hon’ble cm conducted review for prioritized projects...
TRANSCRIPT
Page 1 of 7
Review of Prioritized Projects
Hon’ble CM conducted Review for Prioritized Projects
RECORD OF DISCUSSION
Date Monday, 2nd
July 2018
Time 3pm to 5:45pm
Agenda Progress review on Prioritized projects by Hon’ble Chief Minister, A.P
Venue Conference room, AP Secretariat, Velagapudi.
Attendees
Shri. D. Uma Maheswara Rao, Hon’ble Minister, WRD
Shri G Sai Prasad. Principle secretary to Hon’ble CM.
Shri. Shashi Bhushan Kumar, Secretary, WRD
Shri. Rajsekhar Budithi – Spl. Chief Secretary (FAC), Agriculture
Smt. Rekha Rani – Commissioner, R&R
Shri M. Venkateswara Rao, EnC, WRD
District collectors
Forest department
Ground water department & APSRAC
Chief Engineers and officials from AP WRD
M/s Vassar Labs
Consultants to APWRD
Page 2 of 7
# Project / Topic Gist of discussions Action to be
taken by Timeline
1 Overall status
Overall status of 55 prioritized projects.
Projects inaugurated: 9 nos.
Projects ready for inauguration: 5 nos.
Projects in progress: 41 nos.
For information -
2 Chintalapudi LIS
CE, DGS – Dowlaiswaram briefed project status to Hon’ble CM.
Hon’ble CM advised EnC WRD to issue month-wise water requirement
targets to the project and instructed WRD and various agencies to
complete project within stipulated timelines to ensure water lifting in
current season.
Hon’ble CM reinstated that the project does not make a business case
unless water is lifted in current season, as Polavaram shall supply water
through gravity by next monsoon.
Secretary, WRD informed Hon’ble CM that a review meeting is planned
on and before 5th July’18 regarding progress and issues to be resolved
for timely completion of Chintalapudi pump house and canal up-to RMC,
along with WRD officials, District administration and agency.
EnC, WRD
CE, DGS -
Dowlaiswaram
EnC, WRD to issue
monthly water
requirement to
Chintalapudi project.
CE, DGS
Dowlaiswaram to
come up with a
revised action plan
for Chintalapudi
review meeting on
5th July’18
3 Adavipalli reservoir
and lift scheme
CE, Tirupathi informed Hon’ble CM that agency has requested for
extension of reservoir completion date by 15 days (instead of 30th
June’18). To ensure that there is no further slippage, 50% of BG
submitted by the agency was sent for encashment.
Hon’ble CM instructed CE, Tiruapthi to ensure that project is completed
by 15th July’18
CE, Tirupathi
Ensure completion
of Adavipalli
reservoir by 15th
July’18
Page 3 of 7
# Project / Topic Gist of discussions Action to be
taken by Timeline
4 Kuppam Branch
Canal
District collector, Chittoor informed Hon’ble CM that 117.32 Km canal
excavation was completed as on 31st May’18 and the status remains
same till date which says that no excavation was carried out for the last
one month though most of LA issues were resolve.
Hon’ble CM instructed the agency to meet on 4th July’18 with action plan
for project completion by 30th July’18
Agency,
Kuppam Branch
Canal
Meet Hon’ble CM
on 4th July’18 with
revised action plan.
5 Nellore & Sangam
Barrage
Hon’ble CM interacted with the agency of Nellore barrage and instructed
for timely completion of works. Agency to give weekly updates during
review meeting on status of works and action plan for completion of
project.
CE, Tirupathi briefed Hon’ble CM on status of Sangam barrage. It was
discussed that 38 nos. rafts out of 42 nos. are completed and WRD is
striving for completion of balance four rafts by 30th July’18.
CE, Tirupathi
Ensuring completion
of Nellore barrage
and Sangam barrage
by 31st Aug’18
6 Mallemadugu
District collector, Chittoor informed Hon’ble CM that Forest department
is claiming for 990 acres instead of 750 acres due to less suitability of
land for vegetation. Permission from CMO is requested for handing over
of additional 240 acres.
Hon’ble CM advised DC, Chittoor to proceed with handing over of
additional land to forest department, since the land being handed over is
less suitable to grow forest and also in the interest of project.
