instrumented (cyclic & lateral) pile load tests for the ...igs/ldh/conf/2010/articles/t133.pdf ·...
TRANSCRIPT
-
Indian Geotechnical Conference 2010, GEOtrendz
December 1618, 2010
IGS Mumbai Chapter & IIT Bombay
Instrumented (Cyclic & Lateral) Pile Load Tests for the Proposed Air
Traffic Control Tower in Mumbai
Ghan, Sandeep M. Mishra, Niraj K. 1 Shankar, C.P. Mahesh2
Engineering Manager Asst. Engineering Manager Asst. Engineering Manager
e-mail: [email protected] e-mail: [email protected] e-mail: [email protected]
1(Geotech), EDRC ECC, Larsen and Toubro Ltd., Mumbai
ABSTRACT
The Air Traffic Control Tower (ATC Tower) of Chhatrapati Shivaji International Airport, Mumbai is a 84m tall
structure which is proposed for regulating air traffic movement and will replace the old air traffic control tower.
This structure will be constructed as a part of the airport expansion and renovation programme. The entire
building is supported on pile foundations socketed in Breccia rock. The present paper describes the details of the
pile load test exercise which was carried out on test piles to ascertain the capacities (vertical, pull out and lateral)
of piles. Out of the four tests carried out on test piles, two tests were carried out in both traditional and instrumented
ways simultaneously. The strain gauges and extensometers (embedded in pile mass) were used in cyclic load test
to record strains and settlements in the test pile though data logger. In lateral load test, an inclinometer was used
to record the lateral deflection of the test pile. The vertical settlements and lateral deflections were also measured
with dial gauges in both the tests and the results were compared. The results were also further compared with the
design parameters.
1. INTRODUCTION
Pile foundations are used to transfer the load to deeper
strata of high bearing capacity or to rock avoiding
shallow layers of soil of lower bearing capacities. Pile
foundations socketed in rock strata is transmitting the
load to the deeper layers through end bearing and
socket friction with adjacent weathered rock layers.
The proposed Air Traffic Control (ATC) Tower of
the Chhatrapati Shivaji International Airport, Mumbai
is approximately a 84m tall structure founded on 108
piles of 800mm diameter socketed into Breccia rock.
The rock socketed piles derive a major portion of their
capacity by mobilizing the socket friction. The socket
length (ranging from 5.5m to 7.0m) was provided in
the present case. Cyclic instrumented pile load test was
carr ied out on test pile to ascertain the design
capacities and also to separate out the end bearing and
skin friction components. The instrumented lateral load
test was conducted to assess the lateral capacity of the
pile for the test load with corresponding deflection.
This paper describes the details of the instrumented
pile load tests and the interpretation of the results thus
obtained.
2. ENGINEERING GEOLOGY OF PROJECT
AREA
The project site is located in the Deccan Trap region.
Hence the usual types of rocks commonly occurring in the
Deccan Trap region, such as different types of basalts,
volcanic Breccias, Tuff Breccias with intercalation of black
shale bands etc are occurring. However, most of the rocks,
on which the structure is to be founded, are concealed
below the overburden. The project site is explored by
taking four boreholes within the building footprint.
Detailed core logging of all the four drill holes was carried
out as per IS 13365: 2006 (Part I).
The rock encountered at the site i.e. Tuff Breccias
are formed by compaction of volcanic tuffaceous
material. Some coarser fragments were blown up
during volcanicity and are caught up in Tuffaceous
matrix giving rise to Tuff Breccia. These rocks are soft,
weak and become weaker and more softer in contact
with water. Due to weathering, these rocks become so
weak and soft that, when tested in soaked condition,
these pieces crumble down. Therefore while deciding
foundation level of pile and socketing length, utmost
care was taken.
-
1000 M. Sandeep Ghan, K. Niraj Mishra and C.P. Mahesh Shankar
3. GEOTECHNICAL INVESTIGATION
The important information from foundation point of
view was obtained by sub-surface exploration. The
drilling was undertaken to ascertain the type of rocks
occurring at the site, their engineering characters, and
physical properties, etc. The geotechnical investigation
program comprised of 4 (four) boreholes. All the four
boreholes falling within the footprint of proposed
building were extended upto sound rock strata.
