insight + passion - city of des moines fire training...insight + passion table of contents...

32
insight + passion

Upload: lynhi

Post on 17-Apr-2018

216 views

Category:

Documents


2 download

TRANSCRIPT

insight + passion

insight + passion

TABLE OF CONTENTS

INTRODUCTION

NARRATIVES

-SITE

-ARCHITECTURAL

-STRUCTURAL

-HVAC

-ELECTRICAL

-PLUMBING

-SUSTAINABLE DESIGN

SITE PLAN

FLOOR PLANS

ELEVATIONS- CONCEPT

SCHEMATIC DESIGN ESTIMATE

APPENDIX

-FURNITURE ESTIMATE

-WAREHOUSE STORAGE DIAGRAM

2

3

28

29

31

32

34

44-AERIAL 46-ROOM AREAS 47

1

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

1.0 Introduction

OPN Architects, Inc. & CR architecture + design 2

Consultant Team:

ArchitectureLandscape ArchitectureStructural DesignElectrical DesignPlumbing/Fire ProtectionMechanical DesignCivil EngineeringCost Estimating

Project Statement

OPN Architects, Inc./CR architecture + designOPN Architects, Inc. Shuck-Britson Inc. Farris Engineering, Inc.Farris Engineering, Inc.Farris Engineering, Inc.Snyder & Associates, Inc.Stecker Harmsen

This report, prepared by OPN Architects, Inc. and CR architecture + design (formally Cole + Russell Architects) describes in detail the design intent for the site, architecture, structural system, and mechanical/electrical/plumbing systems.

Items of Note:-Elevations are conceptual and have been included for reference only. They will continue to be explored, for form, materiality and day lighting opportunities through the Design Development stage. -Schematic cost estimate reflects Option 1 in the HVAC narrative. Option 2 (Geo-Thermal system) will be explored and priced in the Design Development stage.

Project Overview The new Fire Department Training and Logistics Facility is an approximately46,000 gross square feet, one and two story building. The estimated project cost is $9.6 million.The facility will be located in Des Moines Iowa on the northeast corner of a site bordered by Dean Avenue to the north, 28th Street to the east, light industrial to the west and a rail yard to the south, a residential neighborhood to the north and east with a former fire station occupying the SE corner of Dean and 28th. The site is generally flat with some adjacent slope off-site to the south to the railroad tracks. The grades under and around the footprint of the building will need to be raised to maintain positive drainage away from the building.The former site was a Perelli-Amstrong tractor tire finishing and tubing factory, of which portions were demolished in 1984 and 1989. Upon demolition and abandonment of the site remedial action was performed circa 1995 to remove various contaminants, receiving clearance for future development in August of 2008.

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

2.0 Site Narrative

OPN Architects, Inc. & CR architecture + design 3

Topography and Stormwater Management

A detention area for the site will be located west of the main building. Anexpected detention volume of approximately 30,000 cubic feet will be needed for the site if a majority of the on-site flows can be routed to the detention area. The stormwater from the roof will be piped into a storm sewer system and routed to the detention area. The detention outlet will be tied to the City of Des Moines storm system in Dean Avenue.

The required erosion control measures will be taken to ensure water quality throughout construction. A stormwater management plan will be required for the site as an NPDES permit through the State of Iowa DNR.

Site Utilities The existing water service will be tapped from an already present 8” main located on the north side of Dean Avenue on the north side of the site. Any water service stubs fronting the site must be cut at the main if they are not going to be used for this project. Three stub locations are present on the east side of the site along E. 28th Street.

System Development fees through Des Moines Water Works are required for both the domestic and fire services and are based on size.

Fire hydrants are currently located on the north side of Dean Avenue near the center of the site and on the southeast corner of the intersection of Dean Avenue and E. 28th Street. Additional hydrants may be required on site according to the building code.

An existing sanitary stub from the sanitary main in Dean Avenue is located approximately 200 feet west of the northeast property corner. Potentially, this may be utilized for the building connection to the City of Des Moines sanitary main. If this is unavailable for connection, sanitary connection will need to be made at the sanitary main in the center of Dean Avenue. Another possible sanitary connection is located under E. 28th Street. Floor drains connecting to the city sewers are required to be protected by an approved sand and oil interceptor.

Existing overhead electric service is located on the north side of Dean Avenue, the east side of E. 28th Street, and on the property in the southeast corner. Contact Mid American Energy in regards to the service routing and required sizes and what is available through each existing line.

The existing gas main is located on the north side of Dean Avenue. Contact MidAmerican Energy in regards to the service relocation and any permitting that may be required.

MLBischof
Inserted Text
Want hydrant is SW corner of site.

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

3.0 Architectural Narrative

OPN Architects, Inc. & CR architecture + design 4

Architectural Overview The proposed design consists of pre-engineered metal building frames with custom skins, along with more traditional construction types skinned with metal panels and brick veneers. The associated building types and forms help reduce the building mass into a more appropriate scale for the residential scale of the neighborhood. The facility includes fire department administration offices, spaces for training such as classrooms and multipurpose areas, as well as spaces for the maintenance of fire apparatus and equipment. The building is designed for the future expansion of both the apparatus and maintenance bays.

The building contains 5 main program elements – 1. Administration offices, 2. Training bays with training support, 3. Classroom spaces, 4. Maintenance bays with maintenance support spaces, and 5. Warehouse component. The training bays consist of a large, open, single story space that provides access to Dean Avenue via multiple overhead doors. The administration offices, training support and classroom spaces are located within the two story portion of the building that is positioned to connect the training bays to the maintenance facility. This area is located at the intersection of Dean Avenue and 28th Street and provides the primary entrance into the facility. Like the training bays, the maintenance bays are a large, open, single story space that provides access to 28th Street via multiple overhead doors. The maintenance support spaces are directly adjacent to the maintenance bays and include a two-story warehouse space.

Exterior Design The exterior of the building is a combination of burnished block, brickveneer, metal panels and glass and aluminum storefront and curtain wall systems. The training and maintenance bays are both pre-engineered metal frames with exterior custom skins, burnished concrete masonry unit (cmu) base and insulated metal wall panels that intern form the sloped metal roofs. Glazing is incorporated in the overhead doors along with translucent panels at the upper portion transoms to provide natural day lighting into these spaces.

The two story Administration area contains administrative offices and support spaces, training support and classrooms. Construction is conventional steel structural framing with first floor concrete slab on grade; second floor concrete slab on metal deck; and roof constructed of membrane roofing, insulation and low slope metal deck. Exterior walls consist of insulated metal stud framing with burnished block and brick veneer.

