ilc kiln manual ed1

Upload: aaron-horton

Post on 09-Oct-2015

177 views

Category:

Documents


9 download

DESCRIPTION

In line calciner manual

TRANSCRIPT

  • 5/19/2018 ILC Kiln Manual Ed1

    1/70

    PROCESS

    OPERATION

    MANUAL

    Page 1 of 68

    OPERATING INSTRUCTIONS

    AND REFERENCE MANUAL

    FOR

    ILC PREHEATER SYSTEM

    CUSTOMER : RAIN INDUSTRIES LTD.,(3800 TPD NEW LINE)

    PLANT LOCATION : KURNOOL, ANDHRA PRADESH, INDIA

    FLSMIDTH LIMITEDWORK ORDER NO. : PRJ06-009-000

    Prepared by: A.SRINIVASAN Date: 21.04.2008

    Checked by: N.SIVAKUMAR Rev.: 0

    Approved by: S.SARAVANAN

  • 5/19/2018 ILC Kiln Manual Ed1

    2/70

    PROCESS

    OPERATION

    MANUAL

    Page 2 of 68

    TABLE OF CONTENTS

    1. GENERAL NOTES

    2. CONSTRUCTION AND OPERATING PRINCIPLE

    3. DRYING AND HEATING OF LINING PRIOR TO START-UP OFKILN

    4. STARTING OF THE KILN PLANT

    5. STOPPAGE OF THE KILN PLANT

    6. OPERATION OF THE KILN PLANT

    7. INTERLOCKINGS, PROGRAMMING AND CONTROL CIRCUITS

    8. PREVENTION OF FIRES AND EXPLOSIONS

    9. BARRING

    10. CAUSE/EFFECT DIAGRAMS, OPERATING PARAMETERSAND ALARM LIMITS.

  • 5/19/2018 ILC Kiln Manual Ed1

    3/70

    PROCESS

    OPERATION

    MANUAL

    Page 3 of 68

    NOTE!

    The present instruction manual is dealing with the

    situations which, according to the experience ofFLS, are the most likely to occur. An exhaustive

    enumeration of all conceivable situations which

    ay occur during the

    erection/operation/maintenance of the kiln

    plant/machine/equipment cannot be provided.

    Consequently, if a situation should arise, the

    occurrence of which is not foreseen in the in-

    struction manual, and which the operator is/or

    feels unable to handle, we would recommend thatFLS is contacted without undue delay for advice on

    appropriate action.

  • 5/19/2018 ILC Kiln Manual Ed1

    4/70

    PROCESS

    OPERATION

    MANUAL

    Page 4 of 68

    1 GENERAL NOTES

    This manual is intended as a reference guide, which can

    be used in connection with the start-up, normal

    operation and shutdown of the plant.

    The majority of the directions given in the manual are

    of a generalized character given that a range of

    relevant factors of a specific or localized nature are

    involved, and it would be impossible to provide adetailed evaluation of all these factors in this manual

    without sacrifice of clarity.

    The manual must be regarded as a tool for optimization

    of the kiln plant, and it can also be used to support

    judgements made by the operator in a given operating

    situation.

    In this manual it is a foregone conclusion that the

    control panel equipment has been installed, tested andmade fully operational.

    This manual should be thoroughly studied prior to

    start-up, so as to permit detailed planning of this

    phase.

    Several separate instruction manuals related to the

    plant under review in this manual; these manuals

    contain detailed information about the single machines

    or arrangements.

    These manuals must also be studied very carefully

    before the plant is put into operation.

  • 5/19/2018 ILC Kiln Manual Ed1

    5/70

    PROCESS

    OPERATION

    MANUAL

    Page 5 of 68

    2 CONSTRUCTION AND OPERATING PRINCIPLE

    2.1 Construction of Main Elements

    The kiln plant construction is schematically shown in

    enclosures.

    The clinker producing plant is a FLS-ILC (In-LineCalciner, Low NOx type) installation incorporating the

    following elements:

    Kiln tube

    Diameter 3.95meters

    Length 61.0 meters

    No of supports 3

    Inclination 4.0%

    Size of Kiln Drive & max. Speed 493 kW, 5.00 rpm

    No. of Preheater Strings and Stage Single stringwith 5 Stages

    Size of Cyclones in Kiln String Stage III: 7.8 m

    Stage III-V: 8.0 m

    Size of Calciner 6.9 m x35.2m Long

    Grate Cooler Type SF CROSS BAR- 3x5F

    Burner Type Duoflex

    Kiln Feed System Bucket Elevator

    2.2 Operating Principle

    The ILC Calciner kiln system is installed. The Calciner

    is placed in-line with the kiln riser duct.

    The combustion gas for the Calciner is hot atmospheric

  • 5/19/2018 ILC Kiln Manual Ed1

    6/70

    PROCESS

    OPERATION

    MANUAL

    Page 6 of 68

    air drawn from the SF CROSS BAR COOLER through tertiary

    air duct mixed with the combustion gas from the kiln.

    The Calciner is dimensioned for a gas retention time of

    approximately 4.5 seconds.

    The kiln and Calciner is provided with a preheater. The

    cyclones are of the proven FLS LP-type, which ensures a

    very low pressure loss of the preheater.

    The kiln main burner is the new Duoflex burner. Theprimary air consumption of this burner is lower as

    compared with traditional burners.

    The burner is provided with an oil burner for start-up.

    The raw meal feed i.e. the kiln feed is extracted from

    the homogenizing raw meal silo into a kiln feed bin.

    The raw meal is then transported to the preheater inlet

    by the Bucket Elevator.

    The preheater is operating as a counter current heat

    exchanger with the raw meal passing downwards through

    the preheater stages by gravity, and the hot gas moving

    upwards drawn by the ID-fan.

    Having passed 4 or 5 preheater stages - depending where

    to the feed is directed - then the raw meal passes a

    splitter gate, where the raw meal flow can be diverted

    into two positions in variable amounts, one to the

    calciner vessel, and two to the riser pipe from the

    kiln. This splitting and the amount of material being

    guided to one way or the other is depending very much

    on the fuel used, and the tendency of coating formation

    in the riser pipe.

  • 5/19/2018 ILC Kiln Manual Ed1

    7/70

    PROCESS

    OPERATION

    MANUAL

    Page 7 of 68

    Approximately 55 - 60% of the fuel can be fired in the

    Calciner. The raw meal will be calcined to a degree of

    about 90-94%. The Calciner can be operated at high

    temperatures of more than 1000 C., which increases the

    combustion rate. The excess air at the top of the

    Calciner is foreseen to be approximately 20%

    corresponding to an oxygen level of 3% in the outlet

    gas duct of the Calciner. These measures should ensure

    complete combustion of the fuel applied.

    The combustion air used in the Calciner is a mixture of

    hot air (875-925 C.) drawn from the SF cooler through

    the tertiary air duct and the kiln gases from the

    rotary kiln.

    The material is leaving the top of the Calciner and is

    then passing onwards to the 5thpreheater stage.

    From this last preheater stage the material slides to

    the rotary kiln inlet.

    Due to the inclination and rotation of the kiln, the

    raw meal is transported downstream through the kiln.

    Simultaneously, the raw meal is gradually heated up and

    fully calcined by the heat supplied to the kiln.

    Clinkerization - clinker formation - takes place when

    the raw meal passes through the burning zone of the

    kiln.

    The clinker formed enters the grate cooler for cooling.

    2.2.1 SF CROSS-BAR COOLER

  • 5/19/2018 ILC Kiln Manual Ed1

    8/70

    PROCESS

    OPERATION

    MANUAL

    Page 8 of 68

    The cooler is the well proven SF (Smidth-Fuller) crossbar cooler. This cooler type comprises a number ofunique features:

    Cross bar, separate conveying clinker device.

    All grate plates are stationary.

    Low energy grate plates with mechanical flowregulators.

    Modular concept.

    The SF cooler has a modular design. The coolernomenclature describes the number of modules the coolerconsists of (width x length). Before each row of coolermodules there is an inlet module without cross bars,serving as impact zone for the clinker leaving thekiln.

    Each cooler module has a width of 1.3 m and a length of4.2 m and comprises 4 x 14 grate plates. The module hasan inclination of 4degrees.

    The inlet modules, 1.3 m wide and 2.0 m long, has an

    inclination of 15 and consist of 4 x 5 grate plates.The outer corners of the two outer inlet modules arecovered with refractory. Each row of cooler module andthe inlet modules has their own cooler fan.

    The grate plates in the cooler modules as well as inthe inlet modules are stationary. The transport of theclinker is made by reciprocating crossbars locatedabout 50 mm above the grate line. Each cooler modulehas 12 cross bars, 6 stationary and 6 moveable. Themoveable crossbars are connected to two longitudinalprofiles, which are driven by a hydraulic cylinder

    below the grate, one for each module. The drive systemin a module is connected to the drive systems in theprevious and subsequent modules. The right set and theleft set of modules can then be moved independent ofeach other for optimum distribution and transport ofthe clinker.

  • 5/19/2018 ILC Kiln Manual Ed1

    9/70

    PROCESS

    OPERATION

    MANUAL

    Page 9 of 68

    As the grate plates are protected by a stationary layerof clinker they will, contrary to other modern coolers,not wear down and deteriorate the air distribution witha lot of sealing air.

