gunn’s hill wind farm o r final...gunn’s hill wind farm design and operations report final june...

81
GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario L8R 2L3 Tel: 905-528-1747 Fax: 866-203-6516 Email: [email protected]

Upload: others

Post on 18-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

GUNN’S HILL WIND FARM

DESIGN AND OPERATIONS REPORT

FINAL

June 2013

Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario L8R 2L3 Tel: 905-528-1747 Fax: 866-203-6516 Email: [email protected]

Page 2: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

January 8, 2014

Reference: Notice of Project Design Change – Gunn’s Hill Wind Farm

PLEASE NOTE:

The Renewable Energy Approval (REA) Application for the Gunn’s Hill wind Farm was submitted to the Ontario Ministry of the Environment (MOE) in June, 2013.

The tap line connecting the project substation to Woodstock Transformer Station will no longer be required, as connection will be at or near the substation itself.

The tapline has been removed from Project mapping, but there are no changes to the Draft REA Reports provided to the MOE for review.

Please note there are no new environmental effects due to removal of the tap line from the Project description.

Page 3: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 i  

TABLE OF CONTENTS 1. INTRODUCTION ........................................................................................................................1

1.1. PURPOSE .............................................................................................................................1

1.2. PROJECT BACKGROUND .........................................................................................................5

2. FACILITY DESIGN PLAN............................................................................................................6

2.1. SITE PLAN ............................................................................................................................8

2.2. PROPERTY ASSOCIATED WITH THE RENEWABLE ENERGY GENERATION FACILITY ...........................8

2.3. WIND TURBINES ................................................................................................................ 10

2.4. ELECTRICAL INFRASTRUCTURE ............................................................................................. 15

2.5. ROADS, TURBINE LAY-DOWN AREAS AND CRANE PADS .......................................................... 18

2.6. O&M BUILDING ................................................................................................................. 19

2.7. EXISTING STRUCTURES WITHIN 300 M OF THE FACILITY ........................................................ 19

2.8. UTILITY CORRIDORS WITHIN 300 M OF FACILITY ................................................................... 20

2.9. STORM WATER MANAGEMENT............................................................................................. 20

3. FACILITY OPERATION PLAN .................................................................................................. 21

3.1. TURBINE OPERATION AND MONITORING................................................................................ 21

3.2. PLANNED MAINTENANCE .................................................................................................... 22

3.3. UNSCHEDULED MAINTENANCE ............................................................................................ 23

4. EMERGENCY RESPONSE AND PREPAREDNESS PLAN....................................................... 23

4.1. WIND FARM EMERGENCY RESPONSE BACKGROUND ............................................................. 23

4.2. ENTITIES AND ROLES .......................................................................................................... 25

4.3. EMERGENCY RESPONSE CHAIN OF COMMUNICATION ............................................................. 29

4.4. NON-EMERGENCY COMMUNICATIONS PLAN .......................................................................... 31

5. POTENTIAL ENVIRONMENTAL EFFECTS AND MITIGATION MEASURES............................. 33

5.1. PERFORMANCE OBJECTIVES ................................................................................................ 33

5.2. HERITAGE AND ARCHAEOLOGICAL RESOURCES ...................................................................... 33

5.3. NATURAL HERITAGE RESOURCES ......................................................................................... 35

5.4. AQUATIC RESOURCES ......................................................................................................... 40

5.5. AIR QUALITY AND ENVIRONMENTAL NOISE ............................................................................ 42

5.6. LAND-USE AND SOCIO-ECONOMIC RESOURCES...................................................................... 45

5.7. EXISTING LOCAL INFRASTRUCTURE....................................................................................... 50

5.8. WASTE MANAGEMENT AND CONTAMINATED LANDS ............................................................... 54

5.9. PUBLIC HEALTH AND SAFETY ............................................................................................... 57

Page 4: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 ii  

6. ENVIRONMENTAL EFFECTS MONITORING PLAN ................................................................ 68

6.1. ENVIRONMENTAL MANAGEMENT SYSTEMS ........................................................................... 69

6.2. PROGRAMS, PLANS, AND PROCEDURES................................................................................ 70

6.3. MONITORING REQUIREMENTS AND CONTINGENCY PLANS....................................................... 72

6.4. COMMUNITY RELATIONS ..................................................................................................... 76

L IST OF TABLES  

Table 1 Design and Operation Report Requirements ..............................................................1  

Table 2   O. Reg 359/09 Setback Requirements .......................................................................7  

Table 3   Property Associated With the Project...........................................................................8  

Table 4   Siemens SWT-3.0-113 Specifications ...................................................................... 10  

Table 5   Siemens SWT 3.0-113 Acoustic Emissions Summary............................................. 12  

Table 6   Automatic Shutdown and Restart In High Winds ..................................................... 12  

Table 7   Setback Distances from Turbines ............................................................................. 14  

Table 8   Turbine Setbacks from Lot Lines............................................................................... 15  

Table 9   Norwich TWP and Woodstock Fire Department Resources..................................... 27  

Table 10   Ambulance Resources Within 20 km of Project....................................................... 27  

Table 11   Local Radio Broadcast Contacts ............................................................................... 28  

Table 12   Local TV BROadcast contacts.................................................................................... 28  

Table 13   Total Expected Quantities of Waste Fluids ............................................................... 55  

L IST OF FIGURES Figure 1 Project Location Within Ontario....................................................................................6

Figure 2 Directional Bore Under Utility (or Road/water Feature) .......................................... 17

Figure 3 Emergency Communication Chain from EPC during Construction/Decomm……… 29

Figure 4 Emergency Communication Chain from Public during Construction/Decomm…… 26

Figure 5 Emergency Communication Chain from OMT during Operation ............................. 30

Figure 6 Emergency Communication Chain from Public during Operation........................... 30

Page 5: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 iii  

LIST OF APPENDICES Appendix A Site Plan

Appendix B Property Line Setback Assessment Report

Appendix C Turbine Specifications Report

Appendix D Noise Assessment Report

Appendix E Sample Emergency Preparedness Template

Appendix F Environmental Effect Monitoring Plan

Appendix G Preliminary Impact Study – Identification of Telecommunications Systems

Appendix H Local Aerodrome Assessment

Page 6: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 1  

1. INTRODUCTION

1.1. Purpose

This   report   outlines   the   information   requested   under   Item   4   of   Table   1   in   Ontario  Regulation   359/09   regarding   Renewable   Energy   Approvals   under   Part   V.0.1   of   the  Environmental   Protection   Act.   The   report   also   includes   information   suggested   in   the  Ministry  of  the  Environment  publication  Technical  Bulletin  #2:  Guidance  for  Preparing  the  Design  and  Operations  Report  as  Part  of  an  Application  Under  O.  Reg  359/09.  

The  documentation  requirements  as  specified  under  O.  Reg.  359/09  are  summarized  in  Table  1.    

TABLE 1 DESIGN AND OPERATION REPORT REQUIREMENTS

Requirements Completed Section Reference

1. Set out a site plan of the project location at which the renewable energy project will be engaged in, including,

i. one or more maps or diagrams of,

A. all buildings, structures, roads, utility corridors, rights of way and easements required in respect of the renewable energy generation facility and situated within 300 m of the facility,

Appendix A

B. any ground water and surface water supplies used at the facility, Appendix A

C. any things from which contaminants are discharged into the air, N/A N/A

D. any works for the collection, transmission, treatment and disposal of sewage, Appendix A

E. any areas where waste, biomass, source separated organics and farm material are stored, handled, processed or disposed of,

N/A N/A

F. the project location in relation to any of the following within 125 m: the portion of the Oak Ridges Moraine Conservation Plan Area that is subject to the Oak Ridges Moraine Conservation Plan, the area of the Niagara Escarpment Plan, the Protected Countryside, the Lake Simcoe watershed, and

N/A N/A

G. any noise receptors or odour receptors that may be negatively affected by the use or operation of the facility, Appendix A

ii. a description of each item diagrammed under subparagraph i, and Section 2

iii. one or more maps or diagrams of land contours, surface water drainage and any of the following, if they have been identified in complying with this Regulation: properties described in Column 1 of the Table to section 19, heritage resources, archaeological resources, water bodies, significant or provincially significant natural features and any other natural features identified in the Protected Countryside or in the portion of the Oak Ridges Moraine Conservation Plan

Appendix A

Page 7: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 2  

Requirements Completed Section Reference Area that is subject to the Oak Ridges Moraine Plan,

iv. a description, map or diagram of the distance between the base of any wind turbines and any public road rights of way or railway rights of way that are within a distance equivalent to the length of any blades of the wind turbine, plus 10 metres,

Table 7

v. a description, map or diagram of the distance between the base of any wind turbines and all boundaries of the parcel of land on which the wind turbine is constructed, installed or expanded within a distance equivalent to the height of the wind turbine, excluding the length of any blades, and

Table 8

vi. a description, map or diagram of the distance between the base of each wind turbine and the nearest noise receptor. Table 7

2. Set out conceptual plans, specifications and descriptions related to the design of the renewable energy generation facility, including a description of,

i. any works for the collection, transmission, treatment and disposal of sewage, including details of any sediment control features and storm water management facilities,

Section 2.6, 2.9

ii. any things from which contaminants are discharged into the air, and N/A N/A

iii. any systems, facilities and equipment for receiving, handling, storing and processing any waste, biomass, source separated organics, farm material and biogas,

N/A N/A

iv. if the facility includes a transformer substation, the works, facilities and equipment for secondary spill containment. N/A N/A

3. Set out conceptual plans, specifications and descriptions related to the operation of the renewable energy generation facility, including,

i. in respect of any water takings,

A. a description of the time period and duration of water takings expected to be associated with the operation of the facility,

Section 2.6

B. a description of the expected water takings, including rates, amounts and an assessment of the availability of water to meet the expected demand, and

Section 2.6

C. an assessment of and documentation showing the potential for the facility to interfere with existing uses of the water expected to be taken,

Section 2.6

ii. a description of the expected quantity of sewage produced and the expected quality of that sewage at the project location and the manner in which it will be disposed of, including details of any sediment control features and storm water management facilities,

Section 2.6, 2.9

iii. a description of any expected concentration of air contaminants discharged from the facility, N/A

N/A

iv. in respect of any biomass, source separated organics and farm material at the facility

Page 8: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 3  

Requirements Completed Section Reference

A. the maximum daily quantity that will be accepted, N/A N/A

B. the estimated annual average quantity that will be accepted, N/A

N/A

C. the estimated average time that it will remain at the facility, and N/A

N/A

D. the estimated average rate at which it will be used, and N/A N/A

v. in respect of any waste generated as a result of processes at the project location, the management and disposal of such waste, including,

A. the expected types of waste to be generated Section 5.8.1

B. the estimated annual average quantity that will be accepted, N/A N/A

C. the estimated average time that it will remain at the facility, and N/A N/A

D. the estimated average rate at which it will be used, N/A N/A

vi. if the facility includes a transformer substation,

A. a description of the processes in place to prevent spills, N/A N/A

B. a description of the processes to prevent, eliminate or ameliorate any adverse effects in the event of a spill, and N/A N/A

C. a description of the processes to restore the natural environment in the event of a spill. N/A N/A

4. Include an environmental effects monitoring plan in respect of any negative environmental effects that may result from engaging in the renewable energy project, setting out,

i. performance objectives in respect of the negative environmental effects, Section 5, Appendix F

ii. mitigation measures to assist in achieving the performance objectives mentioned in subparagraph i, Section 5, Appendix F

iii. a program for monitoring negative environmental effects for the duration of the time that the project is engaged in, including a contingency plan to be implemented if any mitigation measures fail.

Section 5, Appendix F

5. Include a response plan setting out a description of the actions to be taken while engaging in the renewable energy project to inform the public, aboriginal communities and municipalities, local roads boards and Local Services Boards with respect to the project, including,

i. measures to provide information regarding the activities occurring at the project location, including emergencies, Section 4

ii. means by which persons responsible for engaging in the project may be contacted, and Section 4.4.2

Page 9: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 4  

Requirements Completed Section Reference

iii. means by which correspondence directed to the persons responsible for engaging in the project will be recorded and addressed.

Section 4.4.2, 5.5.3

6. If the project location is in the Lake Simcoe watershed, a description of whether the project requires alteration of the shore of Lake Simcoe, the shore of a fresh water estuary of a stream connected to Lake Simcoe or other lakes or any permanent or intermittent stream and,

i. how the project may impact any shoreline, including the ecological functions of the shoreline, and N/A N/A

ii. how the project will be engaged in to,

A. maintain the natural contour of the shoreline through the implementation of natural shoreline treatments, such as planting of natural vegetation and bioengineering, and

N/A N/A

B. use a vegetative riparian area, unless the project location is used for agricultural purposes and will continue to be used for such purposes.

N/A N/A

7. If it is determined that the project location is not on a property described in Column 1 of the Table to section 19, provide a summary of the matters addressed in making the determination.

N/A N/A

8. If section 20 applies in respect of the project and it is determined that the project location does not meet one of the descriptions set out in subsection 20 (2) or that the project location is not in an area described in subsection 20 (3), provide a summary of the matters addressed in making the determination.

N/A N/A

9. If subsection 21 (3) or 23 (2) applies, provide a summary of the matters addressed in making the determination,

i. under subsection 21 (3) or clause 23 (2) (a), as the case may be, including a copy of the document completed under the applicable provision, and

N/A N/A

ii. under clause 23 (3) (b), if applicable. N/A N/A

 

A   preliminary   version   of   this   report   has   been   made   available   to   Aboriginal  stakeholders,  public  stakeholders  and  agency  stakeholders  for  review  prior  to  the  REA  submission.  This  report  will  also  be  available  online  for  download  at  www.prowind.ca  and   available   in   hard   copy   at   select   locations   identified   on   the   website   and   in  newspaper  advertisements.    

A  final  version  of  this  report  is    included  in  the  REA  submission  to  the  Ontario  Ministry  of  the  Environment  (MOE).  

Page 10: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 5  

1.2. Project Background

The  Gunn’s  Hill  Wind  Farm  is  a  25  MW  project  that  is  categorized  as  a  Class  4  Facility  under  O.  Reg  359/09.  The  wind   farm  will   employ   the  use  of  up   to   ten  wind   turbines  from   the   Siemens   SWT   3.0-­‐113   family   with   a   maximum   power   output   of   2.5   MW.    These  wind  turbines  have  a  hub  height  of  99.5  m  and  a  rotor  diameter  of  113  m  for  a  total   height   of   156  m.     The  wind   farm  will   also   consist   of   access   roads,   a   substation,  underground   cabling   to   connect   the   turbines   to   the   substation,   and   above   ground  cabling  to  connect  the  substation  to  the  tap  line.  

The   project   is   proposed   on   privately   owned,   agricultural   land   neighbouring   the  Hamlets  of  Oxford  Centre  and  Curries,  Ontario;  located  approximately  5  km  southeast  of   the   City   of   Woodstock,   Ontario.   The   project   area   containing   the   turbines   and  associated   infrastructure   is   bounded   by   Firehall   Road   to   the   north,   Oriel   Line   to   the  east,  Gunn’s  Hill  Road  to  the  south,  and  Highway  59  to  the  west.    

The  overhead  line  that  connects  the  wind  farm  to  the  Woodstock  Transformer  Station  will   use   existing   poles   along   Firehall   Rd,   County   Road   59,   Patullo   Ave,   Athlone   Ave,  Juliana  Dr,  Cedar  Creek  Gold  Club,  Parkinson  Rd  and  South  St.  

Figure  1  illustrates  the  project  location  within  Ontario.  

Page 11: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 6  

FIGURE 1 PROJECT LOCATION WITHIN ONTARIO

2. FACILITY DESIGN PLAN

This  section  provides  design  description  and  detail  for  each  element  of  the  Gunn’s  Hill  Wind   Farm   as   well   as   the   significant   features   that   lie   within   300   m   of   the   project  boundary.  

The   proposed   Project   Location   is   shown   in   Appendix   A   and   includes   the   following  major  components  of  the  Project:  

• Up  to  10  Siemens  SWT  3.0-­‐113  wind  turbines  (2.5  MW  maximum  power);    

• Step  up  transformers   located  at  or  within   the  base  of  each  turbine  (step  up  voltage  approximately  0.69  kV  to  27.6  kV);    

• Underground   fibre   optic   cables   and   electrical   collection   lines   (27.6   kV)   and  ancillary  equipment  (e.g.,  above  ground  electrical  junction  boxes)  to  connect  the  turbines  to  the  proposed  substation;  

Page 12: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 7  

• Substation   which   switches   the   underground   electrical   collection   lines   to  overhead   lines   and   contains   the   necessary   protection   and   control,   switchgear,  and  communication  equipment  to  safely  operate  the  project;  

• An  approximately  6.5  km  underground  and  overhead  dedicated  tap  line  (27.6  kV)  on   Hydro   One   and   Woodstock   Hydro   poles   to   connect   to   the   provincially  controlled  electrical  grid  (through  the  Woodstock  Transformer  Station).    

• Turbine  access  roads;      

• Turbine   laydown   and   storage   areas   (including   temporary   staging   areas,  crane  pads  and  turnaround  areas  surrounding  each  wind  turbine);  

• Temporary   construction   infrastructure   (including   laydown   areas   for  construction   materials,   construction   trailers,   storage   sheds,   parking   areas,  concrete  wash  ponds);  

• Optional   Operations   and   Maintenance   building,   with   permanent   parking  and/or  storage  shed.  

The  setbacks  that  govern  project  design  are  summarized  in  Table  2.  

TABLE 2 O. REG 359/09 SETBACK REQUIREMENTS  

O N T A R I O R E G U L A T I O N 3 5 9 / 0 9 S E T B A C K D I S T A N C E S

S e t b a c k D i s t a n c e ( M e t r e s ( m ) )

D e t a i l s

Noise Receptors 550* To be measured from the centre of a turbine’s base to a noise receptor.

Property Line Hub height (99.5)

Setback can be reduced to blade length plus 10 m (66.5 m total) measured from the centre of the turbine’s base to the nearest property boundary if a property line setback assessment report demonstrates that siting turbines closer will not cause adverse effects.

Roads And Railway

Blade length plus 10 m

Blade length plus 10 m (66.5 m total) measured from the centre of the turbine’s base to the boundary of the right-of-way.

Significant Natural Heritage Features

120 Measured from the project location boundary to the nearest point of the natural features. Project components may be sited closer than the prescribed setback if an environmental impact study is prepared.

Water Bodies 120

Measured from the average annual high water mark of a lake, or permanent / intermittent stream (Project components may be sited closer than 120 m if a Water Body Report is prepared - note that turbines and transformers may not be sited closer than 30 m to these features).

Petroleum Resources 75

Setback may be reduced with the submission of a Petroleum Engineer’s Report to the MNR.

Note:    *   Setback  does  not  apply  to  noise  receptors  on  land  owned  by  a  Proponent  of  a  wind  energy  facility  or  by  a  person  who  has  entered  into  an  agreement  to  permit  all  or  part  of  the  facility  on  their  lands.  

Page 13: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 8  

 

A  Property  Line  Setback  Assessment  Report  has  been  prepared  in  accordance  with  s.53  (3)   of   O.   Reg.   359/09,   and   is   one   component   of   the  REA   application   for   this   Project.    The   purpose   of   this   report   is   to   provide   a   review   of   potential   adverse   impacts   and  preventative  measures   for  wind   turbines   located  within   the  prescribed   setback   from  non-­‐participating  parcels  of  land  (i.e.,  where  there  is  no  agreement  with  the  landowner  specifically  permitting  a  closer  setback).  A  copy  of  the  report  is  provided  in  Appendix  B.  

2.1. Site Plan

A   site   plan   diagram   for   the   Gunn’s   Hill   Wind   Farm   is   provided   in   Appendix   A.   As  specified  in  Table  1  of  O.  Reg  359/09,  the  site  plan  diagram  details  the  location  of  the  following:  

1. property  associated  with  the  renewable  energy  facility,  

2. all  turbines,  buildings,  structures,  roads,  utility  corridors,  rights  of  way  and  easements  required  in  respect  of  the  renewable  generation  facility  and  situated  within  300  m  of  the  facility,  

3. noise   receptors,   as   defined   in   the   MOE   October   2008   document  entitled  “Noise  Guidelines  For  Wind  Farms”,  

4. land   contours,   surface   water   drainage,   and   if   applicable   heritage  resources,   archaeological   resources,   water   bodies,   and   significant   or  provincially  significantly  natural  features,  and  

5. a  boundary  indicating  120  m  from  project  infrastructure.  

2.2. Property Associated with the Renewable Energy Generation Facil ity

Properties   that   will   host   project   turbines,   roads,   substation,   and/or   cabling   are  presented  in  Table  3.  

TABLE 3 PROPERTY ASSOCIATED WITH THE PROJECT

Property ID on Site Plan

PIN# Listed Owners Legal Description

P1 00073-0004 Southlea Farms Ltd.

Part Lots 17 and 18, Concession 5, in the Township of Norwich (formerly the Township of East Oxford), County of Oxford, as described in Deed 280248

P2 00073-0031

David W. Start and Susan V. Start

Part Lot 16 and 17, Concession 5, in the Township of Norwich (formerly the Township of East Oxford), County of Oxford, as described in Deed 278250

Page 14: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 9  

Property ID on Site Plan

PIN# Listed Owners Legal Description

P3 00073-0069(R) Huinink Farms Inc.

Part of Lot 14, Concession 6, Township of Norwich (formerly Township of East Oxford) in the County of Oxford as 1stly described in Deed 453303 East half of the southwest ¼ of Lot 14, Concession 6, Township of Norwich (formerly Township of East Oxford) in the County of Oxford as 2ndly described in Deed 453303

West half of the southeast ¼ of Lot 14, Concession 6, Township of Norwich (formerly Township of East Oxford) in the County of Oxford as 3rdly described in Deed 453303

P4 00073-0073(R)

Joseph Bernard McKiernan and Marjorie Joyce McKiernan as joint tenants

Joseph Bernard McKiernan and Marjorie Joyce McKiernan as joint tenants as to a ½ interest Pamela Denise McKiernan and Ivan Douglas McKiernan as joint tenants as to a ½ interest

Part of Lots 13 and 14, Concession 6, Township of Norwich (formerly the Township of East Oxford), in the County of Oxford, as 1stly described in Deed No. 470968

Part of Lots 13 and 14, Concession 6, Township of Norwich (formerly the Township of East Oxford), in the County of Oxford, as 2ndly described in Deed No. 470968

P5 00074-0004(R)

Lloyd Alyea & Sons Limited

Part of Lot 12, Concession 5, Township of Norwich (formerly Township of East Oxford) in the County of Oxford (Deed 268419)

P6 00074-0006(R)

Jan Boudewin Reyneveld

Part of the south half of Lot 11, Concession 5, Township of Norwich (formerly Township of East Oxford) in the County of Oxford as described in Deed 486287

P7 00074-0005

Bartus Jan Veldhuizen and Jane Klazina Veldhuizen

East Part of the south half Lot 11, Concession 5, Township of Norwich, formerly Township of East Oxford, County of Oxford, previously described in Instrument Number A97548 (Deed #445641)

P8 00074-0048

Robert Neutel and Gerry Neutel

Part of Lot 12, Concession 6, Township of Norwich (formerly Township of East Oxford), County of Oxford, designated as Part 1 on Plan 41R-851

P9 00074-0049(R) Sonya Ann Neutel

South ¾ of the east half of Lot 12, Concession 6, Township of Norwich (formerly Township of East Oxford), in the County of Oxford as 1stly and 2ndly described in Deed 340761

Page 15: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 10  

Property ID on Site Plan

PIN# Listed Owners Legal Description

P10 00074-0038 1050185 Ontario Inc.

