g.s.m based three phase fault analysis with auto reset
TRANSCRIPT
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 1 of 108
CONTENTS
TABLE OF FIGURE ...................................................................................................................... 4
CHAPTER 1: Introduction ............................................................................................................. 6
1.1 FUNCTIONALITY ............................................................................................................... 7
1.2 PROBLEM CONTEXT ........................................................................................................ 8
1.3 CHALLENGES IN THE PROJECT ..................................................................................... 8
1.3.1 New technology need to be learnt: ................................................................................. 9
1.4 TANGIBLE BENEFIT & INTANGIBLE BENEFITS ........................................................ 9
1.4.1 TANGIABLE BENEFIT ................................................................................................ 9
1.4.2 INTANGIBLE BENEFITS .......................................................................................... 10
1.5 Need of such system ............................................................................................................... 10
1.6 TARGET USERS ................................................................................................................ 10
1.7 Report Layout ......................................................................................................................... 11
CHAPTER 2: PROJECT MANAGEMENT ................................................................................ 12
2.1 TIME MANAGEMENT ..................................................................................................... 12
2.2 PERT CHART..................................................................................................................... 16
2.3 TIMELINE .......................................................................................................................... 16
2.4 PROJECT RISK MANAGEMENT ISSUE ........................................................................ 16
CHAPTER 3: TECHNICAL LITERATURE REVIEW .............................................................. 18
3.1 PURPOSE OF LITERATURE REVIEW ........................................................................... 18
3.2 NEED OF LITERATURE REVIEW .................................................................................. 18
3.3 FAULT DETECTION & CLASSIFICATION: PREVIOUS STUDIES & RESEARCH .. 19
3.4 FAULT DETECTION TECHNIQUE ................................................................................. 22
3.4.1 Impedance-Based Methods ........................................................................................... 23
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 2 of 108
3.4.2. Traveling Wave-Based Methods ................................................................................. 24
2.4.3 Detection and Location Using Magnetic Field Sensors ............................................... 24
2.5 FAULT CLASSIFICATION TECHNIQUE ....................................................................... 25
3.6 CONCLUSION OF LITERATURE REVIEW ................................................................... 26
Chapter 4: fault in transmission line ............................................................................................. 28
4.1 INTRODUCTION TO 3-PHASE FAULT ......................................................................... 28
4.2 REPRESENTATION OF DIFFERENT TYPE OF FAULT .............................................. 29
4.3 SYMMETRICAL COMPONENT & SIGNIFICANCE OF NEGATIVE, POSITIVE
SEQUENCE & ZERO SEQUENCE CURRENT ..................................................................... 31
4.4 USE OF SYMMETRICAL COMPONENT METHOD IN FAULT ANALYSIS ............. 33
Chapter 5: mathematical modeling ............................................................................................... 34
5.1 THE A OPERATOR ........................................................................................................... 34
5.2 THE J OPERATOR ............................................................................................................ 34
5.3 FAULT CALCULATION IN THREE PHASE SYSTEM ................................................. 34
5.3.1 Three- phase fault ......................................................................................................... 34
5.3.2 Single Phase to ground Fault ........................................................................................ 35
5.3.3 Line –to –Line fault ...................................................................................................... 35
5.3.4 Line- to-Line –ground fault .......................................................................................... 35
5.4 THE PER UNIT SYSTEM ................................................................................................. 36
CHAPTER: 6 MATLAB Simulation & Block Explanation ......................................................... 38
6.1 KEY FEATURES OF MATLAB ....................................................................................... 38
6.2 THE ROLE OF SIMULATION IN DESIGN ..................................................................... 38
6.3 MATLAB SIMULATION .................................................................................................. 39
6.4 DESCRIPTION OF BLOCK .............................................................................................. 39
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 3 of 108
6.5 MATLAB SIMULATION RESULT .................................................................................. 45
6.5.1Three phase to ground fault ........................................................................................... 45
6.5.2 Line –Line –ground fault .............................................................................................. 45
6.5.3 L-G Fault ...................................................................................................................... 46
6.6 CONCLUSION ................................................................................................................... 46
Chapter 7: system design .............................................................................................................. 47
7.1 SIMPLIFIED BLOCK DIAGRAM OF THE CIRCUIT & EXPLANATION ................... 47
7.2 EXPLANATION ................................................................................................................. 47
7.3 LIST OF COMPONENT .................................................................................................... 48
7.4 POWER SUPPLY SYSTEM DESIGN .............................................................................. 54
7.4.1 Ideal Power supply system design ................................................................................ 55
7.4.2 Prototype Power supply system design ........................................................................ 56
7.5 FAULT DETECTION & CLASSIFICATION SYSTEM .................................................. 56
Chapter 8: System Implementation ............................................................................................... 59
8.1 SOFTWARE TO BE USED FOR SOFTWARE SIMULATION ...................................... 59
8.2 PROTEUS SIMULATION ................................................................................................. 60
8.3 WAVEFORM OF LINEAR NON LINEAR LOAD & RELAY ........................................ 61
8.3.1Input Voltage of Linear & Non- Linear Load ............................................................... 61
8.3.2 Output voltage of Relay ................................................................................................ 62
8.4 COMPONENT ASSEMBLY .............................................................................................. 63
Chapter 9: Hardware testing ......................................................................................................... 69
CHAPTER: 10 Calcuation ............................................................................................................ 71
CHAPTER: 11 REFLECTIVE SUMMARY & OVERVIEW ..................................................... 73
Chapter 12: conclusion ................................................................................................................. 75
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 4 of 108
CHAPTER 13: COST ESTIMATION.......................................................................................... 76
13.1 COST ESTIMATION FOR THE DEVLOPER ................................................................ 76
13.2 Software required .................................................................................................................. 77
References ..................................................................................................................................... 78
Appendix A ................................................................................................................................... 82
Appendix B ................................................................................................................................... 84
Appendix D ................................................................................................................................... 94
Appendix c: Heath Safety and Ethical Assessment .................................................................... 104
Appendix D: User manual .......................................................................................................... 106
APPENDIX E : REVIEW & RESERCH PAPER ...................................................................... 108
TABLE OF FIGURE
Figure 1 : Developed hardware ....................................................................................................... 6
Figure 2: Transmission line ............................................................................................................ 6
Figure 3: Project Management Flow chart .................................................................................... 14
Figure 4: Pert chart........................................................................................................................ 16
Figure 5: flow chart of fault detection method ............................................................................. 22
Figure 6: Various method for detecting fault ................................................................................ 22
Figure 7: fault detection using magnetic field sensor ................................................................... 25
Figure 8: fault classification algorithm ......................................................................................... 26
Figure 9: L-L Fault representation ................................................................................................ 29
Figure 10: Sequence network of line to line fault ......................................................................... 29
Figure 11: L-G fault representation .............................................................................................. 30
Figure 12: Sequence network of line to ground fault ................................................................... 30
Figure 13: L-L-G fault representation........................................................................................... 30
Figure 14: Sequence Network of L-L-G fault ............................................................................... 31
Figure 15: unbalanced network ..................................................................................................... 32
Figure 16: Positive sequence representation ................................................................................. 32
Figure 17: Negative sequence representation ............................................................................... 33
Figure 18: Zero sequence representation ...................................................................................... 33
Figure 19: Flow chart of fault analysis using Matlab ................................................................... 39
Figure 20: Matlab simulation of developed interface ................................................................... 39
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 5 of 108
Figure 21: Simplified Synchronous Machine ............................................................................... 40
Figure 22: Three-Phase Series RLC Load .................................................................................... 40
Figure 23: three phase transformer two winding .......................................................................... 41
Figure 24: Three phase breaker..................................................................................................... 41
Figure 25: Distributed parameter line ........................................................................................... 42
Figure 26: Three phase V-I measurement ..................................................................................... 43
Figure 27: Three phase sequence analyzer .................................................................................. 43
Figure 28: scope ............................................................................................................................ 43
Figure 29: Three phase fault ......................................................................................................... 44
Figure 30: Three phase fault Matlab Waveform ........................................................................... 45
Figure 31: Line –Line –ground fault Matlab Waveform from scope ........................................... 45
Figure 32: L-G fault Matlab Waveform........................................................................................ 46
Figure 33: Block diagram of Circuit ............................................................................................. 47
Figure 34: Transformer connection to three phase source in star connection .............................. 49
Figure 35: Transformer connection to three phase source in wye connection ............................. 50
Figure 36: Op-Amp ....................................................................................................................... 50
Figure 37: Switch .......................................................................................................................... 51
Figure 38: Resistor ........................................................................................................................ 51
Figure 39: Capacitor ..................................................................................................................... 52
Figure 40: LED ............................................................................................................................. 52
Figure 41: Relay ............................................................................................................................ 52
Figure 42: Diode ........................................................................................................................... 53
Figure 43: Three Phase supply ...................................................................................................... 54
Figure 44: Working of GSM Modem ........................................................................................... 54
Figure 45: Ideal block diagram of power supply .......................................................................... 55
Figure 46: PROTOTYPE POWER SUPPLY SYSTEM DESIGN .............................................. 56
Figure 47: Transmission line ........................................................................................................ 56
Figure 48: Step by step component used ...................................................................................... 57
Figure 49: Proteus Simulation ...................................................................................................... 60
Figure 50: Wave Form of Linear Load ......................................................................................... 61
Figure 51: Waveform of Non Linear Load ................................................................................... 61
Figure 52:5.Output voltage of the 12v dc supply ......................................................................... 62
Figure 53:6.Output voltage of the 12v dc ..................................................................................... 62
Figure 54: Power supply from three phase source ........................................................................ 63
Figure 55: Input Supply ................................................................................................................ 63
Figure 56: Assembly for single phase ........................................................................................... 64
Figure 57: Assembly for six transformer ...................................................................................... 65
Figure 58: Connection of 555 timer & Lm358 ............................................................................. 66
Figure 59: Connection of Op-amp & transistor with 555 timer & relay ...................................... 67
Figure 60: Completed Assembled Circuit..................................................................................... 68
Figure 61: Final circuit.................................................................................................................. 68
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 6 of 108
CHAPTER 1: INTRODUCTION
G.S.M based three phase fault analysis with auto reset on transient fault or remain tripped
otherwise. Fault in power system is deviation of voltage or current from its nominal value and state
which happens more often leading to the failure of many equipment or may even be life threatening
to the operating personal, so to overcome this engineers have developed a system to analysis the
fault in power system. The fault analysis of power system is required in order to provide
information to selection of safety gear.
