inputs and outputs to aggregate production planning

35
1 DSCI4743 Inputs and Outputs to Aggregate Production Planning Aggregate Production Planning Company Policies Financial Constraints Strategic Objectives Units or dollars subcontracted, backordered, or lost Capacity Constraints Size of Workforce Production per month (in units or $) Inventory Levels Demand Forecasts

Upload: vallerie-aubert

Post on 03-Jan-2016

57 views

Category:

Documents


2 download

DESCRIPTION

Capacity Constraints. Strategic Objectives. Company Policies. Demand Forecasts. Financial Constraints. Aggregate Production Planning. Size of Workforce. Units or dollars subcontracted, backordered, or lost. Production per month (in units or $). Inventory Levels. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Inputs and Outputs to Aggregate Production Planning

1DSCI4743

Inputs and Outputs to Aggregate Production Planning

AggregateProductionPlanning

CompanyPolicies

FinancialConstraints

StrategicObjectives

Units or dollarssubcontracted,backordered, or

lost

CapacityConstraints

Size ofWorkforce

Productionper month

(in units or $)

InventoryLevels

DemandForecasts

Page 2: Inputs and Outputs to Aggregate Production Planning

22DSCI4743

Material Requirements Planning (MRP)

• A computerized inventory control & production planning system

• Schedules component items when they are needed - no earlier and no later

Page 3: Inputs and Outputs to Aggregate Production Planning

33DSCI4743

When to Use MRP

• Dependent and discrete items

• Complex products

• Job shop production

• Assemble-to-order environments

Page 4: Inputs and Outputs to Aggregate Production Planning

44DSCI4743

Demand Types

Two Types of Demand: Independent

• Not related to the demand for any other product & must be forecast

• MPS items are independent demand items

Dependent• Directly related to other items or end items• Such demand should be calculated should not be

forecast

Page 5: Inputs and Outputs to Aggregate Production Planning

55DSCI4743

MRP Inputs & OutputsMaster Production Schedule

MaterialRequirements

Planning

Planned Order Releases

Work Orders Purchase Orders Rescheduling Notices

ProductStructure

File

InventoryMaster

File

Page 6: Inputs and Outputs to Aggregate Production Planning

66DSCI4743

MRP Inputs

• Master production schedule

• Product structure file

• Inventory master file

Page 7: Inputs and Outputs to Aggregate Production Planning

77DSCI4743

Master Production Schedule

• Drives MRP process with a schedule of finished products

• Quantities represent production not demand

• Quantities may consist of a combination of customer orders & demand forecasts

• Quantities represent what needs to be produced, not what can be produced

Page 8: Inputs and Outputs to Aggregate Production Planning

88DSCI4743

Product Structure TreeLevel 0

Level 1

Level 2

Level 3

Clipboard

Rivet (2)

Iron Rod

(3 in.)

Spring (1)

Spring Steel

(10 in.)

Bottom Clip (1)

Top Clip (1)

Pivot (1)

Sheet Metal (8 in2)

Clip Assembly (10)

Sheet Metal (8 in2)

Board (1)

Pressboard (1)

Finish (2oz.)

Page 9: Inputs and Outputs to Aggregate Production Planning

99DSCI4743

Indented Bill of Material

LEVEL ITEM Unit of Measure Quantity0 - - - - Clipboard Ea 1- 1 - - - Clip Assembly Ea 1- - 2 - - Top Clip Ea 1- - - 3 - Sheet Metal In2 8- - 2 - - Bottom Clip Ea 1- - - 3 - Sheet Metal In2 8- - 2 - - Pivot Ea 1- - - 3 - Iron Rod In 3- - 2 - - Spring Ea 1- - - 3 - Spring Steel In 10- 1 - - - Rivet Ea 2- 1 - - - Board Ea 1- - 2 - - Press Board Ea 1- - 2 - - Finish Oz 2

Page 10: Inputs and Outputs to Aggregate Production Planning

1010DSCI4743

Specialized BOMS

• Phantom bills• transient subassemblies• never stocked• immediately consumed in next stage

• K-bills• group small, loose parts under pseudoitem #• reduces paperwork

Page 11: Inputs and Outputs to Aggregate Production Planning

1111DSCI4743

Specialized BOMS

• Modular bills• product assembled from major subassemblies

& customer options• modular bill kept for each major subassembly• simplifies forecasting & planning• automobile example

- 3 x 8 x 3 x 8 x 4 = 2,304 configurations- 3 + 8 + 3 + 8 + 4 = 26 modular bills

Page 12: Inputs and Outputs to Aggregate Production Planning

1212DSCI4743

Inventory Master File

Description Inventory Policy

Item Board Lead time 2

Item no. 7341 Annual demand 5,000

Item type Manuf. Holding cost 1

Prod/sales Ass’y Ordering/setup cost 50

Value class B Safety stock 25

Buyer/planner RSR Reorder point 39

Vendor 07142 EOQ 316

Phantom code N Minimum order qty 100

Unit price/cost 1.25 Maximum order qty 500

Pegging Y Multiple order qty 100

Page 13: Inputs and Outputs to Aggregate Production Planning

1313DSCI4743

Inventory Master File, Con’t.