The Administration Block is divided in the east/west direction by an architectural “Spine Wall” element that “slides” vertically and horizontally through the building. The wall serves to define and organize spaces along the primary circulation route. On the first floor, classrooms are on the north side of the wall with support spaces on the south. On the second floor,office spaces are to the north with support spaces primarily to the south. A similar wall perpendicular to the Spine Wall terminates the block and separates it from the training functions farther west. The walls are expressed on the exterior by extending beyond the perimeter walls and roof of the Administration Block. They will be clad in metal panel siding to match the maintenance and training bays serving to visually tie together the different functional areas of the building. The walls on the interior along the

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

3.0 Architectural Narrative

5ngised + erutcetihcra RC &.cnI ,stcetihcrA NPO

corridors will become gallery space to display artifacts and photographs depicting the fire department’s history. Periodically along the main Spine Wall, openings are present through the second floor. These openingsspatially connect the two floors and allow natural light to penetrate to the first floor corridor from above.

Entrance and vertical circulation are celebrated with two story aluminum frame and glass elements at the main entrance and east and west stairs,complementing the spine wall element. A full height glass “seam” at the midpoint along the North Elevation corresponds with the Break Room on the first floor and the primary open office area on the second floor affording daylight and views to a large portion of the building. The masonry exterior of the Administration Block is further punctuated with individual aluminum framed windows, corresponding with interior spaces.

Interior Design The interior finishes of the training and maintenance bays, along with a majority of the support spaces, are painted exposed structure and sealed concrete floors. Interior partitions are painted concrete masonry with hollow metal doors. The locker rooms/restrooms have epoxy painted concrete masonry walls, suspended acoustical tile ceilings. Classrooms and offices have painted gypsum board walls, carpeting, suspended acoustical tile ceilings, and solid core wood doors. The break room has painted gypsum board walls, vinyl composition tile flooring, andplastic laminate cabinetry.

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

4.0 Structural Narrative

OPN Architects, Inc. & CR architecture + design 6

Codes The building will be designed according to provisions in 2009 International Building Code (IBC).

Design Criteria The building will be designed for a ground snow load of 30 psf and snow drift loading per IBC. The live load will be designed as follows:

Classrooms: 50 psf + 20 psfAssembly Areas: 100 psf Hallways / Corridors: 100 psfStairs: 100 psfMechanical: 125 psfStorage: 125 psf

The wind load will be designed for 90 mph and Exposure C. The seismic loading will be based on Site Class D, to be verified in the Geotechnicalsoils report.

Foundations To be verified in the Geotechnical soils report, the main foundation system will be spread footings per the Geotechnical report recommendations. Reinforced concrete perimeter walls will be used to support exterior wallsand columns. Bottom of perimeter walls will be located 3'-6" below grade to protect against frost.

First Floor Framing

Second Floor Framing

The First floor will be slab on grade. Typical concrete slabs will be 4" thick and reinforced with welded wire fabric. Concrete slabs will be located on a minimum of 4" of compacted granular material per Geotechnical report recommendations.

The main floor will be a 6” concrete slab on a 2” - 20 ga. galvanized composite metal deck reinforced with welded wire fabric. Slab will besupported on steel beams/columns.

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

4.0 Structural Narrative

OPN Architects, Inc. & CR architecture + design 7

Roof Framing

Exterior Wall Systems

Lateral Resistance System

Pre-Engineered Frames

Roof framing consists of 1 1/2” - 20 ga. metal deck supported on steeljoists and steel beams/columns and masonry bearing walls.

Exterior walls will consist of either insulated precast concrete wall panels or light-gage steel studs with metal panels.

Lateral shear resistance to wind loads will be provided by reinforced masonry wall systems and precast concrete shear walls. Under special conditions, rigid moment resistive steel frames may be used.

Pre-Engineered building frames will be used for the training bays, warehouse and maintenance bays. Walls will have girts supporting metal panels. Roof will have purlins supporting metal deck.

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

5.0 HVAC Narrative

OPN Architects, Inc. & CR architecture + design 8

HVAC Overview

Codes

The main heating and cooling for the building shall be provided by a rooftop VAV system. Ventilation for these areas shall be through the outside air damper of the unit. The restrooms will be exhausted according to the latest code requirements.

The Warehouse will be heated by a dedicated rooftop unit.

The Training Bay will have a general exhaust system. Room supporting these areas will be heated only. Ventilation will be provided for each room.

The Maintenance Bay will have general exhaust and vehicle exhaust systems. Room supporting these areas will be heated only. Ventilation will be provided for each room.

2009 International Mechanical Code

Design Parameters Outside Air ConditionsDes Moines, IACooling Design: 93.0°F db, 76.0°F wbCooling Tower Design: 78°F wb, 89°F mdb

(1)

Heating Design: -9°F(1)

Inside Air Conditions

Heated and air conditioned spaces shall be maintained at the following indoor design conditions unless noted otherwise in the Room Criteria Sheets:

Summer Indoor, Occupied – 74°F +/-2, 50% RH +10, - 5%Summer Indoor, Unoccupied – 80°F +/-2, 50% RH +10, - 5%Winter Indoor Occupied – 72°F +/-2, 30% RH +10, -5% Winter Indoor Unoccupied – 65°F +/-2, 30% RH +10, -5%

Heated only spaces shall be maintained at: Winter: 65°F

Option 1Rooftop VAV System:

The Administration/Office areas shall be heated and cooled via a rooftop VAV system. The unit shall have a natural gas-fired heat exchanger and an electric air cooled condensing unit. Hot water or electric reheat coils in the VAV boxes shall modulate to maintain room temperature during the winter heating season. The VAV boxes shall vary the air flow to the space to maintain summer room temperatures. The coils shall also modulate if necessary during minimum flow through the box to maintain room temperatures.

A natural gas-fire high efficiency boiler shall provide heating water for the VAV reheat and auxiliary heating units.

MLBischof
Cross-Out
JETenney
Cross-Out
JETenney
Cross-Out
JETenney
Callout
Geothermal system
JETenney
Cross-Out
JETenney
Callout
geothermal system

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

5.0 HVAC Narrative

OPN Architects, Inc. & CR architecture + design 9

Ventilation shall be provide according to ASHRAE Standard 62.Outside air for ventilation shall be introduce through the units outside air damper. Building pressure shall be maintained via a pressure sensor and an exhaust air fan in the unit.