Subsurface profile at this site generally consists of
existing road crust and fill (as it was existing car
parking) overlying residual soil underlain by Completely
Weathered Rock followed by weathered bedrock.
4. FOUNDATION RECOMMENDATIONS
Bedrock was encountered at depths between 6.0m to
7.50m below ground surface.The pattern of irregular
weathering of the rock was observed in the borelogs
especially in the upper rock stratum. Termination
depths were so suggested that the pile rests on a sound
stratum (Fair as indicated by the RMR classification).
The building was proposed to be supported on bored
cast-in-situ piles socketed in Tuff Breccia bedrock and
were suggested for termination at depths ranging from
12.25m to 13.5m below ground level (socket length
varies from 5.5m to 7.0m). While deciding the
termination depth for each borehole area, it was ensured
that the pile lengths should not vary drastically.
However, for identification of start of socket and
termination of piles at fixed depth, the strata was
compared with geological identification of rock and the
termination criteria defined in terms of penetration rate.
The comparison was carr ied out by Engineering
Geologist using physical properties such as colour, grain
size and mineralogy.
The pile capacities were worked out by the various
methodologies like pile capacity as per IS 14593- 1998
for rock socketed piles, pile design as given by
Foundation design handbook, allowable pile stress as per
IS 2911-1979, and compared with the recommended pile
stress of 550t/m2 (as recommended for rock socketed
piles in Bombay region). Finally, the vertical pile
capacities are finalized based on the allowable pile stress
of 550t/m2 which is followed in Mumbai region.
5. PILE LOAD TESTS
Considering the importance of the structure, it was
decided to verify these pile capacities by carrying out
test pile exercise. Three tests were initially planned
(vertical, lateral and pull out). Cyclic load test was later
scheduled to identify end bearing and socket friction
components separately. Four test piles were cast in
the vicinity of borehole BH-2(which was identified for
weakest rock profile) namely ITP-1, ITP-2, ITP-3 and
ITP-4. Vertical and uplift load tests were performed on
ITP-1 and ITP-4 respectively. Instrumented cyclic load
test and lateral load tests were conducted on ITP-2 and
on ITP-3 respectively. The instrumentation in form of
load cells, strain gauges, extensometers and inclinometer
was also proposed in addition to conventional measuring
instruments like dial gauges and hydraulic jacks to
differentiate between skin fr iction, end bearing
component as also to accurately measure settlement and
lateral deflection of the pile.
In cyclic pile load test, the instrumentation was
done in test pile by installing strain gauges and
extensometers at different elevations along the pile
length. A total of 16 strain gauges (4 at each level)
were installed at depths 3.5m, 7.0m, 9.5m and 12.0m
from ground level. Similarly extensometers were placed
at depths 6.5m, 9.0m and 12.0m.
In case of lateral load test, an inclinometer was
used apart from dial gauges for assessing the lateral
deflection of the pile along the length. The horizontal
modulus of subgrade reaction was also determined from
the test.
6. TEST DETAILS
The tests were carried out as per the procedure given in
IS 2911-2006. The cyclic test load (1.50 times of
working load) and lateral test load (2.50 times of
working load) were applied on the test pile in
incremental way as also decreased in the same way. The
strain gauge readings and extensometer readings were
recorded through data logger every 15 minutes
automatically. Manual readings were taken every 30
minutes.
The inclinometer readings were recorded after each
load increment as well as decrement.
In the case of cyclic instrumented load test, the net
differences in strain gauge readings (at one elevation)
for each load cycle were averaged out and were
multiplied by modulus of concrete to obtain stress at
that point. The axial force in the pile mass at that
point is obtained by multiplying with the pile cross
section area. In the later exercise, the axial force at
two subsequent elevations is divided by the pile
perimeter in between to obtain skin friction component.
The skin friction component is considered to be acting
at -4.50m where CWR is encountered and friction zone
is assumed to be started.
