i, · i. introduction the south florida water management district is responsible for the permitting...
TRANSCRIPT
I
I..'
I'
I
I
I
I
.1
I
I,
I
I
I
I
I
I
I
I.-
DESIGN OF EXFILTRATION TRENCHES
TO MEET
SFWMD REGULATORY CRITERIA
October 1982
Charles A. Hall, P.E., Director Water Management Division Resource Control Department
South Florida Water Management District
-C-?3-
lIST OF FIGURES
Figure 1 - SFWMD Jurisdictional Boundaries ------------------- 2
Figure 2 - Ideal Condition Test ------------------------------ 10
Figure 3 - Usual Open-hole Test ------------------------------ 12
Figure 4 - 0.0.1. Standard Test ------------------------------ 14
Figure 5 - Falling-head Open-hole Test ----------------------- 16
Figure 6 - Typical Exfiltration Trench ----------------------- 21
-ii-
-C-74-
I
I
I.
I.
I
I
I
I
1
1
I
I
I,
I
I
I
I°
I
TABLE OF CONTENTS
I. Introduction --------------------------------------------- 1
U. SFWMD Trench Design Requirements ------------------------- 3
III. Field Test Procedures ------------------------------------ 6
A. Ideal Condition Test ---------------------------------- 8
B. Usual Condition. Test --------------------------------- g
C. D.O.T. Standard Test --------------------------------- 11
0. Falling-head Test ------------------------------------ 15
IV. Analysis of Test Data ------------------------------------ 17
V. Design of Trenches --------------------------------------- 19
Appendix - Derivation of Equations --------------------------- 23
-C-75-
I. INTRODUCTION
The South Florida Water Management District is responsible for
the permitting of surface water management systems within its
boundaries (see Figure 1) under Part IV of Chapter 373, Florida
Statutes, and Rule Chapter 40E-4. The objective of the permitting
program is to insure that proposed systems will not be harmful
to the water resources of the District and are consistent with
the public interest. Since the deterioration of water quality
is harmful to the water resource, specific Best Management Practices
(BMP) have been.developed to provide for the "treatment" of
storm water prior to discharge.
It is generally felt that total retention of a specific runoff
volume, known as the "first flush", provides, the most desireable
pollutant removal efficiencies. Retention is defined in the
District's "Basis of Review for Surface Water Management Permit
Applications Within the South Florida Water Management
District" as:
"RETENTION" - the prevention of storm runoff from direct
discharge into receiving waters; included as
examples are systems which discharge through
percolation, exfiltration, and evaporation
processes.
-1-
-C-7 6-
I
IS
I
I
I
I, I
I
I
I
I
I
I
I
I
I:;.
1 I-
BEST AVAILABLE COPY
South FIorIda Water
1
i.i;)
-
N
'I'
c .L
r \ j]
'1 * I
.
-. H y 7
t.IQIND
-2-
-C-77-
.,
Since the inception of the District's surface water management
permitting program the most popular retention design technique
utilized is the exfiltratlon trench, which is also referred to
as french drain or seepage trench. Unfortunately, with the wide
usage of the concept also came a wide range of interpretations
and misinterpretations of how to design such systems.
It is felt that a more rigorous treatment of exfiltration
system design is now needed. The purpose of this report is to
present alternative field testing methods and application of the
test results to the final trench design.
II. SFWMD TRENCH DESIGN REQUIREMENTS
The District's "Basis of Review ." document specifies criteria
for the design of exfiltration trench retention systems as follows:
"3.2.2. WATER QUALITY
3.2.2.2. Retention/Detention Design Criteria - retentionand/or
detention in the overall system, including swales, lakes,
canals, greenways, etc., shall be provided for one of the
three following criteria or equivalent combinations
thereof:
-3-
I
a. Wet detention volume shall be provided for the first
Iinch of runoff from the developed project, or the
total runoff from a 3-year, 1-hour rainfall event
Iwhichever is greater. lb. Dry detention volume shall be provided equal to
75 percent of the above amounts computed for wet
detention.
c. Retention volume shall be provided equal to 50
1 percent of the above amounts computed for wet
detention."