North ½ of Lot 11, Conc. 6 as 4thly described in Deed and Part of Lot 10, Conc. 6 as 5thly described in Deed 387184, Township of Norwich, formerly Township of East Oxford, County of Oxford

P11 00074-0050

Rutherford Farms Limited

Southwest ¼ of Lot 10, Conc. 6, and South ½ of Lot 11, Conc. 6, Township of Norwich, formerly Township of East Oxford, County of Oxford

P12 00074-0035 John W. C. Rutherford

1stly: South ¼ of Lot 10, Concession 5 and 2ndly: Easterly 2k/3 of the Northeast ¼ of Lot 10, Concession 6, Township of Norwich, formerly Township of East Oxford, County of Oxford, as described in Deed 286078

 2.3. Wind Turbines

2.3.1. Specif ications

The   project   will   consist   of   up   to   ten   wind   turbines   from   the   Siemens   SWT   3.0-­‐113  family  rated  for  a  maximum  output  of  2.5  MW.  Full  turbine  specifications  are  included  in  Appendix  C.    The  wind  turbines  are  3-­‐bladed,  upwind  horizontal–axis  turbines  that  utilize   direct   drive   technology,   which   avoids   the   need   for   a   gearbox.   This   reduces  sound  output  and  increases  efficiency.  The  turbines  have  a  113  m  rotor  diameter  with  a  swept  area  of  10,000  m2.    

Table   4   summarizes   key   turbine   parameters,   Table   5   summarizes   the   Siemens   SWT  3.0-­‐113   acoustic   emission   data   used   in   the   Noise   Assessment   Report   (contained   in  Appendix  D),  and  Table  6  details  certain  wind  conditions  under  which  the  turbine  will  automatically  shut  down  as  a  protective  measure.  

TABLE 4 SIEMENS SWT-3.0-113 SPECIFICATIONS

General Manufacturer Siemens Model SWT 3.0 113 Name plate capacity (MW) 2.5 MW Cut-in wind speed (m/s) 3-5 m/s (10.8 – 18 km/hr) Cut-out speed (m/s) 25 m/s (90 km/hr) Frequency (Hz) 50 or 60 Hz Max Sound power (dBA) 102.5 dBA Tonal audibility <2dB Rotor Blade length (m) 56.5 m Rotor diameter (m) 113 m

Page 16: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 11  

Rotor swept area (m2) 10,000 m2 Rotational speed (rpm) 6.0 – 15.5 rpm Structure Hub height (m) 99.5 m Total height (m) 156 m Diameter of tower base (m) ~4.2 m

   

Page 17: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 12  

TABLE 5 SIEMENS SWT 3.0-113 ACOUSTIC EMISSIONS SUMMARY

Turbine Make/Model: Siemens SWT-3.0-113

Electrical Rating: 2.5 MW

Hub Height: 99.5 m

Wind Shear Exponent: 0.50 or higher (summer night-time average)

Octave Band Sound Power Level (dBA)

Manufacturer’s Emission Levels Generic Adjusted Emission Levels

Wind Speed 6 7 8 9 10 6 7 8 9 10

Frequency (Hz)

63 89.5 89.9 91.5 91.6 91.3 89.9 89.9 89.9 89.9 89.9

125 92.6 93.0 93.0 92.5 91.7 93.0 93.0 93.0 93.0 93.0

250 96.4 96.5 95.4 94.8 94.1 96.5 96.5 96.5 96.5 96.5

500 94.9 94.8 94.4 94.2 94.0 94.8 94.8 94.8 94.8 94.8

1000 95.0 94.9 95.0 94.9 95.2 94.9 94.9 94.9 94.9 94.9

2000 94.1 94.0 95.1 95.2 95.9 94.0 94.0 94.0 94.0 94.0

4000 91.2 91.8 91.8 93.6 93.9 91.8 91.8 91.8 91.8 91.8

8000 81.8 81.9 84.1 84.1 84.1 81.9 81.9 81.9 81.9 81.9

Weighted

Total 102.4 102.5 102.5 102.5 102.5 102.5 102.5 102.5 102.5 102.5

TABLE 6 AUTOMATIC SHUTDOWN AND RESTART IN HIGH WINDS

Cutout Wind Speed

at Turbine Hub Restart Wind Speed at Turbine

Hub (after cutout event)

Approximately 25 m/s Approximately 20 m/s

 

Page 18: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 13  

2.3.2. Turbine Setbacks

Table   7   summarizes   setbacks   between   turbines   and   relevant   features   as   required   in  Table  1  of  O.  Reg  359/09  and  the  MOE  publication  Technical  Guide  to  Renewable  Energy  Approvals  (July  2011).    Setback  definitions  are  outlined  below:  

‘Nearest   Non-­‐Participating   Receptor’,   ‘Lot   Lines’,   ‘Nearest   Public   Roads’,   ‘Utility  Corridors’,   and   ‘Nearest   Structures   of   Any   Kind’   setbacks   were   determined   via  professional   surveyor   using   on-­‐site   survey   data   and   geo-­‐referenced   ortho-­‐rectified  aerial   images  of   the  project  area.  The  setbacks  were  measured  from  the  centre  of   the  turbine  base.  

Setbacks   from   ‘Cultural   Heritage   Resources’,   ‘Archaeological   Resources’,   ‘Water  Bodies’,   and   ‘Significant   Natural   Features’   were   determined   using   Ontario   Base  Mapping   data,   on-­‐site   Ecological   Land   Classification   mapping,   and   GIS   software   in  conjunction   with   ortho-­‐rectified   aerial   photography.   These   setbacks   are   measured  from  the  edge  of  the  blade  swept  area.    

Turbine   setbacks   exceed   all   applicable   provincial   regulations   outlined   in   O.   Reg  359/09.  These  setabacks  are  listed  in  Table  2  of  this  report.  

Turbine   setbacks   from   non-­‐participating   receptors   are   less   than   those   outlined   in  Section  55  of  O.  Reg  359/09.  As  such,  a  Noise  Assessment  Report  has  been  prepared  in  accordance  with   the   Ontario  Ministry   of   the   Environment’s   publication   titled   “Noise  Guidelines  for  Wind  Farms”  dated  October  2008.  The  report  is  attached  as  Appendix  D  and  demonstrates  that  the  Gunn’s  Hill  Wind  Farm  fully  complies  with  provincial  noise  regulations.  

 

Page 19: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 14  

TABLE 7 Setback Distances from Turbines

Turbine ID #

Nearest Non-

Participating Receptor

(m)

Nearest Non-

Participating Lot Line

(m)

Nearest Structure

of Any Kind

(m)

Nearest Public Road

(m)

Uti l i ty Corridor*

(m)

Cultural Heritage

Resources closer

than 120 m (m)

Archaeological Resources

Closer than 120 m (m)

Water Body

Closer than 120

m (m)

Signif icant Natural

Features Closer than 120 m (m)

1 604.4 69.3 405.6 476.8 > 1000 n/a n/a n/a 78 - woodland 78 - wildlife hab. 33 - wildlife hab.

2 609.5 147.2 430.2 331.5 > 1000 n/a n/a n/a 116 - woodland

3 781.6 145.5 675.8 659.6 > 1000 n/a n/a n/a n/a

4 650.7 82.4 422.8 667.1 > 1000 n/a n/a n/a n/a

5 611.7 140.5 396.0 525.6 677.0 n/a n/a n/a 1 - wildlife hab.

6 578.6 69.2 386.1 522.2 > 1000 n/a n/a n/a n/a

7 737.2 68.8 582.7 723.5 > 1000 n/a n/a n/a n/a

8 709.2 307.5 437.0 600.6 622.4 n/a n/a n/a n/a

9 692.6 513.2 446.6 612.1 897.7 n/a n/a n/a n/a

10 561.7 69.9 470.4 579.6 > 1000 n/a n/a n/a n/a

*Does  not  include  distance  to  utilities  in  municipal  ROW  

**  Structure  does  not  appear  on  site  plan  aerial  imagery  (new  home)  

Page 20: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 15  

TABLE 8 TURBINE SETBACKS FROM LOT LINES

 

 

NOTE:  Measurements  were  made  parallel  to  lot  and  concession  lines  

2.4. Electrical Infrastructure

2.4.1. Collection System and Tap Line

Turbines  will  be  electrically  connected  to  one  another  and  to  the  substation  by  buried    cables  referred  to  as  the  collection  system.  The  collection  system  brings  electricity  and  operational   data   from   each   turbine   to   the   control   and   switchgear   hardware   in   the  substation.  The  electricity  is  then  fed  to  the  point  of  common  coupling  (PCC)  with  the  Hydro  One  controlled  grid  via  the  tap  line.  

The  collection  system  will  consist  of  three  electrical  cables  running  at  a  system  voltage  of   27.6   kV,   a   neutral   ground,   and   a   fibre   optic   cable   for   communication   and   control  purposes.     The   grounding  wire  will   be   the   same   diameter   as   the   Hydro   One   system  grounding  wire  to  minimize  any  risk  of  “stray  voltage”.      

A   tap   line  will   be   used   to   connect   the   project   substation   to   the   existing   provincially  controlled  grid.  The  routing  of  the  tap  line  was  selected  to  follow  the  most  direct  path  that  has  existing  hydro  poles  back  to  the  point  of  common  coupling  with  the  provincial  electrical  grid.  The  selected  route  follows  Hydro  One’s  M4  feeder  to  the  low  voltage  bus  of  the  Woodstock  TS.  Where  the  M4  feeder  traverses  the  Cedar  Creek  Golf  and  Country  

Lot Line Setbacks (m) Turbine

Front Rear Side Side

1 466.32 69.85 106.59 517.45

2 319.33 1221.24 147.22 267.72

3 647.73 892.96 145.51 270.76

4 661.64 667.72 82.40 218.78

5 517.75 141.18 137.67 463.05

6 815.29 69.12 82.24 513.28

7 521.66 68.80 221.87 380.66

8 588.34 58.55 303.73 912.06

9 598.75 45.69 635.99 579.86

10 570.74 72.21 83.78 111.80

Page 21: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 16  

Club,  alternate  routes  were  considered  along   Juliana  Dr,  Norwich  Ave,  and  Parkinson  Rd,  as  well  as  through  other  nearby  residential  streets.  However,  the  route  through  the  golf  course  was  deemed  preferable.  

The   tap   line  will   be   buried   for   a   length   of   approximately   350  m   from   the   substation  west  to  the  existing  overhead  Hydro  One  poles.  The  line  will  share  the  Hydro  One  and  Woodstock   Hydro   poles   up   to   the   point   of   common   coupling   at   or   adjacent   to   the  Woodstock   TS.     The   overhead   wires   will   have   a   rated   voltage   of   27.6   kV,   which   is  common  on  Hydro  One’s  distribution  network  in  the  area.  Hydro  One  and  Woodstock  Hydro  will  determine  whether  upgrades  are  needed  to  the  existing  poles  to  support  the  additional  cables  and  perform  the  upgrades  at  the  cost  of  the  Proponent.    

The  portion  of   the   tap   line   that  will   traverse   the  Cedar  Creek  Golf  Club   lands  may  be  overhead  or  underground  depending  on  the  needs  of  the  golf  course  owners  and  Hydro  One.    

All  works  will  comply  with  Ontario  Electrical  Safety  Code  regulations.    

Installation  of  buried  cables  is  typically  done  in  two  ways:  

1. Trenched:   An   excavator   will   dig   a   trench   below   the   tile   drainage   system   in   an  agricultural  field  and  lay  all  cables  and  fibre  optic  line  at  a  depth  of  1  m  or  greater  to   avoid   conflict   with   farming   operations.   All   damage   to   tile   drainage   will   be  repaired  by  a  contractor  of  the  landowner’s  choosing.    A  small  amount  of  crushed  gravel  or   sand  may  be  used   to   line   the   trench.    Flagging  will  be  placed  above   the  buried  cable  to  provide  a  physical  warning  to  anyone  performing  future  excavation.  Material  excavated  from  the  trench  will  be  used  to  refill  the  trench  once  the  cables  are  in  place.    The  trench  will  be  compacted  in  approximately  20  cm  increments  and  the  original  topsoil  will  be  replaced.      

TRENCHLESS:  IN  CERTAIN  LOCATIONS  IT  IS  NECESSARY  TO  USE  TRENCHLESS  TECHNOLOGY  BETWEEN  TWO  POINTS  AND  RUN  CONDUIT  AND  CABLES  THROUGH  A  BOREHOLE.  THIS  METHOD  WILL  BE  USED  TO  PASS  UNDER  ROADS.

Figure  2  illustrates  how  directional  boring  will  pass  beneath  a  feature.  

The   project   requires   that   buried   cables   or   overhead   lines   be   permitted   within   the  municipal  road  allowance  for  a  3.6  km  stretch  along  Firehall  Rd  (between  Middletown  Line  and  County  Road  59)  and  a  <1  km  stretch  along  Middletown  Line  (heading  south  from   Firehall   Rd).   Any   driveways   impacted   by   cable   burial   along   this   route   will   be  promptly  repaired  at  the  expense  of  the  Proponent.  Overhead  Cables  will  also  require  road  allowance  permission  for  2.8  km  along  Hwy  59,  0.6  km  along  Pattullo  Ave,  0.7  km  along   Athlone   Ave,   0.2   km   along   Juliana  Dr,   0.2   km   along   Parkinson   Rd,   and   0.3   km  along  South  St.  All  distances  are  approximate.    

The   alternate   tap   line   outlined   above  would   result   in   the   elimination   of   the   sections  along  Hwy  59,  Pattullo  Ave,  Athlone  Ave,  Juliana  Dr,  Parkinson  Rd,  and  South  St.  

Page 22: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 17  

 

 

FIGURE 2 DIRECTIONAL BORE UNDER UTILITY (OR ROAD/WATER FEATURE)

2.4.2. Substation

The  substation  will  consist  of  an  entrance  from  Firehall  Rd,  an  internal  access  road,  and  fenced-­‐in  metal   enclosures  housing   switchgear   and   communication  hardware   for   the  project.   Construction   will   involve   the   removal   and   storage   of   topsoil   from   an   area  approximately   40   m   x   80   m   (this   is   the   same   40   m   x   80   m   area   that   will   host   the  optional   Operations   and   Maintenance   Building).     A   concrete   slab   to   host   the   metal  enclosures   will   be   poured   on   top   of   engineered   gravel   that   raises   the   grade   to   a  sufficient   height   to   prevent   standing   water   to   develop   during   spring   melt   or   heavy  rains.  

Substation   electrical   components   typically   consist   of   switchgear,   SCADA,   fuses,   and  other   protection   and   control   systems.     This   equipment   will   be   housed   in   electrical  cabinets  bolted  to  the  concrete  slab  and/or  a  small  e-­‐house  approximately  2.5  m  x  6  m  that  can  be  accessed  by  maintenance  and  emergency  personnel.    There  is  also  potential  for  a  grounding  transformer  to  be  installed  at  the  substation.  A  grounding  transformer  differs   from   and   should   not   be   confused   with   a   power   transformer   that   is   used   to  increase   voltage   for   a   power   grid   connection.   The   substation   is   not   defined   as   a  Transformer   Substation   according   to   O.   Reg   359/09   or   the   MOE’s   Oct   2008   Noise  Guidelines  for  Wind  Farms.      

The  metal  enclosures  for  the  electrical  components  will  be  bolted  to  the  concrete  slabs  outlined  above.    The  precise  dimensions  of  the  electrical  enclosures  will  be  determined  once   specific   equipment   has   been   selected   by   the   Engineering   and   Procurement  Contractor.    

Page 23: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 18  

A   small   metal   lattice   tower,   approximately   10   m   in   height,   will   be   mounted   to   a  concrete  footing.  An  antenna  will  be  mounted  on  the  tower  for  the  purpose  of  allowing  the  electrical  system  operator  to  control  the  switches  that  connect  the  wind  farm  to  the  electrical  grid.  

2.5. Roads, Turbine Lay-down Areas and Crane Pads

2.5.1. Access Roads

Access  roads  to  project  turbines  will  be  5  m  wide  during  the  operational  phase  and  will  have   a   foundation   of   ‘grade   B’   gravel   and   a   finished   surface   of   ‘grade   A’   gravel.   To  construct   the   roads  within   agricultural   fields   the   topsoil  will   be   stripped   and   spread  over   the  directly   adjacent   field  of   the   same  owner.  The   stored   topsoil  will   be   seeded  with  vegetation  suitable  to  prevent  erosion,  or  covered  with  an  erosion  control  mat,  if  required.      

Geotechnical   testing   will   determine   if   further   excavation   is   required   to   support   the  access  road  and  will  determine  the  thickness  of  each  gravel  layer.  Siemens  requires  the  roads  to  have  a  bearing  capacity  of  9072  kg  (20,000  lbs)  per  axle  plus  any  applicable  safety  margin.  Wherever  possible,  access  roads  will  be  built  such  that  the  surface  of  the  road  is  roughly  flush  with  the  field  surface  to  allow  for  minimal  disruption  of  farming  operations.   Access   roads   during   the   operation   phase   of   the   project   will   be  approximately   5   m   wide   to   accommodate   the   requirements   of   local   emergency  services.   The   extra   gravel   making   up   the   48   m   turning   radii   required   during   the  construction  phase  of  the  project  will  be  removed  during  the  operational  phase.    

2.5.2. Laydown Area

A  turbine  component  “lay-­‐down”  area  covering  approximately  1  hectare  (100  m  x  100  m)  will   be   required   around   each   turbine   during   the   construction   phase.   This   area   is  required   to   store   tower   sections,   blades,   the   nacelle   and   the   rotor   hub   during   the  construction  process  and  decommissioning  process.  The  crane  pad  will  also  be  located  within  this  area.  The  turbine   lay-­‐down  area  will  be  constructed  by  stripping  back  the  topsoil  layer  and  covering  the  area  with  gravel.  Topsoil  will  be  stockpiled  in  low-­‐lying  windrows  adjacent  to  the  lay-­‐down  area  and  will  be  seeded  with  vegetation  suitable  to  prevent  erosion,  or  covered  with  an  erosion  control  mat,  if  required.  After  the  turbine  is  installed  the  gravel  will  be  removed  from  the  lay-­‐down  area  and  the  topsoil  will  be  returned  to  remediate  the  area  for  the  operational  phase.  

2.5.3. Crane Pad

A   crane   pad   approximately   20  m   x   40  m  will   be   constructed  within   the   turbine   lay-­‐down  area  during  the  construction  phase.  The  crane  pad  will  be  constructed  of  gravel  such   that   the  bearing  capacity   is  approximately  200+  kPa.  The  gravel   from   the  crane  pad   area   will   also   be   stripped   away   and   the   topsoil   will   be   restored   after   the  construction  phase  of  the  project.    

Page 24: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 19  

Details  on  soil  storage  during  the  construction  phase  of  the  project  can  be  found  in  the  Construction  Plan  Report.  

As   with   the   laydown   areas,   the   crane   pads   will   be   remediated   for   the   construction  phase,  however   if   there   is   a  need   to   replace   a  major   turbine   component   they  will   be  reconstructed   as   outlined   the   Construction   Plan   Report   and   remediated   once   the  replacement  is  complete.  

2.6. O&M Building

An   Operations   and   Maintenance   building   may   be   constructed   to   support   the  operational  phase  of  the  project.    The  building  would  have  dimensions  up  to  16  m  x  32  m  and  would  host  office  space,  parking  for  4  vehicles,  tools,  equipment,  and  spare  parts  for   the  wind   farm.    New  and  waste   lubricants   and   fluids  would  be   stored  within   the  facility.  An  area  within  the  building  would  be  built  to  a  standard  suitable  for  hazardous  waste  storage  so  that  any  leaks  or  spills  of  waste  lubricants  from  the  site  are  contained  and  prevented  from  contacting  the  ground  or  surface  water.    

If   required,   the   building   would   be   constructed   on   the   property   with   the   substation  within   the   40  m   x   80  m   area   indicated   in   the   Site   Plan   diagram   in   Appendix   A.   The  building  would  be  constructed  on  a  standard  concrete  foundation  using  wood  and/or  steel  building  materials  that  are  typical   in  agricultural  settings.    A  new  well  would  be  drilled  to  provide  the  facility  with  water.    

The  facility  would  use   less  than  the  50,000  L/day  threshold  that  requires  a  Permit  to  Take  Water   from  MOE.  Water   usage   could   occur   at   any   hour   of   the   day   when   staff  would  be  present  and  would  be  used  for  drinking,  hand  washing,  to  supply  domestic-­‐type   hoses,   and   to   flush   toilets.   Geotechnical   drilling   and   analysis   at   the   proposed  location  indicates  that  water  levels  and  water  infiltration  rates  are  sufficient  to  support  the  facility  without  interfering  with  water  levels  at  nearby  wells.    

Sewage  would  be  handled  by  a  new  septic  system  installed  on-­‐site.  The  septic  system  could   be   comprised   of   a   storage   tank   and   a   tile   seepage   bed   installed   in   a   layer   of  gravel.   If   the   installation   of   a   septic   field   is   deemed   impractical   for   any   reason,   a  sewage  holding  tank  will  be  installed  and  will  be  pumped  out  by  a  qualified  contractor.    

2.7. Existing Structures Within 300 m of the Facil ity

All   structures   within   300   m   of   project   infrastructure   are   shown   on   the   site   plan  diagram   via   aerial   imagery.   Setbacks   from   turbines   to   the   nearest   structure   are  provided  in  Table  7  in  Section  2.3.2.    These  structures  are  all  agricultural  buildings  or  residences.  There  are  no  residences  or  buildings  within  300  m  of  a  turbine.  There  are  residences  in  Woodstock  that  are  within  300  m  of  the  tap  line  (which  is  proposed  to  be  mainly   upgraded   overhead   lines   connecting   to   the   existing  Woodstock   Transformer  Station).    The  buried  portion  will  run  within  road  easements  along  a  portion  of  Firehall  Road  and  a  portion  of  Middletown  Line.  The  overhead  portion  will   run  along  a   short  

Page 25: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 20  

section   of   Firehall   Rd   and   along   Highway   59,   Pattullo   Ave,   Athlone   Ave,   Juliana   Dr,  Cedar   Creek   Golf   Club,   Parkinson   Ave,   and   South   St   to   the  Woodstock   Transformer  Station.  

2.8. Util ity Corridors Within 300 m of Facil ity

Municipal   road   allowances   exist   throughout   the   project   area   and   carry   standard  residential   utilities   such   as   electricity,   telecommunications,   water,   and   natural   gas.  Onsite  locates  will  be  performed  before  construction  to  ensure  that  precise  locations  of  each  utility  are  marked.  

 

A  high  voltage  Hydro  One   transmission   line  runs  along   the  west  side  of  South  St  and  along   the   north   side   of   Parkinson   Rd.   The   lines   are   built   to   a   230   kV   standard,   but  currently  operate  at  115  kV.  The  corridor  is  shown  in  Appendix  A.  The  project  tap  line  will  cross  this  corridor  in  accordance  with  Hydro  One  and  ESA  specifications.  

