integration of the construction estimate in construction ... · integration of the construction...
TRANSCRIPT
Integration of the Construction Estimate in
Construction Programe
Construction Project Managment Model
Pedro Alexandre Amaral Lopes
Extended abstract of thesis to obtain the Degree of Master in
Civil Engineering
Jury
President: Prof. Albano Luís Rebelo da Silva Das Neves e Sousa
Supevisor: Prof. Pedro Miguel Dias Vaz Paulo
Vowel: Prof. Nuno Gonçalo Cordeiro Marques de Almeida
October, 2013
1
1. Introduction
Bearing in mind the current economic crisis, the hardships that are being felt by the
construction industry are increasing as companies seek to systematically to reduce their
costs whilst maintaining their levels of competitiveness.
Thus, as companies from the construction industry seek substantial improvements in
project results, a plethora of project management and production control software
packages are evolving and are being implemented.
Further gains can be achieved by implementing integration of the construction estimate
with the construction program during the construction phase of the project, with the
objective of managing the cost and duration control of the project more efficiently.
By introducing and linking together the construction estimate and construction schedule
in one software package, at the beginning of the construction phase, forecasts can be
obtained, and if the progress and production data are systematically introduced during
the construction phase, comparisons can be made against the base forecasts and critical
information such as cost and schedule deviations can be obtained efficiently and with
ease, providing decision-enabling facts for implementing timely corrective measures.
The primary objective of this investigation is to demonstrate to any construction
company that is interested in improving its results and competitiveness, that the
implementation of the chosen methodology will provide a more effective and efficient
cost and time control of its projects. The methodology that is analyzed is that the
estimating and planning schedules be linked dynamically using just one software
package.
2. State of Art
This chapter intends to conduct an analysis of the State of Knowledge of Integrated
Project Management, specifically some “good practice” rules of Cost and Time control
in construction projects, and to present the most relevant information within this
subject.
2
2.1 Project definition
The Project Management Institute (PMI) defines a Project as a temporary group of
outlined activities to produce a unique product, service or result. It is temporary because
it has a beginning and an end within a specific period of time and therefore resources
and scope is also defined.
A project must meet certain specific objectives and must be completed within schedule
and it also must be completed within a stipulated budget and satisfy all the project
quality requirements (Lester, 2007).
2.2 Project Management
Project Management can be defined as the planning, monitoring and control of all
aspects of a Project in order to achieve all the objectives within the criteria of time,
costs and agreed performance. (Lester, 2007).
It’s also the art of directing and coordinating all human and material resources during
the lifetime of the project using modern management techniques to achieve predefined
objectives such as the scope, cost, time, quality and stakeholder satisfaction (PMI).
2.3 Planning and Time Control
Given the uncertainty and complexity inherent to the construction projects, planning
becomes an activity with a high degree of difficulty for project managers, given their
constant need to provide and coordinate all tasks to be performed and control them
during their execution (Lia et al., 2009).
Planning is a key activity in the construction industry both in its management and
during its execution. Developing a plan to manage a project involves several phases,
from decision making in order to devise a project with the development of different
solution to achieve this objective, to the definition of the tasks to be performed in the
project; the estimated physical and financial resources; the determination of the activity
durations and finally the identification and interconnection between the different
activities. (Hendrickson & Au, 1989 & Angelim, 2009).
The bar charts are by definition the representation of the project activities in function of
time in the form of horizontal lines, usually without any connection between them.
These bar charts emerged based on the work of Henry Gantt, mainly dedicated to the
construction industry – Gantt Bar Charts (Figure 1). In such bar charts, the activities
3
durations are estimated and the bars are drawn, respectively, for each activity,
depending on its duration, its beginning and its end in the chart (Mubarak, 2010).
Figure 1 – Gantt Chart with activity links
These bar charts present some advantages to the Project manager (Table 1). A graphic
representation of the information makes the process simpler to analyze the project
without requiring any special training or using any complex calculation methods. It
provides a more accurate view of the estimated activities' durations and consequently of
the entire project, enabling a greater understanding of the all involved parties such as
the client, the subcontractors and to the contractors’ managers.
Table 1 – Advantages and Disadvantages using the Gantt Bar Chart
Gantt Bar Chart
Advantages Disadvantages
Graphical representation of the
information
Simpler analysis of the activity
durations
Earlier forecasts of the resource usages
in the activities
Logical connections in projects with a
large number of activities
Great difficulty to understand the
consequences between activities, if not
properly connected
The Critical Path Method (CPM), one of the most widespread techniques in planning, is
specially oriented to a Project with a large number of individual activities, as is the case
for most construction projects (Baker, 2010).
