Page 1 of 12 Review of Prioritized Projects Hon’ble CM conducted Review for Prioritized Projects RECORD OF DISCUSSION Date Monday, 5 th March 2018 Time 4.00 PM to 7.30 PM Agenda Progress review on Prioritized projects by Hon’ble Chief Minister, A.P Venue AP Secretariat, Velagapudi Attendees Shri Devineni Umamaheswara Rao, Hon’ble Minister, Water Resources Shri M. Venkateswara Rao, EnC, WRD Chief Engineer – Kurnool Chief Engineer – Kadapa Chief Engineer – Anantapur Chief Engineer – Tirupathi Chief Engineer – Ongole Chief Engineer – North Coast Director, Ground water department SE, PPMU Engineers from WRD Engineers from Ground water department Representative from APSRAC Representatives from Vassar labs. Consultants to APWRD

Upload: others

Post on 11-Feb-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • Page 1 of 12

    Review of Prioritized Projects

    Hon’ble CM conducted Review for Prioritized Projects

    RECORD OF DISCUSSION

    Date Monday, 5th

    March 2018

    Time 4.00 PM to 7.30 PM

    Agenda Progress review on Prioritized projects by Hon’ble Chief Minister, A.P

    Venue AP Secretariat, Velagapudi

    Attendees

    Shri Devineni Umamaheswara Rao, Hon’ble Minister, Water Resources

    Shri M. Venkateswara Rao, EnC, WRD

    Chief Engineer – Kurnool

    Chief Engineer – Kadapa

    Chief Engineer – Anantapur

    Chief Engineer – Tirupathi

    Chief Engineer – Ongole

    Chief Engineer – North Coast

    Director, Ground water department

    SE, PPMU

    Engineers from WRD

    Engineers from Ground water department

    Representative from APSRAC

    Representatives from Vassar labs.

    Consultants to APWRD

  • Page 2 of 12

    Sl

    no.

    Project / Topic Gist of discussion Action to be

    taken by Timeline

    1

    Projects completed

    and ready for

    inauguration.

    Projects inaugurated out of 29 prioritized projects

    1. Purushotha Patnam LIS inaugurated on 15th Aug’17.

    2. Anicut across Sarada River inaugurated on 6th Sept’17.

    3. Mutchumarri LIS inaugurated on 8th Sept’17

    4. Kandaleru Left Canal LIS inaugurated on 12th Nov’17

    5. Gandikota – CBR Lifts inaugurated on 3rd Jan’18

    6. Siddapuram LIS inaugurated on 7th Jan’18

    7. Modernisation of Yerracalva inaugurated on 8th Jan’18

    8. Formation of Pogonda reservoir inaugurated on 19th Feb’18

    Projects ready of inauguration

    1. Pedapalem LIS

    2. Chinasana LIS

    3. Owk Tunnel (GNSS Phase - I)

    4. Gorakallu Balancing Reservoir (Sri Narasimharaya Sagar)

    5. Pulikanuma LIS

    For information.

    2 LMC

    SE, LMC briefed Hon’ble CM about the status of woks at LMC and

    informed that notices are issued to PKG 1, 4 and 5 contractors due to

    slow progress.

    Hon’ble CM instructed SE, LMC to present following details during

    weekly review meetings

    I. Agency-wise progress of works

    II. Progress of the works during the week

    III. Monthly program

    IV. Action plan for structures and completion dates, structure-wise

    SE, LMC

    Detailed status and

    action plan for all

    structures in LMC to

    be prepared by 12th

    March’18

  • Page 3 of 12

    Sl

    no.

    Project / Topic Gist of discussion Action to be

    taken by Timeline

    3 116 days water

    conservation drive

    Hon’ble CM reviewed 116 days action plan and instructed WRD officials

    to prepare department-wise action plan for taking up various activities

    under Jala-Samrakshna-Udhayamam (116 days water conversation

    drive). It was also discussed that drone surveys shall be done for

    evaluating status of existing canals. Extensive report shall be prepared

    by running drones all through the canals to assess the status of canals

    in state.

