IBM TRIRIGA
Amending lease and then perform adoption process after, 840 schedule before and after adoption is changed
IBM TRIRIGA Pre-Release 10.6.1
APAR Resolution Summary
11/30/2018
NOTE: This document provides guidance for resolving an APAR via TRIRIGA application configuration changes. The APAR will be resolved formally in a supported release of TRIRIGA, the timing of which will be indicated in the APAR record. This document is only intended to serve as an example of how an application developer might configure/modify an existing generally available TRIRIGA Application version to resolve this APAR until a formal supported resolution is released. Implementation details may vary depending on other application customizations already applied in the environment.
2 © Copyright IBM Corporation 2018
Problem Summary When amending a lease and then perform an adoption process after the accounting schedule before
and after adoption from the modification period (amendment period) is not the same.
Solution There are two workflows that need to be updated and 1 new workflow that needs to be created. Please
follow steps described below to resolve this issue.
1. Log in as an admin user and go to Workflow Builder > triContract > -Any-.
2. Search and open the workflow named, “triContract - Subflow - Create System Contract Revision
Log”. Revise the workflow.
3. Scroll toward the end of the workflow, there are 2 existing Trigger Actions, move the “Trigger
triClearCurrentRevisionHidden triContractRevision” task to be above the “Trigger triContinue
triContractRevision” task, as shown in below screenshot.
4. Publish and close the workflow.
3 © Copyright IBM Corporation 2018
5. Log in as an admin user and go to Workflow Builder > triContract > -Any-.
6. Create a new workflow named, “triContract - Synchronous - Get History Contract From Change
Type”.
7. Add a Variable task and set the properties as shown in below screenshot.
8. Add another Variable task and set the properties as shown in below screenshot.
9. Add another Variable task and set the properties as shown in below screenshot.
4 © Copyright IBM Corporation 2018
10. Set the workflow return parameter as shown in the below screenshot.
11. Add a Call Workflow task and set its properties as shown in below screenshot.
12. Add a Switch task and set the condition as shown in below screenshot.
5 © Copyright IBM Corporation 2018
13. Add an Assign Variable Task and set its properties as shown in below screenshot.
14. Publish and close the workflow.
6 © Copyright IBM Corporation 2018
15. Log in as an admin user and go to Workflow Builder > triContract > -Any-.
16. Search and open the workflow named, “triContract - Synchronous - Re-Calculate Fiscal Line
Item Values”. Revise the workflow.
17. Go to the existing Call Workflow task, “Get Latest History Contract” as shown in below
screenshot.
18. Update the task to point to point to the new workflow by setting its properties as shown in
below screenshot.
19. Publish and close the workflow.