Page 1 of 7 Review of Prioritized Projects Hon’ble CM conducted Review for Prioritized Projects RECORD OF DISCUSSION Date Monday, 2 nd July 2018 Time 3pm to 5:45pm Agenda Progress review on Prioritized projects by Hon’ble Chief Minister, A.P Venue Conference room, AP Secretariat, Velagapudi. Attendees Shri. D. Uma Maheswara Rao, Hon’ble Minister, WRD Shri G Sai Prasad. Principle secretary to Hon’ble CM. Shri. Shashi Bhushan Kumar, Secretary, WRD Shri. Rajsekhar Budithi – Spl. Chief Secretary (FAC), Agriculture Smt. Rekha Rani – Commissioner, R&R Shri M. Venkateswara Rao, EnC, WRD District collectors Forest department Ground water department & APSRAC Chief Engineers and officials from AP WRD M/s Vassar Labs Consultants to APWRD

Upload: others

Post on 28-Dec-2019

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Hon’ble CM conducted Review for Prioritized Projects ...irrigationap.cgg.gov.in/uploadedFiles/Prioritized... · 7/2/2018  · Page 1 of 7 Review of Prioritized Projects Hon’ble

Page 1 of 7

Review of Prioritized Projects

Hon’ble CM conducted Review for Prioritized Projects

RECORD OF DISCUSSION

Date Monday, 2nd

July 2018

Time 3pm to 5:45pm

Agenda Progress review on Prioritized projects by Hon’ble Chief Minister, A.P

Venue Conference room, AP Secretariat, Velagapudi.

Attendees

Shri. D. Uma Maheswara Rao, Hon’ble Minister, WRD

Shri G Sai Prasad. Principle secretary to Hon’ble CM.

Shri. Shashi Bhushan Kumar, Secretary, WRD

Shri. Rajsekhar Budithi – Spl. Chief Secretary (FAC), Agriculture

Smt. Rekha Rani – Commissioner, R&R

Shri M. Venkateswara Rao, EnC, WRD

District collectors

Forest department

Ground water department & APSRAC

Chief Engineers and officials from AP WRD

M/s Vassar Labs

Consultants to APWRD

Page 2: Hon’ble CM conducted Review for Prioritized Projects ...irrigationap.cgg.gov.in/uploadedFiles/Prioritized... · 7/2/2018  · Page 1 of 7 Review of Prioritized Projects Hon’ble

Page 2 of 7

# Project / Topic Gist of discussions Action to be

taken by Timeline

1 Overall status

Overall status of 55 prioritized projects.

Projects inaugurated: 9 nos.

Projects ready for inauguration: 5 nos.

Projects in progress: 41 nos.

For information -

2 Chintalapudi LIS

CE, DGS – Dowlaiswaram briefed project status to Hon’ble CM.

Hon’ble CM advised EnC WRD to issue month-wise water requirement

targets to the project and instructed WRD and various agencies to

complete project within stipulated timelines to ensure water lifting in

current season.

Hon’ble CM reinstated that the project does not make a business case

unless water is lifted in current season, as Polavaram shall supply water

through gravity by next monsoon.

Secretary, WRD informed Hon’ble CM that a review meeting is planned

on and before 5th July’18 regarding progress and issues to be resolved

for timely completion of Chintalapudi pump house and canal up-to RMC,

along with WRD officials, District administration and agency.

EnC, WRD

CE, DGS -

Dowlaiswaram

EnC, WRD to issue

monthly water

requirement to

Chintalapudi project.

CE, DGS

Dowlaiswaram to

come up with a

revised action plan

for Chintalapudi

review meeting on

5th July’18

3 Adavipalli reservoir

and lift scheme

CE, Tirupathi informed Hon’ble CM that agency has requested for

extension of reservoir completion date by 15 days (instead of 30th

June’18). To ensure that there is no further slippage, 50% of BG

submitted by the agency was sent for encashment.

Hon’ble CM instructed CE, Tiruapthi to ensure that project is completed

by 15th July’18

CE, Tirupathi

Ensure completion

of Adavipalli

reservoir by 15th

July’18

Page 3: Hon’ble CM conducted Review for Prioritized Projects ...irrigationap.cgg.gov.in/uploadedFiles/Prioritized... · 7/2/2018  · Page 1 of 7 Review of Prioritized Projects Hon’ble

Page 3 of 7

# Project / Topic Gist of discussions Action to be

taken by Timeline

4 Kuppam Branch

Canal

District collector, Chittoor informed Hon’ble CM that 117.32 Km canal

excavation was completed as on 31st May’18 and the status remains

same till date which says that no excavation was carried out for the last

one month though most of LA issues were resolve.

