ii ra bill (ivrcl) new revised 07-12-09
TRANSCRIPT
TIRUCHIRAPPALLI CITY CORPORATIONHISTORY OF THE WORK
1 Name of the work :
2 Year : 2008-09
3 Scheme :
4 Estimate Amount :
5 Date of Administrative Sanction :
6 Date of Technical Sanction :
7 Date of Tender : 29-01-2009
8 Date of finalisation of tender : 27-02-2009
9 Date of work order issued : 09-04-2009
10 Execution period (with date) : 06-09-2009 to 31-10-2009
11 Name of the contractor : M/s.IVRCL Infrastructures & Projects Ltd.
12 Completion date as per agreement : 08-04-2011
13 Actual date of completion : -
14 Value of work done :
15 Delayed period : -
16 Whether board provided or not? : -
Trichy Water Supply Improvement Scheme Package III Improvements to water supply in Ariyamangalam and Ponmalaipatty area: Creation of source of collector well - 1 & II, Construction of common sump and laying conveying main from collector I and II to Common
Trichy Water Supply Improvement Scheme Package III
Original - Rs.1774.00 Lakhs Revised - Rs.1965 Lakhs
G.O.Ms.No. 134 MA & WS Department dated 25-09-2007
Total Value - Rs. 27539364/- II RA Bill Value - Rs. 9960099/-
17 : -Area of building / Length of the road / pipe line
/2/
17 If it work executed deparmental : No
18 : ---
19 Nature of executing of work : Contract Agency
20 :
21 :
22 : -
23 :
24 Date of commencement of the work : 9/4/2009
25 Date of completion of work : Work in progress
b. Date of completion as per the agreement : 8/4/2011
26 Explanation of the contractor for the delay :
27 Amount of agreement : 238832445.00
28 Value of work done :
29 :
30 : 06-09-2009 to 11-11-2009
31 :
32 :
33 : -
34 : CC 2nd & Part Bill 30-11-2009
Quote the Corporation Council No. and date of sanctioning
Whether the approval of the council of Contractor, Public work Committed obtained for the execution of work a quote Rs. and Date
MCRMCRMCR
DatedDatedDated
If it is grant work, please quote the G.O. and date of approving the same
Whether outside sanction is obtained for the premium tender or for any condensation for the irregularities committed in the disposal of tenders If so, Corporation Council Resolutions Rs. and Date
Whether the agreement has been executed by the contractor why?
Total Value - Rs. 27539364/- II RA Bill Value - Rs. 9960099/-
Explanation for short work or excess work if the difference excess
Date of measurement by Senior Level Expert, WAPCOS Limited.
Explanation of the Site Engineer for the delay in the case of interval between the column Rs.24 & 29
Date of check - measurement by the Project Engineer WAPCOS Limited.
Explanation of Senior Level Export for the delay in case of the interval between column Rs.24 & 32
Date of Preparation of the part bill & final bill by the Senior Level Export (Public works)
FORM NO. MCF 21
Tiruchirappalli City Corporation No
Date
NAME OF THE CONTRACTOR: Part Bill M.Book Nos :
CC 2nd & Part BillWork Commenced on : Work Completed on : PAGES
09-04-2009 5-09-2009
Dept. CONTRACT BILL
Bills inwardRegisterNo / Date
M/s.IVRCL Infrastructures & Projects Ltd. Chennai.
053/2009-10 056/2009-10 057/2009-10 058/2009-10 059/2009-10
044/2009-10 071/2009-10 072/2009-10 060/2009-10 062/2009-10
1 to 36 1 to 58 1 to 35 1 to 96 1 to 100 1 to 96 1 to 99 1 to 55 1 to 14 1 to 100
Estimate No.
G.O.Ms.No. 134 MA & WS Department dated 25-09-2007
NAME OF WORK : Trichy Water Supply Improvement Scheme Package III Improvements to water supply in Ariyamangalam and Ponmalaipatty area: Creation of source of collector well - 1 & II, Construction of common sump and laying conveying main from collector I and II to Common sump.
Original- ER No 135/2007-08 Revised- ER No 04/2008-09
AppropritationNo & Date
Estimated Amount Rs.