Through CPM is possible to determine:
the project duration with a complex activity network
4
critical activities, i.e. activities that must be performed in time under the risk of
delaying the entire project
CPM defines the predecessors/successors activities sequence that determines the
minimum time to complete the project, i.e. any delay in activities that are part of the
critical path (critical activities) will cause a delay of the completion date of the entire
project.
2.4 Estimating and Cost Control
The cost estimate is one of the most important processes in project management. The
cost estimate or the initial budget allows the establishment of the cost basis for the
different phases of construction, and represents the estimate of the present contractual
scope of works. Engineering experience and the expertise are of great importance in the
application of the principles and techniques of estimating in order to reduce problems
with the cost control and specially to increase profits and maximize revenues
(Hendrickson & Au, 1989).
Estimating or making an initial budget means determining the approximate amount of
resources, time and all the costs required to develop a project, in order to obtain the
necessary information to make critical decisions in all aspects of developing a
construction project (Carr, 1989).
Nowadays, almost every company uses software systems for estimating and cost
control. Whilst price estimates and initial budget determination are performed before the
production phase of the project, cost control has to be realized throughout its entire
execution (Azhar et al, 2002).
3. Analysis and Interpretation of the results of the Enquiry
Through this inquiry it was possible to become aware of the reality in some companies,
particularly in relation to the planning and estimating systems. Since these two
procedures are essential in project management and are unequivocally used in
construction companies, regardless of their size, it was important to know how
companies implement these systems and the importance they have in the organization
(Table 2).
5
Currently, one of the main problems that have hindered the optimization of procedures
in cost and time control within construction organizations is the difficulty that they have
in integrating the Planning schedule with the Estimate. In general, the use of various
software packages for project management has exacerbated this situation.
Table 2 – Key aspects of the implemented Planning and Estimating systems in the companies
Planning Estimating
Very important in Project
management
Average satisfaction with its
application
Periodicity: Weekly and Monthly
Most commonly used software
package: MS Project
Presents gaps in planning detail and
time control
Responds satisfactorily to the needs of
companies
Very important in Project
management
Average satisfaction with its
application
Periodicity: Monthly
Most commonly used software
package: Candy, Microsoft Excel,
SAP
Responds satisfactorily to the needs of
companies
4. Presentation of the Planning and Estimating Management Systems
This chapter describes the Independent System Planning and Estimating Management
and the Integrated Planning and Estimating Management System. First a brief
description of the procedures in common use is made and then the Integrated System is
referred to and described. This is the proposed model for integrating planning and time
control with the estimating and cost control, in order to achieve the objectives proposed
for this investigation.
4.1 Planning and Estimating Management Independent System
Currently the most implemented management and time control system in construction
companies is the Independent System. This system is characterized by the separation
between planning and time control from the estimating and cost control. Commonly,
construction companies plan and estimate the entire project and then carry out the
project’s time and cost control using separate software packages. This procedure
reinforces the separation of the two data streams, as often the software package do not
share compatible data.
6
4.2 Planning and Estimating Management Integrated System
Given the fierce competition in the construction industry and the companies’ needs to
respond in a faster, effective, efficient and most profitable way to the costumers’
requirements, the interconnection between Planning and Estimating, for an integrated
approach to project management, has becoming more and more important.
Figure 2 and Figure 4 are representations of the proposed model in this investigation.
Figure 2 – Analyzed Model for the Planning and Estimating interconnection
Figure 3 – Proposed Model Diagram
7
In Table 3, we can see the main differences between the two Management Systems
previously described.
Table 3 - Comparative analysis of the two Planning and Estimating Management Systems
System Features Independent
System
Integrated
System
Cost and time Control Separate Integrated
Number of software packages used Several One
Investment in Planning and Estimating
professional software packages High Optimized
Compatibility between the Project cost
and time control
Depends on the
compatibility of the
software package
Integrated and
synchronized
Time and resources spent for updating
and synchronizing the project costs and
deadlines
Vast Reduced
Monitoring the consequences of the
changes (cost or deadline) during the
project execution
Depends on the chosen
computer systems. Cost
and Time updates are
slow and with high
probability of
synchronization errors
Immediate
Detail for the project cost and time
forecasts Scarce
Abundant and
Diverse
Investment in Human Resources and
Formation
Lengthy training in
multiple software
packages
Higher investment
Rapid training in
one software
package
Lower investment
5. Case Study Presentation
This chapter aims to identify and analyze the project management processes, mainly the
cost and time control, by the Portuguese subsidiary company SPIE BATIGNOLLES
EUROPE, through the analysis of the methodologies that were applied in a specific case
study, a construction project that has been successfully executed.