Figure 1 : Developed hardware
Faults usually occur in a power system due to either insulation failure, flashover, physical damage
or human error. These faults, may either be three phase in nature involving all three phases in a
symmetrical manner, or may be asymmetrical where usually only one or two phases may be
involved.
Figure 2: Transmission line
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 7 of 108
Fault analysis usually carried out in per-unit quantities (similar to percentage quantities) as they
give solutions which are somewhat consistent over different voltage and power ratings, and operate
on values of the order of unity. Relating to one single phase gives information related to two or
three phase as well so it is more obvious & sufficient to do calculation in one phase.
This project system will be designed to develop an automatic griping mechanism for three phase
supply system. The output will reset automatically when there is brief interruption (temporary
fault) or remain tripped otherwise in case of permeant fault.
To reach the aim following are the field required in which researcher is to work on:
1. Fault detection in three phase transmission line.
2. Fault classification in three phase transmission line.
3. Fault location in three phase transmission line.
4. Best fault calculation method to be implemented for calculation
5. Interfacing G.S.M technology with transmission line to alert the operating personal.
1.1 FUNCTIONALITY
A transmission line is an important component of the electrical power system & its protection is
necessary for ensuring system stability.
Fault detection
Fault classification
Fault location
SOS message
Fault detection performs an important role in minimizing damaging equipment due to short circuit
& fast detection of fault in any line condenses to quick isolation of faulty line from service and
hence protecting it from harmful effect of the fault.
Fault classification determines the type of fault that may occur on transmission line & hence
knowledge of fault type essentially be required on fault location procedure.
Fault location- when fault occur in transmission line, finding the fault location id an essential
problem in order to make necessary repair & restore power as soon as possible.in locating fault,
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 8 of 108
information produced from classification section could be used for accurate fault location &
evaluate the necessary repairing procedure to be carried out. Usual method of fault location are
under:
The measurement of time between sending & receiving an electric pulse reflected from
fault location.
The measurement of fundamental periodic component of voltage & current in terminal of
the line.
SOS message- In case if the operating personal is not near the operating system when the fault
occurred the proposed system will send SOS message to the individual with the help of GSM
modem installed in the system ensuring that operating act as soon as possible.
1.2 PROBLEM CONTEXT
Transmission line protection is an important issue in power system reason behind it is 85-87%
fault occur in transmission line.
Fault detection & classification is an important step to safeguard power system. an automated
analysis approach which can automatically characterized fault and subsequent relay operation is
required is fault detection play an important role in damaging equipment due to short circuit and
fast detection of fault In any line conduces to quick isolation of faulty line from service and hence
protecting it prom harmful effect of fault is required. So, the proposed system is required to act
fast to the fault condition.
1.3 CHALLENGES IN THE PROJECT
Many challenges were to be faced to develop the proposed system “G.S.M based three phase fault
analysis with auto reset on transient fault or remain tripped otherwise”. Among the major challenge
in the proposed system was to choose the method for calculation of fault current or which technique
to use for fault classification & location. Weather to stick with the traditional impendence based
method or to choose the technology which was developed the recent past like artificial neural
network technology or synchronized sampling or fuzzy based.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 9 of 108
Many challenges need to face for the development of this project by researcher as a student. The
major and the foremost challenge in building this system the conventional fault analysis tool with
the proposed system. A deep study of the technologies is required to overcome the drawbacks of
the existing system and prepare a system which will be better in every respect from the existing
system. To fulfil this need, several technologies need to be learned to address the fault prevention
system.
1.3.1 NEW TECHNOLOGY NEED TO BE LEARNT:
Developer needs to learn new technology for development of project which includes various fault
analysis method proposed in recent time such as synchronized sampling or K-NN based analysis.
The researcher has to understand various interfacing concepts of components relay as it play the
most significant role. Interfacing requires proper understanding of architecture of controller and
components.
GSM technology has to be interfaced with the fault analysis tool giving the proposed system an
upper hand then all other system. So researcher has to go through the concept of how GSM
technology works and how it can be interfaced in the proposed system
1.4 TANGIBLE BENEFIT & INTANGIBLE BENEFITS
Below mentioned are tangible and intangible benefit to support the rational:
1.4.1 TANGIABLE BENEFIT
i. Increasing the power system safety making it more efficient.
ii. The proposed system will speed up the development and features related to three phase
fault analysis tool.
iii. SOS message of the proposed system alarms the operating personal by delivering message
telling them to operate in the faulty area.
iv. Proposed system is reliable and cost effective GSM based fault analysis tool.
v. Proposed system act’s automatically in case of permanent fault the system will isolate the
faulty phase from rest of phase making sure no equipment gets damaged.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 10 of 108
1.4.2 INTANGIBLE BENEFITS
i. The proposed system will help to reduce the injury or death caused due to line to ground
fault in transmission line especially in short distance transmission line in urban area
making the system tripped.
ii. The proposed system will automatically respond to transient fault making the power
system to run smoothly.
iii. The system trips or isolates the line permanently till the permanent fault is being restored.
iv. The proposed system will provide more safety as it will avoid because of its auto tripping
mechanism.
1.5 Need of such system
83% of fault in power system is in transmission line caused by system problem (i.e. failure of any
electrical equipment or human error) or external hindrance such as lightning to overcome such
fault is not within our reach but the fault which occur in system due to system failure can be
controlled. Many type of to control such problem a proper automated device is required which can
sense the fault and perform the subsequent relay operation. Making such device can ensure the
reliability of power system
1.6 TARGET USERS
This system is designed to save life when there is fault in transmission line such as earth to ground
or double line to line fault. Since this fault are in high voltage transmission which is at least 60
KM long short transmission line carrying heavy voltage can take life whosoever come in
contact(person, animal ,etc.) will be life threatening so it is necessary to isolate the phase for less
damage.
This system is specially designed for
Power sector
i. Power generation plant (power plant)
ii. Transmission substation
iii. Distribution substation
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 11 of 108
1.7 REPORT LAYOUT
The report comprises of a survey on three phase fault analysis tool. A detailed discussion on the
application of fault detection system is included. Chapter 3 contains the detailed discussion &
literature review.
Chapter 4 includes introduction to various kind of fault in power system
Chapter 5. Contain mathematical modeling of power system to compute driftnet type of fault in
power system
Chapter 6 includes Matlab simulation & result
After Chapter 6 further chapters 7, 8 and 9 includes System design, implementation, testing and
evaluation along with the output results are also included in the report.
The testing and evaluation results are discussed in the end and then final conclusion is reached.
References, and appendices are also attached at the end of the document.
This project is one year work and an estimation of approximately 274 days was decided to
complete it. Different time slots are allotted for different chapter of the report. Refer to pert chart
and Gantt chart given in appendix-E for the detailed time management plan of the project.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 12 of 108
CHAPTER 2: PROJECT MANAGEMENT
The main objective of this project is to build an intelligent device for power system transmission
line network which can classify detect and respond to the fault and respond accordingly depending
weather it is transient fault or permanent fault and even send SOS message to the operating
personal that some problem is there. Condition & time both actually demands this kind of system
because power demand is increasing in urban area so continues power flow is required to meet the
increasing demand and a condition of fault is not at all useful to that so the proposed system dose
a bit to meet the demand in transmission line fault detection in better way.
A perfect fault analysis tool should be able to perform the following task
1. Fault detection in three phase transmission line.
2. Fault classification in three phase transmission line.
3. Fault location in three phase transmission line.
Interfacing two technology
4. Interfacing G.S.M technology with transmission line to alert the operating personal
2.1 TIME MANAGEMENT
To achieve project objective time management is to be taken care of seriously from the very
beginning. The first step is to project in serval part or task that has to be performed. This process
should be completed before the implementation of the project. For the proposed project, it is
necessary to create a time plan be setting the objective and then subdividing them into manageable
sequence with a deadline attach to it.
The first step for the researcher is to identify how to perform the specific schedule activity to be
performed & time period needed to complete those activity. The researcher must be aware of all
the task need to be carried out to achieve the objective. The amount of time each task will take to
complete should also be estimated clearly. The next step is to decide which work is most important
and set the priorities accordingly.
As management analysis is concern Gantt Chart & PERT chart are useful tool for any project. The
researcher is using two time management tool namely
A. Gantt chart
B. Pert chart
C. Timeline
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 13 of 108
Gantt chart is a very useful tool while the project is going on to check whether the project is meting
it’s time limit which are the area which is to focused more on in order to complete project in
allotted time and necessary steps to achieve that.
The overall project is broken down in serval part with possible duration for every task.
The breakdown list of the plan for the project is are as follows:
1. Project commencement
Duration:
Task performed:
i. Idea generation for the approval to topic for the final year project.
ii. Preparation of draft proposal form.
iii. Submission of draft proposal form.
iv. Investigation related to the project to make a healthy project proposal form.
v. Finalization of project proposal form.
In the allotted period of time, the project idea was developed by the researcher after going
through various journal related to fault detection & classification which will provide the
pillar for the complication of the project. To make topic more justifiable various library
resource, book, E-book were used by the researcher.
2. Project planning
Duration:
Task performed
i. Feasibility study
ii. Planning of the research method to be adopted.
In this period of time, project planning was done by the researcher & the feasibility study
about the topic and the methodology to be used was performed. Planning for primary and
secondary research method which will be adopted was done in this period of time again for
this purpose various book, E-book, library resource was used by the researcher.
3. Requirement analysis & research
Duration:
Task performed
i. Preparation of questionnaire
ii. Question to be asked in interview.
iii. Literature review.
