Guam Transportation Program Project Updates
Joanne M.S. Brown Director
Carl Dominguez Deputy Director
February 6, 2012
![Page 2: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/2.jpg)
• Road Construction Highlights
• Ongoing Construction
– Route 17 Rehabilitation and Widening
– Route 7A Resurfacing & Pavement Rehabilitation
• Planning & Design
– Route 1 / Route 8 Intersection Improvements
& Agana Bridges Replacement (Design-Build)
– Tiyan Parkway
– Guam Transportation Improvement Plan 2012-2015
Agenda
![Page 3: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/3.jpg)
• 18 projects worth $102 million are under construction, 11 of which will be complete by June 2012
• Asphalt base course and friction course pavements that meet all federal requirements are now being produced
• Working to streamline:
– Contract and Change Order Approval Process
– Building Permit Approval Process
– Payment Review and Processing
Roadway Construction Highlights
![Page 4: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/4.jpg)
![Page 5: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/5.jpg)
Route 17 Resurfacing
• Contractor: Sumitomo Mitsui
• Construction Management: TG Engineers
• Cost: $5.6 million
• Scope of Work: reconstruct and widen from Route 4 to Route 4A, including drainage and four foot shoulders
![Page 6: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/6.jpg)
Route 17 Resurfacing
• Base Course pavement has been completed on about 90% of the project
• Utility relocations underway at the hairpin curve
• Expected completion: June 2012
![Page 7: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/7.jpg)
Route 7A Pavement Rehabilitation
![Page 8: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/8.jpg)
• Contractor: Sumitomo Mitsui Construction Co.
• Scope of Work: Pavement Reconstruction – Route 4 to Route 8
– Major drainage system upgrades
– Replacement of approaches at Mindoro Bridge from asphalt to concrete
– New sidewalks, curbs and gutters
• Return to two-way traffic: May 2012
• Expected project completion: October 2012
Route 7A Pavement Rehabilitation
![Page 9: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/9.jpg)
![Page 10: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/10.jpg)
Featured Projects Planning-Design
• Route 1 / Route 8 Intersection Improvements & Agana Bridges Replacement (Design-Build)
• Tiyan Parkway
• Transportation Improvement Plan 2012 - 2015
![Page 11: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/11.jpg)
Route 1 / Route 8 Intersection Improvements
& Agana Bridges Replacement (Design-Build)
Agana Bridge #2 Chalan Santo Papa Juan Pablo Dos
Agana Bridge #1 Route 1 (Marine Corps Drive)
![Page 12: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/12.jpg)
![Page 13: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/13.jpg)
Route 1 / Route 8 Intersection Improvements
& Agana Bridges Replacement (Design-Build)
Project Information
Contractor: CoreTech International
Cost: $16.4 million Jointly funded by FHWA & DOD
Project Start: October 2011
Completion: December 2013
![Page 14: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/14.jpg)
Project Timeline
Final Design/Permits: October 2011 – May 2012
Preliminary Site Work: February – April 2012
Rte 1 / Rte 8 & Bridge #1 April 2012 – June 2013 Construction (3-phase) Bridge #2 Construction: June 2013 – December 2013
Route 1 / Route 8 Intersection Improvements
& Agana Bridges Replacement (Design-Build)
*Dates are approximate and subject to change.
![Page 15: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/15.jpg)
PHASE 1
Construction Sequence & Traffic Control – Agana Bridge #1
PHASE 2
PHASE 3
Route 1 / Route 8 Intersection Improvements
& Agana Bridges Replacement (Design-Build)
![Page 16: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/16.jpg)
Tiyan Parkway
Rte 1
Rte16
Rte10A
Rte 8
East Sunset Blvd
Rte10
Existing Entrance to Tiyan from Rte 8
Existing Road Network
![Page 17: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/17.jpg)
Tiyan Parkway
GIAA Road Closure Points
Central Avenue & other roads to be Closed
Existing Traffic Signal
Gates on Route 8 to be Closed
![Page 18: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/18.jpg)
Tiyan Parkway
Alignment Alternate 4
![Page 19: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/19.jpg)
Tiyan Parkway
Right-of-Way Acquisition Plan • DPW owns no right-of-way at Tiyan
• Phase 1 ROW to be acquired from GIAA using FHWA funds (avoidance of cliff line retaining walls)
• Phase 1 sale is contingent on assurances that Phase 2 ROW will be re-acquired by the Government
• DPW is working cooperatively with GIAA, DLM and the Governor’s office on the Phase 2 ROW acquisition plan
![Page 20: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/20.jpg)
Tiyan Parkway
Phase 1 Project Information
Designer: Duenas Camacho & Associates
Est. ROW Cost: $5.6 million
Est. Const. Cost: $9.9 million
Design Start: April 2012
Completion: December 2012
![Page 21: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/21.jpg)
Tiyan Parkway
Project Timeline – Phase 1 NEPA Clearance: June 2012
Final Design: April 2012 – December 2012
ROW Acquisition: April 2012 – September 2012
Bid/Award/Permit: January 2013 – August 2013
Construction: September 2013 – June 2014
GIAA Road Closures: February 2013 or TBD
*Dates are approximate and subject to change.
![Page 22: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/22.jpg)
Guam Transportation Improvement Plan
2012 - 2015
• Guam TIP is a four year financially constrained plan required by federal statute
• Draft 2012-2015 TIP has been developed
• Primary fund source is approximately $18.4M a year from the Federal Highway Administration
• GARVEE bond is under consideration to leverage and accelerate FHWA funding
• No DOD funding in the 2012-2015 plan
![Page 23: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/23.jpg)
Guam Transportation Improvement Plan
2012 - 2015
Project Construction Value Route 17 Phase 2A – Drainage Culverts $1,610,000
Route 4 Agfayan Bridge Replacement $3,595,000
Bile & Pigua Bridges Replacement $2,532,000
Route 4 Merizo Bridge Roadway Restoration $1,208,000
Traffic Signal System Upgrade - Islandwide $1,779,000
Traffic Mgt Center - Communications $2,042,000
Route 4 Inarajan North Leg Bridge Repair $2,392,000
Continued Next Slide
2012 Construction Projects (Draft Plan)
![Page 24: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/24.jpg)
Guam Transportation Improvement Plan
2012 - 2015
Project Construction Value Route 4 Togcha River to Ipan Beach Park $630,000
Route 3A Extension, Jinapsan Access $2,415,000
Rte 1 Bridge Rehab – Asan & Aguada Rivers $1,380,000
ADA Compliance $1,510,000
Route 4 Merizo Creek Culvert Replacement $1,725,000
TOTAL $22,818,000
2012 Construction Projects (Draft Plan)
![Page 25: Guam Transportation Program Project Updates · Final Design: April 2012 – December 2012 ROW Acquisition: April 2012 – September 2012 Bid/Award/Permit: January 2013 – August](https://reader033.vdocuments.us/reader033/viewer/2022060321/5f0d277f7e708231d438f121/html5/thumbnails/25.jpg)
Si Yu’us Ma’ase
For more information visit: www.guamtransportationprogram.com