    Action plan shall be prepared district-wise and department-wise to

    assess weekly progress.

    WRD

    Department-wise

    action plan shall be

    presented during 12th

    March’18 meeting

    4

    — Adavipalli reservoir — Kuppam branch

    canal

    — Nellore barrage — Sangam barrage

    Adavipalli reservoir :

    — CE, Tirupathi informed Hon’ble CM that the project will be

    completed by 15th

    March’18 though the planned completion date is

    31st March’18.

    Kuppam branch canal :

    — CE, Trupathi informed Hon’ble CM that small bits of canal length,

    each ranging from 50 to 200m length, total put together 1.961 Km

    held up due to land acquisition payments and court cases.

    — Collector, Chittoor district informed Hon’ble CM that INR 10.56 Cr is

    required for completion of balance LA. Hon’ble CM assured that

    required payment shall be cleared immediately and project should be

    completed by targeted date – 30th

    June’18

    Nellore barrage :

    — CE, Tirupathi informed Hon’ble CM that civil works shall be

    completed by 31st March’18. Encroachments clearance for taking up

    balance protection works and flood banks is in progress.

    — CE, Tirupathi — Finance

    department

    CE, Tirupathi to ensure

    — Completion of Adavipalli reservoir

    by 15th

    March’18

    — Design clearances for Sangam barrage

    by 15th

    March’18

    Finance department

    shall release INR 10.56

    Cr for LA bills at

    Kuppam branch canal

  • Page 4 of 12

    Sl

    no.

    Project / Topic Gist of discussion Action to be

    taken by Timeline

    — Hon’ble CM instructed for completion of civil works by 30th March’18

    and flood banks by 31st May’18

    Sangam barrage :

    — CE, Tirupathi briefed Hon’ble CM about the status of works at

    Sangam barrage. Hon’ble CM interacted with the respective agency

    and instructed APWRD officials to ensure all design clearances by

    15th

    March and agency to improve productivity and complete civil

    works by 31st March’18 and balance works by 30

    th June’18.

    5

    — Marala & Cherlopally

    reservoirs

    — Madakasira branch canal beyond

    Gollapalli reservoir

    Marala reservoirs :

    — CE, Anantapuram informed Hon’ble CM that case is running in

    Supreme Court. It is expected to be finalized by 8th

    Mar’18.

    Cherlopally reservoir :

    — CE, Anantapuram informed Hon’ble CM that the case is running in

    Supreme Court and shall be finalized by 8th

    Mar’18. It was also

    discussed that Somandapalli railway crossing is completed but

    additional side walls needs to constructed on upstream and

    downstream side, as per requirement of Indian railways, to ensure

    safety in case of water leakage.

    — Hon’ble CM instructed that respective railway contractor shall attend

    the review meeting on 12th

    March’18

    Madakasira branch canal beyond Gollapalli reservoir :

    — CE, Anantapuram informed Hon’ble CM that LA Problem is solved is

    Kirikera village and work is in progress. It was also discussed that

    balance pumping station works shall be awarded to M/s MEIL under

    60(C) since the existing agency - M/s IVRCL is under insolvency

    proceedings by NCLT.

    — Hon’ble CM instructed AP WRD officials to continuously follow up

    for Land Acquisition Court Case at Demakethapalli for early

    resolution.

    For information

  • Page 5 of 12

    Sl

    no.

    Project / Topic Gist of discussion Action to be

    taken by Timeline

    6

    Electricity supply for

    Punganuru branch

    canal

    CE, Ananthapur informed Hon’ble that 16 pumping stations under

    Punganuru branch canal are lacking timely power supply due to pending

    payments with APTRANSCO & APSPDCL.

    Hon’ble CM assured that payments shall be processed and issues shall

    be sorted on immediate basis

    For information.

