hazard identification plan (hip) haradh

Upload: asif-khanzada

Post on 02-Mar-2016

533 views

Category:

Documents


64 download

DESCRIPTION

Fugro-suhaimi format for Saudi aramco

TRANSCRIPT

PROJECT EXECUTION PLAN FOR

HSE IDENTIFICATIN PLAN

Project No. SA14-1159 Page: 11 of 10

HSE IDENTIFICATIN PLAN

Project No. SA14-1159

Page: 16 of 16

Hazard IDENTIFICAtion PLAN FOR

Geotechnical Investigation

Southern Area Power Reliability Enhancement Detail Design of

13.8 kV Overhead Power Transmission Line

Haradh Area, Saudi ArabiaPrepared by: Fugro-Suhaimi Ltd. (FSL)

Issue Status

Issue No.DatePrepared ByApproved By

0.011 Aug 2014KJ / NCSAA

Table of Contents

Page1.0 INTRODUCTION..3

1.1 Project Definition..3

PURPOSE AND SCOPE OF WORK..4

1.2 Purpose and scope of work.................

4

2.0 HEALTH, SAFETY AND ENVIRONMENTAL POLICY STATEMENT..5

3.0 ORGANIZATIONAL STRUCTURE..63.1 Rules and Responsibilities .63.2 HSE Advisor (HSEA) .63.3 Project Manager (PM) ..63.4 Safety and Health Officer ..63.5 Site HSE Coordinator .64.0 SITE COMMUNICATIONS ...85.0 EMERGENCY MEDICAL ASSISTANCE - HARADH ..95.1 EMERGENCY RESPONSE DUTIES AND COMMUNICATIONS ...9

5.2 Mobilization Plan / Resources Availability .

16

6.0 HAZARD CLASSIFICATION ...

17

7.0 CLASS A HAZARDS ...18

7.1 DRILLING ..

18

7.2 HEAVY EQUIPMENT

197.3 ELECTRICAL .

197.4 ENERGIZED EQUIPMENT.

207.5 FIRE PREVENTION ..

207.6 WELDING / CUTTING .207.7 UN-AUTHORIZED SITE ACCESS 217.8 EXCAVATION ..218.0 CLASS BAND C HAZARDS 22 8.1 POWER TOOLS 23 8.2 CHEMICALS ..

24 8.3 COMPRESSED AIR EQUIPMENT .

25 8.4 PPE ..

26 8.5 WORK PERMIT .271.0 INTRODUCTION1.1 Project DefinitionGeotechnical Investigation Southern Area Power Reliability Enhancement Detail Design of 13.8 kV Overhead Power Transmission Line Haradh Area, Saudi ArabiaPURPOSE AND SCOPE OF WORK1.2 Purpose and Scope of Work Drilling 875 Nos. borehole to a maximum depth of 6-m depth into soil or 3-m into rock whichever is shallower; and

Performing 875 Nos. electrical resistivity tests.

1.3 HEALTH, SAFETY AND ENVIRONMENTAL POLICY STATEMENT

It is the policy of Fugro-Suhaimi Ltd that at all times the health and safety of our employees will be paramount. The prevention of accidents and occupational injuries or illness is of such importance as to be given precedence over productivity whenever necessary. Under this policy, we include contractors, temporary workers, and clients representatives working on Company premises, and on job sites that are under our control. Management seeks to implement this Policy by providing a healthy and safe working environment to meet the highest standards.

Fugro-Suhaimi Ltd maintains a Health, Safety, and Environmental Protection Management System (HSE MS) conforming to the best practice of organizations of our type. The System provides a process for implementation of our stated Policy and compliance with Saudi Arabian laws and regulations. Only the full cooperation of all concerned can ensure the System will work. The System is documented in the Health, Safety, and Environmental Protection Manual to promote awareness of the Safety Policy, safe working practices, and a healthy lifestyle among our employees and others associated with the Company. It is through the System and its successful implementation that our good record of health and safety can be maintained.

Fugro-Suhaimi Ltd also recognizes that the environment is a major influence on the health of people, not least that of our employees, their families, and their descendents. Maintenance of safety is difficult in a hazardous environment. Environmental protection is therefore an intrinsic part of our health and safety policy.