A DDC system shall control the various components.

Warehouse System The Warehouse will be heated by a dedicated gas-fired rooftop unit.

The Weidt Group is performing a Life Cycle Cost Analysis to determine the costs of provide heating and air conditioning to the Warehouse. This will be by a gas/electric rooftop unit or geothermal heat pump.

Training Apparatus BaySystems

Heating for this area shall be provided by overhead natural gas-fire radiant tube heaters. It shall have a general exhaust system capable of providing 1.5 CFM/SF of floor area for the purpose of exhaust CO and NO2 gasses. The system shall be controlled via CO and NO2 sensors located in the space. The area shall also be equipped with a vehicle tailpipe exhaust system that will automatically release from the apparatus on departure. A natural gas-fired makeup air unit shall provide makeup air for the exhaust system.

Adjacent heated only spaces shall have hot water or electric heaters to maintain winter room temperatures. Ventilation shall be provided according to ASHRAE Standard 62.

These controls shall be stand alone and integral with each system.

Maintenance Bay Systems: Heating for this area shall be provided by overhead natural gas-fire radiant tube heaters. It shall have a general exhaust system capable of providing 1.5 CFM/SF of floor area for the purpose of exhaust CO and NO2 gasses. The system shall be controlled via CO and NO2 sensors located in the space. The area shall also be equipped with a vehicle tailpipe exhaust system. A natural gas-fired makeup air unit shall provide makeup air for the exhaust system.

Adjacent heated only spaces shall have hot water or electric heaters to maintain winter room temperatures. Ventilation shall be provided according to ASHRAE Standard 62.

These controls shall be stand alone and integral with each system.

Option 2Geothermal Heat Pump System:

The Weidt Group is performing a Life Cycle Cost Analysis for utilizing a geothermal heat pump system.

Warehouse System Geothermal heat pump – heating only.

Training Apparatus BaySystems

The Weidt Group is performing a Life Cycle Cost Analysis for utilizing a hot water in-floor heating system.

Add auxiliary gas-fired unit heaters at overhead doors for fast recovery of space temperature.

MLBischof
Cross-Out
MLBischof
Cross-Out
MLBischof
Highlight
JETenney
Callout
in-floor exhaust
JETenney
Callout
now considering cooling as well

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

5.0 HVAC Narrative

OPN Architects, Inc. & CR architecture + design 10

Maintenance Bay Systems: The Weidt Group is performing a Life Cycle Cost Analysis for utilizing a hot water in-floor heating system.

Special Ventilation Systems(Same in option 1 &2)

The Woodworking Shop shall be equipped with a dust removal system for the saws.

The Fabrication room shall be capable of exhaust 1 CFM/SF to maintain indoor air quality.

The Welding Booth shall be equipped with a hood or extractor system for using during the welding process.

The Battery Room shall have a dedicated exhaust system interlocked with the battery charger.

The Chemical Storage Area shall have a dedicated exhaust system that shall run continuously. The fan shall have a non-sparking wheel with the motor outside the air stream. There shall be a break glass emergency shut down outside room.

All areas shall be provided with ventilation according to ASHRAE Standard 62.

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

6.0 Electrical Narrative

OPN Architects, Inc. & CR architecture + design 11

Electrical Overview The electrical and communications systems described herein will be representative of the systems that will be designed in the Bidding Documents.

Codes 2009 National Electric Code

Electrical Service Electrical Service to the building will be provided via a pad mount transformer provided by the power company located near the building.

Primary service conductors and connections, the meter and CTs will be provided by the power company.

Secondary service conductors, connections and the meter base and CT cabinet will be provided by the electrical contractor.

An existing 125 KW, natural gas powered generator will be relocated to this project for use in providing emergency backup power to serve emergency egress lighting loads as well as provide power to the Classrooms.

Distribution System Building power distribution system will be 480/277V, 3-phase, 4-wire. There will be 480/277V main distribution panel located in a lower level electrical room. The electrical service to the building will be approximately 1000-Amps. A transient Voltage Surge Suppression unit will be provided at the main distribution panel.

480/277V, 3-phase, 4-wire branch circuit distribution panel boards, powered from the building main distribution panel will be located near the mechanical and lighting loads being served, where possible.

208/120V, 3-phase, 4-wire branch circuit distribution panel boards, powered from the building main distribution panel, via a step down transformer, will be located near the loads being served, where possible. These branch circuit distribution panel boards will power receptacles, kitchen equipment,small equipment, and small mechanical loads.

An Automatic Transfer Switch (ATS) will be provided to transfer from normal power to backup Emergency Generator power in the event of a loss of normal power.

An emergency electrical distribution system will be provided to distribute the electrical power from the generator to the specific electrical loads, emergency egress lighting and Classrooms, in the event of a loss of normal power.

All branch circuit panelboards will be circuit breaker type with bolt on breakers and aluminum bus.

Each power and lighting panelboard will have spare capacity for 20% additional spaces and amperage capacities.

MLBischof
Cross-Out
MLBischof
Inserted Text
, 4500 SCBA Compressor, HVAC, overhead door, 6509 router, and Admin. 60 KW for shop,

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

6.0 Electrical Narrative

OPN Architects, Inc. & CR architecture + design 12

Receptacle branch circuits will be provided with separate neutrals. Isolated grounding circuits will not be provided for equipment unless specifically directed by the owner.

Motors of 3/4 HP and less will be 120V, single phase. Motors 1 HP and above will be 480V, three phase. Some equipment as manufactured may dictate exceptions to this rule.

Motors will have isolating safety switches in the motor circuit located near the motor. The switches will be capable of being padlocked in the “off” position.

Motors will be fed from distribution panelboards with discreet starters/VFD’s located in the vicinity of equipment.

Conduit inside the building will be EMT for branch circuits in dry locations only. Minimum conduit size will be 1/2 inch. PVC-40 conduit will be used when encased in concrete underground, and for separate ground wires in building. All conduit penetrations through walls and floors will be sealed.

Flexible metal conduit will be used for connections to motors (between aconduit and terminal box on a motor), connections to equipment subject to movement, connections from the conduit system to an electrified furniture system and recessed lighting fixtures. Liquid tight flexible metal conduit will be used for equipment mentioned above, in lieu of flexible conduit, in wet or damp locations.

All distribution feeders will be copper and will be installed in conduit.

