installation, commissioning and decommissioning offshore windpic.jpg 23 available technology for the...
TRANSCRIPT
![Page 1: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/1.jpg)
Installation, commissioning and decommissioning offshore wind
Marcus Bentin
![Page 2: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/2.jpg)
2
Faculty of Maritime
Studies
Weiter
![Page 3: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/3.jpg)
3
Maritime Industry in Germany
![Page 4: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/4.jpg)
4
Installation of offshore wind turbines
• In 2015 3,230 offshore wind turbines in the EU (11,027 MW)
• New installation of 759 offshore wind turbinesin the EU (3,019 MW) in 2015
• Installation of offshore wind turbines is large market sector
• Dismantling or repowering after 20-25 years(by law)
![Page 5: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/5.jpg)
5
Installation of offshore wind turbines in Germany
![Page 6: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/6.jpg)
6
Installation of offshore wind turbines in Germany
![Page 7: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/7.jpg)
7
Commission of Windpark Riffgat in Germany from EWE
![Page 8: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/8.jpg)
8
Dismanteling of offshore wind turbines
not so much experiences could be gained yet
2016 Yttre Stengrud, Vattenfall (5 turbines each 2 MW)
http://www.maritime-
executive.com/article/first-offshore-wind-
farm-decommissioning-complete
![Page 9: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/9.jpg)
9
Key problem
• Most wind farms (in Germany) are founded in deep water several seamiles off the coast
• Long trip for the workers from the coast to thewind farms
• Often small time windows of good weather
• As yet no established processes fordismanteling
• Sometimes not even established laws andregulations
![Page 10: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/10.jpg)
10
Key problem
![Page 11: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/11.jpg)
11
Key problem
![Page 12: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/12.jpg)
12
Principle decommissioning processsuggested by Rhenus
![Page 13: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/13.jpg)
13
Today proposed methods for decomission
• The today proposed methods have there roots in the onshore wind sector, offshore oil and gas industry and the experience from the erection processof the offshore wind farms
• One principle is to do most of the decommission process onshore. The offshore operations are costly and have to be minimized
• The difference to oil and gas is:– there are many smaller sized structures in the field that have to be removed instead of
one big platform. Hence the tools might be oversized?
– the water depth is usualy less than 50m in Germany it can be more
– the distance to the coast is usualy less than 50 miles, in Germany it can be more
![Page 14: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/14.jpg)
14
Today proposed methods for decomission
• The operations can be clustered for:
– Wind Turbines
• lift operations
– Fundation of Turbines, Substation, Met Mast
• Cut and lift operations
– Offshore Substation
• Lift operation
– Cables Inter-array/Export
• Cut and remove or left in situ
– Onshore Cables, Substation (wedo not focus here)
e.g. Topham
![Page 15: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/15.jpg)
15
Used Literature
• Eva Topham*, David McMillan: “Sustainable decommissioning of an offshore wind farm” in Renewable Energy 102 (2017) p. 470-480
• Gillian Smith, Chris Garrett & George Gibberd: “Logistics and Cost Reduction of Decommissioning Offshore Wind Farms” presented at EWEA Offshore 2015 10 - 12 March 2015, Copenhagen
![Page 16: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/16.jpg)
16
Operations for Turbine
• First the turbine has to be prepared todecommission, powerless,– Cut electric cable
– Dismantel Nacelle
• Heavy lift operation around 600t (Rotor and Nacelle)
• Dismantele rotor from nacelle on thedeck of the vessle otherwise it has to bedone before?
https://cdn1.pri.org/sites/default/files/styles/story_main/publi
c/story/images/BIWF%20Tower%201%20complete.jpeg?itok=l
n86I6_z
![Page 17: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/17.jpg)
17
Operations for Tower and Transition piece /Monopile
• Most productive way would be liftingTower and Transition piece together withthe foundation– Therefore cutting of foundation only from
outside
– Lifting of 1500t and later even more
http://www.4coffshore.com/windfarms/images/
articles/4/image4(1).jpg
![Page 18: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/18.jpg)
18
Operations for Fondations /Monopile
• First the pile has to be inspected (ROVs)
• Score protection has to be removed for cutting?– The effort depends on the protection type
• Cable has to be cut and burried in ground. (ROV, diver)
• Excavation with sea trencher
• Crane hooks are positioned to the lifting points
• The piles are cut below seabed and have to be monitored afterwards
• Removing entire structure??? As alternative
http://www.4coffshore.com/windfarms/images/
articles/4/image4(1).jpg
![Page 19: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/19.jpg)
19
Operations for Score protection
• The hope is that it can be left in Situ– But today you cannot realy be sure in
Germany if the general rule is applied everything has to be left as it was before
– Argumentation: new marine habitat, removalwould distroy the habitat
– If they have to be moved productive ideas arenecessary otherwise it is done with a grapperdiver or ROV assistance
![Page 20: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/20.jpg)
20
Operations for Cables
• The hope is that they can be left in Situ– If the burial depth of the inter-array and
export cable is deeper than 1m.
