Makers (09) Packers (09)
Case Packer (3), Transit (4), Filtromat (2), FLT (1) and Checker (1)
ODMS and Filter Feeding (3)
KDFs
KDFs (4)
Cleaning and waste collection (3)
Crew Positions in SMDODM
S
Filtromat
CIGRATTE STOCK
FILT
ROM
ATFI
LTER
ST
OCK
Line
01
Line
02
Line
03
Line
04
Line
05
Line
08
Line
10
Line
07
Line
06
CASE
PA
CKER
TRAN
SIT
CONFERENCE ROOM
TLOFFICE
WASHING BAY
TEAM
ROOM
QUALITY LAB
Office TOILETS
EXIT EXIT
Filtromat
Master technicians (3)
ClosedOFFICE
![Page 4: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/4.jpg)
• Study the Brand change Overs & Format change overs.
• Change Overs Downtime Analysis.
• RCO Deployment for reducing changeover downtime.
![Page 5: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/5.jpg)
• Analysis of Data Starting from 1st January, 2016 till July end.
• Analyse the downtime of different changeovers shift wise and brand wise.
• Driving the conclusions to select target areas for RCO.
![Page 6: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/6.jpg)
• Late shift has mostly less downtime than early & night shifts.
• Change Over from CBPM to PG.
![Page 7: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/7.jpg)
• Change Over from CBPM to B&H.
![Page 8: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/8.jpg)
• Change Overs from PG-CBPM
• Total Number of Change Overs = 14
• Minimum Downtime = 0:15
• Maximum Downtime = 6 :00???
• Average Downtime = 1:55
![Page 9: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/9.jpg)
• RCO stands for Rapid change over.
• Each element of the changeover is analyzed
to see if it can be eliminated, simplified,
moved or streamlined.
• NASCAR Pit Crew a simple demonstration
of RCO.
![Page 10: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/10.jpg)
• Reduced downtime. (Increased OEE).
• Increased capacity.
• Greater flexibility.
• Reduced stock.
• Improved responsiveness to customer demand.
![Page 11: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/11.jpg)
ProcessMapping
SeparateExternalElements
OrganizingExternalElements
ConvertInternal toExternal
Streamline
Remaining
Elements
ContinuousImprovement
![Page 12: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/12.jpg)
• The target area for the pilot SMED program is selected. Ideal line have the following characteristics.• Duration
• Variation
• Opportunities
• Familiarity
![Page 13: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/13.jpg)
• Analyzing all the steps of changeover. (Process Mapping)
• Change Overs time can be nearly cut to half with this step only.
• Examples: Retrieval, Inspection, Cleaning, Quality.
![Page 14: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/14.jpg)
• Advance preparation.
• Modularize.
• The remaining elements are tried to simplify.
• Following techniques could be used: release, Motion, Parallel operations.
![Page 15: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/15.jpg)
• Always keep looking for further improvements• New Technologies.
• New people-New Ideas.
• New premises or changes to layout.
![Page 16: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/16.jpg)
Step 1: Process Mapping
![Page 17: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/17.jpg)
Step 2: Separate External Elements
![Page 18: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/18.jpg)
Step 3: Organizing External Elements• The blanks could reach before the process stop.
• The cleaning of surrounding could be done before stopping.
• The quality check could be done either after running the machine. To stop the machine was not a good idea.
• There was a jam and operators were not technical so it took time to clear the jam.
![Page 19: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/19.jpg)
Step 4: Convert Internal Elements to External• Removing wastes from the surroundings of machine.
Step 5: Streamline remaining elements• Use two code & date printers.
Step 6: Continuous Improvement• Keep analyzing to make improvements.
![Page 20: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/20.jpg)
Process Mapping
![Page 21: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/21.jpg)
• After process mapping separation of activities was done.
• Separating activities in the categories like Value Added, Not Value added nut required, delay etc.
• Time optimization of different activities.
• Separating external & Internal activities.
• Streamlining internal activities.
![Page 22: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/22.jpg)
![Page 23: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/23.jpg)
• Proper Preparation.
• Eliminating delay like discussions during work, remaining Idle, Long lunch and tea breaks.
• Training Operators specifically for changeovers.
• Standardize all necessary nuts, bolts etc.
• Give timelines to workers.
• Moving Internal activities to external.
![Page 24: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/24.jpg)
• Changes in methods. Like segregating external and internal,Eliminating delays etc.
• Changes in methods are not expensive and can generate significantreductions in setup time.
• Once the benefits have been realized from the methodsimprovements mechanical modifications can be explored.
![Page 25: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/25.jpg)
• Area sorted and cleaned.
• Use of shadow boards for hand tools.
• All necessary tools nearby.
• Incoming and outgoing areas are clearly defined.
• Dedicated tool or tie carts for each machine station and worker.
• Visual flow of work through the area.
![Page 26: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/26.jpg)
• Machine Operators.
• Setup Crew.
• Mechanic/Maintenance.
• Quality.
• Planning.
• Others as needed.
Anyone touched or affected by setup times should be involved!!!
![Page 27: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/27.jpg)
• The Changeovers downtime can be significantly reduced by deploying RCO.
• More than 40% setup time can be reduced by eliminating delays, proper planning, Segregating external and internal activities.
![Page 28: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/28.jpg)
![Page 29: Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST](https://reader031.vdocuments.us/reader031/viewer/2022022419/58876f1a1a28ab22358b61d3/html5/thumbnails/29.jpg)