Hon’ble CM instructed the agency to meet on 4th July’18 with action plan

for project completion by 30th July’18

Agency,

Kuppam Branch

Canal

Meet Hon’ble CM

on 4th July’18 with

revised action plan.

5 Nellore & Sangam

Barrage

Hon’ble CM interacted with the agency of Nellore barrage and instructed

for timely completion of works. Agency to give weekly updates during

review meeting on status of works and action plan for completion of

project.

CE, Tirupathi briefed Hon’ble CM on status of Sangam barrage. It was

discussed that 38 nos. rafts out of 42 nos. are completed and WRD is

striving for completion of balance four rafts by 30th July’18.

CE, Tirupathi

Ensuring completion

of Nellore barrage

and Sangam barrage

by 31st Aug’18

6 Mallemadugu

District collector, Chittoor informed Hon’ble CM that Forest department

is claiming for 990 acres instead of 750 acres due to less suitability of

land for vegetation. Permission from CMO is requested for handing over

of additional 240 acres.

Hon’ble CM advised DC, Chittoor to proceed with handing over of

additional land to forest department, since the land being handed over is

less suitable to grow forest and also in the interest of project.

DC, Chittoor

Proceed with

handing over of

extra 240 acres of

land to forest

department

7 Balaji reservoir

District collector, Chittoor informed Hon’ble CM that 81 acres of forest

land is being cultivated by encroachers for more than 30 years.

DC, Chittoor requested for clearance from Hon’ble to pay compensation

for vacating lands without any issues

DC, Chittoor

Proceed with

compensation for 81

acres of land in

forest area,

Page 4: Hon’ble CM conducted Review for Prioritized Projects ...irrigationap.cgg.gov.in/uploadedFiles/Prioritized... · 7/2/2018  · Page 1 of 7 Review of Prioritized Projects Hon’ble

Page 4 of 7

# Project / Topic Gist of discussions Action to be

taken by Timeline

Hon’ble CM advised DC, Chittoor to proceed with compensation

payment to encroachers since they are dependent on the land for more

than 3 decades.

cultivated by

encroachers

8

Stage II forest

clearances at state

level authorities

Forest department officials requested for release of INR 17.7 Cr for

compensatory afforestation at Chintalpudi. Secretary WRD informed

Forest department that payment shall be cleared at the earliest.

Secretary, WRD advised all APWRD officials to note that Stage II forest

clearances can be issued at state level in case of linear projects. He

informed that this is an important update that can help in expediting

forest clearances for irrigation projects.

For information -

9

Tender finalization for

Lifting of water from

Jeedipalli Reservoir

to Bhairavanithippa

Project.

Secretary, WRD instructed CE, Ananthapuram that package 2 tenders

for Bhairavanithippa Project shall be finalized at the earliest. Also, it was

discussed that a package-wise clear status shall be presented in the

weekly review meeting with Hon’ble CM.

Hon’ble CM instructed WRD to take necessary measures for completion

of project within an year instead of 1.5 years duration mentioned in the

bid document.

For information -

10

Community Lift cum

Drip Irrigation Project,

Uravakonda

CE, Anantapuram briefed Hon’ble CM that project serves 50,000 acres

of land and costs INR 985 Cr. Hon’ble CM instructed WRD to expedite

project works and ensure completion within 12 months. It was also

discussed that CLDI, Uravakonda is pilot case and shall have all advanced

drip irrigation techniques, methodologies and modern equipment for

enhancing benefit cost ratio and save more water to encourage more

such projects.

For information -

Page 5: Hon’ble CM conducted Review for Prioritized Projects ...irrigationap.cgg.gov.in/uploadedFiles/Prioritized... · 7/2/2018  · Page 1 of 7 Review of Prioritized Projects Hon’ble

Page 5 of 7

# Project / Topic Gist of discussions Action to be

taken by Timeline

11 Land acquisition for

Gandikota

Commissioner, R&R informed Hon’ble CM that revised list of

beneficiaries shall be received by 10th July’18. Hon’ble CM instructed

district administration and RR authorities to ensure that timely

completion of R&R activity to facilitate water storage.

