in the matter of sui northern gas pipelines...
TRANSCRIPT
1
Case No. OGRA-6(2)-1(3)/2011-Review
IN THE MATTER OF SUI NORTHERN GAS PIPELINES LIMITED
REVIEW OF ESTIMATED REVENUE REQUIREMENT, FY 2011-12
UNDER
SECTION 8(2) OF OIL AND GAS REGULATORY AUTHORITY ORDINANCE, 2002 AND NATURAL GAS TARIFF RULES, 2002
DECISION
NOVEMBER 24, 2011 Before: Mr. Sabar Hussain, Acting Chairman /Member (Oil) Mir Kamal Marri, Member (Finance) Mr. Mansoor Muzaffar Ali, Member (Gas)
ii
Table of Contents
1. Background................................................................................................................................... 1
2. Petition........................................................................................................................................... 2
3. Proceedings................................................................................................................................... 4
4. Authority’s Jurisdiction, Determination Process and Discussion about Related Points6
5. Operating Fixed Assets............................................................................................................... 7
5.2. Transmission ................................................................................................................................. 7
5.3. Distribution Development .......................................................................................................... 9
5.4. Compression & Normal Assets ................................................................................................ 12
5.5. Pipeline infrastructure for upcoming LNG import................................................................ 12
6. Other Operating Revenues ...................................................................................................... 14
7. Operating Expenditures ........................................................................................................... 14
7.1. Cost of Gas .................................................................................................................................. 14
7.2. Human Resource (HR) Cost ...................................................................................................... 16
7.3. Cost of Reinstated employees................................................................................................... 16
7.4. Stores and Spares Consumed - Odorant Oil .......................................................................... 17
7.5. Operating Cost for Pipeline infrastructure for upcoming LNG import ............................. 18
7.6. Remaining items of Operating Expenditure ........................................................................... 18
7.7. Revenue Shortfall of FY 2010-11............................................................................................... 19
8. Determination ............................................................................................................................ 20
9. Public Critique, Views, Concerns, Suggestions .................................................................. 20
Annexure:
1. Computation of Revised Estimated Revenue Requirement FY 2011-12 ......................... 22
2. Provisional Prescribed Prices for FY 2011-12........................................................................ 23
Appendix:
Written submissions of the interveners
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
1
1. Background
1.1. Sui Northern Gas Pipelines Limited (the petitioner) is a public limited company,
incorporated in Pakistan, and listed on Karachi, Lahore and Islamabad Stock
Exchanges. It is engaged in the business of construction and operation of gas
transmission & distribution pipelines, sale of natural gas and compressed
natural gas, and sale of gas condensate (as a by-product) .
1.2. Petitioner had filed a petition under Section 8(1) of the Oil and Gas Regulatory
Authority Ordinance, 2002 (the Ordinance) for determination of Estimated
Revenue Requirement (ERR) for FY 2011-12 (said year) on November 30, 2010,
which was subsequently amended by it on March 01, 2011. The Authority, vide
its decision dated May 24, 2011 determined a shortfall of Rs. 4,583 million (the
amounts have been rounded off to the nearest million here and elsewhere in this
document) translating into an increase of Rs. 7.54 per MMBTU in the average
prescribed price w.e.f July 01, 2011. Subsequently, Authority revised this
revenue requirement per Ministry of Petroleum and Natural Resources
(MP&NR) advice, and adjusted shortfall arisen due to interim relief granted by
Lahore High Court (LHC) pertaining to FY 2010-11. Accordingly, average
prescribed price was increased to the tune of Rs. 11.02 per MMBTU effective
July 01, 2011.
1.3. Being aggrieved by the determination, petitioner challenged issues of UFG, non
operating income, gain on construction contracts, HR benchmark and provision
for doubtful debts in LHC. The Honorable Court granted interim relief to the
petitioner and directed OGRA to determine the revenue requirement of the
petitioner for the said year in accordance with the LHC Order dated January 11,
2011 against OGRA petition No. 1068-2010. The Authority, based on said
decision, revised the revenue requirement at Rs. 227,699 million translating into
an increase of Rs. 23.90 per MMBTU w. e. f July 01, 2011.
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
2
2. Petition
2.1. Petitioner has submitted this review petition on October 14, 2011, under Section
8(2) of the Ordinance, which was subsequently amended by it on October 16,
2011 and October 31, 2011, projecting a shortfall of Rs. 31,548 million in
determined ERR, translating into an increase of Rs. 112.41 per MMBTU, w.e.f.
January 01, 2012 (Rs. 56.45 per MMBTU on annualized basis for said year).
Petitioner further amended the petition vide its letter dated November 24, 2011
(the petition), requesting to allow increase in average prescribed price at Rs.
59.69 per MMBTU w.e.f. 1st July, 2011, based on inclusion of additional pipeline
infrastructure for up coming LNG project envisaged to be completed in said
year.
2.2. Earlier, petitioner had submitted a review motion on June 22, 2011 under Rule
16 of the Natural Gas Tariff Rules, 2002 (NGT Rules) against determination of
ERR for the said year. Later on, petitioner filed an amendment dated August 20,
2011 in motion for review, taking into account additional impact of HR bench
mark proposed by it, adjustment of prior year revenue shortfall on the basis of
initialed accounts and revenue loss owing to prescribed prices applicable from
August 07, 2011 instead of July 01, 2011. Authority observes that the said
petition is under its consideration, and decision in the matter has not yet been
announced. The Authority observes that petitioner has included all its claims
per the said motion for review in the instant petition as well, along with request
to treat review motion as part of the instant petition. Authority, in view of the
request of petitioner, decides to treat said review motion as part of the instant
petition.