 

2.9. Storm Water Management

Storm  water  management   features  will  be   incorporated   into  the  access  roads  where  appropriate   and   constructed   in   accordance   with   appropriate   regulations   and   local  municipal   engineering   guidelines.   In   addition,   area   drainage   from   the   distribution  substation   will   be   accomplished   through   swales/ditches   adjacent   to   the   elevated  gravelled  area  that  will  collect  and  convey  runoff.  The  total  drainage  area  associated  with   the  substation  and  associated  access  road  “hard”  surfaces   is   less   than  2  ha  and  therefore  a  “wet”  water  quality  control  pond  (i.e.  one  containing  a  permanent  pool)  is  inappropriate,  as  per   the  MOE  SWM  Planning  and  Design  Guidelines  Manual  (2003).  In   addition   to   the   conveyance   of   runoff,   the   swales   will   also   provide   water   quality  control,   which   is   a   suitable   stormwater   management   practice   for   such   an   area  according  to  the  MOE  guidelines.  

 

Page 26: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 21

3. FACILITY OPERATION PLAN

3.1. Turbine Operation and Monitoring

Turbine  operation  and  maintenance  (O&M)  will  be  either  contracted  to  a  specialized  third   party   service   provider   or   handled   by   the   project   owner   possessing  infrastructure  and  capabilities  for  this  activity.    The  O&M  service  provider  will  have  a  staff   of   trained  Wind  Turbine  Technicians,   Site   Supervisors,   and   a   data  monitoring  centre   located   in   the   O&M   building   (if   constructed)   and/or   off-­‐site   to  monitor   the  status  of  each  turbine  24  hours  per  day,  365  days  per  year.  

The   scope  of   the   activities  will   include  day-­‐to-­‐day  monitoring   and  operation  of   the  turbines  via  SCADA  hardware  and  fibre  optic  communication   linkage  as  well  as  on-­‐going  maintenance  required  on-­‐site.    

Maintenance   personnel  will   be   dispatched   to   the   site  when   required   from   either   a  service  building  located  on  site,  or  from  a  regional  service  centre.  

Turbine  monitoring  will  encompass  the  following  services  as  a  minimum:  

• Meteorological   monitoring   and   corresponding   turbine   operational   decision  making   to   ensure   that   maintenance   crews   are   not   endangered   and   that  turbine   design   specifications   are   not   exceeded   during   extreme   weather  events,   e.g.   precautionary   turbine   shutdown   and   blade   feathering   during  storms  and  extreme  events  to  prevent  damage.  Table  4  lists  automatic  turbine  shutdown  conditions  in  high  winds.  

• Turbine  performance  monitoring  and   tracking   in   relation   to  expected  power  output  to  identify  maintenance  issues,  or  issues  that  may  be  causing  increased  noise  emission.  

• Equipment   diagnostic   monitoring   for   parameters   such   as   component  vibrations,  component  temperatures,  fluid  pressures,  power  usage,  emergency  sensor  triggers,  etc.  

In   total,   approximately   500   parameters   for   each   turbine   will   be   continuously   and  remotely   monitored   by   a   service   provider   to   ensure   that   potential   issues   are  identified  and  addressed.  

Turbine  maintenance  services  will  encompass  the  following  services  as  a  minimum:  

• Response  to  issues  identified  via  turbine  monitoring  

• Scheduled  maintenance  as  per  turbine  manufacturer  requirements  and  on-­‐site  diagnostics  

• Fluid  changes  including  removal  and  disposal  of  waste  fluids  (including  those  deemed  to  be  hazardous)  

• Replacement  of  broken  or  worn  out  minor  components   such  as  yaw  motors,  pitch  actuators,  lubricant  pumps,  fuses  and  circuit  boards,  etc.  

Page 27: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 22

• Responsibility  for  general  site  cleanliness  

• Major  component  replacement  during  the  operational  phase  will  be  overseen  by  a  selected  Engineering  and  Procurement  Contractor.  

 3.2. Planned Maintenance

The  wind   turbines  will  be  subject   to  periodic   inspection  and  maintenance,   including  routine  motor  maintenance,   and   lubricant  and   fluid   replacement.    To  ensure  proper  operational   output   and   safety,   the   wind   turbines   will   be   maintained   by   certified  technicians  according  to  the  schedules  recommended  by  equipment  manufacturers.  

Regular   maintenance   activities   will   be   performed   by   a   small   crew   (2-­‐4   people)  accessing  the  site  using  a  pick-­‐up  truck.    Periodically,  major  components  of  the  wind  turbines   such   as   blades   or   generators  may   require   replacement.    Major   component  replacement  will  be  performed  with  similar  equipment  and  methods  to  those  used  in  the   construction   phase,   including   cranes   and   oversized   vehicles   for   transportation.    Crane  pads  will  be  reconstructed  as  necessary  for  this  activity.    

Through   the   Supervisory   Control   and   Data   Acquisition   (SCADA)   system   that   is  connected  to  the  fibre  optic  cables  installed  with  the  collector  lines,  the  maintenance  staff  will  be  able  to  monitor  the  performance  of  all  turbines  on-­‐line  in  real  time.    The  SCADA  system  will  also  identify  any  potential  problems  so  that  pro-­‐active  inspection  and  maintenance  can  be  undertaken.    Potentially  damaged  turbines  will  be  shut  down  until   maintenance   staff   can   perform   a   site   inspection.     Regular   maintenance   of   the  equipment  will  be  a  key  method  of  mitigating  these  potential  effects.    

Scheduled  maintenance  will  include  the  following:  

• Visual  inspection;  

• Inspection  of  mechanical  components;  

• Inspection  of  electrical  components;  and,  

• Greasing  and  general  maintenance.  

Initial   visits   for   planned  maintenance   are  more   frequent,   slowing   to   once   every   six  months   or  more   as   the  Project  matures.    Maintenance   of   each  wind   turbine   usually  takes  one  day  to  complete.    

The  proposed  turbine  for  the  project  uses  direct-­‐drive  technology  and  therefore  does  not   contain  a  gearbox  on   the  main  driveshaft.  This   results   in   significantly   less  noise  and  eliminates  the  need  for  gearbox  oil  changes.  However,  yaw  motor  oil  changes  will  be  completed  in  accordance  with  oil  analysis  recommendations.    An  oil  change  is  not  likely  to  occur  until  the  findings  of  the  annual  oil  analysis  indicate  that  it  is  required,  which  could  be  after  several  years  of  operation.    The  amount  of  oil  and  grease  stored  

Page 28: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 23

on   site   will   depend   on   availability,   transportation   schedules,   and   the   service   cycle.    The   maintenance   team   will   be   responsible   for   transport   of   used   oil   to   a   certified  disposal/recycling  site  following  maintenance.      

Access  to  all  turbines  will  be  maintained  year  round.  This  is  required  for  operations,  maintenance  and  emergency  response  purposes.  

Access  road  maintenance  contract(s)  will  be  awarded  to  a  local  service  provider.  The  scope   of   access   road   maintenance   will   include   snow   removal   and   grading   if/when  necessary   to   allow  all  maintenance  and  emergency   service  vehicles   to  drive   to   each  turbine.   Snow   will   be   ploughed   to   the   side   of   each   access   road   by   a   pickup  truck/tractor   with   a   plow   or   will   be   blown   into   adjacent   fields   belonging   to  participant   owners   by   a   tractor   mounted   snow   blower.   Other   appropriate   snow  removal  equipment  may  also  be  utilized.  Sand  will  be  applied  to  roads  as  necessary.  No  salt  or  chemical  treatments  will  be  applied  to  access  roads.  

If  needed  during  dry  conditions,  a  15,000  L  water  tank  truck  will  be  filled  off-­‐site  and  brought  to  the  project  area  for  dust  suppression  on  the  access  roads.  

3.3. Unscheduled Maintenance

The  Proponent  will  also  provide  unscheduled  maintenance  for  the  turbine  units  when  required.  Maintenance  and  inspection  related  to  the  electrical  collector  system  will  be  sub-­‐contracted.    

Temporary  crane  pads   that  may  be  required   for  unscheduled  maintenance  activities  will  be  constructed  adjacent  to  individual  turbine  sites  as  required  to  facilitate  turbine  maintenance.     The   crane   pads   will   be   in   the   same   location   as   the   crane   pads   used  during   construction   of   the   Project,   if   possible.     Operation-­‐phase   crane   pad  construction,   if   required,   will   follow   the   same   design   and   process   used   during   the  construction   phase,   as   described   in   the   Construction   Plan   Report.     As   a   result,   any  potential  effects  from  construction  of  the  crane  pads  will  be  similar  to  those  identified  during   the   construction   phase.     Disturbed   areas   will   be   restored   immediately  following  completion  of   the  maintenance  activities   in   the  same  manner  as  described  in   the   Construction   Plan   Report   unless   the   landowner   asks   for   the   crane   pads   to  remain.    

 

4. EMERGENCY RESPONSE AND PREPAREDNESS PLAN

4.1. Wind Farm Emergency Response Background

Emergency  response  at  a  wind  farm  can  involve  specialized  training,  equipment,  and  procedures  due  to  the  height  and  dynamic  nature  of  the  wind  turbines.  In  rural  areas,  such   as   the   site   of   the   Gunn’s   Hill   Wind   Farm,   it   is   common   for   local   emergency  

Page 29: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 24

services   such   as   the   fire  department   to  be   volunteer-­‐based  with   a   scope  of   service  that  does  not  cover  certain  potential  emergencies  at  wind  projects.  For  this  reason,  a  detailed  Emergency  Response/Preparedness  Plan  is  developed  with  local  authorities  once  a  project  gains  approvals  and  before  construction  occurs.  One  common  element  of   the   plan   involves   having   highly   trained   wind   farm   construction   as   well   as  operation  and  maintenance  staff  provide  emergency  services  “up  tower”  and  transfer  responsibility   to   local   emergency   services   at   a   pre-­‐determined   location   on   the  ground  such  as  at  a  point  near  a  wind  turbine  base.    

The  potential  for  coordinated  emergency  response  by  two  or  more  separate  entities  requires   that   responsibility   and   communication   structures   are   clearly   defined  between   all   groups.   The   following   sections   summarize   the   entities   involved   in  emergency  response  for  the  project,  provide  an  overview  of  their  responsibilities  and  resources   where   applicable,   define   the   communication   chain   between   them,   and  discuss   the   general   response   to   potential   emergency   scenarios   related   to   wind  projects.  

4.1.1. Construction and Decommissioning Phases

Specific  emergency  response  procedures   for  the  construction  and  decommissioning  phases  of  the  project  will  be  established  between  the  lead  EPC  conducting  the  work,  the  Proponent,  and  Local  Emergency  Services.  This  will  take  place  immediately  after  selection  of  an  EPC  and  in  advance  of  any  construction  or  decommissioning  activity  conducted  onsite.    

Response   to   emergency   scenarios   such   as   vehicle/equipment   accidents,   fire,  environmental   emergencies,   extreme  weather,   and   emergencies   “up-­‐tower”  will   be  addressed.  

To   reduce   likelihood  of   confusion,   all   turbines  will  be  assigned  a   civic   address   that  will   be   marked   on   the   road   following   standard   protocols.     This   aids   in  communication   of   the   location   of   interest   in   both   emergency   and   non-­‐emergency  situations.  

4.1.2. Operation Phase

Specific  emergency  response  procedures   for   the  operation  phase  of   the  project  will  be  established  between  the  Operation  and  Maintenance  Team  (OMT)  conducting  the  work,   the   Proponent,   and   Local   Emergency   Services.   This   will   take   place   after   a  turbine   supply   agreement   has   been   finalized   and   the   project   has   the   necessary  approvals   to   proceed   to   construction,   in   advance   of   any   construction   activity  conducted   onsite.   A   sample   Emergency   Preparedness   and   Fire   Prevention   template  that  is  adapted  by  one  turbine  manufacturer  to  each  specific  wind  farm  is  included  as  Appendix  E.  This  document  is  intended  to  provide  an  example  of  the  general  process  and   scope   of   emergency   planning   for   the   site   during   the   operational   phase   of   the  project;   this   is  NOT  a   final  Emergency  Response/Preparedness  Plan   for   the  Gunn’s  Hill  Wind  Farm.    

Page 30: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 25

4.2. Entit ies and Roles

The   emergency   response   may   consist   of   any   of   the   entities   listed   within   this  subsection.  

4.2.1. Proponent

Certain   staff   of   the   Proponent   will   be   designated   with   the   responsibility   of   being  available   for   emergency   response   communication.   This   designation   carries   the  responsibility   to  ensure   that  during  each  phase  of   the  project   the  EPC  and/or  OMT  for   the   site   is   aware   of   any   emergency   issue   brought   to   the   attention   of   the  Proponent  and  that  local  Emergency  Services  are  also  made  aware  of  the  same  in  the  event   that   the   emergency   is   beyond   the   scope   handled   exclusively   by   the   EPC   or  OMT.    

The   Proponent   will   also   be   responsible   for   notifying   local   media/emergency  broadcaster(s)   (if   required)   and   nearby   residents   (if   required)   in   the   event   of   an  emergency  that  threatens  public  health  or  safety.    

The   Proponent   will   be   available   via   mobile   phone   and/or   a   paging   system   at   all  times.  The  contact  numbers  for  these  devices  will  be  determined  and  distributed  to  the  EPC,  OMT  and  Local  Emergency  Services  in  advance  of  any  construction  activity  at  the  site.  

4.2.2. Engineering and Procurement Contractor

The  EPC  selected  to  oversee  all  construction  and/or  decommissioning  work  on-­‐site  will   be   responsible   for   monitoring   emergency   response   requirements   during   the  construction  and  decommissioning  phases.    

The  EPC’s  Site  Manager  will  directly  coordinate  emergency  response  on-­‐site  and  will  contact   local   emergency   services   when   required   in   adherence   to   pre-­‐established  division   of   responsibilities   discussed   under   Section   4.1.2.   The   EPC   will   also   be  responsible   for   communicating   the   status   of   ongoing   emergency   response   to   the  Proponent   and   will   be   available   via   any   number   of   the   following   contact   avenues  during  emergencies:  

• Two-­‐way  radio  with  Proponent  and/or  Local  Emergency  Services  -­‐  tuned  to  a  frequency  to  be  established  in  consultation  with  Local  Emergency  Services  as  discussed  under  Section  4.1.2.  

• Mobile   phone   –   specific   number   to   be   established   as   part   of   an   Emergency  Response/Preparedness  Plan  as  outlined  in  Section  4.1.2.  

 

4.2.3. Operation and Maintenance Team

The  OMT  will  be  responsible  for  coordinating  onsite  emergency  response  during  the  operation  phase  of   the  project   in   accordance  with   the  emergency   response  plan  as  

Page 31: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 26

outlined   in   Section   4.1.2.   As   a   minimum,   the   OMT   will   consist   of   a   Service   Site  Manager   to   be   based   on   site   and/or   a   Region  Manager.   Either   one   or   both  will   be  available   24   hours   per   day,   365   days   per   year.   The   OMT   will   directly   coordinate  emergency  response  on-­‐site  and  will  contact  local  emergency  services  when  required  in   adherence   to   pre-­‐established   division   of   responsibilities.   The   OMT   will   be  available  via  any  number  of  the  following  contact  avenues  during  emergencies:  

• Two-­‐way  radio  with  Proponent  and/or  Local  Emergency  Services  -­‐  tuned  to  a  frequency  to  be  established  in  consultation  with  Local  Emergency  Services  as  part   of   the   Emergency   Response/Preparedness   Plan,   referenced   in   Section  4.1.2.  

• Mobile   phone   –   specific   number   to   be   established   as   part   of   the  Emergency  Response/Preparedness  Plan,  referenced  in  Section  4.1.2.    

• A  designated   toll   free  number  –   specific  number   to  be  established  as  part  of  the  Emergency  Response/Preparedness  Plan,  referenced  in  Section  4.1.2.  

The  OMT  will  also  be  responsible   to  communicate  the  status  of  ongoing  emergency  response  to  the  Proponent.  

4.2.4. Local Emergency Services

Local  Emergency  Services  consist  of  the  fire  department  in  Norwich  Township  (four  districts),   Woodstock   Fire   Department,   the   Ontario   Provincial   Police   (OPP),   and  ambulance   service   from   the   Oxford   County   Board   of   Health.   These   emergency  services  will  be  contacted  via  911  emergency  dispatch,  which  can  be  initiated  by  any  party,  or  by   two-­‐way  radio  as  outlined  above.  Local  Emergency  Services  will  notify  both   the   Proponent   and   the   OMT   when   informed   of   an   emergency   on-­‐site   as   to  enable  appropriate  coordination.    

For   reference   purposes,   Fire   Department   resources   and   proximity   to   the   site   are  outlined  in  Table  9.  The  4  nearest  ambulance  stations  and  their  proximity  to  the  site  are   outlined   in   Table   10.   The   nearest   hospital   is   the   Woodstock   General   Hospital  located  8  km  from  the  site.  There  are  4  OPP  detachments  within  50  km  of  the  project  area:  Oxford,  Brant  County,  Norfolk  County,  and  Middlesex  (London).  

Page 32: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 27

TABLE 9 NORWICH TWP AND WOODSTOCK FIRE DEPARTMENT RESOURCES

Fire Department Location

Approximate Distance from Project Boundary by Road (km)

Staff Equipment Resources

Station 4 - Oxford Centre 1

1 - District Chief

2 - Captains

15 - Firefighters

1 – 1000gal pumper

1 – 1800gal tanker

Station 3 - Burgessville 5

1 – District Chief

2 – Captains

15 – Firefighters

1 – 500gal pumper

1 – 1800gal tanker

1 mini pumper/rescue pickup truck

Woodstock – 1203 Parkinson Road 8 12 full-time per

shift

1- ALF Eagle aerial pumper

1- ALF Eagle 100ft mid-mount aerial platform

Station 2 – Norwich 13

1 – District Chief

2 – Captains

12-15 – Firefighters

1 - 500gal pumper

1 – 1800gal tanker

Station 1 – Otterville 18

1 – District Chief

2 – Captains

15 – Firefighters

1 – 1000gal pumper

1 – 1500gal tanker

TABLE 10 AMBULANCE RESOURCES WITHIN 20 KM OF PROJECT

Ambulance Station

Approximate Distance from Project Boundary by Road (km)

Staff Hours of Operation

Station 0 – Woodstock

377 Mill St 6.0 2 paramedic

crews

One crew 24 hours, 7 days per week

One crew 8 AM – 6 PM - Monday to Friday

Station 01 – 9.0 1 paramedic crew 24 hours, 7 days per week

Page 33: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 28

Woodstock

208 Bysham Park

Station 04 – Norwich

6 Tidey Street 13.5 1 paramedic crew 24 hours, 7 days per week

Station 02 – Ingersoll

162 Carneige Street 19.0 1 paramedic crew 24 hours, 7 days per week

4.2.5. MOE and/or Spi l ls Action Centre

The  MOE  and/or  the  MOE’s  Spills  Action  Centre  will  be  notified  by  the  Proponent  of  any   incident   requiring   MOE   attention.   The   EPC   or   OMT   will   also   notify   the   MOE  and/or  the  MOE’s  Spills  Action  Centre  of  any  incident  requiring  MOE  attention  at  1-­‐800-­‐268-­‐6060.  

4.2.6. Media Broadcasters

Local   radio   and  TV   stations  will   be  notified  by   the  Proponent  of   emergency  events  that   may   impact   public   health   or   safety   in   the   vicinity   of   the   project.   Proposed  stations  to  contact  are  listed  in  Table  11  and  Table  12.    

TABLE 11 LOCAL RADIO BROADCAST CONTACTS

Station Name Frequency

(Hz) Station ID Contact Number

CBC Radio 1 93.5 CBCL (519) 255 3456

HOPE FM 94.3 CJFH (519) 539 2304

The Hawk 103.9 CKDK (519) 931 6000

Heart FM 104.7 CIHR (519) 537 8040

TABLE 12 LOCAL TV BROADCAST CONTACTS

Station Name Channel Contact Number

Rogers TV Cable 13 13 (519) 675 1313

 

Page 34: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 29

4.3. Emergency Response Chain of Communication

4.3.1. Construction and Decommissioning Phases

Figure  3  illustrates  the  chain  of  communication  during  an  emergency  response  when  the   EPC   detects   the   emergency.   Figure   4   illustrates   the   chain   of   communication  during  an  emergency  response  when  a  member  of  the  public  detects  the  emergency.    

As   previously   discussed,   the   EPC   will   be   responsible   for   determining   if   local  emergency  services  are  required  for  a  potential  emergency.  

Once  an  emergency  is  communicated,  the  Proponent,  the  EPC,  and  Local  Emergency  Services  (if  required)  will  remain  in  contact  to  monitor  the  status  of  the  emergency.  

 

   

FIGURE 3 EMERGENCY COMMUNICATION CHAIN FROM EPC DURING CONSTRUCTION/DECOMM

 

   

FIGURE 4 EMERGENCY COMMUNICATION CHAIN FROM PUBLIC DURING CONSTRUCTION/ DECOMM

 

Proponent

Engineering  and  Procurement  Contractor

Nearby  Residents   (as  required)

Media/Emergency  Broadcaster  (as  

required)

MOE  and/or  Spills  Action  

Centre   (as  required)

Local  Emergency  Services

(as  required)

Proponent

Engineering  and  

Procurement  Contractor

Public Nearby  Residences (as  required)

MOE  and/or  Spills  Action  

Centre   (as  required)

Local  Emergency  Services

Media/Emergency  Broadcaster  (as  

required)

Page 35: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 30

4.3.2. Operation Phase

Figure     illustrates  the  chain  of  communication  during  an  emergency  response  when  the   OMT   detects   the   emergency.     Figure     illustrates   the   chain   of   communication  during  an  emergency  response  when  a  member  of  the  public  detects  the  emergency.    

As   previously   discussed,   the   OMT   will   be   responsible   for   determining   if   local  emergency  services  are  required  for  a  potential  emergency.  

Once  an  emergency  is  communicated,  the  Proponent,  the  OMT,  and  Local  Emergency  Services  (if  required)  will  remain  in  contact  to  monitor  the  status  of  the  emergency.  

 

   

FIGURE 5 EMERGENCY COMMUNICATION CHAIN FROM OMT DURING OPERATION

   

   

FIGURE 6 EMERGENCY COMMUNICATION CHAIN FROM PUBLIC DURING OPERATION

 

Proponent

Operation  and  Maintenance  

Team Nearby  Residents   (as  required)

Media/Emergency  Broadcaster  (as  required)

MOE  and/or  Spills  Action  

Centre   (as  required)

Local  Emergency  Services

(as  required)

Proponent

Operation  and  Maintenance  

Team

Public Nearby  Residences

(as  required)

MOE  and/or  Spills  Action  

Centre   (as  required)

Local  Emergency  Services

Media/Emergency  Broadcaster  (as  

required)

Page 36: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 31

4.3.3. Typical Emergency Response Scenarios

As   referenced   in   Sections   4.1.1   and   4.1.2,   the   EPC   and   OMT   contractors   will   be  required   by   the   Proponent   to   draft   a   detailed   Emergency   Response/Preparedness  Plan,   specific   to   the  Gunn’s  Hill  Wind  Farm,   in  advance  of  any  construction  activity  on-­‐site.  These  plans  will  be  developed  in  ongoing  consultation  with  local  emergency  services.   Section   5.9   elaborates   on   potential   emergency   circumstances   for   wind  projects   and   provides   general   mitigation   measures   for   scenarios   that   will   be  addressed  in  greater  detail  before  construction.  

4.4. Non-Emergency Communications Plan

Non-­‐emergency  communication  will  be  conducted  in  a  uniform  manner  for  all  phases  of  the  project.  