4. Project management
Duration: 7 days
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 14 of 108
Task performed:
i. Cost estimation
ii. Time estimation
iii. Health & risk management.
This will take a week and the work done in this week are time estimation, cost estimation.
Figure 3: Project Management Flow chart
5. Project methodology
Duration: 7 days
Task performed:
i. Overview of block diagram
ii. Component analysis.
This week take a week to make block diagram and analysis component to be used in the project.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 15 of 108
6. Analysis
Duration: 6 days
Task performed
iii. Analysis of questionnaire conducted
iv. Analysis of interview conducted
This include analysis of primary research both interview and questionnaire
7. Midpoint submission
Duration: 9 days
Task performed
i. Documentation
More than a week was taken to complete mid-point submission
8. Implementation
Duration: 99 days
Task performed:
Software implementation
i. Code generation
ii. Simulation
Hardware implementation
i. Layout design
ii. Hardware integration
This section include hardware and software implementation.
9. Testing & evolution
Duration: 30 days
Task performed
i. Hardware testing
ii. Performance validation.
This section should be performed as it is the final testing.
10. Project editing
Duration: 19days
Task performed
i. Documentation
ii. Submission of final year project
This stage include final documentation for the final year report.
Gantt chart is included in appendix.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 16 of 108
2.2 PERT CHART
For the proposed project researcher has used pert chart to deal with time management for the
project.
ECT-The Earliest Completion Time (ECT) i.e. the minimum amount of time needed to complete
all the activities that precedes every event is mention in the upper part of the circle and the
Latest Completion Time (LCT) which is the latest time needed at which the event can occur
without delaying the overall project is mention in the
The critical path is the path of the tasks which cannot be delayed and project will not move forward
without completing these tasks. In the pert chart drawn below, black lined tasks which are from
task 1, 4, 5, 7, 8, 9, 10. Task 8 is dependent upon task 9 and 3 and task 7 depends upon 6. It means
9 cannot be starting before task 8 is not completed.
Figure 4: Pert chart
2.3 TIMELINE
For the proposed project researcher has used a timeline to evaluate time properly and distribute
the work load matrix. Time line has been included in the appendix section at the end.
2.4 PROJECT RISK MANAGEMENT ISSUE
No proper planning
Proper planning is one of the key aspect for any project to succeed, if it is not done so it
might lead to risk of not meeting the project deadline or if the cost estimation is not done
properly it might lead to out project. So proper planning is one of the aspect where
researcher should focus primarily.
Almost all type of component available on simulation software
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 17 of 108
It is not possible to test directly on hardware so researcher use a simulation tool to achieve
that without wasting money. But in many cases the component to be used in circuit is not
available in simulation software or simulation software provides many type of component.
So this can cause delay in project. If the researcher tries to design the circuit directly in
hardware there are certain chances that circuit might not work
lack of component in market
Sometime the component become unavailable in the as these component are used
frequently. This situation can be very risky resulting in delay of project falling to meet the
deadline. It is very much obvious that hardware implementation take much time
(maximum) out of all the work distribution of the project.
Relay or not working
Relay is the mastermind of the project as it carries the most important role in the device to
detect and classify fault. So researcher must take a note on this. Taking this is mind
researcher should select the proper relay meeting system requirement and should be first
then applied in system.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 18 of 108
CHAPTER 3: TECHNICAL LITERATURE REVIEW
A good literature review will help you justify researcher’s research and develop your thesis
position. The literature review deals with critical analysis of any published piece of knowledge
through study of the literature and comparison of those prior research findings to draw a conclusion
which supports the proposed research project.
Literature review has to be the essential part of any project so same apply for the project titled
‘G.S.M based three phase fault analysis with auto reset on transient fault or remain tripped
otherwise’ as this review provides a complete overview of the technical perspective of project that
is to be developed. With increase number of research journal’s power system transmission line
fault it clearly shows the increase in interest related to this topic as fault is one major thing which
is to be dealt with.
The literature review also gives an outlook of the technology to be used for the implementation of
the project.
3.1 PURPOSE OF LITERATURE REVIEW
Literature review helps in understanding the problem faced by the researcher to understand various
problem related to topic Review helps the researcher to frame the problem related to topic.
Some of the important purpose of literature review helped the researcher to get the final result are:
1. Literature review did provide a context for the research related to G.S.M based three phase
fault analysis with auto reset on transient fault or remain tripped otherwise
2. It helped establish a theoretical framework for related topic.
3. Help’s to define key terms, definitions and terminology
4. Helps to justify the research topic.
5. Enable the researcher to learn from previous theory related to the topic.
6. Helps to develop much needed fault analysis system for the power system.
3.2 NEED OF LITERATURE REVIEW
The proposed system is being developed to analysis various fault occurring in power system with
interfacing another technology GSM which will send the SOS message to operating personal. So
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 19 of 108
the literature review of this project will clearly focus on various approach related to fault problem
and there limitation.
Some of them are mentioned below:
1. Various fault occurring in transmission line
2. Method used to detect fault
3. Method used to classify fault
4. Use of fault limiting device
5. Dose any running system has interfaced fault with GSM technology.
3.3 FAULT DETECTION & CLASSIFICATION: PREVIOUS STUDIES &
RESEARCH
1. Transmission line fault detection & classification this paper presents a technique to detect
and classify shunt fault which will be achieved with the help of programming tool called
“PSCADA” the method through which this is achieved is by discreet wavelet transform.
(Manohar Singh 2011)
DWT wavelet transform is applied for decomposition of transient fault because of its ability
to extract signal from transient signal simultaneously both from time & frequency domain.
After extracting the useful features from measured signal a decision of fault or no fault is
carried out using SVM classifier. (B.K. Panigiri, 2011)
2. Analysis of the unbalanced fault in three phase transmission line using Flux coupling type
SFCL” using symmetrical co-ordinate method in this paper researcher discusses the sizes
of fault currents limited by flux coupling type SFCL using the symmetrical coordinate
method in the case of unbalanced faults such as a single and double line-to ground faults
in the power system. An unbalanced current of three phase was indicated by three balanced
symmetrical components using the symmetrical coordinate method comparing the
component sizes.
Controls unbalanced fault by changing primary secondary coil turn, it can even reduce the
current value of symmetrical component. (Byung-Ik-jung, Hyo-Sang-choi, Doung- chul
chung 2012)
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 20 of 108
3. Transmission line fault analysis using synchronized sampling in this research paper the
author discusses an automated analysis approach which can automatically characterized
fault and subsequently relay operation is performed this is achieved by changing the
instantaneous power on all three phase connected at two end of transmission line using
synchronized voltage & currnet sample. ( Mladen Kezunovic, 2014)
4. Fault analysis is transmission line using K-nearest neighbor algorithm in this paper
researcher discusses that that fault detection and classification is done in time domain using
K-nearest neighbor algorithm using PSCADA software this is achieved by for fault
detection a k-NN module is designed. Input to the k-NN module is fundamental component
of currents of three phases. Half cycle of post fault samples are given as input to train the
network. Output of the fault detection module is ‘0’ for no fault and ‘1’ for fault.( Anamika
Yadav, 2014)
5. Fault classification & location of power transmission line using artificial neural network in
this paper researcher discusses fault location strategy based on ANN and this method is not
dependent on fault inception angle and the process of ANN is achieved by
MATLAB/Neural network tool box. ( M. Tarafdar, K. Razi, 2007)
6. Improved fault location algorithm for multiple fault location in compressed transmission
line in this paper researcher proposes a method which is combined discrete WT & A-NN
based fault location algorithm in this method unlike other fault location scheme this method
does not require fault classification i.e. fault type and faulty phase information. The main
significant contribution is it not only pin point the location of shunt fault occurring at
single location but also find the location of multi-location and transforming fault that to
using single terminal data (Anamika Yadav, 2015)
7. Advance distance protection scheme for long transmission line in electrical power system
using multiple classifier ANFIS network in this paper researcher discusses the advance
application of artificial intelligence approach which is achieved through ANFIS classifier.
This ANFIS classifier has
8. Improved fault location algorithm for multi-location fault , transforming fault & shunt fault
in Thyristor controlled series capacitor compensated transmission line” discusses
“combining two method discreet WT & ANN fault method reduces the fault classification(
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 21 of 108
fault type & faulty phase(s) information for fault location estimation most important
significance is that it not only locate shunt fault but also find location of multi-location
fault & transforming fault that too using single terminal data.” (Yadav,
Swerpadama,2015)”
9. Recent techniques used in transmission line protection: a review “discusses “The ANN,
fuzzy logic, genetic algorithm, SVM and wavelet based techniques have been quite
successful but are not adequate for the present time varying network configurations, power
system operating conditions and events. Therefore, it seems that there is a significant scope
of research in AI techniques which can simplify the complex nonlinear systems, realize the
cost effective hardware with proper modification in the learning methodology and
preprocessing of input data and which are computationally much simpler. Also
development of reliable software and communication system will pave the way”
(Singh,Tripathi,Vekataramana,2013)”
10. A Combined Wavelet-ANN based fault classifier has been investigated for electrical
distribution systems “discusses some fault condition wore taken to identify by this the
proposed approach. It is shown that the technique correctly recognizes and discriminates
the fault type and faulted phases with a high degree of accuracy. (0. Dag & Ucak, 2003) “
11. Multiple failure analysis for complex electrical power system in this paper researcher
combines the two method to form a new algorithm they are
Virtual node method
The compensation method
And its benefits are when compared to traditional algorithm new algorithm has a complete
fault calculation system but has lower reliability than tradition method. The proposed
algorithm is to read the network model and fault condition after this is done analyze the
status quo of the fault to choose an appropriate algorithm once this is done get the
admittance matrix for n port three sequence impedance matrix with this done n port matrix
can be formed with the help of formula and later at later stage impedance matrix for virtual
note can be can be calculated. (Xiao hen Liu, 2012)
Below is the flow chart of the proposed method
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 22 of 108
Figure 5: flow chart of fault detection method
3.4 FAULT DETECTION TECHNIQUE
Fault detection technique is one of the main objective of power system to run continuously. Quick
fault detection can help to protect equipment by allowing the disconnection of faulted lines before
any major damage is done. Accurate fault location can help utility personnel remove persistent
faults and locate areas where faults regularly occur. Various fault detection and location schemes
have been developed in the past, a variety of algorithms continue to be developed to perform this
task more accurately and more effectively.
