Page 1: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

HYDRO

NEPAL POWER INVESTMENT SUMMIT, KATHMANDU, JANUARY 27, 2018

ALEXANDER BIHLMAYER

LOW HEAD

HYDROPOWER SOLUTIONS

© Nepal Power Investment Summit 2018

Page 2: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

• 06.09.1967

• Technical University in Graz, Austria:

• Master (DI) Mech. Engineering & Business Administration

• Johannes Kepler University Linz, Austria

• M.Sc. in Innovation Management

• Married, 2 children

• Since 1995 VOEST ALPINE MCE resp. VA - TECH

• Since 2006 part of Andritz Group

• Since 2007 Vice President of Business Development

• Since 2016 also Managing Director of ANDRITZ HYDRO Myanmar

ALEXANDER BIHLMAYER

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 20182

[email protected]

© Nepal Power Investment Summit 2018

Page 3: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

01 KEY CONSIDERATIONS FOR CHOOSING LOW HEAD HPP SOLUTIONS

02 BOUNDARY CONDITIONS AND APPLICATION RANGE

03 PROJECT EXAMPLES AND PLANT REFERENCES

04 KEY SELECTION CRITERIA AND PROJECT DEVELOPMENT ASPECTS

05 CONCLUSIONS

CHAPTER OVERVIEW

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 20183 © Nepal Power Investment Summit 2018

Page 4: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

KEY CONSIDERATIONS

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 20184

Needs of HPP Developers ANDRITZ Low Head HPP Solutions

1. Maximum Energy Yield • Higher hydraulic efficiency due to better streamlined horizontal water

flow -> higher annual energy output

2. Operational Flexibility • Possibility of operation at larger head variations

3. Low Construction Cost • Shallower setting –> less excavation -> less civil engineering and

construction costs (up to 30% cost savings for powerhouse)

• Use of existing non-hydro dams -> HYDROMATRIX

• Shorter erection schedules

4. a. Low Environmental Impact

b. Fish Friendliness

c. Ecological safety

• Small powerhouse footprint -> easier integration into landscape

• Fish friendly runner design

• Oil-less runner hub

5. Easy & Low Cost Maintenance • Abrasion and cavitation easily manageable

• Easy accessibility to Turbine parts

© Nepal Power Investment Summit 2018

Page 5: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

OIL FREE HUB -

KEEPING THE WATER CLEAN

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 20185

Conventional Hub Design

• “Oil-filled hub” inside hub pressure higher than outside

• In case of seal failure the oil will leak out of the hub

“Oil Free Hub” Design

• Special blade and piston rod seals and composite bearings

• Special coating and hub filling

• Safely prevents any oil from leaking into the river

© Nepal Power Investment Summit 2018

Page 6: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

• 749 installed units in operation

• Over 80 years of experience

• Approx. 12,800 MW installed

• Over 70% market share for large BULB units

• Largest direct driven BULB turbine

7,700 mm runner diameter (Racine / USA)

• Highest unit output 76.55 MW (Jirau / Brazil)

LOW HEAD HYDROPOWER BULB TURBINES

WORLD LEADING TECHNOLOGY

/ PRESENTATION TITLE / © BY ANDRITZ HYDRO GMBH 20186 © Nepal Power Investment Summit 2018

Page 7: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

CHOOSING THE RIGHT TECHNOLOGY

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 20187

Bulb turbines (mid size to large size diameters)

Small Axial Turbine (Compact Bulb)

Bevel Gear and Belt Driven Bulb Turbine

HYDROMATRIX® and StrafloMatrixTM

Proper Assessment Process is Crucial

LO

W H

EA

D

AP

PL

ICA

TIO

N

Complex decision process

Multitude of available technologies

Overlapping operation ranges of different technologies

Many decision criteria

© Nepal Power Investment Summit 2018

Page 8: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

01

02 BOUNDARY CONDITIONS AND APPLICATION RANGE

03 PROJECT EXAMPLES AND PLANT REFERENCES

04 KEY SELECTION CRITERIA AND PROJECT DEVELOPMENT ASPECTS

05 CONCLUSIONS

CHAPTER OVERVIEW

8

KEY CONSIDERATIONS FOR CHOOSING LOW HEAD HPP SOLUTIONS

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 2018© Nepal Power Investment Summit 2018

Page 9: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

OPERATING RANGE

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 20189

Head: 2-70 m

Discharge: 5 – 500 m3s

Output: 50 kW – 76 MW

© Nepal Power Investment Summit 2018

Page 10: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

10

LOW HEAD “SMALL” HYDROPOWERTurbine Types

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 2018

Net Head (m)

Dis

ch

arg

e (

ltr.