    The grate plate is made with labyrinth air path forelimination of through fall of clinker. Transportequipment below the grate is then completelyeliminated. The grate plate proper has a low pressuredrop. In order to ensure an optimal air distributionevery grate plate is provided with a mechanical flow

    regulator (MFR). The MFR maintains a constant airflowthrough the grate and clinker bed irrespective ofclinker bed height, particle size distribution,temperature, etc; i.e. separate flow control for eachgrate plate. The MFRs allow use of one fan forrelative large areas and completely eliminates the useof under-grate ducts and dampers seen in other moderncoolers.

    The modular concept of the SF cooler allows shopassembling of large part and very fast erection. Due tothe cross bar system the number of wear parts are

    minimized and replacement of these parts are fast andeasy to perform.

    The kiln hood is common for the kiln and the tertiary

    air duct. The hood is made so large, that minimum

    clinker dust is recirculated to the kiln and Calciner.

    2.2.2 Gas treatment and distribution

    Whenever the kiln is in normal operation, the preheater

    exhaust gases or part of these can be utilizeddepending on the raw mill or coal mill is in operation

    or it is stopped. When the mill is in operation, part

    of the gases is used for drying raw material in raw

    mill or coal in coal mill.

  • 5/19/2018 ILC Kiln Manual Ed1

    10/70

    PROCESS

    OPERATION

    MANUAL

    Page 10 of 68

    The dust precipitated in the kiln/raw mill filter

    installation is returned to either

    the raw meal silo

    or the kiln feed.

    The cooler excess air is treated in a separate ESP -

    designed especially for clinker dust. The recuperated

    dust is returned to the clinker transport system.

    2.2.3 Separate Instruction Manuals

    A number of other instruction manuals for the

    individual machines or arrangements are available for

    the plant concerned.

    STUDY THESE MANUALS BEFORE THE PLANT IS STARTED

    It is not all machines or equipment in this instruction

    manual, that are supplied by FLS.

    The FLS delivery range can be read in the order

    acknowledgement and the order list.

    3 DRYING AND HEAT-UP OF LINING PRIOR TO START-UP

    OF KILN

    3.1. Preconditions and Criteria for start-up

    This section must be compared with the graphical form

    given section 9, which provides information about

    heating and start-up procedures.

    3.1.1 Personnel

    Operators and operating personnel must be fully

  • 5/19/2018 ILC Kiln Manual Ed1

    11/70

    PROCESS

    OPERATION

    MANUAL

    Page 11 of 68

    familiarized with the instruments and functions of the

    control panel.

    Furthermore, the personnel must be well informed about

    the layout and operating principle of the motor control

    system, especially all interlocking diagrams indicating

    protective, safety and operational interlocking.

    3.1.2 Raw Materials

    Prior to start-up, raw materials must be available in

    sufficient quantities and with a well known quality in

    order to ensure continuous, stable kiln operation.

    3.1.3 Preparations

    The following activities must be carried out prior to

    the initial start-up:

    1. All kiln plant machinery should be subjected to no-

    load testing and, where possible testing under load.

    The trial run of the kiln should comprise only of the

    kiln motor, with the coupling bolts removed.

    Trial run of machines loaded with material should be

    performed over a prolonged period. For instance 24

    hours, with the kiln feed in circulation.

    Water and/or air must be available where necessary.

    2. The entire electrical and electronic control system

    must be tested to ensure that all interlockings i.e.

    safety, protective and operational interlockings are

    active and that they function properly.

  • 5/19/2018 ILC Kiln Manual Ed1

    12/70

    PROCESS

    OPERATION

    MANUAL

    Page 12 of 68

    3. Ensure that all alarm limits have been set. (Refer

    section 10 in this instruction manual).

    4. The raw meal must be recirculated to sustain the

    operation of the feed arrangement and for calibration

    of the load cells.

    5. Prior to the production of clinker an appropriate

    amount of correct quality raw meal must be available.At least 3 days consumption must be available.

    6. Where possible, the oil in the firing installation

    should be recirculated to check the function ability of

    the installation.

    7. Ignition burner and burner equipment must have been

    prepared for start-up.

    8. The chemical laboratory at the plant should be onstandby to perform the necessary analyses of the kiln

    feed and clinker, particularly to determine the content

    of free lime, the litre weight of the clinker, and the

    kiln feed analysis.

    9. In order to optimize the regulation of the primary

    air volume in the kiln, for optimization of the flame

    structure, it is advisable to measure the airflow

    supplied to the burner by the primary air fan at

    different valve openings and pressures. Hence it is

    possible to ascertain what valve position should be

    used during operation.

  • 5/19/2018 ILC Kiln Manual Ed1

    13/70

    PROCESS

    OPERATION

    MANUAL

    Page 13 of 68

    NOTE!

    Where specific demands for initial drying procedure of

    the concrete are stipulated by the supplier of the

    castable for the grate cooler, account must be taken of

    such criteria during the start-up phase, or, if this is

    not possible, it may be necessary to dry out the cooler

    on a separate basis.

    3.1.4 Preparations Prior to Heating

    Before the below mentioned start-up sequence is

    followed and any machines are put into operation, the

    description in section 7 of the interlockings, the

    programming and the control should be read through.

    CHECK

    - That all tools and all alien objects have been

    removed from all kiln plant machines.

    - That potential coatings have been removed from

    cyclones, flue ducts and riser ducts.

    - that all doors and clean-out hatches are closed.

    - that the motorized dampers function properly

    - that the barring device, with brake , is ready

    to be operated.

    - that all plant machinery has been lubricated in

    strict accordance with directions given in

  • 5/19/2018 ILC Kiln Manual Ed1

    14/70

    PROCESS

    OPERATION

    MANUAL

    Page 14 of 68

    separate instruction manuals.

    - oil must be applied to the journals of the

    supporting rollers to ensure that they are

    covered by oil when barring operation is

    started.

    - the water supply to kiln bearings and gas

    analyzer is functioning.

    - that all instruments in the control system are

    functioning.

    - that all alarm limits have been set.

    Start the compressed-air supply and check that

    compressed air is present at the points of consumption

    at the correct pressure.

    Place the gas analyzer equipment in the kiln system inthe state of readiness.

    Check that the thrust roller device and the spray

    lubrication for gear rim are ready with sufficient oil

    and grease. Refer separate instruction manual.

    Mount the light-up nozzle on the burner installation of

    the kiln and prepare the ignition burner for operation.

    Prepare the cooler and the clinker transportation

    system. Place about 300 - 400 mm layer of cold clinker

    on the Fixed Inlet section of the cooler.

    See separate instruction manual for cooler.

  • 5/19/2018 ILC Kiln Manual Ed1

    15/70

    PROCESS

    OPERATION

    MANUAL

    Page 15 of 68

    If special requirements for the initial drying of the

    castable are stipulated by the supplier of the castable

    for the grate cooler, these requirements must either be

    met during the start-up procedure or, if this is not

    possible, the grate cooler must be dried out

    separately.

    Once these checks and activities have been completed,

    both the electrical and the mechanical department must

    ensure that the installation is reported ready forstart-up.

    3.2 Drying-out procedure

    3.2.1 Kiln & Preheater

    The heating and drying-out of the refractory lining

    must be performed very slowly and gradually in order toavoid cracking and spalling. This applies especially in

    places where large zones are lined with castable and

    are to be dried out.

    The initial heat-up/drying-out operation should stretch

    NOTE

    The given heat-up schedule is applicable for

    refractory supplied by FLS only. It may be necessary

    to modify the outlined drying out procedure in case a

    different code of practice is recommended by thebrick supplier. However, consultations between the

    plant management and FLS are needed before any

    modifications are introduced.

  • 5/19/2018 ILC Kiln Manual Ed1

    16/70

    PROCESS

    OPERATION

    MANUAL

    Page 16 of 68

    over a time period of approximately 72 hours as shown

    in the diagram given in section 9.

    In connection with subsequent kiln starts, the heating

    period can normally be reduced to 24 hours, though it

    depends on the type of lining repairs conducted during

    the intervening periods.

    As mentioned previously, it is recommended to extend

    the heat-up period if concrete castable has been used

    for casting operations inside the kiln system.

    3.3 Initiation of Heat-up Operation

    See also the separate instruction manuals related to

    the individual equipment mentioned.

    Heat-up operation is started as follows:

    3.3.1 Kiln and Preheater

    Checkthat the dampers in the ducts to all the mills,which will be supplied with drying gas, are closed.

    Start the oil circulation to the burner.

    Checkthe pressure and temperature of the oil.

    Start the hydraulic pump of the thrust device.

    Start the spray lubrication system for the kiln drive.

    Start the kiln bag house -fan with closed damper.

    Open the filter fan damper gradually, so that a

    negative pressure of 1-2 mmwg is maintained in the gas

    duct just after the ID-fan.

  • 5/19/2018 ILC Kiln Manual Ed1

    17/70

    PROCESS

    OPERATION

    MANUAL

    Page 17 of 68

    The damper for the ID-fan are opened 10-15% so that

    there is created a slight negative pressure in the kiln

    hood.

    Start the primary air fan and close the primary air

    damper to 10%.

    Start the ignition burner.

    Start the oil burner by opening the oil valve for the

    light-up nozzle.

    Checkthat the oil is ignited; if necessary adjust the

    primary air valve to facilitate the flame formation.

    Adjust the draught in the kiln by means of the exhaust

    gas damper, the filter fan speed and the damper.

    Start the barring of the kiln in accordance with thebarring programme outlined in section 9.

    Check lubrication of supporting rollers. The journals

    must not become dry. During barring it may be required

    to pour additional oil directly on the journals.

    The specified barring program must be adhered to;

    however, if the thrust device equipment for indication

    of kiln position gives alarm, barring must be

    continuous until the alarm can be cancelled.