2.3. Petitioner has projected an increase of Rs. 59.69 per MMBTU w.e.f July 01, 2011
based on following claims for said year:
i. Projected Weighted Average Cost of Gas (WACOG) at Rs. 308.95 per
MMBTU taking into account the latest actual/estimated oil prices in the
international market, devaluation of rupee against US $, revised projection
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
3
of gas purchase volume based on actual gas availability for the months of
July and August, 2011 and latest indications.
ii. Capitalization of operating fixed assets- transmission lines (Kunnar /
Pashaki & Capacity enhancement for LNG import), distribution
development, compression & normal assets.
iii. UFG target at 7%.
iv. Revised HR benchmark cost.
v. Cost of reinstated employees
vi. Stores and spares consumed
vii. Repair & maintenance
viii. Fuel and power
ix. Rent, rates, electricity and telephone
x. Transport
xi. Legal and professional charges
xii. Gathering charges of collection data
xiii. Advertisement
xiv. Security expenses
xv. Provision for doubtful debts
xvi. Five years’ special training program
xvii. Other expenses
xviii. Prior year adjustment Final Revenue Requirement (FRR) FY 2010-11
xix. Negative GDS – FRR FY 2010-11
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
4
Table 1: Component-wise Breakup of Requested Increase in Average Prescribed Price
Rs./MMBTUA Decrease in revenue due to Sales Mix at revised volume (23.87)
Adjustment in operating revenues due to Volume variance. (0.15)Total Decrease in Revenues (24.03)
Decrease in Cost of gas sold due to increase in WACOG. 20.18 Decrease in UFG Disallowance (10.08) Net impact of Increase in T&D cost, depreciation and decrease in GIC 15.37 Prior year adjustment pertain to FY 2010-11 4.35 Increase in Rate of Return 5.85
B Total Increase in Expenditures 35.67 C=A-B Total Increase in Revenue Requirement 59.69
Net Increase effective January 01, 2012 118.86 2.4. Authority admitted the petition for consideration, as a prima facie case for
evaluation existed and it was otherwise in order.
3. Proceedings 3.1. A notice inviting interventions / comments from consumers, general public and
other interested / affected persons, and intimating time and place of the public
hearing, was published in daily newspapers, namely: Dawn (combined),
Nawa-e-Waqt (combined), Mashriq (Peshawar) and Express (Lahore). The
Authority received applications to intervene in the proceedings from the
following persons / entities:
(i) All Pakistan Textile Processing Mills Association (APTPMA),
(ii) Mr. Mahmood Elahi Engineer, Sui Gas Contractor, Faisalabad,
(iii) Mr. Jahanzaib Ahmed Siddiqui, Islamabad,
3.2. Written submissions were also received from some of the interveners, which are
appended to this order.
3.3. Authority admitted all the above intervention requests.
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
5
3.4. A public hearing was held on November 17, 2011, at Lahore, which was
participated by the following:
Participants
i. Mr. Mahmood Elahi Engineer, Sui Gas Contractor, Faisalabad
ii. Mr. Mohsin Aftab, Regional Secretary, APTMA Lahore / Gujranwala
iii. Mr. Tauqeer Ahmed Taqi, Director, Zaheer Soap Factory, Faisalabad
iv. Mr. Masood Ali Shah, Manager Punjab Gases, Lahore
v. Mr. Abdullah Fahim, Lahore
vi. Mr. Naeem Rahat, Lahore
vii. Mr. Aftab, Gas Consumer, Sheikhupura
viii. Mr. Khalid Mehmood, Gas Consumer, Sheikhupura
Petitioner:
ix. Petitioner’s team lead by Mr. Arif Hameed, Managing Director
3.5. Petitioner was given full opportunity to present its petition. Petitioner made
submissions in detail with help of multi-media presentation.
3.6. Participants were of the view that there are 8 regions of petitioner therefore gas
holiday for CNG stations should be made for 1 day for each region during the
week, instead of 3 days on a consecutive basis.
3.7. It was urged that regular participants in public hearing should be informed in
respect of public hearings scheduled, through separate letters in addition to
press advertisements.
3.8. Participants stressed that UFG / gas theft must be controlled at all costs and
effective legislation must be put in place at the earliest. It was further added that
projected increase in gas prices will further add to miseries of people of
Pakistan, wherein a major chunk is already living below poverty line.
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
6
4. Authority’s Jurisdiction, Determination Process and Discussion about Related Points 4.1. Authority examines, in depth, all applications and petitions in light of relevant
legal provisions. Petitions / applications are admitted for consideration, only if
they meet pre-admission criteria laid in the NGT Rules. In the process, public
notices are issued and all stakeholders are provided full opportunity to
intervene / comment upon issues pertaining to determination of revenue
requirement, in writing and at public hearings. Authority gives full
consideration to observations and comments of all stakeholders while
determining revenue requirement and prescribed prices. As regards policy
matters, since Federal Government (FG) is legally competent authority, policy-
related pleas, reservations and sentiments of stakeholders are brought to its
specific attention for consideration before deciding retail prices for various
categories of consumers.
4.2. Authority, under Licence Conditions of the licence granted to petitioner,
determines total revenue requirement of licencee to ensure that it operates
prudently and achieves 17.5% return on its average net fixed assets in operation
for each financial year, subject to efficiency related benchmarks, imposed from
time to time. Authority, may, however, in consultation with GoP and licencee
prescribe revised rate of return or a different basis for determination of a return,
pursuant to Licence Condition No. 5.3 of the licence granted to petitioner.