Fugro-Suhaimi Ltd is therefore committed, under the Policy, to implementing the following actions:

to provide safe and healthy working conditions, and to ensure that all company works have minimal adverse effect upon the health and safety of anyone;

to provide sufficient and appropriate information, training, and instructions to all employees concerning health and safety issues;

to develop and implement procedures designed to ensure that safe-working practices and environmental protection are operating effectively and are encouraging healthy and safe conditions throughout the Company; and

to comply with all applicable Saudi Arabian laws and regulations.

Fugro-Suhaimi Ltd recognizes that responsibility for health and safety is shared along the following guidelines:

the Management of the Company is responsible for leadership in implementing the System and for creating a safe and healthy working environment, insofar as possible;

Supervisors are responsible for developing proper attitudes to health and safety in themselves and in those they supervise, and for ensuring all operations under their control are conducted with full regard for the health and safety of all personnel, including themselves; and

Employees are responsible for working in the safest way possible and for cooperating fully with the spirit of the System as well as the safety rules given in the Health, Safety and Environmental Protection and Employees Safety Handbook. 1.4 ORGANIZATIONAL STRUCTURE

This section of the Health and Safety Plan describes lines of authority, responsibility, and communication as they pertain to health and safety functions at this site. The purpose of this chapter is to identify the personnel who impact the development and implementation of the site health and safety plan and to describe their roles and responsibilities.

1.5 Roles and Responsibilities

All personnel and visitors on this site must comply with the requirements of this Health and Safety Plan. The specific responsibilities and authority of management, safety and health, and other personnel on this site are detailed in the following paragraphs. A site organizational chart illustrating the hierarchy of personnel and lines of communication within this company and with additional contractors on site is found in Figure 1-1.

1.6 HSE Advisor (HSE A).

The principle Safety Manager for all FSL projects is Mr. Kamran Jawaid, who is responsible for the implementation and compiling of FSLs Safety Systems.

1.7 Project Manager (PM)

The Project Manager (PM) for this site is Mr. Ashfaq Andrabi. The PM has responsibility and authority to direct all work operations. The PM coordinates safety and health functions with the Safety and Health Officer (SHO), has the authority to oversee and monitor the performance of the SHO, and bears ultimate responsibility for the proper implementation of this HASP.

The specific duties of the PM are:

Preparing and coordinating the site work plan; providing site supervisor(s) with work assignments and overseeing their performance; coordinating safety and health efforts with the SHO; ensuring effective emergency response through coordination with the FSL Laboratory Manager at Yanbu; serving as primary site liaison with public agencies and officials and site contractors.

1.8 Safety and Health Officer (SHO)

The Safety and Health Officer (SHO) for this company is Mr. Norman Canedo. The SHO has full responsibility and authority to develop and implement this HASP and to verify compliance. The SHO reports to the HSE Manager. The SHO has the authority to halt site work if unsafe conditions are detected. The specific responsibilities of the SHO are:

Managing the safety and health audits on this site; coordinating with the Project Manager, Site Supervisor(s), and others as necessary for safety and health efforts.

1.9 Site HSE Coordinator The Site HSE coordinator for this site is to be decided later on.The HSE coordinator is responsible for field operations and reports to the Project Manager (PM). The HSE coordinator ensure the implementation of the HASP requirements and procedures in the field. The specific responsibilities of the HSE coordinators are:

Executing the work plan and schedule as detailed by the PM; ensuring site monitoring, worker training, and effective selection and use of PPE; assessing site conditions for unsafe acts and conditions and providing corrective action; assisting the preparation and review of this HASP; maintaining effective safety and health records as described in this HASP; coordination with the Safety and Health Officer (SHO) at Dammam; ensuring site work compliance with the requirements of this HASP.