Figure 6: Various method for detecting fault
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 23 of 108
Most analysis methods depends on the values of either current or voltage phasor measured by
means of current or voltage transformers at substations or switching stations. To collect this
information, at least three transformers are typically required at each end of the sub transmission
or transmission line. These transformers are expensive, especially when the system involves high
voltage lines. Some algorithms mainly fault impedance-based algorithms require both current and
voltage information.
Some fault detection technique:
Sr.
No.
Method Type Function requirement
1. Impedance method One terminal
Two terminal
Impedance of transmission is used in this
method
2. Travelling wave One terminal
Two terminal
One-terminal depends upon timing between
reflection of voltage/current
while
Two terminal depends upon time delay at the
end of transmission line
3. Magnetic field In this two sensing coils at each end of the
transmission line. One detect the vertical
magnetic field intensity and the other detects
horizontal field intensity
Table 3.1: some fault detection technique
3.4.1 IMPEDANCE-BASED METHODS
No table of figures entries found.Traditional impedance-based fault location methods use the
voltages and currents at one or both ends of a transmission line to determine where a fault has
occurred. The impedance of the transmission line per unit length is usually required in these
calculations. One of the major problems with basic one-terminal impedance-based fault location
methods – those that only use measurements from one end of the transmission line is that the fault
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 24 of 108
impedance must be near-zero for the result to be accurate, since the fault impedance affects the
impedance seen at the end of the transmission line. This problem has been mitigated in several
different ways. One of the best-known of these ways is the Takagi method. This changes the
calculation to include the difference between the current measured before the fault and the current
measured after the fault (which is the fault current). This eliminates the fault impedance from the
analysis, thus removing this significant source of error. However, the angle of the fault current and
the angle of the current during the fault at the relay terminals are assumed to be equal; if this is not
true, there may be errors in the fault location.
Two-terminal impedance-based fault location methods, or those that use measurements from both
ends of the transmission line, can also significantly improve the accuracy of the fault location
estimate. Two-terminal methods require communication between the locators at both ends of the
transmission line to transfer information about the currents, voltages, and source impedances in
order to perform the fault location.
3.4.2. TRAVELING WAVE-BASED METHODS
Traveling wave-based fault location methods, like impedance-based methods, can be divided into
one-terminal and two-terminal methods. With traveling wave analysis, however, the entire method
of location rather than simply the equations change between the one- and two-terminal methods.
One-terminal methods rely on the timing between reflections of voltage or current at impedance
discontinuities – in this case, the fault – to find the distance between the sensor and the fault while
two-terminal methods work based on the time delay between arrivals of information at the ends of
the transmission line.
3.4.3 DETECTION AND LOCATION USING MAGNETIC FIELD SENSORS
Due to the simple relationship between current and magnetic field intensity, it is understandable
that magnetic field sensors have previously been used in fault detection and location schemes.
These schemes often use magnetic field sensors in place of current transformers since magnetic
field sensors can be installed independently from a substation or switching station with a minimum
amount of additional equipment
One possible use of this relationship is simply replacing each current transformer with a Hall Effect
transducer. This transducer would typically need to be within the electrical arcing distance of the
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 25 of 108
conductors to produce enough voltage for analysis and would thus require insulation. To remove
this need for insulation, the transducer can be located between two tapered pieces of ferromagnetic
material in order to concentrate the magnetic field into the transducer; as a result, the transducer
does not need to be located within the arcing distance of the conductors. The measured magnetic
field result can then be used similarly to a current measurement for fault detection and location.
Figure 7: fault detection using magnetic field sensor
3.5 FAULT CLASSIFICATION TECHNIQUE
Fault classification plays an important role in any fault analysis tool. For a reliable protection of
transmission line fault classification has to be taken seriously. There are different issue of fault
classification. Fault type like line-to-ground or line to line fault is one aspect & other is fault
direction estimation. Importantly the classification of fault area in a series compensated line is
another challenging task. Different neural network, fuzzy based, synchronized sampling are
generally used to classify fault.
Fault occur in different places of transmission line. All data are collected from sending end of the
system.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 26 of 108
Below shown figure is the simple flow chart use for classification technique of fault in transmission
line.
Figure 8: fault classification algorithm
3.6 CONCLUSION OF LITERATURE REVIEW
As concluded from the above researches done by various researchers, fault detection & fault
classification is the need of the hour. The similar projects discussed in the review, one fulfils the
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 27 of 108
feature of fault detection and other project is meant for fault classification purpose. Thus the
researcher concluded that automation power system is the need to of the hour by reviewing the
'fault cases round the world. The fault detection and classification both the factors seem to be very
important in power system. The research proves that 65% of fault in power system occur in
transmission line thus proving the researcher’s hypothesis true. So the researcher has decided to a
fault detection tool which can detect and classify fault with emphasis on cost efficiency and
affordability in the proposed project with some further enhancements if possible.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 28 of 108
CHAPTER 4: FAULT IN TRANSMISSION LINE
83% fault in power system is in transmission line so in order to safeguard power system & make
it reliable it is essential to analysis the type of fault & resolve the problem quickly & continue the
power supply. To safeguard power system it is essential to have good knowledge of fault in
transmission line.
4.1 INTRODUCTION TO 3-PHASE FAULT
Transmission line Fault can be of two type
1. Shunt fault
2. Series fault
Shunt Fault are of 4 type namely
I. Line to Line Fault. (L-L)
II. Line to Ground (L-G)
III. Line to line to Ground (L-L-G)
IV. 3-Phase
Series or Open Conductor Fault are of two type namely
I. 1 conductor open
II. 2 conductor open
Note
L-L, L-G,L-L-G are unsymmetrical type of fault & 3-Phase fault,1 Conductor open, 2 conductor
open are symmetrical type of fault
Symmetrical fault
In this type of fault all fault all three phase are simultaneously short circuited hence the network
remain balanced.
Unsymmetrical fault
The fault in power system which gives rise to unsymmetrical current (i.e. unequal fault current in
line with unequal phasor displacement) is known as Unsymmetrical fault.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 29 of 108
4.2 REPRESENTATION OF DIFFERENT TYPE OF FAULT
Line to line fault
In this type of fault two phases are short circuited
Boundary condition: Ifa =0
Figure 9: L-L Fault representation
The boundary condition are Ia0=0 , Ia1+Ia2=0 & Va1=Va2 indicates a sequence network where the
positive & negative sequence are in parallel & the zero sequence is open circuited as shown in
figure below
Figure 10: Sequence network of line to line fault
Line to Ground fault
In this type of fault 1 phase gets in contact with the ground so potential then becomes infinite
Boundary condition: Ifb=Ifc=0
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 30 of 108
Below figure shows sequenc netork which show that the three netwok must be connectd in series
Figure 12: Sequence network of line to ground fault
Line to line to ground
It is assumed that the fault has occurred at node k of the network. In this the phase’s b and c got
shorted through the impedance Zf to the ground.
Boundary condition: 3Ifa=Ifb+If
Figure 13: L-L-G fault representation
Under the fault condition Ia =Vb=Vc=0
Figure 11: L-G fault representation
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 31 of 108
Ia0+Ia1+Ia2+=0
These condition are taken together& can correspond to all three sequence network connected in
parallel
Figure 14: Sequence Network of L-L-G fault
3-Phase fault
Figure 4: Phase fault representation
4.3 SYMMETRICAL COMPONENT & SIGNIFICANCE OF NEGATIVE,
POSITIVE SEQUENCE & ZERO SEQUENCE CURRENT
Power systems are always analyzed using per-phase representation because of its simplicity.
Balanced three-phase power systems are solved by changing all delta connections to equivalent
wye connections and solving one phase at a time. The remaining two phases differ from the first
by 120°. To analyze an unbalanced system, the system is transformed into its symmetrical
components for per-phase analysis. Charles Legeyt Fortescue developed a theory which suggests
that an unbalanced system can be well defined using the symmetrical components. These three
symmetrical components are positive sequence, negative sequence and zero sequence. They are
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 32 of 108
represented by “+”, “-”, and “0” or “1”, “2”, and “0” for positive, negative and zero sequence
respectively.
Figure 15: unbalanced network
A system of three unbalanced phasors can be resolved in the following three symmetrical
components.
1. Positive sequence component: (VA+,VB
+,VC+)
Three phasors
Equal in magnitude
Displaced by 120o in phase
Having the same sequence as the original phasors (abc)
Figure 16: Positive sequence representation
2. Negative sequence component: (VA-,VB_,VC
-)
Three phasors
Equal in magnitude
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 33 of 108
Displaced by 120o in phase
Having the opposite sequence as the original phasors (acb)
3. Zero sequence component: (VA0,VB
0,VC0)
Equal in magnitude
Three phasors
Having the same phase shift ( in phase)
Figure 18: Zero sequence representation
4.4 USE OF SYMMETRICAL COMPONENT METHOD IN FAULT
ANALYSIS
Faulted power systems do not have three phase symmetry, so it cannot be solved by per phase
analysis. To find fault currents and fault voltages, it is first transformed into their symmetrical
components. This can be done by replacing three phase fault current by the sum of a three phase
zero sequence source, a three phase positive sequence source and a three phase negative sequence
source. Each circuit is solved by per phase analysis called a sequence networks.
Figure 17: Negative
sequence representation
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 34 of 108
CHAPTER 5: MATHEMATICAL MODELING
5.1 THE A OPERATOR
As the symmetrical component theory involves the concept of 120 displacement in the positive
sequence set & negative sequence set, therefore, it is desirable to involve some operator which
could cause 120 rotation. For the purpose, operator ‘a’ (symbols h or are sometime used
instead of ‘a’) is used. It defines as under:
The operator ‘a’ is one, which when multiplied to a vector rotates the vector through antilock
direction at 120.
