INSTALLATION OF 3-RD AUTOTRANSFORMER
330/110/35 kV AT SUBSTATION 330 kV
“CHERNIVETSKA”
INFRASTRUCTURE PROJECTS
PROJECTS LIFE CYCLE ≈3-7 years and more1
REQUIRES A LOT OF INVESTMENTS.
ONE PROJECT USUALLY HAS SEVERAL SUBCONTRACTS:
CORRUPTION RISKS AND RISKS OF INEFFECTIVE MANAGEMENT
INCLUDES THE FOLLOWING STAGES:
1 Planning Designing2Performance of works
under contracts3 Technical maintenance4
Project Performance
of works
Лот#1
Лот#3
Лот#2
Technical
maintenance
Project
documentation
2
COMPLEXITY OF MONITORING
3
4
5
HOW COST WORKS
PROZORRO PROVIDES EVERYONE WITH A POSSIBILITY
TO FOLLOW EVERYTHING RELATED TO PROCUREMENT.
"DARK ZONES"
OF INFRASTRUCTURE:
- Planning
- Performance of works
- Quality control
About the project
Agreement on cooperation between the Ministry of Energy and Coal Industry of
Ukraine, Chernivtsi Regional State Administration and Chernivtsi Regional Council
regarding the development of fuel and energy complex and social infrastructure of
settlements of Chernivtsi region dated 22.03.2011.
Objective: to increase the substation’s capacity to provide the
consumers of Pivdenno-Zakhidna power system with electricity
The project is based on:
2011 Investment Program of
SE “NPC “Ukrenergo”
“Plans for the perspective development of Pivdenno-Zakhidna
PS for the period up to 2015 with prospects up to 2020.”
2 0 1 5
2 0 2 0
The project’s total value:
131.591 mln ₴The expected date of works completion:
01.07.2017
Project’s status:
In progress
Overload of existing grids
For a long period of time, the load of АТ in a usual mode has been exceeding
the standard level (70%) and amounting to 8 0 % and more, while in specific
years, it reached the level of 91.2% and 102 .3% respectively.
According to the existing draft, there are two autotransformers (АТ)
330/110/35 kV with the capacity of 200MVA installed at “Chernivetska”
substation
91.2% 102.3%
100
50
0
100
50
0
Ініціатива
з прозорості
інфраструктури
Parties to the project
Customer: General designer:
1.8 mln ₴
82.099 mln ₴
47.238 mln ₴
0.228 mln ₴
88.29 thous. ₴
PJSC “Zaporizhtransformator”
1 SE “NPC “Ukrenergo” 2 DPVNDI “UKRENERGOMEREZHPROEKT”
6 Supplier of the autotransformer:
5 Author’s supervision: LLC “SichEnergo”
4 Contractor: LLC “SichEnergo”
3 Adjustment of project documentation:PJSC “Kyivorgbud”
Project’s Life Cycle
01.04.2011
Approval of instructions
for the object’s draft
07.07.2011
Agreement for designing with
DPVNDI “Ukrenergomerezhproekt”
19.12.2012
Order of the CMU about
the project’s approval No. 1035-r
06.11.2015
Agreement for adjustment of the estimate
part of the project with “PTI “Kyivorgbud”
24.03.2016
Agreement for the supply of
an autotransformer from
PJSC “Zaporizhtransformator”
01.07.2016
Order of the Ministry of Energy and Coal Industry
N o . 4 2 1 on approval of the adjusted project
12.08.2016
Agreement for construction and installation
works with the supply of basic
equipment from LLC “Sichenergo”
18.11.2016
Договір на авторський нагляд за
будівництвом з ТОВ «СічЕнерго»
30.06.2017
Supplemental agreement No. 1 ,
prolongation of the term of performance
of works until 01.10.2017
04.10.2017
Supplemental agreement No. 2 , adjustment of the
volume of works, supply of equipment, terms for
performance of works prolonged until 30.09.2018
January 2018
Intention
to terminate the
agreement
3 months
3 years
1.5 years
4 months
4 months
42 days
3 months7 months
3 months 2 months
Ініціатива
з прозорості
інфраструктури
93% of information indicators
of the project
Transparency of the project
The Customer
independently disclosed
57 documents, including 4 (7 %)
available for free access
in the course of
preparing the
report, worked on
93% of requested data
was provided
The verification team received
responses to all appeals
The Contractor failed to provide full
information about subcontractors
Ініціатива
з прозорості
інфраструктури
19.12.2012
134.177mln ₴
Project’s planning. Estimated cost
The actual cost of the project is
lower that the estimated cost
The project’s estimated
cost was approved
335.866 mln ₴
01.07.2016
The project was not implemented
within 2.5 years
an increase in the cost of construction parts
led to adjustment of the project’s
estimated cost
2.5 times!