The analyzed Integrated System model is applied to this case study so that the benefits
and advantages that it could bring to the project management can be represented.
The procedures for Planning and time control as well for Estimating and Cost control
management are well defined within the SPIE BATIGNOLLES organization. The
company mainly uses their own software package and Microsoft Project to perform
8
their Projects’ Planning and Time Control requirements. Estimating and Cost Control,
are accomplished using the Construction Computer Software (CCS) – Candy System.
This chapter intends to apply the proposed model to the case study and evaluate the
Integrated System Implementation in the organization and to present the advantages in
cost and time control management.
5.1 Cost Control
By implementing this Integrated System, it is possible to obtain data regarding the
current state of the project as well as its future, reliably, securely and quickly.
Thus, any change in the resource cost or in its consumption to in any bill item, will be
reflected dynamically in all of the reports and the documents that are available in the
software package, and this information, if used correctly, will allow the project
managers to make informed decisions whenever to improve the Project’s final cost and
completion date. This is true both when establishing the base forecast and at any stage
during the execution phase of the Project.
5.2 Time Control
With the implementation of the analyzed model, the activities durations and the project
deadlines are also critical for the Projects’ cost forecasts. Thus, any changes in the
activity program will affect the time element resulting changes in the previous forecasts.
Figure 4 – Activitiy Program with a delay of 10 days in the selected activity
Figure 4 presents the consequences to the entire program of the change of a duration of
one activity.
9
Analyzing the results of this change in the case study, there are some advantages that
can be easily presented in the proposed model implementation for project management
(Table 4).
Table 4 – Advantages in the implementation of the Integrated System analyzed model
Planning and Estimating Management Integrated System
Cost and time control integration in a single software package
Reduction in costs related to the investment in cost and time control software
packages
Faster monitoring of the updates of costs and deadlines
Constant updates of the Project status
Synchronized forecasts of costs and deadlines during project execution
Forecasts with greater anticipation of changes and verification of the effect of
changes on the Project’s cost and deadlines
Reducing the number of meetings needed to update and integrate the different
cost and time control software packages
Possibility to spread the items’ quantities over the activities’ durations and
obtain dynamic forecasts
Constant comparisons of current costs and deadlines against the planned costs
and deadlines.
6. Conclusions
6.1 Results and Proposed Objectives Evaluation
The results obtained from the dynamic interconnect of the estimating schedule with the
planning schedule allow one to conclude that the implementation of this method meets
the expectations initially proposed. The data that is available in the software package’s
reports, effectively present the Project’s current status including change of scope,
current progress and real costs to date, and forecast the future cost and date of
completion if no steps are taken by the project managers.
6.2 Contributions and innovative aspects
Note that this is a very simple and effective model to apply in project management and
monitoring, and presents the current project status as well the forecasts of its status
through explanatory reports and other able performance indicators.
10
One of the most innovative aspects of this model is the interconnection of the activities
from the planning program with the items from the bill of quantities as well with the
budget in one software package. This process reduces the workload required in making
compatible data produced of the two different cost and time control software package so
that it can be analyzed.
6.3 Future Works
Since the application of this model in a single case study wasn’t ideal, it’s suggested for
further investigation that this model be applied to a larger number of case studies, such
that results can be obtained of its implementation in different kinds of projects and
environments and also to quantify the benefits that are gained with its implementation.