Original - Rs.1774.00 Lakhs Revised - Rs.1965 Lakhs
Abstract PART - II
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
1
87.92 117 M3 10286.64 1/56 87.92 10286.64 0 0.00 TR. No 1
2
1.00 325440 No 325440 2/56 1.00 325440.00 0 0.00 TR. No 2
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
CONSTRUCTION OF COLLECTOR WELL I - 6M INNER DIA
Earthwork excavation above water level in light or sandy or clay soil for collector well including levelling the site -From bed level =69.58m to LSWL 68.08m Ist depth.
Providing RCC 1:1 ½:3 well curb of 6.00M internal dia and 7.90 M outer dia using 20mm HBS for an overall size of 2.0M at outer face and 0.60M at inner face with 150mmx150mmx10mm MS angle cutting edge excluding the cost of reinforcement fabricating and placing the grills in position but including the cost of welding the holding down rods with MS angle centering strutting and shuttering charges compacting with vibrators etc. complete as directed by the Departmental Officers.
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
3
TR. No 3
a) I DEPTH OF 2 M As per GA 14/450.25 4750 M 1187.5 3/56 0.25 1187.50 0 0.00 TR. No 3a
b) II DEPTH OF 2M As per GA 14/452.00 7120 M 14240 3/56 2.00 14240.00 0 0.00 TR. No 3b
c)2.00 11040 M 22080 3/56 2.00 22080.00 0 0.00 TR. No 3c
4
TR. No 4
a)
325.86 4920 M3 1603231.2 4/56 160.02 787298.40 165.84 815932.80 TR. No 4a
Sinking of 6 M inner dia Collector well below water level including all incidental charges such as baling and pumping water use of special tools and plants etc.,complete (a) In light or sandy soil.
III DEPTH OF 2M As per GA 24/46
RCC 1:1½:3 using 20mm HBS for well steining of 0.95M thick for the Collector well of 6.0M inner dia excluding the cost of reinforcement fabricating and placing the grill in position and centering strutting and shuttering but including the cost of virbatio.
Below bed level( upto 1.5m below G.L.) As per GA page 35/53
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
5
TR. No 5
a)
697.78 251 M² 175142.78 4/56 348.62 87503.62 349.16 87639.16 TR. No 5a
6
TR. No 11
a)137.58 5550 Qtl 763569 5/56 75.81 420745.50 61.77 342823.50 TR. No 11a
b) RTS rods Above 16 mm dia.24.17 5410 Qtl 130759.7 5/56 24.17 130759.70 0 0.00 TR. No 11b
7
13.00 34207.50 Nos 444697.5 0.00 0.00 13.00 444697.50 TR. No 13
Centering the soffits of RCC work steining of collector well including the cost of materials and labour charges.Curved surface.
Upto 3.30m height below B.L and above GL. As per GA page 35/53
Supplying fabricating and placing the reinforcement in position including the cost of steel binding wire and all labour charges as directed by the Dept. Officers.
RTS rods Upto 16 mm dia. As per GA page 36/53
Supply delivery and fixing of 350mm dia CI sluice valves confirming to ISI spceification with operating gear rod arrangements for the radial drain IS 14846/2000 (PN-1) (75% Value) As per GA page 35/53
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
8
1224.00 56.25 Nos 68850 0.00 0.00 1224.00 68850.00 TR. No 14
9
905.30 475 M 430017.5 6/56 905.30 430017.50 0 0.00 TR. No 20
10
TR. No 45
Supply delivery and fixing of 350mm dia CI tail piece in the well steining for driving radial pipes (75% Value) As per GA page 35/53
Labour charges for putting bore holes of size 6" to 8" in river bed in sandy and other loose soils using hand boring sets including the cost of hire charges ,coveyance charges of hand boring sets , collection of soil sample at frequent intervals and as directed by the Departmental officers.
CONSTRUCTION OF FOOT BRIDGE FOR COLLECTOR WELL I - 380M
Earthwork excavation above Water Level in light or sandy soil for infiltration wells ,suction wells etc including levelling the site with the initial lead of 10 m and initial lead of 2m etc. complete.
