integrity respect commitment passion focus results matter motiva first business confidential norco...

11
tegrity Respect Commitment Passion Focus Results Matter Motiva F Business Confidential Norco Tank Strategy Norco Tank Strategy Overview of Work / TOR Report on 0-3 year priority list Past and Present 20 Year Tank T/A Schedules Future work – about 90% done, just need to coordinate on the business side for 3+ years

Upload: phebe-marshall

Post on 29-Dec-2015

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Integrity Respect Commitment Passion Focus Results Matter Motiva First Business Confidential Norco Tank Strategy  Overview of Work / TOR  Report on 0-3

Integrity Respect Commitment Passion Focus Results Matter Motiva FirstBusiness

Confidential

Norco Tank StrategyNorco Tank Strategy Overview of Work / TOR Report on 0-3 year priority list Past and Present 20 Year Tank T/A Schedules Future work – about 90% done, just need to coordinate

on the business side for 3+ years

Page 2: Integrity Respect Commitment Passion Focus Results Matter Motiva First Business Confidential Norco Tank Strategy  Overview of Work / TOR  Report on 0-3

Integrity Respect Commitment Passion Focus Results Matter Motiva FirstBusiness

Confidential

The objective of the Process is to: Identify all Turnaround, Maintenance, Inspection, Environmental

needs for Tanks for the next 5 years Provide a defined Tank TA Schedule Identify Back-Up Tank Requirements Identify any potential Capital requirements for tankage Incorporate Tank Outage into Businesses 90 day plan Insure Tank Outages are aligned with unit T/A schedule Identify any Business Requirements/Needs for Tankage

This report-out focuses on the first 4 bullets……

Overview of Work / TOROverview of Work / TOR

Page 3: Integrity Respect Commitment Passion Focus Results Matter Motiva First Business Confidential Norco Tank Strategy  Overview of Work / TOR  Report on 0-3

Integrity Respect Commitment Passion Focus Results Matter Motiva FirstBusiness

Confidential

Overview of Work / TOROverview of Work / TOR

Sponsors Jones Devlin – Business Planning Manager John Nagy – Business Manager Alan Sullivan – Logistics CAM Mike Bilello – T/A Manager

Page 4: Integrity Respect Commitment Passion Focus Results Matter Motiva First Business Confidential Norco Tank Strategy  Overview of Work / TOR  Report on 0-3

Integrity Respect Commitment Passion Focus Results Matter Motiva FirstBusiness

Confidential

Overview of Work / TOROverview of Work / TOR

Team Members Logistics Operations - Jeff Shaw, Larry Voelkel, Larry Fryoux,

Alan Sullivan Business Planning – Ralph Guillot, Tom Waller, Kenny

Werhan Maintenance – Perry Montz, Kirby Nunez, Mike Bilello PEI – Mark Mondello

Page 5: Integrity Respect Commitment Passion Focus Results Matter Motiva First Business Confidential Norco Tank Strategy  Overview of Work / TOR  Report on 0-3

Integrity Respect Commitment Passion Focus Results Matter Motiva FirstBusiness

Confidential

Overview of Work / TOROverview of Work / TOR

The team reviewed known business plans, tank histories, and API/EPA required tank inspections to determine where schedule of tanks and business continuity needed to be immediately addressed.

The team also reviewed each hydrocarbon system to identify planned backup tanks to enable turnarounds.

And finally, the team shuffled the tank T/A schedule to flatten the year-to-year work load and cost profile for the Site, and to minimize business impacts of the outages.

Budgets for 2007-2011 planned tank inspection, maintenance, and capital work were included in 2007 T&R. Budgets include full T/A costs for tanks scheduled for RBI re-evaluation – RBI process may extend due those dates.

Page 6: Integrity Respect Commitment Passion Focus Results Matter Motiva First Business Confidential Norco Tank Strategy  Overview of Work / TOR  Report on 0-3

Integrity Respect Commitment Passion Focus Results Matter Motiva FirstBusiness

Confidential

The Priority ListThe Priority List A-415 (Crude) Tie-In Project must be completed during the 2006 DU-5 T/A.

