HCTC Timeline for Implementation HCTC Timeline for Implementation Critical Dates: April 4, 2003 Record File Format approved by DOL and IRS. April 7 – June 6, 2003 SWAs receive Program Logic Document and UIPL with instructi what programming must be completed. Completed NLT June 6, 2003. May 15 – June 13, 2003 Lockheed Martin (ICON) will verify that the SWAs are able t the approved record layout file. Certification may begin sooner. May 26 – 28, 2003 ICON will verify that the record layout submitted by the SWAs can be transmitted to the IRS contractor, Accenture. June 12 – July 1, 2003 The SWAs will submit completed record layout files to ICON the data and files are received with no errors. July 21 – 31, 2003 Validation of Deployment. This process will ensure that the process i complete. It will ensure that the file processing is working as well resolution portion. August 1, 2003 The HCTC program is implemented. August 1, 2003 HCTC Program Implemented April 7, 2003 Program Logic Document to SWAs April 7, 2003 UIPL to SWAs May 26 - 28, 2003 Certification of Interface between ICON and HCTC May 15 – June 13, 2003 Certification of Interface between ICON and SWAs June 12 – July 1, 2003 Integration Testing with all SWAs July 2 – 21, 2003 Deployment of Systems July 21 – 31, 2003 Validation of Deployment April 4, 2003 Approval of Record File Format April 7 – June 6, 2003 SWAs Programming

Upload: alisa

Post on 06-Jan-2016

33 views

Category:

Documents


0 download

DESCRIPTION

April 4, 2003 Approval of Record File Format. May 15 – June 13, 2003 Certification of Interface between ICON and SWAs. July 21 – 31, 2003 Validation of Deployment. April 7, 2003 Program Logic Document to SWAs. June 12 – July 1, 2003 Integration Testing with all SWAs. July 2 – 21, 2003 - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: HCTC Timeline for Implementation

HCTC Timeline for HCTC Timeline for ImplementationImplementation

Critical Dates:April 4, 2003 Record File Format approved by DOL and IRS.April 7 – June 6, 2003 SWAs receive Program Logic Document and UIPL with instructions on

what programming must be completed. Completed NLT June 6, 2003.May 15 – June 13, 2003 Lockheed Martin (ICON) will verify that the SWAs are able to send

the approved record layout file. Certification may begin sooner.May 26 – 28, 2003 ICON will verify that the record layout submitted by the SWAs can be

transmitted to the IRS contractor, Accenture.June 12 – July 1, 2003 The SWAs will submit completed record layout files to ICON to ensure

the data and files are received with no errors. July 21 – 31, 2003 Validation of Deployment. This process will ensure that the process is

complete. It will ensure that the file processing is working as well as the resolution portion.

August 1, 2003 The HCTC program is implemented.

August 1, 2003HCTC Program Implemented

April 7, 2003Program Logic Document to SWAs

April 7, 2003UIPL to SWAs

May 26 - 28, 2003Certification of Interface between ICON and HCTC

May 15 – June 13, 2003Certification of Interface between ICON and SWAs

June 12 – July 1, 2003Integration Testing with all SWAs

July 2 – 21, 2003Deployment of Systems

July 21 – 31, 2003Validation of Deployment

April 4, 2003Approval of Record File Format

April 7 – June 6, 2003SWAs Programming