Physical Inventory Usage/SalesOn hand 100 YTD usage/sales 1,100Location W142 MTD usage/sales 75On order 50 YTD receipts 1,200Allocated 75 MTD receipts 0Cycle 3 Last receipt 8/25Difference -2 Last issue 10/5

CodesCost acct. 00754Routing 00326

Engr 07142

Page 14: Inputs and Outputs to Aggregate Production Planning

1414DSCI4743

Inventory Accuracy

1. Maintain orderly stockrooms2. Control access to stockrooms3. Establish & enforce procedures for inventory

withdrawal4. Ensure prompt and accurate entry of inventory

transactions5. Take physical inventory count on a regular basis6. Reconcile inventory discrepancies in a timely manner

(use cycle counting)

Page 15: Inputs and Outputs to Aggregate Production Planning

1515DSCI4743

The MRP Matrix

Gross Requirements

Scheduled Receipts

Projected On Hand

Net Requirements

Planned Order Receipts

Planned Order Releases

ITEM: LLC: Lot Size: LT: PD 1 2 3 4 5 6 7 8 9

Page 16: Inputs and Outputs to Aggregate Production Planning

1616DSCI4743

Parts Of MRP Matrix

• Item name or number identifying scheduled item

• LLC low-level-code; lowest level at which item appears in a product structure

• Lot size order multiples of this qty; can be min/max qty

• LT (lead time)-time from order placement to receipt

• PD (past-due)-orders behind schedule

• Gross requirements-demand for item by time period

Page 17: Inputs and Outputs to Aggregate Production Planning

1717DSCI4743

• Scheduled receipts- quantity already on order & receipt date

- released orders become scheduled receipts

• Projected on hand - expected on-hand inventory at end of period

• Net requirements - net amount needed after on-hand adjustments

• Planned order receipts - net requirements adjusted for lot-sizing

• Planned order releases - planned order receipts offset by lead time

Parts Of MRP Matrix

Page 18: Inputs and Outputs to Aggregate Production Planning

1818DSCI4743

MRP Example

Item On Hand Scheduled Receipts Lot Size MPS

A 10 0 1 100, period 8

B 5 0 1 - - -

C 140 0 150 - - -

ALT=3

B (3)LT=4

C (2)LT=2

Page 19: Inputs and Outputs to Aggregate Production Planning

1919DSCI4743

MRP Matrices For A & BItem: A LLC: 0 PeriodLot size: 1 LT: 3 PD 1 2 3 4 5 6 7 8Gross requirements 100Scheduled receiptsProjected on hand 10 10 10 10 10 10 10 10 0Net requirements 90Planned order receipts 90Planned order releases 90

Item: B LLC: 1 PeriodLot size: 1 LT: 4 PD 1 2 3 4 5 6 7 8Gross requirements 270Scheduled receiptsProjected on hand 5 5 5 5 5 0 0 0 0Net requirements 265Planned order receipts 265Planned order releases 265

Page 20: Inputs and Outputs to Aggregate Production Planning

2020DSCI4743

MRP Matrices For C

Item: C LLC: 1 PeriodLot size: 150 LT: 2 PD 1 2 3 4 5 6 7 8Gross requirements 180Scheduled receiptsProjected on hand 140 140 140 140 140 110 110 110 110Net requirements 40Planned order receipts 150Planned order releases 150

Page 21: Inputs and Outputs to Aggregate Production Planning

2121DSCI4743

Manufacturing Resource Planning (MRP II)

• Extension of MRP

• Plans all resources needed for running a business

• Usually includes capacity planning, but

• Has many different modules

Page 22: Inputs and Outputs to Aggregate Production Planning

2222DSCI4743

MRP II Modules

Forecasting

Customer order entry

Production planning / master production scheduling

Product structure / bill-of-material processor

Inventory control

Material requirements planning

Capacity planning

Shop floor control

Purchasing

Accounting

Financial analysis

Page 23: Inputs and Outputs to Aggregate Production Planning

2323DSCI4743

Capacity Requirements Planning (CRP)

• Computerized system that projects loads from the planned order releases of MRP

• Creates load profile

• Identifies underloads and overloads

Page 24: Inputs and Outputs to Aggregate Production Planning

2424DSCI4743

Feasible?