4.4.1. Outgoing

Non-­‐emergency  announcements   and  updates   related   to   the  project  will   be   sent   via  email   to   the  project  stakeholder  mailing   list  and  posted  on  a  website  designated   to  the   project.   The   current   project   contact   list   of   stakeholders   will   continue   to   be  utilized   for   ongoing   announcements   during   the   construction,   operation,   and  decommissioning  phases.  Stakeholders  wishing  to  discontinue  receipt  of  updates  and  announcements  will  be   removed   from   the   list   at   their   request.  The  project  website  address  will   be   sent   to   stakeholders  and  will   be  posted  on  at   least  one   sign  within  public  view  in  the  project  area.  

4.4.2. Incoming

Non-­‐emergency  incoming  communication  will  be  received  by  phone,  mail,  or  through  a  designated  email  address  for  the  project.  These  contact  details  will  be  provided  to  the  stakeholders  as  outlined  in  Section  4.2.3,  and  will  be  posted  on  at  least  one  sign  within  public  view  in  the  project  area.  

Communication  received  by  phone  may  be  followed  up  by  or  directed  toward  written  submission  to  ensure  proper  documentation.  

Procedures  for  receiving  complaints  related  to  the  project  are  outlined  below  and  in  Section  5.5.3.    

4.4.2.1. General Complaints Monitoring

A  website  will  be  established   for   the  wind   farm   in  order   to   receive  any  complaints  from   the   public.     Complaints   will   be   compared   with   climatic   and   operational  conditions  at   the  referenced  time  of   the  complaint  and  will  be  kept  on  record   in  an  electronic  file.    The  information  recorded  from  the  sender  will  include  name,  address  and  the  telephone  number;  time  and  date  of  the  complaint,  and  details  of  the  actions  taken  to  remediate  the  cause  of  the  complaint;  and  proposed  actions  to  be  taken  to  prevent   reoccurrence   in   the   future.   Complaints   specific   to   noise   are   addressed   in  

Page 37: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 32

Section  5.5.3.  Any  complaints  related  to  spills  will  be  investigated  and,  if  appropriate  will  be  communicated  to  the  MOE  Spills  Action  Centre.  

 

Page 38: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 33

5. POTENTIAL ENVIRONMENTAL EFFECTS AND MITIGATION MEASURES

Descriptions  of  the  existing  natural  heritage,  water,  archaeological  and  built  heritage  environments   in   the   area   and/or  Project   Location   can  be   found  within   the  Natural  Heritage  Assessment  Report,  Water  Bodies  and  Assessment  Report  and  Archaeological  Assessment  and  Cultural  Heritage  Resources  Report.     These   reports   form  part  of   the  complete  REA  application.  

For  some  natural  environment  and  socio-­‐economic  features,  mitigation  measures  are  anticipated  to  eliminate  all  effects.    The  need,  assessment,  and  selection  of  protection  and  mitigation  measures  discussed  in  the  following  sections  have  been  predicated  on  the  hierarchical  principles  of:    

• avoidance   –   the   elimination   of   adverse   environmental   effects   by   siting,  scheduling,  and  design  considerations;  

• minimization  –  reduction  or  control  of  adverse  environmental  effects  through  Project   modifications   or   implementation   of   protection   and   mitigation  measures;    

• rehabilitation   –   the   improvement   and   monitoring   of   features   if   negative  environmental  effects  are  felt.  

• compensation  –  enhancement  or  rehabilitation  of  affected  areas.  

The   application   of   these   principles   has   greatly   reduced   the   potential   for   adverse  environmental  effects  from  the  Project  as  demonstrated  in  the  following  subsections.    The   key   mitigation   strategy   used   to   address   potential   environmental   effects   from  operation   of   the   facility   was   avoidance   of   significant   natural   features   and   water  bodies  to  the  extent  possible  during  siting  of  the  Project.  

5.1. Performance Objectives

The  key  performance  objective   for  each  of   the   features  discussed  below  is  avoiding  and/or   minimizing   potential   effects   (through   the   use   of   appropriate   mitigation  measures)   to   the   features   throughout   the   operational   phase   of   the   Project.     The  proposed   mitigation   measures   will   assist   in   achieving   this   performance   objective.      An  Environmental  Effects  Monitoring  Plan  is  provided  in  Appendix  F.    

5.2. Heritage and Archaeological Resources

5.2.1. Protected Propert ies and Heritage Resources

In   accordance   with   O.   Reg.   359/09,   a   Heritage   Impact   Assessment   (HIA)   was  undertaken  for  the  Project,  and  is  included  within  the  Archaeological  Assessment  and  Cultural  Heritage  Resources  Report.  

Page 39: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 34

Two  HIAs  were  completed  for  this  project:  1  -­‐  wind  farm  area  excluding  the  overhead  cable  route,  2  -­‐  overhead  cable  route.    The  results  of  both  reports  have  been  merged  for  the  following  summary.  The  Heritage  Impact  Assessments  determined  that:    

• There  are  no  protected  properties  within  the  Project  Study  Area;    

• 32   properties   with   potential   Built   Heritage   resources   are   within   the   Study  Area  (32  of  which  are  of  Cultural  Heritage  Value  or  Interest);  these  will  not  be  negatively  impacted  by  the  Project;  and,  

• 3  potential  Cultural  Heritage  Landscapes  are  within  the  Study  Area;  these  will  not  be  negatively  impacted  by  the  Project.    

MTCS   provided   a   letter   of   Concurrence   with   the   recommendations   of   the   initial  heritage   assessment   on   July   28,   2011   and   indicated   that   further   heritage   analysis  would  not  be  required.    MTCS  sign-­‐off  on  the  Heritage  Assessment  Report  from  May  2012   was   received   on   December   11,   2012   and   no   further   heritage   analysis   is  required   and   no   negative   impacts   are   anticipated   from   the   project   on   the   heritage  resources  present.  

5.2.1.1. Potential Effects

As  operational  and  maintenance  activities  will  not  occur  on  the  properties  containing  the  Built  Heritage  resources  and  Cultural  Heritage  Landscapes,  no  adverse  effects  on  heritage  resources  are  anticipated  during  operations.      

The   Heritage   Impact   Assessment   Reports   determined   that   the   proposed   Project  infrastructure  will   not   result   in   the  direct  or   indirect  obstruction  of   any   significant  views  or  vistas  within,  from,  or  of  built  or  natural  features  associated  with  the  Built  Heritage  resources  or  Cultural  Heritage  Landscapes.    Significant  views  and  vistas  are  not  heritage  attributes  of  any  of  the  properties  with  identified  heritage  resources.  

5.2.1.2. Mit igation Measures

As   no   potential   effects   are   likely   to   occur   as   a   result   of   the   Project   on   heritage  resources,   no  mitigation  measures   are   necessary.     The  Heritage   Impact   Assessment  Reports   recommended   that   “the   Gunn’s   Hill   Wind   Farm   be   released   from   further  heritage  concerns”.    

5.2.1.3. Net Effects

No  net  effects  are  anticipated.  

5.2.2. Archaeological Resources

In  accordance  with  O.  Reg.  359/09,  a  Stage  1  Archaeological  Assessment  and  Stage  2  Archaeological  Assessments  were  completed  for  the  Project.      

The  results  of  the  Stage  1  indicated  that:  

Page 40: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 35

“…it   was   determined   that   the   subject   property   and   the   area   within   which   it   is  situated,   is   an   area   of   high   potential   to   yield   evidence   of   potentially   significant  archaeological  deposits.  A  Stage  2  Archaeological  Assessment  of  the  study  area  was  recommended.”  

A   Stage   2   Archaeological   Assessment   was   recommended   for   all   areas   of  archaeological  potential  within  the  Project  Location  including  the  areas  proposed  for  access   roads,   parking   lot,   optional   O&M   Building,   collector   lines,   turbines   and  substation.  

The   Stage   2   assessment   indicated   that   “…a   single   First   Nations   findspot   was  encountered.   The   First   Nations   findspot,   an   isolated   individual   artifact,   does   not  represent   a   significant   planning   concern.   No   further   work   is   recommended   at   this  location.”  

MTCS  provided  a  letter  of  sign-­‐off  for  the  archaeology  assessments  on  Oct  26,  2009,  March   18,   2013,  March   21,   2013   and  May   22,   2013   and   indicating   that   they   agree  with  the  conclusions  in  the  reports  and  that  further  archaeology  analysis  would  not  be  required.    

5.2.2.1. Potential Effects

There   are  no   areas   that  will   be   excavated  during   the  operation  phase   that  will   not  have   been   assessed   by   a   Stage   2   Archaeology   Assessment;   therefore   no   potential  effects  are  anticipated  to  archaeological  resources.      

5.2.2.2. Mit igation Measures

No   potential   effects   are   anticipated   during   operation   and   therefore   no   mitigation  measures  are  necessary.  

5.2.2.3. Net Effects

No  net  effects  are  anticipated.    

5.3. Natural Heritage Resources

In   accordance   with   O.   Reg.   359/09,   a   Natural   Heritage   Assessment   Report   was  undertaken  for  the  Project  and   is   included  under  separate  cover  as  part  of   the  REA  application.  The  following  provides  a  summary  of  the  potential  effects  and  associated  mitigation  measures  as  described  in  that  report  in  relation  to  facility  operation.  

The  Natural  Heritage  Assessment  Report   for   the  Gunn’s  Hill  Wind  Farm  received  a  Confirmation  Letter   from   the  MNR  on  May  8,   2013   confirming   that   the   report  was  completed   according   to   the   regulations.   This   letter   can   be   found   in   the   Natural  Heritage  Assessment  Report,  Appendix  I.  

Page 41: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 36

5.3.1. Wetlands

There   were   5   wetlands   identified   within   the   Zone   of   Investigation.   None   of   the  wetlands  will   be   directly   impacted   by   the   Project   and   therefore   assumed   to   all   be  significant  features.      

5.3.1.1. Potential Effects

No  direct   effects   are   anticipated   to   significant  wetlands   as   a   result   of   operation   or  maintenance  activities.      

Indirect  impacts  may  occur  to  significant  wetlands  due  to  erosion.      

During  operation  and  maintenance  of  the  facility,  some  materials  such  as  lubricating  oils   and   other   fluids   associated   with   turbine   maintenance   have   the   potential   for  discharge  to  the  on-­‐site  environment  through  accidental  spills.      

5.3.1.2. Mitigation Measures

Mitigation   measures   related   to   erosion   are   outlined   in   Sections   5.9   of   the  Construction   Plan   Report.   Mitigation   measures   for   accidental   spills   are   outlined   in  Section  5.8.2.  

5.3.1.3. Net Effects

Indirect  impacts  are  expected  to  be  short-­‐term  in  duration,  and  highly  localized.  

Accidental   spills  would   be   spatially   limited   and   of   short   duration   and   protocols   to  minimize  their  impact  would  be  provided  in  the  Emergency  Response/Preparedness  Plan  (see  Section  4.1.2).  

5.3.2. Areas of Natural and Scientif ic Interest

The  Study  Area  does  not  contain  any  Earth  Science  or  Life  Science  Areas  of  Natural  and   Scientific   Interest   (ANSIs).     As   no   ANSIs   are   present,   no   potential   effects   will  occur  and  therefore  no  mitigation  measures  are  necessary.  

5.3.3. Woodlands

Four  significant  woodlands  are  located  within  the  120  m  Zone  of  Investigation.  None  of  the  woodlands  will  be  directly  impacted  by  the  Project..  

5.3.3.1. Potential Effects

No  direct  effects  are  anticipated  to  significant  woodlands  as  a  result  of  operation  or  maintenance  activities.      

Indirect  impacts  may  occur  to  significant  woodlands  due  to  erosion.      

Page 42: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 37

During  operation  and  maintenance  of  the  facility,  some  materials  such  as  lubricating  oils   and   other   fluids   associated   with   turbine   maintenance   have   the   potential   for  discharge  to  the  on-­‐site  environment  through  accidental  spills.      

5.3.3.2. Mitigation Measures

Mitigation   measures   related   to   erosion   are   outlined   in   Sections   5.9   of   the  Construction   Plan   Report.   Mitigation   measures   for   accidental   spills   are   outlined   in  Section  5.8.2.  

5.3.3.3. Net Effects

Indirect  impacts  are  expected  to  be  short-­‐term  in  duration,  and  highly  localized.  

Accidental   spills  would   be   spatially   limited   and   of   short   duration   and   protocols   to  minimize  their  impact  would  be  provided  in  the  Emergency  Response/Preparedness  Plan  (see  Section  4.1.2).  

5.3.4. Provincial Parks and Conservation Reserves

The   Project   Study   Area   does   not   contain   any   provincial   parks   or   conservation  reserves,  nor  is  it  adjacent  to  any  such  areas.    As  no  provincial  parks  or  conservations  reserves   are   present,   no   potential   effects   will   occur   and   therefore   no   mitigation  measures  are  necessary.  

5.3.5. Other Designated Natural Areas

The   Study   Area   does   not   contain   any   other   designated   natural   areas.     As   such   no  potential  effects  will  occur  and  therefore  no  mitigation  measures  are  necessary.  

5.3.6. Signif icant Wildl i fe and Wildl i fe Habitat

The   following   significant   wildlife   habitats   were   identified   within   the   Zone   of  Investigation.   These   wildlife   habitats   were   not   able   to   be   confirmed   as   significant  without   additional   fieldwork   and   further   pre-­‐construction   surveying   to   accurately  determine  their  significance  will  be  conducted  in  the  upcoming  survey  season.  

• Amphibian  Wetland  Breeding  (1  location)  

• Bat  Maternity  Colonies  (2  locations)  

5.3.6.1. Potential Effects

Amphibian  Breeding  Habitat  

Due  to   the  hydrological   functions  needed   for  Wetland  Amphibian  Breeding  Habitat,  water   quality   degradation   could   pose   a   threat   to   the   quality   of   the   habitat.     A  potential  mode   of   water   quality   degradation   is   siltation   of   the   surface  water   from  disturbed  soils  from  construction  and  decommissioning  activities.      

Page 43: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 38

Where  the  significant  wildlife  habitat  is  within  the  Zone  of  Investigation  of  a  turbine  location,   dewatering   of   the   turbine   foundation   could   pose   a   risk   to   the   soil   and  surface  water  of   the  habitat.     Increased  overland  flow  from  dewatering  could  cause  soil  erosion  of  sensitive  wildlife  habitat.  

During   operation   of   the   project,   infrequent   day   to   day   use   of   access   roads   and  maintenance   activities   associated   with   the   roads  may   result   in   impacts   to   wildlife  habitat,  due  to  dust,  but  such  impacts  are  expected  to  be  minimal.    If  maintenance  of  access   roads   or   collector   lines   adjacent   to   significant   wildlife   habitat   is   required  during  operation,  potential  impacts  could  include  erosion  or  siltation.  

Bat  Maternity  Colonies  

There  will  be  no  direct   loss  of  Bat  Maternity  Colony  Habitat  due   to   construction  of  the   project.   Indirect   impacts   during   construction   could   include   disturbance   or  disruption   to   roosting   bats.   Disturbance   from   construction   activities,   such   as  increased  traffic,  noise,  or  dust,  may  result  in  avoidance  of  adjacent  habitats  by  bats.  These   effects   may   be   greatest   if   disturbance   occurs   while   rearing   young.   Direct  impacts  to  the  Bat  Maternity  Colonies  during  operation  of  the  project  are  anticipated  to   be   very   minimal.     Little   information   or   research   is   available   regarding   indirect  impacts  of  wind  turbines   from  roosting  bats  or  bat  habitat.    However,  avoidance  or  disturbance  to  the  Bat  Maternity  Colony  Habitat  is  identified  as  a  potential  impact.  

5.3.6.2. Mitigation Measures

Pre-­‐construction  surveys  for  all  of  the  above  potential  significant  wildlife  habitat  will  be   conducted   in   the   upcoming   seasons.   If   any   of   the   habitats   are   found   to   be  significant,  mitigation  measures  will  be  put  in  place  in  discussion  with  MNR.    

Mitigation  measures  for  amphibian  species  will   include  silt  fencing  located  between  habitat   feature   and   wind   farm   infrastructure   and   construction   activities   and  education  of  construction  and  maintenance  crews  about  the  risks  at  each  particular  site.   If   habitat   is   found   to   be   significant,   post-­‐construction   monitoring   will   be  conducted  as  outlined  in  the  Environmental  Effects  Monitoring  Plan.  

Mitigation  Measures   for  Bat  Maternity  Colonies   include  post-­‐construction  mortality  monitoring   as   outlined   in   the   Environmental   Effects   Monitoring   Plan.   Mitigation  measures  described   in   this  report   include   increasing  cut-­‐in  speed,   feathering  of   the  blades  or  stopping  the  turbine  during  periods  of  high  bat  activity.  

Elements  of  the  post-­‐construction  monitoring  program  include:  

• Bird  mortality  monitoring  at  all  wind  turbines  will  be  conducted  twice-­‐weekly  (3-­‐4   day   intervals)   at   all   turbines   from   May   1st   -­‐   October   31st   and   raptor  mortality   surveys   weekly   from   May   1st   -­‐   November   30th   for   three   years  following  start  of  operations.  

Page 44: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 39

• Bat  mortality  monitoring  at  all   turbines  will  be  conducted   twice-­‐weekly  (3-­‐4  day   intervals)   at   all   turbines   from   May   1st   -­‐   October   31st   for   three   years  following  start  of  operations.    

• Searcher   efficiency   and   carcass   removal   trials   will   be   conducted   seasonally  (spring,   summer,   and   fall)   between  May  1   and  October  31,   and   repeated   for  each  searcher.  Searcher  efficiency  and  carcass  removal  rates  are  known  to  be  more  variable   for  bats   than   for  birds   throughout   the  year  and  depending  on  habitat  (in  part  due  to  the  relative  size  of  the  species).      

• Regular  reporting  that  includes  analysis  and  submission  of  results  to  the  MOE  and  MNR.  

5.3.6.3. Net Effects

Net   impacts   to   significant   wildlife   habitat   during   construction,   operation   and  decommissioning  of  the  project  are  anticipated  to  be  minimal  to  none.    The  likelihood  and   magnitude   of   impacts   without   mitigating   strategies   is   already   low.     With   the  application  of  mitigation  described  above  the  impact  will  be  very  minimal.      

Consultation  with  the  MNR  will  be  ensured  should  significant  impacts  to  any  species  in  the  area  be  identified.    

5.3.7. General ized Signif icant Wildl i fe Habitat

In   addition   to   the   significant  wildlife  habitats,   the   following  Generalized  Significant  Wildlife  Habitats  were  identified  within  the  Zone  of  Investigation:    

• Species  of  Conservation  Concern  –  River  Bluet  (Damselfly)  (2  locations)  

• Terrestrial  Crayfish  (3  locations)  

• Seeps  and  Springs  (1  locations)  

• Bat  Maternity  Colony  (1  locations)  

5.3.7.1. Potential Effects

There   are   no   potential   effects   to   Species   of   Conservation   Concern   –   River   Bluet,  Terrestrial   Crayfish   or   Seeps   and   Springs   from   the   Operation   and   Maintenance  period  of  the  wind  farm  life  cycle.    

Risks  do   exist   for  Bat  Maternity   Colonies   during   the   operation  period.   If  maternity  colonies   are   found  within   120  m   of   a   turbine   blade   swept   area,   this   increases   the  likelihood  of  bat  mortality  at  this  site  from  collisions  with  turbines.    

Page 45: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 40

5.3.7.2. Mitigation Measures

A  post-­‐construction  monitoring  plan  for  bird  and  bat  mortality  has  been  developed  in  consultation  with   the  Ministry   of   Natural   Resources   (MNR)   that   is   consistent  with  guidance   provided   in   MNR’s   Bat   Guidelines   and   MNR’s   Bird   Guidelines.     This   is  contained   within   the   Environmental   Effects   Monitoring   Plan   and   is   provided   in  Appendix  F.  

5.3.7.3. Net Effects

Pre-­‐construction   surveys   to  determine   if  Bat  Maternity   colonies  are  present  on   the  landscape  will  help  to  more  accurately  define  the  effects  expected  at  this  site.    

Post-­‐Construction  will   be   carried   out   regardless   of   the   result   of   the   above   survey.  Mortality  monitoring  of  bats  will  determine  the  level  of  impact  the  wind  farm  has  on  bat  populations,  but  based  on  pre-­‐construction  radar  surveys  of  the  area,  bat  activity  is  likely  to  be  low.    

Given   that   all   mitigation   and   monitoring   measures   developed   by   the   MNR   are  implemented,  any  adverse  net  effects  on  wildlife  from  operations  are  anticipated  to  be   insignificant.     There   is   some   potential   for   disturbance   to   wildlife   during  operations   and  maintenance   of   the  Project   as   a   result   of   increased  human   activity.    Some   limited  mortality   is   possible;   however   potential   long-­‐term   effects   to  wildlife  populations   from   this   mortality   and   from   barrier   effects   are   anticipated   to   be  minimal.      

5.3.8. Signif icant Flora and Vegetation Communit ies

No   rare   flora   or   vegetation   communities  were   identified  within   the  120  m  Zone  of  Investigation,  therefore  mitigation  measures  are  not  necessary.    

5.4. Aquatic Resources

5.4.1. Groundwater

5.4.1.1. Potential Effects

It   is  not  anticipated   that  operation  of   the  Project  will   adversely  affect  groundwater  quality,   quantity   or   movement.   Some   materials,   such   as   fuel,   lubricating   oils   and  other  fluids  associated  with  turbine  maintenance  have  the  potential  for  discharge  to  the  on-­‐site  environment  through  accidental  spills.  

5.4.1.2. Mitigation Measures

Mitigation  measures  for  accidental  spills  are  listed  in  Section  5.8.2  

5.4.1.3. Net Effects

Accidental   spills  would   be   spatially   limited   and   of   short   duration   and   protocols   to  minimize   any   impact   will   be   provided   in   the   Emergency   Response/Preparedness  Plan  (Section  4).    

Page 46: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 41

5.4.2. Surface Water, Fish and Fish Habitat

In   accordance   with   O.   Reg.   359/09,   a   Water   Bodies   and   Assessment   Report   was  undertaken  for  the  Project  to  determine  the  presence  of  water  bodies  as  defined  by  O.   Reg.   359/09   and   associated   setbacks.     The   following   provides   an   assessment   of  potential   effects   and   mitigation   measures   during   operation   for   water   bodies   and  fish/fish  habitat  within  the  120  m  Zone  of  Investigation.    

Eight  REA  water  bodies  were  identified  within  the  Zone  of  Investigation.  Two  will  be  crossed  by  underground  collector  lines  and  five  will  be  crossed  by  overhead  tap  line.  One  Water  Body  is  more  than  30  m  from  the  overhead  tap  line  and  does  not  require  environmental  effect  and  mitigation  measures  analysis.  No  access  roads,  turbines  or  transformers  are  located  within  30  m  of  a  Water  Body.  

5.4.2.1. Potential Effects

The   potential   effects   to   watercourses   during   operation   exist   from   soil   erosion  resulting   from   maintenance   activities   (removal   of   stabilizing   vegetative   cover).  Erosion   can   cause   downstream   sediment   transport   and   a   short-­‐term   increase   in  surface   water   turbidity,   including   associated   impacts   to   fish   and   fish   habitat.   The  magnitude  and  duration  of  potential  effects   to  watercourses  depend  on  the  specific  characteristics  of  each  watercourse  (e.g.  flow  regime,  water  velocity,  bed  substrates,  bank   conditions,   local   soils   and   the   extent   and   duration   of   exposure).   In   addition,  some  materials,  such  as  fuel,  lubricating  oils  and  other  fluids  associated  with  turbine  maintenance   have   the   potential   for   release   to   the   environment   in   the   event   of  accidental  spills.    