Wall switches will be 20A, 120/277V, toggle type, single pole and 3-way as required. Convenience receptacles will be 20A, 125V, 3 wire, duplex,grounding type, specification grade. GFI receptacles will be provided restrooms, on the roof, outdoor and within 6’-0” of all sinks. Weatherproof cover plates will be provided for receptacles and switches installed in wet or damp locations.

Grounding System A complete grounding system will be provided in accordance with requirements of the National Electrical Code.

A main ground bus will be installed in the main electric room. This will be the main node for all bonding references.

Lighting Systems Lighting throughout the facility will be designed to support the visual tasks being performed, create comfortable and attractive luminous environments, and reinforce architectural forms and concepts. The lighting design will consider energy efficiency, economy of construction, and ease of maintenance.

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

6.0 Electrical Narrative

OPN Architects, Inc. & CR architecture + design 13

To reduce energy use, day lighting strategies such as dimming or perimeter switching will be considered.

Fluorescent lamps with electronic ballasts will be the primary interior light source. Lamps will be T8, or compact fluorescent with a 3500K color temperature, and 85 CRI. Ballasts will have minimum 0.88 ballast factor and 10% THD. Fluorescent lamps will have low mercury content (TLCP compliant).

Halogen and HID lamps and ballast will be used where fluorescent lighting is inappropriate or ineffective. HID lamps and ballasts will be the primary light source at the exterior. Some LED lamps and drivers will be considered at the exterior.

Illumination Levels:Target illumination levels will be in accordance with Illuminating Engineering Society (IES) recommendations. Average values will be calculated at a horizontal plane at the working/task height. The working plane will vary between floor level and 2'-6" AFF, depending on task. Calculations will include light-loss factors appropriate for the space and light source to account for decrease in light over time.

Area Target Light Level(Footcandles)

Training Apparatus BaysTactical Training RoomWarehouseMaintenance BaysWelding BoothFabrication Room Woodworking ShopWork RoomClassroom-ISC/EOCClassroom-ComputerKitchen/Lunch RoomConference Room/LibraryOfficesFitness RoomLibraryBreak RoomStairsLocker RoomsStorage RoomsRestroomsLobbyLaundry/Extraction

5050 30 5050505050503050/3040/3030 ambient (50 w/ task lights)3030105 10 30 103030

General Lighting by Area

Training Apparatus Bays, Tactical Training Room, Warehouse, and Maintenance Bays: General illumination will be provided by suspended or

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

6.0 Electrical Narrative

OPN Architects, Inc. & CR architecture + design 14

pendant mounted industrial linear fluorescent high bay fixtures with protective wire guards. Each fixture will have multiple lamps that will be switched separately to provide varied light levels. Lighting controls will be provided by manual switches and occupancy sensors in the space.

Welding Booth, Fabrication Room, Woodworking Shop, Compressor Room, Tire Storage/Repair, Battery Storage/Test Area, SCBA Rooms, Chemical Storage, Storage Rooms, Laundry/Extraction, and TOG Areas: General illumination will be provided by suspended or pendant mounted industrial linear fluorescent fixtures with protective wire guards. Lighting controls will be provided by manual switches and occupancy sensors in the space.

Work Room, Kitchen/Lunch Room, and Locker Rooms: General illumination will be provided by recessed mounted lensed lay-in troffer linear fluorescent fixtures. Lighting controls will be provided by manual switches and occupancy sensors in the space.

Classrooms and Conference Room/Library: General illumination will be provided by dimmable recessed mounted direct/indirect lay-in troffer linear fluorescent fixtures. Lighting controls will be provided by dimmer switches to provide varied light levels and occupancy sensors in the space.

Offices, Lobby, and Corridors: General illumination will be provided by recessed mounted direct/indirect lay-in troffer linear fluorescent fixtures with multiple lamps that will be switched separately to provide varied light levels and opportunity for daylighting. Ceiling or wall-box style occupancy sensor switches will provide control for lighting.

Restrooms: Fluorescent, linear and/or compact, fixtures will provide illumination in the Restrooms. Recessed fixtures will be used for general illumination and surface/wall mount fixtures will be utilized at the vanity areas. Lighting controls will be provided by manual switches and occupancy sensors in the restrooms.

Exit / Egress Lighting:

Emergency egress lighting shall be provided throughout the facility.Emergency egress lighting fixtures will be powered from the emergency generator.

Exit lights will be the LED type with red letters and chevron arrows.

Exterior Lighting :

Exterior walkways, building mounted and entrance illumination will be provided with a combination of pedestrian-scale metal halide pole mounted fixtures, bollards, exterior soffit downlights, and/or landscape lights.

Parking lot and drives, building mounted illumination will be provided with a combination of parking lot-scale metal halide pole mounted fixtures

Exterior lighting will be controlled by photocell and timeclock through the central lighting control system.

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

6.0 Electrical Narrative

OPN Architects, Inc. & CR architecture + design 15

Telecommunications Building Technology Conduit Infrastructure:

The following technology conduit and wiring infrastructure only for the facility will be provided. The actual Head end and Technical Equipment for telecommunications systems (voice and data) is NOT included in the design or scope of design services to be provided for this project at this time. The design for the electronic equipment (computers, server, etc.) to utilize this infrastructure is NOT to be provided via this scope.

Raceway and Distribution System:

A complete raceway system will be provided for voice (telephone) and data processing systems. The system will include recessed outlet boxes, conduitfrom outlet to either cable tray or direct to designate telecommunications/data rack area. The design for a system of cabling, and terminations for telecommunications systems (voice and data) is included. The design for the electronic head end equipment (computers, server, etc.) is NOT included.

Conduit will be extended from recessed outlet boxes to an accessible ceiling cavity. Conduit sleeves will be provided in rated walls for passage of wiring.

IT Grounding System:

A uniform telecommunications grounding and bonding system shall be provided in accordance with EIA/TIA-607, Grounding and Bonding Require-ments for Telecommunications in Commercial Buildings. This system shall be designed in conjunction with the electrical power grounding system.

The telecommunications grounding backbone shall consist of solid copper busbars and copper conductors interconnected with the existing building grounding system.

All bonding conductors shall be #6 AWG copper (minimum) conductors, green in color or marked appropriately, and installed in continuous lengths.

The telecommunications ground bus bars shall be a minimum of 1/4-inch thick, solid copper bar, electro-tin plated, and insulated from their supports.

Fire Alarm and Detection Systems A complete addressable fire alarm system will be provided in accordance

with applicable codes and requirements.