For information -

12

GNSS Ph-II up to

Kodur in Kadapa Dist.

CE, Kadapa briefed package-wise status to Hon’ble CM. It was

discussed that WRD officials, JC and DFO to discuss and come up with

a clear cut package wise action plan.

CE, Kadapa

JC, Kadapa

DFO, Kadapa

Package wise action

plan for GNSS Ph-II

by 13th July’18

13 Veligonda Project

Secretary, WRD instructed CE, Ongole on the immediate action plan and

letter to be submitted for clearing bottlenecks. Hon’ble CM advised CE,

Ongole to take immediate action to clear road blocks for project progress

and resume works.

CE, Ongole

Take necessary

action to resume

tunneling works at

Veligonda project.

14

Yerram Chinnapoli

Reddy Korisapadu LIS

Hon’ble CM instructed WRD to proceed with crop compensations and

clear bottlenecks in the interest of project. For information -

15

Tenders for

Vykuntapuram and

Godavari-Penna link

Pahse I

CE, KDS, Vijayawada informed Hon’ble CM that tenders for Construction

of new barrage (10 TMC) across Krishna river near Vykuntapuram (V)

shall be released by 6th July’18 and that of Interlinking Of Godavari –

Penna Rivers Phase-1 shall be released by 10th July’18

CE, KDS,

Vijayawada

Tenders for

Vykuntapuram

project by 6th

July’18

Tenders for

Godavari-Penna link

Phase I by 10th

July’18

16

High Level Canal

from Hiramandalam

Reservoir to

Itchapuram

CE, (North Coast), Visakhapatnam informed Hon’ble CM that DPR shall

be completed by 31st July’18 and tenders shall be released by 15

th

Aug’18

CE (North

Coast),

Visakhapatnam

DPR for HLC from

Hiremandamalm by

31st July’18

Page 6: Hon’ble CM conducted Review for Prioritized Projects ...irrigationap.cgg.gov.in/uploadedFiles/Prioritized... · 7/2/2018  · Page 1 of 7 Review of Prioritized Projects Hon’ble

Page 6 of 7

# Project / Topic Gist of discussions Action to be

taken by Timeline

17

Taraka Rama Thirtha

Sagaram Reservoir

Project

CE, (North Coast), Visakhapatnam briefed Hon’ble CM on LA and R&R

issues. It was discussed that clearance for 11 acres of Reserve Forest

land shall be expedited to execute tunnel works.

Hon’ble CM instructed CE, (North Coast), Visakhapatnam to come up

with a time bound program by 13th July’18

CE, (North

Coast),

Visakhapatnam

Submission of time

bound program

during review

meeting on 13th

July’18

18

Modernization of

Thotapalli Old Canal

System

CE, (North Coast), Visakhapatnam informed Hon’ble CM that tenders

for Modernization of Thotapalli Old Canal System shall be released by

7th July’18

CE, (North

Coast),

Visakhapatnam

Releasing of

tenders by 7th

July’18

19 Water Conservation

Drive

Hon’ble CM reviewed activity wise progress of 139 days water

conservation drive / Jala Samrakshana Udhyamam. It was advised that

WRD shall take up balance works in regular Neeru-Pragathi program.

For information. -

20

Micro Irrigation and

holistic approach on

water management

Department of Micro Irrigation informed Hon’ble CM that 31,000 ha of

land shall be taken up in micro irrigation by 15th July’18 from Chittoor and

Kadapa districts.

Hon’ble CM advised that focus shall on areas with ground water below

20m and there shall be a holistic approach in Ground Water

Management, Micro Irrigation, water supply from Major & Medium

irrigation projects and utilization of rain guns for optimal productivity.

For information -

21

Action plan by

Agriculture

department

Department of Agriculture briefed Hon’ble CM on various activities taken

up for improvement of crop productivity. It was also discussed that

12,000 no. of rain guns are positioned in 437 Mandals for optimal

utilization in Karif & Rabi seasons.