Authority has developed a new tariff regime for regulated natural gas sector of
Pakistan, which, in the course of legally mandatory consultation process, is with
GoP since October, 2005.
4.3. Petitioner has mainly sought review of cost of gas/WACOG, based on actual
changes in well-head gas prices and relevant factors, in petition submitted
under section 8(2) of the Ordinance. Petitioner has also incorporated all its
claims per review motion against DERR for said year, as explained in para 2.2
above, in the instant petition. It has been observed that said review motion is
under consideration of Authority since decision in the matter has not yet been
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
7
issued. Authority has, therefore, decided to treat the review motion filed under
rule 16 of the NGT Rules as part of petition filed under section 8(2) of the
Ordinance.
4.4. Well-head gas prices for the said year are based on actual prices of crude oil and
HSFO during the period December, 2010 to September, 2011 and include
estimates for October and November, 2011. Latest trend in recent months is to
be taken into account, while determining WACOG to ensure that determination
is rational and fair to all stakeholders.
4.5. Operating revenues, operating expenses and changes in asset base are
scrutinized by Authority in depth. Appropriate benchmarks are set in critical
areas of operation to ensure that cost of petitioner’s inefficiencies and
imprudence are not passed on to consumers. Independent audits are also
conducted, wherever deemed necessary by Authority. Operating expenses of
licencee would have been much higher than what they are and so would have
been gas prices had there been no such control.
5. Operating Fixed Assets
5.1. Petitioner has requested to allow projected capital expenditure of Rs. 34,809
million as against Rs. 5,127 million provided in DERR for said year in respect of
following items:-
5.2. Transmission
5.2.1. Petitioner has submitted that capitalization of Rs. 1,863 million has been
projected on account of 42’’ dia, 21.92 Km loop line between valve assemblies
SV 4 (Rehmat injection point) to valve assemblies SV 5 (24” Sawan– Qadirpur
line). This pipeline has been pended in DERR for said year owing to litigation
cases lodged by landowners in respect of Kunnar / Pashaki and delay in
import of gas from Iran and RLNG. Petitioner has accentuated that said
project is enormously important since it is aimed to facilitate swap
arrangement for receiving additional gas in order to curb extensive gas load
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
8
shedding.
5.2.2. Petitioner has elaborated that its board of directors accorded approval to
undertake the project in year, 2009. ECC also approved gas allocation based
on swap arrangement from different injection points. The project activities in
past years however remained suspended for want of confirmation of
additional gas from gas producers and advancement in cross border gas
import projects. Now, in recent past, OGDCL has informed that it is likely to
put 100 MMCFD off-spec gas in the system followed by another gas pack of
100-150 MMCFD within nine months of first supply. This whole supply from
Kunnar / Pashaki will be injected in SNGPL network since SSGCL has
expressed its reluctance to receive off-spec gas in its system.
5.2.3. Petitioner has further elaborated that fast track efforts have been undertaken
by FG to bring RLNG and gas from Iran. FG has formulated multi-pronged
strategy along with serious initiatives to inject additional gas in national grid
from indigenous sources as well as import projects including third party
access, to the network by participation of private investors.
5.2.4. Petitioner further argued that requisite project is critical part of advance
action plan of Project–X and part & parcel for receiving additional gas
through above proposed arrangements. The project, after approval, will also
take about two years for its completion. In this scenario, if this project is
deferred further, petitioner will not be able to ensure pipeline capacity to
receive additional gas. Petitioner, owing to said compelling circumstances
has requested to allow capitalization under transmission amounting to Rs.
1,863 million for said year.
5.2.5. The Authority observes that combined strategy and concerted efforts are
being undertaken by all concerned quarters including petitioner to explore
new avenues and enhance gas supplies in order to abridge demand supply
gap, which is soaring to adverse level. FG has also made significant progress
in gearing up IPI project, induced gas producers to enhance gas supply from
indigenous sources and invited number of private investors to come at resort
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
9
on RLNG import projects. FG has also finalized necessary policy framework
to attract capital investment in import projects and advised gas utilities to
ensure capacity for third party access to receive additional gas.
5.2.6. Authority also observes that consumers are facing severe gas shortage owing
to extensive load shedding by petitioner, thereby giving rise to violence in
the country. In this exigency, petitioner has no alternate except to test all out
means to increase gas supply to its existing consumers.
5.2.7. The Authority, in view of above, provisionally allows expenditure of Rs.
1,863 million on account of capitalization under head of Transmission for
said year.
5.3. Distribution Development (Govt. schemes, system augmentation, extension of network in existing towns & villages, cost recovery schemes, rehabilitation of systems, replacement of defective meters, modification of TBS’s, construction of SMSs, spares of regulators & meters)
5.3.1. Petitioner submitted that Authority has allowed Rs. 3,918 million for
distribution development during said year as against its request of Rs. 15,589
million to execute a physical target of 5,000 Km extension in network.
5.3.2. Petitioner argued that it has intended to lay 800 Km distribution lines at a
cost of Rs. 1,800 million with more emphasis on rehabilitation, removal of
anomalies, augmentation and UFG related activities, while a separate
requirement of 3,800 Km costing Rs. 7,948 million for completion of ongoing
projects for new towns and villages, per the directives of FG, has also been
submitted. A substantial investment has been made on such projects which
are in progress and if they are abandoned, material already laid will be
wasted due to corrosion. Resultantly, no benefit will be attained from assets
in future. Further, cost recovery jobs of 340 Km amounting to Rs. 600 million
have also been planned.