References
Angelim, V. L. (2009) – Planning and Production Control in Construction Works based on
Lean Construction Principles (Planejamento e Controle da Produção de Obra baseado em
Principio da Construção Enxuta) – Fortaleza
Azhar, S.; Ahmed, S. M. & Caballero, A. A. (2002) – Development of an Integrated Cost
Estimation and Cost Control System for Construction Projects – National Institute of Standards
and Technology, Gaithersburg, Maryland
Bhaba R. S.; Pius J. E.; Liao, T. W. & Yu, F. (2012) - Planning and design models for
construction industry: A critical Survey - Automation in Construction, Vol. 22, pages. 123 –
134
Bowers, J.A. (2000) - Interpreting float in resource constrained projects – International Journal
of Project Management, Vol. 18, pages. 385-392
Carr, R. (1989) – Cost Estimating Principles - Journal of Construction Engineering and
Management, Vol. 115, pages. 545-551
Chagas, A. K. (2007) – Cost and schedule Integrated Management – The Earned Value
Management – Master Degree Thesis (Gestão Integrada de Prazos e Custos – O Método do
Earned Value – Dissertação de Mestrado) - Instituto Superior Técnico
Chelaka, M.; Abeyasinghe, L.; Greenwood, D. J. & Johansen, D. E. (2001) - An efficient
method for scheduling construction projects with resource constraints – International Journal of
Project Management, Vol. 19,pagess. 29-45
Fernandes, M. N. (2008) – Energy Systems Business Management – Application of the Earned
Value Management Methodology – Master Degree Thesis (Gestão de Negócios de Sistemas de
Energia Aplicação da Metodologia Earned Value Management (EVM) – Dissertação de
Mestrado) – Instituto Superior Técnico
Fleming, Q.W. & Koppelman, J.M. (2002) – Earned Value Management: Mitigating the Risks
Associated with Construction Projects - Risk Management
Fonseca, A. (2006) – Schedule Control in Construction – The Earned Value Management
Methodology – Master Degree Thesis (Controlo de Prazos na Construção - A metodologia
Earned Value, Dissertação de Mestrado) – Instituto Superior Técnico
Grant, B. & Kelly, K. (2009) – The Evolution of Project Management - University of Phoenix
11
Hadju, M. (1997) - Network Scheduling Techniques for Construction Project Management –
Kluwer Academic Publishers
Hendrickson, C. & Au, T. (1989) – Project Management for Construction – Prentice Hall
Henriques, A. (2008) – Schedule and Cost Integrated Management Methodology – Master
Degree Thesis (Metodologia de Gestão Integrada de Prazos e Custos – Dissertação de
Mestrado) – Instituto Superior Técnico
Kerzner, H. (2003) – Project Management: A System Approach to Planning, Scheduling and
Controlling Eight Edition – John Wiley & Sons
Kozak-Holland, M (2011) – The History of Project Management - Multi-Media Publications
Inc.
Lester, A. (2007) – Project Management, Planning and Control (Fifth Edition) – Butterworth-
Heinemann
Lia H.; Chana, N.; Huanga, T.; Guoa, H.L.; Lua, W. & Skitmoreb, M. (2009) - Optimizing
construction planning schedules by virtual prototyping enabled resource analysis - Automation
in Construction Vol. 18, Págs. 912-918
Madadi, M. & Iranmanesh, H. (2012) – A management oriented approach to reduce a project
duration and its risk - European Journal of Operational Research, Vol. 219 pages. 751 – 761
Malcolm D.G.; Roseboom J.H.; Clark, C.E. & Fazar, W. (1959) – Application of a Technique
for Research and Development Program Evaluation - US Navy
Marshall, B. e Raz, T. (1996) – Effect of resource constraints on float calculations in project
networks – International Journal of Project Management, Vol. 14, pages. 241-248
Miranda, T. (2011) – Economical Control of Construction Works: Method Proposal – Master
Degree Thesis (Controlo Económico de Obras: Proposta de Método – Dissertação de Mestrado)
- Faculdade de Engenharia da Universidade do Porto
Mubarak, S. (2010) – Construction Project Scheduling and Control – Second Edition – John
Wiley & Sons, Inc.
Paulo, J. A. (1995) – Time and Cost Integrated Management – Master Degree Thesis (Gestão
Integrada do tempo e do Custo - Dissertação de Mestrado) – Universidade Aberta
Project Management Institute (PMI) (2008) - “PMBOK" - Project Management Guide Body off
Knowledge 4º Edição
Roldão, V. S. (2004) – Performance Evaluation and Earned Value Management in Project
Management (Avaliação de desempenho e Earned Value Management em gestão de projectos –
INDEG – ISCTE), Lisboa
Samuel L. Baker – Critical Path Method (CPM) – Julho, 2010
Sousa, N. (2008) – Project Management in Construction – Evaluation model of the Project
performance – Master Degree Thesis (Gestão de Projectos na Construção - Modelo de
avaliação do desempenho em projectos – Dissertação de Mestrado) Instituto Superior Técnico
Stretton, A. (2007) – A Short History of modern Project Management - PM World Today, vol.
IX
Zammori, F. A.; Braglia, M. & Frosolini, M. (2009) – A fuzzy multi-criteria approach for
critical path definition – International Journal of Project Management, Vol. 27, pages. 278-291