    Continuous barring is also required if the kiln is

    subjected to cooling, for instance due to heavy rain.

    Soon after the start of the burner, the gas analyzer in

  • 5/19/2018 ILC Kiln Manual Ed1

    18/70

    PROCESS

    OPERATION

    MANUAL

    Page 18 of 68

    the riser duct should be put into operation.

    Start the fans for the cooler inclusive the nose ring

    fan (it is the fan at the kiln outlet).

    Start the Bag house-fan for excess air from the cooler

    with closed damper.

    Setthe automatic negative pressure control in the kiln

    hood to a set point of -0.5 mmwg.

    Openthe hoisting damper in the tertiary air pipe 50%.

    Start the burner in the kiln hood, if supplied, the oil

    volume is set to 10-20% of full capacity. Over heating

    of the lining in the TA duct is thus avoided.

    Regulate the kiln string exhaust fan damper to get

    oxygen content of 8-10% in the kiln inlet. When thekiln has become hotter after some hours this level can

    be reduced to 3-4%.

    The ignition burner can be extinguished after

    approximately 8 hours or as soon as the lining is hot

    enough to support the ignition of the oil.

    3.3.2Air Supply during the Heat-up Phase

    During the heat-up period, the maximum amount of the

    heat input should be utilized for heating of the kiln,

    i.e. only the necessary air volume should be drawn

    through the kiln.

    However, an adequate air surplus must be present for

  • 5/19/2018 ILC Kiln Manual Ed1

    19/70

    PROCESS

    OPERATION

    MANUAL

    Page 19 of 68

    the complete combustion process.

    It could be necessary to start 2-3 cooling air fans and

    to start the excess air fan to be able to control the

    negative pressure in the kiln outlet.

    The oil flame must not cause sooting.

    Often, this would require that the oxygen content

    indicated by exit gas analysis in the riser duct is8-10%. When the kiln has become hotter after a couple

    of hours, then the oxygen content can be reduced to

    about 3-4%. An oxygen content smaller than this might

    cause a sooting flame.

    An exit gas analyser after the preheater is not of much

    use during the heat-up phase, since air infiltration

    from the preheater system would influence the analysis.

    3.4 Inspection during heat-up period

    The programme for heat-up period is graphical indicated

    in section 9.

    Following major lining repairs, a heat-up period of

    approximately 72 hours is recommended, whereas for

    normal starting of cold-state kiln the period should be

    approximately 24 hours.

    It is very important that no attempt is made to speed

    up the programme.

    In case of interruptions during the heat-up period

    compensation is needed by extending the time period, so

    that the actual heating period has the stipulated

  • 5/19/2018 ILC Kiln Manual Ed1

    20/70

    PROCESS

    OPERATION

    MANUAL

    Page 20 of 68

    duration.

    The heat-up speed, as measured at the kiln inlet and

    the outlet from the preheater tower, should very

    closely follow the curves as indicated in section 9.

    It is advisable to record operational experience gained

    during initial heat-up periods, so that the curves in

    the enclosure can be adjusted in accordance with the

    local conditions.

    A regulation of fuel rate, draught level and oxygen

    level is needed to ensure strict adherence to the

    curves for the temperature rise.

    Overall, the prime aim is, as previously mentioned, to

    ensure retention of the supplied heat inside the kiln.

    Any increase in the draught level will rapidly cause

    the temperature in the cyclone tower to rise at the

    expense of the temperature in the kiln, and this is notdesirable.

    The following inspection and check-up must be made

    during the heat-up period:

    Kiln Lining

    Inspect the kiln lining at regular intervals. The

    lining in the burning zone must not be exposed to fast

    and local overheating.

    The lining temperature must not exceed 1000 C.

    If the lining temperature rises too quickly and/or

    becomes too high, reduce the amount of fuel.

  • 5/19/2018 ILC Kiln Manual Ed1

    21/70

    PROCESS

    OPERATION

    MANUAL

    Page 21 of 68

    Kiln Shell Temperature

    Check the kiln shell temperature. Special attention

    must be focused on the burning zone where high surface

    temperatures may occur. Temperatures of up to 350 C.

    will be acceptable.

    If the kiln should become too hot in the burning zone,

    and the temperature after the preheater is relativelylow, i.e. it permits that surplus heat is drawn from

    the kiln upstream to the preheater by increasing the

    draught.

    Alternatively the flame shape must be adjusted by

    regulating the air volume to the main burner.

    Bearings for supporting rollers

    Check the lubrication. Dry running of the bearingjournals must not occur. When the kiln is barred, it

    may be necessary to apply additional oil directly to

    the bearing journals.

    Barring

    Strict observance of the specified barring programme is

    needed, but in the event that an alarm is tripped by

    the thrust device equipment indicating the position of

    the kiln, then the kiln must be barred continuously

    until the alarm can be cancelled.

    Continuous barring is also needed if the kiln is

    subjected to cooling, for example due to heavy

    rainfall.

  • 5/19/2018 ILC Kiln Manual Ed1

    22/70

    PROCESS

    OPERATION

    MANUAL

    Page 22 of 68

    Clearance between kiln shell and live ring

    The clearance between the kiln shell and the kiln tires

    must be checked at regular intervals during heat-up and

    start-up phase, especially at piers I and II.

    Clinker transport

    If the kiln has been filled with raw materials, it may,from time to time, be necessary to start the grate

    cooler and the clinker conveying system in order to

    transport away the materials, however, do not empty the

    cooler. To ensure effective cooling at the cooler

    inlet, it may as previously stated be necessary to

    start the first fans of the cooler.

    4 STARTING THE KILN PLANT

    4.1 Getting Ready for Operation

    Operational status must be prepared approximately 3

    hours in advance of the anticipated time for start-up

    with feed.

    At this stage the temperature of the kiln lining is

    sufficiently high to ensure ignition of the coal from

    the burner, which is put into operation as follows:

    - Reduce the oil flow to the burner.

    - Start coal firing with minimum coal.

    - Finally stop the oil & continue heating with

    necessary coal until the desired temperature profiles

    have been achieved, as indicated below.

  • 5/19/2018 ILC Kiln Manual Ed1

    23/70

    PROCESS

    OPERATION

    MANUAL

    Page 23 of 68

    Start the transport lines for dust and clinker after

    the kiln.

    Start the recirculation of raw meal if the equipment

    has been out of operation over a prolonged period of

    time.

    Start the burner in the kiln hood, if installed, unless

    it is already in operation. The oil quantity isadjusted so the lining temperature does not exceed 1000

    C.

    Start the dust conveyance system after the kiln bag

    house, and the cooler ESP.

    Check that the dividing or splitter gate after the 2nd

    lower most cyclones is adjusted so all the raw meal is

    directed to the riser pipe.

    4.2 Starting of kiln Feed

    When the temperature at the top of the 2nd lower most

    cyclone stage is about 750 C., and assuming compliance

    with the heating programme as outlined in enclosure,

    the kiln is ready to accept feed material.

    Personnel must be stationed in the cyclone tower in

    order to watch the raw meal as it passes through the

    cyclone preheater.

    Supervision is performed at the sluice flaps under each

    cyclone. The flaps must move freely. This is done to

    ascertain that the raw meal is passing through. The

    risk of jamming in the cyclones is particularly high

  • 5/19/2018 ILC Kiln Manual Ed1

    24/70

    PROCESS

    OPERATION

    MANUAL

    Page 24 of 68

    during start-up.

    The control room must have the possibility to contact

    the supervising personnel via mobile communication

    equipment, radio or telephone; so that early warning

    can be given from the supervising personnel to the

    control room in event of jamming symptoms in cyclones

    are observed.

    4.3 Starting of Kiln Main Motor

    Stop the barring motor, disengage the barring gear and

    start the kiln main motor at the lowest speed.

    Start the exhaust gas fan with closed damper. Sometimes

    it is necessary to stop the burner if it takes a long

    time to establish the draught as the fan is started

    with closed damper. However, it should be possible to

    operate the burner at minimum rate.

    Therefore the draught and fuel rate must be reset tolevels applicable prior to the starting of the exhaust

    gas fan. Please make sure that the filter fan speed is

    adjusted to maintain sufficient suction after the kiln

    exhaust gas fan.

    Start the clinker transport system, with clinker

    breaker, and the cooler drives and fans (refer to

    separate manual for the SF-cooler).

    4.4 Establishing Normal Production Rate

    Perform the following operations in RAPID but PROPER,

    sequence:

    - Start the raw meal feed to the preheater.

  • 5/19/2018 ILC Kiln Manual Ed1

    25/70

    PROCESS

    OPERATION

    MANUAL

    Page 25 of 68

    - Increase the draught level by opening the damper for

    the exhaust gas fan as well as the speed of the fan.

    - Increase the fuel rate accordingly.

    - Increase the feed rate to 55-60% of full production,

    with simultaneous increase in kiln speed to 1.4-1.6

    rpm.

    - Start the fuel supply to the Calciner at minimum

    rate. As soon as the kiln feed has reached the lower

    most cyclone stage, then increase the fuel rate in

    order to maintain the temperature of this lower most

    stage of about 860 C.

    - Set the draught level and fuel rate so the fuel

    supply rate is 5-10 % in excess of the normal

    operational level at the same production rate. The

    reason is that the kiln system is colder at start-up ascompared with normal operation.

    The draught must always be increased prior to any

    increase in the fuel rate in order to avoid CO-

    formations. Also remember to regulate the damper in the

    tertiary air duct for the Calciner.