Fire alarm initiating devices shall include:

Manual fire alarm stations at exits and where exit travel distances exceed 150 ft.

Smoke detectors for initiating building safety functions including fan

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

6.0 Electrical Narrative

OPN Architects, Inc. & CR architecture + design 16

shutdown, door release, etc.

Heat detectors for initiating alarm.

Sprinkler alarm and supervisory switches.

Fire alarm notification appliances shall include:

Fire alarm strobe lights located throughout the building in accordance with governing codes and the Americans with Disabilities Act Accessibility Guidelines.

Fire alarm building safety control interfaces shall include:

Fan shutdown functions in accordance with NPFA 90A and governing codes.

Fire/smoke door release.

Locked door release.

Fire alarm control and annunciator panels shall be provided in location(s) approved by the Fire Department. They shall be equipped with control switches, indicators and readouts.

Remote station fire alarm reporting shall be by digital alarm communicator system using public switched telephone network in accordance with NFPA 72.

Sound System A Sound System for the facility is NOT included in the design or scope of design services to be provided for this project at this time.

Media Distribution Cabling will be provided for CATV broadband distribution. Cabling will consist of 18-gauge RG6 cable and shall be homerun back to the nearest main cross connect or intermediate cross connect closet. Cabling will consist of RG-11 cable between the outlets and the intermediate cross connect point.

Paging System A Paging System is NOT included in the design or scope of design services to be provided for this project at this time.

Electronic Security Systems Access Control System:

An Access Control System is NOT included in the design or scope of design services to be provided for this project at this time.

Intrusion Detection System:

An Intrusion Detection System is NOT included in the design or scope of design services to be provided for this project at this time.

MLBischof
Highlight
MLBischof
Text Box
Provide conduit, chases etc. for paging system.

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

6.0 Electrical Narrative

OPN Architects, Inc. & CR architecture + design 17

CCTV Surveillance System:

A CCTV Surveillance System is NOT included in the design or scope of design services to be provided for this project at this time.

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

7.0 Plumbing Narrative

OPN Architects, Inc. & CR architecture + design 18

Plumbing Overview The plumbing systems described herein shall be representative of the systems documented in detail in the Bidding Documents. These systems shall be in the contract of the Plumbing Contractor.

Code 2009 Uniform Mechanical Code

Potable Water Systems The goal shall be to maintain a minimum of 30 psig at the most remote flush valve and 8 psig at the most remote lavatory faucet. A water pressure booster pump shall be provided if necessary to maintain water pressure.

The potable water systems shall be designed to maintain a maximum velocity of eight fps in mains and risers, six fps in branches at designed flow conditions.

Water meter shall be installed in a room near the exterior of the building and shall contain water meter, multiple 2” reduced pressure zone backflow preventers sized for building flow, floor drains, separate 4” branch piping for truck fill lines and fire sprinkler entrance with zone valves and vertical double check valves, water flow switch, inspector’s test, etc.

The systems shall be designed to prevent water hammer conditions by utilizing shock arrestors for required individual fixtures, quick closing valves and batteries of fixtures.

Water piping shall be Type K copper below grade, Type L copper above grade with wrought copper fittings and lead free solder joints.

Shut-off valves shall be provided at strategic locations throughout the building for the isolation of piping sections for maintenance and repair.

Vacuum breakers shall be provided at all kitchen faucets and kitchenequipment water connections as required by plumbing codes.

Freeze proof wall hydrants shall be provided at approximately every 100 feet around the exterior of building.

The Plumbing Contractor shall perform disinfection of all domestic water system piping.

Non-Potable Water Systems Truck Fill Piping:

Maintenance Bays and Training Apparatus Bays shall have a 4” truck fill piping mains for each area with 1-1/2” branch lines terminating with 1-1/2” male national thread connection and 1/4 turn truck fill valve terminating at 15’-6” above finished floor.

Truck fill piping shall be copper piping.

Valves shall be of brass construction.

MLBischof
Highlight
JETenney
Cross-Out

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

7.0 Plumbing Narrative

OPN Architects, Inc. & CR architecture + design 19

2” spool shall be provide for a future separate 2” water meter on this line at the take off from the fire protection service entrance piping.

2” reduced pressure zone backflow preventer shall be provided after the spool and a 4” O.S. and Y. gate valve or indicator butterfly valve for master shutoff of truck fill line.

Water Heaters Gas Fired Water Heaters:

Water heaters shall be 94% efficiency, natural gas fired.

Domestic hot water from water heater(s) shall be supplied at 140º F. and tempered down to 110º F at lavatories, hand wash sinks, Conference Room sinks, Break Room sinks.

Mop service Basins, Clothes Washers and Extractors shall be supplied with 140º F domestic hot water.

Dishwasher and pot and pan sink final rinse compartment shall be provided with booster heaters to raise water temperature to 180º F from the 140º F. supplied by the domestic hot water system.

Recirculating pumps shall be provided to assure availability of hot water throughout the systems. Circulation Pump(s) shall be controlled by an aqua stat and the building DDC system – shutting pump(s) off during unoccupied times of the building for energy savings.

Building Gas Systems Natural Gas:

Natural Gas shall be provided to Domestic Water Heaters, Mechanical Heating and Ventilation Equipment, Clothes Dryer(s) and Boiler(s) with flexible connector and manual gas shutoff valve.

Gas shall be provide to Kitchen for kitchen Equipment and shall have flexible connector, Automatic Gas Shut off valve connected to the Kitchen Hood Fire Extinguishing system and manual gas shutoff valve(s) as required.

If required, all interior piping shall be Schedule 40 black steel.

Lock-up type regulators shall be provided at each connection requiring 7” w.c. or greater.

All piping 1 psi and greater will have welded joints. Joints for piping under 1 psi shall be threaded (or welded) 2” and smaller; welded above 2”.

A separate gas pressure regulator and shutoff valve shall be provided to the emergency generator after the gas meter and before the pressure regulator

MLBischof
Callout
no dishwasher, large commercial sinks.
MLBischof
Cross-Out
JETenney
Cross-Out

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

7.0 Plumbing Narrative

OPN Architects, Inc. & CR architecture + design 20

and shutoff valve for the building.

Gas in building shall be distributed at 0.5” w.c inside building. If gas loads are such that pipe sizes are exceed 4” and 600, in length gas will be distributed from the roof at 2 psi and reduced down to 0.5” w.c to drop thru roof into building. Gas loads will be zoned (grouped together in smaller areas of gas usage) when distributed from the roof.