DC, Chittoor
Proceed with
handing over of
extra 240 acres of
land to forest
department
7 Balaji reservoir
District collector, Chittoor informed Hon’ble CM that 81 acres of forest
land is being cultivated by encroachers for more than 30 years.
DC, Chittoor requested for clearance from Hon’ble to pay compensation
for vacating lands without any issues
DC, Chittoor
Proceed with
compensation for 81
acres of land in
forest area,
Page 4 of 7
# Project / Topic Gist of discussions Action to be
taken by Timeline
Hon’ble CM advised DC, Chittoor to proceed with compensation
payment to encroachers since they are dependent on the land for more
than 3 decades.
cultivated by
encroachers
8
Stage II forest
clearances at state
level authorities
Forest department officials requested for release of INR 17.7 Cr for
compensatory afforestation at Chintalpudi. Secretary WRD informed
Forest department that payment shall be cleared at the earliest.
Secretary, WRD advised all APWRD officials to note that Stage II forest
clearances can be issued at state level in case of linear projects. He
informed that this is an important update that can help in expediting
forest clearances for irrigation projects.
For information -
9
Tender finalization for
Lifting of water from
Jeedipalli Reservoir
to Bhairavanithippa
Project.
Secretary, WRD instructed CE, Ananthapuram that package 2 tenders
for Bhairavanithippa Project shall be finalized at the earliest. Also, it was
discussed that a package-wise clear status shall be presented in the
weekly review meeting with Hon’ble CM.
Hon’ble CM instructed WRD to take necessary measures for completion
of project within an year instead of 1.5 years duration mentioned in the
bid document.
For information -
10
Community Lift cum
Drip Irrigation Project,
Uravakonda
CE, Anantapuram briefed Hon’ble CM that project serves 50,000 acres
of land and costs INR 985 Cr. Hon’ble CM instructed WRD to expedite
project works and ensure completion within 12 months. It was also
discussed that CLDI, Uravakonda is pilot case and shall have all advanced
drip irrigation techniques, methodologies and modern equipment for
enhancing benefit cost ratio and save more water to encourage more
such projects.
For information -
Page 5 of 7
# Project / Topic Gist of discussions Action to be
taken by Timeline
11 Land acquisition for
Gandikota
Commissioner, R&R informed Hon’ble CM that revised list of
beneficiaries shall be received by 10th July’18. Hon’ble CM instructed
district administration and RR authorities to ensure that timely
completion of R&R activity to facilitate water storage.
For information -
12
GNSS Ph-II up to
Kodur in Kadapa Dist.
CE, Kadapa briefed package-wise status to Hon’ble CM. It was
discussed that WRD officials, JC and DFO to discuss and come up with
a clear cut package wise action plan.
CE, Kadapa
JC, Kadapa
DFO, Kadapa
Package wise action
plan for GNSS Ph-II
by 13th July’18
13 Veligonda Project
Secretary, WRD instructed CE, Ongole on the immediate action plan and
letter to be submitted for clearing bottlenecks. Hon’ble CM advised CE,
Ongole to take immediate action to clear road blocks for project progress
and resume works.
CE, Ongole
Take necessary
action to resume
tunneling works at
Veligonda project.
14
Yerram Chinnapoli
Reddy Korisapadu LIS
Hon’ble CM instructed WRD to proceed with crop compensations and
clear bottlenecks in the interest of project. For information -
15
Tenders for
Vykuntapuram and
Godavari-Penna link
Pahse I
CE, KDS, Vijayawada informed Hon’ble CM that tenders for Construction
of new barrage (10 TMC) across Krishna river near Vykuntapuram (V)
shall be released by 6th July’18 and that of Interlinking Of Godavari –
Penna Rivers Phase-1 shall be released by 10th July’18
CE, KDS,
Vijayawada
Tenders for
Vykuntapuram
project by 6th
July’18
Tenders for
Godavari-Penna link
Phase I by 10th
July’18
16
High Level Canal
from Hiramandalam
Reservoir to
Itchapuram
CE, (North Coast), Visakhapatnam informed Hon’ble CM that DPR shall
be completed by 31st July’18 and tenders shall be released by 15
th
Aug’18
CE (North
Coast),
Visakhapatnam
DPR for HLC from
Hiremandamalm by
31st July’18
Page 6 of 7
# Project / Topic Gist of discussions Action to be
taken by Timeline
17
Taraka Rama Thirtha
Sagaram Reservoir
Project
CE, (North Coast), Visakhapatnam briefed Hon’ble CM on LA and R&R
issues. It was discussed that clearance for 11 acres of Reserve Forest
land shall be expedited to execute tunnel works.