    The temperature after the preheater must not exceed

    400 C.

    The gas analyzer after the preheater will typically

    indicate an oxygen level of 6-8% during start-up.

    However, the oxygen level should be in the range of 3-

    4% at the kiln inlet.

    When it has been ascertained that the clinker in the

  • 5/19/2018 ILC Kiln Manual Ed1

    26/70

    PROCESS

    OPERATION

    MANUAL

    Page 26 of 68

    burning zone is well-burned, the kiln speed can

    gradually be increased to match the production level.

    The kiln feed rate and the kiln speed rpm should be

    synchronized to maintain constant material level, for

    instance 4.0 rpm corresponds to 100% production level.

    It is of critical importancethat the first material is

    well burned in order to avoid circulation of dust

    between kiln and cooler. Dust circulation may cause

    cooling of the burning zone so more time is needed tostabilize the kiln operation.

    Since, as mentioned above, the heat input to the kiln

    at the beginning exceeds the amount required for

    clinker formation, the kiln system will gradually be

    heated.

    When there is solid evidence of satisfactory clinker

    formation at low free lime levels, the kiln output can

    gradually be increased with simultaneous increase ofdraught level, feed rate and fuel rate.

    Especially the kiln torque and visual inspection of the

    clinker are useful parameters to use in order to judge

    whether the clinker are well burned. Further analyses

    of the clinker litre weight and content of free lime

    are useful for judgment of the clinker quality.

    The duration of the period from starting of the kiln

    feed to full production level is reached, will normally

    be 5 - 8 hours.

    4.5 Starting and Operation of the Cooler

  • 5/19/2018 ILC Kiln Manual Ed1

    27/70

    PROCESS

    OPERATION

    MANUAL

    Page 27 of 68

    See also separate instruction manual.

    4.6 Preparations for Calciner Operation

    As mentioned above the firing in the Calciner must be

    started at the same time as feed taken to the

    preheater. However, the following interlockings must be

    fulfilled:

    - Kiln main burner in operation with ID-fan inOperation.

    - Kiln main drive in operation.

    - The temperature in the lower most cyclone stage must

    be higher than minimum (750 C.) and lower than max

    I (920 C).

    - The feed to the preheater is on.

    - CO content in the gases after the preheater must not

    be higher than max II (0.9%) for more than 10

    seconds, and then the fuel rate to the Calciner

    must automatically be reduced by minimum 20%. Theburner is then automatically changed to manual

    control mode.

    The combustion gas/air to the Calciner is controlled

    both by adjustment of the ID-fan speed and by changing

    the position of the damper in the tertiary air duct.

    The draught adjustment should maintain 3-4% oxygen at

    the preheater outlet with CO content lower than 0.05%

    and an oxygen level between 3-4.5% at the kiln inlet.

    Always increase draught before fuel rate is increased

    to prevent formation of explosive gases.

    4.6.1 Achieving Nominal Capacity

  • 5/19/2018 ILC Kiln Manual Ed1

    28/70

    PROCESS

    OPERATION

    MANUAL

    Page 28 of 68

    During the first couple of hours after the production

    has been started the feed rate is increased gradually,

    however, only concurrently with production of well

    burnt clinker.

    Adapt feed and fuel so the temperature in the lower

    most cyclone stage is maintained at approximately 880 -

    890 C., which would correspond to a degree of

    calcination of 90-94%. This calcining temperatureshould be maintained automatically by the CCR-control

    system.

    Consequently the kiln production is increased as

    follows:

    - Increase the draught

    - Increase the feed. (Synchronously with the kiln

    Speed).

    - Increase the fuel supply to the Calciner(possibly automatically).

    - Check whether a change of the kiln fuel is

    needed. (Depending of free lime level, litre weight

    and torque).

    The temperature of the hot air from the cooler to the

    Calciner through the tertiary air duct will increase

    progressively as the clinker volume is increased.

    Therefore the fuel rate to the Calciner will be

    reduced.

    5 SHUTDOWN

    5.1 Normal shutdown of the plant

  • 5/19/2018 ILC Kiln Manual Ed1

    29/70

    PROCESS

    OPERATION

    MANUAL

    Page 29 of 68

    It is advisable to shutdown the kiln plant in a

    controlled manner by following the sequence outlined

    below:

    - Reduce the total air-flow to the cooler.

    - Stop the fuel to the Calciner.

    - Stop the exhaust gas fan and close the

    damper (automatically)

    This automatically involves that:

    - The kiln burner is stopped

    - The kiln feed is stopped or switched over to

    recirculation back to the CF silo.

    - Stop the kiln motor.

    - Stop the filter fan and close the motorized

    damper ahead of the fan.

    - Reduce the amount of primary air to a minimum.

    However, a certain amount of primary air is needed tocool down the burner pipe, if the burner remains in the

    kiln.

    - Reduce the cooler grate speed. After a few

    minutes they can be stopped.

    - The cooling air fans can be stopped one by one

    gradually.

    Start barring operation as outlined in section 9.

    BARRING.

    Where the shutdown period of the kiln extends over a

    prolonged period of time, then all machinery not

    required for barring of the kiln and cooling of the

  • 5/19/2018 ILC Kiln Manual Ed1

    30/70

    PROCESS

    OPERATION

    MANUAL

    Page 30 of 68

    burner pipe must be stopped. i.e.:

    - Stop the dust conveyance system when the system

    is empty.

    - Withdraw the gas analyzer from the riser duct.

    - Stop the compressors.

    - Draw up plans for subsequent clean-up operation

    in the cyclones, flue ducts and riser ducts.

    - Make sure that the cooling water supply for the

    kiln bearings is functioning as long as the kilnis barred.

    After the kiln has cooled off:

    - Stop the primary air fan and retract the burner.

    - Stop the clinker conveying system.

    - Inspect the kiln, the cooler, the hot gas ducts

    and the preheater.

    - Planning of the maintenance- and repair work

    required prior to renewed start-up.

    NOTE!

    The kiln must always be cooled off slowly to prevent

    too rapid cooling of the lining in relation to the kiln

    shell. Otherwise, the lining may become loose,

    involving risk of twisting and drop-out of bricks.

  • 5/19/2018 ILC Kiln Manual Ed1

    31/70

    PROCESS

    OPERATION

    MANUAL

    Page 31 of 68

    5.2 Unscheduled shutdowns

    In the following a description is given of the most

    common types of operational disorders.

    5.2.1 Total Power failure

    All machines and motors are stopped.

    The emergency power generator must be started making it

    possible to bar the kiln, to close the fan dampers, to

    cool down the burner pipe, to start the nose-ring fan

    and to start the first 3 fans of the cooler. Cooling

    water for cooling of the support roller bearings must

    be available as long as the kiln is barred.

    5.2.2 The kiln main burner stops functioning.

    If operational status cannot be restored immediately,

    the exhaust gas fan must be stopped; thereafter the

    shutdown procedure outlined in subsection 5.1 must be

    initiated.

    5.2.3 The Calciner burner stops functioning

    If the Calciner burner can be restarted immediately,

    then there is a possibility of restoring stable

    operation. Otherwise, the kiln may have to be stopped.

    Until the burner can be restarted the kiln feed as well

    as the draught should be reduced. The draught in the

    Calciner and the preheater is likely to be too low

    causing drop-through of material from one preheater

  • 5/19/2018 ILC Kiln Manual Ed1

    32/70

    PROCESS

    OPERATION

    MANUAL

    Page 32 of 68

    stage to another. So if the Calciner burner is not

    restarted fairly quickly then kiln operation must stop,

    and the shutdown procedure outlined in subsection 5.1

    must be initiated.

    5.2.4 Kiln Feed Failure

    If the kiln feed cannot be restarted immediately, it

    will be necessary to shut down the kiln. Stop the

    exhaust gas fan and follow the shutdown procedureoutlined in subsection 5.1.

    5.2.5 Blockage of Cyclones

    Blockage symptoms are normally indicated by a drop in

    the negative pressure at the bottom of the cyclone or a

    drop in the temperature of the material after the

    cyclone.

    If blockage is ascertained in a cyclone, it isessential, that the kiln is brought to immediate

    standstill in order to avoid overfilling.

    Stop the exhaust gas fan and the kiln motor. The feed

    is stopped by interlocking.

    Then follow the shutdown procedure outlined in

    subsection 5.1.

    Before the clean-up operation is started, a negative

    pressure can be generated by means of the filter fan.

    5.2.6 Hot spots on the kiln shell

    A shutdown of the kiln will normally be required if the

  • 5/19/2018 ILC Kiln Manual Ed1

    33/70

    PROCESS

    OPERATION

    MANUAL

    Page 33 of 68

    kiln shell temperature is higher than 400 C.

    An attempt can be made to maintain the kiln in

    operation to postpone the shutdown to a more

    appropriate time, provided the temperature can be

    lowered by means of cooling fans with concentrated

    cooling at the hot spot(s).

    It is prudent practice to keep the kiln motor running

    on minimum speed until the temperature of the hot spothas been substantially reduced.

    If, however, it is not possible to cool the hot spot,

    then a kiln shutdown for repairs of the lining is

    described in subsection 5.1.

    It may be advantageous to make a partial discharge of

    material from the kiln by prolonged barring before the

    repair of the lining is initiated.

    5.2.7 Failure of Clinker Transport

    In event of clinker transport failure, the kiln can

    normally be maintained in operation for a couple of

    minutes before it must be shutdown.

    During this period of time an attempt to restart the

    clinker transport must be made, but if operation cannot

    be resumed, it will be necessary to shutdown the kiln

    in accordance with the procedure outlined in subsection

    5.1.

