instrumented (cyclic & lateral) pile load tests for the ...igs/ldh/conf/2010/articles/t133.pdf ·...

Download Instrumented (Cyclic & Lateral) Pile Load Tests for the ...igs/ldh/conf/2010/articles/t133.pdf · Instrumented (Cyclic & Lateral) Pile Load Tests for the Proposed Air ... pile design

If you can't read please download the document

Upload: ngokhue

Post on 06-Feb-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • Indian Geotechnical Conference 2010, GEOtrendz

    December 1618, 2010

    IGS Mumbai Chapter & IIT Bombay

    Instrumented (Cyclic & Lateral) Pile Load Tests for the Proposed Air

    Traffic Control Tower in Mumbai

    Ghan, Sandeep M. Mishra, Niraj K. 1 Shankar, C.P. Mahesh2

    Engineering Manager Asst. Engineering Manager Asst. Engineering Manager

    e-mail: [email protected] e-mail: [email protected] e-mail: [email protected]

    1(Geotech), EDRC ECC, Larsen and Toubro Ltd., Mumbai

    ABSTRACT

    The Air Traffic Control Tower (ATC Tower) of Chhatrapati Shivaji International Airport, Mumbai is a 84m tall

    structure which is proposed for regulating air traffic movement and will replace the old air traffic control tower.

    This structure will be constructed as a part of the airport expansion and renovation programme. The entire

    building is supported on pile foundations socketed in Breccia rock. The present paper describes the details of the

    pile load test exercise which was carried out on test piles to ascertain the capacities (vertical, pull out and lateral)

    of piles. Out of the four tests carried out on test piles, two tests were carried out in both traditional and instrumented

    ways simultaneously. The strain gauges and extensometers (embedded in pile mass) were used in cyclic load test

    to record strains and settlements in the test pile though data logger. In lateral load test, an inclinometer was used

    to record the lateral deflection of the test pile. The vertical settlements and lateral deflections were also measured

    with dial gauges in both the tests and the results were compared. The results were also further compared with the

    design parameters.

    1. INTRODUCTION

    Pile foundations are used to transfer the load to deeper

    strata of high bearing capacity or to rock avoiding

    shallow layers of soil of lower bearing capacities. Pile

    foundations socketed in rock strata is transmitting the

    load to the deeper layers through end bearing and

    socket friction with adjacent weathered rock layers.

    The proposed Air Traffic Control (ATC) Tower of

    the Chhatrapati Shivaji International Airport, Mumbai

    is approximately a 84m tall structure founded on 108

    piles of 800mm diameter socketed into Breccia rock.

    The rock socketed piles derive a major portion of their

    capacity by mobilizing the socket friction. The socket

    length (ranging from 5.5m to 7.0m) was provided in

    the present case. Cyclic instrumented pile load test was

    carr ied out on test pile to ascertain the design

    capacities and also to separate out the end bearing and

    skin friction components. The instrumented lateral load

    test was conducted to assess the lateral capacity of the

    pile for the test load with corresponding deflection.

    This paper describes the details of the instrumented

    pile load tests and the interpretation of the results thus

    obtained.

    2. ENGINEERING GEOLOGY OF PROJECT

    AREA

    The project site is located in the Deccan Trap region.

    Hence the usual types of rocks commonly occurring in the

    Deccan Trap region, such as different types of basalts,

    volcanic Breccias, Tuff Breccias with intercalation of black

    shale bands etc are occurring. However, most of the rocks,

    on which the structure is to be founded, are concealed

    below the overburden. The project site is explored by

    taking four boreholes within the building footprint.

    Detailed core logging of all the four drill holes was carried

    out as per IS 13365: 2006 (Part I).

    The rock encountered at the site i.e. Tuff Breccias

    are formed by compaction of volcanic tuffaceous

    material. Some coarser fragments were blown up

    during volcanicity and are caught up in Tuffaceous

    matrix giving rise to Tuff Breccia. These rocks are soft,

    weak and become weaker and more softer in contact

    with water. Due to weathering, these rocks become so

    weak and soft that, when tested in soaked condition,

    these pieces crumble down. Therefore while deciding

    foundation level of pile and socketing length, utmost

    care was taken.