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
a)260.24 117 M3 30448.08 7/56 236.24 27640.08 24 2808.00 TR. No 45a
b)
127.59 M3 93.29 34.30 TR. No 45b
c)1.51 0.00 1.51 TR. No 45c
11
33.00 18700 No 617100 8/56 28.00 523600.00 5 93500.00 TR. No 46
12
TR. No 47
For first depth of 2 m. As per GA page 84/44
For second depth of 2 m (SupplimentalItem) As per GA page 84/44
For Third depth of 2 m (SupplimentalItem) As per GA page 84/44Providing RCC 1:1 ½:3 well curb of 1.25M internal dia and 2.35 M outer dia using 20mm HBS for an overall size of 0.60M at outer face and 0.20M at inner face excluding the cost of reinforcement fabricating and palcing in position etc. complete as directed by Dept. officers. As per GA page 85/44
Sinking of well below water level including all incidental charges using special tools and plants such as air compressors,helmets etc complete including bailing out water (for 1.25 m inner dia. ) etc. as directed by the departmental Officers.
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
a I depth of 2 m. As per GA page 2.45 1290 M 3160.5 8/56 2.45 3160.50 0.00 TR. No 47a
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
b II depth of 2 m. As per GA page 29.20 1930 M 56356 8/56 29.20 56356.00 0.00 TR. No 47b
c III depth of 2 m. As per GA page 49.00 3090 M 151410 8/56 49.00 151410.00 0.00 TR. No 47c
d IV depth of 2 m. As per GA page 34.00 4950 M 168300 8/56 34.00 168300.00 0.00 TR. No 47d
e V depth of 2 m. As per GA page 26.00 7920 M 205920 8/56 26.00 205920.00 0.00 TR. No 47e
f VI depth of 2 m. As per GA page3.20 12670 M 40544 8/56 3.20 40544.00 0.00 TR. No 47f
13
TR. No 48
a)891.00 5660 M3 5043060 10/56 596.20 3374492.00 294.80 1668568.00 TR. No 48a
Reinforced cement concrete 1:1½:3 (one cement, one & half sand, three course aggregate) using 20mm size hard blue granite stone (machine crushed ) excluding cost of reinforcement, fabrication and placing the grills in position centering., strutting, shutttering but including cost of vibration charges , curing finishing etc. complete.as directed by departmental officers.
For well steining-upto 4.5m from GL. Asper GA page 88/44
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
14
33.67 6510 219191.7 0.00 0.00 33.67 219191.70 TR. No 49
15
274.98 662 182036.76 0.00 0.00 274.98 182036.76 TR. No 50
Cement concrete 1:1:2 (one cement, one sand and two aggregate ) for bottom well plugging using 20mm HBS including cost of special tools and plants to inject the CM 1:1 under water and curing (4.5m to 9.0m below G.L.) etc., complete as directed by the Dept. As per GA page 90/44
Supply and filling the foundatiion and basement with clear river sand in layers complying with standard specification including watering and consolidation etc.complete and as directed by Dept. Officers. As per GA page 92/44
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
16
6.25 4160 26000 0.00 0.00 6.25 26000.00 TR. No 51
17
TR. No 52
a)33.36 4920 164131.2 0.00 0.00 33.36 164131.20 TR. No 52a
Top plugging with P.C.C 1:2:4 (one cement, two sand,four course aggregate) using 20mm H.B.G stone including mixing concrete, laying, curing and compacting of concrete etc., complete and as directed by the Dept. Officers.Below bed level up to 1.5 m. As per GA page 92/44
Reinforced cement concrete 1:1½:3 (one cement, one & half sand, three course aggregate) using 20mm size hard blue granite stone (machine crushed) excluding cost of reinforcement, fabrication and placing the grills in position and centering strutting.
Upto 1.5m below GL for capping slab. As per GA page 94/44
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
18
TR. No 53
a)18.26 5660 103351.6 0.00 0.00 18.26 103351.60 TR. No 53a
Reinforced cement concrete 1:1½:3 ( using 20mm size hard blue granite stone (machine crushed) excluding cost of reinforcement, fabrication and placing the grills in position and cost of centering, strutting and shuttering charges but including mixing conc.
