hvdc terminal station

28
HVDC TRANSMISSION H-HIGH V-VOLTAGE D-DIRECT C-CURRENT 1

Upload: maka27

Post on 26-Sep-2015

25 views

Category:

Documents


3 download

DESCRIPTION

A description of HVDC Terminals Station and equipment installed in AC and DC yard

TRANSCRIPT

  • HVDC

    TRANSMISSION

    H-HIGH

    V-VOLTAGE

    D-DIRECT

    C-CURRENT

    1

  • WHY HVDC ?

    BULK POWER TRANSMISSION WITHLOWER LINE LOSSES AS NO REACTIVE POWER TRANSFER TAKES PLACE

    CONNECT TWO ASYNCHRONOUS SYSTEM. PROVIDES SYSTEM STABILITY.

    CONTROLABILITY OF POWER FLOW AT HIGH SPEED.

    LESS RIGHT OF WAY FOR TRANSMISSION LINES.

    NO CONTRIBUTION TO SHORT CIRCUIT LEVEL OF THE AC BUS CONNECTED.

    NO CHARGING CURRENT TO DIMINISH THE USEFUL CAPACITY OF THE LINE.

    DISTANCE IS NOT LIMITED BY STABILITY POINT OF VIEW.

    2

  • BREAKEVEN DISTANCE FOR HVDC

    DC LINE COST

    DC TERMINAL COST

    AC LINE COST

    AC TERMINAL COST

    EXPENDITURE /

    COST

    DISTANCE

    BREAKEVEN

    POINT

    BREAKEVEN POINT FOR HVDC TRANSMISSION IS

    ABOVE 700KMS

    3

  • CONFIGURATION

    NON CONTROLLABLE VALVE

    CONTROLLABLE VALVE

    NON CONTROLLABLE VALVE GROUP

    CONTROLLABLE VALVE GROUP

    4

  • TYPES OF CONVERTER BRIDGES

    6-PULSE CONVERTER

    BRIDGE

    12- PULSE CONVERTER

    BRIDGE / TWO 6PULSE BRIDGES

    CONNECTED IN SERIES

    5

  • BACK -TO-BACK This is application where two AC systems to be connected are physically in same substation and no transmission line or cable is required.This is used for interconnection between asynchronous Power System networks.

    TRANSMISSION BETWEEN TWO SUBSTATION.

    This is for bulk power transfer through dc line or cable from one Substation to another which are geographically far away from each other.

    MULTITERMINAL SYSTEM

    More than two HVDC Substation, geographically separated are connected to each other by same transmission line then it is multiterminal system.

    PARALLEL MULTITERMINAL SYSTEM

    If one or more converters are connected at same voltage level then system is parallel multiterminal.Here voltage remains same but the current capacity increases.

    SERIES MULTITERMINAL SYSTEM

    If one or more converters are connected in series then system is series multiterminal.Here voltage increases.

    UNIT CONNECTION

    This is scheme when generator is directly connected to the converter transformer of the rectifier so that generated power is directly fed into dc line

    Different types HVDC Converter Bridge Arrangements

    6

  • MONOPOLAR GROUND CONNECTION

    BIPOLAR CONNECTION

    TYPES OF CONNECTIONS OF HVDC CONVERTER BRIDGE

    7

  • MONOPOLAR METALLIC RETURN

    8

    RECTIFIER INVERTER

    RECTIFIER INVERTER

    POLE-1

    POLE-2

    MRTB

    RECTIFIER INVERTER

    RECTIFIER INVERTER

    POLE-1

    POLE-2

    MRTB

    GRTS

    GRTS

    c:\ V.B.Bhandarkar

  • 9

    1 3 5

    4 6 2

    1 3 5

    4 6 2 15 3

    2 6 4

    2 6 4

    5 3 1

    PRINCIPLE OF WORKING

  • CHANDRAPUR PADHE HVDC

    PROJECT

    FEATURES:

    A. BIPOLE PROJECT

    B. TRANSMISSION VOLTAGE 500KV

    C. POWER CARRYING CAPACITY 1500 MW OR 750MW /POLE.

    D. OVERLOAD CAPACITY : 1650 MW FOR 2HRS AMBIENT ABOVE 33C . 2200 MW FOR 5 SECS AMBIENT BELOW 33C .

    E. TYPE OF THRISTOR VALVE QUARAPULE VALVE.

    F. TYPE OF CONDUCTOR -QUARAPULE CONDUCTOR/POLE.

    G. NO.OF FILTERS/STATION-4NOS.

    H. FILTER MVAR CAPACITY /STATION-800MVAR.

    I. LINE LENGTH 753 KM.

    J. INTERSTATION COMMUNICATION AND COMMUNICATION BETWEEN LD,KALWA THROUGH OPTICAL FIBRE

    10

  • Static Ud/Id Characterstics

    11

    Io(rectifier)Io(inv erter)

    Current Margin

    DC Voltage

    DC Current

    c:\ V.B.Bhandarkar

  • 12 pulse bridge with three phase transformer connected

    12

    DCCT

    DCCT

    To control

    system

    To

    control

    system

    DC voltage

    divider

    DC voltage

    divider

    Smoothing

    reactor

    c:\ V.B.Bhandarkar

  • PRINCIPLE OF POWER TRANSFER BETWEEN TWO CONVERTER STATIONS

    13

    I=(V1-V2)/R

    V1V2

    RECTIFIER INVERTER

    TRANSMISSION LINE

    RESISTANCE (R)

    CURRENT

    (I)

    P=V2*I

    10V9V

    RECTIFIER INVERTER

    TRANSMISSION LINE

    RESISTANCE

    (R=1OHMS)

    CURRENT

    (I)

    I=(10-9)/1

    =1AMP

    P=9*1=9W

    129V

    RECTIFIER INVERTER

    TRANSMISSION LINE

    RESISTANCE

    (R=1OHMS)

    CURRENT

    (I)

    I=(12-9)/1

    =3AMP

    P=9*3=27W

    c:\ V.B.Bhandarkar

  • AC SIDE VALVE HALL DC SIDE

    A) AC FILTERS A)THYRISTOR VALVES A)DC FILTERS

    B) CONVERTER BREAKERS

    B)DC BUS ARRESTORS B)DC BREAKER (METALLIC RETURN TRANSFER BREAKER, GROUND RETURN TRANSFER SWITCH,NEUTRAL BUS SWITCH)

    C) MEASURING EQUIPMENTS

    C)VALVE COOLING SYSTEM

    C) SMOOTHING REACTOR

    D) CONVERTER TRANSFORMERS

    D)DC CTs, DC VOLTAGE DIVIDERS.

    14

    CONVERTER

    TRANSFORMER

    AC SIDE

    DC SIDE

    VALVE

    HALL

    CONVERTER

    BREAKERAC FILTER

    DC BUS

    ARRESTOR

    DC

    FIL

    TE

    R

    DC VOLTAGE

    DIVIDER

    DC CT

    DC LINE

    ISOLATOR

    NBS

    c:\ V.B.Bhandarkar

  • AC SIDE EQUIPMENTS AC Side mainly Constitutes of

    1)Ac filters: They serve two purpose

    A) They offer low impedance path to the harmonics which travel on AC side generated during the conversion process.

    B)Filters constitutes of R,L&C .These filter caters part of capacitive MVAR to the AC Bus which helps in boosting the system voltage.

    Harmonics Generated are:

    i)Harmonics of the order of h=2 to 5 due to voltage imbalance caused by firing angle and transformer commutation inductance.

    ii)h=Kn1 order Harmonics are generated on AC side of Converter where K is a value dependent on 6 or 12 pulse Bridge and n=1,2,

    Switching of the Ac filters through Circuits Breakers are done by

    Reactive Voltage Controller depending on the DC power flow through

    the link.

