highlights on the ulu jelai hydroelectric...

2
FORUM | JURUTERA August 2012 30 Highlights on the Ulu Jelai Hydroelectric Project THE Water Resources Technical Division organised a technical talk on the construction of a 372 MW hydro-power project in Cameron Highlands in April 2012 at the Wisma IEM, Petaling Jaya. The talk on the Ulu Jelai Hydroelectric Project was jointly presented by Ir. Mohd. Isa Mustaza, a Civil Engineer (Project Services) attached to Tenaga Nasional Berhad; and Mr. Keith Kinsella, the current Chief Resident Engineer (CRE) for the project. Ir. Isa kick-started the talk by highlighting the rationale for implementing the project, which is to help meet the power demand of the country. Subsequently, Mr. Keith Kinsella elaborated on the project components and briefed the audience on the current construction progress of the project. The Ulu Jelai Hydroelectric Project is a 372 MW hydropower development on the Bertam River, Pahang. The scheme is expected to produce an annual energy supply of 326 GWh. The main features of the project are an 88-metre high, 740,000 cubic metre RCC dam with service and emergency ungated spillways, provision for the the Telom and Lemoi rivers for the transfer of water to Susu Dam, an intake tower, power tunnels and an underground powerhouse cavern. Construction work for the project commenced in late 2010 and has been scheduled to complete by end of 2016. associated earthworks is in progress. Meanwhile for the second contract package, construction of the dam and the various tunnels leading to the underground power station has just begun. The dam is constructed of roller compacted concrete (RCC), reaching a crest height of approximately 88 metres above existing river bed level and extending approximately 470 metres along the crest. Integrated into the RCC dam is a non-gated 78-metre long service spillway, a 60-metre long non-gated emergency spillway and a stepped spillway chute on the downstream dam face, terminating in a stilling basin. Appropriate river diversion works for the dam including upstream and downstream cofferdams and two 90 metres long and 4.5 metres width by 8.0 metres height diversion culverts would also be required. The gated power intake structure is located near the upstream face of Susu Dam. The power intake comprises a metre wide by 6.5 metre high vertical gates, through which the water will enter into the power waterway leading to the underground Telanok power station. The power waterway which extends from the power intake structure to the power station basically consists of a 9.5 metre diameter horseshoe-shaped and 4.2 kilometre long unlined headrace tunnel, which includes a 40 metres long concrete lined rock trap; a 5.2 metre diameter by 173 metres high concrete-lined pressure shaft; 5.2 metre diameter horseshoe-shaped by 86 metres long concrete lined pressure tunnel; 5.2 metre diameter, 10 metres long steel-lined, single penstock embedded in concrete; steel bifurcation; and 3.75 metre diameter steel-lined, dual penstock, embedded in concrete. The generating units (2 x 186 MW) would be housed in an underground power station cavern, approximately 82 m x 22.5 m x 35.5 m. Other underground facilities include the transformer cavern of approximately 34 m x 17 m x 17 m, downstream surge chamber of approximately 40 m x 14 m x 35 m, associated service tunnels, access tunnels, and ventilation tunnels, and a concrete lined 7.7 metre diameter horseshoe-shaped tail race tunnel of approximately 1,720 metres in length. The scheme also includes the diversion of water from the Telom and Lemoi river catchments through the 3-metre diameter transfer tunnels, with respective lengths of 8,500 metres and 7,500 metres to the Susu Dam storage. Apart from presenting the project key features and how it works, the talk also touched on the excavation of the tunnels, which is a major part of the construction work. The construction of the Main Access Tunnel (MAT) involving the excavation of a top heading in soft material using canopy tubes, steel ribs and shotcrete for support was highlighted. Upon reaching competent rock, the tunnel excavation WATER RESOURCES TECHNICAL DIVISION Tunnel construction within Lemoi river catchment

Upload: dongoc

Post on 17-Mar-2018

220 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: Highlights on the Ulu Jelai Hydroelectric Projectdspace.unimap.edu.my/dspace/bitstream/123456789/23407/1/aug 10.pdf · The Ulu Jelai Hydroelectric Project is a 372 MW ... long unlined

FORUM

| JURUTERA August 201230

Highlights on the Ulu JelaiHydroelectric Project

THE Water Resources Technical Division organised atechnical talk on the construction of a 372 MW hydro-powerproject in Cameron Highlands in April 2012 at the WismaIEM, Petaling Jaya.