Compressed Air Piping:

Compressed Air piping shall be provided to Maintenance Bays, Tire Storage/Repair Area, Fabrication Room, Woodworking Shop, SCBA Cleaning Room, Extinguisher Filling Room, SCBA Room and Training Apparatus Bays.

Two air compressors (sized at 60% load) shall be provided with one storage receiver tank, air filters with manual by-pass line, shutoff valves and unions, refrigerated air dryer with by-pass line, shutoff valves and unions and pace regulator system by-pass line, shutoff valves and unions. This equipment shall be located in the Compressor Room.

Compressed Air piping shall be Transair Aluminum Pipe and Fittings and Valves.

Compressed Air piping shall be provided to Maintenance Bays, Tire Storage/Repair Area and Training Apparatus Bays shall be terminated with retractable hose reels with 50 foot of hose and quick connect coupler. Hose reels shall be mounted at the ceiling or on the bottom of trusses or bar joists.

Compressed Air piping shall be provided to Tire Storage/Repair Area, Fabrication Room, Woodworking Shop, SCBA Cleaning Room, and Extinguisher Filling Room, and SCBA Room shall be terminated with manual shutoff valve and quick connect coupler at various points around the room. This piping shall be run exposed on the walls, above the ceiling and terminate at approximately 42” above finished floor.

Breathing Air:

Breathing Air Piping shall be in rooms SCBA Cleaning Room and SCBA Room. . This piping shall be run exposed on the walls, above the ceiling and terminate at approximately 42” above finished floor.

Piping shall be fully annealed high quality type 316, seamless or welded and drawn stainless steel tubing astm a269 or a213.

Fittings shall be "Swagelok" 316ss. maximum working pressure 5000 psi.

JETenney
Callout
one compressor
JETenney
Cross-Out

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

7.0 Plumbing Narrative

OPN Architects, Inc. & CR architecture + design 21

Shut-off valve shall be "whitey" model h83p 2-way ball valve. 316 stainless steel body and end screws. maximum working pressure 5000 psi.

Pressure gauge shall be 2-1/2" stainless steel line gauge, 1/4" npt.

Pressure regulator shall be high pressure regulator, 6000 psi in, 2200 psi out, 316 stainless steel.

In-line bleeder shall be 1/4" in-line bleeder with thumb screw, 6000 psi, 316 stainless steel.

Quick connectors shall be 1/4" quick connectors, 6000 psi, 316 stainless steel screw on type.

Sanitary Waste and Vent Systems Sanitary Waste:

Sanitary waste from fixtures and equipment in general building areas shall be routed by gravity through a separate waste and vent system to the sanitary sewer service.

Sanitary waste and vent piping from general building areas shall be no-hub cast-iron pipe and fittings. Underground piping shall be bell-and-spigot extra-heavy cast-iron pipe with push-on joints.

Grease Waste:

There will be cooking in the facility. Therefore a grease interceptor will be required.

Special/Hazardous Waste:

Training Apparatus Bays, Dirty Restrooms, Laundry/Extraction, Maintenance Bays and Tire Storage/Repair Area floor trenches, floor drains and sinks shall discharge into a sand interceptor as detail by the city of Des Moines plumbing inspection department.

Battery Storage/Test Area, Chemical Storage and Extinguisher Filling Room shall have acid resistant waste and vent piping and be run through a neutralization tank which shall then discharge to the sanitary sewer system.

Plumbing Fixtures Base Building Plumbing Fixtures:

Plumbing fixtures shall be commercial quality and shall be selected to be ADA compliant for the physically disabled where required.

Water Closets: Wall-hung, vitreous china, water conserving, with battery powered sensor operated dual flush valve.

Urinals: Wall-hung, vitreous china, water conserving, low flow (one pint) with

MLBischof
Callout
trench drains - shop at door between bays. training mid bays.
MLBischof
Cross-Out
MLBischof
Callout
Maintenance Bay trench drains not to be under vehicles

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

7.0 Plumbing Narrative

OPN Architects, Inc. & CR architecture + design 22

battery powered sensor operated flush valve and urinal.

Lavatories: Wall-hung and counter-mounted, vitreous china type with appropriate trim and battery powered sensor operated faucets and 0.5 gpm aerators.

Shower Stalls: One-piece gelcoat enclosure with microban® antibacterial protection and non-scald thermostatic shower mixing valve, low flow shower head (1.6 gpm) and stainless steel curtain rod with fire retardant antibacterial vinyl curtain.

ADA Shower Units: One-piece gelcoat enclosure with microban® antibacterial protection and non-scald thermostatic shower mixing valve, low flow shower head (1.6 gpm) and stainless steel curtain rod with fire retardant antibacterial vinyl curtain and shall have a fold up teakwood phenolic transfer seat with stainless steel supports and personal hand-held shower on slide bar with a 60” flexible hose.

Stainless Steel Sinks: Kitchen, Break Room and Conference room areas shall be: Counter-mounted, 18 gauge, type 304 stainless steel, double or single compartment types and sizes, with gooseneck faucet with dual wing handle faucets handles, 2.1 gpm flow aerators.

Acid Resistant Stainless Steel Sinks: Battery Storage/Test Area and Chemical Storage shall be: Counter-mounted, 18 gauge, type 316 acid resistant stainless steel, double or single compartment types and sizes, with gooseneck faucet with dual wing handle faucets handles, 2.1 gpm flow aerators.

Large Compartment Stainless Steel Sinks: 18 gauge, type 304 stainless steel, double or single compartment types and sizes, with swing spout with dual wing handle faucets handles, 2.1 gpm flow aerators, knee pedal operated hose spray bed pan washer, twin drain boards, locking basket strainer(s) and tubular stainless steel legs.

Molded Stone Sinks: SCBA Room, Laundry/Extraction, Wash Up Area andDirty Restroom areas shall be: Floor-mounted with legs, molded stone, various types and sizes, with appropriate trim.

Mop Service Basins: Floor-mounted, terrazzo material, with appropriate trim.

Electric Water Coolers: Wall-hung, stainless steel, refrigerated types.

A combination Emergency Eye/Face and Shower shall be provide in the Battery Storage/Test Area and Chemical Storage at approximately 10 seconds travel time or 55 foot radius travel. Units shall be supplied with tempered water to Eye/Face wash sprays and deluge shower head.

