interconnection business
TRANSCRIPT
![Page 1: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/1.jpg)
Distributed Generation &On-Site Power Conference
New OrleansMarch 21-22, 2001
Presented by N. Richard Friedman
DG Interconnection & the Business Deal
Resource Dynamics Corporation 8605 Westwood Center Drive
Vienna, Virginia 22182703/356-1300, Ext 203 | [email protected]©Copyright 2001 Resource Dynamics Corporation
![Page 2: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/2.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal2
The Return of Distributed Generation
• “Reappearing” After a Long Absence• The Concept of Distributed Power is Not
New– “Total Energy” experiment in the 1960s– Packaged cogeneration of the 1980s
![Page 3: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/3.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal3
What’s the DG Buzz About?• Restructuring Presents DG Opportunities
– Price rises & supply availability cause concern– Numerous applications are cited, including grid
support• Many DG Technologies in Marketplace
– New technologies being commercialized– Ambitious improvements slated for old standbys
• Environmental Restrictions Add Complexity– High price regions overlap with non-attainment areas– NOx control cost burdens smaller units
![Page 4: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/4.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal4
What’s the DG Buzz About? (cont.)• Availability and Price of Natural Gas• Increasing Sensitivity of Electrical Equipment
and Concern for Power Quality• Heightened Reliability Awareness• New Business Opportunities for Energy
Companies• Interconnection A Potential Barrier - “But Help
is On the Way”
![Page 5: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/5.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal5
Electric Power Systems Not Designedfor Distributed Power Resources
• Utility Circuits Typically Radial, Designedfor “1-Way” Operation
• Selling Power into the Grid Was Not anIssue Until PURPA
![Page 6: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/6.jpg)
The Electric Power System
![Page 7: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/7.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal7
A Number of Service Layers
![Page 8: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/8.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal8
Transmission and DistributionSystem Voltage -
DG Interconnection Where?
![Page 9: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/9.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal9
Interconnection is Not a New Issue• Customer Generation Has Been Around for Over 50
Years (Frequently CHP)• Interconnection of Larger Generator (> 25MW)
Accomplished at Customer-Owned Substation• Smaller Projects Used All Power On Site,
Paralleling Grid for Backup/Supplementary Power• Power Sometimes Provided to Grid in Emergency
and Special Situations
![Page 10: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/10.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal10
When Did InterconnectionBecome a Concern?
• Smaller, Most Gas-Fired Reciprocating Engine• Manufacturers and Gas Companies Frustrated by
Inability to Sell Their Technology to Customersin Late 60s -- Zeroed in On Gas Cogeneration
• Market Problems They Identified:– Not Economic to Install Full Capacity Backup– Utility Refusal to Interconnect for Backup
![Page 11: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/11.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal11
When Did InterconnectionBecome a Concern (cont.)?
• Impact of Arab Oil Embargo Dramatic– New Energy Conservation Initiatives– Lines for Gasoline– Image of President Carter in Sweater in 650 Office– Pushed 1978 National Energy Act
• National Drive to Achieve Energy Independence
![Page 12: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/12.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal12
Interconnection Then GetsSome Attention
• PURPA and NGPA Highlighted Renewables andCogeneration (Lobbyists Active)
• Focus Was on Availability of Backup Power andSale of NUG Power at Utility “Avoided Cost”,Not On Details or Costs of InterconnectionArrangement
• Result: Utilities Left Alone to SpecifyRequirements
![Page 13: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/13.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal13
Utility Motivations in Past• Maintain Grid Stability and Reliability• Minimize Problems from Uncontrolled Customer
Generation• Obtain Protective Relaying to Protect the Grid• Discourage Customer Generation
– Discount Retail Rates– Discredit Customer Cogen Proposals– Take a Position in Development of Project
![Page 14: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/14.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal14
Interconnection is Not a Simple IssueUtility Concerns
• Electric Power Distribution Systems Designedfor One-Way Operation
• Personnel Safety and Grid Stability AreDominant Concerns
• Utilities Reluctant to Rely on Unfamiliar,Customer-Supplied Protective RelayingSchemes
• Integrated Interconnection “Packages” NotGenerally Accepted and Known
![Page 15: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/15.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal15
Interconnection is Not a Simple IssueCustomer Concerns
• Utility Interconnection Costs Can Be a “DealBreaker” for Smaller-Sized Projects
• Some Requirements Not Understood byCustomer, and May Appear Unreasonable
• Manufacturer, Customer and Utility DGActivities are Frequently Not Coordinated
• Interconnection Requirements Are Far FromStandard
![Page 16: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/16.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal16
Interconnection Getting MoreAttention Today
• New Vendor Packages Available, Often IntegratedWith the Inverter
• Under the EEI Umbrella, Utilities Identifying Issues ofConcern
• Interconnection Being Addressed at State Level• Interconnection “Flagged” in Senate Proposed
Legislation• IEEE Standards Coordinating Committee Developing
Interconnection Standard