Agriculture

Department

Integrated action

plan shall be

presented during

review meeting on

13th July’18

Page 7: Hon’ble CM conducted Review for Prioritized Projects ...irrigationap.cgg.gov.in/uploadedFiles/Prioritized... · 7/2/2018  · Page 1 of 7 Review of Prioritized Projects Hon’ble

Page 7 of 7

# Project / Topic Gist of discussions Action to be

taken by Timeline

Hon’ble CM instructed Agriculture department to present integrated

action plan by during review meeting on 13th

July’18

22 AP WRIMS

M/s Vassar Labs informed Hon’ble CM that a model with capability to

forecast water inflows shall be presented during review meeting on 13th

July’18, to help better understand the water resources for upcoming

seasons in the state and plan crops accordingly.

M/s Vassar

Labs

Presenting water

inflows forecasting

model by 13th

July’18

23 Upcoming review

meeting

Hon’ble CM announced that he shall be back from international travel on

11th July’18 and review meeting for 2

nd week of July shall be planned on

13th July’18 tentatively.

For information -

Encl.: Annexure 1 (Brief status of 55 prioritized projects as on 2nd July’18)

Page 8: Hon’ble CM conducted Review for Prioritized Projects ...irrigationap.cgg.gov.in/uploadedFiles/Prioritized... · 7/2/2018  · Page 1 of 7 Review of Prioritized Projects Hon’ble

Sl no. Project Major Issue / Current statusTarget Date of project

completionInaugurated projects

1 Purushotha Patnam LIS Inaugurated on 15th Aug 2017 -

2Construction of Anicut across Sarada River

Inaugurated on 6th Sept 2017 -

3 Mutchumarri LIS Inaugurated on 8th Sept 2017 -

4 Kandaleru Left Canal – Lift Scheme Inaugurated on 12th Nov 2017 -

5 Gandikota – CBR Lifts Inaugurated on 3rd Jan 2018 -

6 Siddapuram Lift Irrigation Scheme Inaugurated on 7th Jan 2018 -

7 Modernisation of Yerracalva Inaugurated on 8th Jan 2018 -

8Formation of Pogonda Reservoir in West Godavari

Inaugurated on 19th Feb 2018 -

9 SH-31 Road Work (GNSS Phase I) Inaugurated on 6th June 2018 -

Projects ready for Inauguration

10 Pedapalem LI Scheme on Krishna River Ready for inauguration -

11 Chinasana LI Scheme on VLMC Ready for inauguration -

12 Owk Tunnel (GNSS Phase I) Ready for inauguration -

13Gorakallu Balancing Reservoir (Sri Narasimharaya Sagar)

Ready for inauguration -

14 Pulikanuma LIS Ready for inauguration -

ANNEXURE I Status of 55 prioritized projects as on 2 July 2018

Page 1 of 7

Page 9: Hon’ble CM conducted Review for Prioritized Projects ...irrigationap.cgg.gov.in/uploadedFiles/Prioritized... · 7/2/2018  · Page 1 of 7 Review of Prioritized Projects Hon’ble

Sl no. Project Major Issue / Current statusTarget Date of project

completion

ANNEXURE I Status of 55 prioritized projects as on 2 July 2018

Projects in progress under purview of CE, Tirupathi

15Adavipalli Reservoir (HNSS Phase-II) & Adavipalli Lift (Peddamandyam lift on Main canal)

Reservoir : Gates erection in progress. Agency requested 15 days extension for completion (Revised completion date - 15th July 2018). It is proposed to encash 50% of BG as penalty to avoid further delays .

Lift scheme : Pump house upto M.F.L level completed. Roof erection in progress.Pumps & motors erection in process.

Reservoir by 15-July-18Lift scheme by 31-July-

18

16 Kuppam Branch Canal (HNSS Phase II)

Part A :From Km. 0.00 to Km 39.225 (up to II lift) : Pump house erection in progress

Part B : Work in progress in 3.487 Km and work to be tackled in 1.15 Km. 38,358 Cum of Concrete is due in 135 Nos. of structures (47 nos are in progress and 88 nos are to be tackled.

Canal shall be made through by 30 July 2018

Structures and balance works shall be

complebted by 31-Aug-18

17 Nellore BarrageR/s Wing & Divide Walls, Fixing of mechanical elements, Erection of embedded parts for gates, Pier, Hoist Columns and Slab wearing coat in progress.