5.3.3. Petitioner has elaborated that it is prudent to restrict distribution
development budget in accordance with current supply of gas position.
However, restricting critical expenses including rehabilitation of system,
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
10
replacement of undersized meters, regulating systems, GI pipes and fittings,
etc, will actually have negative impact on UFG control efforts. Petitioner in
view of above has requested to allow capitalization of Rs. 15,589 million for
said year.
5.3.4. Petitioner has further argued that main chunk of distribution development
encompasses on-going projects which were undertaken to comply with GoP
socio-political agenda. Authority, in its earlier determination, linked
capitalization under head distribution development with gas availability and
excluded the same from rate base owing to squeezing/debilitating gas
supply. Recently, the FG has formulated a policy for such development
projects and implemented the following moratorium, dated October 4, 2011
on development schemes:
i. Only ongoing development schemes will be executed.
ii. The schemes where work has yet to commence (funding received)
will be initiated after completion of ongoing schemes.
iii. No new gas development scheme will be allowed till implementation
of previous directives / commitments as indicated at para (i) and (ii)
above.
iv. Gas producing districts shall be exempted from Moratorium as
indicated at para (iii) above. Preference will be given to villages /
towns located in the vicinity of gas fields.
5.3.5. Petitioner, in view of above moratorium, submitted that proposed extension
in T& D network and capital cost for attached activities corresponding to new
towns & villages qualifies for capitalization and inclusion in rate base on
account of distribution development for said year.
5.3.6. Petitioner has submitted detailed information pertaining to on-going projects.
The Authority observes that progress on these projects during the current
year denotes that these capital projects and few GoP funded schemes are
likely to be completed during said year. Therefore, Authority, in view of
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
11
above, allows projected capitalization of 4,600 Km in T & D network for
said year.
5.3.7. Authority however observes that petitioner has overestimated standard cost
for laying of each Km of distribution development. In the instant petition, it
has projected cost at Rs. 2.06 million per Km whereas in most recent
completed financial year, actual cost has been observed at Rs. 1.02 million per
Km. Authority, in view of above, adopts Rs. 1.28 million/Km (i.e; at the level
of FRR FY 2010-11 plus 25% to cater for inflation and enhanced activities) as
standard cost and provisionally allows Rs. 5,865 million for distribution
mains. The same will, however, be revisited at the time of FRR for said year,
based on prudently incurred actual costs of projects.
5.3.8. Estimated cost for allied activities in terms of construction of TBSs & DRSs,
replacement of undersized meters, construction of SMS for on-going projects
etc; have also been unreasonably projected on higher side. Keeping in view
the historical trend, which corresponds to petitioner’s capacity to undertake
the capitalization of such activities, the Authority determines projected cost
for other distribution development activities at Rs. 4,936 million for said year.
5.3.9. Accordingly, the Authority, allows Rs. 10,801 Million under distribution
development for said year.
Million Rs.
Sr.# Description Claimed by the
petitionerAllowed by the
Authority1 Distribution System Mains 9,747 5,865
2 Laying of distribution mains on cost sharing basis 600 600
3 Installation of new connections 2,207 2,206
4 Construction of TBS/DRS 582 214 5 Construction of SMS 400 276
Sub- total 13,536 9,161 6 Replacement of defective meters 1,183 994 7 Rehabilitation of distribution system 600 487 8 C.P. System 220 117 9 Spares of meters & Regulators 50 42
Sub- total 2,053 1,639 Total 15,589 10,801
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
12
5.4. Compression & Normal Assets (Plant & machinery, measuring and regulating assets, motor vehicles, construction equipments, office equipments)
5.4.1. Petitioner has elaborated that Rs. 183 million on account of compression,
disallowed in DERR for said year, is part of complete package for import of
material, therefore it should be allowed. Authority allows the same keeping
in view integrated cost of project.
5.4.2. Petitioner has requested for admissibility of Rs. 336 million on account of
normal assets, disallowed in DERR for said year.
5.4.3. Authority observes that petitioner has neither provided any new admissible
evidence or justification which could not have reasonably been discovered at
the time of original decision nor has it been able to prove any change in
circumstances to consider its request. Authority therefore maintains its
earlier decision and rejects petitioner’s request on this account for said year.
5.4.4. Authority also observers that petitioner has included a net amount of Rs. 232
million as addition in fixed assets on account of new offices /regions for said
year. Petitioner however has not sought prior approval or provided detailed
information about the project. Therefore, claimed capitalization on this
account is disallowed.
5.5. Pipeline infrastructure for upcoming LNG import
5.5.1. Petitioner has requested to allow Rs. 15,379 million for laying of pipeline
infrastructure for up coming LNG project envisaged to be completed in said
year. Petitioner has elaborated that GoP is aggressively pursuing import of
LNG to make up shortfall in gas supplies. In this respect a meeting was held
on October 27, 2010 under chairmanship of Secretary, MP&NR, in which
decision was taken to allocate capacity to all three LNG terminal licensees
enabling them to transport their RLNG to customers, on payment of
transportation tariff plus capacity charge to respective gas utility company.
Formal letters of capacity allocation has been issued by OGRA to all three
LNG licensees. Allocation of capacity is subject to a number of conditions out
which following are directly related to gas utility companies for provision of
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
13
pipeline system capacity for LNG terminal licensees:
(i) Entry and exit points should be indicated to gas utility companies within 90 days.
(ii) Performance guarantee of US $ 10 million per project to be furnished within 90 days of capacity allocation.
(iii) The utility companies, SNGPL and SSGCL, will start investing in capacity enhancement after receipt of performance guarantee.