![Page 17: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/17.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal17
IEEE Interconnection Standard• Being Developed by IEEE SCC21-P1547• Responsible for Standards Development in
Areas of– Fuel Cells– Photovoltaics– Dispersed Generation– Energy Storage
• Reports to IEEE Standards Board
![Page 18: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/18.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal18
IEEE Interconnection Standard• Title: Standard for Interconnecting Distributed
Resources With Electric Power Systems• Purpose: Provide a Uniform Standard for
Interconnection of Distributed Resources WithElectric Power Systems, and RequirementsRelevant to the Performance, Operation, Testing,Safety Considerations, and Maintenance of theInterconnection
![Page 19: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/19.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal19
IEEE Standards Committee Plans
• Spring 2001 Balloting Completion Date• Working Group of Over 300• Meetings Every 2 Months• Richard DeBlasio, NREL is Chair
![Page 20: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/20.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal20
Examples of Some States NotWaiting for IEEE
• New York• California• Vermont• Texas• Delaware
![Page 21: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/21.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal21
Interconnection ConcernsCovered in Standard
• Safety• System and Equipment Protection• Power Quality and Reliability
![Page 22: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/22.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal22
Technical Requirements Fall IntoSeveral Categories
• General• Response to Abnormal Conditions• Power Quality• Islanding
![Page 23: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/23.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal23
Defining Area and Local EPS
Local EPS 1
Area EPS
LoadDR unit
Local EPS 3
Load
PCC
Point of DRConnection
PCC
DR unit
Local EPS 2
Point of DRConnection
PCC
Note: Dashed lines are EPS boundaries. There can be any number of Local EPSs.
![Page 24: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/24.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal24
DG Interconnection Process
DRAreaEPS
Interconnection
![Page 25: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/25.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal25
General Requirements• Voltage Regulation & Reactive Power
Support• Integration with EPS Grounding• Synchronization• DR on Distribution Spot Networks• Inadvertent Energizing of Area EPS• Monitoring
![Page 26: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/26.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal26
Response to Abnormal Conditions
• Voltage Disturbances• Frequency Disturbances• Disconnection for Faults• Loss of Synchronism• Feeder Reclosing Coordination
![Page 27: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/27.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal27
Power Quality• Limitation of DC Injection• Limitation of Voltage Flicker Induced by the
Distributed Generator• Harmonics• Immunity Protection• Surge Withstand Capability
![Page 28: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/28.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal28
Islanding
• Prevention of Islanding at Point of CommonCoupling
• Intentional Islanding
![Page 29: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/29.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal29
Future IEEE SCC21-P1547 Activities
• Draft 7 Out for Ballot Now• Next Meeting - April 18-20, New Orleans• Several New 1547 Projects Initiated
– Applications Guide– Communications– DG Textbook– Networks
![Page 30: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/30.jpg)
2/2001-3/2001WG Ballot
Liaison FinalReview
4/2001Ballot ResolutionP1547 Meeting
4/2001(6/2001)Working Groupapproves draft toREVCOM and
IEEE-SAStandards Board
6/2001IEEE
StandardsBoard approval
1st try
12/2001Publish as
IEEEStandardsFINISH
Working GroupGoal
Editing andPrinting
9/2001IEEE
StandardsBoard approval
2nd try
4/2001Require
Working GroupRe-ballot
Proposed Timeline for IEEE SCC21 Standards Development ProjectP1547-Standard for Distributed Resources Interconnected with Electric Power Systems
![Page 31: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/31.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal31
Source: EPRI Report TR111489
Typical Engine Generator DR
![Page 32: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/32.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal32
Interconnection & the Business Deal• Power Quality and Reliability
– Interconnection Hardware May Reduce Costs– DG Can be a Negative Impact
• Dispatchability– Interconnection Hardware May Reduce Costs– Communications the Open Issue
• Serving the Internet Economy– Interconnection “Black Box “ Developments– Complex Interconnection Arrangements
![Page 33: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/33.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal33
Power Quality & Reliability
• DC Injection• Light Flicker• Harmonics
![Page 34: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/34.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal34
Dispatchability
• Genset Control Module• Human-Machine Interface (HMI)• Communications Interface/Hardware &
Software• Power Management Software• Monitoring & Metering Module
![Page 35: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/35.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal35
Genset Control• Supplied by
– engine manufacturer– software vendor (retrofit & OEM market)
• Must communicate with powermanagement module
• Integrated control software offeringincreased flexibility
![Page 36: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/36.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal36
HMI at the Genset• Membrane keypad typical• Status monitor for operator
HMI at the Control Room• Data & event logging• Data trending• Alarm display and annunciation
![Page 37: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/37.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal37