  • 1000 M. Sandeep Ghan, K. Niraj Mishra and C.P. Mahesh Shankar

    3. GEOTECHNICAL INVESTIGATION

    The important information from foundation point of

    view was obtained by sub-surface exploration. The

    drilling was undertaken to ascertain the type of rocks

    occurring at the site, their engineering characters, and

    physical properties, etc. The geotechnical investigation

    program comprised of 4 (four) boreholes. All the four

    boreholes falling within the footprint of proposed

    building were extended upto sound rock strata.

    Subsurface profile at this site generally consists of

    existing road crust and fill (as it was existing car

    parking) overlying residual soil underlain by Completely

    Weathered Rock followed by weathered bedrock.

    4. FOUNDATION RECOMMENDATIONS

    Bedrock was encountered at depths between 6.0m to

    7.50m below ground surface.The pattern of irregular

    weathering of the rock was observed in the borelogs

    especially in the upper rock stratum. Termination

    depths were so suggested that the pile rests on a sound

    stratum (Fair as indicated by the RMR classification).

    The building was proposed to be supported on bored

    cast-in-situ piles socketed in Tuff Breccia bedrock and

    were suggested for termination at depths ranging from

    12.25m to 13.5m below ground level (socket length

    varies from 5.5m to 7.0m). While deciding the

    termination depth for each borehole area, it was ensured

    that the pile lengths should not vary drastically.

    However, for identification of start of socket and

    termination of piles at fixed depth, the strata was

    compared with geological identification of rock and the

    termination criteria defined in terms of penetration rate.

    The comparison was carr ied out by Engineering

    Geologist using physical properties such as colour, grain

    size and mineralogy.

    The pile capacities were worked out by the various

    methodologies like pile capacity as per IS 14593- 1998

    for rock socketed piles, pile design as given by

    Foundation design handbook, allowable pile stress as per

    IS 2911-1979, and compared with the recommended pile

    stress of 550t/m2 (as recommended for rock socketed

    piles in Bombay region). Finally, the vertical pile

    capacities are finalized based on the allowable pile stress

    of 550t/m2 which is followed in Mumbai region.

    5. PILE LOAD TESTS

    Considering the importance of the structure, it was

    decided to verify these pile capacities by carrying out

    test pile exercise. Three tests were initially planned

    (vertical, lateral and pull out). Cyclic load test was later

    scheduled to identify end bearing and socket friction

    components separately. Four test piles were cast in

    the vicinity of borehole BH-2(which was identified for

    weakest rock profile) namely ITP-1, ITP-2, ITP-3 and

    ITP-4. Vertical and uplift load tests were performed on

    ITP-1 and ITP-4 respectively. Instrumented cyclic load

    test and lateral load tests were conducted on ITP-2 and

    on ITP-3 respectively. The instrumentation in form of

    load cells, strain gauges, extensometers and inclinometer

    was also proposed in addition to conventional measuring

    instruments like dial gauges and hydraulic jacks to

    differentiate between skin fr iction, end bearing

    component as also to accurately measure settlement and

    lateral deflection of the pile.

    In cyclic pile load test, the instrumentation was

    done in test pile by installing strain gauges and

    extensometers at different elevations along the pile

    length. A total of 16 strain gauges (4 at each level)

    were installed at depths 3.5m, 7.0m, 9.5m and 12.0m

    from ground level. Similarly extensometers were placed

    at depths 6.5m, 9.0m and 12.0m.

    In case of lateral load test, an inclinometer was

    used apart from dial gauges for assessing the lateral

    deflection of the pile along the length. The horizontal

    modulus of subgrade reaction was also determined from

    the test.

    6. TEST DETAILS

    The tests were carried out as per the procedure given in

    IS 2911-2006. The cyclic test load (1.50 times of

    working load) and lateral test load (2.50 times of

    working load) were applied on the test pile in

    incremental way as also decreased in the same way. The

    strain gauge readings and extensometer readings were

    recorded through data logger every 15 minutes

    automatically. Manual readings were taken every 30

    minutes.

    The inclinometer readings were recorded after each

    load increment as well as decrement.

    In the case of cyclic instrumented load test, the net

    differences in strain gauge readings (at one elevation)

    for each load cycle were averaged out and were

    multiplied by modulus of concrete to obtain stress at

    that point. The axial force in the pile mass at that

    point is obtained by multiplying with the pile cross

    section area. In the later exercise, the axial force at

    two subsequent elevations is divided by the pile

    perimeter in between to obtain skin friction component.