31/Aug/18

18 Sangam Barrage Rafts, 38 nos. completed out of 42 nos.Piers, 68 raised to required height and 6 nos above crest level against 86 Nos. Fabrication of Gates & EM Parts are in Progress

31/Aug/18

19Water Supply to Mulapalli and other 4 tanks.

Received administrative approval for INR 39.48 Crores on 04 June 2018. Tenders shall be finalized by 25th July 2018

31/Dec/18

Page 2 of 7

Page 10: Hon’ble CM conducted Review for Prioritized Projects ...irrigationap.cgg.gov.in/uploadedFiles/Prioritized... · 7/2/2018  · Page 1 of 7 Review of Prioritized Projects Hon’ble

Sl no. Project Major Issue / Current statusTarget Date of project

completion

ANNEXURE I Status of 55 prioritized projects as on 2 July 2018

20

Lifting of water from Somasila Swarnamuki link canal (Merlapaka Reservoir) to Mallemadugu Reservoir and Mallemadugu to Balaji Reservoir

Part-A: Lifting of water from Merlapaka to Mallemadugu Reservoir : Detailed estimate submitted to GoAP for an amount of INR 288.80 Cr, seeking administrative approval.

Part-B: Lifting of water from Mallemadugu to Balaji Reservoir : Detailed estimate submitted to GoAP for an amount of INR 198.00 Cr, seeking administrative approval

-

21 Mallimadugu ReservoirBund portion at length of 4.00 KM in progress as against 4.400 Kms (0.40 Kms is pending due to R &R, Forest and HT Lines). DGPS survey in 266.67 ha of new land shall be completed by 15th July 2018.

31/Dec/18

22 Balaji ReservoirBund portion at 1.750 Kms in progress as against 3.335 Kms (1.585 Kms is pending for want of Forest Clearance). Proposals for additional lead cost to a tune of INR 23.81 Cr is submitted for approval.

31/Dec/18

23 Venugopala sagar Reservoir

Bund portion at 5.076 Kms in progress as against 6.596 Kms (1.520 Kms is pending due to Forest and HT Lines).

Received suitability certificate for 242.816 Ha. against 375.472 Ha. from DFO, West Divn., Chittoor. DGPS survey shall be completed by 15-July-2018.

31/Dec/18

24Somasila Swarnamuki link canal. (from km 56.000 to 100.425)

CA land issue resolved. Collector, Chittoor District handed over 21.213 Ha of CA land to Forest Department . The PCCF, Guntur authenticated DGPS Survey for 21.213 Ha of CA Lands. Surplus Weir completed. Inlet structures are in progress.

31/Dec/18

25Lifting of water from SSG Canal to Althurupadu Reservoir (2.356 TMC)

Administrative approval received. Works shall be grounded for reservoir and lift portion by 7th July 2018.

31/Mar/19

Page 3 of 7

Page 11: Hon’ble CM conducted Review for Prioritized Projects ...irrigationap.cgg.gov.in/uploadedFiles/Prioritized... · 7/2/2018  · Page 1 of 7 Review of Prioritized Projects Hon’ble

Sl no. Project Major Issue / Current statusTarget Date of project

completion

ANNEXURE I Status of 55 prioritized projects as on 2 July 2018

Projects in progress under purview of CE, Anantapur

26 Marala Reservoir

Rectification measures for tunnel in progress. Shall be completed by 15th July 2018.

Since water in Jeedipalli reservoir is not sufficient to supply water to Marala reservoir, this will be filled in the coming khariff season.

15/Jul/18

27 Cherlopally Reservoir

Rectification measures for tunnel in progress. Shall be completed by 15th July 2018.

Since water in Jeedipalli reservoir is not sufficient to supply water to Marala reservoir, this will be filled in the coming khariff season.

15/Jul/18

28Madakasira Branch Canal beyond Gollapalli Reservoir

Lepakshi, Peddacheruvu, Korlakunta, Konduru and Chalivendula tanks are filled in Hindupur Constituency i.e., upto 67 Km and also Penugonda constituency. 31/Jul/18

29Widening of HNSS Main Canal under Phase-I

Works resumed on 23rd March 2018. Project shall be completed by 31 July 2018 31/Jul/18

30Lifting of water from Jeedipalli Reservoir to Bhairavanithippa Project.