Communications Interface & ControllerHardware/Software Platforms
• Widely accepted protocols preferable– e.g., Modbus, Echelon LonWorks– PC technology/Windows operating
environment– Relational databases (e.g., SQL, OLE)
• Proprietary microprocessors an alternative(e.g., Onan)
![Page 38: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/38.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal38
Power Management SoftwareCharacteristics
• Interface with digital electronic governor• Synchronize frequency• Share real & reactive power loads• Manage power factor and VAR• Protect genset and personnel• Ramp genset loading• Offer data processing options
Goal - complete array of functions
![Page 39: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/39.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal39
Monitoring & Metering Module• Monitor major parameters for genset
operation• Key functions
– utility grade metering– data trending for display
• Option to regulate and operate with grid• Addition of remote communications for
dispatch
![Page 40: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/40.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal40
Applications of the Internet Economy
• Web-Hosting Companies• Internet Service Providers• Call Centers• Credit Card Processing Centers• Telecom Service Centers• Other
![Page 41: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/41.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal41
Data Centers Typically Have:• Robust physical security• Raised floors• Fire suppression equipment• Strict climate control, including large
HVAC systems• UPS systems• Backup power• Redundant connections to the Internet
backbone and grid
Complexinterconnectionarrangements
![Page 42: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/42.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal42
What is the Issue?• Availability of electricity to serve Internet-
related applications• 10-40 MW per location/50-130 w/ft2
• 12-18 month lead times• 10-25 percent of new load• 60 million ft2 of new facilities by 2001• Some 6,000-8,000 MW of new load
The Ultimate Need ------------> Information Quality Power
![Page 43: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/43.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal43
Examine CustomerBusiness Perspective
• Energy cost reduction– part of general business goal to lower/control costs– reflected in minor budget savings– frequently obtain new equipment with no upfront capital
outlay
• Outage cost reduction– gets to the core customer business– requires customer sophistication to value outage cost– much higher value savings
![Page 44: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/44.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal44
Assured Power Services Attraction
• High 6 - 9s reliability for mission criticaloperations (e.g., internet, telcom, other)
• Outage cost reduction perspective highvalue to customer
• Need to understand what this really meansto customer
![Page 45: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/45.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal45
The Reality of the 9sReliability (%)
1 - 9 90 876 Hours2 - 9s 99 88 Hours3 - 9s 99.9 9 Hours4 - 9s 99.99 53 Minutes5 - 9s 99.999 5 Minutes6 - 9s 99.9999 32 Seconds7 - 9s 99.99999 3 Seconds8 - 9s 99.999999 19 Cycles9 - 9s 99.9999999 2 Cycles
Total Outage Time/Year
![Page 46: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/46.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal46
How Much Reliability Do You Get?
• Utility power: 2 or 3 - 9s, maybe• Grid plus UPS: 4 - 9s• Grid, UPS, DG: 5 - 9s• Grid, UPS, DG, nearly full battery backup: 6 - 9s
Interconnection & Transfer Switch Arrangements Can Help!
![Page 47: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/47.jpg)
ASD Input Voltage
0 10 20 30 40 50 60
Cycle
ASD DC Bus Voltage
0 10 20 30 40 50 60
Cycle
Motor Current
0 10 20 30 40 50 60
Cycle
Motor Speed
0 10 20 30 40 50 60
Cycle
ASD Motor
Consequences of a 2-Cycle Interruption
![Page 48: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/48.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal48
What Might the Future Hold?• DG as an integral and growing component of data center
design• Near-term delays in service to data centers• Increasing peak power demands of internet applications• Inability of many distribution systems to serve the data
centers• Emergence of premium power parks solely for data center
location• Major new business for DG
![Page 49: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/49.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal49
What to Expect Next?• Continued Attention to Easy, Low Cost and
“Standardized” Interconnection - Will Not Workat All Points on Utility System
• Utilities Still Nervous and Uncertain of Impact onTheir T&D Operations
• Standardized Interconnection May Not ApplyUniversally
• Improved Manufacturer InterconnectionPackages - Lower Cost, Improved Performance
![Page 50: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/50.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal50
What to Expect Next (cont.)?• Accelerated Activity at State Level Regarding
Interconnection, But Deferral to IEEE Standard• Standard Completed by Fall 2001 - Functional
Rather Than Prescriptive Approach• Utility Specification of “Preferred Points of
Interconnection” Likely
![Page 51: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/51.jpg)
Distributed Generation & On-Site Power:Impact of DG Interconnection
Requirements on the Business Deal51
What could the power system of the future look like?
![Page 52: Interconnection Business](https://reader031.vdocuments.us/reader031/viewer/2022030312/577cca1d1a28aba711a5684f/html5/thumbnails/52.jpg)
Distributed Generation &On-Site Power Conference
New OrleansMarch 21-22, 2001
Presented by N. Richard Friedman
DG Interconnection & the Business Deal
Resource Dynamics Corporation 8605 Westwood Center Drive
Vienna, Virginia 22182703/356-1300, Ext 203 | [email protected]©Copyright 2001 Resource Dynamics Corporation