I and Section 3.2.2.5:
I"Underground Exflltration Systems
a. Systems shall be designed for the retention volumes
specified in Section 3.2.2.2 above for retention systems,
exfiltrated over one hour for retention purposes,
prior to overflow, and based on test data for the site.
b. Safety factor - 2 minimum
To aid engineers in the design of exfiltration systems an
Iearly "Basis of Review . ." provided some "quick n' dirty"
I
design guides:
"The following procedure nay be used in the design of surface
Iwater management systems utilizing underground exfiltration
systems such as French Drains, etc.
1 a. Systems should preferably have an overflow to a
positive system with a control device, if necessary,
4
I
between the exfiltration system and the outfall pipe.
The overflow or control device should be sized for the
allowable discharge. Based on the geometric properties
of an exfiltration system, the length of the system may
be determined as follows, unless other methods having
scientific validity or local jurisdictional approval
are utilized:
L = 10 150 C A
wtfü h) where, L = Length of system (feet)
C = Runoff coefficient (rational method) A = Contributing area (acres) W = Trench width (feet) h = Average drop per minute in open hole
exfiltratlon test data (Inches) H = Non-saturated trench depth (feet)
b. Based on the geometric properties, the length of
exfiltration systems without overflows may be determined
as follows, unless other methods having scientific
validity or local jurisdictional approval are utilized:
L = 7260CAR W(l0 h + H)
where all terms are the same as in item "a" plus:
H = one hour rainfall to meet local jurisdictional frequency criteria (inches)."
These simple short-cut design tecnniques have been so extensively
utilized, it is felt that more reliable procedures should be developed.
Much reliance has been placed on these formulae with only a light
treatment of the subject of the type of percolation test or use
of test data.
This report will present both field test procedures and application
of test results to trench design in order to meet the above stated
cr1 teria.
-5-
-C-80-
Iii
III. FIELD TEST PROCEDURES
IThe District's criteria states that, "...tests shall he consistent
as to elevation, location, soils, etc. with the system desiqnto
Iwhich the test data will be applied... ." There has been a sub-
stantial amount of confusion in the design community as to what
Ithe District staff intended by this statement:
IThe field test utilized should be of a type which will yield the
desired Information, i.e. percolation ability of the applicable
1 soil stratum.
IPerhaps the most common test utilized was the Health Department
standard septic tank test for obtaining the design percolation rate.
There Is a basic problem with use of the septic tank test. The
problem is that the test is usually run with a hole eighteen (18)
inches deep, whereas the design depth of the exfiltration trench
Iis usually at least five (5) feet deep, and the data generated
may not at all be representative of the hydraulic characteristics
of the deeper strata. Most soil engineering texts recommend that
the permeability of the appropriate soil layers be determined.
Four field test procedures for determining hydraulic conductivity
Iwill be described in the following, all of which should yield the
needed design information. Three of the tests are known ; constant
I(.
-6- I
I
head tests which should be representative of the design condition of
water ponded at the elevation of the inlet. The fourth test is a
falling-head test which should be used in areas of known good
percolation and when difficulty "filling the hole" is encountered.
-7-
-C-82-
I
I,.
A. Ideal Condition Test
IThe "ideal" test be duplicated as procedure would one which
I. many of thedesign conditions as practical. This procedure
would have a test hole "drilled" such'that the bottom of
Ithe hole was at the proposed invert of the exflltration
trench. It would have a perforated casing which would
Iextend from the bottom of the hole up to the proposed top
elevation of the trench, and would have an impermeable
from casing there up to natural ground level (or estimated
I. finished grade level would be better). The test would be
run until in the opinion of the engineer the pumpinn rate stabil-
I izes and remains essentially constant. The field procedure would
be described as follows:
1. Auger a 4 to 9 inch diameter hole to a depth below the
ground surface equivalent to the design depth of trench
I(usually 4 to 6 feet).
I2. Record distance from ground surface to water table
prior to addition of test water.
3. Lower a casing into the hole with perforatiOns in the
Ibottom portion equivalent to the design trench height.
The perforations should be 3/8 inch in diameter and
Ishould be uniformly spaced with not less than 30 perfora-
tions per square foot of pipe surface (RE: FHWA-TS-80-218).
I
I -8-
-C-83-
I
4. Fill hole with water and maintain water level at ground
surface. Record rate of pumping in g.p.m. giving
direct readings from water meter at fixed intervals.
Use one minute intervals or greater, and continue
recording rate of pumping for approximately 10 minutes
following the stabilization of the recorded pumping rate.
