57

  • IV.7 Proven Reserves (By Country) 58

    58

  • IV.7 Proven Reserves (By Country) 59

    59

  • IV.8 Produksi Minyak Bumi dari KKKS 2013 60

    60

    Chevron Pacific Ind.;

    327.692

    PERTAMINA, 120,798

    Total E&P; 64.788

    PHE - ONWJ, 38,178

    CNOOC SES, 36,331

    ConocoPhillips Ind., 35,146

    CICO, 26,910

    Mobil Cepu Ltd., 24,083

    PetroChina Jabung, 16,345

    Vico Ind., 15,236

    41 KKKS Lainnya, 120,817

    Chevron Pacific Ind.

    PERTAMINA

    Total E&P

    PHE - ONWJ

    CNOOC SES

    ConocoPhillips Ind.

    CICO

    Mobil Cepu Ltd.

    PetroChina Jabung

    Vico Ind.

    41 KKKS Lainnya

    14,6% 7,8%

    Sumber: SKK MIGAS

    STATUS 27 JANUARI 2013 (BOPD)

    39,7%

  • IV.9 Profil Produksi Migas Indonesia 61

    61

    52 57 57 51 53 59 74

    91 99 109

    153

    266

    401

    488 512

    550 544

    585

    744 773

    797

    847

    904

    966

    1056

    1214

    1264

    1302 1302 1327

    1397 1404

    1316

    1364

    1267

    1229

    1366

    1522 1501

    1468 1462

    1373 1408

    1499

    1586

    1498 1496

    1240

    1375

    1460

    1500 1500

    466

    569 601

    742

    853

    889

    1082

    1336

    1373

    1305

    1506

    1683

    1631

    1589 1587

    1624

    1288

    1407

    1519

    1338 1362

    1445

    1303

    1387

    1539 1575

    1491

    1535

    1612 1624

    1574 1557

    1537

    1500

    1415

    1341

    1252

    1147

    1096 1062

    1006

    954 977

    949 945

    902

    861 830

    900

    1000 1010 1010

    0

    500

    1000

    1500

    2000

    1966 1968 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016

    MB

    OEP

    D

    TAHUN Minyak

    PEAK 1977

    Plateau stage

    *) Outlook per 29 Januari 2013

    PEAK 1995

    Sumber: SKK MIGAS

  • IV.10 Profil Produksi Migas Indonesia 62

    62

    52 57 57 51 53 59 74

    91 99 109

    153

    266

    401

    488 512

    550 544

    585

    744 773

    797

    847

    904

    966

    1056

    1214

    1264

    1302 1302 1327

    1397 1404

    1316

    1364

    1267

    1229

    1366

    1522 1501

    1468 1462

    1373 1408

    1499

    1586

    1498 1496

    1240

    1375

    1460

    1500 1500

    466

    569 601

    742

    853

    889

    1082

    1336

    1373

    1305

    1506

    1683

    1631

    1589 1587

    1624

    1288

    1407

    1519

    1338 1362

    1445

    1303

    1387

    1539 1575

    1491

    1535

    1612 1624

    1574 1557

    1537

    1500

    1415

    1341

    1252

    1147

    1096 1062

    1006

    954 977

    949 945

    902

    861 830

    900

    1000 1010 1010

    0

    500

    1000

    1500

    2000

    1966 1968 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016

    MB

    OEP

    D

    TAHUN Minyak

    PEAK 1977

    Plateau stage

    *) Outlook per 29 Januari 2013

    PEAK 1995

    Sumber: SKK MIGAS

  • IV.9 Model 63

    63

    New Blocks Offered

    Existing Contracts

    Expiring Contracts

    Where do you apply the new model?

  • 64

    64

    Deepwater Challenges in Indonesia Exploration and Exploitation : subsurface uncertainties, difficulties in seismic, geological modeling, reservoir engineering, reserve calculation Procurement : Scarcity of seismic survey vessels, deepwater drilling rigs Development : Difficulties and uncertainties in development concept selection, design and technological approaches Commercial : Huge capital investment, Economics enhancement target of production Legal : Timing of evaluation and approvals of POD are critical relative to the expiration of the exploration period