Allows A-415 to spare the Delta and Foreign systems. 1 crude tank is in T/A each of next 3 years. (COMPLETE)

A-420 – A-416 T/A must be complete before taking A-420 out of service. F-501 (Olefins Feed – 1 year lease to Motiva) has to be emptied of the MTBE

contaminated water. Expect Complete at EOY 2007 F-473 (XC-517) is being built for sour water service allowing F-465 to return to

reformate service and have 3 reformate tanks. Only have 3 days storage with two tanks. F-516 will be placed in Reformate Service while F-464 & 465 undergo T/A. Considering F-464 T/A prior to F-465 if XC-517 completion is too far into 2008. NOTE: F-516 is 200 MBBLs, F-464/469 are 100 MBBL tanks. Could refill F-469 from F-516 to satisfy blending needs.

F-464 (Reformate) is due for T/A in September 2008. Any work on F-465 must be complete to maintain at least two (F-464/469) reformate tanks at all times. See above.

F-465 (Sour Water) is due for T/A in July 2008. XC-517 must be completed before taking F-465 out of service. F-465 to return to service as a Reformate Tank.

Page 7: Integrity Respect Commitment Passion Focus Results Matter Motiva First Business Confidential Norco Tank Strategy  Overview of Work / TOR  Report on 0-3

Integrity Respect Commitment Passion Focus Results Matter Motiva FirstBusiness

Confidential

F-432 must be cleaned prior to April 2007 to serve as backup for F-490 T/A (CCLGO). F-432 has T/A wash water /oil from RCCU and OL-5 turnarounds in it – that has to get run off. This is not a line item in budget. (Complete) F-490 in T/A

A-405 (Slop/Ballast Water) rebuild needs to be completed by September 2007. D-413 inspection and T/A is due that month – it may be possible to get a short deferral from PEI if required to complete A-405. The rebuild has been approved by both sides. DEMO Complete. XC-518 construction to be complete in the 4th quarter 2008.

D-413 – Slop Tank T/A Differed until Sept. 2008. See strategy above – use A-405’s replacement.

Reroute of DHT naphtha from slop to HCU would be needed for containment of slop oil during D-413 T/A if A-405 (XC-518) not ready. This is NEP Project 114. Need to determine where this project is prioritized.

Tanks F-516 (MTBE) and F-513/514 (Methanol) are due for RBI re-evaluation in October 2008, and could have to come out for T/A within 12 months of that date. Will hold 516 to backup 515. 513/14 might find use in slop/wastewater/caustic etc. Re-evaluation is COMPLETE per PEI AND PUSHED-OUT TO 2012. 516 to reformation service

The Priority ListThe Priority List

Page 8: Integrity Respect Commitment Passion Focus Results Matter Motiva First Business Confidential Norco Tank Strategy  Overview of Work / TOR  Report on 0-3

Integrity Respect Commitment Passion Focus Results Matter Motiva FirstBusiness

Confidential

F-492 (No.6 Oil) is due for T/A in October, 2009. One of the RCCU Residue tanks (F-511/512) will be placed in No.6 Oil service for this T/A. No change.

PV-82 (Anhydrous Ammonia) is due for T/A in June, 2009. S-2 and S-3 are the only units still using this system, and they should install permanent facilities to use aqueous ammonia prior to 2009. Item is being worked by Joe Delerno and should complete in 2006. Need to check on status of Permanent facilities for S2 & 3 – Need to Inform Joe D of this requirement.

H-432 (PyPitch) needs to be rebuilt. (Brian Lewis of SCC working). Following completion of that, the sister tank H-433 will likely need to be rebuilt. H-433 inspection is due in April 2009, after receiving a 36 month deferral from PEI due to issues with H-432. SCC working on IP for H-432 rebuild.