    The skin friction component is considered to be acting

    at -4.50m where CWR is encountered and friction zone

    is assumed to be started.

    The lateral load test was carried out as per IS

    2911-2006. The deflections were measured with

    inclinometer which moved through the PVC conduit

  • Instrumented (Cyclic & Lateral) Pile Load Tests for the Proposed... 1001

    laid in the test pile. The lateral deflection was measured

    at every 0.50m through the length of the pipe. The

    same was also measured with the help of dial gauges.

    6. ANALYSIS AND DISCUSSION

    Cyclic Load Test

    The interpretation of the test results is done in two

    ways:-

    (i) Calculations as per IS 2911- 2006 (by dial

    gauge readings and corresponding loadings)

    (ii) Calculations as per strain gauge readings and

    extensometer readings with corresponding

    loadings

    (i) As per IS 2911-2006, the socket friction and

    end bearing stresses are worked out with dial

    gauges for each cycle and the results are

    tabulated below.

    Table1: Values Based on Dial Gauge Readings

    (as per IS: 2911-2006)

    Test Load (T) Socket friction

    (T/M2)

    End bearing (T/M

    2)

    56.74 3.05 25.18

    113.49 5.90 56.13

    170.23 8.47 95.27

    226.98 11.76 113.46

    283.72 14.48 147.97

    340.46 17.31 179.61

    397.21 21.16 181.96

    415.65 22.14 189.09

    Table 2: Percentage Based on Dial Gauge Readings

    (as per IS: 2911-2006)

    Test

    Load

    (T)

    Total

    Load

    Taken by

    Socket

    Friction

    (T)

    Total

    Load

    Taken by

    End

    Bearing

    (T)

    % of

    Socket

    Friction

    % of

    End

    Bearing

    56.74 44.08 12.66 77.69 23.21

    113.49 85.27 28.21 75.13 24.86

    170.23 122.33 47.89 71.86 28.14

    226.98 169.93 57.03 74.86 25.14

    283.72 209.32 74.38 73.77 26.22

    340.46 250.16 90.28 73.47 26.52

    397.21 305.74 91.47 76.96 23.03

    415.65 319.95 95.05 76.98 23.02

    (ii) The analysis is done for all load ranges for readingsobtained through instrumentation also and the

    range of the values is as given below.

    Table 3: Values Based on Strain Gauge Reading

    Test Load

    (T)

    Socket Friction

    (T/M2)

    End Bearing

    (T/M2)

    56.74 1.48 48.89

    113.49 4.14 49.72

    170.23 6.50 62.33

    226.98 9.72 38.57

    283.72 12.60 29.06

    340.46 17.62 71.59

    397.21 18.26 14.02

    415.65 18.84 26.28

    Table 4: Percentage Based on Strain Gauge Reading

    Test

    Load

    (T)

    Total

    Load

    Taken by

    Socket

    Friction

    (T)

    Total

    Load

    Taken by

    End

    Bearing

    (T)

    % of

    Socket

    Friction

    % of

    End

    Bearing

    56.74 31.66 25.08 55.80 44.20

    113.49 88.50 24.99 77.98 22.02

    170.23 138.90 31.33 81.59 18.41

    226.98 207.59 19.39 91.46 8.54

    283.72 269.11 14.61 94.85 5.15

    340.46 328.37 12.08 96.45 3.55

    397.21 390.16 7.05 98.22 1.78

    415.65 402.44 13.21 96.82 3.18

    The variation of skin frictional resistance with depthis shown in the figure.

    Fig. 1: Variation of Skin Friction with Depth for Each Load

    Lateral Load Test

    The test was carried out as per the procedure elaborated in

    IS 2911-2006. The lateral deflection obtained in the test

    was 4.19mm at the top of the pile after the maximum test

    load of 22 T was retained for 24 hours. The dial gauges

    readings were suitably extrapolated to the cut-off level. The

    cut- off level is 2.875m below existing ground level, which

    was the test level. The inclinometer readings were also

    taken at cut-off level and other elevations. The deflection

    obtained with inclinometer at existing ground level was

    3.58mm. The values obtained with dial gauge and

    instruments are presented in Table 5 placed below.