Property of operator A
1+a2+a2=0
a –a2=j3
5.2 THE J OPERATOR
In polar form, j =1∠90 . Multiplying by j has the effect of rotating a phasor 90 without
affecting the magnitude
Property Of operator J
1 = 0.1 + j 0.0
j =1∠90
j2=1180 = -1
j3=1270=-j
-j=1-90
J=1
5.3 FAULT CALCULATION IN THREE PHASE SYSTEM
To calculate symmetrical & unsymmetrical fault firstly we need to calculate positive sequence
component. The fault current of sequence have been determined by using the reactance (Z1, Z2,
Z0) have been calculated. The current & voltage value of other phase could be calculated via
these component.
5.3.1 THREE- PHASE FAULT
Ia1=𝐸𝑎
𝑧𝑖
Ia0=0
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 35 of 108
Ia2=0
Where Ea & Zi are phase voltage & positive sequence reactance.
5.3.2 SINGLE PHASE TO GROUND FAULT
Ia1=𝐸𝑎
𝑍0+𝑍1+𝑍2
Ia0= Ia2= Ia1
Where Z0 & Z2 are zero & negative sequence reactance.
5.3.3 LINE –TO –LINE FAULT
Ia1=𝐸𝑎
𝑍1+𝑍2
Ia0= -Ia1
Ia2=0
Where Z0 & Z2 are zero & negative sequence reactance.
5.3.4 LINE- TO-LINE –GROUND FAULT
Ia1=𝐸𝑎
𝑍1+𝑧0𝑧2
𝑧0+𝑧2
Ia0= -- 𝑍0
𝑍0+𝑍2 Ia1
Ia2= − 𝑍0
𝑍0 +𝑍2Ia1
The current have been calculated using positive negative & zero component of phase –a for each
fault using equation
(
𝑉𝑎0
(𝑉𝑎1)𝑉𝑎2
) = (0
𝐸𝑎0
) −𝑍0 0 00 𝑍1
0 0 𝑍2
(𝐼𝑎0
𝐼𝑎1
𝐼𝑎2
)
Additionally, the symmetrical component of phase a has calculated by using
X1(T) =((1
𝑋"𝑑−
1
𝑋𝑑) 𝑒 + (
1
𝑋′𝑑−
1
𝑋𝑑) 𝑒 + (
1
𝑋"𝑑))
Other phase voltage has been determined via the voltage of phase a. the positive sequence
reactance must be calculated using for time variation of signal
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 36 of 108
Where Xd” Xd’, Xd direct axis sub transient, transient, & synchronous reactance Td”, Td’ direct
axis fault sub transient & transient time constant. Ea, E: complex RMS value of phase –a voltage
of synchronous machine terminal before fault occurrence.
Below table could be used for calculating & drawing the fault current & voltage. The signal
must be drawn by taking into account the real part of current equation. After finding the
symmetrical component of a phase current, the value of current & voltage can be calculated.
Table 2: Symmetrical – component circuit constant & fault current
Ta=𝐿0
𝑅
X2=ⱷL2
X0= ⱷL0
Ea=2Ec
Where Ta is armature time constant
L(0)= initial inductance at t,0,Ra & R0 are armature resistance & zero phase sequence
resistance.L1(t), L2 & L0 are positive negative & zero phase sequence respectively .
5.4 THE PER UNIT SYSTEM
In many engineering situations it is useful to scale, or normalize, dimensioned quantities. This is
commonly done in power system analysis. The standard method used is referred to as the per-
unit system. Historically, this was done to simplify numerical calculations that were made by
hand. Although this advantage is eliminated by the calculator, other advantages remain.
Device parameters tend to fall into a relatively narrow range, making erroneous values
conspicuous.
Using this method all quantities are expressed as ratios of some base value or values.
The per-unit equivalent impedance of any transformer is the same when referred to either
the primary or the secondary side.
The per-unit impedance of a transformer in a three-phase system is the same regardless of
the type of winding connections (wye-delta, delta-wye, wye-wye, or delta-delta)
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 37 of 108
The per-unit method is independent of voltage changes and phase shifts through
transformers where the base voltages in the winding are proportional to the number of turns
in the windings.
Manufactures usually specify the impedance of equipment in per-unit or percent on the
base of its nameplate rating of power (usually kVA) and voltage (V or kV)
The per-unit system is simply a scaling method. The basic per-unit scaling equation is
Per –Unit = Actual_Vaule
𝐵𝑎𝑠𝑒_𝑣𝑎𝑙𝑢𝑒
The base value always has the same units as the actual value, forcing the per-unit value to be
dimensionless. The base value is always a real number, whereas the actual value may be complex.
The subscript pu will indicate a per-unit value. The subscript base will indicate a base value, and
no subscript will indicate an actual value such as Amperes, Ohms, or Volts. Per-unit quantities are
similar to percent quantities. The ratio in percent is 100 times the ratio in per-unit. For example, a
voltage of 70kV on a base of 100kV would be 70% of the base voltage. This is equal to 100 times
the per unit value of 0.7 derived above.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 38 of 108
CHAPTER: 6 MATLAB SIMULATION & BLOCK
EXPLANATION
The name MATLAB stands for Matrix Laboratory. MATLAB was written originally to provide
easy access to matrix software developed by the (Linear system package & Eigen system package
projects).
MATLAB is a high performance language for technical computing.it integrates computation,
visualization & programing environment where problem & solution are expressed in familiar
mathematical notation. MATLAB has many advantage to conventional computer language
example (C, FORTRAN) for solving technical problem.
6.1 KEY FEATURES OF MATLAB
High level language for technical computing.
Development environment for managing code, files & data.
Interactive tools for iterative exploration, design & problem solving.
2D & 3D graphic function for visualization data.
Tools for building custom graphical & user interface.
6.2 THE ROLE OF SIMULATION IN DESIGN
Electrical power system are combination of electrical circuit & electromechanical device like
motor & generator. Engineers working in the discipline are constantly improving
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 39 of 108
Figure 19: Flow chart of fault analysis using Matlab
6.3 MATLAB SIMULATION
Figure 20: Matlab simulation of developed interface
6.4 DESCRIPTION OF BLOCK
Simplified Synchronous Machine
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 40 of 108
Figure 21: Simplified Synchronous Machine
The Simplified Synchronous Machine block models both the electrical and mechanical
characteristics of a simple synchronous machine.
The electrical system for each phase consists of a voltage source in series with an RL impedance,
which implements the internal impedance of the machine. The value of R can be zero but the value
of L must be positive.
Three-Phase Series RLC Load
Implementing a three-phase series RLC load with selectable connection.
Figure 22: Three-Phase Series RLC Load
The Three-Phase Series RLC Load block implements a three-phase balanced load as a series
combination of RLC elements. At the specified frequency, the load exhibits a constant impedance.
The active and reactive powers absorbed by the load are proportional to the square of the applied
voltage.
Three-Phase transformer (Two-Winding)
Implementing a Three-Phase transformer with configurable winding connection.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 41 of 108
Figure 23: three phase transformer two winding
Three-Phase transformer (Two-Winding) block implements a three phase transformer using three
single phase transformer. We can simulate the saturable core or not simplify by setting the
appropriate check box in the parameter of the block.
Three Phase Breaker
Implementing a three-phase circuit breaker opening at the current zero crossing.
Three-Phase Breaker block implements a three-phase circuit breaker where the opening and
closing times can be controlled either from an external Simulink signal (external control mode),
or from an internal control timer (internal control mode). The Three-Phase Breaker block uses
three Breaker blocks connected between the inputs and the outputs of the block
Figure 24: Three phase breaker
This block can be used in series with the three-phase element that one wants to switch. If the Three-
Phase Breaker block is set in external control mode, a control input appears in the block icon. The
control signal connected to this input must be either 0or 1, 0 to open the breakers, 1 to close them.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 42 of 108
If the Three-Phase Breaker block is set in internal control mode, the switching times are specified
in the dialog box of the block. The three individual breakers are controlled with the same signal.
Distributed Parameter Line
Implementing an N-phase distributed parameter transmission line model with lumped losses
Figure 25: Distributed parameter line
The Distributed Parameter Line block implements an N-phase distributed parameter line model
with lumped losses. The model is based on the Bergeron's traveling wave method used by the
Electromagnetic Transient Program (EMTP). In this model, the loss less distributed LC line is
characterized by two values (for a single-phase line): the surge impedance
Zc= (L/C) and the phase velocity v= 1/√ (LC)
. The model uses the fact that the quantity e+Zi (where e is line voltage and i is line current)
entering one end of the line must arrive unchanged at the other end after a transport delay of τ=
d/v, where dis the line length.
Three-Phase V-I Measurement
Measures three-phase currents and voltages in a circuit
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 43 of 108
Figure 26: Three phase V-I measurement
The Three-Phase V-I Measurement block is used to measure three-phase voltages and currents in
a circuit. When connected in series with three-phase elements, it returns the three phase-to-ground
or phase-to- Phase voltage & the three line current. The block can output the voltage & current in
per unit value or in volt & ampere.
Three-Phase sequence analyzer
Measures the positive negative & zero sequence component of the three phase signal
Figure 27: Three phase sequence analyzer
The three phase sequence analyzer Output the magnitude and phase of the positive (denoted by
index 1), negative (index 2) & zero (index zero) sequence component of a set of three balanced or
unbalanced signals. The signal can contain harmonics or not.
Scope
Displays signal generated during simulation
Figure 28: scope
The scope block displays its input with respect to simulation time. The scope block can have
multiple axes. All axes have one common time range with independent y axis. If the scope signal
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 44 of 108
is discreet the scope produces a stair- step-plot. The scope prove toolbar button which enables to
zoom on its display data display all the data input to the Scope, preserve axis settings from one
simulation to the next, limit data displayed, and save data to the workspace.