5.4.2.2. Mitigation Measures

Mitigation   measures   related   to   sedimentation   and   erosion   would   be   the   same   as  discussed  in  Section  5.10  and  5.9  respectively  of  the  Construction  Plan  Report.    

The  Emergency  Response/Preparedness  Plan  (Section  4)  will  contain  procedures  for  spill  contingency  and  response  plans,  spill  response  training,  notification  procedures,  and   necessary   cleanup  materials   and   equipment.   As   per   S.13   of   the  Environmental  Protection  Act,  all  spills  that  could  potentially  have  an  adverse  environmental  effect,  are   outside   the   normal   course   of   events,   or   are   in   excess   of   prescribed   regulatory  levels  will  be  reported  to  the  MOE’s  Spills  Action  Centre.  

Construction   activities   located   within   120   m   of     fish   habitat   will   consider   the  sensitive  fish  spawning  and  rearing  period  of  March  15  to  June  30,  if  feasible.  

5.4.2.3. Net Effects

Provided  that  maintenance  activities  are  performed  properly,  no  adverse  net  effects  on   surface  water   features   and   fish/fish   habitat   are   anticipated   during   operation   of  the  Project.    

Page 47: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 42

5.5. Air Quality and Environmental Noise

5.5.1. Air Emissions

5.5.1.1. Potential Effects

During  operations,  minor  localized  air  emissions  will  occur  from  the  periodic  use  of  maintenance  equipment  over  the  life  of  the  Project.    

5.5.1.2. Mitigation Measures

To  reduce  emissions  from  equipment  and  vehicles,  several  mitigation  measures  will  be  employed:    

• Multi-­‐passenger  vehicles  will  be  utilized  to  the  extent  practical;  

• Company   and   construction   personnel   will   avoid   idling   vehicles   when   not  necessary  for  operational  activities;  

• Equipment   and  vehicles  will   be   turned  off  when  not   in  use  unless   required  for   operational   activities   and/or   effective   operation   of   the   equipment   or  vehicle;  

• Equipment   and   vehicles   will   be   maintained   in   good   working   order   with  functioning  mufflers  and  emission  control  systems  as  available;  

• All  vehicles  will  be  fitted  with  catalytic  converters  as  required  by  applicable  legislation;  

• All  operational  equipment  and  vehicles  will  meet  the  emissions  requirements  of  the  MOE  and/or  MTO;    

• As   appropriate,   records   of   vehicle   maintenance   will   be   retained   and  made  available  for  periodic  review  by  the  Operations  and  Maintenance  Contractor;  and  

• All  vehicles   identified   through   the  monitoring  program  that   fail   to  meet   the  minimum   emission   standards   will   be   repaired   immediately   or   replaced   as  soon  as  practicable.    

5.5.1.3. Net Effects

The   application   of   the   recommended   mitigation   measures   during   operations   will  limit   air   emissions   to   the   work   areas   and   limit   the   magnitude   of   combustion  emissions.  As  a  result,  any  adverse  net  effects  to  air  quality  from  air  emissions  during  operation   of   the   Project   are   anticipated   to   be   short-­‐term   in   duration   and   highly  localized.  

Page 48: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 43

5.5.2. Dust and Odour Emissions

5.5.2.1. Potential Effects

Operations   related   traffic   and   maintenance   activities   have   the   potential   to   create  nuisance  dust  effects  in  the  immediate  vicinity  of  the  Project.    Unpaved  road  surfaces  exposed  to  wind  can  also  be  a  source  of  fugitive  dust  emissions.    

No  odour   emissions   are   anticipated  during  operation  of   the  Project.     Therefore,   no  mitigation  measures  are  required  to  address  odour.  

5.5.2.2. Mitigation Measures

To  protect   adjacent   receptors   from  potential   off-­‐site   dust   concerns,   the  Operations  and  Maintenance   Contractor   and/or   Proponent  will   implement   good   site   practices  during  operations  which  may  include:    

• Maintaining   equipment   in   good   running   condition   and   in   compliance   with  regulatory  requirements;    

• Dust  suppression  (e.g.  water)  of  source  areas  as  necessary;  

• Covering  loads  of  friable  materials  during  transport;  and,    

• Limiting  vehicle  speeds  on  gravel  or  dirt  roads.  

The  Proponent  will  monitor  concerns  raised  by  the  public  regarding  dust  and  noise.    

5.5.2.3. Net Effects

The   application   of   the   recommended   mitigation   measures   during   operations   will  limit  fugitive  dust  emissions  to  the  work  areas.  As  a  result,  any  adverse  net  effects  to  air  quality  from  dust  emissions  during  operation  of  the  facility  are  anticipated  to  be  short-­‐term  in  duration  and  highly  localized.  

5.5.3. Environmental Noise

Zephyr  North  conducted  a  Noise  Assessment  as  per   the   requirements  of   the  MOE's  2008  Noise  Guidelines  (see  Appendix  D).  The  Noise  Assessment  Report  determined  that   that   the  estimated  sound  pressure   levels  at   receptors  and  vacant   lot  surrogate  receptors   (VLSRs)   in   the   Project   area   comply   with   the   Ontario   Ministry   of  Environment  sound  level  limits  at  all  qualified  points  of  reception.  

5.5.3.1. Potential Effects

During   operations   of   the   Project,   noise   will   be   generated   by   the   periodic   use   of  maintenance  equipment  to  repair  the  wind  turbines.    In  addition,  vehicles  will  travel  to   and   from   the   substation   property   and   Operation/Maintenance   building   during  regular   business   hours.   The   audible   sound   at   receptors   beyond   the   turbine   siting  areas  and  substation  property  is  expected  to  be  a  minor,  short-­‐term  disruption.  

Page 49: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 44

Sound  will  also  be  emitted  from  the  wind  turbines.  All  turbines  proposed  as  part  of  the   Project   are   located   at   a   distance   of   at   least   550   m   from   the   nearest   non-­‐participating  noise  receptor.  Based  upon  the  Project  design,  the  analysis  carried  out  in  the  Noise  Assessment  indicates  that  sound  produced  by  the  Project  is  modeled  to  be  within  the  acceptable  limits  established  by  the  MOE  at  all  noise  receptors.    

5.5.3.2. Mitigation Measures

To   minimize   inconvenience   brought   on   by   vehicle   noise   during   operations,   all  engines   will   be   equipped   with   mufflers   and/or   silencers   in   accordance   with   MOE  and/or  MTO   guidelines   and   regulations.     Maintenance   equipment   noise   levels   will  also  be  compliant  with  sound  levels  established  by  the  MOE.      

To  the  greatest  extent  possible,  operations  activities  that  could  create  excessive  noise  will  be  restricted  to  regular  business  hours  and  adhere  to  any  local  noise  by-­‐laws.    If  maintenance   activities   that   cause   excessive   noise   must   be   carried   out   outside   of  these   time   frames,   adjacent   residents   will   be   notified   in   advance   and   by-­‐law  conformity  will  occur,  as  required.  Any  potential  noise  complaints  will  be  handled  on  an  individual  basis  by  the  Proponent.  

The  Project  will  be  required  to  operate  according  to  the  terms  and  conditions  of  the  Renewable   Energy   Approval   (REA).     In   the   event   the   Project   does   not   operate  according  to  the  terms  and  conditions  of  the  REA,  the  non-­‐compliant  turbine(s)  may  be   curtailed   or   shut   down   until   the   problem   is   resolved.   A   regular   maintenance  program   will   largely   mitigate   potential   effects   related   to   noise   from   damaged  turbines.  Routine  facility  maintenance  to  ensure  infrastructure  is  operating  properly  and  efficiently  will  be  performed  as  required.  

 Noise  Complaint  Monitoring  -­‐  A  website  will  be  established  for  the  wind  farm  in  order  to   receive   potential   complaints   from   the   public   regarding   noise   from   the   wind  turbines.  The  website  will  list  an  email  address  and  a  mailing  address  for  the  receipt  of  potential  noise  complaints.    The  communication  options  covered   in  Section  4.4.2  are  also  a  suitable  avenue  for  reporting  noise  complaints.    Any  noise  complaints  will  be  compared  with  climatic  and  operational   conditions  at  the  referenced  time  of  the  complaint  and  will  be  kept  on  record  in  an  electronic  file  stored   in   the   Proponent’s   database   for   the   duration   of   the   project   lifetime.     As   a  minimum,   the   information   recorded   from   the   sender   will   include   name,   address,  telephone  number,   time   and  date   of   the   complaint,   and  details   of   the   complaint   as  well  the  fields  listed  in  the  Noise  Complaint  Form  attached  as  Appendix  A  to  the  MOE  document  “Compliance  Protocol  for  Wind  Turbine  Noise”.  The  Proponent  will  also  add  meteorological  and  project  operational  conditions  to  the  complaint  information.  

Consultation   with   MOE   and   potential   future   MOE   protocols   will   determine   what  courses  of  action  are   subsequently   required.    Mitigation  and  contingency  measures  are  outlined  below.  

Page 50: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 45

1. The   MOE   document   “Compliance   Protocol   for   Wind   Turbine   Noise”   will   be  followed  in  addressing  noise  complaints.  Should  the  result  indicate  that  there  is   an   issue   with   non-­‐compliance   to   sound   regulations,   the   one   or   more  contingency  measures  listed  in  items  2-­‐3  will  be  enacted  

2. Turbine   components   such   as   rotor   blades,   bearings,   generator   etc.,   will   be  evaluated   for   wear   or   damage   that   causes   increased   sound   emission.   An  example  of   this  process   involves   inspecting   rotor  blades   for   inconsistencies  that   could   have   been   caused   by   damage   during   construction,   a   lightning  strike,  avian  impact,  or  wear  from  operation.  Timing  of  repair  or  replacement  of   worn   or   damaged   components   will   be   evaluated   together  with   option   3  below  to  determine  the  most  cost  effective  course  of  action  to  reduce  sound  emission.  

3. Turbines   can  be  programmed  and   controlled   to  operate   in  a  manner  which  emits   less   sound   (and   produces   less   power)   during   certain   times   of   day  and/or   certain   meteorological   conditions   as   appropriate.   This   course   of  action   may   be   used   on   a   temporary   or   permanent   basis   to   reduce   sound  emission  and  correct  an  issue  with  non-­‐compliance  to  sound  regulations.  As  an  example,  a  turbine  can  be  controlled  to  limit  operational  intensity  during  night-­‐time   hours,   or   when   the   wind   is   blowing   from   a   direction   that  correlates  to  a  measured  noise  issue.  An  operating  regime  will  be  developed  such  that  turbines  conform  to  noise  regulations.  

5.5.3.3. Net Effects

Application   of   the   recommended  mitigation  measures   during   operations   will   limit  noise   emissions   to   the   general   vicinity   of   the   turbine.   Given   that   the   facility   must  comply  with  the  requirements  of  the  REA  process  and  applicable  MOE  environmental  noise  guidelines,  no  significant  net  effects  are  anticipated.    

Any  adverse  net  effects  due  to  noise  during  operation  of  the  Project  are  anticipated  to  be  short-­‐term  in  duration  and  intermittent.  

5.6. Land-use and Socio-Economic Resources

5.6.1. Areas Protected Under Provincial Plans and Pol ic ies

No  areas  protected  under  specified  Provincial  Plans  and  Policies  are   located  within  the  120  m  Zone   of   Investigation.    No  potential   effects   are   anticipated   to   occur   and  therefore  no  mitigation  measures  are  necessary.  

5.6.2. Exist ing Land Uses

5.6.2.1. Potential Effects

During   the  operation  phase  of   the  Project,   the   lands  which   are  occupied  by   facility  components   will   be   removed   from   their   present   agricultural   land-­‐use;   however,  existing  surrounding  land  uses  will  remain  unchanged.      

Page 51: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 46

During  operations   there  will  be  a   temporary   increase   in  noise  and  dust  around   the  work   and   haul   areas   used   by   maintenance   and   personnel   vehicles,   resulting   in   a  potential  effect  to  adjacent  land  uses.  

There  is  potential  for  a  minor  increase  in  traffic  during  operations  on  roadways  near  the  Project   due   to  maintenance   vehicles.    No   adverse   effects   on   existing   land  uses,  including  local  businesses,  are  anticipated  from  increased  traffic  during  operations  of  the  Project..  

No   local   businesses   are   expected   to   be   displaced   as   a   result   of   operations   of   the  Project.  

5.6.2.2. Mitigation Measures

The  Project  is  considered  to  be  compatible  with  existing  land  use;  therefore  no  other  mitigation  measures  are  required  to  address  effects  to  the  existing  land  use.    Siting  of  turbines   and   access   roads   are   completed   with   the   approval   of   the   participating  landowner.  

Landowners  will  be  compensated  by  the  Proponent  for  agricultural  or  industrial  land  that  will   be   taken  out  of  production/use  during   the   lifespan  of   the  Project   through  the  land  lease  agreements.    

Mitigation  measures  related   to  dust,  noise  and   traffic  are   identified   in  Sections  5.5  and  5.6.8  respectively.  

5.6.2.3. Net Effects

Although  some  disturbance  to  adjacent  land  uses  from  noise  and  dust  is  unavoidable,  it   is  expected   to  be  short-­‐term   in  duration,   temporary,  highly   localized,  and  will  be  minimized   through   the   implementation   of   good   site   practices,   transportation  planning,  and  communication  with  the  community.    

5.6.3. Hazard Lands

There  is  one  hazard  land  (valleyland)  located  within  the  120  m  Zone  of  Investigation.  None   of   the   hazard   lands   contain   Project   infrastructure.   No   potential   effects   will  occur  and  therefore  no  mitigation  measures  are  necessary  

5.6.4. Recreation Areas and Features

No  recreational  areas  or  features  are  located  within  the  120  m  Zone  of  Investigation.  Operations  activities  would  be  limited  to  private  land  and  therefore  is  not  expected  to   directly   affect   recreation   areas.   As   no   potential   effects   are   likely   to   occur   as   a  result   of   the   Project   on   recreation   areas   and   features,   no  mitigation  measures   are  necessary.      

Page 52: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 47

5.6.5. Agricultural Lands and Operations

The   existing   land   use   within   the   Project   Location   is   primarily   agricultural   lands.  Potential   effects   to   the   agricultural   lands   used   for   the   turbines   access   roads   and  collector  lines  are  related  to  the  change  in  use  from  agricultural  to  renewable  energy  development.   However,   where   lands   are   being   used   for   Project   infrastructure,  landowners  are  being  financially  compensated  for  the  lease  of  the  private  lands,  and  thus  offset  the  financial  impact  of  removing  the  land  from  agricultural  production.    

Impacts  to  livestock  from  operation  of  the  Project  are  not  anticipated.  

Dust  emissions   from  operations  activities  are  associated  with  vehicular   traffic   from  maintenance  and  personnel  vehicles.  Dust  emissions  are  expected  to  be  short-­‐term  in  duration   and   highly   localized.   No   potential   physical   effects   are   anticipated   on  agricultural   lands   and   operations   from   dust   during   operations   of   the   Project,   and  therefore  no  mitigation  measures  are  required.  

5.6.6. Mineral, Aggregate and Petroleum Resources

There   are   no   lands   designated   for   aggregate   resource   extraction,   including   licensed  pits   and  quarries,  within   the  Project  Area.  No   abandoned  or   active   petroleum  wells  are  located  within  the  120  m  Zone  of  Investigation.  A  Petroleum  Resource  Operations  Report  will  be  produced  and  submitted  to  MNR.  

5.6.6.1. Potential Effects

Given   that   no  mineral,   aggregate   or   petroleum   resources   are   located   in   the   Study  Area,  no  potential  effects  are  anticipated.  

5.6.6.2. Mitigation Measures

Final   infrastructure   alignments   will   be   confirmed   prior   to   construction   based   on  consultation   with   the   MNR’s   Petroleum   Resources   Branch   and   based   on   technical  constraints   that   may   be   identified   during   detailed   design   and   engineering.    Underground   locates  would  be   conducted  prior   to   construction   given   the  potential  for  unrecorded  and  improperly  decommissioned  wells.  

The   Emergency   Response/Preparedness   Plan   (Section   4.1.2)   will   contain  procedures   for   spill   contingency   and   response   plans,   spill   response   training,  notification  procedures,  and  necessary  cleanup  materials  and  equipment.  As  per  S.13  of  the  Environmental  Protection  Act,  all  spills  that  could  potentially  have  an  adverse  environmental   effect,   are   outside   the   normal   course   of   events,   or   are   in   excess   of  prescribed  regulatory  levels  will  be  reported  to  the  MOE’s  Spills  Action  Centre.  

5.6.6.3. Net Effects

No  adverse  net  effects  are  anticipated  to  mineral,  aggregate  or  petroleum  resources  during  operation  of  the  Project.  

Page 53: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 48

5.6.7. Game and Fisheries Resources

5.6.7.1. Potential Effects

Since   the   Project   has   been   sited   entirely   on   agricultural   lands,   potential   indirect  effects  to  wildlife  and  their  habitats  will  be  temporary  until  the  Project  becomes  part  of  the  environmental  “background”.  The  mammals  present  on  the  agricultural  lands  are  common   in  southern  Ontario  and   tend   to  be  well-­‐adapted   to  human-­‐influenced  landscapes  and  disturbance.  No   impacts   to   traditional   treaty   rights  are  anticipated;  however  these  will  be  confirmed  in  discussion  with  relevant  First  Nations  and  Métis  communities  as  appropriate.  Consultation  with  Aboriginal  communities  is  detailed  in  the  Consultation  Report.  

5.6.7.2. Mitigation Measures

Turbines   are   generally   placed   on   agricultural   land,   away   from  woodlands,   and   far  enough  away  to  minimize  potential  effects.    Siting  the  Project  on  agricultural  land  has  largely  precluded  disturbance  to  local  flora,  small  mammals  and  amphibians,  natural  habitat,  and  corridor  functions.    No  further  mitigation  measures  are  required.  

5.6.7.3. Net Effects

Once  the  Project  is  operating,  human  activity  around  the  facilities  will  decrease,  thus  allowing  local  wildlife  movement  patterns  to  quickly  re-­‐establish.    

Considering   the   periodic   nature   of  maintenance   activities,   it   is   likely   that   resident  game  species  will  adapt  to  the  Project  quickly.  Consequently,  no  net  adverse  effects  are  anticipated  during  the  Project  to  game  and  fishery  resources.  

5.6.8. Local Traff ic

5.6.8.1. Potential Effects

The  number  of  vehicles  required  during  operation  will  be  minimal.    A  small  number  of   light   trucks   will   be   required   for   typical   maintenance   activities,   however  occasionally   larger   vehicles   will   be   required   to   transport   turbine   and   switching  station   components.   The   increase   in   traffic   may   result   in   short-­‐term,   localized  disturbance  to  traffic  patterns  or  increases  in  traffic  volume,  and/or  create  potential  traffic  safety  hazards.    

5.6.8.2. Mitigation Measures

There   may   be   instances   during   maintenance   activities   where   excess   loads   (e.g.  turbine  and  substation  station  components)  will  require  special  traffic  planning.     In  addition,   widening   turning   radii   and   road   widths   and   the   creation   of   new  ingress/egress  nodes  from  the  work  areas  may  be  required.    As  appropriate,  permits  will  be  obtained   to   implement   these  activities.    As  appropriate,   for  public   safety  all  non-­‐conventional  loads  will  have  front  and  rear  escort  or  “pilot”  vehicles  accompany  the  truck  movement  on  public  roads.  

Page 54: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 49

Although   there   are   no   requirements   for   formal   public   notification   of  wind   turbine  component   load   movements,   the   Proponent   may   provide   notification   of   non-­‐conventional   load   movements   that   may   interfere   with   local   traffic,   with   potential  methods   of   notification   including   postings   on   the   Project   website   or   email  notification  to  a  stakeholders  list.    This  notification  will  be  provided  in  the  interest  of  public   safety,  minimization  of  disruption  of   other   road  users,   and  good   community  relations.    

5.6.8.3. Net Effects

Road  safety  is  not  expected  to  be  an  issue  during  operations;  however,  the  potential  for  accidents  along  the  haul  routes  and  on-­‐site  cannot  be   totally  disqualified.  Truck  traffic  will  increase  on  some  roads  during  maintenance  activities  and  from  personnel  vehicles;  however  this  traffic  will  be  short-­‐term  in  duration  and  intermittent.  

The  effect  of  operating  the  wind  project   is  anticipated  to  have  a   limited,  short   term  effect  on  traffic.    

5.6.9. Local Economy

5.6.9.1. Potential Effects

Operation  of  the  Project  is  expected  to  continue  for  a  minimum  of  approximately  20  years.  The  Proponent  may  hire  a  specialized  Operation  and  Maintenance  Contractor  for   specific   tasks,   and,   to   the  extent  possible,   local  hiring  will  be  maximized  during  operations,   providing   work   for   existing   tradespersons   and   labourers.   Trades   that  could   be   provided   locally   may   include   pipefitters,   electricians,   ironworkers,  millwrights,   truck  drivers,   and   carpenters.   Since   it   is   likely   that   the  majority  of   the  labour  force  will  be  supplied  through  local  and  neighbouring  communities,  no  special  housing,  healthcare,  or  food  facilities  will  be  required  as  part  of  the  Project  operation  activities.    

No  local  businesses  or  facilities,  other  than  agricultural  land  uses,  are  located  within  the   Project   Location   or   immediately   adjacent   to   the   area.   The   operation   and  maintenance   of   the   Project   will   result   in   direct,   indirect   and   induced   benefits   in  terms  of  business  income  and  employment.    

Local   economic   benefits   will   also   include   a   minimum   of   20   years   of   land   lease  payments   to   participating   landowners.   Additionally,  municipal   taxes   to   be   paid   for  the  development  by  the  Proponent  will  be  paid  to  all  applicable  municipalities.    

5.6.9.2. Mitigation Measures

The   Proponent   will   make   all   reasonable   efforts,   to   the   extent   possible,   to   source  required  services  and  materials  from  local  suppliers  where  these  items  are  available  in  sufficient  quantity  and  quality  and  at  competitive  prices.    

Page 55: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 50

5.6.9.3. Net Effects

The   Project   provides   positive   benefits   to   the   local   area,   including   the   upper   and  lower   tier   municipalities   through   ongoing   property   tax   income   with   no   increased  demands  for  municipal  services  that  cannot  readily  be  met.    

5.6.10. Viewscape

5.6.10.1. Potential Effects

Siting  of  the  facility  will  alter  the  visual  landscape.    However,  visibility  of  the  facility  will  vary  from  receptor  to  receptor  based  upon  the  following  factors:    

• Surficial   patterns:   landform   –   largely   determined   by   physiography   and   tree  cover;  

• Topography:   slope   –   the   greater   the   slope   the   greater   the   visibility   of   the  turbines  and  other  project  infrastructure  from  more  vantage  points;  

• Observer  position:  viewing  –  distance   from  the   facility  reduces  scale  and   the  apparent  size  of  a  project  is  directly  related  to  the  angle  between  the  viewer’s  line-­‐of-­‐sight  and  the  slope  upon  which  the  project  is  to  take  place;  

• Atmospheric  conditions:  clarity  –  air  pollution,  natural  haze,  fogging,  and  snow  affect  daytime  and  nighttime  visibility;  and,  

• Turbine  marking:  lighting  –  primarily  affecting  nighttime  visibility.  