Figure 2 shows a cross-section of the test hole with the
appropriate dimensions shown. Also shown is a formula for
relating the field information to the soil hydraulic conductivity.
Further discussion of the interpretation of test data will
be contained in Part IV of this report. Obviously to perform
this test the designer must, to some degree, have already
designed the trench since special casings must be fabricated
in advance which have the proper lengths of perforated and
unperforated sections. Since this is usually n.qt. the case
the next test procedure is the type most commonly performed
and. is hence entitled the 'usual" test.
B. Usual Condition Test
The usual test performed is an open-hole test which is
either un-cased or cased with fully-perforated casing.
The procedure is described as follows:
1. Auguer a 6 to 9 Inch diameter hole to a depth below
the ground surface equivalent to the design depth of
trench (usually 4 to 6 feet).
-9-
-C-84-
I
I. IDEAL CONDITION TEST
NG.
i d 1. IMPERVIOUS CASING
H,
I H2 ii
WATER TABLE Du
PERFORATED CASING
I iDs
"A" - ELEV.
I
4Q IK lTd(4H2Du2Du2+4H2Ds+H2d)
K HYDRAULIC CONDUCTIVITY (CFS/FT.2- FT. HEAD) Q AVERAGE FLOW RATE (CFS)
I d DIAMETER OF TEST HOLE (FEET) H2a DEPTH TO WATER TABLE (FEET)
I Dua UNSATURATED HOLE DEPTH (FEET) D8 SATURATED HOLE DEPTH (FEET)
IELEV. "A" a PROPOSED TRENCH BOTTOM ELEV. H, a AVERAGE HEAD ON UNSATURATED HOLE SURFACE (FT. HEAD)
ID a UNPERFORATED CASING DEPTH (FEET)
10- FIGURE 2
(
-C-85-
5-.
I
2. Recor1 the distance from the ground surface to the water I table prior to the addition of test water.
I 3. If holewalls are, unstable lower screen or fully-
perforated casing into the hole. I
4. Fill hole with water and maintain water level at ground I
surface. Record rate of pumping in g.p.m. giving direct
readings from water meter at fixed intervals of one I minute or greater. Continue recording rate of pumping
for 10 minutes followng the stabilization of the I
recorded pumping rate.
Figure 3 shows a cross-section of the test hole with a
formula relating the hydraulic conductivity to the field
information. The hydraulic conductivity obtained by this method
may be either greater or less than the effective trench hydraulic
conductivity depending upon the relative hydraulic conductivity I of the surface layers. Another test which is quite often used
'is the D.0.T. standard test. I
C. 0.0.1. Standard Test I The Florida Department of Transportation utilizes a standard
test for design of seepage trenches in conjunction with I highway projects. The 0.0.1. test procedure is as follows:
1. Auger a 7 Inch diameter hole to a depth of 10 feet
below normal ground surface.
-C-86-
i
I
Ii
I
I
1
I
I
I
I
I.
I
1
I.
I
I
I
vt
I
I
WA1
USUAL OPEN HOLE TEST
Q
4Q K 1-rd(2H22+ 4H2Ds+ H2d)
K' HYDRAULIC CONDUCTIVITY (CFS/FT.1- FT. HEAD) Q'°STABILIZED" FLOW RATE (CFS) d DIAMETER OF TEST HOLE (FEET) P12 = DEPTH TO WATER TABLE (FEET) Ds SATURATED HOLE DEPTH (FEET) ELEV. 'A" PROPOSED TRENCH BOTTOM ELEV.
AVERAGE HEAD ON UNSATURATED HOLE SURFACE(FT.HEAD)
I2-
- C- 87-
FIGURE 3
2. Record distance from ground surface to water table
prior to addition of test water.
3. Pour 1/8 cubic foot of 1/2 inch diameter gravel in
hole to prevent scouring.
4. Lower a 6 inch diameter perforated 10 gauge aluminum
casing into hole. Casing to be 9 feet in length with
perforations in the bottom 6 feet of the casing.
5. Fill hole with water and maintain water level at ground
surface. Record rate of pumping in g.p.m. giving direct
readings from water meter at fixed intervals. Use one
minute intervals or greater, depending on the hydraulic
conductivity of the soil. Continue recording rate of
pumping for 10 minutes following the stabilization of
the recorded pumping rate.
