Guam Transportation Program Project Updates Joanne M.S. Brown Director Carl Dominguez Deputy Director February 6, 2012

Upload: others

Post on 25-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Guam Transportation Program Project Updates  

Joanne M.S. Brown Director

Carl Dominguez Deputy Director

February 6, 2012

Page 2: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

•  Road Construction Highlights

•  Ongoing Construction

–  Route 17 Rehabilitation and Widening

–  Route 7A Resurfacing & Pavement Rehabilitation

•  Planning & Design

–  Route 1 / Route 8 Intersection Improvements

& Agana Bridges Replacement (Design-Build)

–  Tiyan Parkway

–  Guam Transportation Improvement Plan 2012-2015

Agenda

Page 3: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

•  18 projects worth $102 million are under construction, 11 of which will be complete by June 2012

•  Asphalt base course and friction course pavements that meet all federal requirements are now being produced

•  Working to streamline:

–  Contract and Change Order Approval Process

–  Building Permit Approval Process

–  Payment Review and Processing

Roadway Construction Highlights

Page 4: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August
Page 5: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Route 17 Resurfacing

•  Contractor: Sumitomo Mitsui

•  Construction Management: TG Engineers

•  Cost: $5.6 million

•  Scope of Work: reconstruct and widen from Route 4 to Route 4A, including drainage and four foot shoulders

Page 6: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Route 17 Resurfacing

•  Base Course pavement has been completed on about 90% of the project

•  Utility relocations underway at the hairpin curve

•  Expected completion: June 2012

Page 7: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Route 7A Pavement Rehabilitation

Page 8: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

•  Contractor: Sumitomo Mitsui Construction Co.

•  Scope of Work: Pavement Reconstruction – Route 4 to Route 8

–  Major drainage system upgrades

–  Replacement of approaches at Mindoro Bridge from asphalt to concrete

–  New sidewalks, curbs and gutters

•  Return to two-way traffic: May 2012

•  Expected project completion: October 2012

Route 7A Pavement Rehabilitation

Page 9: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August
Page 10: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Featured Projects Planning-Design

•  Route 1 / Route 8 Intersection Improvements & Agana Bridges Replacement (Design-Build)

•  Tiyan Parkway

•  Transportation Improvement Plan 2012 - 2015

Page 11: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Route 1 / Route 8 Intersection Improvements

& Agana Bridges Replacement (Design-Build)

Agana Bridge #2 Chalan Santo Papa Juan Pablo Dos

Agana Bridge #1 Route 1 (Marine Corps Drive)

Page 12: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August
Page 13: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Route 1 / Route 8 Intersection Improvements

& Agana Bridges Replacement (Design-Build)  

Project Information

Contractor: CoreTech International

Cost: $16.4 million Jointly funded by FHWA & DOD

Project Start: October 2011

Completion: December 2013    

Page 14: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Project Timeline

Final Design/Permits: October 2011 – May 2012

Preliminary Site Work: February – April 2012

Rte 1 / Rte 8 & Bridge #1 April 2012 – June 2013 Construction (3-phase) Bridge #2 Construction: June 2013 – December 2013

Route 1 / Route 8 Intersection Improvements

& Agana Bridges Replacement (Design-Build)  

*Dates are approximate and subject to change.

Page 15: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

PHASE 1

Construction Sequence & Traffic Control – Agana Bridge #1

PHASE 2

PHASE 3

Route 1 / Route 8 Intersection Improvements

& Agana Bridges Replacement (Design-Build)  

Page 16: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Tiyan Parkway

Rte 1

Rte16

Rte10A

Rte 8

East Sunset Blvd

Rte10

Existing Entrance to Tiyan from Rte 8

Existing Road Network

Page 17: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Tiyan Parkway

GIAA Road Closure Points

Central Avenue & other roads to be Closed

Existing Traffic Signal

Gates on Route 8 to be Closed

Page 18: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Tiyan Parkway

Alignment Alternate 4

Page 19: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Tiyan Parkway

Right-of-Way Acquisition Plan •  DPW owns no right-of-way at Tiyan

•  Phase 1 ROW to be acquired from GIAA using FHWA funds (avoidance of cliff line retaining walls)

•  Phase 1 sale is contingent on assurances that Phase 2 ROW will be re-acquired by the Government

•  DPW is working cooperatively with GIAA, DLM and the Governor’s office on the Phase 2 ROW acquisition plan

Page 20: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Tiyan Parkway

Phase 1 Project Information

Designer: Duenas Camacho & Associates

Est. ROW Cost: $5.6 million

Est. Const. Cost: $9.9 million

Design Start: April 2012

Completion: December 2012    

Page 21: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Tiyan Parkway

Project Timeline – Phase 1 NEPA Clearance: June 2012

Final Design: April 2012 – December 2012

ROW Acquisition: April 2012 – September 2012

Bid/Award/Permit: January 2013 – August 2013

Construction: September 2013 – June 2014

GIAA Road Closures: February 2013 or TBD

*Dates are approximate and subject to change.

Page 22: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Guam Transportation Improvement Plan

2012 - 2015  

•  Guam TIP is a four year financially constrained plan required by federal statute

•  Draft 2012-2015 TIP has been developed

•  Primary fund source is approximately $18.4M a year from the Federal Highway Administration

•  GARVEE bond is under consideration to leverage and accelerate FHWA funding

•  No DOD funding in the 2012-2015 plan

Page 23: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Guam Transportation Improvement Plan

2012 - 2015

Project Construction Value Route 17 Phase 2A – Drainage Culverts $1,610,000

Route 4 Agfayan Bridge Replacement $3,595,000

Bile & Pigua Bridges Replacement $2,532,000

Route 4 Merizo Bridge Roadway Restoration $1,208,000

Traffic Signal System Upgrade - Islandwide $1,779,000

Traffic Mgt Center - Communications $2,042,000

Route 4 Inarajan North Leg Bridge Repair $2,392,000

Continued Next Slide

2012 Construction Projects (Draft Plan)

Page 24: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Guam Transportation Improvement Plan

2012 - 2015

Project Construction Value Route 4 Togcha River to Ipan Beach Park $630,000

Route 3A Extension, Jinapsan Access $2,415,000

Rte 1 Bridge Rehab – Asan & Aguada Rivers $1,380,000

ADA Compliance $1,510,000

Route 4 Merizo Creek Culvert Replacement $1,725,000

TOTAL $22,818,000

2012 Construction Projects (Draft Plan)

Page 25: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August

Si Yu’us Ma’ase

For more information visit: www.guamtransportationprogram.com