131.592 mln ₴Actual cost of the project
as of December 2017
2011: tender for choosing a designer
Participant
LLC “Kyivenergomerezhproekt,” affiliated company in Odesa
Tender 1: project documentation
DPVNDI “Ukrenergomerezhproekt,” affiliated company
in Lviv
on the date of signing the agreement (06.11.2015) the amount of the
agreement was reduced to 227 966.40 thous. ₴
The winner’s offer is by 42% lower than the competitor ’s one
2015 : tender for adjusting project documentation
Participant
LLC “Podilskyi enerhokonsaltynh”
PJSC PTI “Kyivorhbud”
3 126 648 ₴
1 799 687 ₴
₴ offers, UAH, VAT included
599 028₴
503 317 ₴
₴ offers, UAH, VAT included
Ініціатива
з прозорості
інфраструктури
The Customer purchased in a centralized manner
13 autotransformers, including for “Chernivetska” substation
The winner’s proposal is lower by 53% than the competitor’s one
The cost of 1 autotransformer
for “Chernivetska” substation amounts to 47 238 024 ₴
The term of delivery of equipment to the object – December 2016.
Participant
LLC “ABB LTD” (Switzerland)
PJSC “Zaporizhtransformator” (Ukraine)
Tender 2: supplier of an autotransformer
₴ offers, UAH, VAR included
1 084 061 ₴
571 408 ₴
Tender 3: construction and installation
works and supply of basic equipment
Expected value: 176 581 000 ₴
offers, UAH, VAT included
# Participant % from the expected cost of the purchase
Rejection
89,5%
50,8%
46,1%
46,5%
60,3%
50,8%
63,4%
Winner82 098 706 ₴
106 524 771 ₴
89 662 253 ₴
112 028 034 ₴
81 467 354 ₴
157 999 623 ₴
89 722 565 ₴
158 700 312 ₴ 89,9% Rejected1
2
3
4
5
6
7
8
PE “Donkom”
Rejected
Rejected
Rejected
LLC “Tekhnostar”
Collective Enterprise “Installation Administration
No.6 “Elektropivdenzakhidmontazh”
LLC “Kyivska enerhetychna budivelna kompaniia”
LLC “Zviazoktekhservis”
LLC “Pivdenna enerhetychna kompaniia”
“Corporation of Production and Commercial Enterprises “Soiuz”
The offer with the lowest cost was rejected due to the reasons not affecting the capability of performing a contract. The winner’s offer is lower than the expected cost by 46.5%.
LLC “Sich energo”
!
Equipment “ZZVA”
Is the Contractor able to ensure the performance of the agreement?
Paid
a failure to supply equipment “ZZVA” to the Contractor
In the amount of 18 mln UAH (paid as a prepayment 50%)
A failure in delivery terms
change of the
plant’s owner
1 8 mln UAH ₴ 2 2 % of the contract’s amount
Equipment “ZZVA”
Customer Contractor
Subcontractor
Supplier 1(“ZZVA”)
Supplier 2
Supplier 3
The necessity of full replacement of
equipment “ZZVA”
The total value of the agreement was reduced by 152 thous. ₴ (0.18%) at the expense of:
Provision by the Customer of 12 current transformers 110 kV of IMB 123 t ype .
Reduction in the value of commissioning and adjustment works.
Exclusion of the part of construction and installation works (motor roads, buildings and constructions)
To complete the project, the Customer decides to replace the part of the
equipment of KT “ZZVA” with similar equipment produced by other
manufacturers, to exclude some parts, to replace some parts from own stocks.
Replacement of equipment and
changes in the volume of works
Departure to the construction site (July 2017 )
In accordance with “the general register of work
performance,” works are performed at the object
starting from 18.11.2016, however,
the Contractor neither prepared nor
signed any acceptance acts
The updated schedule of performed works
failed to include a number of works,
specified in the agreement and the project
documentation.
Autotransformer ATZ installed at
the project site
A high level of openness of the Customer, CoST received responses to all appeals, all
requested materials were provided rapidly
The Customer expressed readiness to work with the Contractor,
acted comprehensively in an extraordinary situation
Problematic issues:
Inaccurate estimate documents, the project’s actual cost is 2.5 times
lower that the estimated cost
Rejection of offers in view of a formal characteristic, rejection of the most
economically beneficial offer
A failure to adhere to the delivery terms of KT “ZZVA” – extensive agreement regarding
the equipment to be replaced – prolongation of the time of the performance of works
The Contractor’s failure to meet the schedule of the performance of works not related to
the availability of equipment
A lengthy period of project implementation,
obsolete project documentation
Conclusions
Ініціатива
з прозорості
інфраструктури
The Customer should take organizational measures to ensure
quicker response to extraordinary situations
The Customer should make amendments to the terms of tenders about decreasing
rejections due to formal characteristics
The Contractor should take measures to adhere to
the schedules of the delivery of equipment
The Customer should pay attention to the determination of estimated cost of
construction at the stage of designing
The Customer should consider the possibility of defining the contractual price as
dynamic in order to exclude the part of works/replace equipment in the case of
unpredicted additional works
Recommendations