hampton comp waterway management plan my briefing remarks 121410

Upload: asoundidea

Post on 09-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Hampton Comp Waterway Management Plan My Briefing Remarks 121410

    1/6

    Hampton Comp Waterway Management Plan

    12/14/10 Briefing Notes on Previous Studies

    by Fred Whitley, PE, URS Corporation

    [Listing of studies slide] Introductory remarks:

    This briefing is to help the steering committee understand what

    work the city has already done on this subject, so it can be aware

    of what has been recommended and/or implemented and perhaps

    utilize and/or build on some the previous work

    The summaries of these studies are contained in the notebooks, in

    Tab N

    These summaries are based on the full studies, which are available

    for reading on both the citys website and the project websiteThe order has been changed slightly from what is in the notebooks

    and this briefing will be a summary of those summaries.

    1) Newmarket Creek Flooding [Title slide]

    Initiated in March 2007 by council to address citizen

    concerns about flooding along Newmarket Creek

    There are 3 primary causes for flooding in Hampton:

    1. Higher than normal tide (includes wind driven waves)

    2. Rainfall intensity exceeding the capacity of the storm

    drains, drainage ditches and canals

    Page 1 of 6

  • 8/8/2019 Hampton Comp Waterway Management Plan My Briefing Remarks 121410

    2/6

    3. Obstructions in the storm drainage system- naturally

    occurring and manmade- fallen trees, illegal dumping

    ( even grocery carts)

    Some areas of the city are only affected by 2 out of the 3 causes.

    But, because of its geography and heavy vegetation, NewmarketCreek is highly susceptible to all three.

    The study was conducted by a 15 member citizens

    committee supported by city staff and a consultant, working

    together for about 4 months

    [Aerial Slide]Watershed aerial slide-(orientation)/what is a

    watershed? (This is the largest watershed in Hampton)

    Watersheds dont respect municipal boundaries-drains some

    of NNews/most of the watershed is in Hampton

    Waterway flows out past the Coliseum and under Mercury

    Blvd and La Salle Ave, near Riverdale, to the Back River

    Background- flooding in Newport News/Hampton- 1960s

    Corps constructed project for northern segment ( Newmarket

    Shopping Center) solved part of the flooding problem

    Today there is recurring flooding all along the creek with one

    of the worst areas around the Paula Maria/City Line Road

    Apts Study involved a series of meetings with the committee and

    the public and the committee noted some ideas which they

    didnt recommend along with some ideas that they did

    recommend.

    [refer to list slides]

    2) Mary Peake Watershed Study- [Title slide]

    This study was the result of the Newmarket Creek Study- it

    did not involve a citizens committee

    [aerial slide] This area is a subset of the Newmarket Creek

    basin ( orientation)

    Page 2 of 6

  • 8/8/2019 Hampton Comp Waterway Management Plan My Briefing Remarks 121410

    3/6

    [aerial slide ] Describe subwatershed boundaries- describe

    canal system in this area, draining higher ground, how

    development spread that way from downtown, and

    distinguish with lower lying areas drainage.

    This was the first project of its kind commissioned by the

    city, using sophisticated computer modeling of thewatershed- this modeling inputs all of the topography,

    drainage pipes, ditches and development in the area across

    the entire watershed and it show how for various rainfall

    intensities, where there will be bottlenecks in the drainage

    system and the probable extent of the flooding. It can also

    reveal how a modification in the drainage system, or a new

    development, might affect the drainage in the rest of the

    system. The study identified a number of specific projects that would

    improve the drainage in the watershed which are identified in

    the full report- most of these involve the replacement of

    undersized drainage pipes.

    City is considering these drainage improvements in its capital

    improvements planning.

    3) Farmington Canal Area Drainage Study [Title slide]

    This study was commissioned as a result of street and yard

    flooding from several storms in 2007- highest land in the city

    ( approx 20 above sea level) but still susceptible to flooding

    in a heavy rainfall event

    [Map slide] This slide shows the study area (orientation)

    History- Bethel High School construction- drainage canal

    dug- years ago this area was known as Sawyers Swamp, and

    Big Bethel Road was then known as SS Road The new canal allowed subdivisions to develop in the area

    -Farmington, Forest Ridge and Micheals Woods in

    accordance with subdivision design standards but, this was

    before the city had computer tools like watershed modeling-

    Page 3 of 6

  • 8/8/2019 Hampton Comp Waterway Management Plan My Briefing Remarks 121410

    4/6

    each subdivision designed to drain its own water w/o looking

    at the bigger picture in the canal.