    7 Road works at SH 31

    CE, Kadapa informed Hon’ble CM that SH 31 road works are under

    finishing stage. 89 out of 90 structures are completed and balance one

    structure – ROB is under construction by railway contractor.

    Hon’ble CM interacted with respective railway contractor and

    instructed that works shall be completed by 30th

    April (extended from

    initial planned completion date - 30th

    March’18 as per the request of

    contractor) without any further delay.

    CE, Kadapa

    Ensuring completion of

    ROB works by 30th

    April’18

    8 Gandikota reservoir

    (GNSS Phase I)

    CE, Kadapa briefed Hon’ble CM about the status of works and it was

    discussed that current storage of water is 4.45TMC. It was also

    discussed that R&R problems in Muchumarri, Nedarpeta and Korrapudu

    villages are being resolved by Revenue authorities by identified land for

    and shifting PDF’s.

    For information.

    9 Pulakurthy LIS

    CE, Kurnool informed Hon’ble CM that works are in progress as per

    schedule. Laying pressure main pipeline is in progress and motors

    erection shall be completed by 15th

    March’18. Project shall be ready for

    inauguration by 31st March’18.

    CE, Kurnool

    Erection of motors by

    15th

    March and project

    inauguration by 31st

    March’18

    10 Gorukallu reservoir

    CE, Kurnool informed Hon’ble CM that land required for balance bund

    formation (3 lakh cum of earth work) is available with endowment

    department. Though the land with endowment is dry land, AP WRD

    shall compensate by providing equal area of wet land to endowment

    department as it falls under 1.5km radius / lead.

    Secretary,

    Endowment

    department

    Immediately provide

    necessary approvals

    for handing required

    land to WRD for

    completion of

    Gorukallu reservoir

  • Page 6 of 12

    Sl

    no.

    Project / Topic Gist of discussion Action to be

    taken by Timeline

    Hon’ble CM instructed that Endowment department secretary shall

    meet on 6th

    March and issue shall be cleared immediately.

    11

    — Kandula Obulreddy Gundlakamma

    reservoir

    — Korisapadu LIS

    Gundlakamma reservoir :

    — JC, Prakasam and CE, Ongole briefed Hon’ble CM about status of

    LA and R&R works and it was discussed that balance 21 farmers, not

    cooperating for handing over land shall be vacated forcefully in the

    interest of project completion, if required.

    — CE, Ongole confirmed Hon’ble CM that project shall be completed

    by 28th

    March’18.

    Korisapadu LIS :

    — CE, Ongole and JC Prakasam briefed Hon’ble CM about various

    alternate options to avoid existing LA issues. Hon’ble CM instructed

    JC, Prakasam and CE, Ongole to explore various possibilities in all

    respects and come up with best possible solution by 12th

    March’18

    CE, Ongole & JC

    Prakasam

    Completion of

    Gundlakamma

    reservoir by 28th

    March’18

    CE Ongole and JC

    Prakasam to come up

    with alternative

    solution for resolving

    LA issues at

    Korisapaud LIS by 12th

    March’18

    12 Vamsadhara Stage II,

    Pahse II

    CE, North coast, Visakhapatnam updated status of works to Hon’ble

    CM as follows

    Package 87:

    — Presently, 412 nos. of workmen (280 skilled &132 unskilled) are

    working at site. The agency is to deploy another 150 workmen to

    achieve the target productivity. The agency has been instructed to

    increase resources for project completion on time.

    — Hon’ble CM interacted with the agency and instructed that works

    shall be completed in time under any circumstances, failing with the

    agency shall be disqualified and blacklisted.

    Package 88:

    — Pending court case in WP 3192/2017 in respect of LA of Flood Flow

    Canal U/S of inlet regulator cum DLRB at KM 26.330. The SDC, LA

    CE, North coast

    Visakhapatnam

    Ensuring works

    completion to enable 8

    TMC water storage by

    31st March’18 and

    total project

    completion by 30th

    May’18

  • Page 7 of 12

    Sl

    no.