Hon’ble CM instructed CE, (North Coast), Visakhapatnam to come up
with a time bound program by 13th July’18
CE, (North
Coast),
Visakhapatnam
Submission of time
bound program
during review
meeting on 13th
July’18
18
Modernization of
Thotapalli Old Canal
System
CE, (North Coast), Visakhapatnam informed Hon’ble CM that tenders
for Modernization of Thotapalli Old Canal System shall be released by
7th July’18
CE, (North
Coast),
Visakhapatnam
Releasing of
tenders by 7th
July’18
19 Water Conservation
Drive
Hon’ble CM reviewed activity wise progress of 139 days water
conservation drive / Jala Samrakshana Udhyamam. It was advised that
WRD shall take up balance works in regular Neeru-Pragathi program.
For information. -
20
Micro Irrigation and
holistic approach on
water management
Department of Micro Irrigation informed Hon’ble CM that 31,000 ha of
land shall be taken up in micro irrigation by 15th July’18 from Chittoor and
Kadapa districts.
Hon’ble CM advised that focus shall on areas with ground water below
20m and there shall be a holistic approach in Ground Water
Management, Micro Irrigation, water supply from Major & Medium
irrigation projects and utilization of rain guns for optimal productivity.
For information -
21
Action plan by
Agriculture
department
Department of Agriculture briefed Hon’ble CM on various activities taken
up for improvement of crop productivity. It was also discussed that
12,000 no. of rain guns are positioned in 437 Mandals for optimal
utilization in Karif & Rabi seasons.
Agriculture
Department
Integrated action
plan shall be
presented during
review meeting on
13th July’18
Page 7 of 7
# Project / Topic Gist of discussions Action to be
taken by Timeline
Hon’ble CM instructed Agriculture department to present integrated
action plan by during review meeting on 13th
July’18
22 AP WRIMS
M/s Vassar Labs informed Hon’ble CM that a model with capability to
forecast water inflows shall be presented during review meeting on 13th
July’18, to help better understand the water resources for upcoming
seasons in the state and plan crops accordingly.
M/s Vassar
Labs
Presenting water
inflows forecasting
model by 13th
July’18
23 Upcoming review
meeting
Hon’ble CM announced that he shall be back from international travel on
11th July’18 and review meeting for 2
nd week of July shall be planned on
13th July’18 tentatively.
For information -
Encl.: Annexure 1 (Brief status of 55 prioritized projects as on 2nd July’18)
Sl no. Project Major Issue / Current statusTarget Date of project
completionInaugurated projects
1 Purushotha Patnam LIS Inaugurated on 15th Aug 2017 -
2Construction of Anicut across Sarada River
Inaugurated on 6th Sept 2017 -
3 Mutchumarri LIS Inaugurated on 8th Sept 2017 -
4 Kandaleru Left Canal – Lift Scheme Inaugurated on 12th Nov 2017 -
5 Gandikota – CBR Lifts Inaugurated on 3rd Jan 2018 -
6 Siddapuram Lift Irrigation Scheme Inaugurated on 7th Jan 2018 -
7 Modernisation of Yerracalva Inaugurated on 8th Jan 2018 -
8Formation of Pogonda Reservoir in West Godavari
Inaugurated on 19th Feb 2018 -
9 SH-31 Road Work (GNSS Phase I) Inaugurated on 6th June 2018 -
Projects ready for Inauguration
10 Pedapalem LI Scheme on Krishna River Ready for inauguration -
11 Chinasana LI Scheme on VLMC Ready for inauguration -
12 Owk Tunnel (GNSS Phase I) Ready for inauguration -
13Gorakallu Balancing Reservoir (Sri Narasimharaya Sagar)
Ready for inauguration -
14 Pulikanuma LIS Ready for inauguration -
ANNEXURE I Status of 55 prioritized projects as on 2 July 2018
Page 1 of 7
Sl no. Project Major Issue / Current statusTarget Date of project
completion
ANNEXURE I Status of 55 prioritized projects as on 2 July 2018
Projects in progress under purview of CE, Tirupathi
15Adavipalli Reservoir (HNSS Phase-II) & Adavipalli Lift (Peddamandyam lift on Main canal)
Reservoir : Gates erection in progress. Agency requested 15 days extension for completion (Revised completion date - 15th July 2018). It is proposed to encash 50% of BG as penalty to avoid further delays .