5.6.10.2. Mitigation Measures

There  are  limited  opportunities  for  potential  mitigation  strategies  given  the  height  of  the  wind  turbines  and  the  landscape  patterns.  

5.6.10.3. Net Effects

Some  disturbance  to  the  viewscape  is  unavoidable  due  to  the  height  of  the  turbines.  The  changed  visual  landscape  will  be  present  during  the  life  of  the  facility.    

5.7. Existing Local Infrastructure

5.7.1. Provincial , Municipal and Other Major Infrastructure

5.7.1.1. Potential Effects

The  tap  line  will  cross  over  Highway  401  along  an  existing  electrical  cable  crossing.    

Municipal   infrastructure   in   the   Study   Area   includes   County   and   Township   roads,  Municipal   water   and   sewage   networks   (near   tap   line   only),   and   Municipal  groundwater  supply.  

Page 56: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 51

The   Proponent  will   continue   to   consult  with   the   Township   of   Norwich   and   City   of  Woodstock,  regarding  any  potential  effects  to  municipal  interests.    The  Proponent  is  committed  to  obtain  all  necessary  permits,  approvals,  and  agreements  related  to  the  Project.    

No   potential   effects   are   anticipated   during   operation   of   the   Project   on   Provincial,  Municipal   or   other  major   infrastructure   other   than   roadways.     Potential   effects   to  traffic   during   the   operation   of   the   Project   are   discussed   in   Section   5.6.8.   Potential  effects   on   Provincial,  Municipal   or   other  major   infrastructure   from   construction   of  the  Project  are  described  in  the  Construction  Plan  Report.      

5.7.1.2. Mitigation Measures

Permits   from   the   MTO   may   be   required   to   facilitate   the   transportation   of  components   used   for   maintenance   (e.g.   cranes)   on   provincial   highways.   As  appropriate,   for   public   safety   all   non-­‐conventional   loads   will   have   front   and   rear  escort  or  “pilot”  vehicles  accompany  the  truck  movement  on  public  roads.  

The   additional   traffic   on   the   provincial   highways   is   not   expected   to   cause   any  significant  traffic  congestion.  

Although   there   are   no   requirements   for   formal   public   notification   of  wind   turbine  component   load   movements,   the   Proponent   may   provide   notification   of   non-­‐conventional   load   movements,   with   potential   methods   of   notification   including  postings  on   the  Project  website  and/or  email  notification   to  stakeholders   list.    This  notification   will   be   provided   in   the   interest   of   public   safety,   minimization   of  disruption  of  other  road  users,  and  good  community  relations.    

5.7.1.3. Net Effects

No  net  effects  are  anticipated  to  provincial  and  local  infrastructure  during  operation  of  the  Project.    

5.7.2. Navigable Waters

No  navigable  waters  will  be  crossed  by  Project   infrastructure.  As  such,  no  potential  effects  will  occur  and  therefore  no  mitigation  measures  are  necessary.  

5.7.3. Radio Communication, Radar and Seismoacoustic Systems

A  study  was  conducted  according  to  the  Radio  Advisory  Board  of  Canada’s  “Technical  Information  On  The  Assessment  of  the  Potential  Impact  Of  Wind  Turbines  On  Radio  Communication,   Radar   And   Seismoacoustic   Systems”   in   order   to   screen   potential  impacts.  The  report  is  attached  as  Appendix  G.    

The  study  concluded  the  following:  

Page 57: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 52

The  detailed  analysis  of   the  possibilities  of   image  ghosting   for   three  CBC   television  broadcast  stations  covering,  even  partially,  the  area  of  the  Gunn’s  Hill  proposed  wind  farm,   made   it   possible   to   determine   that   a   certain   number   of   dwellings   would  possibly   experience   this   type  of   interference   in  dynamic  mode,   static  mode  or   even  both…  

…   The   methodology   used   is   not   considered   as   an   extreme   worst   case   scenario  analysis;  we   strongly   believe   it   represents   a   conservative   approach  and   the   actual  impact  will  be  significantly   lower  than  the  presented  results.  While  the  model  used  has   not   been   benchmarked   against   actual   field   measurements,   similar   impact  predictions  at  other  wind  farms  resulted  in  no  complaint.  

An  additional  study  to  identify  and  evaluate  the  communication  systems  in  the  vicinity  of  the  project  was  commissioned  and  is  also  included  in  Appendix  G.  The  study’s  purpose  is  quoted  below:  

 

This   preliminary   study   report   presents   the   results   of   the   first   phase   of   the   study,  identifying   the   telecommunication   systems   in   the   wind   farm   area   that   might   be  affected   by   the   deployment   of   the   Gunn’s   Hill   wind   farm   project.   This   study   aims,  among   other   things,   to   identify   point-­to-­point  microwave   telecommunication   links  that   intersect   the  proposed  wind   farm  project  and  to  define  the  consultation  zones  associated  with   these   links  and  with   the  mobile  base   station   located   in   the   region.  The  study  also  aims  to  identify  radar  and  navigation  systems  with  the  potential  to  be  affected   by   wind   turbines   and   to   assess   the   potential   for   impact   on   radio   and  television  broadcast  signals  in  the  region.  

 

 The  study   identified  10  digital  TV  stations  within   the  project  area,  one   land  mobile  base   station,   and   2   turbines   with   the   1   km   consultation   zone   of   a   point-­‐to-­‐point  microwave  tower.    

5.7.3.1. Potential Effects

Impact   screening   and   consultation   suggests   that   impacts   to   Radio   Communication,  Radar,  and  Seismoacoustic  systems  are  predicted  to  be  either  non-­‐existent  or  within  acceptable  levels  to  system  operators.  

5.7.3.2. Mitigation Measures

A  website  will  be  established   for   the  wind   farm   in  order   to   receive  any  complaints  from   Radio   Communication,   Radar,   and   Seismoacoustic   system   operators.   Any  complaints   will   be   compared   with   climatic   and   operational   conditions   at   the  referenced  time  of  the  complaint  and  will  be  kept  on  record  in  an  electronic  file.    The  information  recorded  from  the  sender  will  include  name,  address  and  the  telephone  number;  time  and  date  of  the  complaint,  and  details  of  the  complaint.  

Complaints  received  will  be  addressed  in  consultation  with  the  system  operator  and  any  corresponding  Provincial  or  Federal  agencies.  As   these   types  of  complaints  can  

Page 58: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 53

be  very  specific   to  a  given  technology  or  electromagnetic   frequency,  mitigation  and  contingency   measures   will   require   analysis   and   development   by   specialized  consultants  if/when  an  issue  is  brought  to  the  Proponent’s  attention.  

If   proof   of   digital   TV   signal   interference   exists,   the   Proponent  will   offer   corrective  measures  such  as  a  higher  quality  receiver  or  a  satellite  receiver.  

5.7.3.3. Net Effects

It   is   anticipated   that   any   interference   with   radio   communication   systems   will   be  limited   and   of   short-­‐term   duration   given   that   the   Proponent   will   review   potential  incidents  of  radio  communication  interference  on  a  case  by  case  basis.    

5.7.4. Aeronautical Systems

5.7.4.1. Potential Effects

The   presence   of   wind   turbines   presents   a   potential   hazard   to   low   flying   aircraft.    Transport   Canada’s   CAR621   publication   specifies   aeronautical   obstruction   lighting  requirements   for  wind   turbines.   Section   12.4   of   CAR621  pertains   to  wind   turbines  with   a   total   height   greater   than   150   m   and   states   “The   provision   of   marking   and  lighting  for  wind  turbines  higher  than  150  m  shall  be  determined  through  means  of  a  risk  assessment.”  

There   is  one   local  private  airfield   in   the  vicinity  of   the  Project,   identified  as  Curries  Aerodrome.  Though  the  airfield  is  not  certified  with  NAV  Canada  and  presently  does  not   operate  outside  of  Visual   Flight  Rules,   consultation  with   the  operator   indicates  that  there  is  potential  to  add  night-­‐time  operations  in  the  future.    

5.7.4.2. Mitigation Measures

Prowind   staff   visited   the   airfield   in   March   of   2010,   at   an   early   stage   of   project  development.  The   locations  and  orientations  of  runway  boundaries  were  measured  in  an  effort  to  account  for  the  airfield  in  a  broader  constraints  analysis  that  informed  turbine   layout  decisions.  Turbine  positions  4,   5,   8,   9,   and  10  were  kept   sufficiently  north   to   avoid   direct   conflict   with   a   runway   approach.   Turbines   1,   2,   and   3   were  spaced   in   a   manner   that   avoids   the   theoretical   approach   path   that   would   be  protected  if  the  runway  were  certified  by  NavCanada.    

A   professional   third   party   assessment   of   the   Crries   Aerodrome  was   commissioned  and   is   included   as   Appendix   H.   The   assessment   states   that   “Although   Obstacle  Limitation   Surfaces   are   not   required   for   aerodromes,   either   registered   or   non-­‐registered,   Prowind  has   taken   appropriate   approach   surfaces   into   consideration   in  defining  turbine  locations.”  The  report  also  recommends  establishing  turbine  lighting  schemes  in  consultation  with  Transport  Canada  and  the  airfield  owner.  

Transport  Canada  has  assessed  the  project  and  has  determined  that  turbines  1,  3,  4,  5,   6,   7,   8,   and   10   must   be   equipped   with   CL-­‐864   medium   intensity   red   flashing  beacons.  These  beacons  are  required  to  have  a  minimum  intensity  of  1,500  candelas  

Page 59: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 54

and  will   be  programmed   to   turn  on  and  off   in  unison.   In   an  effort   to   reduce  visual  impact  at   the  ground  level,  Prowind  will  also  propose  using  recent  technology  with  very   low   levels   of   ground   scatter   so   visibility   is   heavily   mitigated   at   ground   level  without  restricting  visibility  from  the  air.    

Due   to   the  potential   for   the  Curries  Aerodrome   to  expand   to  night-­‐time  operations  and  for  the  sake  of  being  conservative,  it  should  be  assumed  that  all  turbines  will  be  equipped  with  the  above  lighting  during  some  portion  of  the  operational  phase  of  the  project.  

Confirmation  will  also  be  obtained  from  the  Department  of  National  Defence  (DND)  which   indicates   that   the   Project   will   not   interfere   with   any   DND   radar   and   flight  operations.  

NavCanada  will  be  responsible  for  updating  all  aeronautical  charts  with  the  turbine  locations.    

Routine   maintenance   of   the   turbines   will   include   replacing   safety   lighting   in   the  event  of  a  malfunction.  

5.7.4.3. Net Effects

With   the   application   of   the   above  mitigation  measures,   functionality   of   the   Curries  Aerodrome  is  preserved  during  operation  of  the  facility.  

5.8. Waste Management and Contaminated Lands

5.8.1. Waste Generation

5.8.1.1. Potential Effects

Waste  created  at  operational  wind  energy  generation  facilities  is  typically  limited  to  small   quantities   of   exchanged   lubricants   and   cooling   fluids,   grease-­‐soaked   rags,  batteries,   air   filters,   replaced   turbine  parts   and   a  minor   amount   of   domestic  waste  (i.e.,  garbage,  recycling,  and  organics).  

All  waste  materials  will   require   reuse,   recycling,   and/or  disposal   at   an  appropriate  off-­‐site   facility.     Improper   disposal   of   waste   material   generated   during   operations  may  result  in  contamination  to  soil,  groundwater,  and/or  surface  water  resources  on  and   off   the   Project   sites.     Litter   generated   during   operations   may   also   become   a  nuisance   to   nearby   residences   if   not   appropriately   contained.   There  will   be  no   on-­‐site  disposal  of  waste  during  the  operation  of  the  Project.      

Expected   quantities   of   waste   fluids   to   be   created   by   the   project   during   the  operational   phase   are   presented   in   Table   13.   Some   variation   to   these   quantities   is  possible   due   to   changing   specifications   from   turbine   manufacturers   or   increased  frequency   of   fluid   exchange   due   to   issues   identified   during   on-­‐site   monitoring.  Emergency  response  to  spills  of  waste  fluids  are  addressed  in  Section  5.8.2.  

Page 60: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 55

TABLE 13 TOTAL EXPECTED QUANTITIES OF WASTE FLUIDS

Type of Waste Expected Quantity Approximate Frequency

Grease 310 L Yearly

Yaw System Gear Oil 608 L Every 5 years or as needed

Hydraulic Oil 2200 L Every 5 years or as needed

 It  is  expected  that  replacement  of  a  small  component  will  occur  annually  per  turbine.  This  may  typically  include  a  fluid  pump,  cooling  fan,  circuit  board,  sensor,  yaw  motor,  pitch  motor,  etc.    

The  substation  does  not  have  a  power  transformer  for  the  purpose  of  feeding  power  to   the   electrical   grid,   since   the   turbines   have   step   up   transformers   located   at   or  within   the   base.     Each   step   up   transformer   contains   a   small   amount   of   oils   and  coolants   and  no   spill   containment  measures   are   required.     These   oils   and   coolants  are   contained  within   the   transformer  and  do  not   require  maintenance  and   thus  do  not  generate  waste  fluids.  

It   is   expected   that   replacement   of   a   major   turbine   component   will   occur   every   7  years   per   turbine   on   average.   This   may   typically   include   a   gearbox,   generator,   or  turbine   blade   and   will   require   a   crane   to   be   brought   to   the   site.   Gearboxes   and  generators  will  be  removed  from  the  site  for  refurbishment.  Turbine  blades  may  be  repaired  and   re-­‐used  but  will  more   likely  be   taken  off-­‐site   for  disposal   in  a   landfill  once  removed  from  the  turbine  hub.  

At   times   of  major   equipment   replacement,   crane   pads  will   be   reconstructed   in   the  same  manner  as  during  construction  and  removed  thereafter.  

There  are  no  planned  water   takings  near  or  above  50,000  L/day  on  any  day  of   the  operational  phase  of  the  project.  

5.8.1.2. Mitigation Measures

During  operations,  the  Proponent  and/or  the  Operation  and  Maintenance  Contractor  will  implement  a  site-­‐specific  waste  collection  and  disposal  management  plan,  which  will  include  good  site  practices  such  as:    

• systematic   collection   and   separation   of   waste   materials   within   on-­‐site  weather-­‐protected  storage  areas;    

• contractors  will   be   required   to   remove   all  waste  materials   from   the   turbine  sites  during  maintenance  activities;    

Page 61: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 56

• all  waste  materials  and  recycling  will  be  transported  off-­‐site  by  private  waste  collection   contractors   licensed   with   a   Certificate   of   Approval   –   Waste  Management  System;  

• labeling  and  proper   storage  of   liquid  wastes   (e.g.  used  oil,  drained  hydraulic  fluid,  and  used  solvents)  in  a  secure  area  that  will  ensure  containment  of  the  material  in  the  event  of  a  spill.    As  per  s.13  of  the  Environmental  Protection  Act,  all   spills   that   could   potentially   have   an   adverse   environmental   effect,   are  outside   the   normal   course   of   events,   or   are   in   excess   of   the   prescribed  regulatory  levels  will  be  reported  to  the  MOE’s  Spills  Action  Centre;  

• as   appropriate,   spill   kits   (e.g.   containing   absorbent   cloths   and   disposal  containers)  will  be  provided  on-­‐site  during  maintenance  activities  and  at   the  operation  and  maintenance  building;    

• qualified  maintenance  personnel  will  immediately  remove  any  replaced  parts  from   the   site   or   store   them   in   the   O   &   M   building   until   removal   can   be  arranged.  These  parts  will  be  refurbished  when  possible  or  recycled/disposed  of  in  accordance  with  local  regulations.  

• dumping  or  burying  wastes  within  the  Project  sites  will  be  prohibited;  

• disposal  of  non-­‐hazardous  waste  at  a  registered  waste  disposal  site(s);    

• if   waste   is   classified   as   waste   other   than   solid   non-­‐hazardous,   a   Generator  Registration  Number   is   required   from   the  MOE   and   the   generator  will   have  obligations   regarding  manifesting   of   waste.     Compliance   with   Schedule   4   of  Regulation  347  is  mandatory  when  determining  waste  category;  and  

• implementation   of   an   on-­‐going   waste   management   program   consisting   of  reduction,  reuse,  and  recycling  of  materials.  

5.8.1.3. Net Effects

With  the  application  of   the  mitigation  measures  outlined  above,  no  net  effects   from  waste  material  disposal  will  occur  on-­‐site  during  operation.    

5.8.2. Spil ls

5.8.2.1. Potential Effects

Some  materials,  such  as  fuel,  lubricating  oils  and  other  fluids  associated  with  turbine  maintenance   have   the   potential   for   discharge   to   the   on-­‐site   environment   through  accidental  spills.  

5.8.2.2. Mitigation Measures

In   terms   of   accidental   spills   or   releases   to   the   environment,   standard   containment  facilities   and   emergency   response  materials  will   be  maintained   on-­‐site   (within   the  

Page 62: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 57

turbines   or   substation)   as   required.   Refuelling,   equipment  maintenance,   and   other  potentially  contaminating  activities  will  occur  in  designated  areas.  As  per  s.13  of  the  Environmental   Protection   Act,   all   spills   that   could   potentially   have   an   adverse  environmental  effect,  are  outside  the  normal  course  of  events,  or  are  in  excess  of  the  prescribed  regulatory  levels  will  be  reported  to  the  MOE’s  Spills  Action  Centre.  

An  Emergency  Response/Preparedness  Plan   (Section  4.1.2)  will   be  developed  and  will   include   protocols   for   the   proper   handling   of   material   spills   and   associated  procedures  to  be  undertaken  in  the  event  of  a  spill.      

5.8.2.3. Net Effects

With  the  application  of   the  mitigation  measures  outlined  above,  no  net  effects   from  accidental  spills  or  releases  to  the  environment  are  anticipated.    

5.9. Public Health and Safety

5.9.1. Turbine Blade and Structural Fai lure

5.9.1.1. Potential Effects

The  potential  exists   for   full  or  partial  blade  detachment   from  the   turbine  structure,  resulting   in   damage   to   the   landing   area   from   the   impact.   Garrad   Hassan   Canada  undertook  a  review  of  publicly-­‐available  literature  on  turbine  rotor  failures  resulting  in  full  or  partial  blade  throws  (Garrad  Hassan  Canada,  2007).  Such  events  were  found  to  be  very  rare;  therefore  data  describing  these  events  are  scarce.      

Root   causes   of   blade   failure   have   been   continuously   addressed   through  developments  in  best  practice  in  design,  testing,  manufacture  and  operation;  much  of  these   developments   have   been   captured   in   the   International   Electrotechnical  Commission  (IEC)  standards  to  which  all  current  large  wind  turbines  comply  (Garrad  Hassan   Canada,   2007).   There   has   been   widespread   introduction   of   turbine   design  certification   and   approval   that   certifies   compliance   with   standards   and   requires   a  dynamic   test   that   simulates   the   complete   life   loading   on   the   blade   (Garrad  Hassan  Canada,   2007).   The   certification   body   also   performs   a   quality   audit   of   the   blade  manufacturing  facilities  and  performs  strength  testing  of  construction  materials.  This  approach  has  effectively  eliminated  blade  design  as  a  root  cause  of   failures  (Garrad  Hassan  Canada,  2007).    

The  reported  main  causes  of  blade  failure  include:  

• Human  interference  with  the  control  system;  

• A  lightning  strike;  and,  

• A  manufacturing  defect  in  the  blade.  

Page 63: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 58

Turbine   control   systems   are   subjected   to   rigorous   specification   in   the   design  standards   for   wind   turbines   (IEC   61400-­‐1)   and   exhaustive   analysis   in   the  certification  process.  Turbines  with  industry  certification  must  have  a  safety  system  completely  independent  of  the  control  system.    In  the  event  of  a  failure  of  one  system,  the  other  is  designed  to  control  the  rotor  speed.    

Lightning  protection  systems  for  wind  turbines  have  developed  significantly  over  the  past  decade  and  best  practices  have  been  incorporated  into  the  industry  standards  to  which   all  modern   turbines  must   comply.   This   has   led   to   a   significant   reduction   in  events   where   lightning   causes   structural   damage.   A   review   of   available   literature,  conducted   by   the   Chatham-­‐Kent   Public   Health   Unit   (2008),   revealed   only   four  documented   turbine   failure   issues   in  Ontario  due   to   lightning   strikes   that   required  the  turbine  to  be  shut  down  for  repair.  

The   occurrence   of   structural   manufacturing   defects   in   rotor   blades   has   also  diminished   significantly   due   to   experience   and   improved   quality   control   in   the  industry.   Design   practice   has   evolved   to   improve   structural   margins   against   any  manufacturing   deficiencies.   Even   in   the   rare   event   of   a   blade   failure   in   modern  turbines,   it   is  much  more   likely   that   the  damaged  structure  will   remain  attached  to  the   turbine   rather   than   separating   (Garrad   Hassan   Canada,   2007).   Reviews   of  available  information  did  not  find  any  recorded  evidence  of  injury  to  the  public  as  a  result  of  turbine  blade  or  structural  failure  (Garrad  Hassan  Canada,  2007;  Chatham-­‐Kent  Public  Health  Unit,  2008).  

Given  that  accidents  or  malfunctions  of  the  turbines  are  considered  to  be  infrequent  events,  and  turbines  will  be  located  at  least  the  minimum  regulated  setback  distance  from  any  residence,  the  event  of  a  failure  of  the  structure  will   likely  not  fall  beyond  the  setback  distance  and  would,  therefore,  not  affect  public  health  and  safety.  

5.9.1.2. Mitigation Measures

Modern   wind   turbines   must   meet   strict   international   engineering   standards.  Standards  include  the  ability  to  withstand  the  forces  of  a  Level  2  tornado  (i.e.,  wind  speeds  of  approximately  55  m/s),  and  structures  must  be  built   to  meet  earthquake  loads   as   per   the   Ontario   Building   Code.   The   structural   integrity   of   the   turbines   is  designed  to  withstand  wind  speeds  of  approximately  55  m/s.  However,  during  high  wind  events  (i.e.,  greater  than  24  m/s)  the  turbines  are  designed  to  cease  operation.  Turbine  braking   is   accomplished  by  aerodynamic   (blade  pitch)   control   and   friction  brakes.   The   wind   turbines   will   be   designed,   installed,   operated   and   maintained  according  to  applicable  industry  standards/certifications.  

The  Proponent  and  the  Operation  and  Maintenance  Contractor  will  aim  to  minimize  accidents  and  malfunctions  with  proper  training  and  education  of  staff  operating  the  control  system.   In  addition,   the   turbines  will  be  equipped  with   lightning  protection  systems  and  located  at  least  the  minimum  regulated  setback  distance  from  receptors.  

Page 64: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 59

5.9.1.3. Net Effects

As  a  result  of  the  structural  integrity  and  design  features  of  the  turbines,  no  adverse  net  effects  from  structural  failure  are  anticipated  during  operation  of  the  facility.  

5.9.2. Ice Fal l and Shed

5.9.2.1. Potential Effects

Another  potential  public  health  and  safety  issue  could  result  from  the  accumulation  of  ice  on  the  turbine  blades  under  specific  temperature  and  humidity  conditions.  This  condition   is   not   unique   to   wind   turbines   and   has   the   potential   to   occur   on   any  structure  that  is  exposed  to  the  elements.  In  Ontario,  this  condition  is  most  likely  to  occur   in   the   winter   months   in   extreme   weather   events.   However   meteorological  conditions  for  ice  formation  and  build-­‐up  are  considered  to  be  relatively  rare  within  the   study   area.   Under   these   conditions   the   turbines  may   be   subject   to   ice   coating  from  freezing  rain  or  interception  of  low  clouds  containing  super-­‐cooled  rain.    