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

7.0 Plumbing Narrative

OPN Architects, Inc. & CR architecture + design 23

An Emergency Eye/Face station shall be provide in the Maintenance Baysand Training Apparatus Bays at approximately 10 seconds travel time or 55 foot radius travel . Units shall be supplied with tempered water to Eye/Face wash sprays conforming to current ANSI Standards.

Insulation and Pipe Identification All piping, components and equipment subject to sweating, heat loss or freezing shall be insulated with appropriate thickness of fiberglass insulation with a fire-resistant jacket.

Water piping shall be insulated to prevent condensation on cold piping, and to reduce thermal losses on hot piping. Types and thicknesses shall be as required by the Building Code.

All piping in accessible areas shall be labeled with proper indicators with system and direction of flow through color-coded labels.

Storm Water System Storm water from roof drains at the flat roof for kitchen equipment shall beconveyed by a separate gravity system through internal piping system to aninfiltration based storm water system on the site. Secondary storm overflow drains shall be provided near roof drains and be piped by aseparate system to discharge open sight above grade.

Above-ground piping shall be no-hub cast-iron pipe and fittings. Underground piping shall be bell-and-spigot extra-heavy cast-iron pipe with push-on joints.

Insulation shall be provided for all horizontal rainwater conductors, including elbows, roof drain bodies and vertical piping underside of roof. Piping exposed to freezing conditions shall be insulated and electrically heat traced

Perimeter Foundation and Under-Slab Drainage shall be provided per theGeotechnical Engineering recommendations on the soil boring analysis. Aforementioned drainage shall be routed to the building storm drain.

Lubrication Systems System:

Ceiling mounted with retractable 50’ hose, compartments and hose reels for lube (grease), Anti-Freeze, 10w oil, 10w30 oil, 15w40 oil, window washer fluid and compressed air.

Piping:

Shall be exposed on ceiling or bottom of structure and run from each dispensing unit back to central supply station consisting of 55 gallon drum barrels and compressed air pumps

Standard iron pipe shall be used for Lube (grease) and Oil systems.

MLBischof
Cross-Out

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

7.0 Plumbing Narrative

OPN Architects, Inc. & CR architecture + design 24

Copper piping shall be used for Anti-Freeze and Window Washer Fluid.

Fire Protection Entire building to be fully sprinklered with an automatic wet sprinkler system.

Flow test data provided determine that a fire pump is required to satisfy system hydraulic demands.

Fire protection standpipes shall be provided in each of the required stairways.

Entire fire protection system to comply with NFPA and Factory Mutual requirements.

Additional fire services/systems shall be provided for every 52,000 sq. ft. of any one floor level.

Individual zones with flow detection switches, control valves and test/drain connections shall be provided on each floor within a stairwell.

Tamper switches shall be provided for all control valves.

Density and sprinkler spacing shall be designed to provide a level of protection consistent with the occupancy hazard.

Piping for standpipes and sprinkler systems shall be Schedule 40 and/or Schedule 10 black steel.

Preaction and/or Dry Pipe sprinkler systems will not be required.

The need for Clean Agent Supression systems shall be determined as the project progresses.

MLBischof
Cross-Out
MLBischof
Cross-Out

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

8.0 Sustainable Design Narrative

OPN Architects, Inc. & CR architecture + design 25

Introduction The sustainable design goal for the project is to earn a LEED® Silver Rating, [i.e. between 50 to 59 points] in the LEED Version 3 rating system. The Design Team – including architects, engineers, landscape architects, and owner’s representatives- has reviewed the LEED requirements as they apply to this project. This group identified which LEED requirements were clearly applicable to the project at minor cost, which credits were not applicable, and which credits might be feasible but would require further study and possibly significant additional cost. In the scoring table that follows, those LEED requirements that are applicable and can be achieved with no cost or at minor cost to the project are shown in the “Yes” column; those that add significant cost or require further investigation are shown in the “Maybe” column. The team will examine the Maybe category of credits over the course of design and prepare cost estimates for each. Costly credits with negligible benefits to the owner or the environment will be rejected, those with promise will be included in the design.

The Design Team’s first goal is to establish a list of credits that achieve 52-58 LEED points to pursue the achievement of the project goal: Earning a at a minimum LEED Silver Rating. Through the course of developing contract documents and during construction, the team anticipates that earning one or more of these credits may prove to be impossible; one or two credits may be rejected by the LEED reviewers during the actual certification process.Currently, the Design Team is anticipating a LEED Silver Rating of 54credits with 16 variable, or alternate, credits that could be included depended on their cost of implementation.

The following paragraphs highlight the Design Team’s approaches for earning credits in each of the LEED categories. A table listing each credit that is being considered is located at the end.

Sustainable Sites The site was selected not for the purposes of the LEED evaluation, however, because it was previously developed, there is potential for Sustainable Sites LEED credit 3 Brownfield Development. The facilitydesign preserves many existing trees and has the ability pursue the restoration of natural habitat. Irrigation systems will not be needed due to the use of only native and hardy plant materials.

Parking spaces will be provided to meet the programmatic needs and minimum zoning requirements of the City of Des Moines. Bicycle parking and preferred parking spaces for low-emitting and fuel-efficient cars and car-pooling will be provided. An exploration of pervious pavers for site parking and approaches, along with high Solar Reflectance rated roof on the building will help reduce the heat island effect.

Storm water runoff will be minimized through the use of on site detention.

Lighting will be carefully designed to minimize light pollution.

Water Efficiency The vegetation on the site will be native or adapted to local climate requiring no irrigation system. Inside the building, water use will be reduced by water-conserving faucets, showerheads and urinals. The use of rainwater andcondensate water for flushing toilets was investigated and was found to be unfeasible for the project.

MLBischof
Callout
Certified
MLBischof
Highlight

DSM-Fire Training and Logistics FacilitySchematic Design NarrativeCity of Des Moines IA.June 30, 2010

8.0 Sustainable Design Narrative

OPN Architects, Inc. & CR architecture + design 26

Energy & Atmosphere A variety of energy saving strategies will be employed to reduce energy use by over 26% compared with ASHRAE 90.1 2004. Enhanced commissioning will cover mechanical systems, lighting and daylighting controls, along with life safety and fire suppression systems. Other features that may beincorporated are refrigerants that reduce global warming and stratospheric ozone depletion, on-site renewable energy systems, metering equipment to monitor energy end-uses and green power purchase.