1.10 SITE COMMUNICATIONSAll the staff will be provided with cell phone for emergency contact .In addition, site personnel are trained to recognize and use hand signals when visual contact is possible but noise or PPE inhibit voice communication. These hand signals are listed below

SignalMeaning

Thumbs upOK/understood

Both arms waving upright above headNeed assistance/send support

Arms horizontal and circling out to sidesSituation under control

Clutching throatOut of air/cannot breathe

Emergency Contact Details FSL DAMMAM HEAD OFFICE038574200

Dlip G. Lakhani (Division Manager)Ext.2010504943876

Kamran Jawaid (HSE-Advisor)Ext.1480564050510

Norman Canedo (HSE-Officer)Ext.1490555881952

Mukhtar Ahmed (Drilling Manager)Ext.2020505855961

Syed Ashfaq Andrabi (Project Manager)Ext.2070564052407

Pratish Maheshwari (Project Engineer)Ext.2030564050513

Muhammad Ijaz (Drilling Senior Supervisor)Ext.1490506857010

1.11 Emergency Medical Assistance - haradh

The nearest emergency medical assistance within 150 Km selected to support this site is:

Almana General Hospital - Hofuf Building

Al Najah StreetHofuf Area50367Saudi Arabia

City:Al Ahsa

City Suffix:31982

Tel:+966 13-588-7000

Fax:+966 13-588-7005

Region:Eastern Province

1.12 EMERGENCY RESPONSE DUTIES AND COMMUNICATIONS

Duties of HSE CoordinatorThe HSE Coordinator shall contact the nearest hospital and to request medical advice and evacuation facilities assistance from FSL Head Office in Dammam. He shall also plan a contingency route to take the casualty to nearest emergency services if available.

The HSE Coordinator shall immediately report to the Project Manager about nature and type of emergencies and also FSL Drilling Manager in Dammam to get any immediate assistance that may be required giving the following information:

Name of injured person;

Location, time of illness or injury;

Cause of illness or injury;

Description of illness or injury;

Medical information required;

Any treatment already given;

Preventative action taken;

Present location;

Evacuation method and steps being taken.ATTACHMENTS

JSAJOB SAFETYANALYSISContractor:Fugro - Suhaimi Ltd

JSA no01Work Permit:

Date:01 July 2014Reviewed /

Approved by SAA

TASK : Drilling Of Boreholes and Electrical Resistivity Tests

Employee Name and Job Title:

Kamran Jawaid , HSE AdvisorAnalyst and Date: Kamran Jawaid, 1 July 2014

Division:

Geotechnical DivisionApproved By and Date: Syed Ashfaq Andrabi, 1 July 2014

Personal Protective Equipment (PPE) Required Or Recommended: First Aid Kit, Sunscreen, Hard Hats, Gloves, Safety Steel Toed Shoes With Non-slip Soles, Water Cooler, and Yellow Safety Vest.

MAIN STEPS OF TASKEach step is for a specific part of the task.

POTENTIAL HAZARDSIdentify the hazards relating to each step.

CONTROL ACTIONS NEEDED TO REDUCE RISKList the controls required to reduce the risk in each step.

1. Prepare for site visitLoss in the middle of desert Prepare listing of emergency phone numbers, both on and offsite; complete appropriate training before going on site. Provide appropriate person in office your itinerary. Familiarize self with site prior to visit.

2. Identify site/activity PPE needs; Check contents of PPE equipment for complete inventory.

Personal injuryInspect all PPE and equipment and ensure that it is working properly and meets all TR guidelines and manufacturer specifications.

3. Carrying equipmentSlips, trips, falls, strainHandle equipment properly

4. Ensure health of employeesInsect/animal born diseaseEnsure that First Aid training is current, and encourage tetanus boosters.

Ensure that environmental hazards training is completed for field hazards including snake and other animal hazards

5. Assess weather conditions to be encountered during site visit

Heat stroke

Sun burn

Wind burn

HypothermiaFamiliarize self with signs of heat related illnesses: cramps, heat rash, dehydration, heat exhaustion, and heat stroke. Additionally, review associated weather guidelines, procedures and training (fluid intake, sunscreen use, proper clothing, work scheduling etc.)

Keep body protected; wear sunscreen, wide brimmed hat or hardhat (depending upon PPE needs and FSL policy).

Wear layered clothing, gloves, hard hat with winter liner, etc.

During cold weather - layer clothing and wear wind impervious outerwear; during warm months wear a long sleeve cotton/breathable fabric shirt and pant.