F-455 – Roof Coating & Temp Roof Patches. Plan on 2007 completion due to roof condition and tankage due in 2008 for T/A. Will use existing storage (458 / 440 / 515 / 481). This needs to be complete before F-458 comes out of service.

F-468 – Roof Coating needed. Need treated naphtha routing to F-463 prior to addressing F-468 roof coating. F-468 is due in 2007. Tim Brewer spec’ing out new control valve for treated naphtha routing to F-463

F-442 – Roof Draining replacement and upgraded seal. COMPLETE F-444 – Replacing Roof, working. Possible Floor repairs and mud jack (raise the floor due to sag) F-502 - Begin T/A November 1, 2007. Use F-495 as a replacement. F-433 – clean and idle tank. Waiting for direction from SCC. F-497 - SCC to determine disposal of material currently in the tank. Emulsion unable to be broken. Using F-496 now. F-497 is idle. S-Tanks (Update pending Curtis Lloyd & CUUSA). Currently no S-Tanks are due for T/A in 2007/2008/2009. F-456 – Due for T/A in August 2008. Use F-442 (SU). Business Planning may decide to convert one RU tank if they like. Loosing F-456 brings us

down to only one SU tank. F-458 - Due for T/A in January 2008 . Will use existing storage (455 / 440 / 515 / 481). Business Planning may not want to take both an SU and RU

tank Out of Service at one time. F-472 – Gas Oil Tank. Due to T/A in October 2008. No alternative storage needed. We should investigate adding mixers and tying this tank into the

DHT cold feed charge system W-428 – Wharf Sump. Due for internal inspection in January 2008. Investigate online inspection. Investigate replacement vessel to minimize wharf

outage. W-427 – Wharf Sump. Due for internal inspection in February 2009. Investigate online inspection. Investigate replacement vessel to minimize wharf

outage. W-435 – Due for inspection in December 2008. This an old drum yard storm water storage tank. This tank is idle. PV-80 – Fish Tanks – Due for inspection in November 2008 (Foreign Fish). Dewater using the Delta Fish. Outage typically takes two weeks to

complete. F-436 – VGO charge tank - Due to RBI Evaluation in December 2008. Use F-438 as the RCCU charge Tank. This limits the water removal

capabilities on the Cat Feed System. A-413 – Due to T/A in July 2009. Need to determine what are the Delta Tank needs in 2009. See Business Planning if in batch operation. PV-122 – Due for inspection in April 2008. F-453 – RBI internal inspection April 2009. F-478 – Due for T/A in January 2009. Use F-477 as a replacement. Mixed gasoline tank. F-494 – RBI internal inspection September 2009.

The Priority ListThe Priority List

Page 9: Integrity Respect Commitment Passion Focus Results Matter Motiva First Business Confidential Norco Tank Strategy  Overview of Work / TOR  Report on 0-3

Integrity Respect Commitment Passion Focus Results Matter Motiva FirstBusiness

Confidential

Original Tank T/A ScheduleOriginal Tank T/A SchedulePRODUCT ASSURANCE TANK INSPECTION SCHEDULE

LAST REV. 2-10-06

IDLE 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 <2026

A-404 A-407 A-416 A-420 A-413 F-432 F - 436 F - 435 W-411 F-442 F-503 A-414 M-419 A-419 A-417 A-418 A-415 F-434 W-409 F-471