MarketingPlan

FinancialPlan

BusinessPlan

ProductionPlan

No

moreYes

MRP II Diagram

Page 25: Inputs and Outputs to Aggregate Production Planning

2525DSCI4743

Master productionschedule

Material requirementsplanning

Capacity requirementsplanning

Manufacture

InventoryShop floor

control

Purchaseorders

Workorders

Feasible?No

Yes

Feedback

MRP II Diagram

Page 26: Inputs and Outputs to Aggregate Production Planning

2626DSCI4743

Problems with MRP

• Material requirements plan is first; capacity is an afterthought

• MRP assumes fixed lead times

• Excessive reporting requirements

Page 27: Inputs and Outputs to Aggregate Production Planning

2727DSCI4743

Using the Material Requirements Plan

• Computer performs all calculations & creates planned order releases,

• Computer software can create exception messages & suggest types of action

• Computer does not (usually) issue purchase or manufacturing orders or reschedule open orders

• Therefore, a Planner is needed

Page 28: Inputs and Outputs to Aggregate Production Planning

2828DSCI4743

The Basic Responsibilities of a Planner

• Launch (release) orders to purchasing or shop floor• Reschedule due dates of open (existing) orders as

required• Reconcile errors & try to find their cause• Address critical material shortages by expediting or

re-planning• Coordinate w/other planners, master production

schedulers, production activity control, & purchasing

Page 29: Inputs and Outputs to Aggregate Production Planning

2929DSCI4743

Prospects for MRP/MRP II

• Coordinates strategy among different functional areas• Responds quickly to what-if? questions at various levels• BOM processors, purchase modules, & customer order

entry are standard requirements for Manufacturing Information Systems

• Monitors design & vendor quality, & customer service• Builds trust, teamwork, & better decisions• Cash-flow planning & profit/cost projections

Page 30: Inputs and Outputs to Aggregate Production Planning

3030DSCI4743

Advanced Planning & Control Systems

• Enterprise Resource Planning (ERP)• updates MRP II with relational DBMS, GUI &

client/server architecture; covers entire enterprise

• Customer Resource Management (CRM)• links business planning & mgmt control systems

• Customer-Oriented Manufacturing Management Systems (COMMS)

• unites departments & suppliers around customer

• multi-plant planning, multiple languages & currencies

Page 31: Inputs and Outputs to Aggregate Production Planning

31DSCI4743

Hierarchical Planning ProcessItems

Product lines or families

Individual products

Components

Manufacturing operations

Resource level

Plants

Individual machines

Critical work centers

Production Planning Capacity Planning

Resource Requirements Plan

Rough-Cut Capacity Plan

Capacity Requirements Plan

Input/Output Control

Aggregate Production Plan

Master Production Schedule

Material Requirements Plan

Shop Floor Schedule

All work centers

Page 32: Inputs and Outputs to Aggregate Production Planning

3232DSCI4743

The Alpha Beta Company

Item On Hand Scheduled Receipts Lot Size MPS

A 10 0 1 100, period 8

B 5 0 1 200, period 6

C 140 0 150 - - -

D 200 0 250 - - -

ALT=3

C (3)LT=4

D (2)LT=2

D (3)LT=2

BLT=2

Page 33: Inputs and Outputs to Aggregate Production Planning

3333DSCI4743

MRP Matrices For A & BItem: A LLC: 0 PeriodLot size: 1 LT: 3 PD 1 2 3 4 5 6 7 8Gross requirements 100Scheduled receiptsProjected on hand 10 10 10 10 10 10 10 10 0Net requirements 90Planned order receipts 90Planned order releases 90

Item: B LLC: 0 PeriodLot size: 1 LT: 2 PD 1 2 3 4 5 6 7 8Gross requirements 200Scheduled receiptsProjected on hand 5 5 5 5 5 5 0 0 0Net requirements 195Planned order receipts 195Planned order releases 195

Page 34: Inputs and Outputs to Aggregate Production Planning

3434DSCI4743

MRP Matrices For C & DItem: C LLC: 1 PeriodLot size: 150 LT: 4 PD 1 2 3 4 5 6 7 8Gross requirements 270Scheduled receiptsProjected on hand 140 140 140 140 140 20 20 20 20Net requirements 130Planned order receipts 150Planned order releases 150

Item: D LLC: 1 PeriodLot size: 250 LT: 2 PD 1 2 3 4 5 6 7 8Gross requirements 585 180Scheduled receiptsProjected on hand 200 200 200 200 115 185 185 185 185Net requirements 385 65Planned order receipts 500 250Planned order releases 500 250

Page 35: Inputs and Outputs to Aggregate Production Planning

3535DSCI4743

Alpha Beta Planned Order Report

Period Item Quantity

1 C 150

2 D 250

3 D 250

4 B 195

5 A 90