6. Carry and load samples and other itemsTrip/fall/strainUse wheelbarrow, hand cart, and employ proper ergonomics and lifting techniques.

7. Equipment liftingBack injury from improper liftingGet help from a coworker to carry and load coolers and other equipment.

8. Insure vehicle has been properly maintainedVehicle accident

Vehicle wont start at the sitePerform quick vehicle inspection for obvious items such as tire inflation, windshield wipers, sufficient fuel to get to destination, observe State guidelines for use of a state vehicle: make certain procedures regarding accidents, injuries, vehicular break downs or roadside emergencies are available in vehicle.

9. Proceed to vehicle/Travel to & from siteMoving vehicles on road or in parking areas/traffic hazards

Slip/Trip/Fall

Vehicle contact with fixed or movable objectsBe attentive when crossing traffic and walking within parking areas. Map route to site; have area map available; follow defensive driving practices.

Do not attempt to walk on surfaces suspected of being slippery due to ice, rain or other conditions

Conduct a walk-around inspection of the vehicle for fixed or movable objects around and/or behind vehicle before entering and driving the vehicle.

10. Vehicle Operations Vehicle vs. vehicle collisions, vehicle vs. fixed object collisions

Vehicle accidents

Vehicle fire

Do not use cell phones when driving. Do not use paper or electronic maps when driving. The passenger should act as the navigator and read off the directions to the driver. The drivers only task is driving the vehicle in a safe and courteous manner. Follow posted speed limits.

Decrease speed in limited sight and rain conditions. Follow one vehicle length per 10 miles of speed. Move to the left lane when vehicles are stopped or workers are present on the right shoulder. Always use turn signals and makes sure all lamps are in working order before each trip. Always wear seat belts. All vehicles must be equipped with a first aid kit

All vehicles must be equipped with a working fire extinguisher.

Never park a warm engine vehicle in tall grass. Avoid engine fuel spills.

11. Assess site conditionsSevere weather conditions

Wind borne contaminants

Physical contact hazards

Fire hazards

If weather has changed since leaving the office or previous site, ensure that proper precautions are taken before beginning site work. Monitor lightning detectors and stop work when alarm alerts closer than 20 miles.

Obtain wind direction information and identify upwind on site map.

Always wear steel toed safety shoes, safety glasses, and hard hats.

Be alert of fire conditions. Do not enter uncontrolled burning areas. Minimize flammables in and near vehicle and work area.

12. Ensure vehicle/equipment/ security on sitePassing Traffic

Theft, vandalism

Contact with fixed or movable objectsBe alert, secure area from through traffic with safety cones, traffic warning signs, use amber colored strobe lights, and wear site/activity appropriate PPE. Pull over at least 4 feet on shoulder from white line. Use parking brake

Always lock vehicle, do not leave valuables in vehicle, cover/keep from view equipment left in vehicle.

Conduct a full walk-around of vehicle and place orange marker cones behind and/or in front of the vehicle.

13. Conduct visual inspection of facility/site layoutIrritated site owner/neighbors

Dangerous surroundings

Animals (dogs), snakes, stinging

insects, ticksBe courteous and diplomatic. Identify yourself immediately. Always wear identification.

Do not enter site unless accompanied by another employee or site personnel. Wear safety shoes, protective eyewear, hearing protection, and hard hat.

Identify areas where biological hazards may be present; wear insect repellant on all exposed skin surfaces; wear long sleeve shirt and full length pants; avoid high grass areas if possible; tuck pants leg into boot; do not put hand/arm into/under an area that you can not see into/under clearly; do not touch any suspected contaminant without appropriate hand PPE; wash hands as soon as possible upon completion of task.

Drilling of Boreholes

14. The drilling crew brings pipe from the rack up to the drilling floor and places it in the boreholeBeing struck by or caught between tubular and other objects during movement.