For piers-upto 4.5m from GL As per GA page 96/44
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
19
TR. No 55
a Curved surface (0m - 3.3m).TR. No 55a
i3901.49 298 M² 1162644.02 11/56 2624.56 782118.88 1276.93 380525.14
b Round column TR. No 55b
i82.89 298 24701.22 0.00 0.00 82.89 24701.22
Centering for sides and soffits of R.C.C well steining,piers,pier top beam,bed block,main beam and deck slab including strutting upto 3.3 m height using MS sheets of size 90cmx60cm BG10 gauge and stiffend with welded MS angle of size 25mmx25mmx3mm laid over silver oak (country wood) joists of size 10cm x 6.5cm spaced at 90cm c/c and supported by casurina props of 10 cm to 13 cm dia spaced at 75cm c/c complying with standard specification etc. and as directed by the departmental officer.
For well steining and capping slab. As per GA page 93/44
TR. No 55a(i)
0m - 3.3m for circular piers As per GA page 95/44
TR. No 55b(i)
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
ii15.24 319 4861.56 0.00 0.00 15.24 4861.56
20
TR. No 57
a280.44 5550 Qtl 1556442 12/56 178.84 992562.00 101.6 563880.00 TR. No 57a
b55.19 5410 Qtl 298577.9 12/56 9.00 48690.00 46.19 249887.90 TR. No 57b
21
408.00 475 M 193800 12/56 408.00 193800.00 0 0.00 TR. No 60
3.3m - 4.3m for circular piers As per GA page 95/44
TR. No 55b(ii)
Supplying fabricating and placing in position of RTS grills at all heights for reinforcement including cost of steel for all works and labour charges including cost of binding wire etc., complete for all RCC works and as directed by Dept. Officers.
RTS rods upto16 mm. As per GA page 83/44
RTS rods above 16 mm. As per GA page 83/44
Labour charges for putting bore holes of size 100mm dia in river bed in sandy and other loose soils using hand boring sets including the cost of hire charges ,coveyance charges of hand boring sets , collection of soil sample at frequent intervals and as directed by Dept. officers.
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
FOR MATERIALS
22
TR. No 93
b)100.00 10965 M 1096500 13/56 100.00 1096500.00 0.00 TR. No 93b
23
45.22 117 M3 5290.74 14/56 45.22 5290.74 0.00 0.00 TR. No 120
PUMPING MAIN COLLECTOR WELL I TO COMMON SUMP - 600M
Supply and delivery of the following sizes of DI & MS pipes as per standard specification.
700mm DI K7 class pipe (75% value).
CONSTRUCTION OF COLLECTOR WELL II - 6M INNER DIA
Earthwork excavation above water level in light or sandy or clay soil for collector well including levelling the site-From bed level =69.58m to LSWL 68.08m first depth.
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
24
1.00 325440 No 325440 15/56 1.00 325440.00 0.00 0.00 TR. No 121
18
TR. No 123
Providing RCC 1:1½:3 well curb of 6.00M internal dia and 7.90 M outer dia using 20mm HBS for an overall size of 2.0M at outer face and 0.60M at inner face with 150mmx150mmx10mm MS angle cutting edge excluding the cost of reinforcement fabricating and palcing in position but including the cost of welding, the holding down rods with MS angle, centering, shutting, shuttering charges compacting with viberators etc. completed as directed by the departmental officers.
RCC 1:1½:3 using 20mm HBS for well steining of 0.95M thick for the Collector well of 6.0M inner dia excluding the cost of reinforcement fabricating and placing the grill in position, the cost of centering strutting and shuttering but including the cost of viberation charges, curing & finishing etc. and as directed by the departmental officers.
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
a)259.25 4920 M3 1275510 16/56 43.60 214512.00 215.65 1060998.00 TR. No 123a
25
TR. No 124
a)
554.27 251 M² 139121.77 17/56 96.02 24101.02 458.25 115020.75 TR. No 124a
26
TR. No 130
a)105.12 5550 Qtl 583416 18/56 30.08 166944.00 75.04 416472.00 TR. No 130a
b) RTS rods Above 16 mm dia.25.03 5410 Qtl 135412.3 18/56 25.03 135412.30 0.00 0.00 TR. No 130b
Below bed level( upto 1.5m below G.L.). As per page 34/57
Centering the soffits of RCC work steining of collector well including the cost of materials and labour charges.Curved surface.