The lateral load test was carried out as per IS
2911-2006. The deflections were measured with
inclinometer which moved through the PVC conduit
-
Instrumented (Cyclic & Lateral) Pile Load Tests for the Proposed... 1001
laid in the test pile. The lateral deflection was measured
at every 0.50m through the length of the pipe. The
same was also measured with the help of dial gauges.
6. ANALYSIS AND DISCUSSION
Cyclic Load Test
The interpretation of the test results is done in two
ways:-
(i) Calculations as per IS 2911- 2006 (by dial
gauge readings and corresponding loadings)
(ii) Calculations as per strain gauge readings and
extensometer readings with corresponding
loadings
(i) As per IS 2911-2006, the socket friction and
end bearing stresses are worked out with dial
gauges for each cycle and the results are
tabulated below.
Table1: Values Based on Dial Gauge Readings
(as per IS: 2911-2006)
Test Load (T) Socket friction
(T/M2)
End bearing (T/M
2)
56.74 3.05 25.18
113.49 5.90 56.13
170.23 8.47 95.27
226.98 11.76 113.46
283.72 14.48 147.97
340.46 17.31 179.61
397.21 21.16 181.96
415.65 22.14 189.09
Table 2: Percentage Based on Dial Gauge Readings
(as per IS: 2911-2006)
Test
Load
(T)
Total
Load
Taken by
Socket
Friction
(T)
Total
Load
Taken by
End
Bearing
(T)
% of
Socket
Friction
% of
End
Bearing
56.74 44.08 12.66 77.69 23.21
113.49 85.27 28.21 75.13 24.86
170.23 122.33 47.89 71.86 28.14
226.98 169.93 57.03 74.86 25.14
283.72 209.32 74.38 73.77 26.22
340.46 250.16 90.28 73.47 26.52
397.21 305.74 91.47 76.96 23.03
415.65 319.95 95.05 76.98 23.02
(ii) The analysis is done for all load ranges for readingsobtained through instrumentation also and the
range of the values is as given below.
Table 3: Values Based on Strain Gauge Reading
Test Load
(T)
Socket Friction
(T/M2)
End Bearing
(T/M2)
56.74 1.48 48.89
113.49 4.14 49.72
170.23 6.50 62.33
226.98 9.72 38.57
283.72 12.60 29.06
340.46 17.62 71.59
397.21 18.26 14.02
415.65 18.84 26.28
Table 4: Percentage Based on Strain Gauge Reading
Test
Load
(T)
Total
Load
Taken by
Socket
Friction
(T)
Total
Load
Taken by
End
Bearing
(T)
% of
Socket
Friction
% of
End
Bearing
56.74 31.66 25.08 55.80 44.20
113.49 88.50 24.99 77.98 22.02
170.23 138.90 31.33 81.59 18.41
226.98 207.59 19.39 91.46 8.54
283.72 269.11 14.61 94.85 5.15
340.46 328.37 12.08 96.45 3.55
397.21 390.16 7.05 98.22 1.78
415.65 402.44 13.21 96.82 3.18
The variation of skin frictional resistance with depthis shown in the figure.
Fig. 1: Variation of Skin Friction with Depth for Each Load
Lateral Load Test
The test was carried out as per the procedure elaborated in
IS 2911-2006. The lateral deflection obtained in the test
was 4.19mm at the top of the pile after the maximum test
load of 22 T was retained for 24 hours. The dial gauges
readings were suitably extrapolated to the cut-off level. The
cut- off level is 2.875m below existing ground level, which
was the test level. The inclinometer readings were also
taken at cut-off level and other elevations. The deflection
obtained with inclinometer at existing ground level was
3.58mm. The values obtained with dial gauge and
instruments are presented in Table 5 placed below.