There  are  two  potential  hazards  associated  with  ice  accumulation  on  wind  turbines:    

• The   danger   of   falling   ice   that  may   accumulate   on   the   turbine   as   a   result   of  freeze-­‐thaw  of  snow  and  ice;  and,  

• The  throwing  of  ice  from  the  moving  turbine  blades.  

Falling   ice   from  an   immobile   turbine  does  not  differ   from  other   tall   structures   like  telecommunication   towers,   power   lines,   and   antenna   masts.   The   potential   ground  area  affected  by   falling   ice  depends   to   a   large  extent  on   the  blade  position  and   the  prevailing  wind   speed   and   direction.   Garrad  Hassan   Canada   (2007)   estimated   that  only   very  high  winds  may   cause   ice   fragments  of   any   significant  mass   to  be  blown  beyond   50   m   of   the   base   of   a   modern,   stationary   2   MW   turbine   (80-­‐100   m   hub  height).  Operating   staff   and   landowners   are  briefed  on   this   situation;   therefore   the  risk  is  considered  minimal  (Garrad  Hassan  Canada,  2007).  

Wind  turbines  typically  operate  when  the  wind  speed  is  within  the  range  of  4  m/s  to  25  m/s;  when  turbines  are  in  operation  they  can  accumulate  ice  on  the  rotor  blades.  Ice   fragments  which  detach   from   the   rotor  blades  can  be   thrown   from   the   turbine;  any   fragments  would   land   in   the   plane   of   the   turbine   rotor   or   downwind   (Garrad  Hassan  Canada,  2007).  Throwing  distance  varies  depending  upon  the  rotor  azimuth,  rotor   speed,   rotor   radius,   and  wind   speed.   Also,   the   geometry   and  mass   of   the   ice  fragments  would  affect  the  flight  trajectory.      

Observations   have   shown   that   the   ice   fragments   do   not   maintain   their   shape   and  immediately   break   into   smaller   fragments   upon   detaching   from   a   blade.   This   will  decrease  drag  and  potentially  allow  the  ice  fragment  to  be  thrown  greater  distances.  For   human   injury   to   result   from   ice   shed,   several   conditions   would   have   to   exist  simultaneously:  

Page 65: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 60

• Sustained  weather  conditions  conducive  to  icing;  

• Ice  dislodging  from  the  turbine  blade;  

• Ice  pieces  large  enough  to  remain  intact  through  the  air;  

• Ice  traveling  in  a  particular  direction  past  setback  guidelines;  and,  

• A  person  in  the  path  of  the  ice  as  it  lands  (Garrad  Hassan  Canada,  2007).  

A   risk   assessment   methodology   was   developed   by   Garrad   Hassan   Canada   and  Partners,   in   conjunction   with   the   Finnish   Meteorological   Institute   and   Deutsches  Windenergie-­‐Institut,   as   part   of   a   research   Project   on   the   implementation   of  Wind  Energy   in   Cold   Climates   (WECO).   Guidelines   produced   in   the   WECO   Project   were  based   on   a   combination   of   numerical   modelling   and   observations.   The   WECO  database   of   observed   ice   fragments   determined   that   recorded   ice   fragments   are  typically  thrown  to  distances  less  than  125  m  from  the  base  of  the  turbine  (Seifert  et  al.,  2003).  

Garrad  Hassan  Canada  developed  an  Ontario-­‐specific   risk   assessment  methodology  for  ice  shed  based  on  the  findings  of  the  WECO  Project.  Modelling  was  undertaken  to  determine   the   probability   of   an   ice   fragment   landing   within   one   square   metre   of  ground  area,  as  a  function  of  distance  from  the  turbine.  The  model  result  determined  that  the  critical   ice  shed  distance  would  be  approximately  220  m  from  a  turbine.  At  distances  greater  than  220  m,  the  probability  of   ice  shed  reaching  ground  level  at  a  mass  that  would  cause  injury  decreases  rapidly.  The  critical  distance  can  effectively  be   regarded   as   a   “safe”   distance,   beyond  which   there   is   a   negligible   risk   of   injury  from  ice  shed  (Garrad  Hassan  Canada,  2007).  

Example   calculations   were   presented   in   the   Garrad   Hassan   Canada   (2007)   report,  using   data   representative   of   a   typical  wind   farm  Project   in   rural   southern  Ontario.  These  conditions  would  be  considered  representative  of  the  Gunn’s  Hill  Wind  Farm.  Risk   to   a   fixed   dwelling,   vehicle   travelling   on   a   road,   and   individual   person   from  being   struck   by   an   ice   fragment   thrown   from   an   operating   wind   turbine   were  modelled,  with  the  following  results:  

• Fixed  dwelling:  equivalent  to  1  strike  per  500,000  years;  

• Vehicle  travelling  on  a  road:  equivalent  to  1  strike  per  260,000  years;  and,  

• Individual  person:  equivalent  to  1  strike  in  137,500,000  years.  

These  predictions  seem  markedly  low;  however,  it  is  due  to  the  fact  that  icing  events  are  limited  to  only  a  few  days  per  year.  For  example,  Vestas  Canada,  which  maintains  turbines  across  Canada,  has  experienced  no  incidents  related  to  falling  ice  in  Canada  (Jacques  Whitford,  2006).      

Page 66: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 61

5.9.2.2. Mitigation Measures

Unlike  telecommunication  towers,  the  turbines  proposed  for  this  Project  will  have  a  solid  conical   tower.  This  design  reduces   the  potential   for   ice  build-­‐up  on   the   tower  since  there  is  no  lattice  or  crevices  where  ice  can  accumulate.      

In   terms   of   ice   shed,   several   control   mitigation   strategies   are   available   to   turbine  operators.  For  example,  when  the  rotor  becomes  unbalanced  due  to  a  change  in  blade  weighting  (e.g.  caused  by  ice  buildup),  the  turbine  brake  is  automatically  applied  to  stop  the  blades  from  turning  (i.e.  it  shuts  itself  off).  The  blades  would  not  restart  their  movement  until  the  imbalance  is  removed  (e.g.  the  majority  of  ice  is  removed).  This  design  feature  greatly  reduces  the  potential  for  ice  shed  from  the  turbines  on  the  few  days  per  year  when  icing  is  possible.    

5.9.2.3. Net Effects

Considering  the  design  features  of  the  turbines  which  act  to  reduce  or  eliminate  the  potential   for   ice   accumulation,   and   that   the   nearest   receptors   are   located   at  minimum  required   setbacks   from   the   turbines,  no  adverse  net   effects   are  expected  due  to  ice  fall  and  shed  from  turbines  during  operation  of  the  Project.    

5.9.3. Extreme Weather Events

5.9.3.1. Potential Effects

Extreme  weather  events  that  could  occur  during  operation  of  the  Project  include  fire,  flood,   temperature   extremes,   heavy   snow,   rain,   hail,   ice   storms,   tornadoes,  earthquakes,  and  lightning  strikes.        

The  likelihood  of  a  fire  occurring  during  operation  is  low.    If  a  fire  were  to  happen,  it  would   likely   occur   in   the   fields   at   the   base   of   the   turbine.     Fire   could   damage   the  turbine   tower   paint   but   it   is   unlikely   that   a   fire   would   damage   the   turbine  components  within  the  tower.  

Since   there   are   no  major  waterways   near   the  Project   Location,   it   is   unlikely   that   a  flood  would   occur.     Temperature   extremes,   to   the   extent   that   they   are   outside   the  turbine’s  operating  range,  are  not  expected.  

No   adverse   effect   is   anticipated   to   the   operation   of   the   turbines   from  heavy   snow,  except  to  prevent  access  to  the  turbines  during  an  emergency.  

In   the   case   of   an   extreme   hail   event,   the   nacelle   could   suffer   cosmetic   damage.    However,   the  operation  of   the  turbine  would  not  be  effected.     It   is  unlikely  that   the  nacelle   cover  would   suffer   structural   damage.     An   extreme  hail   event  may  damage  the  turbine’s  meteorological  sensors.    

Climatic   fluctuations   in   temperature   and/or   humidity   are   unlikely   to   have   a  significant  effect  on  the  Project.    A  change  in  the  annual  average  air  temperature  or  relative   humidity   could   (slightly)   affect   the   energy   production   of   the   Project   as  

Page 67: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 62

higher   density   air   (corresponding   to   lower   temperatures   and   lower   humidity)  will  result   in  higher  production  since   the  wind  power  density   is  a   linear   function  of   the  air  density.  

Climatic  variations  in  rainfall  or  snowfall  are  unlikely  to  affect  the  Project.    Variations  in   freezing   precipitation   (but   not   extreme   events)   could   change   the   overall   energy  production  through  inefficiencies  caused  by  modification  of  the  aerodynamic  profile  of   the   turbine  blade.    However,   such   events   occur   for   such   a   limited   time   that   it   is  very  unlikely  that  there  would  be  a  significant  impact  on  energy  production.  

A   change   in   the   wind   climate   is   the   likeliest   cause   for   significant   impact   on   the  Project’s   energy   production.     This   results   from   the   very   high   sensitivity   of   wind  power   density   to   the   wind   speed   (i.e.,   small   changes   in   wind   speed   can   result   in  relatively   large   changes   in   kinetic   energy   available   for   conversion   to   electrical  energy).    It  is  not  unusual  for  the  average  wind  speed  to  fluctuate  from  year  to  year  by   up   to   +/-­‐   10%.     This   maximum   would,   typically,   translate   into   Project   energy  fluctuations  of  +/-­‐  20  to  25%.      

5.9.3.2. Mitigation Measures

Weather   conditions  will   be   continuously  monitored   by   the   site  manager   during   all  project  phases  to  identify  potential  emerging  hazards  on  the  project  site.  

When  weather  forecasts  indicate  the  likelihood  of  extreme  events,  on-­‐site  work  and  operation  plans  will  be  modified  to  mitigate  potential  emergencies.  This  will  occur  in  several  stages  as  the  potential  for  extreme  weather  increases.  If  necessary,  all  work  will  be  stopped  and  staff  will  be   instructed  via  two-­‐way  radio  to  secure  equipment,  vacate   wind   turbines   and   adjacent   work   areas,   and   take   appropriate   shelter.   The  status   of   the   site   and   weather   will   be   continually   monitored   and   re-­‐evaluated   to  determine  if  additional  emergency  response  is  required.  

If  necessary  during  the  operation  phase,  turbines  will  be  shut  down,  the  blades  will  be   feathered   to  negate   lift,   and   the  rotors  will  be   locked   to  guard  against  excessive  loads  on  the  turbine  machinery  and  structures.  

Project   components   have   been   designed   to   withstand   effects   of   extreme   weather  events  as  follows:  

• Rain  –  surficial  drainage  patterns  will   remain   intact  and  continue   to  convey  rain  water;  

• Hail  –turbine  blades,  nacelle,  and  tower  are  constructed  of  materials  able  to  withstand  damage  from  the  impact  of  hail;  

• Ice   storms/freezing   rain   –   as   noted   above,   the   turbines   are   designed   to  automatically   shut   down   when   ice   load   on   the   blades   exceeds   a  predetermined  threshold;  

Page 68: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 63

• Tornadoes  –  the  blades  will  stop  moving  at  wind  speeds  greater  than  25  m/s,  and   generally,   the   structural   integrity   of   turbines   is   designed   to   withstand  gusts  of  greater  than  59  m/s;  

• Earthquakes  –structures  will  be  designed  to  meet  the  earthquake  loads  as  per  the  Ontario  Building  Code;  and  

• Lightning   –   turbines   are   equipped   with   sophisticated   lightning   protection;  lightning   strikes   are   safely   absorbed   by   conductors   and   the   current   is  conducted   via   a   spark   gap   and   cables   into   the   ground   surrounding   the  foundation.  

The   turbines   will   be   designed,   installed,   operated   and   maintained   according   to  applicable  industry  standards/certifications.  

5.9.3.3. Net Effects

Considering  the  design  features  of  the  turbine,  which  act  to  reduce  or  eliminate  the  potential   for   damage   from   extreme   weather   events,   no   adverse   net   effects   from  extreme  weather  events  are  anticipated  during  operation  of  the  facility.  

5.9.4. Third Party Damage

5.9.4.1. Potential Effects

Turbines   are   typically   located   away   from   roads   and   in   largely   open   areas.    Nevertheless,   the   possibility   exists   for   accidental   collision   with   off-­‐road   and  maintenance   vehicles.     Although   possible,   it   is   highly   unlikely   that   this   equipment  will   significantly   damage   the   towers   given   their   structural   integrity   (e.g.   the   rolled  steel   in   the   towers   is   over   an   inch   thick,   supporting   foundations,   and   surrounding  gravel  pad).    

5.9.4.2. Mitigation Measures

Access   to   the   towers   will   be   restricted   to   avoid   potential   accidents   to   unqualified  persons.  

5.9.4.3. Net Effects

As  a  result  of  restricting  access  of  unqualified  persons  to  the  turbines,  no  adverse  net  effects   from  third  party  damage  to   the   turbines  are  anticipated  during  operation  of  the  Project.  

5.9.5. Ground Level Injury to Personnel

5.9.5.1. Potential Effects

Safety  culture  will  be  of  utmost  importance  for  all  work  on-­‐site.  Nevertheless,  there  is  always   potential   for   an   injury   or   illness   to   occur   or   for   a   pre-­‐existing   condition   to  surface  while  personnel  are  on-­‐site.  This  type  of  event  has  the  potential  to  impact  the  health  of  the  individual  and  increases  risk  to  responders.  

Page 69: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 64

5.9.5.2. Mitigation Measures

All   construction,   operation,   and   decommissioning   staff   will   be   fully   trained   in   site  safety  requirements  and  protocols,  emergency  first  aid,  and  will  be  required  to  be  on-­‐site  with  at  least  one  additional  staff  member  at  all  times.  All  staff  will  have  access  to  two-­‐way  radio  and/or  mobile  phones  while  on-­‐site  with  pre-­‐designated  emergency  contacts.  

All  injuries  on-­‐site  will  be  reported  to  the  acting  site  manager  for  further  direction  on  appropriate  response.  The  chain  of  communication   in  Figure  5  and  Figure  6  will  be  followed   as   required.   Emergency   911   dispatch   will   determine   the   appropriate  responders   in   the  event   that   local   emergency   services  are   required   to  attend   to  an  injury   and/or   to   transport   injured   personnel   to   hospital.     If   safe   to   do   so,   injured  personnel   will   be   transported   to   a   predetermined  meeting   location   for   transfer   of  care  to  local  emergency  services.  The  local  emergency  services  and  the  EPC/OMT  will  remain  in  ongoing  contact  to  ensure  proper  coordination.  

5.9.5.3. Net Effects

The   likelihood   of   this   type   of   incident  will   be   in   compliance  with   labour   laws   and  regulations  using  best  industry  practices.  

5.9.6. Up-Tower Injury to Personnel

5.9.6.1. Potential Effects

Safety  culture  will  be  of  utmost  importance  for  all  work  on-­‐site.  Nevertheless,  there  is  always   potential   for   an   injury   or   illness   to   occur   or   for   a   pre-­‐existing   condition   to  surface   while   personnel   are   on-­‐site.   This   type   of   event   carries   considerable  additional   complication   if   the   individual   is   located   somewhere   above   ground   level  within   a   turbine   and   has   the   potential   to   impact   the   health   of   the   individual   and  significantly  increases  risk  to  responders.  

Local   emergency   response   capacity   is  not   configured   to  provide   services  up-­‐tower,  and  therefore  this  responsibility  is  covered  by  the  O  &  M  staff.  

5.9.6.2. Mitigation Measures

All   construction,   operation,   and   decommissioning   staff   will   be   fully   trained   in   site  safety   requirements   and   protocols   as   well   as   emergency   first   aid.   All   work   “up-­‐tower”  during  all  phases  of  the  project  requires  that  a  minimum  of  2  staff  be  present.    Regular   two-­‐way   radio   or   mobile   phone   contact   between   up-­‐tower   staff   and   a  supervisor  will  be  maintained.  

All  staff  working  up-­‐tower  will  be   fully   trained   in   tower  evacuation  and  rescue  and  will  be  equipped  with  an  emergency  evacuation  kit  either  on  their  person  or  within  the  nacelle.  

All  injuries  on-­‐site  will  be  reported  to  the  acting  site  manager  for  further  direction  on  appropriate  response.  The  chain  of  communication   in  Figure  5  and  Figure  6  will  be  

Page 70: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 65

followed   as   required.   Emergency   911   dispatch   will   determine   the   appropriate  responders   in   the  event   that   local   emergency   services  are   required   to  attend   to  an  injury  and/or  to  transport  injured  personnel  to  hospital.  A  hand-­‐over  between  O  &  M  staff  and  local  emergency  responders  would  then  occur  at  ground  level.  If  safe  to  do  so,   injured   personnel  will   be   transported   to   a   predetermined  meeting   location   for  transfer  of  care  to  local  emergency  services.  

5.9.6.3. Net Effects

The   likelihood   of   this   type   of   incident  will   be   in   compliance  with   labour   laws   and  regulations  using  best  industry  practices.  

5.9.7. Vehicle/Equipment Accident

5.9.7.1. Potential Effects

Safety  culture  will  be  of  utmost  importance  for  all  work  on-­‐site.  Nevertheless,  there  is  always   potential   for   a   vehicle/equipment   accident   on-­‐site.   This   can   lead   to   ground  level   injury   of   personnel,   spill   of   hazardous   fluid,   fire,   damaged   equipment,   and  trapped  personnel.    

5.9.7.2. Mitigation Measures

Access   roads   have   been   designed   with   maximum   visibility   and   few   intersections.  Equipment   operators  will   be   fully   trained   and   briefed   on   site   safety   requirements.  When   deemed   necessary,   traffic   directors/flags   people   will   be   used   to   control   the  flow  of  traffic  on-­‐site.  

Vehicle  and  equipment  accident  prevention  and  response  plans  will  be  specific  to  the  project   phase   and   the   associated   equipment.   Potential   elements   in   vehicle   and/or  equipment   accidents   such   as   personal   injury,   spill   of   hazardous   fluids,   and   fire   are  detailed  in  Sections  5.9.5,  5.8.2,  and  5.9.8  respectively.  

All  accidents  on-­‐site  will  be  reported  to  the  acting  site  manager  for  further  direction  on  appropriate  response.  The  chain  of  communication  in  Figure  5  and  Figure  6  will  be   followed   as   required.   Emergency   911   dispatch   will   determine   the   appropriate  responders   in   the  event   that   local   emergency   services   are   required   to   attend   to  an  accident.      

Though   extremely   rare,   some   of   the   unique   types   of   vehicle   and/or   equipment  accident   risks   that   can   exist   at   wind   projects   involve   large   cranes   or   the   turbine  structures   themselves.  Accidents  of   this  magnitude  will   require  careful  and  specific  response   evaluation.   Equipment   on-­‐site   such   as   other   cranes   or   heavy   machinery  may   be   required   in   an   emergency   response   in   addition   to   EPC,   OMT,   and   local  emergency  services.  

5.9.7.3. Net Effects

The   likelihood   of   this   type   of   incident  will   be   in   compliance  with   labour   laws   and  regulations  using  best  industry  practices.  

Page 71: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 66

5.9.8. Fire

5.9.8.1. Potential Effects

Fire   poses   risks   to   personnel,   project   equipment,   and   surrounding   crops   and  property.  

5.9.8.2. Mitigation Measures

Fire  prevention  strategies  will  be  established  for  the  site  by  the  EPC  and  OMT  for  all  phases  of  the  project.    

Remote  monitoring   of   commissioned   turbines   will   also   occur   to   avoid   operational  modes  that  could  cause  a  fire  (such  as  component  overheating)  and  will  also  be  used  to  detect  early  signs  of  fire.    

The  turbine  is  equipped  with  ion-­‐based  or  optical-­‐based  smoke  detectors  that  link  to  digital   inputs   in   the   turbine  control   system.  When  an  alarm   is   registered   in   case  of  smoke  in  a  panel  (or  failure  in  the  smoke  detector  circuit),  the  turbine  is  stopped  and  the  cooling  fans  in  all  cubicles  are  switched  off  in  order  to  reduce  the  admission  of  air  to   a   possible   fire   and   to   prevent   spreading   of   smoke   and   gasses   in   the   tower   and  nacelle.  Additionally,  all  motors  and  the  main  circuit  breaker  are  switched  off.  

The   weather   screen   and   housing   around   the   machinery   in   the   nacelle   is   made   of  fibreglass-­‐reinforced   laminated  panels  with  multiple   fire-­‐protecting  properties.  The  design   incorporates   fully   integrated   lightning   and   Electro-­‐Magnetic   Current   (EMC)  protection.  The  steel  tower  is  fully  enclosed  and,  as  such,  limits  a  possible  fire.  Both  Nacelle   and   Tower   act   as   a   Faraday   Cage   (blocking   external   static   and   non-­‐static  electric   fields),   thus   preventing   fire   caused   by   lightning   strikes.   Excess   grease   and  spilt  oil  are  collected  in  reservoirs  to  be  cleaned  out  during  scheduled  maintenance.  The  brake  system  is  shielded  around  the  moving  parts,  which  ensures  that  possible  sparks  will   not   spread   into   the  nacelle.   The  wind   turbine  has   an   efficient   lightning  protection   system   as   additional   protection   against   fire.   The   use   of   flammable  materials  has  been  avoided  to  the  greatest  extent  possible  in  the  turbine  design.  

All   fires  on-­‐site  will  be  reported   to   the  acting  site  manager   for   further  direction  on  appropriate  response.  The  chain  of  communication   in  Figure  5  and  Figure  6  will  be  followed   as   required.   Emergency   911   dispatch   will   determine   the   appropriate  responders   in   the  event   that   local  emergency  services  are  required   to  respond  to  a  fire.    

All  on-­‐site  personnel  will  be  permitted  to  use  fire  extinguishers  to  eliminate  fires  in  their   incipient   stage.   If   this   is   not   possible,   personnel   will   attempt   to   remove  additional   fuel   sources   in   the   vicinity   of   the   fire   (if   safe   to   do   so)   and   will   be  evacuated  from  the  area  surrounding  the  fire.    

Coordination  with  Norwich  Township   and  City  of  Woodstock   fire  departments  will  occur  to  determine  the  course  of  the  response.  

Page 72: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 67

The  main  potential   type  of   fire   unique   to  wind  projects   is   a   fire   in   the  nacelle   of   a  turbine.  Fire  in  the  nacelle  of  a  turbine  cannot  be  directly  extinguished  once  past  the  incipient   phase.   The   EPC   or   OMT   and   the   Fire   Department   will   be   required   to  monitor  a  fire  in  a  turbine  nacelle  from  a  safe  distance  to  prevent  any  spread  of  the  fire  to  other  locations.  OPP  will  be  called  to  divert  traffic  if  a  potential  risk  to  a  public  roadway  is  determined  during  this  time.  

Any  damage  to  crops  or  property  will  be  compensated.  

5.9.8.3. Net Effects

Fire  prevention  and  early  detection  measures  reduce  the  risk  and  severity  of  fire  on-­‐site.  Mitigation  measures  will  contain  a  fire  to  the  project  lands  and  shield  the  public  from  risk.  