Lift scheme : Pump house upto M.F.L level completed. Roof erection in progress.Pumps & motors erection in process.
Reservoir by 15-July-18Lift scheme by 31-July-
18
16 Kuppam Branch Canal (HNSS Phase II)
Part A :From Km. 0.00 to Km 39.225 (up to II lift) : Pump house erection in progress
Part B : Work in progress in 3.487 Km and work to be tackled in 1.15 Km. 38,358 Cum of Concrete is due in 135 Nos. of structures (47 nos are in progress and 88 nos are to be tackled.
Canal shall be made through by 30 July 2018
Structures and balance works shall be
complebted by 31-Aug-18
17 Nellore BarrageR/s Wing & Divide Walls, Fixing of mechanical elements, Erection of embedded parts for gates, Pier, Hoist Columns and Slab wearing coat in progress.
31/Aug/18
18 Sangam Barrage Rafts, 38 nos. completed out of 42 nos.Piers, 68 raised to required height and 6 nos above crest level against 86 Nos. Fabrication of Gates & EM Parts are in Progress
31/Aug/18
19Water Supply to Mulapalli and other 4 tanks.
Received administrative approval for INR 39.48 Crores on 04 June 2018. Tenders shall be finalized by 25th July 2018
31/Dec/18
Page 2 of 7
Sl no. Project Major Issue / Current statusTarget Date of project
completion
ANNEXURE I Status of 55 prioritized projects as on 2 July 2018
20
Lifting of water from Somasila Swarnamuki link canal (Merlapaka Reservoir) to Mallemadugu Reservoir and Mallemadugu to Balaji Reservoir
Part-A: Lifting of water from Merlapaka to Mallemadugu Reservoir : Detailed estimate submitted to GoAP for an amount of INR 288.80 Cr, seeking administrative approval.
Part-B: Lifting of water from Mallemadugu to Balaji Reservoir : Detailed estimate submitted to GoAP for an amount of INR 198.00 Cr, seeking administrative approval
-
21 Mallimadugu ReservoirBund portion at length of 4.00 KM in progress as against 4.400 Kms (0.40 Kms is pending due to R &R, Forest and HT Lines). DGPS survey in 266.67 ha of new land shall be completed by 15th July 2018.
31/Dec/18
22 Balaji ReservoirBund portion at 1.750 Kms in progress as against 3.335 Kms (1.585 Kms is pending for want of Forest Clearance). Proposals for additional lead cost to a tune of INR 23.81 Cr is submitted for approval.
31/Dec/18
23 Venugopala sagar Reservoir
Bund portion at 5.076 Kms in progress as against 6.596 Kms (1.520 Kms is pending due to Forest and HT Lines).
Received suitability certificate for 242.816 Ha. against 375.472 Ha. from DFO, West Divn., Chittoor. DGPS survey shall be completed by 15-July-2018.
31/Dec/18
24Somasila Swarnamuki link canal. (from km 56.000 to 100.425)
CA land issue resolved. Collector, Chittoor District handed over 21.213 Ha of CA land to Forest Department . The PCCF, Guntur authenticated DGPS Survey for 21.213 Ha of CA Lands. Surplus Weir completed. Inlet structures are in progress.
31/Dec/18
25Lifting of water from SSG Canal to Althurupadu Reservoir (2.356 TMC)
Administrative approval received. Works shall be grounded for reservoir and lift portion by 7th July 2018.
31/Mar/19
Page 3 of 7
Sl no. Project Major Issue / Current statusTarget Date of project
completion
ANNEXURE I Status of 55 prioritized projects as on 2 July 2018
Projects in progress under purview of CE, Anantapur
26 Marala Reservoir
Rectification measures for tunnel in progress. Shall be completed by 15th July 2018.
Since water in Jeedipalli reservoir is not sufficient to supply water to Marala reservoir, this will be filled in the coming khariff season.
15/Jul/18
27 Cherlopally Reservoir
Rectification measures for tunnel in progress. Shall be completed by 15th July 2018.