-
1002 M. Sandeep Ghan, K. Niraj Mishra and C.P. Mahesh Shankar
Table 5: Comparison of Lateral Deflections
Instrument of
Measurement
Deflection at Top
(mm)
Deflection at Cut-off
Level (mm)
Dial gauge 4.19 3.16 (extrapolated)
Inclinometer (for
A) (In the direction of
loading)
3.58 0.94 (actual)
Inclinometer (for
A) (In the direction of
loading)
3.10 1.10 (actual)
Cut-off level: 2.875m below EGL.
7. CONCLUSIONS
The exercise was conducted to verify the design parameters
of end bearing and socket friction. The assessment of
separate values of end bearing and socket friction was also
an aim to conduct the test exercise. Although, end bearing
values are exceeding the safe bearing capacities (worked
out with RMR) of the stratum in case of higher loads, this
is expected because of ignorance of friction component in
soil region which is definitely sharing some load.
The results obtained by conventional instrumentation
and digital instrumentation are analysed. The load tests
are conducted in the region influenced by BH-2 as the RMR
analysis has shown minimum values for this borehole.
Following are the observations
(i) The settlements by both ways is found to be less
than 12mm and hence permissible as per IS 2911-
2006.
(ii) Skin friction as per strain gauge readings is
between 0.05 T/M2 and 28.70 T/M2. The
minimum value of skin friction was observed
between depth of 9.5m and 12.0m and the
maximum value was observed between -4.5m and
-7.0m. In design, the skin friction component is
taken as 10 T/M2 for entire length of rock
socketing. However, it is a general pattern seen in
the test results that the skin friction reduces with
depth and found minimum at the base of the pile.
The average skin friction for design load of the
pile (276 T) is found to be 8.92 T/M2 which is in
tune of 10 T/M2 as per instrument readings.
However the conventional method of analysis
shows the skin friction as 14 T/m2.
(iii) End bearing as per strain gauge readings is
between 10.11 T (20.12 T/M2) and 151.83 T
(302.21 T/M2). The end bearing is observed to be
much less than the skin friction component and
the major portion of the load gets dissipated with
depth. The end bearing at design load is observed
to be 230.15T/M2. The safe bearing capacity by
RMR value is worked out as 165 T/M2 at this
depth. The probable explanation for the same is
given in point no. iv.
(iv) The end bearing value for the pile is observed to
be more than safe bearing capacity of the rock
stratum. This is due to the fact that the socket
friction in the soil portion is neglected in this
analysis. As this value is not accounted for in the
design (but actually existing in the field), end
bearing stress is observed to be more than
allowable Safe Bearing Capacity.
(v) A lateral load i.e. test load of 22T was used
considering the case of test pile as a free head pile
for lateral load test (ITP 3). The lateral deflection
was obtained as 3.16mm from dial gauges and
0.94mm from inclinometer at cut off level. The
lateral deflection was estimated as 0.40mm at 18T
(design load at fixed head condition) in the pile
design. However, if the comparison is done with
the actual observed values, the field deflection is
obtained as 0.0535mm for the test pile at design
load (8.75T for free head condition) at cut-off level
which is less as compared to design value. The
value of Kh obtained from the test as 484.35kg/
cm2 which is higher as compared to the design
value of 48.80 Kg/cm2.
(vi) After comparing the results obtained with various
criterion given in IS 2911 and IS 14593, the design
load values are recommended as acceptable.
ACKNOWLEDGEMENTS
We are thankful to MIAL led by GVK group and their
Program Managers CH2MHill for granting us permission
to present the paper and to use the experimental data to
reach to the conclusions.
REFERENCES
IS 2911 Part IV, Code of Practice for the Design and
Construction of Pile Foundations Load Test on Piles.
New Delhi.
IS 14593, Design and Construction of Bored Cast In-Situ
Piles founded on Rock-Guidelines. New Delhi.
Premchitt J., Gray I., and Ho K. K. S.; Skin Friction on
Piles at the New Public Works Central Laboratory;
Geo Report No. 38.
Machan George and Bennett Victoria G ; Use of
Inclinometers for Geotechnical Instrumentation on
Transportation Projects.(TRB Circular Number E-C
129; October 2008)
IS 13365 Part I, Quantitave Classification Systems of Rock
Mass - Guidelines. New Delhi.