I-5 North Coast Corridor Project Phase 1 (CM/GC)

Upload: others

Post on 26-Jul-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services

I-5 North Coast Corridor Project Phase 1 (CM/GC)

Page 2: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services

Flatiron-Skanska-Stacy and Witbeck (FSSW)

FSSW Joint Venture is comprised of nationally recognized contractors:

• Flatiron West, Inc.

• Skanska USA Civil West California District Inc.

• Stacy and Witbeck, Inc.

Page 3: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services

Flatiron-Skanska-Stacy and Witbeck (FSSW)

• Local Contractors

• Leading CMGC experienced firms

• Significant CALTRANS and SANDAG contracting experience

• Dedicated to supporting small, local and minority business

Page 4: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services

North Coast Corridor Project Overview

• 14 Miles of HOV between L. Santa Fe and Hwy 78 • New Sound and Retaining Walls • Bridge Reconstruction • Pavement Widening and Reconstruction • 4 Miles of LOSSAN Double Track • Rail Bridge replacement • Lagoon Enhancement

Page 5: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services

5

NCC PHASE 1

Page 6: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services
Page 7: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services
Page 8: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services
Page 9: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services
Page 10: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services
Page 11: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services
Page 12: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services
Page 13: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services

• CM/GC team selected based on qualifications and experience

• CM/GC consults with Owner during the design phase

• CM/GC evaluates costs, schedule and constructability

• Multiple segment GMPs issued for bid

What is CM/GC

Page 14: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services

Minority Goals

• I-5 Highway and Lagoon Work: DBE Goal for Pre-Construction

Services: 5.1 percent

• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent

• DBE Goals for Construction Services will be determined near

completion of Pre-Construction Services

Page 15: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services

Potential Opportunities Construction Phase

• Articulated Concrete Block • GRE Wall Materials • Quality Control • Asphalt Paving • Grind Existing Concrete Pavement • Railroad Signals • Biological Monitoring • Ground Anchors and Soil Nails • Railroad Track Materials • Bridge Concrete Barrier • Guardrail • Reinforcing Steel • Bridge Demolition • Habitat Restoration • Revegetation and Planting • Channel Lining • Hydrographic Surveys • Rip Rap • CIDH Pile • Jack and Bore • Roadside Signs • Clear and Grub • Joint Seal • Roadway Concrete Barrier • Cold Plane Asphalt • Landscape and Irrigation • Shotcrete • Concrete Supply • Masonry • Slope Protection • Construction Area Signs • Minor Concrete • Striping • Driven Pile • Miscellaneous Metal • Survey • Electrical • Miscellaneous Iron and Steel • SWPPP • Environmental Compliance Officer • Overhead Signs • Transparent Soundwalls • Erosion Control • Pipe Supply

Page 16: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services

Assistance to DBE/UDBE/SBE Firms

• FSSW is committed to helping Caltrans and SANDAG meet/exceed its overall U/DBE goals

• Work packages will be broken down into economically feasible portions of work

• FSSW is available to assist subcontractors in obtaining bonding, lines of credit, and insurance as required

• Project website to facilitate communication of project opportunities and events

Page 17: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services

PROJECT WEBSITE – i5northcoast.com

Page 18: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services

REGISTER ON THE WEBSITE TO STAY INFORMED

Page 19: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services

DBE RESOURCES AND WORKSHOPS

Page 20: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services

Contact Information

Flatiron-Skanska-Stacy and Witbeck, a Joint Venture (FSSW) 1770 La Costa Meadows Drive San Marcos, CA 92078 Email: [email protected] Phone: (760) 916-9151 FAX: (760) 471-4860

Page 21: I-5 North Coast Corridor Project Phase 1 (CM/GC) Outreach Presentation.pdf• LOSSAN Rail Work: UDBE Goal for Pre-Construction: 5.1 percent • DBE Goals for Construction Services

Questions ????