5.5.2. Petitioner has urged that above conditions related to capacity allocation calls
for immediate action from both petitioner and SSGCL to make available
pipeline system capacity to LNG developers in line with their terminals.
5.5.3. Authority observes that gas supply in national network is dwindling thereby
creating a massive shortfall faced by each category of consumers. FG, in
order to prevent economic distortion, is vigorously making concerted efforts
to increase gas supply in the system and has developed multi-pronged
strategy in this regard. On one hand, it has inked long term capital intensive
pipeline project with Iran and Turkmenistan to import 500 MMCFD gas and
on the other, it has induced number of potential investors to develop
terminal and import RLNG on fast track basis. OGRA, for this purpose, has
also issued licenses to interested stakeholders and assisted FG in
establishment of necessary regulations in this regard.
5.5.4. Authority also observes that RLNG import option is practicable only if
availability of additional pipeline capacity is ensured by gas utilities to RLNG
transporter. Gas utilities, however, in the present circumstances, reported
their inability to allocate additional capacity owing to their own operational
requirement.
5.5.5. Authority observes that petitioner would undertake massive capital
investment to transport LNG through its network, and therefore emphasize
that petitioner should only incur expenditure on this account subject to the
following:-
a) compliance of Article 4 of Schedule IV of the OGRA Natural Gas
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
14
Regulated Third Party Access Rules, 2011, as reproduced below:
“Transporter will start investing in capacity enhancement after receipt of requisite performance bank guarantee of US $ 10 million from the shipper”
b) decision taken in the meeting held on October 27, 2011, under the
Chairmanship of Secretary MP&NR, as stated under :-
“The utility companies SNGPL and SSGCL, will start investing in capacity enhancement after receipt of performance bank guarantee from a reputable bank acceptable to OGRA and en-cashable in Pakistan.”
5.5.6. Authority, in view of above, observes that availability of infrastructure, in
timely manner, is an essential prerequisite of RLNG import arrangements.
Authority, therefore, approves the said project in principle and decides that
actual expenditure on this account will be added in rate base at the time of
FRR, subject to successful commissioning of said pipeline as well as
requisite compliance of relevant rules and applicable decisions.
5.6. In view of above, depreciation expense claimed by petitioner comes down to Rs.
8,761 million as against Rs. 9,395 million. Decrease in depreciation is
consequence of adjustment on account of claimed addition in assets for said
year, as discussed above. Accordingly, net closing fixed assets for said year
works out to Rs. 82,200 million for said year.
6. Other Operating Revenues
6.1. Petitioner has projected “Rental and Services Charges” at Rs. 1,100 million and
“Other Operating Income” at Rs. 300 million, as against Rs. 1,331 million and Rs.
450 million per DERR respectively for said year. Petitioner has not cited any
reason for revised estimates, the Authority, therefore, determines the same at
level of DERR for said year.
7. Operating Expenditures
7.1. Cost of Gas 7.1.1. Petitioner has projected WACOG to increase to Rs. 308.95 per MMBTU on an
annualized basis as against Rs. 300.31 per MMBTU, projected at time of
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
15
determination of ERR for said year, based on following parameters:
(i) Well-head gas prices of various producing fields for period July 1, 2011
to December 31, 2011, as already notified by Authority.
(ii) US $ exchange rate for payment of monthly invoices of gas producers
has been assumed at Rs. 88.29 for period July-December, 2011.
(iii) Prices of crude oil / HSFO during the period June, 2011 to November,
2011 to form basis for computing well-head prices for the period
January 1, 2012 to June 30, 2012 in accordance with provisions of
existing GPAs between producers and GoP.
(iv) Actual international FOB prices of crude oil and HSFO for the period
June, 2011 to September, 2011. For October and November, 2011, crude
oil prices have been assumed at US $ 107.76 and US $ 108.30 per barrel
respectively and HSFO prices have been assumed at US $ 647.43 and US
$ 650.66 per ton respectively.
(v) US $ exchange rate assumed at Rs. 90 for calculation of well-head gas
prices as well as for monthly invoicing to gas producers for the period
January–June, 2012.
7.1.2. On the basis of above parameters, petitioner has estimated average C & F
prices of crude oil and HSFO for June-November, 2011 at US $ 109.55 per
barrel and US $ 654.06 per ton respectively, and has used them for
computation of well-head prices for January-June 2012.
7.1.3. Authority observes that well-head prices of gas for all fields in Pakistan are
computed in accordance with GPAs and/or provisional pricing parameters,
available on record, and are notified in exercise of powers vested in it under
the Ordinance.
7.1.4. Authority finds that, on the basis of currently available information, revised
projections of sale and purchase volume, and computation of cost of gas
submitted by petitioner are reasonable.
7.1.5. Authority, therefore, provisionally determines WACOG at Rs. 308.95 per
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
16
MMBTU and cost of gas of petitioner at Rs. 194,870 million for said year.
7.2. Human Resource (HR) Cost
7.2.1. Petitioner has referred its proposal for review of HR benchmark submitted in
August, 2011 and accordingly requested to revise HR benchmark cost for
said year.
7.2.2. Authority observes that proposals from gas utilities for revision in HR
benchmark have been received, but only after considerable delay and
repeated reminders. Same are under examination in terms of its rationality
and relevance. Also, some detailed information / data in this regard has been
sought from utilities, which is pending till date. The consultative session with
stakeholders in this regard will be initiated soon. Petitioner should not
assume its proposal as being approved by Authority until it is finalized.