    5.2.8 Failure of the Cross bar Cooler

  • 5/19/2018 ILC Kiln Manual Ed1

    34/70

    PROCESS

    OPERATION

    MANUAL

    Page 34 of 68

    In this case, the precautionary measures which should

    be taken are identical to those outlined in subsection

    5.2.7.

    5.2.9 Failure of dust handling system

    Normally, kiln operation may continue for a short

    period (if some accumulation of material in the dust

    transport system is found to be acceptable, and if the

    authorities will allow short periods of kiln operationwithout dedusting). If it is not possible to restart

    the dust conveyance in this short period, the kiln must

    be stopped in accordance with procedure outlined in

    subsection 5.1.

    6 OPERATION

    6.1 General Notes

    The kiln performance is optimized by ensuring that

    operational kiln adjustments are restricted to an

    absolute minimum. The necessary adjustments must be

    phased in gradually.

    Once all control loops are active, these will ensure

    maintenance of:

    - the pressure after the exhaust gas fan for

    stabilization of the draught.

    - the outlet temperature from the Calciner, ensuring

    a constant degree of calcination.

    - the pressure at the kiln outlet, this contributes

  • 5/19/2018 ILC Kiln Manual Ed1

    35/70

    PROCESS

    OPERATION

    MANUAL

    Page 35 of 68

    towards stable cooler operation, and stable

    secondary and tertiary air conditions.

    - the operation of the cooler, with a battery of

    regulators providing uniform cooling by adjustment

    of air flows and grate speeds.

    The fuel supply rate to the kiln installation is

    determined on the basis of an evaluation of the clinker

    quality, i.e. the litre weight, free lime content andthe general appearance of the clinker.

    Another determinant is the current status of the kiln,

    i.e. the trend of the torque curve, the potential

    presence of coating formation or other operational

    disorders recently encountered.

    6.2 Specific Conditions related to kiln operation

    In the following a review is made of a range of

    specific factors affecting the kiln operation.

    6.2.1 Exit Gas Analysis

    The exit gas analysis constitutes the most important

    source of information for the evaluation of the

    combustion process. Therefore, it is of crucial

    importance to ensure that the analysis equipment is

    functioning properly.

    The smoke gases must not contain any unburnt substances

    i.e. C (Carbon) or CO (Carbon Monoxide).

  • 5/19/2018 ILC Kiln Manual Ed1

    36/70

    PROCESS

    OPERATION

    MANUAL

    Page 36 of 68

    Presence of such gases may, under adverse

    circumstances, cause fires or explosions and further,

    the loss incurred by wasting the latent heat of the

    unburnt part of the gases may be quite substantial.

    A CO level of more than 0.1% in the smoke gases may

    entail added calorie consumption in the kiln.

    Any presence of unburnt substances would indicate

    inadequacy of air for the combustion of the fuel. Evenwith an adequate air volume, the smoke may contain

    unburnt substances due to the fact that the mixture of

    fuel and air is not ideal. Therefore, a certain air

    surplus should be applied during the combustion

    process.

    As previously mentioned, the exit gases from the

    preheater should contain 3-4% of oxygen. It is possible

    to set a lower alarm limit for the oxygen level. For

    example, a limit of 2% can be applied. This alarm willinform the operator about the risk of unburnt

    substances in the exit gases.

    After the preheater the gas analyser will continuously

    monitor the CO level in the exit gases.

    The alarm limits should be set as follows:

    MAX I : 0.5% CO

    MAX II : 0.9% CO

    MAX I will signal alarm. Then the operator must make

    the necessary adjustments to the combustion process.

  • 5/19/2018 ILC Kiln Manual Ed1

    37/70

    PROCESS

    OPERATION

    MANUAL

    Page 37 of 68

    MAX II will signal alarm and after 10 seconds

    automatically reduce the fuel rate to the Calciner by

    minimum 20%. The Calciner burner is then in manual

    control mode.

    6.2.2 Primary Air Volume

    The primary air is supplied through the burner pipe,

    ensuring an effective mixture of air and fuel.

    Normally the primary air volume supplied by the fanconstitutes 5-6% of the air volume needed for

    combustion.

    6.2.3 Temperatures after Cyclone Preheater.

    The exhaust gas fan is designed to withstand operating

    temperatures up to 400 C. However, short term

    temperature rises up to 450 C. can be tolerated.

    The following alarm limits should be set:

    MAX I : Giving alarm which is 400 C.

    MAX II : Causing alarm tripping and

    Stoppage of the exhaust gas fan

    at a temperature level which is

    450 C.

    but never higher than 450 C.

    Note:

    Also one bleed air damper is provided in the downcomer

    duct to cool the preheater hot gases whenever the

    temperature rises beyond 450 oC.

    6.2.4 Bearing Temperatures

  • 5/19/2018 ILC Kiln Manual Ed1

    38/70

    PROCESS

    OPERATION

    MANUAL

    Page 38 of 68

    An excessive temperature in any fan bearing will cause

    alarm tripping and automatic switch the fan off. This

    applies to the exhaust gas fan, the filter fan and the

    grate cooler excess air fan.

    An excessive temperature in any supporting roller

    bearing will only cause alarm indication, but the

    operator must ensure, that immediate action is taken

    for the remedy of the situation, if kiln operation iscontinued.

    6.2.5 Bag-Filter

    The operating temperature of the filter must never

    exceed the maximum temperature specified by the

    supplier.

    The thermocouples at the inlet and the outlet of the

    Bag-filter casing are connected to electricalinterlockings that will stop the filter fan in case of

    elevated temperature.

    6.2.6 Blockage in the Cyclones

    Changes in the temperatures of the material at the

    discharge point from the cyclones, may be signs of

    incipient - the beginning stages of a - blockage in the

    cyclones.

    Negative pressure meters are installed at the bottom of

    all the cyclones. If the negative pressure drops during

    normal operation, this is, combined with a possible

  • 5/19/2018 ILC Kiln Manual Ed1

    39/70

    PROCESS

    OPERATION

    MANUAL

    Page 39 of 68

    change in temperature, confirms a sure sign of

    blockage. The pressure gauges will cause alarm

    indication, if the negative pressure should drop below

    the set minimum value. It is then up to the operator to

    assess, on a case by case basis, whether a kiln

    shutdown is required.

    A drilled hole, with a diameter of about 2 mm must be

    present in the connecting bushings for the negative

    pressure meters, and it is very important to keep thishole clean. In case of blockage in the cyclones, the

    pressure measurement will gradually move towards zero

    as the tube is filled with atmospheric air.

    Once blockage in a cyclone has been ascertained, the

    operator must ensure that the kiln is shutdown,

    thereafter the blockage is removed manually.

    Normally, air lances in appropriate lengths are

    effective tools. Extreme caution must be exercisedduring the clean-out operation.

    NOTE!

    The temperature of the material cakings may be as high

    as 800 C., with attendant risk of sudden outflow of

    hot raw meal, flowing as if it were a liquid.

    Therefore, it is essential that extreme caution andcare is being exercised during the operation, and it is

    advisable that the operators involved are equipped with

    heat-insulated protective suits during the clean-out

    operation.

  • 5/19/2018 ILC Kiln Manual Ed1

    40/70

    PROCESS

    OPERATION

    MANUAL

    Page 40 of 68

    A number of precautionary measures to be taken in a

    cement plant are outlined in a separate instruction

    manual.

    6.2.7 Cakings in the Riser Duct and kiln Inlet

    It is possible to detect major cakings in the riser

    duct and kiln inlet by checking the difference between

    the negative pressures at the kiln outlet and at thelower most cyclone.

    The safety precautions which must be taken during the

    clean-up operation are similar to those stipulated for

    the cyclones.

    Operational experience will show whether the extent and

    locations of potential cakings would make it

    appropriate to equip the installation with additional

    clean-out hatches.

    Also it may be practical to install air shock blasters

    at appropriate locations.

    6.2.8 Kiln Position

    The axial position of the kiln on the supporting

    rollers is monitored by the thrust device. The alarm

    limits must be set as directed in the instruction

    manual for the thrust device.

    The MAX I alarm is a signal instructing the operator to

    undertake inspection of the thrust device and/or the

    position of the supporting rollers.

  • 5/19/2018 ILC Kiln Manual Ed1

    41/70

    PROCESS

    OPERATION

    MANUAL

    Page 41 of 68

    The MAX II alarm automatically stops the kiln drive for

    prevention of damage to the smoke chamber seal, kiln

    hood seal or thrust roller.

    It may be necessary to check the thrust direction of

    the supporting rollers. See separate instruction

    manual.

    In a critical situation, it may be necessary to apply

    oil directly to the supporting rollers if the rollerstend to thrust the kiln upwards, but it is very

    important to ensure that the oil is removed as soon as

    possible following the re-alignment of the supporting

    rollers.

    The lubrication between the supporting rollers and the

    kiln tyre must be provided by means of dry graphite

    lubrication. See separate instruction manual.

    6.2.9 Kiln Lining

    The temperatures in the kiln system are so high that

    most of the system is protected by means of a lining

    which consists of bricks and castable.

    It is a prerequisite for smooth kiln operation that the

    kiln lining is intact. Consequently, proper maintenance

    of the lining is of paramount importance.

    Normally, the lining in the preheater, hot-air duct and

    in most parts of the cooler will have a lifetime of

    several years with no need for replacements.

    However, especially the lining installed in the burning

    zone of the kiln will require more frequent replacement

  • 5/19/2018 ILC Kiln Manual Ed1

    42/70

    PROCESS

    OPERATION

    MANUAL

    Page 42 of 68

    of bricks.