Upto 3.30m height below B.L and above GL. As per page 31/57
Supplying fabricating and placing the reinforcement in position including the cost of steel binding wire and all labour charges as directed by the Dept. Officers
RTS rods Upto 16 mm dia. As per page 33/57
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
27
10.00 34207.5 No 342075 0.00 0.00 10.00 342075.00 TR. No 132
28
884.50 475 M 420137.5 19/56 884.50 420137.50 0.00 0.00 TR. No 139
Supply delivery and fixing of 350mm dia CI sluice valves confirming to ISI spceification with operating gear rod arrangements for the radial drain IS 14846/2000 (PN-1) (75% Value)
Labour charges for putting bore holes of size 6" to 8" in river bed in sandy and other loose soils using hand boring sets including the cost of hire charges ,coveyance charges of hand boring sets , collection of soil sample at frequent intervals and as directed by the Departmental officers
CONSTRUCTION OF FOOT BRIDGE IN COLLECTOR WELL II - 410M
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
29
TR. No 164
a)279.76 117 M3 32731.92 20/56 160.39 18765.63 119.37 13966.29 TR. No 164a
b)128.09 M3 128.09 TR. No 164b
c)0.87 M3 0.87 TR. No 164c
30
22.00 18720 No 411840 21/56 21.00 393120.00 1.00 18720.00 TR. No 165
Earthwork excavation above Water Level in light or sandy soil for infiltration wells ,suction wells etc including levelling the site with the initial lead of 10 m and initial lift of 2m etc. complete.
For first depth of 2 m. As per page 12/62. (770.89-119.37=651.52)
For second depth of 2 m (Suplimental Item)
For third depth of 2 m (Suplimental Item)
Providing RCC 1:1 ½:3 well curb of 1.25M internal dia and 2.35 M outer dia using 20mm HBS for an overall size of 0.60M at outer face and 0.20M at inner face excluding the cost of reinforcement fabricating and palcing in position etc. complete as directed As per page 68/60
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
31
TR. No 166
a I depth of 2 m. 3.10 1290 M 3999 22/56 3.10 3999.00 0.00 TR. No 166a
b II depth of 2 m. 9.10 1930 M 17563 22/56 9.10 17563.00 0.00 TR. No 166b
c III depth of 2 m. 14.00 3090 M 43260 22/56 14.00 43260.00 0.00 TR. No 166c
d IV depth of 2 m. 6.00 4950 M 29700 22/56 6.00 29700.00 0.00 TR. No 166d
32
TR. No 167
Sinking of well below water level including all incidental charges using special tools and plants such as air compressors,helmets etc complete including bailing out water for 1.25 m inner dia etc as directed by the departmental officers.
Reinforced cement concrete 1:1½:3 (one cement, one & half sand, three course aggregate) using 20mm size hard blue granite stone (machine crushed) excluding cost of reinforcement, fabrication and placing the grills in position centering strutting, shutteri.
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
a)613.48 5660 M3 3472296.8 23/56 175.68 994348.80 437.80 2477948.00 TR. No 167a
33
TR. No 174
a)TR. No 174a
i For well steining and capping slab2441.94 298 M² 727698.12 24/56 703.36 209601.28 1738.58 518096.84
34
TR. No 176
a164.08 5550 Qtl 910644 25/56 62.59 347374.50 101.49 563269.50 TR. No 176a
For well steining-upto 4.5m from GL. As per page 98/59
Centering for sides and soffits of R.C.C well steining,piers,pier top beam,bed block,main beam and deck slab including strutting upto 3.3 mt height using MS sheets of size 90cmx60cm BG10 gauge and stiffend with welded MS angle of size 25mmx25mmx3mm laid .
Curved surface (0 - 3.3m). As per page 97/59
TR. No 174a(i)
Supplying fabricating and placing in position of RTS grills at all heights for reinforcement including cost of steel for all works and labour charges including cost of binding wire etc., complete for all RCC works and as directed by Dept. Officers.