  • 1002 M. Sandeep Ghan, K. Niraj Mishra and C.P. Mahesh Shankar

    Table 5: Comparison of Lateral Deflections

    Instrument of

    Measurement

    Deflection at Top

    (mm)

    Deflection at Cut-off

    Level (mm)

    Dial gauge 4.19 3.16 (extrapolated)

    Inclinometer (for

    A) (In the direction of

    loading)

    3.58 0.94 (actual)

    Inclinometer (for

    A) (In the direction of

    loading)

    3.10 1.10 (actual)

    Cut-off level: 2.875m below EGL.

    7. CONCLUSIONS

    The exercise was conducted to verify the design parameters

    of end bearing and socket friction. The assessment of

    separate values of end bearing and socket friction was also

    an aim to conduct the test exercise. Although, end bearing

    values are exceeding the safe bearing capacities (worked

    out with RMR) of the stratum in case of higher loads, this

    is expected because of ignorance of friction component in

    soil region which is definitely sharing some load.

    The results obtained by conventional instrumentation

    and digital instrumentation are analysed. The load tests

    are conducted in the region influenced by BH-2 as the RMR

    analysis has shown minimum values for this borehole.

    Following are the observations

    (i) The settlements by both ways is found to be less

    than 12mm and hence permissible as per IS 2911-

    2006.

    (ii) Skin friction as per strain gauge readings is

    between 0.05 T/M2 and 28.70 T/M2. The

    minimum value of skin friction was observed

    between depth of 9.5m and 12.0m and the

    maximum value was observed between -4.5m and

    -7.0m. In design, the skin friction component is

    taken as 10 T/M2 for entire length of rock

    socketing. However, it is a general pattern seen in

    the test results that the skin friction reduces with

    depth and found minimum at the base of the pile.

    The average skin friction for design load of the

    pile (276 T) is found to be 8.92 T/M2 which is in

    tune of 10 T/M2 as per instrument readings.

    However the conventional method of analysis

    shows the skin friction as 14 T/m2.

    (iii) End bearing as per strain gauge readings is

    between 10.11 T (20.12 T/M2) and 151.83 T

    (302.21 T/M2). The end bearing is observed to be

    much less than the skin friction component and

    the major portion of the load gets dissipated with

    depth. The end bearing at design load is observed

    to be 230.15T/M2. The safe bearing capacity by

    RMR value is worked out as 165 T/M2 at this

    depth. The probable explanation for the same is

    given in point no. iv.

    (iv) The end bearing value for the pile is observed to

    be more than safe bearing capacity of the rock

    stratum. This is due to the fact that the socket

    friction in the soil portion is neglected in this

    analysis. As this value is not accounted for in the

    design (but actually existing in the field), end

    bearing stress is observed to be more than

    allowable Safe Bearing Capacity.

    (v) A lateral load i.e. test load of 22T was used

    considering the case of test pile as a free head pile

    for lateral load test (ITP 3). The lateral deflection

    was obtained as 3.16mm from dial gauges and

    0.94mm from inclinometer at cut off level. The

    lateral deflection was estimated as 0.40mm at 18T

    (design load at fixed head condition) in the pile

    design. However, if the comparison is done with

    the actual observed values, the field deflection is

    obtained as 0.0535mm for the test pile at design

    load (8.75T for free head condition) at cut-off level

    which is less as compared to design value. The

    value of Kh obtained from the test as 484.35kg/

    cm2 which is higher as compared to the design

    value of 48.80 Kg/cm2.

    (vi) After comparing the results obtained with various

    criterion given in IS 2911 and IS 14593, the design

    load values are recommended as acceptable.

    ACKNOWLEDGEMENTS

    We are thankful to MIAL led by GVK group and their

    Program Managers CH2MHill for granting us permission

    to present the paper and to use the experimental data to

    reach to the conclusions.

    REFERENCES

    IS 2911 Part IV, Code of Practice for the Design and

    Construction of Pile Foundations Load Test on Piles.

    New Delhi.

    IS 14593, Design and Construction of Bored Cast In-Situ

    Piles founded on Rock-Guidelines. New Delhi.

    Premchitt J., Gray I., and Ho K. K. S.; Skin Friction on

    Piles at the New Public Works Central Laboratory;

    Geo Report No. 38.

    Machan George and Bennett Victoria G ; Use of

    Inclinometers for Geotechnical Instrumentation on

    Transportation Projects.(TRB Circular Number E-C

    129; October 2008)

    IS 13365 Part I, Quantitave Classification Systems of Rock

    Mass - Guidelines. New Delhi.