A-405 F-477 D-413 F-456 F-453 F-499 F - 438 F-455 S-412 F-482 PV-500 F-444 W-

411

F-425 F-462 F-476 W-412 F-509 F-443

A-408 F-483 F-433 F-458 F-466 PV-493 F - 440 F-469 K-

478

PV-501 F-467 F-484 F-488 F-485 F-481 W-416 F-454 F-457

A-409 F-495 F-465 F-464 F-478 PV-494 F - 441 F - 510 D-

422

PV-502 F-468 F-500 W-406 F-501 F-480

A-412 K-562 F-490 F-472 F-492 PV-495 F - 463 K - 558 F-496

B-450 F-497 F-491 PV-122 F-494 PV-496 F-479 S-405 F-509

B-451 S-408 F-502 W-428 H-433 S-404 F - 487 S-407

F-430 PV-681 W-435 PV-82 S-413 F - 493 S-409

F-431 S-406 W-427 S-414 F - 498 S-410

F-450 F-504 S-411

F-451 F-505 S-417

F-473 F-506 W-414

F-515 F-507

G-402 F - 511

G-403 F - 512

H-432 F - 513

H-434 F - 514

H-435 F - 516

H-436 PV-497

H-437 PV-498

PV-499

PV-503

S-403

S-415

S-416

W - 410

W - 437

W - 438

Page 10: Integrity Respect Commitment Passion Focus Results Matter Motiva First Business Confidential Norco Tank Strategy  Overview of Work / TOR  Report on 0-3

Integrity Respect Commitment Passion Focus Results Matter Motiva FirstBusiness

Confidential

Revised Tank T/A ScheduleRevised Tank T/A SchedulePRODUCT ASSURANCE TANK INSPECTION SCHEDULE

LAST REV. 4-11-06

IDLE 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 <2026

A-404 A-407-12 A-416-4 A-420-10 A-413-7 F-432-4 F-479-4 F-455-2 F-442 F-503 A-414 M-419 A-419 A-417 A-418 A-415 F-474 F-434 W-409 F-471 F-470

A-405 F-477-9 D-413-9 F-456-8 F-453-4 F-499-10 F-504-8 F-469-8 F-482 F-467 W-411 F-425 F-462 F-476 W-412 F-454 F-443

A-408 F-483-8 F-433-5 F-458-1 F-478-1 F-506-7 F-505-8 W-414-6 K-478 F-468 F-466 F-488 F-485 F-481 W-416 F-457

A-409 F-495-7 F-465-7 F-464-9 F-492-10 F-507-1 PV-499-11 D-422 F-484 F-500 W-406 F-501 F-480

A-412 K-562-5 F-490-4 F-472-10 F-494-9 PV-493-5 F-475 F-496

B-450 F-497-5 F-491-5 W-428-1 H-433-4 PV-494-6 F-509

B-451 S-408-9 F-502-11 W-435-12 PV-82-6 PV-495-5

F-430 F-444-? W-427-2 PV-496-5

F-431

F-450

F-451

F-473

F-515

G-402

G-403

H-432

H-434

H-435

H-436

H-437

F-463

F - 493

*** IDLE *** *** INTERNAL INSP. DUE DATE *** ***RBI INTERNAL INSP. DATES*** *** RBI Evaluation Date*** ****Onstream Posible****

Page 11: Integrity Respect Commitment Passion Focus Results Matter Motiva First Business Confidential Norco Tank Strategy  Overview of Work / TOR  Report on 0-3

Integrity Respect Commitment Passion Focus Results Matter Motiva FirstBusiness

Confidential

Revised Tank T/A ScheduleRevised Tank T/A SchedulePossible Onstream and RBI re-evaluation dates

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2

0

2

3

2024 2025 <2026 2006

PV-681-5 F-436-12 F - 438 - 12 F-487-3 F - 498 - 11 F - 435 - 12 S-412 PV-500

S-406-3 F - 513 - 10 F - 440 - 12 F - 511 - 10 F-512-10 F - 510 - 6 PV-214-9 PV-501

F - 514 - 10 F - 441 - 12 S-404-4 W - 410 - 11 K - 558 - 6 PV-215-1 PV-502

F - 516 - 10 S-413-12 W - 437 - 9 S-405-6

PV-122-4 S-414-11 W - 438 - 10 S-407-5 XC-363

S-403-1 S-409-4

S-415-10 S-410-5

S-416-11 S-411-5

PV-497-8 S-417-5

PV-498-11

PV-503-8

*** IDLE *** *** INTERNAL INSP. DUE DATE *** ***RBI INTERNAL INSP. DATES*** *** RBI Evaluation Date*** ****Onstream Posible****