    15

    U

    (a) (b) (c)

    Single Tuned Filter Double Tuned Filter

    HP-12 HP-3 HP-24/36

  • AC SIDE EQUIPMENTS 2) Converter breakers: Breakers generally SF6 are used for catering AC

    supply to the Converter Transformer. In Bipolar Projects sometimes it is required that only one Converter Breaker caters load to both poles depending on the type of Bus bar arrangements .In such cases Converter Breakers of high current carrying capacity are employed s. Also Circuit Breakers are employed for Switching in and out of the AC Filters.

    3) Measuring Equipments: Equipments like CVTs are installed for measurement of bus voltages which useful in for control of power on HVDC link. CTs installed in AC yard as well as Filter area are employed for protection of AC Bus and Filters respectively.

    4) Converter Transformers: This is one of the key equipments in HVDC link.AC supply is fed to the Converter through the transformer .As the name suggests the transformer is connected to the converter. The secondary or the valve winding of the Transformer is directly connected to valve through either wall mounted bushing or the bushings of the transformer are protruding inside the valve hall and are connected to the valve. The secondary of the converter transformer is carrying AC as well as DC valve current through it. The transformers may be of following type in case of 12- pulse converters:-

    a) 3phase

    i) 3phase 3 winding transformer 1 unit/pole.

    ii) 3phase 2 winding transformer 2 units/pole.

    b) 1 phase

    i) 1phase 3 winding transformer 3units/pole.

    ii)1phase 2winding transformer 6units/pole.

    16

  • CONVERTER TRANSFORMER

    17

    .

    3A

    3B

    A

    B1 B2

    2A

    2B

    1PHASE THREE WINDING CONVERTER TRANSFORMER

    PRIMARY

    WINDING

    SECONDARY

    WINDING 1

    SECONDARY

    WINDING 2

    .

    .

    .

    ....

    c:\ V.B.Bhandarkar

  • CONVERTER TRANSFORMER

    12 -PULSE CONVERTER FED BY THREE PHASE TRANSFORMER

    18

  • VALVE HALL EQUIPMENTS 1) Thyristor Valves: Thyristor valves are heart of HVDC .These valves

    are air insulated , water cooled and suspended in controlled enviroment. Previously the thyristor valves where erected on ground but nowadays they are suspended to meet the seismic requirements. The 12-pulse bridge consist of 3 nos. quadruple valve. Each quadruple valve is connected to one phase. One valve consists of no. of thyristors connected in series depending on the rating of the thyristor. Each thyristor is equipped with damping circuit for dv/dt protection, series connected reactor for di/dt protection for group of thyristor and thyristor control unit for the firing as well as for status monitoring of thyristor .

    Configuration for Chandrapur Padghe project:

    3 nos. Quadruple valve

    1 valve consist of 16 modules

    1 module consist of 6 thyristors

    1 valve consist of 96 thyristors

    Each phase quadruple valve consist of 384 thyristor

    One pole converter consist of 1152 thyristor

    Series connected thyristor

    Fine Water cooled valves.

    Each thyristor of blocking voltage 7kv ,1700amp DC.

    19

  • VALVE HALL EQUIPMENTS

    2) Fine Water Cooling system For Converter Valves:

    Dissipation of losses in the form of heat from Thyristor Valves.

    Fine water / Demineralised water used for heat dissipation. Few percent of water routed through water treatment circuit.

    Temperature, Conductivity and leakage is monitored.