– They are cut and removed where they come up less than 1m
• Cut operation with ROV???
• Towed on a drum on board the vessel
• The buried cables have to monitored during years.
![Page 21: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/21.jpg)
21
Operations for Offshore Substations
• Here know how of the oil and gas industry is available as well as technology.
• Platforms already have to be removed
![Page 22: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/22.jpg)
22
Available Technology for the Operations
• Cutting technology:– Hydraulic shears for cable
– Abrasive wire cutting or abrasive jet cuttingfor 80mm and more wall thickness and over5m diameter
http://miragemachines.com/files/cache/fa500
1c62306763e2a02ab1cdea6b797_f792.jpg
http://www.oceaneering.com/wp-
content/uploads/2013/03/Conductor-Cut-
Pic.jpg
![Page 23: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/23.jpg)
23
Available Technology for the Operations
• Logistic and heavy lift operations:– Several offshore vessels from the oil and gas
industry
– Wind park erection vessel, Jack Up Vessels, Heavy Lift Vessels
![Page 24: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/24.jpg)
Project Idea:
Offshore Wind Decommissioning Toolbox for the North Sea Region
Project Titel:
Eco-innovative concepts for the end of offshore wind
energy farms’ lifecycle
Isabel Sünner
Interwork Event, Göttingen, 29.6.2017
![Page 25: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/25.jpg)
Background and Relevance
Offshore wind industry mainly focuses on setting up new
projects
Only little attention is given to decommissioning
It is foreseeable that 50 offshore wind farms will need to be
dismantled until 2038
Hamburg Institute of International Economics (HWWI) Slide 25
Central aim:
is to develop new processes and working tools to organize
the decommissioning of offshore wind energy parks in an
environmentally safe and cost-effective way
![Page 26: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/26.jpg)
Aspects to be considered:
• Economic and legal framework
• Impact on regional development
• Impact on environment
• Requirement profile for new working tools /
operations
• Logistical concepts, including material and
personal resources
• New vessel type
• Recycling / disposal of components
Hamburg Institute of International Economics (HWWI) Slide 26
![Page 27: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/27.jpg)
Envisaged output
• Logistical concepts including material and personal
resources (using a model of wind energy plants)
• Concept for recycling / disposal of particular components
• Definition of requirements for a new vessel type
• Environmental and safety analysis of the new tools
• Exploitation plan for the new tools
• Impact analysis on regional development
Hamburg Institute of International Economics (HWWI) Slide 27
![Page 28: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/28.jpg)
Hamburg Institute of International Economics (HWWI) Slide 28
Isabel SünnerHamburg Institute of International Economics (HWWI)International cooperation and project development
Please get in contact!
• Business / Industry Partners (from all over the NSR)
• Cluster organisations in the field of offshore wind (particularly
from BE, DK, NL, UK)
Potential partners
![Page 29: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/29.jpg)
29
Project Partners
Confirmed:
• University of Applied Sciences Emden-Leer, Germany
• HILOG, Institute for Logistics, Emden, Germany
• Port of Oostende, Belgium
• Flanders Maritime Cluster, Belgium
• HWWI, Germany
• Energy Valley, Netherlands
• WPT Winschoten, Netherlands
![Page 30: Installation, commissioning and decommissioning offshore windPic.jpg 23 Available Technology for the Operations • Logistic and heavy lift operations: – Several offshore vessels](https://reader034.vdocuments.us/reader034/viewer/2022051923/6010cb793d1bd60e621175e9/html5/thumbnails/30.jpg)
30
Possible fonds Interreg North Sea Region (www. http://www.northsearegion.eu)