    Project / Topic Gist of discussion Action to be

    taken by Timeline

    Unit-IV, Srikakulam has been requested to take necessary action to

    vacate the stay orders. The matter is in process.

    13

    Hiremandalam reservoir :

    — The agency has been instructed to increase resources to

    achieve targets. Diversion Road Work is being carried out by

    R&B Department, shall be completed by 31st March’18.

    — Works of all 3 Packages to store 8.00TMC of water in

    Hiramandalam Reservoir shall be completed by 31st March’18

    and balance work store 19 TMC shall be completed by 30th

    May’18

    Hon’ble CM interacted with Collector, Srikakulam and advised to

    complete LA activity at the earliest to complete reservoir and link canal

    at the earliest.

    14 Mahendratanaya

    project

    Collector, Srikakulam informed Hon’ble CM that project works are in

    progress as per schedule and Tunnel approvals are awaited. It was also

    discussed that R&R tenders shall be opened by 9th

    March and shifting

    of PDF’s is planned by 30th

    April’18. It was requested that pending INR

    14 Cr may be cleared

    Hon’ble CM assured that pending bills for LA shall be cleared

    immediately.

    Finance

    department

    Clearing pending LA

    bills of INR 14 Cr for

    Mahendratanaya

    project

  • Page 8 of 12

    Sl

    no.

    Project / Topic Gist of discussion Action to be

    taken by Timeline

    15 Tarakarama

    Theertham project

    Hon’ble CM instructed WRD to include Tarakarama Teertham project in

    prioritized projects list. CE, Vijayanagaram informed Hon’ble CM that

    project was initiated in the year 2006 but delayed to due to LA issues.

    Subsequently, project has been divided into two packages in the year

    2013-14 with administrative sanction of INR 471.3 Cr and storage

    capacity of 2.76 TMC.

    Current status of Package 1: 37% completed.

    Current status of Package 2: 47% completed.

    LA for Tunnel and Canal is in progress. Stage 2 forest clearances are

    expected by May’18.

    Hon’ble CM instructed that project shall be completed on time if

    required by assigning new agencies.

    EnC, AP WRD informed Hon’ble CM that proposal for deleting works

    from existing agency for one package is under evaluation and might

    require legal action against the agency.

    Hon’ble CM instructed that a detailed status shall be presented with

    action plan by 12th

    March’18 meeting.

    AP WRD

    Inclusion of Project in

    prioritized projects list.

    Evaluation and

    finalization of proposal

    from agency to delete

    works without legal

    action and further

    action plan to be

    presented by AP WRD

    during review meeting

    on 12th March’18

    16 Velugonda tunnels

    CE, Ongole informed Hon’ble CM that administrative sanction from

    finance department is awaited for revised estimated. Tunnel-I shall be

    completed by 30th

    Oct’18 and Tunnel-II by 31st March’19

    Finance

    department

    Necessary

    administrative

    sanctions for

    Velugonda tunnels

  • Page 9 of 12

    Sl

    no.

    Project / Topic Gist of discussion Action to be

    taken by Timeline

    Hon’ble CM instructed finance department to provide necessary

    approvals at the earliest. It also discussed that WRD shall release

    tenders immediately after finance department approvals.

    shall be issued

    immediately.

    17

    — Swarnamukhi link

    — Balaji reservoir

    — Mallemadugu and Venugopal sagar

    reservoirs

    Swarnamukhi link :

    CE, Tirupathi informed Hon’ble CM that estimated are under scrutiny

    by government. Stage 1 forest clearances proposals shall be submitted

    by 12th

    March’18 and clearances are expected by 30th

    June’18.

    Balaji reservoir :

    CE, Tirupathi informed Hon’ble CM that progress is slow due to

    unavailability of soil. A special request has been sent to GoAP for

    approval of extra lead since the required soil is unavailable within the

    specified limits.