Page 73: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 68

6. ENVIRONMENTAL EFFECTS MONITORING PLAN

The   environmental   effects   monitoring   plan   for   the   Project   has   been   designed   to  monitor  implementation  of  the  proposed  protection  and  mitigation  measures  and  to  verify  compliance  of  the  Project  with  O.  Reg.  359/09.  

Environmental  monitoring,  which  started  with  the  collection  of  primary  background  data,  will  continue  with  appropriate  follow-­‐up  activities  during  the  operation  of  the  Project.  Monitoring  will   provide   data   on   key   functions   of   natural   environment   and  socio-­‐economic  features  that  may  be  affected  during  construction  or  operation  of  the  Project,  and  on  the  effectiveness  of  mitigation  measures  implemented  as  part  of  the  Project.  The  monitoring  procedures  noted  herein  are   linked   to   the  potential   effects  and  protection  and  mitigation  measures  discussed  throughout  Section  5.  

Goals and Objectives

The  goals  of  the  monitoring  plan  are  to:  

• Minimize  environmental  effects  from  the  Project  during  the  operation  phase;  

• Minimize   conflicts   in   the   communities   affected   by   the   Project   according   to  legal  terms  and  to  the  Proponent’s  policies;  

• Avoid  accidents  and  malfunctions;    

• Minimize  environmental  effects  on  natural  habitats,  flora  and  fauna;  

• Avoid   levies   or   sanctions   from   relevant   government   agencies   for   negligent  environmental  performance;  

• Comply  with  environmental  quality  standards  set  by  law;  and,  

• Establish  measures  that  enhance  occupational  safety.  

Guiding Principles

The   following  guiding  principles  were   considered   in  preparation  of   the  monitoring  plan:    

• Focus  upon  environmental,  health,  and  safety  risk  prevention;  

• Conform   to   relevant   standards,   codes,   and   practices   considered   in   the  application  of  safe  technologies;  

• Perform  all  activities  in  a  safe  and  effective  manner,  by  trained  personnel;  

Page 74: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 69

• Maintain  all  equipment   in  good  operating  condition   for  protection  of  worker  health   and   safety,   conservation   of   the   environment,   and   protection   of  property;  

• Implement  all  necessary  precautions  to  control,  remove,  or  otherwise  correct  any  health  and  safety  hazards;  and,  

• Meet   all   relevant   county,   provincial,   and   federal   standards   that   collectively  ensure  sufficient  technical  levels  of  safety  during  operation  of  the  Project.  

6.1. Environmental Management Systems

As   part   of   the   environmental   monitoring   objectives,   several   programs,   plans,   and  procedures  will  be  developed  by  the  Proponent,  the  turbine  manufacturer,  and/or  the  operation  and  maintenance  contractor.    They  will  guide  the  operation  of  the  Project  to  optimize   its   environmental   performance.     In   order   for   the   programs,   plans,   and  procedures   to   be   effective,   appropriate   management   structures   and   contract  documents  must  be  firmly  established.  

6.1.1. Management Structures

The  Proponent  and/or   the  O&M  Contractor  will   take   steps   to  ensure   that   they  have  appropriately   skilled   personnel   to   carry   out   the   environmental   responsibilities   as  defined  in  this  document.    All  organizations  associated  with  Project  development  and  operational   activities   will   develop   responsive   reporting   systems   that   clearly   assign  responsibility  and  accountability.    As  appropriate,  the  Proponent  and/or  the  OMT  will  review  these  reporting  documents.      

6.1.2. Contract Documents

The   Proponent   is   committed   to   operating   the   Project   in   an   environmentally  responsible   manner   and   in   compliance   with   all   applicable   environmental   laws,  regulations,  and  guidelines.  All  of  the  Proponent’s  contractors  and  subcontractors  will  be  accountable   for  actions  that  have  an  adverse  effect  on  the  environment.    As  such,  any  contract  documents  executed  by  the  Proponent  and/or  the  O&M  Contractor  will  incorporate   appropriate   provisions   from   documents   prepared   for   the   REA  application.      

Additionally,   all   contractors,   subcontractors,   and  other   associates  of   the  Project  will  follow   the   guiding   principles   of   the   monitoring   program.     These   organizations   will  also  comply  with  all  relevant  municipal,  provincial,  and  federal  legislation.      

6.1.3. Change Management

During  the  operation  of  the  Project,  changes  to  operational  plans  may  be  required  to  address  unforeseen  or  unexpected  conditions  or  situations.  The  Proponent  and/or  the  O&M  Contractor  will  be  responsible  for  ensuring  environmental  and  safety  issues  are  

Page 75: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 70

addressed   for   any   such   changes.     The   Proponent   will   undertake   any   significant  changes   to   the  Project  programs,  procedures  and  plans   throughout   the  operation  of  the  Project  with  the  goal  of  avoiding  or  minimizing  environmental  effects.    

6.2. Programs, Plans, and Procedures

As   appropriate,   the   Proponent,   and/or   the   O&M   Contractor   will   implement   the  programs,  plans,  and  procedures  discussed  below.  

6.2.1. Operation and Maintenance Program

The  operation  and  maintenance  program,  including  turbine  maintenance,  is  described  in  Section  3.    

6.2.2. Environmental Procedures

The   Proponent   and/or   the   O&M   Contractor   will   be   responsible   for   implementing  environmental   procedures   during   the   operation   phase   of   the   Project.     Individual  employee   responsibilities   will   be   assigned   as   necessary   to   support   the   full   and  effective   implementation   of   the   environmental   procedures.     As   appropriate   the  environmental  procedures  will  address  the  following  issues  to  prevent  environmental  contamination  and  injury  to  personnel:  

• Environmental   calendar:   to   establish   the   specific   dates   and   times   for  environmental   inspections   of   turbine   facilities,   monitoring   events,   and  emergency  notifications;  

• Spills   and   releases:   to   identify   the   specific   procedures   for   the   prevention,  response,   and   notification   of   spills.     In   addition,   establish   the   general  procedures   for   spill   clean-­‐up,   personnel   training,   and  material   handling   and  storage  to  prevent  spills;      

• Hazardous   waste   management:   to   outline   the   procedures   for   proper  identification,   storage,   handling,   transport,   and   disposal   of   hazardous  waste.    In   addition,   the   procedures   will   outline   specific   requirements   for   personnel  training,   emergency   response,   product   review   and   approval,   and   record  keeping;  and,  

• Non-­hazardous  waste  management:  to  establish  alternative  procedures  for  the  management  and  disposal  of  used  lubricants,  used  drums,  and  general  waste.  

These  procedures  will   ensure   internal   and  external   risks  are   fully  evaluated  and   the  information  communicated  to  personnel  in  advance  of  any  accident  or  malfunction.    

6.2.3. Occupational Health and Safety Procedures

The  Proponent  and/or  the  O&M  Contractor  will  ensure  employee  health  and  safety  is  maintained  throughout  their  employment  term  and  will  also  implement  the  following  safety  procedures  and  protocols  as  appropriate  in  an  effort  to  ensure  employee  safety  is  addressed  throughout  operation  and  maintenance  activities:  

Page 76: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 71

• Personal   protective   equipment,   including   non-­‐slip   footwear,   eye   protection,  clothing,  and  hardhats,  will  be  worn  by  operations  and  maintenance  personnel  when  on  duty;  

• Elevated   platforms,  walkways,   and   ladders  will   be   equipped  with   handrails,  toe  boards,  and  non-­‐slip  surfaces;  and,  

• Electrical   equipment  will   be   insulated   and   grounded   in   compliance  with   the  appropriate  electrical  code.    

Incidents   in   the  work  place  have  the  potential   to  cause  personal   injury  and  property  damage.    As  appropriate,  the  O&M  Contractor  will  maintain  a  master  Incident  Report  that   documents   illnesses   and   accidents.     Incident   reporting   will   follow   the  requirements  of  the  Occupational  Health  and  Safety  Act.    

6.2.4. Training Program

As   appropriate,   the   Proponent   and/or   the   O&M   Contractor  will   develop   or   have   an  existing  operations  training  program  to  ensure  personnel  receive  appropriate  training  in  relation  to  operation  and  maintenance  programs,  environmental,  health,  and  safety  procedures,  and  the  Emergency  Response/Preparedness  Plan.    Training  may  include,  but  not  be  limited  to,  the  following  issues:  

Facility  Safety  

• Accident  reporting;  • Chemical  and  hazardous  materials  handling;  • Fall  and  arrest  protection;  • Eye,  ear,  head,  hands,  feet,  and  body  protective  equipment;  • First  aid  training  and  equipment;  • Equipment  operation  and  hazards;  • Fire  prevention  and  response;  • Lockout  and  tag  out  procedures;  and,  • Scaffolds  and  ladders.  

Emergency  Preparedness  

• Fire  preparedness  and  response;  • Natural  disasters  (i.e.,  extreme  weather  events);  • Hazardous  materials  and  spill  response;  • Medical  emergencies;  and,  • Rescue  procedures.      

6.2.5. Emergency Response/Preparedness Plan

As   indicated   in   Section   4.1.2,   an   Emergency   Response/Preparedness   Plan   will   be  drafted  for  the  site  in  advance  of  construction  and  will  cover  all  phases  of  the  project.  This  process  will  be  carried  out  in  consultation  with  local  emergency  services,  the  EPC,  and   the   OMT.   Though   a   detailed   and   specific   plan   is   not   part   of   the   REA   process,   a  

Page 77: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 72

sample  Emergency  Preparedness/Response  Plan  template   is   included  as  Appendix  E.  This  is  a  document  in  the  public  domain  that  a  specific  turbine  manufacturer  adapts  to  each  site  where  their  turbines  will  be  operating.    

6.2.6. Measurement of Performance

Once  performance  standards  have  been  established  and  personnel  have  been  trained  (and   are   functional   in   procedural   operations),   the   next   step   is   to   monitor   the  performance  of  the  facility  and  individuals  relative  to  the  performance  standards  and  programs.      

Specific   internal   audits   (e.g.   management   team   and/or   process   team),   and   external  audits  against  the  plans,  safety  and  environmental  procedures,  and  other  policies  and  procedures  are  all  part  of  establishing  performance  standards  necessary  to  minimize  risks  on  a  continuing  basis.      

As   appropriate   a   formal   audit   program   for   the   Project,   with   regard   to   loss   control  programs  (i.e.,  health,  safety,  environment,  and  security)  will  be  performed  regularly.  

6.3. Monitoring Requirements and Contingency Plans

Building  upon   the  environmental  management  measures  recommended   to  minimize  potentially   adverse   effects,  while   enhancing   the   positive   effects   associated  with   the  operation   of   the   facility,   the   following   operations   monitoring   and   contingency  planning  program  has  been  developed.    The  monitoring  program  is  designed  to  allow  the  Proponent  and/or  the  O&M  Contractor  to  monitor  and  assess  the  effectiveness  of  the   proposed  management  measures/mitigation  measures   and   to   verify   compliance  of  the  Project  with  O.  Reg.  359/09.      

The   Proponent   and/or   the   O&M   Contractor   will   be   the   primary   organization  responsible   for   the   implementation   of   the   operational   monitoring   and   contingency  planning  measures.   Implementation   of   the   measures   will   be   undertaken   consistent  with   the   Proponent   and/or   the   O&M   Contractor   standard   environmental   and  engineering  practices.      

6.3.1. Terrestr ial Habitat and Signif icant Natural Features

Operational   activities   that   have   the   potential   to   affect   terrestrial   flora   and   fauna  include  equipment  operation  and  accidental  spills  and/or  leaks.    Stringent  monitoring  of   operational   activities   is   necessary   to   ensure   terrestrial   flora   and   fauna   are  protected.  

As   appropriate,   records  of   vehicle  maintenance  will   be   retained   and  made  available  for   periodic   review   by   the   Proponent   and/or   the   O&M   Contractor.   All   vehicles  involved   in  maintenance   activities  must  be  maintained   in   good  operating   condition;  

Page 78: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 73

all  vehicles  identified  through  the  monitoring  program  that  fail  to  meet  the  minimum  emission  standards  will  be  repaired  immediately  or  replaced  as  soon  as  practicable.      

Monitoring   will   be   required   following   the   unlikely   event   of   contamination   from   an  accidental  spill  or  leak  (method  for  monitoring  may  be  developed  in  consultation  with  the   Spills   Action   Centre   of   the   MOE).     Contaminated   soils   will   be   removed   and  replaced  as  appropriate.  

6.3.2. Birds and Bats

The   project   is   located   within   an   active   agricultural   landscape   where   there   is   little  remnant  natural  habitat  remaining.  The  focus  of  pre-­‐construction  monitoring  was  on  breeding   birds,   migrating   birds,   wintering   birds,   migrating   and   resident   bats,    endangered   species   and   significant   wildlife   habitat.   Protocols   were   developed   and  vetted  through  the  Ontario  Ministry  of  Natural  Resources  (MNR).  

Some   specific   performance   objectives   were   provided   by   the   MNR   and   some   pre-­‐construction  protocols  were  vetted  through  the  agencies  and  a  mutually  agreed  study  plan   was   developed   and   implemented.   Continuing   consultation   is   maintained   to  ensure   that  professional  overview  of   the  project  occurs  and   that  adaptations  can  be  made,   if   required.   Pre-­‐construction   bird,   bat   and   other   wildlife   monitoring   data   is  included  in  the  Natural  Heritage  Assessment  Report.  

The  foremost   important  measure  to  minimize  negative  environmental  effects  was  to  choose  a  location  that  was  unlikely  to  interfere  with  natural  ecosystem  functions  and  that   was   known   to   have   limited   sensitive   ecosystem   value   such   as   endangered  species,  migration  corridors  or  unique  habitat  elements.  The  Gunn’s  Hill  Wind  Farm  project   area  was   screened,  with   the  use  of   the  Natural  Heritage   Information  Centre,  Ontario   Breeding   Bird   Atlas,   Christmas   Bird   Counts,   the   Breeding   Bird   Survey,   and  other   sources   that   provided   baseline   historical   information.   This   screening   process  was   followed   by   scientifically   designed   field   surveys   that   were   tailored   to   provide  detailed   data   on   potentially   sensitive   features   identified   in   the   screening   process.  Comments  and  suggestions  from  EC  and  MNR  were  also   incorporated   into  the  study  protocols.  

The  results  of  all  aspects  of  the  field  program  support  the  initial  screening  conclusion  that   the   Gunn’s   Hill   Wind   Farm   is   unlikely   to   cause   significant   impact   to   natural  heritage   features.   The   area   was   shown   to   have   few   sensitive   species.   Indeed,   all  species  documented  are  those  that  are  well  adapted  to  the  highly  disturbed  habitats  of  this   agricultural   area.  The   area  was   shown   to  not   be  one  of   concentrated  migration  movements  during  the  fall  period,  a  period  when  there  is  most  concern  for  migrating  birds.  The  winter  landscape  was  shown  to  be  one  of  low  diversity  of  species  and  not  likely  to  result   in  significant  harm  to  any  bird  species.  Bat  diversity  was  found  to  be  relatively  low.  Both  RADAR  and  acoustical  surveys  show  that  the  project  area  is  not  a  

Page 79: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 74

concentration  area  for  either  migrating  or  breeding  bats  and  that  there  are  no  known  bat  hibernacula  areas  nearby.  

A  detailed  Environmental  Effects  Monitoring  Plan  for  wildlife  is  provided  in  Appendix  F.     A   post-­‐construction  monitoring   program   has   been   developed   for   birds   and   bats  that   is   consistent   with   guidelines   provided   by   regulatory   agencies   at   the   time   of  writing.     The   plan   gives   consideration   to   adaptive   management   and   operational  control  options.    Elements  of  the  bird  and  bat  post-­‐construction  monitoring  program  include:  

• Bird   and   bat   mortality   monitoring   at   all   wind   turbines   will   be   conducted  twice-­‐weekly  (3-­‐4  day  intervals)  at  all  turbines  from  May  1  -­‐  October  31  and  once-­‐weekly  from  November  1  -­‐  November  30  for  three  years  following  start  of  operations.  

• Searcher   efficiency   and   carcass   removal   trials   will   be   conducted   seasonally  (spring,  summer,  and  fall)  between  May  1  -­‐  October  31,  and  repeated  for  each  searcher.  Searcher  efficiency  and  carcass  removal  rates  are  known  to  be  more  variable  for  bats  than  for  birds  throughout  the  year  and  depending  on  habitat  (in  part  due  to  the  relative  size  of  the  species).    Data  from  these  trials  will  be  used   to  provide  corrected  mortality  rate  estimates  as  per  standard  guideline  methods.  

• Reports  will  be  prepared  at  the  end  of  each  year  of  the  program  and  submitted  to  the  MNR  within  3  months  of  the  end  of  fall  monitoring.  Mortality  frequency  will   be   reported   as   per   the   recommendations   in   the   MNR   guideline  documents,  and  will,  in  the  end,  be  expressed  as  birds  or  bats  per  turbine  per  year,  corrected  for  the  effect  of  scavenger  rates  and  searcher  efficiency.      

• Should  significant  mortality  events  be  detected  during  the  program,  MNR  will  be   notified.   Such   an   event   will   be   considered   to   be   ten   bats   or   ten   bird  mortalities   detected   during   any   single   day   of   searching   (or   as   otherwise  defined  by  MNR).    

• If  required,  mitigation  techniques  may  include  (but  not  limited  to)  operational  controls,   such   as   periodic   shut-­‐down   and/or   blade   feathering   (if   annual  mortality   levels   exceed   MNR   thresholds).     Results   will   be   reviewed   by   the  Proponent,   MNR   and   other   relevant   agencies   to   determine   if   and   when  additional  monitoring  and/or  mitigation  are  required.  

6.3.3. Signif icant Wildl i fe Habitat

A   detailed   Environmental   Effects   Monitoring   Plan   (EEMP)   for   significant   wildlife  habitats  identified  within  the  Zone  of  Investigation  is  provided  in  Appendix  F.      

Page 80: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 75

Should  additional  pre-­‐construction  surveys   identify  significant  wildlife  habitat   in  the  Project   Area,   post-­‐construction   disturbance   monitoring   programs   have   been  developed   for   those   potential   Significant  Wildlife   Habitats   identified   for   Amphibian  Breeding  Wildlife  Habitat  and  Bat  Maternity  Colonies.  

Amphibian  Breeding  Habitat  will  require  one  year  of  post-­‐construction  monitoring  as  outlined  in  the  EEMP.  This  involves  Call  Counts  for  anuran  (frog/toad)  species  at  the  identifies  habitat.  Further  details  can  be  found  in  the  EEMP  in  Appendix  F.    

Bat   Maternity   Colonies   will   require   three   years   of   exit   surveys   at   significant   bat  maternity   roosts   to   determine   the   impact   of   wind   turbine   operation   on   the   use   of  maternity  roosts.  Further  details  can  be  found  in  the  EEMP  in  Appendix  F.  

6.3.4. Surface Water Features and Aquatic Habitat

Operation   activities   that   have   the   potential   to   affect   aquatic   habitat   includes  accidental  spills  and/or  leaks.    Proper  storage  of  materials  (e.g.  maintenance  fluids)  at  off-­‐site  storage  containers  will  greatly  reduce  the  potential  for  accidental  spills  and/or  leaks.  Appropriate  remedial  measures  may  be  completed  as  necessary  and  additional  follow-­‐up   monitoring   conducted   as   appropriate   in   the   event   of   an   accidental   spill  and/or  leak.    The  level  of  monitoring  and  reporting  will  be  based  on  the  severity  of  the  spill/leak   and   may   be   discussed   with   the   MOE   (Spills   Action   Centre)   and   MNR.    Environmental   inspection   following   spring   run-­‐off   the   year   after   construction   (first  year   of   operation)   may   be   considered   to   ensure   surface   drainage   has   been  maintained.  

6.3.5. Environmental Noise and Public Health and Safety

The  Project  will  follow  the  guidelines  put  in  place  by  the  MOE  regarding  sound  levels  and   minimum   distances   for   wind   projects   in   Ontario.   The   key   consideration   is   the  sound   level.   The   requirements,   supported   by   information   from   the   Ontario   Chief  Medical  Officer  of  Health,  Health  Canada,  and  the  World  Health  Organization  (WHO)  Europe  and  upheld  by  Ontario  courts,  ensure  a  project  must  be  sited  at   least  550  m  from  non-­‐participating  receptors,  provided  the  cumulative  sound  level  at  the  receptor  does   not   exceed   thresholds   established   by   the   MOE.   Siemens   has   guaranteed   the  maximum   sound   power   level   from   the   turbines.   This   level   has   been   used   in  calculations   to   ensure   the   sound   level   at   non-­‐participating   receptors   meets   the  requirements  of  the  Regulation.    

The  Environmental   Protection   Act   (EPA)   requires   that   noise   emissions   for   any   new  project  must  not  have  adverse  effects  on  the  natural  environment.    The  REA  process  is  the  mechanism  through  which  the  controls  are  administered  under  the  EPA,  and  the  Proponent  commits  to  comply  with  any  conditions  and  requirements  for  the  approval,  as  directed  by   the  MOE.     In   the   event  of   a  malfunctioning   turbine   resulting   in  noise  emissions   that  are  above  MOE  requirements,   the  Proponent  will   contact   the  MOE  to  

Page 81: GUNN’S HILL WIND FARM O R FINAL...GUNN’S HILL WIND FARM DESIGN AND OPERATIONS REPORT FINAL June 2013 Gunn’s Hill Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario

Gunn’s Hill Wind Farm Design and Operations Report

June 2013 76

determine   the  best  path   forward   for   resolving   the   issue.  The   resolution  of   the   issue  could  include  shutting  down  or  reducing  the  nameplate  capacity  of  the  non-­‐compliant  turbine(s)  until  the  problem  is  resolved.  Routine  turbine  maintenance  and  electronic  monitoring  will  also  help  minimize  the  likelihood  of  malfunctioning  turbines  resulting  in  excessive  noise  emissions.  

Turbines  will  be  monitored  electronically  twenty-­‐four  hours  a  day,  seven  days  a  week,  to   allow   operational   changes   to   be   noted   and   assessed   quickly.   Turbine   shut   down  will  occur  automatically  upon  detection  of  extreme  weather.   Inspections  of   turbines  will  occur  after  extreme  weather  events.    

6.4. Community Relations

6.4.1. Local Expenditures

As   was   the   case   during   the   construction   phase,   the   Proponent   will   continue   to  encourage   the   use   and   procurement   of   local   goods   and   services   where   they   are  available  in  sufficient  quantities  and  qualities  and  at  competitive  pricing.  

6.4.2. Community Benefit Fund Committee

The   Proponent   has   committed   to   providing   a   $25,000   annual   community   benefit    fund,  to  be  administered  by  an  open  and  local  committee  comprised  of  local  citizens.  The   proposed   structure   is   to   have   the   committee   recommend   annual   funding  allocation(s)   to   initiatives   that   have   accessible   benefit   to   the  wider   community,   and  present   the   recommendation   to   the  Proponent   for   sign-­‐off.   Consultation   to  date  has  identified   the  park  and  playground  at   the  corner  of  Curries  Rd  and  Hwy  59  and   the  community  centre  in  Oxford  Centre  as  potential  recipients.    

6.4.3. Community Complaints

Avenues  for  the  community  to  contact  the  Proponent,   including  with  any  complaints  have  been  presented  in  Sections  4.4.2  and  5.5.3.