RTS rods upto16 mm. As per page 96/59
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
b6.52 5410 Qtl 35273.2 25/56 6.22 33650.20 0.30 1623.00 TR. No 176b
35
444.00 475 M 210900 26/56 444.00 210900.00 0.00 0.00 TR. No 179
For MATERIALS
36
TR. No 228
b)400.00 14775 M 5910000 27/56 400.00 5910000.00 0.00 0.00 TR. No 228b
TOTAL AMOUNT 30370347.71 19398772.29 10971575.42
Discount 4.61% -1400073.00 -894283.40 -505790.00
RTS rods above 16 mm. As per page 96/59
Labour charges for putting bore holes of size 100 mm dia in river bed in sandy and other loose soils using hand boring sets including the cost of hire charges,coveyance charges of hand boring sets , collection of soil sample at frequent intervals and as
PUMPING MAIN FROM COLLECTOR WELL II TO COMMON SUMP - 1980M
Supply and delivery of the following sizes of DI-K7 & MS pipes as per IS 8329/2000 and including rubber gaskets as per IS 5382/1985 standard specification. As per page 5/59
800mm dia DI K7 class pipe (75% Value)
Description work RATE Rs. PerTotal Previous Measurment
Page Qty Amount Rs. Qty Amount Rs.
Item No
Upto Date Qty
Upto date Value
Since Last Measurment Remarks
(Agreement Item No.)
Total Amount 28970274.71 18504488.89 10465785.42
Deduct : Withheld 5% -1448513.74 -925224.00 -523289.27
Net Amount 27521761 17579265 9942496
Prepared By Checked By Approved By
SLE Project Engineer Team LeaderWapcos, Trichy Wapcos, Trichy Wapcos, Trichy
Counter Signed
Executive Engineer (East) Executive Engineer (West) City EngineerTiruchirappalli City Corporation. Tiruchirappalli City Corporation Tiruchirappalli City Corporation
sin pre upto
0.00 10286.64 10286.64
0.00 335726.64 335726.64
0.00 335726.64 335726.64
0.00 336914.14 336914.14
0.00 351154.14 351154.14
0.00 373234.14 373234.14
0.00 373234.14 373234.14
815932.80 1160532.54 1976465.34
815932.80 1160532.54 1976465.34
903571.96 1248036.16 2151608.12
903571.96 1248036.16 2151608.12
1246395.46 1668781.66 2915177.12
1246395.46 1799541.36 3045936.82
1691092.96 1799541.36 3490634.32
1759942.96 1799541.36 3559484.32
1759942.96 2229558.86 3989501.82
1759942.96 2229558.86 3989501.82
1759942.96 2229558.86 3989501.82
1762750.96 2257198.94 4019949.9
1762750.96 2257198.94 4019949.9
1762750.96 2257198.94 4019949.9
1856250.96 2780798.94 4637049.90
1856250.96 2780798.94 4637049.9
1856250.96 2783959.44 4640210.4
1856250.96 2840315.44 4696566.4
1856250.96 2991725.44 4847976.4
1856250.96 3160025.44 5016276.4
1856250.96 3365945.44 5222196.4
1856250.96 3406489.44 5262740.40
1856250.96 3406489.44 5262740.4
3524818.96 6780981.44 10305800.40
3744010.66 6780981.44 10524992.1
3926047.42 6780981.44 10707028.86
3952047.42 6780981.44 10733028.86
3952047.42 6780981.44 10733028.86
4116178.62 6780981.44 10897160.06
4116178.62 6780981.44 10897160.06
4219530.22 6780981.44 11000511.66
4219530.22 6780981.44 11000511.66
4219530.22 6780981.44 11000511.66
4600055.36 7563100.32 12163155.68
4600055.36 7563100.32 12163155.68
4624756.58 7563100.32 12187856.90
4629618.14 7563100.32 12192718.46
4629618.14 7563100.32 12192718.46
5193498.14 8555662.32 13749160.46
5443386.04 8604352.32 14047738.36
5443386.04 8798152.32 14241538.36
5443386.04 8798152.32 14241538.36
5443386.04 8798152.32 14241538.36
5443386.04 8798152.32 14241538.36
5443386.04 9894652.32 15338038.36
5443386.04 9894652.32 15338038.36
5443386.04 9899943.06 15343329.10
5443386.04 10225383.06 15668769.10