A schematic cross-section of the D.0.T. test hole is shown in
Figure 4 with a formula which relates the hydraulic conductivity
to the field data. The 0.0.1. does not recommend utilization
of seepage trenches in. areas where this test yields less than
6 g.p.m.
-13-
-C-88-
I
I 1 I
I
I
I
I
1
I
I
I
I
I
I
I
I
I
I
I
1
I
1
I
I
I.
I
I
I
I
I
I
I
I
WA1
D.O.T. STANDARD TEST
FOR H3.O FEET:
K ir(2O.25H2-H 9) K HYDRAULIC CONDUCTIVITY (CF/FT.Z FT. HEAD) Q "STABILIZED" FLOW RATE (CFS) d DIAMETER OF TEST HOLE (FEET) Du UNSATURATED HOLE DEPTH (FEET) D5 SATURATED HOLE DEPTH (FEET) H1 AVERAGE HEAD ON UNSATURATED HOLE SURFACE (FT. HEAD) H2 DEPTH TO WATER TABLE (FEET)
FOR H23.O FEET: 0
K II.192H2
- 14 FIGURE 4
D. Falling-head Test
The falling-héad test is an open-hole test which is either
un-cased or cased with fully-perforated casing. The procedure
is described as follows:
1. Auger a 6 to 9 inch diameter hole to a depth below the
ground surface equivalent to the design depth of the
trench (usually 4 to 6 feet).
2. Record the distance from the ground surface to the water
table prior to the addition of test water.
3. If hole walls are unstable lower screen or fully-perforated
casing into the hole.
4. Fill hole with water and maintain water level at ground
surface. Cease adding water and measure the water level
versus elapsed time in equal time increments, usually
in 15-second increments. Continue measuring water level
until it has dropped at least half the distance to the
water table.
Figure 5 shows a cross-section of the test hole with a formula
relating the hydraulic conductivity to the field information.
-15- -c-go-
I
I...
I
I
I
I.
I
I
I
11
I
I
I
I
I
I
I
I
WAT
FALLING - HEAD OPEN - HOLE TEST
N. G.
dln(Hi/H2) K
(2H1+2H2+4Ds+d)(t2- t1)
K HYDRAULIC CONDUCTIVITY (CFS/FT.2-FT. HEAD) c1DIAMETER OF TEST HOLE (FEET) Hi HEIGHT OF WATER IN HOLE ABOVE WATER TABLE AT TIME,ti H2 HEIGHT OF WATER IN HOLE ABOVE WATER TABLE AT TIME,t2 D3SATURATED HOLE DEPTH (FEET) ELEV. UAU:PROPOSED TRENCH BOTTOM .ELEV. (FT.-NGVD) til f2 TIME, SECONDS
16 FIGLFcE 5 -c-g1-
IV. ANALYSIS OF TEST DATA
In this section actual test data which was compiled during a field
test of the "usual" case will be described and the soil permeability
calculated. The test was performed on a piece of property in
Broward County, Florida. The test hole was 9 Inches In diameter
augered to a depth of 6 feet. A 9 inch diameter by 72 inch long
perforated casing was set In the hole. The depth to the water
table prior, to introduction of test water was 5.3 feet below the
ground. The field data collected during the test Is shown ln
Table 1.
Taking the total flow Into the test hole during the 75 minute
test period and dividing by 75 minutes, since there was no
significant variation in flow during the test, yields an average
flow rate, Q, of 3.46 g.p.m., which is equivalent to 7.71 x 1O cfs.
The diameter of the test hole, 0, was 0.75 feet. The saturated
hole depth, Ds, was equal to the depth of the hole, 6 feet,
minus the depth to the water table, 5.3 feet, which is equal to
0.7 feet.
Utilizing' the formula from Figure 3:
K = 4Q
TTd(2E1 + 4H2D5 + H2d)
K 4ç7.7lx io) '
r(O.75)(2(5.3)+4(5.3)(o.7) + (5.3)(0.75))
K = 1.75 x IO4cfs/ft?ft.head
- 17-
-C-92-
I
I
I
I
I
I
I
I
I
I
I
I.
1
I
I.
I
I
TABLE 1
BROWARD COUNTY - USUAL OPEN-HOLE TEST
Elapsed Time Begin Meter End Meter Flow Q (Minutes) Reading Reading Gallons (G.P.M.)