Three-Phase Fault
Implementing a programmable phase-to-phase and phase-to-ground fault breaker system
Figure 29: Three phase fault
The Three-Phase Fault block implements a three-phase circuit breaker where the opening and
closing times can be controlled either from an external Simulink signal (external control mode),
or from an internal control timer (internal control mode). The Three-Phase Fault block uses three
Breaker blocks that can be individually switched on and off to program phase-to-phase faults,
phase-to-ground faults, or a combination of phase-to-phase and ground faults.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 45 of 108
6.5 MATLAB SIMULATION RESULT
Following are the graph obtained from scope of different type of fault
6.5.1THREE PHASE TO GROUND FAULT
Figure 30: Three phase fault Matlab Waveform
6.5.2 LINE –LINE –GROUND FAULT
Figure 31: Line –Line –ground fault Matlab Waveform from scope
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 46 of 108
6.5.3 L-G FAULT
Figure 32: L-G fault Matlab Waveform
6.6 CONCLUSION
A MATLAB/GUI based education tool has been developed to calculate the short-circuit faults in
transmission systems by using symmetrical components method. This software provides a user-
friendly interface to help the student to understand the symmetrical components and fault
calculations. After the entering of the system parameters, the student chooses one of the four fault
options. By choosing the fault type, all the calculations of fault currents and voltages have been
performed
After the MATLAB simulation for faults, it was observed that the voltage and current waveforms
were transient in nature in the initial period after the occurrence of faults. During the initial part of
short circuit, the short circuit current was limited by sub transient reactance of synchronous
machine and impedance of transmission line between the machine and point of fault. After that, it
was limited by transient reactance of synchronous machine and impedance of line. Finally, the
short circuit current settled down to steady state short circuit value limited by synchronous
reactance of the machine and line impedance. The negative and zero sequence components were
present initially only and they disappeared after the circuit breaker cleared the fault
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 47 of 108
CHAPTER 7: SYSTEM DESIGN
Design phase starts from making a block diagram of the proposed fault analysis in three phase
transmission line with auto reset on transient fault or remain tripped otherwise. The circuitry
designing and the explanation of components to be used is done in the design phase of the project
7.1 SIMPLIFIED BLOCK DIAGRAM OF THE CIRCUIT & EXPLANATION
Figure 33: Block diagram of Circuit
7.2 EXPLANATION
The project is designed to check fault that occur mainly in transmission line. A 3-phase supply
with frequency 50Hz is fed through voltage drop arrangement stabilized be Zener diode to a logic
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 48 of 108
circuit comprising NAND & OR gate to detect the proper sequence of RYB by series of pulse
fixed duration.
Suppose if the sequence is changed from YB to YRB the combination of NAND & or gate creates
an output with a missing pulse during the fixed time duration. This pulse is used in triggering a
monostable 555 timer. Thus, while the sequence is not there the triggering to the timer is missed
which is indicated by an LED driven from the output of the 555 timer. DC requirement of the
circuit is powered from a step down transformer along with a bridge rectifier and filter capacitor.
The project uses 6numbers step-down transformers for handling the entire circuit under low
voltage conditions of 12v only to test the 3 phase fault analysis. The primaries of 3 transformers
are connected to a 3 phase supply in star configuration, while the secondary of the same is also
connected in star configuration. The other set of 3 transformers with its primary connected in star
to 3 phase have their secondary’s connected in delta configuration.
The outputs of all the 6 transformers are rectified and filtered individually and are given to 6 relay
coils. 6 push buttons, one each connected across the relay coil is meant to create a fault condition
either at star i.e. LL Fault or 3L Fault. The NC contacts of all the relays are made parallel while
all the common points are grounded. The parallel connected point of NC are given to pin2 through
a resistor R5 to a 555 timer i.e. wired in monostable mode. The output of the same timer is
connected to the reset pin 4 of another 555 timer wired in astable mode. LED’S are connected at
their output to indicate their status.
The output of the U3 555 timer from pin3 is given to an Op-amp LM358 through wire 11 and d12
to the non-inverting input pin3, while the inverting input is kept at a fixed voltage by a potential
divider RV2. The voltage at pin2 coming from the potential divider is so held that it is higher than
the pin3 of the Op-amp used as a comparator so that pin1 develops zero logic that fails to operate
the relay through the driver transistor
This relay Q1 is ‘3CO’ relay i.e. is meant for disconnecting the load to indicate fault conditions.
7.3 LIST OF COMPONENT
Following are the list of component used in making the fault detection device:
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 49 of 108
Transformers
Op-amps
Switches
Resistors
Diodes
Capacitors
LEDs
Relays
i. Transformer:
In simple line transformer can be defined as an apparatus for reducing or increasing the
voltage of an alternating current.
In the proposed system transformer is connected in two different type of connection with
three phase supply for obvious reason:
a) Three transformer connected in star connection- three transformer are
connected in star connection because fault may occur at any point to take care of
fault which may occur at any point over 120km three transformer are connected in
star connection.
Star connection is preferred in long transmission line network i.e. Over 120 KM.
because it is having a neutral point, during balanced condition there will be no
current flowing through the neutral line and hence there is no use of the neutral
terminal. But when there will be unbalanced current flowing in the three phase
circuit, neutral is having a vital role. It will take the unbalanced current through to
the ground and protect the transformer.
Figure 34: Transformer connection to three phase source in star connection
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 50 of 108
b) Three transformer in delta connection: three transformer are connected in delta
connection because fault may occur at any point as mentioned above which could
be in region less than 60km to take care of that fault which may occur three
transformer are connected in delta connection.
Normally delta connection is preferred for short distance due to the problem of
unbalanced current in the circuit. The figure is shown below for delta connection.
In the load station, ground can be used as neutral path if required.
Figure 35: Transformer connection to three phase source in wye connection
.
ii. Op-Amp:
use of Op-Amp is to perform the following task
I. Signal conditioning
II. Signal filtering
III. Perform mathematical operation (+, -, ∫, dy/dx).
Op-Amp is fundamentally a voltage amplifying device.it will do the same in the above
proposed circuit.
Figure 36: Op-Amp
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 51 of 108
Switches: Switches
A set of switches will be used in the system to create the LL, LG and 3L fault in low voltage
side, for activating the tripping mechanism. Short duration fault returns the supply to the load
immediately called as temporary trip while long duration shall result in permanent trip
Figure 37: Switch
A switch is a component which controls the open-ness or closed-ness of an electric circuit.
They allow control over current flow in a circuit (without having to actually get in there and
manually cut or splice the wires). Switches are critical components in any circuit which
requires user interaction or control.
iii. Resistor:
A resistor is a passive two-terminal electrical component that implements electrical
resistance as a circuit element. Resistor will be used in proposed system so that it can
reduce current flow &, at the same time, act to lower voltage levels within circuits
Figure 38: Resistor
iv. Capacitor:
Capacitor is an electronic component that stores electric charge. The capacitor is made of 2
close conductors (usually plates) that are separated by a dielectric material. The plates
accumulate electric charge when connected to power source
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 52 of 108
Figure 39: Capacitor
v. LED’S:
LED will be used to show the fault which will occur in system such as line to line fault or
line to ground fault, etc.
A light-emitting diode (LED) is a semiconductor device that emits visible light when an
electric current passes through it. An LED or IRED consists of two elements of processed
material called P-type semiconductors and N-type semiconductors. These two elements are
placed in direct contact, forming a region called the P-N junction.
Figure 40: LED
vi. Relay:
A relay is electrical switch whose use in the proposed system is to isolate the faulted section
instantaneously & should cover protected circuit & fault resistance with some margin to
take care of error in measurement.
Figure 41: Relay
Some type of fault & operation are mentioned below in the box.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 53 of 108
S. No. Type of fault Operation of relay
1 Phase to ground fault (earth fault) Earth fault relay
2 Phase to phase fault Related phase overcurrent
relay.
3 Double phase to ground fault Related phase overcurrent
& earth fault relay
Table 3: some fault operation
vii. Diode
In the proposed system use of diode is allowing an electric current to pass in one direction
(called the diode's forward direction), while blocking current in the opposite direction (the
reverse direction) condition which will be used to block fault condition. It will help the fault
current to go get grounded preventing transformer from getting damaged.
A diode is a specialized electronic component with two electrodes called the anode and the
cathode. Most diodes are made with semiconductor materials such as silicon, germanium, or
selenium.
Figure 42: Diode
viii. Three phase supply- Three-phase electric power is a common method of alternating-
current electric power generation, transmission, and distribution across worldwide so the
researcher has tried to propose system which work for three phase simple reason behind it
single phase cannot handle heavy load while three phase can.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 54 of 108
Figure 43: Three Phase supply
ix. G.S.M modem
A GSM modem is a specialized type of modem which accepts a SIM card, and operates
over a subscription to a mobile operator, just like a mobile phone. From the mobile operator
perspective, a GSM modem looks just like a mobile phone.
When a GSM modem is connected to a computer, this allows the computer to use the GSM
modem to communicate over the mobile network. While these GSM modems are most
frequently used to provide mobile internet connectivity, many of them can also be used for
sending and receiving SMS and MMS messages.
Figure 44: Working of GSM Modem
7.4 POWER SUPPLY SYSTEM DESIGN
It is seen that the supply from the ac power socket cannot be supplied directly to the circuit as it
may damage the electronic components of the system which operated at very low voltage. So there
is a necessity to design a power system that can convert the ac supply coming from the supply
socket. For this purpose, there exists an ideal power supply design and following that ideal power
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 55 of 108
supply system, the prototype power supply system is used for this project that can fulfill the power
supply requirements of the system.
7.4.1 IDEAL POWER SUPPLY SYSTEM DESIGN
Ideally the power supply coming from the socket is firstly stepped down using step down
transformer. Then it is rectified as there is a need of ac to dc conversion as most of these electronics
devices operate at dc voltage. This is done by using rectifier circuit. After ac to dc conversion there
are some ripples remaining in the voltage signal so to suppress these ripples and to obtain ripple
free voltage, filters are used is used. As there is a requirement to design a regulated power supply
so a voltage regulator is used to regulate the voltage. Thus the ideal power supply system should
contain all these blocks.