Agreement concluded. Project shall be grounded by 5th July 2018 31/Dec/19

31Lifting of water from Jeedipalli Reservoir to Upper Pennar Project

Agreement concluded. Project shall be grounded by 5th July 2018

Jeedipalli reservoir - Awaiting GO on declaration of Affected Zone. 31/Dec/19

32Modernization of Mid – Pennar South Canal from Km 0.000 to Km 40.000 & from Km 40.000 to Km 84.000

Upto 40th KM : 11,02,000 Cum of Earthwork Excavation is completed out of 30,61,650 Cum. Structures in progress.

40th KM to 84 KM : 5,72,853 Cum of Earthwork Excavation is completed out of 15,97,480 Cum. Structures in progress.

31/Mar/19

33Community Lift cum Drip Irrigation, Uravakonda

Agreement concluded on 15th June'18 with M/s MEIL. Revised action plan under preparation to complete the project within 12 months, instead of contractual duration of 18 months as per instructions of Hon'ble CM.

30/Jun/19

Page 4 of 7

Page 12: Hon’ble CM conducted Review for Prioritized Projects ...irrigationap.cgg.gov.in/uploadedFiles/Prioritized... · 7/2/2018  · Page 1 of 7 Review of Prioritized Projects Hon’ble

Sl no. Project Major Issue / Current statusTarget Date of project

completion

ANNEXURE I Status of 55 prioritized projects as on 2 July 2018

Projects in progress under purview of CE, Kadapa

34 Gandikota Reservoir (GNSS Phase I)

R&R issues at RS Kondapuram village shall be addressed to store 12 TMC of water. At Kondapuram Village, a low lying area Ramachandra Nagar colony is getting submerged at 8.25 TMC. Funds to the tune of 238 Cr needed for R&R issues resolution.

Proposed for Inauguration by Hon’ble

CM after Water is Stored in reservoir up to 12

TMC

35 GNSS Ph-II up to Kodur in Kadapa Dist.Getting authentication for 5 Packages completed where DGPS Survey is completed. Estimates submitted to GoAP seeking administrative approval

31/Dec/19

Projects in progress under purview of CE, Kurnool

36Pulakurthy LIS (Guru Raghavendra Project)

Project shall be inaugurated after receiving flows into the TungaBhadra River. -

37Hagari (Vedavathi Project) Lift irrigation scheme

Hydrological clearances in progress. Tenders finalization for SID operations is in progress

-

38Water Supply to Western Mandals of Kurnool District

Tenders are submitted to COT on 15-6-2018 for approval 31/Jan/19

39 Formation of Gundrevula ReservoirSurvey works completed to the tune of 95%. CWC, KRMB and Telangana Govt. to be addressed for co-operation and concurrence. CE ISWR, Vijayawada to examine the issue and furnish a detailed report to Govt.

-

40Rajolibanda Diversion Scheme (RDS) Right Canal

Clarifications on DPR submitted to GoAP. Project value INR1761.30 Cr -

Projects in progress under purview of CE, Ongole

41Kandula Obul Reddy Gundlakamma Reservoir Project

LA issues resolved. Land owners agreed to give their lands for alternative methods like laying pipeline at certain lengths. Requested permission from GoAP on 21st June 2018, to execute the balance work based on the method finalized in the meeting.

31/Jul/18

42Yerram Chinnapoli Reddy Korisapadu LIS

Valuation of structures of Thurpupalem and Pedduru villages by R&B department is completed. (assessed value INR 14.84 Cr ). Land Acquisition is under process for R & R Colony and to resettle the PDFs of Thurpupalem and Pedduru Villages.

Project is proposed to be inaugurated during next

khariff season after impounding water in the

reservoir.

Page 5 of 7

Page 13: Hon’ble CM conducted Review for Prioritized Projects ...irrigationap.cgg.gov.in/uploadedFiles/Prioritized... · 7/2/2018  · Page 1 of 7 Review of Prioritized Projects Hon’ble

Sl no. Project Major Issue / Current statusTarget Date of project

completion

ANNEXURE I Status of 55 prioritized projects as on 2 July 2018

43Veligonda Project - Tunnels I & II & Head Regulator

Tunnel-1 for a length of 3.60 KM and Tunnel-2 for a length of 8.037 Km were deleted from the existing agencies under clause 60('C). New tenders are being finalized for balance works. Agencies agreed to give undertaking as per the Hon’ble High Court judgment and requested for settlement of pending claims.