    Mallemadugu and Venugopal sagar reservoirs :

    CE, Tirupathi informed Hon’ble CM that agency has requested WRD to

    pay INR 21 Cr directly to Energy department for diversion of HT lines to

    take up balance works.

    Hon’ble CM emphasized that only 9% of works are completed as on

    date at Mallemadugu, and also there hasn’t been substantial progress

    at Balaji reservoir project. It was instructed that action plan has to be

    prepared to ensure projects completion by 31st Dec’18 and respective

    forest officials shall attend review meeting on 12th

    March’18.

    CE, Tirupathi

    Action plan for projects

    completion by 31st

    Dec’18

  • Page 10 of 12

    Sl

    no.

    Project / Topic Gist of discussion Action to be

    taken by Timeline

    18 Althurpadu LIS and

    reservoir

    CE, Tirupathi informed Hon’ble CM that estimates are under scrutiny

    by finance department. It was also discussed that total value of

    estimate is tentatively INR 1000 Cr.

    Hon’ble CM instructed that tenders shall be called immediately for LIS

    and reservoir.

    SE, Nellore informed Hon’ble CM that most of the land out of 560 acres

    required area is government land. Hon’ble CM instructed that land

    acquisition and related details shall be presented during meeting on 12th

    March’18.

    JC Nellore and

    SE Nellore

    Detailed presentation

    about land required for

    Althurpadu LIS and

    reservoir on 12th

    March’18

    19

    Inclusion of new

    projects to prioritized

    projects list.

    Hon’ble CM instructed WRD officials to include following 21 projects to

    existing prioritized projects list and focus on their completion.

    1. Mahendra Tanaya project

    2. Tarakaramateertham project

    3. Uthara Andhra Srujana Sravanthi

    4. Chintalapudi LIS project

    5. Swarnamkhi – Somasila link canal

    6. Balaji reservoir

    7. Mallemadugu

    8. Venugopala Sagar

    9. GNSS Phase II – Kadapa project

    10. HNSS widening project

    11. Veligonda tunnels

    12. Sompeta – Achampeta project

    13. Ichapuram project

    14. Bhiravatippa project

    15. Perur project

    For information.

  • Page 11 of 12

    Sl

    no.

    Project / Topic Gist of discussion Action to be

    taken by Timeline

    16. Kurnool tanks

    17. Mulapalli project

    18. Kuppam project

    19. Vikuntapuram project

    20. Godavari-Penna linking

    21. Althurpadu LIS project

    20 Measures to improve

    ground water levels.

    Ground water department and APSRAC presented analysis on existing

    status of ground water levels at all the villages in the state. It was also

    informed villages are being prioritized w.r.t ground water levels to take

    up ground water improvement measures. Additional structures

    requirement is under assessment to improve GW levels in villages

    under top priority.

    Hon’ble CM instructed that all measures shall be taken to ensure that

    ground water levels are improved in all the areas of the state. A detailed

    presentation shall be made during review meeting on 12th

    March’18.

    GW department

    and APSRAC

    Detailed presentation

    on categorization of all

    the villages in state

    w.r.t to ground water

    levels and proposed

    measures to improve

    GW levels by 12th

    March’18

    21 Study on water

    management

    Hon’ble CM instructed M/s Vassar labs to take up a detailed study on

    world’s best water management systems to enhance water utilization

    and management in drinking, agricultural and industrial sectors. Also, a

    study needs to be done for utilization of treated water in urban areas.

    It was also discussed that a works shop is scheduled during March’18

    to enable other states officials to visit AP and learn water management

    systems and technologies under implementation in AP.

    For information

  • Page 12 of 12

    Sl

    no.

    Project / Topic Gist of discussion Action to be

    taken by Timeline

    Hon’ble CM instructed that AP shall provide consulting support to other

    states for water resource utilization and optimization if required. It was

    discussed that special focus and care should be taken to ensure

    protection of intellectual property of certain technologies / methods,

    under implementation in AP.