    20

  • DC SIDE EQUIPMENTS DC Side mainly constitutes: 1)DC filters:-The harmonics generated on DC side are of the order of h=kn where k=6 or 12 depending on the type of converter 6 or 12 pulse. These harmonics result in current harmonic in DC line. As no. of harmonics increases the amplitude of the harmonics decreases. 2)DC Switches/Breakers :- DC side Switches are basically High speed isolator which connect the neutral bus to earth electrode line or metallic return path or station ground .They divert/isolate the dc current in event of any fault on DC side. They do not perform the function of current breaking. There are 4 types of DC Switches: A) Neutral Bus Switch (NBS): This DC Switch performs the function of connecting the the converter to the neutral bus. In event of any fault on the neutral bus the NBS isolates the neutral bus and the converter after the operation of respective protection. B) Neutral Bus Grounding Switch (NBGS): This Switch provides path for local / station grounding in event of breakdown on electrode line or any maintenance on electrode line or on Metallic return transfer breaker during bipolar balanced condition . C)Metallic return transfer Breaker (MRTB):-This Switch is used to commutate the current from ground return path to metallic return path. In this type of transfer .The current that is commutated from Ground path to metallic path is near about 70 t0 80 percent of pole current due to difference in the resistance offered by these two paths. Hence Special Arrangement is adopted for current quenching from Ground to metallic path which shown in figure on page 21. D) Ground return transfer Switch (GRTS) :The GRTS is used to commutate current from metallic return to ground return The maximum DC current that is to be commutated in this case is only 20 to 30 percent.

    21

  • DC SIDE EQUIPMENTS

    3) DC Smoothing Reactor: Smoothing Reactor is the first equipment connected in series on DC side i.e. HV side .As the name suggest it is for Smooth ripple free DC and also limits the sudden change in DC current during fault on DC line or DC bus. The reactor are generally air insulated or oil filled smoothing reactor. At low DC voltage air insulated smoothing reactor are used but for high voltage oil insulated smoothing reactor is used. Specification of Smoothing reactors in Chapad Project: Inductance (L): 365mH Rated Voltage : 500KV DC Rated current 1700 amp DC

    22

    Arrangement for MRTB

    BREAKER

    CONTACTS

    SPARK GAP

    CAPACITOR

    NON-LINEAR

    RESISTORc:\ V.B.Bhandarkar

  • DC SIDE EQUIPMENTS 4) DC MEASURING DEVICES: Unlike AC side , measurement are also to be carried out on DC side of voltage and current. Following are used to carry out the measurement : A)DC Voltage Divider:-This is used to carry out the measurement of DC voltage on Line side and neutral side. As shown in figure voltage Across H-L is transmitted upto control room via screened cable where another small Voltage divider is installed .The final voltage received from line side Divider is for 500kv is 5v DC and for neutral side the ratio is for 50kv it is 2v DC. Accordingly from the measured dc voltage the actual voltage on line is fed to control system .

    23

    .

    .

    .

    HV

    R1

    R2F

    H

    L

    E

    c:\ V.B.Bhandarkar

  • DC SIDE EQUIPMENTS B) DC CT(Zero Flux CT): On Ac side the Current measured is carried out by AC Current Transformer, but the measurement of DC current is not possible with normal CT.Hence DC CT is used for the measurement of current on DC side . DC CT is a DC Current Transducer or it is also called Zero Flux CT. This Transducer just like normal CT only difference is that an electronic circuit is connected in the secondary circuit which detects the static field / flux developed by the DC current flowing in the primary. This circuit gives input to the Power Amplifier which injects current in the secondary .This secondary current nullifies the field / flux produced by the primary and the output is in the form of voltage drop measured across a resistor in secondary ckt. Measurement Ratio of DC CT is 1500A / 2V.

    24

    Magneticfeild

    detection

    circuit

    PowerAmplifier

    OutputAmplifier

    I1

    I2

    K U2=k*I2

    C:\ V.B.Bhandarkar

  • Quadruple Converter Valves

    Quadruple

    valve

    Double valve

    Single valve

    25

  • ELECTRODE

    LINE

    ELECTRODE STATION

    EARTH ELECTRODE STATION

    26

    Electrode Station:-

    In HVDC system the terminal which is formed to be a neutral is not grounded locally. The reason behind this is that the DC corrodes and destroys the metal structures , earthmats,etc. very fast. Hence the earthing in done in earth electrode station geographically away from the converter station in a remote place in the periphery of 20 -30 kms .The current flowing through earth electrode line reaches to the electrode station from where it takes the path to the earth through various electrodes which are buried inside the earth about 3 to 3 mtrs deep.

    ELECTRODE BURIED INSIDE EARTH

  • 27

  • 28

    THANK YOU