Slip, Trips, and FallsBurns , or physical injury caused by Contact with skins or eyes

Take precaution when lifting pipesStand clear of suspended and moving loadsWear appropriate PPE including eye and face protection

15. Preparing drilling fluidSlip , Trips, and FallsBurns ,or physical injury caused byContact with skins or eyes

Stand clear of suspended and moving loadsWear appropriate PPE including eye and face protection

16. Starting of Drilling

Receiving strain and sprains during lifting or controlling movement of drill collars, bit breaker, pipe and tongs

Use proper lifting technique

17. Preparing to break out pipePinching fingers or other body parts between slip handles and rotary tables

Implement effective , safe work procedures forusing slips and tongs

18. House KeepingSlip/ Trip due to scattered drilling debris. Follow FSLs SWP & Use proper PPE

Electrical Resistivity Test

19. Using of AA Size Alkaline Battery for power supply of electrical resistivity meter.Battery leakage.

Unexpected high voltages to appear at the current and voltage probes.

Presence of toxic gasses in the area.Technician should wear rubber protective gloves (ANSI/ ASTM D120 or equal) while making connections and use a rubber safety mat (ANSI/ASTM D178 or equal) while operating the ERT meter.

Mobilization Plan / Resources Availability

To carry out the field work, we plan to mobilize the following personnel to the site: geotechnical supervisor/Geologist drillers; and

Helpers.

We plan to mobilize the following equipment to the site:

Two drilling rig and the associated water truck;

Tank, drill pipes and miscellaneous tools;

Hand tools;

Electrical Resistivity Test Equipment;6.0 Hazard Classification:Location of Hazard Area has been identifiedPotential riskThe definition of Hazard is the possibility of loss and/or injury to people and property.The following HAZARDS classes have been identified in this project:Class A Hazards:A condition or practice likely to cause permanent disability, loss of life or body part and/or extensive loss of structure, equipment or materials.Class B Hazards:A condition or practice likely to cause serious injury or illness (resulting in temporary disability) or property damage that is disruptive, but less severe than Class AClass C Hazards:A conditions or practice likely to cause minor (non-disability) injury or illness or non- disruptive property damage.The project has been evaluated in terms of the three (3) hazard classes and specific hazards in each class have been identified. A corrective action is recommended for each hazard.POTENTIAL RISKClass A HazardClass B/C Hazards1.Drilling1.Power tools

2.Heavy Equipment2.Chemicals

3.Electrical3.Compressed air equipment

4.Energized Equipment4.Personal Protective Equipment

5.Fire Prevention5.Work Permit

6.Welding & Cutting

7.Unauthorized Site

Access

8.Excavation

Class A Hazards:1. DRILLINGAll courses of actions pertaining to drilling shall be in compliance with Saudi Aramco Construction Safety Manual (SACSM), section 2 in Part II.The causes of drilling accidents and losses are any of (but not limited to) the following:a. By falls of equipment and persons.b. By lifting heavy object hitting personnel.c. By hitting with underground utilities.d. By inadequate tools & equipment.e. By unfavorable weather condition.Safety Measures to be taken:a. Obtain Work Permits from Saudi Aramco.b. Consider the following factors before starting any drilling works.i. Size and purpose of drillingii. Nature of the site condition including the proximity of made-up land and adjacent structures.iii. Proximity of land obstruction such as pipes and cables.iv. Weather conditions.v. Traffic site condition.vi. Method of drilling.c. Present drilling plan to include depth of drilling, location, and underground utilities to Saudi Aramco Utilities and obtain Saudi Aramco Representatives approval on all areas to be drilled.

d. Erect/install adequate safety warning at all times.e. Excess sample materials should not be discarded into the nearby lot but rather it should be dumped to designated dumping area.2. HEAVY EQUIPMENTAccidents can be caused by workmen actions and/or unanticipated mechanical failure of machinery.Heavy equipment such as boom rig will be needed during the hoisting of heavy pipe, and the materials used in the work. Where a mechanical hoisting machine is used for lifting, special procedures outlined in the FUGRO-SUHAIMI HSE manual shall be followed. Hazards can arise from the following: A defective lifting device or crane. Unqualified equipment operator. Defective lifting accessories, clamp, hooks, sling, etc. Non-stable rig positioning. Non use of personal protection devices, i.e. hard hats, gloves, goggles, safety vest, etc. Improper rigging. Improper signaling between the rigger guiding the load and the lifting operator. Failure to follow heavy lift procedures.Rig Operators shall be fully conversant in the lifting capacity of rig at various angular positions.Recommended Action: Inspection of equipment by Saudi Aramco Oil Company inspection Unit. Provide warning signs of clearance limit. Rated load of the machine marked on each side. Only licensed, qualified persons shall be permitted to operate lifting equipment. Only trained and qualified riggers shall be allowed to attach slings to loads being lifted. Special custom designed hook, clamp or other lifting accessories shall be marked with (SWL) safe workload. Conduct frequent and periodic inspection of lifting of equipment, accessories and slings. Damaged or unsafe accessories and