1 0.0 5.5 5.5 5.5 2 5.5 11.0 5.5 5.5 3 11.0 16.0 5.0 5.0 4 16.0 19.0 3.0 3.0 5 19.0 22.5 3.5 3.5 6 22.5 26.5 4.0 4.0 7 26.5 30.0 3.5 3.5 8 30.0 33.5 3.5 3.5 9 33.5 37.5 4.0 4.0
10 37.5 40.5 3.0 3.0 11 40.5 44.5 4.0 4.0 12 44.5 48.5 4.0 4.0 13 48.5 51.5 3.0 3.0 14 51.5 55.5 4.0 4.0 15 55.5 59.5 4.0 4.0 16 59.5 63.0 3.5 3.5 17 63.0 67.0 4.0 4.0 18 67.0 70.0 3.0 3.0 19 70.0 73.5 3.5 3.5 20 73.5 77.5 4.0 4.0 25 77.5 96.0 18.5 3.7 30 96.0 114.5 18.5 3.7 35 114.5 132.0 17.5 3.5 40 132.0 154.0 22.0 4.4 45 154.0 172.5 18.5 3.7 50 172.5 190.5 18.0 3.6 55 190.5 208.5 18.0 3.6 60 208.5 220.0 11.5 2.3 65 220.0 235.0 15.0 3.0 70 235.0 247.0 12.0 2.4 75 247.0 259.5 12.5 2.5
-18-
-C-93-
V. DESIGN OF TRENCHES
Since the first publ1ction of Volumej, Permit Information Manual
additional consideration has been given to the derivation of an
acceptable exflltration trench design formula. The latest
development is shown on Figure 6 along with the description of
the appropriate parameters. The derivation of this trench sizing
formula Is given in the Appendix along with the derivations of
the formulae used for use with the field testing procedures.
An example of the use of this formula with the data from the
Broward County test site follows:
L= CAR
(1.39 x 1 o)wD
C=O.60
A = 10.0 Acres
R = 2.5 Inches
K = 1.75x 10 CFS/FT.2-FT.HEAD
112= 5.0 Feet (Design Condition)
W = 4.0 Feet
2.5 Feet
b 1.5 Feet
H = + 4.0 Feet
Solving for L gives,
L 1389 feet of 4' x 4' exfiltration trench.
This formula can be used for sizing exfiltration trenches to meet
SFWMD criteria as it is since it already takes into consideration
both a Safety Factor of 2 and the 50% credIt for retention systems
as opposed to detention systems.
-19-
-C-94-
I
For those situations when either: (1) the saturated depth of trench
greater than the non-saturated depth of trench; or (2) the trench
width is greater than two times the total trench depth, the proportional
assumptions for flow out the trench bottom are probably not valid. A
conservative design formula for use in these cases would be: L CAR
IK(2H2Du - Du2 + 2H2Ds) + (1.39 x 104)WDu
As with any design method a good amount of engineering judgement must
Ibe applied for use on site-specific cases.
I
I
II
I
I
I
1
I
I
I
-20-
-C-95-
I
TYPICAL EXFILTRATION TRENCH
, 1.*..::.: ': I9-I 12 INCHES tBACKFILL
6INCHES PIPE COVER H2 TRENCH UNSATURATED
MINIMUM
12 INCHES PERFORATED Du DEPTH
MINIMUM PIPE DIAMETER
12 INCHES OARSE RO MINIMUM PIPE BED
TRENCH WIDTH
CAR
L: .K(H2w$-2H2Duu2+2H2Ds)(I.39xIo4)wDu
La LENGTH OF TRENCH REQUIRED (FEET)
Ca RUNOFF COEFFICIENT (RATIONAL RUNOFF METHO .Aa CONTRIBUTING AREA (ACRES)
R: ONE-HOUR DESIGN RAINFALL (INCHES)
W=TRENCH WIDTH (FEET) HYDRAULIC CONDUCTIVITY (CFS/FT. - FT.HEAD)
H2 DEPTH TO WATER TABLE(FEET)
Du: NON-SATURATED TRENCH DEPTH (FEET)
Ds* SATURATED TRENCH DEPTH (FEET)
-21- FIGURE 6 -C-96-
I
REFERENCES
.1. Bouwer, Herman, Groundwater Hydrology, McGraw-Hill Book Company, I 1978.
2. Harr, M.E., Groundwater and Seepage, McGraw-Hill Book Company,
I 1962.