The talk on the Ulu Jelai Hydroelectric Project wasjointly presented by Ir. Mohd. Isa Mustaza, a Civil Engineer(Project Services) attached to Tenaga Nasional Berhad;and Mr. Keith Kinsella, the current Chief Resident Engineer(CRE) for the project.

Ir. Isa kick-started the talk by highlighting the rationalefor implementing the project, which is to help meet thepower demand of the country. Subsequently, Mr. KeithKinsella elaborated on the project components and briefedthe audience on the current construction progress of theproject.

The Ulu Jelai Hydroelectric Project is a 372 MWhydropower development on the Bertam River, Pahang.The scheme is expected to produce an annual energysupply of 326 GWh. The main features of the project arean 88-metre high, 740,000 cubic metre RCC dam withservice and emergency ungated spillways, provision for the

the Telom and Lemoi rivers for the transfer of water to SusuDam, an intake tower, power tunnels and an undergroundpowerhouse cavern.

Construction work for the project commenced in late2010 and has been scheduled to complete by end of 2016.

associated earthworks is in progress. Meanwhile for thesecond contract package, construction of the dam and thevarious tunnels leading to the underground power stationhas just begun.

The dam is constructed of roller compacted concrete(RCC), reaching a crest height of approximately 88 metresabove existing river bed level and extending approximately470 metres along the crest. Integrated into the RCC damis a non-gated 78-metre long service spillway, a 60-metrelong non-gated emergency spillway and a stepped spillwaychute on the downstream dam face, terminating in a stillingbasin.

Appropriate river diversion works for the dam includingupstream and downstream cofferdams and two 90 metreslong and 4.5 metres width by 8.0 metres height diversionculverts would also be required.

The gated power intake structure is located near theupstream face of Susu Dam. The power intake comprises a

metre wide by 6.5 metre high vertical gates, through whichthe water will enter into the power waterway leading to theunderground Telanok power station.

The power waterway which extends from the powerintake structure to the power station basically consists ofa 9.5 metre diameter horseshoe-shaped and 4.2 kilometrelong unlined headrace tunnel, which includes a 40 metreslong concrete lined rock trap; a 5.2 metre diameter by173 metres high concrete-lined pressure shaft; 5.2 metrediameter horseshoe-shaped by 86 metres long concretelined pressure tunnel; 5.2 metre diameter, 10 metres longsteel-lined, single penstock embedded in concrete; steelbifurcation; and 3.75 metre diameter steel-lined, dualpenstock, embedded in concrete.

The generating units (2 x 186 MW) would be housed inan underground power station cavern, approximately 82 mx 22.5 m x 35.5 m. Other underground facilities include thetransformer cavern of approximately 34 m x 17 m x 17 m,downstream surge chamber of approximately 40 m x 14 mx 35 m, associated service tunnels, access tunnels, andventilation tunnels, and a concrete lined 7.7 metre diameterhorseshoe-shaped tail race tunnel of approximately 1,720metres in length.

The scheme also includes the diversion of water fromthe Telom and Lemoi river catchments through the 3-metrediameter transfer tunnels, with respective lengths of 8,500metres and 7,500 metres to the Susu Dam storage.

Apart from presenting the project key features and howit works, the talk also touched on the excavation of thetunnels, which is a major part of the construction work. Theconstruction of the Main Access Tunnel (MAT) involving theexcavation of a top heading in soft material using canopytubes, steel ribs and shotcrete for support was highlighted.Upon reaching competent rock, the tunnel excavation

WATER RESOURCES TECHNICAL DIVISION

Tunnel construction within Lemoi river catchment

Page 2: Highlights on the Ulu Jelai Hydroelectric Projectdspace.unimap.edu.my/dspace/bitstream/123456789/23407/1/aug 10.pdf · The Ulu Jelai Hydroelectric Project is a 372 MW ... long unlined

FORUM

August 2012 JURUTERA | 31

would be continued by drill and blast methods. Tunnelling inrock for the Telom and Lemoi tunnels would be carried outusing a Tunnel Boring Machine (TBM).

The talk was followed by a lively Q&A session betweenthe participants and the speakers. Most of the questionswere related to the return on investment (ROI) of theproject, as well as environmental and operational issues.The session ended with a memento presentation to thespeakers.

Construction of the Main Access Tunnel (MAT)

CONGRATULATIONS

The IEM Council wishes to congratulate Y.Bhg.Academician Dato’ Ir. Lee Yee Cheongfor being appointed Pro-Chancellor of KualaLumpur Infrastructure University College. IEM

Y.Bhg. Academician Dato’ Ir. Lee a platform toassist in human resource capacity building for infrastructuredevelopment in the country.