slings shall be immediately removed from the site. When slings are not in use they shall be stored in location safe from possible

damage or misuse. While equipment is traveling, hoisting or lowering is not allowed. Carrying people on the load is prohibited. Machines are not to be refueled with engines running. Fire extinguisher shall keep in the vicinity of the equipment performing the lift. Barricadetheareaduringliftingoperationandredirect traffic/personnel. Post back-up spotter for all heavy equipment. Instruct operations of heavy equipment not to operate equipment with workers in the immediate area Operators must be certified and have valid Saudi Government license. 360 degree clear view required for all vehicles. Heavy equipment operator sunshades obstructing clear view are

prohibited. Regular inspection for hydraulic leaks, breakage, tires, slings, etc Post signs Danger-Keep Away in Arabic and English. Provide designated parking area in and around job site. Remove keys and/or disconnect battery cables, ensure, equipment is correctly parked, e.g. crane booms lowered, parking

brakes applied. Provide escort when moving. Lifting operation of heavy equipment/structure such as structural steel, Unistruts, etc. shall be witnessed by Project Inspection

and Loss Prevention representatives, as required. Survey site for utility hazards such as overhead wire, and develop special operating procedures for working in their vicinity.3. ELECTRICAL:b. Portable Electrical Equipment and Flexible Cords:Distribution and electrical power on construction site is different from permanent installations. Hazards will arise when: Unqualified electricians carry out electrical work. Defective electrical equipment is used. Electrical equipment is not grounded. Electric circuits have no ground Faults Interrupter (GFI) breakers. 220 Volts outlets are used. Damaged cord or plugs are used.Recommended Action: Ensure that only qualified electrician use electrical equipment. Inspect electrical equipment and tool that will be used, remove any damaged ones from site. Regularly check grounds faults circuit interrupters. Check for use of grounds fault circuit interrupters (GFIs). All receptacle outlets should be 120 volts single-phase 15 and 20 amps. Visually inspect portable cords, plug connected equipment and flexible cord sets for damage.4. ENERGIZED EQUIPMENTHazards can be arises as a result of unexpected release of energy in the isolated equipment. Power disconnection/Isolation shall be in accordance withG.I. 6.012 Isolation Lockout and Hold Tags.Safety Measure to be Taken:a. Lockout / Tag out system shall be used when maintaining the electrical equipment.b. After isolation or power disconnection, residual energy in the system must be removed before work begins.c. Prior to commencing work on energized equipment, isolating locations and type of isolating devices shall be identified.d. Each lock on a piece of equipment must have a tag indicating the date and time of lockout, name, badge number of lock

installer and the reason for the locks installation.e. Hold Tag shall not be removed without the approval of the electrical supervisor.5. FIRE PREVENTION:Danger of fire represents one of the serious hazards to life and property on a construction site. Potential fire hazards result from the following conditions:-Storage of flammable or combustible materials on the site. Fuel and oil leakage equipment. Failure to enforce no smoking rules. Poor housekeeping which allows combustible debris to buildup in the building or on the site. Improperly installed or poorly maintained temporary electrical systems. Poor welding & cutting procedures. Poor ventilation when using substances which generate flammable gasses or sprays. Failure to provide adequate firefighting equipment on the site and failure to train workers in proper steps to take if

a fire is started.Recommended Action:The following actions will be implemented to minimize fire hazards: A plan shall be developed and approved to provide for safe storage of flammable and combustible materials on the site. Equipment shall be stored in areas where fuel and oil leakage will not present a hazard to material storage areas or

the construction area. Fuelling operations must not take place in construction or storage areas. No smoking rules shall be strictly enforced. A designated smoking area shall be provided away from the construction or