3. Hwang, Ned H.C. , Fundamentals of Hydraulic Eninj, Prentice- i Hall, Inc., 1981.
U 4. Raudkivi, A.H., 8nd Callander, R.A., Analysis of Groundwater Flow,
John Wiley & Sons, 1976.
I. 5. Measuring Saturated Hydraulic Conductivity of Soils, Special PublTcation SP-SW-0262, American Sodety of Agricultural EngIneers, 1962.
6. 0rainage Manual, A Water Resources Technical Publication, U.S. Department of the Interior, Bureau of Reclamation, 1978.
I 7. Underground Disposal of Storm Water Runoff, Design Guidelines Manual, U.S. Department ofTransportation, Federal Highway Administration, FHWA-TS-80-218, 1980.
I
I
I
I
I
I
I,
I -22-
-C-97-
I
APPENDIX
DERIVATION OF EQUATIONS
-23-
-C-98-
I
I.
I
I
I
I
I
I
I
I
I
I
I
I
IT
I..-
I. IDEAL CONDITION TEST
K S1H1+S2H2 (EQ. I)
WHERE, K HYDRAULIC CONDUCTIVITY (CFS/FT.2-FT. HEAD) Q AVERAGE FLOW RATE (CFS) S1 UNSATURATED SURFACE AREA OF HOLE (FT,2) S2 SATURATED SURFACE AREA OF HOLE .(FT.2) H1 AVERAGE HEAD ON UNSATURATED SURFACE AREA (FT. HEAD) I12 HEAD ON SATURATED SURFACE AREA (FT. HEAD)
FROM FIGURE 2. D1d
S2 Ds1Td+Td2 H1 H2Du
SUBSTITUTING INTO EQUATION I.
K [(Dulld)(H2 Du)+(D51Td+Ttd2) (H2)I
40 K
11d(4H2Du 2Du244H2Ds4H2d)
-24- -C-99-
(EQ. 2) (EQ. 3) (EQ. 4)
(EQ. 5)
Q K (EQ I)
S1 H1+S2H2
FROM FIGURE 3:
H2 DEPTH TO WATER TABLE (FT.) Os SATURATED DEPTH OF HOLE (FT.) d DIAMETER OF HOLE (FT.) S1 H2lrd (EQ. 2) S2 D1rd f lrd2 (EQ. 3)
H, H2 (EQ. 4)
SUBSTITUTING INTO EQUATION Q
K ((Hjnd)(H2)+(D1Td+4-,d2)(H2)j 4Q
K 1Td(2H*4H2Ds+H2d)
(EQ. 5)
-25- -c-100-
I
.. D.OT. STANDARD TESL
EQ. I) 1 K
S1H1+S2H2
I
FROM FIGURE I DUZ
d I H2
Id:=
FOR H2 > 3.0
4:
UNSATURATED DEPTH, OF HOLE (FT.) SATURATED DEPTH OF HOLE (FT.) DIAMETER OF HOLE (FT.) DEPTH TO WATER TABLE (FT.) H2 - 3.0 0.0-H2 0.50
FEET:
H1 H2- D= H2+ 1.5 (EQ. 2) S1 D1Td(H2_3.0)11d (EQ. 3) I S2 : Dsird+rd2: (IO.0-H2),id*r1d2 (EQ. 4)
SUBSTITUTING INTO EQUATION I: K [(H2- 3.0),id( H2+I,5)1 ((JO. 0.- H2)TTdt4rd2)H2 J
I K 40
i,2O.25 H2- H- 9) (EQ. 5)
FOR H23.0 FEET
1 SH
IWHERE ; S 7lpd + 1rd2 d: 0.50 FT.