    The exact frequency depends on a range of factors, but,

    generally, replacement is recommended in case the

    thickness of bricks has been reduced to half the

    original size owing to wear.

    Any damage to the lining involves risk that the kiln

    shell will be overheated. Particularly the kiln burning

    zone should be kept under continuous supervision.

    If the kiln shell temperature should rise to 380-400

    C, the affected area must be cooled by means of fans.

    In event of a further rise in temperature, the kiln

    must be shutdown for repair of the lining.

    During operation the condition of the kiln lining can

    be checked by installing a radiation pyrometer

    (scanner) for monitoring of the kiln shell temperature.This alarm level should not exceed 400 C.

    Whenever access to the kiln is possible during a

    shutdown period the opportunity should be taken to

    inspect the lining, so appropriate time schedules for

    replacement or repair can be worked out.

    7.0 INTERLOCKINGS, PROGRAMMING AND CONTROL

    CIRCUITS

    The various motors, machines, dampers and other

    equipment are operated and controlled by the central

    control system. In the following the proposed structure

    of the control system is described seen from the

  • 5/19/2018 ILC Kiln Manual Ed1

    43/70

    PROCESS

    OPERATION

    MANUAL

    Page 43 of 68

    operational and process point of view. A proposal for

    grouping of the motors is given below. The general and

    special rules of interlockings are listed. A survey of

    all process related measurements and their treatment is

    given in section 10.

    Finally the list of control loops is presented.

    7.1 Interlockings

    The detailed interlockings, as programmed, are

    described in the interlocking diagrams, however, main

    philosophy is given below.

    The general rule of operational interlockings is that

    no machine can be started before the subsequent machine

    has been started. Inversely, stop of any machine will

    cause the stop of the machine ahead. This follows the

    process order.

    Protection interlockings like

    - bearing temperature

    - vibrations

    - winding temperature

    - minimum oil level

    - speed monitors

    - skew running

    - maximum material level, etc.

    will stop the machine in question immediately.

    Examples:

    - If the speed monitor of an air sluice does not

    indicate any rotations, then the motor for this air

  • 5/19/2018 ILC Kiln Manual Ed1

    44/70

    PROCESS

    OPERATION

    MANUAL

    Page 44 of 68

    sluice will stop.

    - If the vibration level of the kiln exhaust gas fan is

    high, then the motor of this fan will stop.

    - If the bearing temperature of the clinker breaker is

    above the maximum temperature allowed, then this

    breaker will stop.

    Special interlockings

    The special interlockings will be described in the

    section of programming as well as in the diagrams

    giving the process instrumentation (CAUSE/EFFECT

    DIAGRAMS as described in section 10.).

    In the control system the various motors and machines

    will be arranged in a number of groups for common start

    and stop.

    7.2 Programming

    From the central control room the kiln department can

    be operated by selection of a number of programs and a

    number of direct functions.

    The programs installed in the control system will

    perform the start and stop procedures for the machines

    divided into groups. Further the operation is

    automatically supervised, checking constantly all

    interlockings for operation, protection and safety.

    The direct functions consist of opening and closing the

    dampers and speed control of motors.

  • 5/19/2018 ILC Kiln Manual Ed1

    45/70

    PROCESS

    OPERATION

    MANUAL

    Page 45 of 68

    The following programs are proposed. (Please note that

    the groupings of machines may be carried out

    differently to the proposal, but the main ideas should

    be kept).

    The following programs are proposed:

    1. Blending silo

    2. Kiln feed

    3. Filter fan4. Dust transport

    5. Bag House control

    6. Kiln exhaust gas fan

    7. Gas analyzers

    8. Kiln auxiliaries

    9. Kiln drive

    10. Kiln barring

    11. Kiln burner fans

    12. Kiln burner

    13. Calciner burner14. Clinker transport system

    15. Cooler excess air fan

    16. Cooler drives

    17. Cooler fans

    19. Scanners and cameras

    The following equipment can be operated individually:

    Fan dampers

    Changeover gates and dividing gates

    Position of valves - oil valves and feed valves

    Motors with speed regulation, such as kiln drive and

    grate drives.

    7.3 Comments to Programs

  • 5/19/2018 ILC Kiln Manual Ed1

    46/70

    PROCESS

    OPERATION

    MANUAL

    Page 46 of 68

    For the details of the programming reference is made to

    the separate documentation for the PLC system, however,

    in the following some important notes are pointed out

    in relation to each program. In general all bag filters

    should stop with a minimum delay of 15 minutes to empty

    the system.

    1. Blending Silo

    Machines:

    Blending silo extraction system

    Blower for aeration

    Gate

    Filter

    Conditions to be fulfilled before start:

    The filter, the blowers and the silo extraction

    sequence can be started at any time.

    Conditions to be fulfilled in order to produce:

    No conditions. The extraction sequence will be stopped

    whenever the kiln feed hopper reaches maximum level.

    2. Kiln feed

    Machines:

    Air slide

    Dosing valve

    Bottom Gate, dividing gate

    Blower for aeration of feed bin

    Bucket Elevator

    Bag filter

  • 5/19/2018 ILC Kiln Manual Ed1

    47/70

    PROCESS

    OPERATION

    MANUAL

    Page 47 of 68

    Sampler

    Conditions to be fulfilled before start:

    Filter on top of the homogenizing silo is in operation.

    The dividing gates are in the correct position

    directing the kiln feed or in recirculation mode back

    to the Inverted cone-homogenizing silo.

    Conditions to be fulfilled in order to produce:

    Same as for start:

    However, once the program is running, the operator can

    change the gates so the raw meal is transported towards

    the kiln and Calciner - becoming kiln feed - provided

    the exhaust gas fan are operational.

    If the feed stops (program 2) for more than 30 seconds,

    then the exhaust gas fan must be stopped to prevent

    overheating of the preheater. This interlock can be

    bypassed during heating up before feeding the kiln.

    3. Bag Filter fan

    Machines:

    Filter fan with damper

    Conditions to be fulfilled before start:

    Damper to be closed, and filter inlet temperature lower

    than the maximum allowed.

    Dust transport operational.

    Conditions to be fulfilled in order to produce:

    Filter inlet temperature below the maximum allowed for

    the filter.

    Once program 4 is in operation a certain allowed stop

  • 5/19/2018 ILC Kiln Manual Ed1

    48/70

    PROCESS

    OPERATION

    MANUAL

    Page 48 of 68

    time of program 5 can be allowed before the filter fan

    program 3 will have to be stopped.

    4.Dust transport

    Selection of which way to send the dust:

    1. dust to Blending silo

    2. dust to kiln feed

    Machines:

    Screw conveyor

    Air slide

    Bucket Elevator

    Filter

    Gate

    Conditions to be fulfilled before start:

    For all possible selections, the subsequent transport

    equipment must be in operation and the silo level must

    not have maximum level alarm.

    Conditions to be fulfilled in order to produce:

    Same as for start.

    NOTE, delayed stop for emptying.

    5. Bag filter control

    Machines:

    Filter fan

    Damper

  • 5/19/2018 ILC Kiln Manual Ed1

    49/70

    PROCESS

    OPERATION

    MANUAL

    Page 49 of 68

    Conditions to be fulfilled before start:

    Damper to be closed.

    Conditions to be fulfilled in order to produce.

    None.

    6. Kiln exhaust gas fan

    Machines:

    Fan

    Damper

    Conditions to be fulfilled before start:

    Bag filter fan in operation.

    Preheater outlet temperature lower than MAX I.

    Damper to be closed

    Conditions to be fulfilled in order to produce:

    Bag filter fan in operation.Preheater outlet temperature lower than MAX II.

    The kiln feed - program 2 - has not been stopped for

    more than 30 sec. after having run simultaneously with

    the kiln exhaust fan.

    7. Gas analyzers

    Machines:

    Analyzer

    Pump

    Conditions to be fulfilled before start:

    availability of compressed air and cooling water.

  • 5/19/2018 ILC Kiln Manual Ed1

    50/70

    PROCESS

    OPERATION

    MANUAL

    Page 50 of 68

    Conditions to be fulfilled in order to produce:

    Same as for start.

    8. Kiln Auxiliaries

    Machines:

    Grease pump

    Thrust deviceSpray lubrication

    Cooling fan

    Outlet seal fan

    Conditions to be fulfilled before start:

    None.

    Conditions to be fulfilled in order to produce:

    None.

    9. Kiln Drive

    Machines:

    Main drive with oil pumps

    Conditions to be fulfilled before start:

    Barring disconnected.

    No alarm for kiln position.

    Cooler grate in operation.

    Cooler fans in operation.

    (These interlockings can be bypassed during kiln start-

    up).

    Conditions to be fulfilled in order to produce:

  • 5/19/2018 ILC Kiln Manual Ed1

    51/70

    PROCESS

    OPERATION

    MANUAL

    Page 51 of 68

    Barring disconnected.

    No MAX II alarm for kiln position.

    Cooler grate in operation or not stopped for more than

    3 minute.

    Cooler fans in operation.

    10. Barring

    Machines:

    Barring drive

    Conditions to be fulfilled before start:

    Main kiln drive stopped.

    Conditions to be fulfilled in order to produce:

    Main kiln drive stopped.

    11. Kiln burner fans

    Machines:

    Primary air fan

    Emergency air fan

    Conditions to be fulfilled before start:

    None

    Conditions to be fulfilled in order to produce:

    Once the kiln burner - program 12 - has been put into

    operation, then the emergency fan must start

    automatically when the primary air fan stops.