Head Works : Earth work excavation of Head Regulator portion completed.

Proposal for entrustment for additional 500 m length of Tunnel – 1 at non EPC rates to the Head regulator agency submitted to the Government.

Head Regulator completion : 31 Aug

2018

Projects in progress under purview of CE, North coast Visakhapatnam

44 Vamsadhara Project Stage II Phase II

Package 88 - 45.84 Acres Balance Land to be acquired for Distributory net work . Works of all 3 Packages of B.R.R. Vamsadhara Project Phase-II of Stage-II shall be completed by 15th July 2018, to store 8.00TMC of water in Hiramandalam Reservoir.

15/Jul/18

45Interlinking of Vamsadhara and Nagavali Rivers

Balance Land to be acquired - 320 acres. 30/Sep/18

46Offshore reservoir on Mahendratanaya River

Land Acquisition for R& R Villages is under progress. The agency has been instructed for improving progress of Earth work and concrete as per targets by mobilizing additional machinery.

30/Sep/18

47High Level Canal from Hiramandalam Reservoir to Itchapuram

Tender Process for DPR is completed. Survey work in progress. Project shall be grounded by Nov 2018.

30/Jun/20

48Taraka Rama Thirtha Sagaram Reservoir Project

Package 21 : Balance Land of 240.31 Ac is to be acquired. 11.00 acres of reserve forest land clearance is required to execute tunnel work.

Package 21A : R&R Works are being resolved at Agraharam, Koradapeta and Padalapeta villages

30/Jun/19

49Modernisation of Thotapalli Old Regulator System

GoAP accorded administrative approval for an amount of Rs.195.34 Cr., vide G.O.MS.No.67, dated 28th June 2018. Tender process shall commence shortly.

-

Page 6 of 7

Page 14: Hon’ble CM conducted Review for Prioritized Projects ...irrigationap.cgg.gov.in/uploadedFiles/Prioritized... · 7/2/2018  · Page 1 of 7 Review of Prioritized Projects Hon’ble

Sl no. Project Major Issue / Current statusTarget Date of project

completion

ANNEXURE I Status of 55 prioritized projects as on 2 July 2018

Projects in progress under purview of CE, KDS, Vijayawada

50 K.L.RAO Pulichinthala ProjectBalance funds to a tune of INR 22Cr needed towards shifting of L.I Schemes. Proposed for inauguration after storing 30.00 T.M.C of water during next season.

-

51 Kondaveeti Vagu ProjectEviction of houses started and Earth work excavation in progress by force. Seeking permission for ROW from Railway authorities through AP Transco.

15/Jul/18

52Construction of new barrage (10 TMC) across Krishna river near Vykuntapuram.

Govt. accorded administrative approval for an amount of INR 2,169 Cr. Designs under preparation. Tenders shall be called shortly.

1/May/20

53Interlinking Of Godavari – Penna Rivers Phase-1

Total Estimated cost of Project: INR 6,212.08 Cr (Works : INR 5,535.81 Cr, LA : INR 676.26 Cr)Utilization (TMC) : 73 TMC

GoAP accorded administrative approval for an amount of Rs. 6020.15 Crs vide GO Ms. No:- 51, dated 13 June 2018.

DPR preparation in progress. Tenders shall be called by 15th July 2018

-

Projects in progress under purview Engineer in chief PIP (SE,LMC,Tuni)

54Uttarandhra Sujala Sravanthi Project Phase-I works

Part I: Agreement concluded with M/s HES Infra on 18 April 2018 and works commenced.

Part II : Tender Notice issued. Last date for tender receipt : 2nd July 2018

-

Projects in progress under purview CE, GDS - Dowlaiswaram

55 Chintalapudi Lift Irrigation Scheme

Design approvals awaited from APGENCO & APTRANSCO. Supervision charges for an amount of INR 10 Cr to be paid to APTRANSCO.

Revised Estimate for INR 6,400 Cr submitted to the Joint Committee of IBM & SLSC on 04-04-2018 duly incorporating the add-on works of Package-1 & 2 for recommendation to the Government. Remarks are being attended.

Necessary proposals were uploaded to MOEF for Stage-I clearance of Forest Land to an extent of 69.30 Ha for Phase-II (Canal) works.

-

Page 7 of 7