Since water in Jeedipalli reservoir is not sufficient to supply water to Marala reservoir, this will be filled in the coming khariff season.
15/Jul/18
28Madakasira Branch Canal beyond Gollapalli Reservoir
Lepakshi, Peddacheruvu, Korlakunta, Konduru and Chalivendula tanks are filled in Hindupur Constituency i.e., upto 67 Km and also Penugonda constituency. 31/Jul/18
29Widening of HNSS Main Canal under Phase-I
Works resumed on 23rd March 2018. Project shall be completed by 31 July 2018 31/Jul/18
30Lifting of water from Jeedipalli Reservoir to Bhairavanithippa Project.
Agreement concluded. Project shall be grounded by 5th July 2018 31/Dec/19
31Lifting of water from Jeedipalli Reservoir to Upper Pennar Project
Agreement concluded. Project shall be grounded by 5th July 2018
Jeedipalli reservoir - Awaiting GO on declaration of Affected Zone. 31/Dec/19
32Modernization of Mid – Pennar South Canal from Km 0.000 to Km 40.000 & from Km 40.000 to Km 84.000
Upto 40th KM : 11,02,000 Cum of Earthwork Excavation is completed out of 30,61,650 Cum. Structures in progress.
40th KM to 84 KM : 5,72,853 Cum of Earthwork Excavation is completed out of 15,97,480 Cum. Structures in progress.
31/Mar/19
33Community Lift cum Drip Irrigation, Uravakonda
Agreement concluded on 15th June'18 with M/s MEIL. Revised action plan under preparation to complete the project within 12 months, instead of contractual duration of 18 months as per instructions of Hon'ble CM.
30/Jun/19
Page 4 of 7
Sl no. Project Major Issue / Current statusTarget Date of project
completion
ANNEXURE I Status of 55 prioritized projects as on 2 July 2018
Projects in progress under purview of CE, Kadapa
34 Gandikota Reservoir (GNSS Phase I)
R&R issues at RS Kondapuram village shall be addressed to store 12 TMC of water. At Kondapuram Village, a low lying area Ramachandra Nagar colony is getting submerged at 8.25 TMC. Funds to the tune of 238 Cr needed for R&R issues resolution.
Proposed for Inauguration by Hon’ble
CM after Water is Stored in reservoir up to 12
TMC
35 GNSS Ph-II up to Kodur in Kadapa Dist.Getting authentication for 5 Packages completed where DGPS Survey is completed. Estimates submitted to GoAP seeking administrative approval
31/Dec/19
Projects in progress under purview of CE, Kurnool
36Pulakurthy LIS (Guru Raghavendra Project)
Project shall be inaugurated after receiving flows into the TungaBhadra River. -
37Hagari (Vedavathi Project) Lift irrigation scheme
Hydrological clearances in progress. Tenders finalization for SID operations is in progress
-
38Water Supply to Western Mandals of Kurnool District
Tenders are submitted to COT on 15-6-2018 for approval 31/Jan/19
39 Formation of Gundrevula ReservoirSurvey works completed to the tune of 95%. CWC, KRMB and Telangana Govt. to be addressed for co-operation and concurrence. CE ISWR, Vijayawada to examine the issue and furnish a detailed report to Govt.
-
40Rajolibanda Diversion Scheme (RDS) Right Canal
Clarifications on DPR submitted to GoAP. Project value INR1761.30 Cr -
Projects in progress under purview of CE, Ongole
41Kandula Obul Reddy Gundlakamma Reservoir Project
LA issues resolved. Land owners agreed to give their lands for alternative methods like laying pipeline at certain lengths. Requested permission from GoAP on 21st June 2018, to execute the balance work based on the method finalized in the meeting.
31/Jul/18
42Yerram Chinnapoli Reddy Korisapadu LIS
Valuation of structures of Thurpupalem and Pedduru villages by R&B department is completed. (assessed value INR 14.84 Cr ). Land Acquisition is under process for R & R Colony and to resettle the PDFs of Thurpupalem and Pedduru Villages.
Project is proposed to be inaugurated during next
khariff season after impounding water in the
reservoir.