Rectifier
Tranformer
Filter
Voltage Regulator
Power supply
socket
Given to the
circuitKey:
Wired
Figure 45: Ideal block diagram of power supply
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 56 of 108
7.4.2 PROTOTYPE POWER SUPPLY SYSTEM DESIGN
The system is firstly given the power of 220V ac supply from the power socket. This supply is
then stepped down using a step down transformer and connected to a bridge rectifier which
converts the power supply from ac to dc and gives the 12 V. This 12 V supply is further transferred
to a voltage regulator to reduce the voltage level to 5V approximately. Now this power 5V will be
provided to all the components of the circuitry which includes sensors, microcontroller, LCD
display, ignition system etc. as all these components work at 5V.
Power supply
socket
Given to the
circuit
Bridge RectifierStep down
transformer
Voltage
regulator
Filters
Electrolytic
Capacitors are
used in this case
Key:
Wired
Figure 46: PROTOTYPE POWER SUPPLY SYSTEM DESIGN
7.5 FAULT DETECTION & CLASSIFICATION SYSTEM
Figure 47: Transmission line
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 57 of 108
When system encounter fault (i.e. when push button is pressed to create a fault condition)
automatic tripping mechanism start but to have a detection system work system need to clarify
which nature of fault it is weather
Transient in nature or
Permanent fault.
This is the main part which is done by the following component
Push Button
Relay
Resistor
Capacitor
Resistor
Op- Amp
If the push button is released after pressing for a while (i.e. it is released immediately) the U1 pin
of relay connected in monostable mode the output disables the U3 pin the output U3 the astable
timer the output of which charges capacitor C13 through R11 such that the output of the
comparator goes high that drives the relay to switch off three phase load. Below shown figure
show the systematic connection how the system works
Figure 48: Step by step component used
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 58 of 108
The output of Op-amp remains high indefinitely through a positive feedback provided for its pin1
to pin3 through a forward biased diode and a resistor in series. This results in the relay permanently
switched on to disconnect the load connected at its NC contacts permanently off. In order to
maintain the flow of DC supply the star connected secondary set DC’S are paralleled through D8,
D9 & D10 for uninterrupted supply to the circuit voltage of 12v DC and 5v DC derived out of
voltage regulator IC 7805
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 59 of 108
CHAPTER 8: SYSTEM IMPLEMENTATION
After the completion of design phase in chapter 6, it is important to implement the system on
software and hardware. The following section will include the discussion about the software used
to implement the system, input devices used, relay unit, and led are output devices used in the
circuit. It will include the implementation of different prototype design systems on software and
hardware both.
8.1 SOFTWARE TO BE USED FOR SOFTWARE SIMULATION
The researcher is familiar with Multisim and Proteus software for simulation purpose.
Multisim includes all necessary tools to take a design from the beginning stage to the finishing of
the project. It is simple software in which you just need to place the components by selecting them
and dragging it to appropriate places and simulation can be seen by pressing RUN button. This
software has a database of most commonly used components (more than 16,000 components) but
still some useful components which will be used in this Accident Prevention Project are missing.
So the developer has decided to use Proteus for simulation of the project due to its following
advanced features.
Justification of using Proteus in the project
•Proteus has the feature to combine various components and 555 timer IC which will facilitate the
simulation of the complete automatic tripping mechanism load design.
•It provides the facility to interact with the design using LED, switches and this simulation takes
place approximately with the real time parameter. So it will help to evaluate the design and its
parameters before actual hardware implementation.
Technical manual explaining the usage of software as well as hardware is attached in appendix.
Below is Proteus simulation
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 60 of 108
8.2 PROTEUS SIMULATION
Figure 49: Proteus Simulation
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 61 of 108
8.3 WAVEFORM OF LINEAR NON LINEAR LOAD & RELAY
8.3.1INPUT VOLTAGE OF LINEAR & NON- LINEAR LOAD
Figure 50: Wave Form of Linear Load
Figure 51: Waveform of Non Linear Load
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 62 of 108
8.3.2 OUTPUT VOLTAGE OF RELAY
Figure 52:5.Output voltage of the 12v dc supply
Figure 53:6.Output voltage of the 12v dc
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 63 of 108
8.4 COMPONENT ASSEMBLY
Power supply
Power supply to the hardware is given through three phase ac source (R, Y, and B). The
input 220V is step down with the help of 12V step down transformer. Below shown figure
shows the initial connection of hardware from three phase supply
Figure 54: Power supply from three phase source
Input Supply
The input supply to hardware is given after stepping down the voltage to 12V its voltmeter
reading is noted
Figure 55: Input Supply
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 64 of 108
Assembly For single phase
Laying component in PCB firstly one single three phase source is used which is fed by three
transformer each transformer has (R, Y, B phase source respectively) which is then rectified
individually & & fed push button which is connected to 12v relay
Figure 56: Assembly for single phase
Assembly for all six transformer
Similarly, above step is repeated to six transformer source which has the same connection as shown
in the above figure These 3 transformers are connected in star connection of both primary as well
as secondary side of transformer. The output of that 3 transformer is given to the 3 relay coils with
rectified and filtered individually. The 3 push buttons are used to create a fault condition and they
are connected across the each relay coils. These 3 push buttons are created a single L-G fault and
LL-G fault simultaneously. The NC contact is connected in parallel and all the common points are
connected to ground. Below is the shown figure:
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 65 of 108
Figure 57: Assembly for six transformer
Connection of 555 timer with relay
After completing the transformer connection & voltage rectification switches & relay are
connected. Relay nc contact is left open & whose output is fed to 555 timer. The parallel connected
NC output is given to the pin 2 through a resister R5 to a timer IC 555 i.e. wired in mono stable
mode. The output of that timer is given to the reset pin 4 of another timer 555 wired it is having in
actable mode. The input of op-amp LM 358 is taken from pin 3 and which is the output of U3
timer 555 through wire 11 and d12 to the non-inverting input pin 3, the inverting input is kept at a
fixed voltage by a potential divider. Below is the shown figure
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 66 of 108
Figure 58: Connection of 555 timer & Lm358
Connection of Op-amp & transistor with 555 timer & relay
Below shown figure shows the connection of Op-amp which is fed by pin 7 of 555 timer IC.
The output of Op-amp remains high indefinitely through a positive feedback provided for its pin1
to pin3 through a forward biased diode and a resistor in series. This results in the relay permanently
switched on to disconnect the load connected at its NC contacts permanently off. In order to
maintain the flow of DC supply the star connected secondary set DC’S are paralleled through D8,
555
Timer
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 67 of 108
D9 & D10 for uninterrupted supply to the circuit voltage of 12v DC and 5v DC derived out of
voltage regulator IC 7805
Figure 59: Connection of Op-amp & transistor with 555 timer & relay
Completed Assembled Circuit
If the fault is off temporary in nature i.e. if the push button pressed is released immediately the U1
monostable disables U3 the output of which goes to zero in the event of any push button kept
pressed for a longer duration the monostable output provides a longer duration active situation for
U3 the astable timer the output of which charges capacitor C13 through R11 such that the output
of the comparator goes high that drives the relay to switch off three phase load.
Below is the shown figure:
Transistor
Op-Amp
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 68 of 108
Figure 60: Completed Assembled Circuit
Final circuit
Figure 61: Final circuit
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 69 of 108
CHAPTER 9: HARDWARE TESTING
.Conductivity Test:
In electronics, a continuity test is the checking of an electric circuit to see if current flows (that it
is in fact a complete circuit). A continuity test is performed by placing a small voltage (wired in
series with an LED or noise-producing component such as a piezoelectric speaker) across the
chosen path. If electron flow is inhibited by broken conductors, damaged components, or excessive
resistance, the circuit is "open". Devices that can be used to perform continuity tests include multi
meters which measure current and specialized continuity testers which are cheaper, more basic
devices, generally with a simple light bulb that lights up when current flows. An important
application is the continuity test of a bundle of wires so as to find the two ends belonging to a
particular one of these wires; there will be a negligible resistance between the "right" ends, and
only between the "right" ends. This test is the performed just after the hardware soldering and
configuration has been completed. This test aims at finding any electrical open paths in the circuit
after the soldering. Many a times, the electrical continuity in the circuit is lost due to improper
soldering, wrong and rough handling of the PCB, improper usage of the soldering iron, component
failures and presence of bugs in the circuit diagram. We use a multi meter to perform this test. We
keep the multi meter in buzzer mode and connect the ground terminal of the multi meter to the
ground. We connect both the terminals across the path that needs to be checked. If there is
continuation then you will hear the beep sound
Power ON Test:
This test is performed to check whether the voltage at different terminals is according to the
requirement or not. We take a multi meter and put it in voltage mode. Remember that this test is
performed without ICs. Firstly, if we are using a transformer we check the output of the
transformer; whether we get the required 12V AC voltage (depends on the transformer used in for
the circuit). If we use a battery then we check if the battery is fully charged or not according to the
specified voltage of the battery by using multimeter. Then we apply this voltage to the power
supply circuit. Note that we do this test without ICs because if there is any excessive voltage, this
may lead to damaging the ICs. If a circuit consists of voltage regulator then we check for the input
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 70 of 108
to the voltage regulator (like 7805, 7809, 7815, 7915 etc) i.e., are we getting an input of 12V and
a required output depending on the regulator used in the circuit. EX: if we are using 7805 we get
output of 5V and if using 7809 we get 9V at output pin and so on. This output from the voltage
regulator is given to the power supply pin of specific ICs. Hence we check for the voltage level at
those pins whether we are getting required voltage. Similarly, we check for the other terminals for
the required voltage. In this way we can assure that the voltage at all the terminals is as per the
requirement
Figure 62: Functional Circuit
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 71 of 108
CHAPTER: 10 CALCUATION
For L-G
Pbase = 𝑃𝑏𝑎𝑠𝑒
𝑉𝑏𝑎𝑠𝑒×√3
= 500
250×√3 =1.255KA
Vbase = 𝑉𝑏𝑎𝑠𝑒
𝐼𝑏𝑎𝑠𝑒×√3
= 12
1.255×√3 = 5.52
Zpu = 𝑍𝑎𝑐𝑡𝑢𝑎𝑙
𝑍𝑏𝑎𝑠𝑒
=6
5.52= = 1.08
Zpu- transformer=base𝑀𝑣𝑎
𝑇𝑟𝑎𝑛𝑠𝑓𝑜𝑟𝑚𝑒𝑟 𝑀𝑣𝑎× 𝑍%/100
500
500×
6
100= 0.06
𝑩𝒂𝒔𝒆𝑴𝒗𝒂
𝒁𝒑𝒖𝒔𝒐𝒖𝒓𝒄𝒆
=𝟏𝟐
𝟏.𝟎𝟖= 11𝑀𝑣𝑎
Line to neutral voltage on the secondary of the transformer 12
√3= 6.92𝑉
Fault KA 𝐹𝑎𝑢𝑙𝑡𝑀𝑣𝑎
3 × 𝑉𝑙 − 𝑁
11
√3 × 6.92
=0.917A
Basemva=10000
1000= 1𝑀𝑣𝑎
Mva value=1𝑀𝑣𝑎
√𝑍𝑝𝑢=
1
0.06= 16.66𝐴
Admittance method to calculate fault current
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 72 of 108
1
𝑈𝑡𝑖𝑙𝑖𝑡𝑦 𝑚𝑣𝑎1/𝑇𝑟𝑎𝑛𝑠𝑓𝑜𝑟𝑚𝑟𝑒𝑟 =
1
𝑀𝑣𝑎
1
500+
1
16.66=
1
𝑀𝑣𝑎
0.002+0.06=1
𝑀𝑣𝑎
Mva=1
0.002+0.06
Mva=16.129A
Fault current at 230V = 16.129
1.66∗0.23= 4𝐴
Fault current at 12V =16.129
1.66∗0.12=8A
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 73 of 108
CHAPTER: 11 REFLECTIVE SUMMARY & OVERVIEW
Fault protection system has become fundamentally important due to its ability to prevent
economical losses. The main purpose of a protection system is to process the voltage and/or current
signals to determine whether a fault is present, to classify what kind of fault it may be, to estimate
the fault location, and to take action to remove the fault from the power transmission-line system.