material storage areas. Trash and debris shall be removed from the site on a daily basis. Temporary electrical cables and equipment shall be inspected regularly by a qualified electrician and any damages

repaired immediately. Fire watch procedures shall be used during all welding and cutting operations. Adequate ventilation shall be provided by fans or other means whenever flammable gases or sprays are generated in

enclosed areas. Fire extinguishers and water barrels shall be available at all times on the site. Placement of firefighting equipment on the site shall be according to the location of the various fire hazards present and in accordance with a plan approved by loss Prevention. Fire extinguisher shall be regularly checked for pressure and kept in working order. Water barrels shall be kept filled. All workmen and supervisors are to be trained in what measures they can safety take to deal with a fire on the site before regular firemen are needed. Routine inspection shall be made at the end of each working day to ensure that everything is left in safe and secured

manner.6. WELDING AND CUTTING:On-site welding and cutting will be required in case slight repair of mechanical part is needed during various phases of geotechnical activity. All operations should be in compliance with FUGRO-SUHAIMI HSE Manual under the fire prevention. Hazards will arise from molten slag, ultraviolet rays, open flames, hot electrodes and electric shock. These hazards are increased if defective or improperly used.Recommended Action:The following actions will be implemented to minimize any welding and cutting hazards: Grease and oil must never be used near oxygen. Acetylene cylinders shall be stored, handled and used in vertical position/ SAUDI ARAMCO color coding of cylinders should be recognized bywelders and other workers. Protection from temperature extremes. Store oxidizers away from flammable cylinders. Provide warning signs. All welding equipment shall be examined immediately before use and regularly maintained. All welding and cutting equipment shall be of SAUDI ARAMCO approved type and operated in accordance with

the latest SAUDI ARAMCO industry safety procedures. Prohibit smoking or other sources of fire near welding or cutting equipment. Provide fire extinguisher with each welding or cutting equipment set Provide a standby man for fire watch during welding or cutting operations. Oxygen and acetylene cylinders shall be stored at least 20 ft apart unless separated in a storage shed, by a barrier with

one hour fire rating. Compressed gas cylinders shall be secured in the upright positions at all times. Non-current carrying metal part of welding machines shall be grounded.7. UNAUTHORIZED SITE ACCESS:Access to the site by unauthorized personnel greatly increases the chance of serious injury on the site to an authorized visitor who may be unaware of the dangers and not know what precautions are necessary. Workers on the site may become distracted from their work by the presence of the unauthorized visitor and may become involved in an accident. Access to the site shall be controlled as follows. Place a full time guard on the site controlling the entrance gate, with instructions not to allow anyone on the site without gaining permission to enter from the site office. If there is more than one gate for the site. Visitors should be reminded to check out when leaving the site. All visitors to the site shall be accompanied by someone knowledgeable of the specific hazards that they may be exposed to. Enforce requirements that visitors wear hard hats, safety shoes, and other clothing appropriate for the site conditions.8. EXCAVATIONAccidents can occur for excavations which are not shored or doesnt have any support. Any man-made depression in the earths surface should be shored & supported, sloped or benched to prevent the sidewall to collapse.Unsafe excavation has caused many unexpected accidents at our work sites including shutting down equipment process unit, damage to equipment, personal injury and fatality. Potential Hazards include the following: Cave-in of the sidewall. Build-up of toxic or flammable atmosphere. Accidental contact with underground utilities Falling into the excavationRecommended Action: All excavation must be sloped or benched in case the depth of excavation exceeds 1.2m deep. Install traffic signs & barricades to warn commuters and other workers. Install flares, lanterns or flashing warning lights to clear mark the entire excavation at night. Cover the pit if possible before leaving the project site. Assign flagman as standby man whenever possible to ward off other workers from excavation. Let the Gas testing be performed if it is necessary prior to enter the excavated area. Assign a standby man when workers are working in the pit if it is more than 1.2m deep. Excavation must be backfilled if it is no longer needed. Shoring is discouraged due to time consuming and costly activity with more hazards than sloped or benched method.Class (B/C) Hazards:1.POWER TOOLS:Power tools allow many jobs to be carried out more efficiently and with greater speed and accuracy. Hazards will arise when unskilled and untrained labors are allowed to operate power tools. Usage of power tools should be in compliance with Saudi Aramco Construction Safety Manual (SACSM), section 10 in Part II.Recommended Action:Only those persons who are qualified are allowed to use power tools.Foreman of the trade shall make sure that these craftsmen utilize tools in a safety manner.All electrically operated tools shall be rated and used at a voltage not exceeding 125 volts.Before any electrical tools are used, a careful check shall be made by the supervisor to ensure that the supply voltage is within the range on the ID/equipment plate. All electrical circuits shall be protected by (GFI).All operators shall use eye, head, or ear and hand protection.Do not leave tools or equipment on the job site after work hours. Return to store yard or provide lock boxes.All power hand tools shall be property grounded and be of the double insulated type.2.CHEMICALSChemical substance is a source of health hazards because of their harmful content. Handling of chemical shall be in accordance with FUGRO-SUHAIMI HSE manual on page 19 of 20. Hazards can arise from the following:a. Inhalation of chemical vapors and gas that acid generate.b. Harm to skin.c. Harm to the eyes.d. Slip cause by spilled material.e. Bad housekeeping of material and equipment during application.f. Fire hazard from flammable substances.Safety Measure to be Taken:a. Use of acid proof apron to protect body in case of acid spill.b. Use of proper moth, nose and eye protection devices during application.c. Use a respirator with filters recommended for the product that is being applied.d. The respirators shall be used by a trained user which they have medical fit for using the respirator and have been fit-tested

