HEALTH, SAFETY & ENVIRONMENTAL

INDUCTION(738-C02)

Page 3: Induction Presentation C02
Page 4: Induction Presentation C02

Client : ROYAL COMMISSION Principle Contractor : KIFAH CONTRACTING COMPANYSite Reference : 738-C02Location : JUBAIL INDUSTRIAL CITYProject Manager : Mr. AMR Mahmoud NaguibEH&S Manager : Mr. Shamim Ahmad Siddique

SITE INFORMATION

Page 5: Induction Presentation C02

Organization objectiveThe main objective of our department is to have ZERO accident at site. Create Safe working Environment. Implement safety culture. To complete the project with ZERO accident.

Page 6: Induction Presentation C02

Policy

Page 7: Induction Presentation C02

About Us……

HSE Manager Shamim Ahmad Siddique

HSE Engineer Faiz Ahmed

Safety OfficerMd Irshad Ali

Shaikh Aashiq Ali

Shaik Mohammad

Masood ShaikPrajith K. R.Manu M. P.

Page 8: Induction Presentation C02

Tank Area Telecommunication Building

PROJECT?

Page 9: Induction Presentation C02

WHY ACCIDENT ? Safety Procedure not followed. Proper PPEs missing. Shortcuts at work. SLIP & Trip due to obstruction & wet surface.

Incompetency.

Page 10: Induction Presentation C02

Basic Reason……..

Page 11: Induction Presentation C02

Color CodeJANUARY - MARCHv

APRIL - JUNE

JULY - SEPTEMBER

OCTOBER - DECEMBER

Page 12: Induction Presentation C02

Signage

Warning Sign giving warning of a hazard or danger.

Prohibited A sign prohibiting behavior likely to increase or cause danger.

Mandatory A sign prescribing specific behavior to followed.

Emergency Sign giving information on emergency exits, first aid, or rescue facilities

Page 13: Induction Presentation C02

Red-man & Green-man

Persons operating within 02 - 10 meters

Persons operating beyond 10 meters

Dead man - Person operating within 0-2 meters

Page 14: Induction Presentation C02

Personal Protective Equipment (PPEs)

Page 15: Induction Presentation C02

Mandatory PPEs

Page 16: Induction Presentation C02

PPEs Related To Work

Hot Work

Working at Height

Page 17: Induction Presentation C02

Unsafe Act

Page 18: Induction Presentation C02

Unsafe Condition

Page 19: Induction Presentation C02

Electrical SafetyOnly qualified electricians shall perform

the job. Never use defective electrical

equipment's, defective extension cords or shop made equipment's.

All electrical conductors shall be considered energized unless notified.

Use 110 V for all portable electrical tools.

No work on exposed live conductors. Metal ladders shall not be used.

Page 20: Induction Presentation C02

DIFFERENCES IN TOOLS

110 VOLT 220 VOLT

Page 21: Induction Presentation C02

Do Not Use…….

Page 22: Induction Presentation C02

Bad Practice

XX

Page 23: Induction Presentation C02

ScaffoldAll Scaffolding must be inspected by Trained Competent

Scaffolding Inspector before they can be used.

Complete guardrails and other fall protection arrangements shall be made for platforms above 1.8 m.

It must contain Guard-rail, Mid-rail & Toe-board.

Use ladder for access & egress while using scaffold.

Always check for SCAF-TAG before using.

Use Body Harness above 1.8 m.

Page 24: Induction Presentation C02

XAccepted Not Accepted

Page 25: Induction Presentation C02

Safe for UseBody Harness Required Do Not Use

Scaf-Tag

Page 26: Induction Presentation C02

Welfare Facilities

Drinking Water.Rest Area.

Smoking Area.Toilet & Ablution.

Page 27: Induction Presentation C02

Water Station

Cool & Sweet drinking water provided at site.

Page 28: Induction Presentation C02

Rest Area

Page 29: Induction Presentation C02

Toilet & Ablution.

Page 30: Induction Presentation C02

Smoking Area

Page 31: Induction Presentation C02

Recycle Area

Separate Skip for• Wood• Steel• Polythene

Page 32: Induction Presentation C02

Ladder Aluminum and steel ladder

always maintain three points of contact

Don’t carry tools, equipment, or material in your hands while climbing

If more than 3 metres or 10 feet up, wear a safety harness.

Page 33: Induction Presentation C02

Unsafe use of Ladder

Page 34: Induction Presentation C02

Wooden ladder is strictly prohibited at site.

X

Page 35: Induction Presentation C02

EMERGENCY CONTACTCall 0580290327 OR Ext. 9601 (PROJECT MANAGER) 0599748039 OR Ext. 9606 0592760385 (SAFETY DEPARTMENT) 0597391457 OR Ext. 9611 (MALE NURSE/ FIRST AID) 0597391457 (AMBAULANCE DRIVER)

Page 36: Induction Presentation C02

From phone/mobile call. Say, “This is an EMERGENCY”. Describe the incident location. Describe the incident. Report injuries, if any. Give your name and other details. Stay on line until further instructed.

EMERGENCY PROCEDURE

Page 37: Induction Presentation C02

Know the Assembly Areas. In case of emergency, stop your

work and rush to the assembly area.

Be there until advised to move. Participate in Roll Call / Head

count. Look for your co-workers.

ASSEMBLY AREA

Page 38: Induction Presentation C02

DRIVING AT SITE

Speed Limit (Km/Hr) Seat Belt

Page 39: Induction Presentation C02
Page 40: Induction Presentation C02

It is the responsibility of the driver to ensure his vehicle is safe to operate.

Only Valid Saudi Government driving license. The driver is responsible for transporting the

materials properly and ensuring that a load does not exceed the manufacturer’s design load capacity.

Follows the traffic rule at site. Watch for the people moving in pedestrian and

crossing point. Park your vehicle in parking area ONLY. Do not leave vehicle in start condition.

Rules……...

Page 41: Induction Presentation C02

Observe

Page 42: Induction Presentation C02

Identify the Hazards

Tie-Back GateHarness Leg Straps

Improper Tie-Off Location

Proper Tie-Off LocationStanding on Scaffold Tube

Sitting on Railing Not Allowed

Knot in Lanyard

No Tie-Off

Extinguisher Not Secured

Housekeeping

Page 43: Induction Presentation C02