    Study identified deficiencies in the canal that slowed the flow

    of water- city has the corrective work done

    Some areas still susceptible to backwater in a major storm

    when the Newmarket Canal outfall becomes full of stormwater.

    Study raises the question of doing future modeling of the

    Newmarket canal watershed, perhaps by the Corps since the

    watershed includes two cities

    4) Pochin Place Canal [Title slide]

    [Aerial photo slide] This is another watershed study usingcomputer modeling, this time in the Wythe area ( orientation)

    History of Wythe development- before there were

    subdivision design standards with drainage calculations

    requirements, drainage systems were expanded as far as

    possible without much regard for downstream capacity

    Recognizing this problem, the city has completed a number

    of drainage improvements in this watershed- diversion of

    some water near Pembroke, a dry basin , and canal widening

    at lower end

    But, flooding along the canal still occurs in major storms

    primarily due to downstream channel siltation and tidal

    encroachment from Hampton Roads

    Study recommended tide gate at Kecoughtan Rd, and

    dredging of waterway. City is working on a project to get

    easements from adjacent property owners for dredging, and

    permits from the Corps and VMRC would be required.

    5) Corps of Engineers- Ches. Bay Storm Damage Reduction

    Study [Title slide]

    This was the mother of all studies, performed by the

    Army Corps of Engineers, taking 8 years and costing many

    Page 4 of 6

  • 8/8/2019 Hampton Comp Waterway Management Plan My Briefing Remarks 121410

    5/6

    hundreds of thousands of dollars (and hundreds of trees

    lives). The Corps follows a very regimented, phased process

    that results in an end product that is very thorough, its just

    very tedious and expensive. Fortunately for Hampton, most

    of the expense was federally funded.

    [Aerial slide of shoreline]. The study began by looking atthe environmental impacts, probable costs and benefits of

    improving Hamptons shoreline along the Ches Bay in order

    to increase the ability of the shoreline/ adjacent structures to

    withstand damage from flood tides and wave action ( coast is

    a mosaic of ownership, some areas are developed and some

    undeveloped)

    A number of public meetings were held to discuss the project

    Corps primary criteria for funding actual improvements is thebenefit/cost ratio, and only a few areas had a benefit cost

    ratio greater than 1, the public beach areas that had

    development in the vicinity ( in order to have something to

    protect)

    Some areas opted out of the study due to not wanting to grant

    public access, such as Malo Beach

    Final report identified Buckroe Beach as an eligible project.

    Council committed a cost share and, in 2005, the Corps

    oversaw the pumping of sand on the beach from an offshore

    source (which has a very large quantity of beach quality

    sand) to provide more storm damage protection. Sand was

    also pumped onto the Salt Ponds public beach at 100% local

    expense.

    Periodic beach nourishment is required as sand is constantly

    drifting away- however, breakwaters have been added to

    slow the movement of sand. One was in place at the time of

    the Corps project, one was added last year and a third will beconstructed in a few months.

    6) Floodplain Management Plan- [Title slide]

    [Study results slide]

    Page 5 of 6

  • 8/8/2019 Hampton Comp Waterway Management Plan My Briefing Remarks 121410

    6/6

    7) Salt Ponds Inlet Study [Title slide]

    Ken Dierks will talk about this one since he was involved in

    the study

    8) Back River Flooding and Shoaling [Title slide]

    Background- rapid disappearance of the sand spit at the

    mouth of the Back River [ Aerial photo of before condition]

    known to most as Factory Point ( former menhaden

    processing plant in late 1800s)

    Gave rise to concerns about increased susceptibility to waves

    in the Back River, shoreline erosion, loss of the recreational

    feature, loss of wildlife habitat, and an increase in siltation of

    the boating channels in the vicinity Council authorized citizens committee to look into this, with

    staff and consultant support

    Committee had a number of findings [Findings slide] and

    recommendations[Recommendations slide]- their highest

    priority was the restoration of Factory Point

    Many of these findings and recommendations are relevant

    still to what this committee will be considering

    After 6 months of design effort, over 2 years of permitting

    effort, and constant battles with Mother Nature, in the spring

    of this year, boating channels were widened and deepened,

    and FactoryPoint was restored, and this is what the finished

    product looks like, with breakwaters added to protect the

    restored spit. [After aerial photo]

    Questions?

    Page 6 of 6