Hence, inclusion of additional impact based on proposed HR benchmark at
this point in time is out of question. Authority, therefore, defers any possible
adjustment on this account in the instant decision. Authority, however,
decides to allow HR cost at Rs. 6,693 million for said year on provisional
basis ( i.e. HR cost per FRR FY 2010-11 Rs. 6,220 million plus provision for
IAS 19 for said year amounting to Rs. 473 million).
7.3. Cost of Reinstated employees
7.3.1. Petitioner has argued that requisite performance / progress report of
reinstated employees for each quarter has been submitted by it, therefore an
amount of Rs. 555 million may be allowed on this account.
7.3.2. Petitioner has further pleaded that reinstated employees, despite possessing
higher education lacks technical knowledge and relevant background to
produce intended results as per OGRA timelines. Petitioner therefore has
made concerted efforts by putting them through various formal training
sessions as well on job trainings. Resultantly, some improvements in various
fields have been witnessed, tangible results however will take time, for which
petitioner is endeavoring to utilize their services to the best of their abilities.
7.3.3. Authority admits the fact that above said employees were reinstated
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
17
pursuant to compliance with FG directives and Sacked Employees
Ordinance, 2009. Authority however notes that these employees, before their
termination, were appointed against suitable positions by the company’s
management itself, surely after due diligence and scrutiny. Authority is of
concerted opinion that desired results can possibly be achieved from
reinstated employees, provided the management eagerly undertakes
appropriate measures for re-training of these employees
7.3.4. Authority also observes that efficiency of petitioner towards some critical
areas particularly UFG is going adverse. Petitioner, in order to pave
efficiency gap, requires motivated workforce to combat all such issues. On
this plea, Authority had adopted rather generous approach in allowing cost
on account of HR for last year.
7.3.5. Authority in view of above, allows 50% expenditure on account of sacked
employees amounting to Rs. 278 million on provisional basis at this time,
subject to improvement consequent to effective utilization of these
employees. The same will, however, be comprehensively reviewed at the time
of FRR and petitioner must be able to demonstrate enhanced utilization of
reinstated employees at that time, in terms of concrete measurable outputs.
7.4. Stores and Spares Consumed - Odorant Oil
7.4.1. Petitioner has argued that odorant oil is a chemical compound which creates
smell and is injected in system in accordance with international standards.
Rate specified in metering manual is 0.5 lbs or 0.22727 kg / MMCF of gas.
Petitioner has pleaded that for projected gas input of 516,475 MMCF, 117,379
KG odorant oil would be required. Petitioner has requested that based on
rate allowed by OGRA odorant oil expense be allowed at Rs. 76 million,
which was earlier claimed in DERR at Rs. 33 million, with the assumption
that actual cost will be allowed for budgeted quantity.
7.4.2. Authority observes that expenditure on account of odorant oil has been
exhaustively discussed and elaborated in DERR for said year. Petitioner’s
own position on this issue is in doldrums and the historical position
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
18
elaborates that initial claims of petitioner, on this account especially, had
been on higher side.
7.4.3. In view of above, Authority maintains its earlier decision for said year,
subject to review based on prudently incurred actual expenditure at the time
of FRR for said year, owing to essential nature of the expenditure in relation
to UFG control.
7.5. Operating Cost for Pipeline infrastructure for upcoming LNG import
7.5.1. Petitioner has claimed Rs. 36 million as operating cost in respect of laying of
pipeline infrastructure for upcoming LNG import.
7.5.2. Authority in view of the discussion per para 5.5 above pends Rs. 36 million
for said year on this account.
7.6. Remaining items of Operating Expenditure (Repair & maintenance, fuel and power, rent, rates, electricity and telephone, transport, legal and professional charges, gathering charges of collection data, advertisement, security expenses, provision for doubtful debts, five years’ special training programme, other expenses)
7.6.1. Authority notes that all other issues contended by petitioner have been
exhaustively discussed & decided by Authority, after duly considering the
petitioner’s submissions presented at the time of DERR FY 2011-12. Authority
gave conscious thought on petitioner’s submission/ claims and has adopted
rather generous approach to allow unavoidable and improvement/efficiency
related expenditures.
7.6.2. Authority observes that it had made exhaustive discussions while deciding
upon any revenue or expenditure item and arguments advanced now have
already been considered and addressed by Authority. Therefore, admission
of petition based on previously discussed issues defies logic.
7.6.3. Authority notes that review on each disallowed item of expenditure has been
claimed as a matter of practice only, and therefore review petition is rather
flimsy and lack any attempt to provide plausible reasons for review. Further,
item by item analysis of operating cost reveals that petitioner exaggerated its
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
19
projections for said year when compared with actual results for FY 2010-11.
Therefore, petitioner’s entire submission is not based on careful estimates
and appears to be a futile exercise to retreat historical facts.
7.6.4. Authority further observes that petitioner has neither provided any new
admissible evidence or justification which could not have reasonably been
discovered at the time of original decision nor has been able to prove any
change in circumstances to consider its request. Further, it has also been
noted that petitioner has adopted a non-professional approach of grossly
exaggerating estimates. This practice is totally sluggish and needs to be
abandoned.
7.6.5. Authority, in DERR for said year, had provisionally restricted provision for
doubtful debts at Rs. 180 million for said year. Authority feels that
appropriate and reasonable benchmark on this critical expenditure is
required not only to protect consumers from this avoidable cost of
petitioner’s inefficient practices but also to introduce systematic
improvements in petitioner’s operations. Authority will, therefore, set
requisite benchmark in due course based on information provided by
petitioner and after having consultation session with it.