Materials & Resources Recycling of waste during building operations is being planned for by providing space for recycling storage and pick-up. Through the development of a construction waste management plan, 75% of the construction waste may be diverted from landfills. Specifications will require significant use of architectural materials with recycled content, and materials manufactured within a 500 mile radius. For the wood products in the building, the design team is considering the use of FSC certified wood for more than half of the wood and wood products in the building.

Indoor Environmental Quality Daylight, views, and low Volatile Organic Compounds (VOC) finish materials form the pillars for indoor environmental quality in this building. The building is being designed to provide daylight to 75% of the regularly occupied spaces and views to the outside for 90% of the regularly occupied spaces. During construction, materials will be stored in a certain manner thatprevents moisture damage, the air handling equipment will be operated with proper filters; after construction, the building will undergo a two-week flush-out just prior to occupancy. Interior finish materials will be specified to have strict limits on the emissions of VOC. The mechanical system will meet ASHRAE standards for ventilation and comfort.

Innovation & Design Process

Regional Priority

The sustainable design consultants are LEED Accredited Professionals, as are some other members of the Design Team. The desired innovation credits will likely be attained by pursuing credits SS 5.1 “revitalized prairie,”and SS 6.1 “drafting wells.”

Regional priority credits that have been identified for the area and are applicable to the project include: Site Credits 4.1, 4.2, and 6.1 and Materials & Resources Credit 2. An additional credit will be awarded for each of the specified credits once they are achieved.

Des Moines Fire Department Logistics and Training Facility

Possible DocumentationLEED Version 3 Scorecard Points Yes Maybe No Responsibility

SUSTAINABLE SITES

Prereq 1 Construction Activity Pollution Prevention Req. x CIVILCredit 1 Site Selection RP 1 1 NACredit 2 Development Density & Community Connectivity RP 5 5 NACredit 3 Brownfield Redevelopment 1 1 NACredit 4.1 Alternative Transportation- Public Transportation Access RP 6 6 NACredit 4.2 Alternative Transportation- Bicycle Storage & Changing Rooms 1 1 NACredit 4.3 Alternative Transportation- Low-Emitting and Fuel-Efficient Vehicles 3 3 OWNERCredit 4.4 Alternative Transportation- Parking Capacity 2 2 OWNERCredit 5.1 Site Development- Protect or Restore Habitat 1 1 OPNCredit 5.2 Site Development- Maximize Open Space 1 1 OPNCredit 6.1 Stormwater Design- Quantity Control RP 1 1 CIVIL/OWNERCredit 6.2 Stormwater Design- Quality Control 1 1 CIVIL/OWNERCredit 7.1 Heat Island Effect- Nonroof 1 1 OPNCredit 7.2 Heat Island Effect- Roof 1 1 OPNCredit 8 Light Pollution Reduction 1 1 MECH/ENGR

WATER EFFICIENCYPrereq 1 Water Use Reduction Req. x OPN LACredit 1 Water Efficient Landscaping 2 to 4 4 OPN LACredit 2 Innovative Wastewater Technologies RP 2 2 NACredit 3 Water Use Reduction 2 to 4 4 MECH/ENGR

ENERGY & ATMOSPHEREPrereq�1 Fundamental�Commissioning�of�Building�Energy�Systems Req. x OWNERPrereq�2 Minimum�Energy�Performance Req. x MECH/ENGRPrereq�3 Fundamental�Refrigerant�Management Req. x MECH/ENGRCredit�1 Optimize�Energy�Performance 1�to�19 8 4 7 MECH/ENGRCredit�2 On�Site�Renewable�Energy 1�to�7 2 7 NACredit�3 Enhanced�Commissioning 2 2 1 NACredit�4 Enhanced�Refrigerant�Management 2 2 MECH/ENGRg g /Credit�5 Measurement�&�Verification 3 3 MECH/ENGRCredit�6 Green�Power 2 2 OWNER

MATERIALS & RESOURCESPrereq 1 Storage & Collection of Recyclables Req. x� OPNCredit 1.1 Building Reuse- Maintain Existing Walls, Floors and Roof 1 to 3 3 OPNCredit 1.2 Building Reuse- Maintain Interior Nonstructural Elements 1 1 OPNCredit 2 Construction Waste Management RP 1 to 2 2 OPNCredit 3 Materials Reuse 1 to 2 2 OPNCredit 4 Recycled Content 1 to 2 2 OPNCredit 5 Regional Materials 1 to 2 2 OPNCredit 6 Rapidly Renewable Materials 1 1 OPNCredit 7 Certified Wood 1 1 OPN

INDOOR ENVIRONMENTAL QUALITYPrereq 1 Minimum Indoor Air Quality (IAQ) Performance Req. x MECH/ENGRPrereq 2 Environmental Tobacco Smoke (ETS) Control Req. x OWNERCredit 1 Outdoor Air Delivery Monitoring 1 1 MECH/ENGRCredit 2 Increased Ventilation 1 1 MECH/ENGRCredit 3.1 Construction IAQ Management Plan- During Construction 1 1 MECH/ENGRCredit 3.2 Construction IAQ Management Plan- Before Occupancy 1 1 MECH/ENGRCredit 4.1 Low-Emitting Materials- Adhesives & Sealants 1 1 OPNCredit 4.2 Low-Emitting Materials- Paints & Coatings 1 1 OPNCredit 4.3 Low-Emitting Materials- Flooring Systems 1 1 OPNCredit 4.4 Low-Emitting Materials- Composite Wood & Agrifiber Products 1 1 OPNCredit 5 Indoor Chemical & Pollutant Source Control 1 1 OPNCredit 6.1 Controllability of Systems- Lighting 1 1 MECH/ENGRCredit 6.2 Controllability of Systems- Thermal Comfort 1 1 MECH/ENGRCredit 7.1 Thermal Comfort- Design 1 1 MECH/ENGRCredit 7.2 Thermal Comfort- Verification 1 1 OWNERCredit 8.1 Daylight & Views- Daylight 1 1 MECH/ENGRCredit 8.2 Daylight & Views- Views 1 1 MECH/ENGR

INNOVATION IN DESIGNCredit�1 Innovation�in�Design 1�to�5 5 OWNERCredit�2 LEED®�Accredited�Professional 1 1 OPN

REGIONAL PRIORITYCredit�1 Regional�Priority 1�to�4 3 1Credit�1 Regional�Priority 1�to�4 3 1

Point Totals 110 54 16 43 LEED Certification LEED�Certified�Silver�Building

27

28

29

30

MLBischof
Polygon
MLBischof
Callout
Move offices to exterior wall and make larger

31