    12. Kiln burner

  • 5/19/2018 ILC Kiln Manual Ed1

    52/70

    PROCESS

    OPERATION

    MANUAL

    Page 52 of 68

    Machines:

    Oil/Coal supply:

    Pump Station

    Conditions to be fulfilled before start:

    bag filter fan - program 3 - is in operation.

    Kiln exhaust fan - program 6 - are in operation, during

    heating up of the kiln a special interlock permissioncan be given, that a start-up of the burner without

    fans in operation is allowed, however, when the fan

    have been started this special interlocking is

    automatically cancelled.

    Primary air fan in operation - program 11 -.

    Conditions to be fulfilled in order to produce:

    Same as for start up.

    13. Calciner Burner

    Machines:

    Oil/coal supply:

    Pump

    Station

    Conditions to be fulfilled before start:

    Kiln burner in operation - program 12

    Kiln fan in operation - program 6

    Calciner outlet temperature must be above minimum level

    and below MAX II level.

    Kiln feed is on - program 2

  • 5/19/2018 ILC Kiln Manual Ed1

    53/70

    PROCESS

    OPERATION

    MANUAL

    Page 53 of 68

    Conditions to be fulfilled in order to produce:

    Same as for start, however, if the Calciner temperature

    rises above MAX II or the CO level after the preheater

    has been above MAX II (0.9%) for more than 10 seconds,

    then the fuel rate is reduced to minimum level.

    14. Clinker transport system

    Selection to clinker silo

    De-dusting of clinker transport and dust transport

    Machines:

    Deep pan conveyor

    Hammer Crusher

    Air sluices below ESP

    Screw conveyor

    Conditions to be fulfilled before start:

    Clinker storage area must not be full.

    Conditions to be fulfilled in order to produce:

    Same as for start.

    15. Cooler Excess Air Fan

    Machines:

    Fan

    Damper

    Conditions to be fulfilled before start:

    Clinker transport group and cooler dust transport

    should run

  • 5/19/2018 ILC Kiln Manual Ed1

    54/70

    PROCESS

    OPERATION

    MANUAL

    Page 54 of 68

    Conditions to be fulfilled in order to produce:

    Same as for start.

    16. Cooler dedusting unit

    Machines:

    ESP Charging

    Conditions to be fulfilled before start:

    Clinker transport group and cooler dust transport

    should run

    ESP fan in operation.

    Conditions to be fulfilled in order to produce:

    Same as for start.

    17. Cooler drives

    (Please also refer to cooler instruction manual)

    18. Cooler Fans

    (Please also refer to cooler instruction manual)

    19. Scanners and cameras

    Television cameras, monitors and kiln shell scanner can

    be operated separately.

    7.3 Control Loops

    The following control Loops are foreseen.

  • 5/19/2018 ILC Kiln Manual Ed1

    55/70

    PROCESS

    OPERATION

    MANUAL

    Page 55 of 68

    1. The kiln feed is synchronized with the kiln speed.

    2. The Bag-filter fan speed controls the pressure

    measured just after the exhaust gas fan.

    3. The temperature in the top of the lower most cyclone

    controls the fuel supply to the Calciner burner.

    4. The pressure in the kiln firing hood is maintainedby the speed of the cooler excess air fan.

    5. The operator can select between the modes of cross

    bar control

    6. For all cooler fans the measured air flow will be

    controlled by the Fan speed.

    7.4 Cause/effect diagram

    In section 10. cause and effect diagrams are shown. All

    instrumentation related to process parameters are

    listed. The handling and the use of these signals are

    presented.

    8. PREVENTION OF FIRES AND EXPLOSIONS

    8.1 General Precautions

    On no account must, soot non-combustible, unburned exit

    gases be allowed to accumulate in the kiln, the

    cyclones, the flue ducts etc., since this would involve

    a serious risk of explosion or fire.

    Therefore strict adherence to the following rules is

  • 5/19/2018 ILC Kiln Manual Ed1

    56/70

    PROCESS

    OPERATION

    MANUAL

    Page 56 of 68

    needed:

    1) In connection with renewed light-up of the kiln,

    following a temporary shutdown, it must be firmly

    established that the kiln heat (material surface

    temperature) is sufficient to ignite the fuel.

    If the kiln is too cold, the kiln must be lit in the

    normal manner, using the light-up equipment, and, if

    necessary, the light-up nozzle, under procedure similarto that applied during normal heat-up phase prior to

    start-up.

    2) Always ensure that the burner is not operating with

    an air deficiency.

    3) Inject the fuel at sufficient primary air velocity,

    i.e. with a nozzle velocity for the primary air of

    about 180-200 m/s.

    4) Never increase the fuel supply rate too suddenly or

    excessively at any one time. In any case, the draught

    must always be increased first, and the upward

    adjustment of the fuel supply must take place evenly

    and slowly.

    8.2 Precautionary measures relating to the burners

    In the following the interlockings for the burners and

    the gas analyzers are summarised. The main purpose of

    the interlockings is to reduce the risk of any fire or

    explosion. Whenever working with fuels, these risks are

    present. Although measures are taken to prevent the

    dangers, the operator should always observe and act

  • 5/19/2018 ILC Kiln Manual Ed1

    57/70

    PROCESS

    OPERATION

    MANUAL

    Page 57 of 68

    carefully when working with fuels and firing equipment.

    It is therefore an important interlocking, that a

    burner can only operate, if at least one of the gas

    analyzers after the preheater is in operation without

    any unit alarms or without analyzer fault on the CO

    channel.

    Further it is conditional for the calciner burner

    operation that the CO level has not been over MAX II(0.9% CO) for more than a few seconds (less than 10

    seconds). In this case the fuel rate must be reduced to

    minimum automatically.

    If the CO level is above MAX I (0.5% CO) or MAX II

    (0.9% CO), then the operator must take actions to

    reduce this immediately. Depending on the circumstances

    these actions could be either to reduce fuel rate or

    increase draught.

    PROCEDURE FOR GAS ANALYZER TEST MODE

    The analyzer has a digital input for permission to test

    mode. This input must be set before any local test can

    be performed.

    The test permission is selected by the operator in the

    central control room and is automatically deselected

    whenever the analyzer is put into test mode, or if not,

    is deselected after 10 minutes by a timer.

    The test permission for analyzers must be separated in

    three test permissions, one for each analyzer. The test

  • 5/19/2018 ILC Kiln Manual Ed1

    58/70

    PROCESS

    OPERATION

    MANUAL

    Page 58 of 68

    mode must always be clearly indicated to the operator.

    For further safety, test permission should only be

    possible for one analyzer at a time.

    8.3 Fuels

    For precautionary measures to be taken when using fuel

    oil, see separate instruction manual.

    Reference is also made to the regulations of the local

    authorities.

    9 BARRING

    9.1 General Instructions

    If the kiln is stopped while hot, barring of the kiln

    is required to avoid kiln shell deformation.

    Normally, barring should always be restricted to an

    absolute minimum to prevent damage to the lining.

    The hydraulic thrust device and the spray lubrication

    system of the kiln drive must be in operation while

    barring operation is being performed.

    The following guidelines apply to a situation where the

    kiln is stopped in a hot condition and is to be barred:

    1) As long as the kiln is hot, the barring operation

    must not be stopped for more than 10 minutes.

    2) If the axial position of the kiln should cause the

  • 5/19/2018 ILC Kiln Manual Ed1

    59/70

    PROCESS

    OPERATION

    MANUAL

    Page 59 of 68

    alarm to be tripped, then barring must be

    continued until the correct position has been re-

    established.

    3) If the kiln shell is exposed to strong external

    cooling, for example due to heavy rainfall,

    then continuous barring is required.

    9.2 Barring programmes

    The barring programmes are divided into stages of 100

    deg. rotation. This is done to ensure variations in the

    position of the kiln during standstill.

    9.2.1 Barring during drying of the lining before

    initial start-up.

    0 - 24 hours: About 100 degrees every 30 minutes

    24 - 64 hours: About 100 degrees every 15 minutes64 - 72 hours: Continuous barring.

    Keep a close check on the longitudinal expansion of the

    kiln and its position on the supporting rollers during

    the entire period.

    See separate instruction manual for thrust device.

    9.2.2 Barring during normal start of cold-state kiln

    0 - 8 hours: About 100 degrees every 30 minutes

    8 - 16 hours: About 100 degrees every 15 minutes

    16 - 24 hours: Continuous barring.

    Keep a close check on the longitudinal expansion of the

  • 5/19/2018 ILC Kiln Manual Ed1

    60/70

    PROCESS

    OPERATION

    MANUAL

    Page 60 of 68

    kiln and its position on the supporting rollers during

    the entire period.

    See separate instruction manual for thrust device.

    9.2.3 Barring during stoppage and shutdown of the kiln

    0 - 1 hour : About 100 degrees every 10 minutes

    1 - 24 hours: About 100 degrees every 15 minutes

    24 - 48 hours: About 100 degrees every 30 minutes48 - hours: Barring as required, if some of the

    conditions mentioned in subsection 9.1 makes it

    necessary.

    During the final period the kiln must be barred for a

    few minutes, if the axial migration of the kiln exceeds

    the maximum value for normal kiln operation.

    This barring operation is required to prevent damaging

    or possibly rupturing of the thrust roller shaft duringthe kiln tube contraction which still may take place up

    to the 72nd hour.

    Proper graphite lubrication of the supporting roller

    surfaces must be ensured. The graphite blocks must rest

    loosely in their holders so that the pressure against

    the supporting roller surfaces is not hampered.