7.6.6. In view of above, Authority maintains its earlier decision taken in DERR for
said year in respect of all other items.
7.6.7. Petitioner has claimed Rs. 242 million on account of additional operating cost
for 3 new regions and 1 sub region. Authority in view of the discussion per
para 5.4.4 above disallows Rs. 242 million for the said year.
7.7. Revenue Shortfall of FY 2010-11
7.7.1. Petitioner has included Rs. 3,078 million, being revenue shortfall pertaining
to FY 2010-11 arisen due to decision of honorable Courts in the matter of
revenue requirements for FY 2010-11. The Authority, at time of FRR for FY
2010-11, had decided to adjust this amount in RERR for said year, since no
cushion was available to adjust the shortfall in FY 2010-11.
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
20
7.7.2. In view of above, the Authority includes Rs. 3,078 million in tariff
calculation for said year.
8. Determination 8.1. Authority, after taking into consideration points raised by interveners,
clarifications provided by petitioner, scrutiny of petition and available record,
provisionally determines the shortfall in estimated revenue requirement for said
year at Rs. 24,984 million (Annexure-I).
8.2. In order to dilute the effect of increase in prices, Authority decides to adjust
shortfall in revenue requirement to the extent of available difference, of Rs.
12,655 million, between consumer and prescribed prices already notified for this
period. Authority decides to adjust the remaining shortfall of Rs. 12,329 million,
in revenue requirement by increasing the average prescribed price by Rs. 43.93
per MMBTU w.e.f January 01, 2012, translating into an increase of 14.05% for
all categories of consumers (Annexure-II) except Liberty Power and fertilizer
feedstock, which are governed by separate policy of the Federal Government.
8.3. Revised provisional prescribed prices w.e.f January 01, 2012 are subject to the
condition that these “may be re-adjusted upon receipt of GoP advice under Section 8
(3) of the Ordinance in respect of the sale price of gas for each category of retail
consumers provided that the overall increase in the average prescribed price remains
unchanged so that the petitioner is able to achieve its total revenue requirements in
accordance with Section 8 (6) (f) of the Ordinance.”
8.4. Under Section 8 (3) of the Ordinance, GoP is required to advise Authority,
within 40 days of advice from the Authority of revision of prescribed prices, the
minimum charges and sale price for each category of retail consumers, for
notification in the Official Gazette by Authority.
9. Public Critique, Views, Concerns, Suggestions 9.1. Authority has recorded concerns of interveners and participants in para 3 above,
which include matters relating to policy and do not fall under the purview of
Authority but affect the consumers. Specific attention of GoP is drawn to these
issues for consideration and necessary action.
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
21
9.2. Authority observes that petitioner is in violation of License Condition No. 34,
wherein it is obligated to ensure continuous and reliable supply of natural gas to
its existing consumers. Petitioner should therefore endeavor to ensure early
compliance of the said condition.
(Mansoor Muzaffar Ali) Member (Gas)
(Mir Kamal Marri)
Member (Finance)
(Sabar Hussain) Acting Chairman /
Member (Oil)
Islamabad,
November 24, 2011
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
22
1. Computation of Revised Estimated Revenue Requirement FY 2011-12 Rs. in million
The Petition Adjustment Allowed BY OGRA
Gas sales volume -MMCF 594,947 - 594,947
BBTU 558,817 - 558,817 July-11 To Dec-11 278,165 - 278,165 January -12 To June-12 280,652 - 280,652
939.2719 - 939.2719 "A" Net Operating revenues
Net sales at current prescribed price 192,741 - 192,741 Rental & service charges 1,100 231 1,331 Amortization of deferred credit 1,904 - 1,904
300 150 450 196,045 196,426
"B" Less ExpensesCost of gas sold 194,870 - 194,870 UFG (disallowance) / allowance (8,197) - (8,197) Transmission and distribution cost 15,349 (5,599) 9,750 Gas Internally Consumed 2,555 - 2,555 Depreciation 9,395 (634) 8,761 Workers Profit Participation Fund 452 - 452
3,078 - 3,078
Total expenses "B" 217,502 (6,233) 211,269
"C" (21,457) (14,843) Return required on net assets:
76,905 - 76,905 102,319 (20,119) 82,200 179,224 159,105
Average fixed net assets (I) 89,612 (10,059) 79,553 20,560 - 20,560 22,656 - 22,656 43,216 - 43,216
Average net deferred credit (II) 21,608 - 21,608
"D" Average operating assets (I-II) 68,004 (10,059) 57,945 Return required on net assets 17.5% 17.5%
"E" Amount of return required 11,901 (1,760) 10,140 "F"
(33,358) 8,374 (24,984) "G"
59.69 (14.99) 44.71 "H"
118.86 (29.84) 89.02 "I" 229,403 (7,993) 221,410 "j"
404.60 (15) 389.62 "K"
- 45.09 "L"
- 43.93
Other operating income
Particulars
Calorific Value
Average Increase/(Decrease) in Prescribed Price (Rs/MMBTU) w.e.f. 01.01.2012
Shortfall adjusted from available difference amounting to Rs. 12,655 million between consumer price & prescribed price (Rs/MMBTU)
Net assets at endingNet assets at begining
Revenue requirement
Average Prescribed Price (Rs/MMBTU)
Excess /(Shortfall) over return required
Remaining shortfall of Rs. 12,329 million adjusted by increasing prescribed prices wef 1.1.2012 (Rs/MMBTU)