for proper seal of face-to-respirator rubber.e. Ensure that proper ventilation is continuously maintained.f. Use of hand/skin protection during handling and application.g. Maintain good housekeeping.h. Quick removal of spilled material and the use of warning signs in such cases.i. Ensure that clear water available close by when working with acid to wash eyes in case of acid spill.j. Both material and application equipment shall be stored properly in suitable temperature storage.k. Keep fire extinguisher nearby when using materials, which have a low flash point.l. Storage of acid in proof containers and proper sealing prior to transportation must be checked thoroughly.3.COMPRESSED AIR EQUIPMENTThe mechanical failure of noisy compressed equipment or associated accessories, i.e. air supply hoses can cause minor or major injury. Therefore, certain safety precautions have to be taken to eliminate this type of hazard:Recommended Action:Ensure that operator uses earplugs and other required personal protection devices.Continuously visual inspection and check of the equipment and accessories, especially the air supply hose. Damaged hose shall not be used.Air hoses must be positively secured at connection points when in use.Ensure that air compressors are monitored by another person to continuously observe the pressure of the supplied air and that pressure relief valves are functioning properly.4.PERSONAL PROTECTIVE EQUIPMENTPersonal Protective Equipment is required in most major course of operation. This will require reducing an employee from exposure to hazards. When it has been decided that personal protective equipment is required, then a proper implementation must take place to choose what type of equipment is required and that a supervising personnel must ensure that his people is knowledgeable to the use and proper care of his equipment.Recommended Action:Protective equipment such as clothing, helmets, goggles, or other garment designed to protect the wearers body from injury by sudden impacts, electrical hazards, heat, chemicals, and infections.Safety personnel must be strict in implementing the use of PPE to its people and a daily check up before start of work shall be enforced.5.WORK PERMITWork Permit procedure incorporates procedures that are common in industrial facilities and a proper communication and guidelines take place. In this manner, hazards are being controlled.Recommended ActionBefore the start of work, especially in industrial area, work permit must be accomplished and filled.Security offices are commonly in charge for the issuance of work permit.Guidelines and precautionary measure must take place in order to acquire work permit.Figure 1-1 Organizational Chart

Organizational chart with lines of authority.

_1346493581.vsdNameTitle

NameTitle

NameTitle

NameTitle

NameTitle

NameTitle

Team Title

NameTitle

Company Name

Company NameDepartment Name

NameTitle

NameTitle

NameTitle

NameTitle

PROJECT MANAGER

Drilling MANAGER

Health & Safety Officer

Drafting Section

Project Engineer

Survey Sub - Contractor

FIELD CREW

WORKSHOP

Geologist

GEOTECHNICAL DIVISION MANAGERDILIP.G.LAKHANI