5443386.04 10225383.06 15668769.1
6504384.04 10439895.06 16944279.10
6504384.04 10439895.06 16944279.1
6619404.79 10463996.08 17083400.87
6619404.79 10463996.08 17083400.87
7035876.79 10630940.08 17666816.87
7035876.79 10766352.38 17802229.17
7377951.79 10766352.38 18144304.17
7377951.79 11186489.88 18564441.67
7377951.79 11186489.88 18564441.67
7377951.79 11186489.88 18564441.67
7391918.08 11205255.51 18597173.59
7391918.08 11205255.51 18597173.59
7391918.08 11205255.51 18597173.59
7410638.08 11598375.51 19009013.59
7410638.08 11598375.51 19009013.59
7410638.08 11602374.51 19013012.59
7410638.08 11619937.51 19030575.59
7410638.08 11663197.51 19073835.59
7410638.08 11692897.51 19103535.59
7410638.08 11692897.51 19103535.59
9888586.08 12687246.31 22575832.39
9888586.08 12687246.31 22575832.39
9888586.08 12687246.31 22575832.39
10406682.92 12896847.59 23303530.51
10406682.92 12896847.59 23303530.51
10969952.42 13244222.09 24214174.51
10971575.42 13277872.29 24249447.71
10971575.42 13488772.29 24460347.71
10971575.42 13488772.29 24460347.71
10971575.42 13488772.29 24460347.71
10971575.42 13488772.29 24460347.71
10971575.42 19398772.29 30370347.71
5445857.11 5525718.31
Form No. MCF 26 TIRUCHIRAPPALLI CITY CORPORATION No DateCONTRACTORS' JOURNAL VOUCHER
Dept.: EngineeringName of Contractor Contract Detail M.Book Nos Contract Bill No Date
2nd & Part Bill 30-11-2009
Account Code Account Head Project CodeLink Reference
NarrationType No
1 2 3 4 5 6 7 8 9 10
1 3121/3122 Work in progress 27521761.00
2 4035 Income Tax 2% 198850.00
3 4037 Sales Tax 2% -
4 4037 Surcharge 10% 19885.00
5 Caution Deposit 1% 99425.00
6 Education Cess 3% 6562.00
7 MWF fund 0.3% 29827.00
8 Mob Advance 700000.00
CC 1st & Part Bill 17579265.00
9 4047 Payable 27521761.00 18633814.00 8887947.00
Engineering Department Account Cell
Certified that the bill has been checked and passed for payment of
Rs.....................
after auditing Rs........................... for cost of materials issued
and for other recoveries and they have been posted in the respective Sub-Ledgers.
Total Prepared by Checkmeasuring Folio No Folio No.Budget Officer in Contractors Ledger in ProjectsProvision Ledger
SLEProject Engineer Folio No
Approved by in Projects Ledger
Team LeaderCounter Signed
Folio Noin Contractors Recovery Regr
Accountant Commissioner / Accounts OfficerEE (East) EE (West) City Engineer
M/s. IVRCL Infrastructures &
Projects Ltd.
Trichy Water Supply Improvement Scheme Package III Improvements to water supply in Ariyamangalam and Ponmalaipatty area: Creation of source of collector well - 1 & II, Construction of common sump and laying conveying main from collector I and II to Common
044, 053, 056, 057, 058, 059, 060, 062, 071, 072
Sl. No.
DebitRs.
CreditRs.
Net PaymentRs.
Certified that the bill is in accordance with imasurements recorded in the M.Book and the claim is correct as per agreement. The cost of materials issued and other recovering have been deducted from this bill and posted in following sub-ledgers. The Pay
(Rs.......................................................................................)
Expenditure upto this bill
27521761 9942496
550435.22 351585 198850 198849.92
55043.52 35159.00 19885 19884.99
275218 175793 99425 99425
18164 11602 6562 6562
82565 52738 29827 29827
2100000 1400000 700000 700000
27539653 17579265 9960388 17579265
30621079 19606142 8887946.59