Total income "A"
Prior Year Adjustment from FRR 2010-11
Average Increase/(Decrease) in Prescribed Price (Rs/MMBTU) w.e.f. 01.07.2011
Operating profit / (loss)(A - B)
Deferred credit at endingDeferred credit at begining
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
23
2. Provisional Prescribed Prices for FY 2011-12
(i) Domestic Consumers:
a) Standalone meters
First slab (upto 100 cubic metres per month). 95.00 107.87 123.02 Second slab (over 100 upto 300 cubic metres per month). 190.00 215.74 246.04 Third slab (over 300 upto 500 cubic metres per month). 800.00 908.39 1,035.98 Seventh Slab(over 500 cubic meters oper month) 1,006.40 1,142.75 1,303.26
b)
(i) Upto 300 M3 per monthFirst slab (upto 100 cubic metres per month). 95.00 107.87 123.02 Second slab (over 100 upto 300 cubic metres per month). 190.00 215.74 246.04
(ii) Over 300 M3 per month383.42 435.37 496.52
All off-takes at flat rate of
(ii) Commercial Consumers:
All off-takes at flat rate of 463.76 526.59 600.55
Special Commercial Consumers (Roti Tandoors)
a) Upto 300 M3 per monthFirst slab (upto 100 cubic metres per month). 95.00 107.87 123.02 Second slab (over 100 upto 300 cubic metres per month). 190.00 215.74 246.04
b) Over 300 M3 per month
All off-takes at flat rate of 463.76 526.59 600.55
(iii) Ice Factories:All off-takes at flat rate of 463.76 526.59 600.55
(iv) Industrial Consumers:
All off-takes at flat rate of 382.37 434.18 495.16
(v) Captive Power :All off-takes at flat rate of 382.37 434.18 495.16
Mosques, churches, temples, madrassas, other Religious Places and Hostels attached thereto; Government and Semi-Government Offices and Hospitals, Government Guest Houses, Armed Forces Messes, Langars, Universities, Colleges, Schools and Private Educational Institutions, Orphanages and other Charitable Institutions along-with Hostels and Residential Colonies to whom gas is supplied through bulk meters..
All establishments registered as commercial units with local authorities or dealing in consumer items for direct commercial sale like cafes, milk shops, tea stalls, canteens, barber shops, laundries, tandours, places of entertainment like cinemas, clubs, theaters and private offices, clinics, maternity homes, etc.
All consumers engaged in the processing of industrial raw material into value added finished products irrespective of the volume of gas consumed including hotel industry but excluding such industries for which a separate rate has been prescribed.
Prescribed Prices w.e.f. July 01, 2011
Prescribed Prices w.e.f.
January 01, 2012
Prescribed Prices w.e.f.
August 07, 2011
Rupees per MMBTU
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
24
(vi) CNG Stations:All off-takes at flat rate of 503.64 571.88 652.20
(vii) Cement Factories:All off-takes at flat rate of 536.42 609.10 694.65
(viii) Fertilizer Factories:
(1) Pak American Fertilizer Limited, Daudkhel.
(a) For gas used as feed stock for fertilizerCommodity charge.All off-takes at flat rate of 102.01 102.01 102.01
(b)
Commodity charge.All off-takes at flat rate of 382.37 434.18 495.16
(2) Pak Arab Fertilizer Limited, Multan.
(a) For gas used as feed stock for fertilizerCommodity charge.All off-takes at flat rate of 102.01 102.01 102.01
(b)
Commodity charge.All off-takes at flat rate of 382.37 434.18 495.16
(3)
(a) For gas used as feed stock for fertilizerCommodity charge.All off-takes at flat rate of 102.01 102.01 102.01
(b)
Commodity charge.All off-takes at flat rate of 382.37 434.18 495.16
(4)
(a) For gas used as feed stock for fertilizerCommodity charge.All off-takes at flat rate of 102.01 102.01 102.01
(b)
Commodity charge.All off-takes at flat rate of 382.37 434.18 495.16
For gas used as fuel for generating steam and electricity and for usage in housing colonies.
For gas used as fuel for generating steam and electricity and for usage in housing colonies.
For gas used as fuel for generating steam and electricity and for usage in housing colonies.
Dawood Hercules Chemicals Limited, Chichoki Malian, Sheikhupura District:
Pak-China Fertilizer Limited/Hazara Phosphate Plant Limited, Haripur.
For gas used as fuel for generating steam and electricity and for usage in housing colonies.
Review of Estimated Revenue Requirement of SNGPL Financial Year 2011-12 Under Section 8(2) of the OGRA Ordinance, 2002 _______________________________________________________________________
25
(5) ENGRO Fertilizer Company Limited
(a) For gas used as feed stock for fertilizerCommodity charge.All off-takes at flat rate of 59.29 59.59 60.67
(b)
Commodity charge.All off-takes at flat rate of 382.37 434.18 495.16
(ix) Power Stations:(a)
All off-takes at flat rate of 393.79 447.14 509.94
(b)
Commodity ChargeAll off-takes at flat rate of 393.79 447.14 509.94 Fixed charge (Rupees per month). 390,000 390,000 390,000
(c) Liberty Power Limited. All off-takes at flat rate of 990.97 1,260.34 1,267.35
(ix) Independent Power Projects
Commodity ChargeAll off-takes at flat rate of 332.36 377.39 430.40
WAPDA's Natural Gas Turbine Power Station, Nishatabad, Faisalabad.
WAPDA's Power Stations and other electricity utility companies excluding WAPDA's Natural Gas Turbine Power Station, Nishatabad, Faisalabad.
For gas used as fuel for generating steam and electricity and for usage in housing colonies.