Page 5 of 7
Sl no. Project Major Issue / Current statusTarget Date of project
completion
ANNEXURE I Status of 55 prioritized projects as on 2 July 2018
43Veligonda Project - Tunnels I & II & Head Regulator
Tunnel-1 for a length of 3.60 KM and Tunnel-2 for a length of 8.037 Km were deleted from the existing agencies under clause 60('C). New tenders are being finalized for balance works. Agencies agreed to give undertaking as per the Hon’ble High Court judgment and requested for settlement of pending claims.
Head Works : Earth work excavation of Head Regulator portion completed.
Proposal for entrustment for additional 500 m length of Tunnel – 1 at non EPC rates to the Head regulator agency submitted to the Government.
Head Regulator completion : 31 Aug
2018
Projects in progress under purview of CE, North coast Visakhapatnam
44 Vamsadhara Project Stage II Phase II
Package 88 - 45.84 Acres Balance Land to be acquired for Distributory net work . Works of all 3 Packages of B.R.R. Vamsadhara Project Phase-II of Stage-II shall be completed by 15th July 2018, to store 8.00TMC of water in Hiramandalam Reservoir.
15/Jul/18
45Interlinking of Vamsadhara and Nagavali Rivers
Balance Land to be acquired - 320 acres. 30/Sep/18
46Offshore reservoir on Mahendratanaya River
Land Acquisition for R& R Villages is under progress. The agency has been instructed for improving progress of Earth work and concrete as per targets by mobilizing additional machinery.
30/Sep/18
47High Level Canal from Hiramandalam Reservoir to Itchapuram
Tender Process for DPR is completed. Survey work in progress. Project shall be grounded by Nov 2018.
30/Jun/20
48Taraka Rama Thirtha Sagaram Reservoir Project
Package 21 : Balance Land of 240.31 Ac is to be acquired. 11.00 acres of reserve forest land clearance is required to execute tunnel work.
Package 21A : R&R Works are being resolved at Agraharam, Koradapeta and Padalapeta villages
30/Jun/19
49Modernisation of Thotapalli Old Regulator System
GoAP accorded administrative approval for an amount of Rs.195.34 Cr., vide G.O.MS.No.67, dated 28th June 2018. Tender process shall commence shortly.
-
Page 6 of 7
Sl no. Project Major Issue / Current statusTarget Date of project
completion
ANNEXURE I Status of 55 prioritized projects as on 2 July 2018
Projects in progress under purview of CE, KDS, Vijayawada
50 K.L.RAO Pulichinthala ProjectBalance funds to a tune of INR 22Cr needed towards shifting of L.I Schemes. Proposed for inauguration after storing 30.00 T.M.C of water during next season.
-
51 Kondaveeti Vagu ProjectEviction of houses started and Earth work excavation in progress by force. Seeking permission for ROW from Railway authorities through AP Transco.
15/Jul/18
52Construction of new barrage (10 TMC) across Krishna river near Vykuntapuram.
Govt. accorded administrative approval for an amount of INR 2,169 Cr. Designs under preparation. Tenders shall be called shortly.
1/May/20
53Interlinking Of Godavari – Penna Rivers Phase-1
Total Estimated cost of Project: INR 6,212.08 Cr (Works : INR 5,535.81 Cr, LA : INR 676.26 Cr)Utilization (TMC) : 73 TMC
GoAP accorded administrative approval for an amount of Rs. 6020.15 Crs vide GO Ms. No:- 51, dated 13 June 2018.
DPR preparation in progress. Tenders shall be called by 15th July 2018
-
Projects in progress under purview Engineer in chief PIP (SE,LMC,Tuni)
54Uttarandhra Sujala Sravanthi Project Phase-I works
Part I: Agreement concluded with M/s HES Infra on 18 April 2018 and works commenced.
Part II : Tender Notice issued. Last date for tender receipt : 2nd July 2018
-
Projects in progress under purview CE, GDS - Dowlaiswaram
55 Chintalapudi Lift Irrigation Scheme
Design approvals awaited from APGENCO & APTRANSCO. Supervision charges for an amount of INR 10 Cr to be paid to APTRANSCO.
Revised Estimate for INR 6,400 Cr submitted to the Joint Committee of IBM & SLSC on 04-04-2018 duly incorporating the add-on works of Package-1 & 2 for recommendation to the Government. Remarks are being attended.
Necessary proposals were uploaded to MOEF for Stage-I clearance of Forest Land to an extent of 69.30 Ha for Phase-II (Canal) works.
-
Page 7 of 7