/s)

Compact Axial

Compact Axial Bulb

Belt Driven BulbBevel Gear Bulb

Hydromatrix

Head: 2-35 m

Discharge: 5 – 100 m3/s

Output: 50 kW – 10 MW

© Nepal Power Investment Summit 2018

Page 11: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

BOUNDARY CONDITIONS

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 201812

Hydraulic Conditions

Site Conditions

Economical Conditions

Environmental Conditions

Electrical Boundary

Conditions

© Nepal Power Investment Summit 2018

Page 12: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

• Structured and iterative assessment process using site

assessment tool

• Step 1: Technical feasibility check

• Step 2: Economic viability check

• Considers all listed boundary conditions

• Eliminates non-viable solutions

• Suggests feasible technical solutions

• Optimized plant performance and, construction schedule

• Considers innovative design options

SITE ASSESSMENT PROCESS

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 201813 © Nepal Power Investment Summit 2018

Page 13: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

01 KEY CONSIDERATIONS FOR CHOOSING LOW HEAD HPP SOLUTIONS

02 BOUNDARY CONDITIONS AND APPLICATION RANGE

03 PROJECT EXAMPLES AND PLANT REFERENCES

04 KEY SELECTION CRITERIA AND PROJECT DEVELOPMENT ASPECTS

05 CONCLUSIONS

CHAPTER OVERVIEW

14 / NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 2018© Nepal Power Investment Summit 2018

Page 14: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

CLIENT : POSCO E&C

• 2 Bulb Turbine units, H =11.28 m, 21.09 MW each

• Contract Year: 2013

• ANDRITZ HYDRO supported POSCO in the design of

intake area to optimize inflow conditions

• CFD Analysis

• Civil Design recommendation

• Support was crucial for optimizing energy revenues

CHI KHE / VIETNAM -

PLANT OPTIMIZATION

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 201815

CFD Model

© Nepal Power Investment Summit 2018

Page 15: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

New Plant at Greenfield Site

• 3 Bevel Gear Bulb Turbines

• Gross Head: 5.77 m

• Plant Output: 5.35 MW

Selection Criteria:

• Fast project implementation

• Rapid mechanical site assembly

• Economical solution with LV generator

YEOJU / KOREA -

OPTIMIZING CONSTRUCTION SCHEDULE

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 201816 © Nepal Power Investment Summit 2018

Page 16: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

Greenfield Application at existing weir

Originally: large dam with Bulb Turbines

Alternative: 2 HPP Stages with 90 HYDROMATRIX Units

• Gross Head : 5 - 7.5 m

• Unit Output : 534 – 1003 kW

• Total Output : 54 MW

• Annual Energy : 250 GWh

ASHTA I AND II / ALBANIA -

INNOVATIVE PLANT DESIGN

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 201817

2-3 Bulb 90 HM

E&M cost $$ $$$

Civil Cost $$$ $

Construction risk $$$ $$

O&M $$ $

© Nepal Power Investment Summit 2018

Page 17: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

01 KEY CONSIDERATIONS FOR CHOOSING LOW HEAD HPP SOLUTIONS

02 BOUNDARY CONDITIONS AND APPLICATION RANGE

03 PROJECT EXAMPLES AND PLANT REFERENCES

04 KEY SELECTION CRITERIA AND PROJECT DEVELOPMENT ASPECTS

05 CONCLUSIONS

CHAPTER OVERVIEW

18 / NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 2018© Nepal Power Investment Summit 2018

Page 18: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

LARGE and COMPACT HYDRO Applications

• New plant (greenfield site) with good geological conditions

• Wide operating range

• No restrictions to grid requirements

• No space restrictions allowing river barrage with spillway

and adjacent powerhouse

HYDROMATRIX Application

• Best for existing structures or multi-purpose dams requiring

small footprint

• Mid- to high river discharges with small head fluctuations

• Greenfield sites with problematic geological conditions

• Special flood / discharge requirements

SELECTION CRITERIA CONVENTIONAL BULB

VERSUS HYDROMATRIX

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 201819 © Nepal Power Investment Summit 2018

Page 19: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

PROJECT DEVELOPMENT

AND WHAT ANDRITZ CAN OFFER

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 201820

Equity IRR / Energy Tariff

Construction Cost

Construction Schedule

Financing Condition

Land Compensation & Other Cost

Energy Generation

Support we can offer:

Hydraulic Layout

Optimization

Plant Design & Construction

Methodology

Construction cost input &

project cost validation

Planning and Structuring

Project Financing

Raise of Equity

Financial Modeling

© Nepal Power Investment Summit 2018

Page 20: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

01 KEY CONSIDERATIONS FOR CHOOSING LOW HEAD HPP SOLUTIONS

02 BOUNDARY CONDITIONS AND APPLICATION RANGE

03 PROJECT EXAMPLES AND PLANT REFERENCES

04 KEY SELECTION CRITERIA AND PROJECT DEVELOPMENT ASPECTS

05 CONCLUSIONS

CHAPTER OVERVIEW

21 / NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 2018© Nepal Power Investment Summit 2018

Page 21: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

CONCLUSIONS

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 201822

Let us help making your projects a success !

• Low Head Hydropower Technologies offer High Energy Yields, Low

Construction Cost and Risk and Environmental Safety

• ANDRITZ has extensive Know-How based on 8 decades of experience

and 750 installed units

• ANDRITZ can help you throughout the development process:

• Assessing your site conditions and development needs

• Choosing the best technology for your particular site conditions

• Assisting in technical layout, project cost and scheduling and

financial engineering

© Nepal Power Investment Summit 2018

Page 22: HYDRO LOW HEAD HYDROPOWER SOLUTIONS · 2018. 2. 12. · KEY CONSIDERATIONS 4 / NEPAL INVESTMENT SUMMIT 2018 ... • Considers innovative design options SITE ASSESSMENT PROCESS

23

Thank You

धन्यवाद

/ NEPAL INVESTMENT SUMMIT 2018 – LOW HEAD HYDROPOWER SOLUTIONS © BY ANDRITZ HYDRO GMBH 2018© Nepal Power Investment Summit 2018