    To protect the surfaces of the supporting rollers and

    live-rings against damage as the live-ring slides over

    the supporting rollers during the axial movement of the

    kiln, it is essential that the mentioned dry matter

    lubrication is in order.

  • 5/19/2018 ILC Kiln Manual Ed1

    61/70

    PROCESS

    OPERATION

    MANUAL

    Page 61 of 68

    Refractory Dryout Schedule

    0

    100

    200

    300

    400

    500

    600

    700

    800

    900

    73696561575349454137332925211713951

    Hours

    TemperatureDeg.C

    Top Cyclone

    Bottom Cyclon

    24 hr. Preheat Schedule

    0

    100

    200

    300

    400500

    600

    700

    800

    900

    2523222019181615141211109765321

    Hours

    Temperatur

    eDeg.C

    Top Cyclone

    Bottom Cyclon

  • 5/19/2018 ILC Kiln Manual Ed1

    62/70

    PROCESS

    OPERATION

    MANUAL

    Page 62 of 68

    9.3 Braking

    If the barring operation is stopped, the kiln is

    automatically braked and maintained in an arbitrary

    position. Therefore, the kiln may be side heavy; this

    fact must be taken into account when the brake is

    slackened.

    Reference is also made to the instruction manual for

    the barring device.

    10 CAUSE/EFFECT DIAGRAMS, OPERATING PARAMETERS AND

    ALARM LIMITS.

    The following tables are a survey of the expected

    normal operating parameters and the normal alarm

    limits.

    The operating parameters stated are for guidance only

    and apply to the normal, stable operating situation.

    The operating limits stated are meant as guidance for

    start-up. It will be possible to adjust many of these

    with advantage later on in order to make them more

    suitable for the actual operation. Concerning many of

    the alarm limits they too will have to be adjusted

    according to local conditions as factors like the

    lubrication oil selected, the ambient temperature,

    etc., will affect the values.

    The mechanical and/or the electrical departments must,

    in every single case, approve the change and fixing of

    the alarm limits for protection of the machines.

  • 5/19/2018 ILC Kiln Manual Ed1

    63/70

    PROCESS

    OPERATION

    MANUAL

    Page 63 of 68

    Normally, the alarm limits for the operating parameters

    will be the responsibility of the production

    management.

    SEE ALSO INSTRUMENTATION INSTRUCTION MANUAL AS WELL AS

    FLOWSHEET FOR CODES AND INSTRUMENTATION.

    The following process instrumentation/indications arerequired:Notes used in the instrument and alarm table:a: Refer to mechanical and electrical documentation forthe equipment.b: To be set empirically at a level not activating thealarm under normal operating conditions.x: To be evaluated during commissioning.

    Kiln feed

    Unit

    Range

    Exp.

    Value

    Min. 2

    Min. 1

    Max. 1

    Max. 2

    Comments

    Raw mealfeed

    t/h 0-307

    256

    kW ofelevator

    kW a

    Preheater

    Unit

    Range

    Exp.

    Value

    Min. 2

    Min. 1

    Max. 1

    Max. 2

    Comments

  • 5/19/2018 ILC Kiln Manual Ed1

    64/70

    PROCESS

    OPERATION

    MANUAL

    Page 64 of 68

    Unit

    Range

    Exp.

    Value

    Min. 2

    Min. 1

    Max. 1

    Max. 2

    Comments

    Temperature ofgases inthe downcomerduct

    C 0-600

    332 380 450

    Pressurein thedowncomerduct

    mmwg-700to0

    -446

    Temperature ofgases inthe ductafter the1stcyclone

    C 0-600

    334 380 450

    Temperature ofmaterialfrom 1stcyclone

    C 0-600

    329

    Pressurein theductafter the1stcyclone

    mmwg

    -700to0

    -420

    Pressurein bottomof 1stcyclone

    mmwg

    -700to0

    -420

  • 5/19/2018 ILC Kiln Manual Ed1

    65/70

    PROCESS

    OPERATION

    MANUAL

    Page 65 of 68

    Unit

    Range

    Exp.

    Value

    Min. 2

    Min. 1

    Max. 1

    Max. 2

    Comments

    Temperature ofgases intop of 2ndcyclone

    C 0-600

    527

    Temperatu

    re ofmaterialfrom 2ndcyclone

    C 0-600

    522

    Pressurein theductafter the2ndcyclone

    mmwg

    -600to0

    -340

    Pressurein bottom

    of 2ndcyclone

    mmwg

    -600

    to0

    -340

    150

    Temperature ofgases intop of 3rdcyclone

    C 0-1000

    690

    Temperature ofmaterialfrom 3rd

    cyclone

    C 0-1000

    685

    Pressurein top of3rdcyclone

    mmwg

    -600to0

    -295

  • 5/19/2018 ILC Kiln Manual Ed1

    66/70

    PROCESS

    OPERATION

    MANUAL

    Page 66 of 68

    Unit

    Range

    Exp.

    Value

    Min. 2

    Min. 1

    Max. 1

    Max. 2

    Comments

    Pressurein bottomof 3rdcyclone

    mmwg

    -600to0

    -295

    120

    Temperature of

    gases intop of 4thcyclone

    C 0-1000

    821

    Temperature ofmaterialfrom 4thcyclone

    C 0-1000

    811

    Pressurein top of4thcyclone

    mmwg

    -400to0

    -250

    Pressurein bottomof 4thcyclone

    mmwg

    -400to0

    -250

    80

    Temperature ofgases intop of 5thcyclone

    C 0-1200

    890 750 920 980

    Temperature of

    materialfrom 5thcyclone

    C 0-1200

    870

    Pressurein top of5thcyclone

    mmwg

    -400to0

    -200

  • 5/19/2018 ILC Kiln Manual Ed1

    67/70

    PROCESS

    OPERATION

    MANUAL

    Page 67 of 68

    Unit

    Range

    Exp.

    Value

    Min. 2

    Min. 1

    Max. 1

    Max. 2

    Comments

    Pressurein bottomof 5thcyclone

    mmwg

    -400to0

    -200

    60

    Positionof

    dividergateafter 4thcyclone

    % 0-100

    O2 out of5thcyclone

    % 0-10

    3.0

    CO out of5thcyclone.

    ppm 0to20000

    0 Max.1

    5000

    Max.2

    9000

    Max.3

    12000

    O2 out of

    cyclonepreheater

    % 0-10

    3.9

    CO out ofcyclonepreheater

    ppm 0to20000

    0 Max.1

    5000

    Max. 2

    9000

    Max. 3

    12000

    Calciner

    Unit

    Range

    Exp.

    Value

    Min. 2

    Min. 1

    Max. 1

    Max. 2

    Comments

    Temperature oftertiaryair

    C 0-1200

    950

  • 5/19/2018 ILC Kiln Manual Ed1

    68/70

    PROCESS

    OPERATION

    MANUAL

    Page 68 of 68

    Unit

    Range

    Exp.

    Value

    Min. 2

    Min. 1

    Max. 1

    Max. 2

    Comments

    Temperature in thereductionzone

    C 0-1200

    Temperature in

    exit ofcalciner

    C 0-1200

    895 750 820

    Pressureintertiaryair duct

    mmwg

    -200to0

    -100

    Positionofhoistingdamper

    % 0-100

    Coal flowto

    calcinerburner

    t/h 2.0-20

    1.4-

    14.7

    Kiln

    Unit

    Range

    Exp.

    Value

    Min. 2

    Min. 1

    Max. 1

    Max. 2

    Comments

    Kilntorque

    Amp

    Kilnspeed rpm0-5 3.6

    Axialmovementof thekiln

    mm -30-+30

    a a

  • 5/19/2018 ILC Kiln Manual Ed1

    69/70

    PROCESS

    OPERATION

    MANUAL

    Page 69 of 68

    Unit

    Range

    Exp.

    Value

    Min. 2

    Min. 1

    Max. 1

    Max. 2

    Comments

    Pressurein kilninlet

    mmwg

    -100to0

    -30

    Temperature inkiln

    inlet

    C 0to1200

    1080

    O2in kilninlet

    % 0-10

    4.2 1

    CO inkilninlet

    ppm 0-20000

    0 Max.1

    5000

    Max. 2

    9000

    Max. 3

    12000

    NOx inkilninlet

    ppm 0-2000

    Kiln Burner

    Unit

    Range

    Exp.

    Value

    Min. 2

    Min. 1

    Max. 1

    Max. 2

    Comments

    Coal feedto kiln

    t/h 1.3-13.5

    1.0-10.8

    Primaryair fanspeed

    % 0-100

    Power forprimaryair fan

    kW a

    Primaryairpressure

    mmwg

    a

  • 5/19/2018 ILC Kiln Manual Ed1

    70/70

    PROCESS

    OPERATION

    MANUAL

    Page 70 of 68

    Unit

    Range

    Exp.

    Value

    Min. 2

    Min. 1

    Max. 1

    Max. 2

    Comments

    Primaryair flow

    m3/min

    a

    Damperpositionforemergency

    coolingofburner

    open /closed

    closed

    ID Fan

    Unit

    Range

    Exp.

    Value

    Min. 2

    Min. 1

    Max. 1

    Max. 2

    Comments

    Positionof ID fan

    damper

    % 0-100

    100

    Motorpower forID fan

    kW 0-1700

    1072

    Pressureafter IDfan

    mmwg*)

    -30to+30

    -20 0 +20

    ID fanspeed

    % 0-100

    *) + indicate pressure above the atmosphere, - indicatepressure below the atmosphere.