I
I
I
I
I
Q
(71.rd+1,d2)H2
K (EQ. 6) 11.192 H2
-26- -c-1o1-
Q KSH (EQ. I)
WHERE 0 AVERAGE FLOW RATE (CFS) K HYDRAULIC CONDUCTIVITY (CFS/FT.2-FT. HEAD) S SURFACE AREA OF HOLE (FT.2) H HEAD ON SURFACE AREA OF HOLE (FT,HEAD)
A P
1rd2 dH 0 4dt
Q AVERAGE FLOW RATE (CFS) d DIAMETER OF HOLE (FEET) dH CHANGE IN HEAD (FT. HEAD) dt = CHANGE IN TIME (SECONDS)
EQUATING EQ. I AND EQ. 2 2 dH
KSH
4KS dH dt= lid H
H2 2 4KS dt - C
5 'rrd
H1
4KS - t ) InCH /H
rrd2 2 I I 2
K -rrd2ln(H1/H2) 4S(t2- t1)
S SURFACE SAREA OF HOLE, EFFECTIVE (FT.2)
S i'rdL-I-ird2
L 2)+ Ds (SEE FIGURE 5)
S
-27- -C-102-
(EQ. 2)
(EQ. 3)
(EQ. 4)
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
rYd2 n(H,/H2) K 4[[(HD] j2 ](t2-t1)
-. dlri(H1/H2)
K (2H1 + 2H2+ 4Ds d)(t2-t1)
-28-
-c-i 03-
(EQ. 5)
V. TRENCH LENGTH EQUATION
A. VOLUME OF RUNOFF
43560 CAR( 363O CAR (El.3) I2
WHERE
C RATIONAL METHOD RUNOFF COEFFICIENT A : DRAINAGE AREA (ACRES) N ONET HOUR RAINFALL. (INCHES)
B. VOLuME OF STORAGE IN TRENCH:
EASED ON 5QO/ VOIDS: 0.50 WDuL (FT. 3)
WHERE
vV TRENCH WIDTH (FT.) Du UNSATURATED TRENCH DEPTH (FT.)
TRENCH LENGTH (FT.)
(.;. VOlUME EXFILTRATED:
(EQ. I)
(EQ. 2)
KH1WL(3600) (EQ. 3)
WHERE
VBOT VOLUME EXFILTRATED OUT BOTTOM IN I HOUR (FT.3) K HYDRAULIC CONDUCTIVITY (CFS/FT.2_ FT. HEAD) H2. HEAD ON SATURATED SURFACE (FT. HEAD)
AND: V..lDE LKS1H + KS2H) 3600 (EQ. 4)
WHERE,
VSIDE VOLUME EXFILTRATED OUT A SIDE IN I HOUR (Fl.3)
S1 UNSATURATED TRENCH SURFACE (Fl.2) S2 SATURATED TRENCH SURFACE (FT.2) H1 AVERAGE HEAD ON UNSATURATED SURFACE (FT. HEAD) H2 . HEAD ON SATURATED SURFACE (FT. HEAD)
-29- -C-i 04-
I IFROM FIGURE 6 WE SEE
S1z DuL I S2
H2-2Du
I THEN;
[KDULHZ- Du)+ KDsLH2]3600 iVsIOE
VSIDE 3600 KL(H2Du ü2 H 2DS) (EQ. 5)
ISETTING THE VOLUME OF RUNOFF EQUAL TO THE VOLUME EXFILTRATED: Q V8 + 2VSIDE
I3OCAR O.5OWDuL + 3600KH2WL t 2{36OOKL(H2Du4Du + H2 Ds )1 - - I SOLVING '. 4 - THIS EQUATION FOR L: -
L I. 00834 CAR (EQ. 6)
IK(H2W+ 2N2Du- 0u2 2H2DS)+
HOWEVER, CONSIDERING THE EFFECT ON THE ANSWER AND THE NORMAL VARIATIONS IN ESTIMA1ION OF C WE HAVE SIMPLIFIED THE EQUATION TO READ:
CAR L (EQ.7) K(H2W 2H2Du-Du2 + 2H2D)+ (I,39x O4)WDU I
WHERE
LENGTH OF TRENCH REQUIRED (FT.) IL C RATIONAL METHOD RUNOFF COEFFICIENT 4 DRAINAGE AREA (ACRES) R ONEHOUR RAINFALL (INCHES) I H2 DEPTH TO WATER TABLE (FT.) W TRENCH WIDTH (FT.) Du UNSATURATED TRENCH DEPTH (FT.)
IDs SATURATED TRENCH DEPTH (FT.)
I I I I
-30- -C-los-
FOR A DISTRICT AVERAGE 3-YEAR, I-HOUR RAINFALL OF
2.5 U4CHES THIS EQUATIOJ BECOMES, SIMPLY:
2.5 CA L
(EQ. 8)
K(H2W+ 2H2Du- Du2+ 2H2D) +(I.39x 104)WDu
-31-
-C-106-