The continuity service depends heavily on the possibility of detecting, classifying, locating, and
isolating faults in the power transmission-line system.
Conventional methods for relay to protect the transmission-line system were to monitor distortions
in voltage and/or current signals in time and frequency domains.
Protection systems generally fit into three categories:
1. quantitative model-based approaches
2. qualitative model-based
3. approaches, and data-driven approaches
The quantitative model- and qualitative model-based approaches showed superior performance in
the simulation studies. However, they delivered poor performance in case of the presence of noise
in the fault voltage or current signals or led to uncertainties due to the variations of system
parameters. Therefore, measurement and system noises are key factors that can affect the
capabilities of these methods, resulting in high false positives or false negatives.
It is necessary to understand the gravity and after effects of a line failure. To overcome these, we
are proposing a GSM based transmission line fault detection System. Whenever the preset
threshold is crossed, the microcontroller instantly initiates a message to be sent to the area lineman
and the Control Station stating the exact pole to pole location. This helps us to realize a almost real
time system
The hardware will be valuable in many ways
will save equation from damaging the component when the flashover is encountered in line
by tripping the line
will save the transmission line when there is fault due to overload
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 74 of 108
Will save the load side & equipment from getting damaged due to various fault such as L-
L, L-G, L-L-G fault.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 75 of 108
CHAPTER 12: CONCLUSION
This project is designed in the form of Hardware for three single phase transformers 230v to 12V
of output for to develop an automatic tripping mechanism for the three phase supply system while
temporary fault and permanent fault occurs. Here we used 555 timer with relay for the fault is
temporary or permanent. Short duration fault returns the supply to the load immediately called as
temporary trip while long duration shall result in permanent trip
The project output resets automatically after a brief interruption in the event temporary fault while
it remains in tripped condition in case of permanent fault. The electrical substation which supply
the power to the consumers, have failures due to some faults which can be temporary or permanent.
These faults lead to substantial damage to the power system equipment. In India it is common, the
faults might be LG (Line to Ground), LL (Line to Line), 3L (Three lines) in the supply systems
and these faults in three phase supply system can affect the power system. To overcome this
problem a system is built, which can sense these faults and automatically disconnects the supply
to avoid large scale damage to the control gears in the grid sub-stations. This system is built using
three single phase transformers which are wired in star input and star output, and 3 transformers
are connected in delta connections, having input 220 volt and output at 12 volt. This concept low
voltage testing of fault conditions is followed as it is not advisable to create on mains line. 555
timers are used for handling short duration and long duration fault conditions. A set of switches
are used to create the LL, LG and 3L fault in low voltage side, for activating the tripping
mechanism. Short duration fault returns the supply to the load immediately called as temporary
trip while long duration shall result in permanent trip.
Fault on the transmission line needs to be restored as quickly as possible. The sooner it is restored,
the less the risk of power outage, damage of equipment of grid, loss of revenue, customer
complaints and repair crew expenses. Rapid restoration of service can be achieved if precise fault
location algorithm is implemented.
Many algorithms have been developed to calculate the fault distance on the transmission line. This
paper gives the general overview of fault location calculation on transmission line using impedance
based method and traveling wave method. It discussed the transmission line model, its sequence
components, symmetrical components for fault analysis, fundamental principal of travelling wave.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 76 of 108
CHAPTER 13: COST ESTIMATION
Cost estimation plays a vital role in project management and is one of the most difficult
responsibility. The researcher must take a close view on this section. The purpose of cost
estimation is simple that is to precisely estimate required resource which would allow the
researcher to implement and develop the proposed system. Not giving importance or
underestimating the section may result in exceeding the estimated budget of the project, poor
quality & even researcher might fail to complete project on time.
Importance of Cost Estimation
Cost estimation is significant for the reason that each project has the possibility of added cost that
was not considered during the proposal such as failure of electrical device while making hardware
of short circuit would result in damaging the system forcing the researcher to make system one
more time exceeding the estimated cost.
For the proposed project i.e. ‘ G.S.M based three phase fault analysis with auto reset on transient
fault or remain tripped otherwise’ cost estimation is required because a project can only be
successful if it is completed in desire time & budget. So to achieve this appropriate cost estimation
is required. For this researcher has to evaluate the cost of component which will be used in the
system. Then the expenditure for the industry that will make the project for the real time scenario
& finally the expense that user has to pay will be evaluated.
13.1 COST ESTIMATION FOR THE DEVLOPER
Sr.
No.
Component
Description
Quantity Single Unit
Cost
(in Rupees)
Total cost of Items
Purchased
(in rupees)
4. Transformer 6 120~150 720~900
5. Op-amp 6 80~100 480~600
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 77 of 108
6. Switches 4~6 30~50 180~300
7. Capacitor 20~40 8~10 200~400
8. Resistor’s 8~10 1~2 20
9. Diode 10~12 1~2 10~20
10. LED’S 6 5~10 30~60
11. Relay 6 30~40 ~200
12. PCB 1 30 ~30
13. 555 Timer 2 40~50 ~100
14. GSM module 1 900~1200 900~1200
Total Cost: ~3100
13.2 SOFTWARE REQUIRED
As a student researcher we get software free of cost from the college itself. By this cost be paid by
the industry.
Sr.
No.
Software Description
1. Matlab/Simulink
Free- student version
Software that is used to make block diagram
2. Proteus-Free for students Software that is used for simulation of system & layout
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 78 of 108
REFERENCES
1. Wadhwa, C.L, 2005. electrical power system . 5th ed. delhi: New Age International
Publisher.
2. T. Takagi, Y. Yamakoshi, M. Yamamura, R. Kondow, T. Matsushima, “Development of a
New Type Fault Locator Using the One-Terminal Voltage and Current Data,” in IEEE
Transactions on Power Apparatus and Systems, Vol. PAS-101, No. 8, August 2015, pp.
2892-2898.
3. D. A. Tziouvaras, J. B. Roberts, G. Benmouyal, “New Multi-Ended Fault Location Design
for Two- or Three-Terminal Lines,” in Developments in Power System Protection (IEE),
Conference Publication No. 479, Amsterdam, 2014, pp. 395-398.
4. . Gross, charles , 2011. power system analysis. 5th ed. delhi: willey india edition.
5. IEEE Power Engineering Society (PES), IEEE Guide for Determining Fault Location on
AC Transmission and Distribution Lines, IEEE Std. C37.114TM-2004.
6. K. Zimmerman, D. Costello, “Impedance-Based Fault Location Experience,” in 2005 58th
Annual Conference for Protective Relay Engineers, 2005, pp. 211-226
7. J. Grainger , John, 2006. power system analysis. 5th ed. delhi: Mc-Graw hill.
8. K. Zimmerman, D. Costello, “Impedance-Based Fault Location Experience,” in 2005 58th
Annual Conference for Protective Relay Engineers, 2005, pp. 211-226.
9. singh, manohar, 2011. Transmission Line fault detection & classification . Ieee, 3, 6.
10. El-Harway, Mohamed E. Electrical power system: design & analysis.
11. P. F. Gale, P. A. Crossley, X. Bingyin, G. Yaozhong, B. J. Cory, J. R. G. Barker, “Fault
Location Based on Travelling Waves,” in Fifth International Conference on Developments
in Power System Protection, 2013, pp. 54-59.
12. P. F. Gale, P. A. Crossley, X. Bingyin, G. Yaozhong, B. J. Cory, J. R. G. Barker, “Fault
Location Based on Travelling Waves,” in Fifth International Conference on Developments
in Power System Protection, 1993, pp. 54-59.
13. M. Aurangzeb, P. A. Crossley, P. Gale, “Fault Location on a Transmission Line Using
High Frequency Travelling Waves Measured at a Single Line End,” in Power Engineering
Society Winter Meeting, Vol. 4, 2000, pp. 2437-2442.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 79 of 108
14. A. Elhaffar, M. Lehtonen, “Travelling Waves Based Earth Fault Location in 400kV
Transmission Network Using Single End Measurement,” in Large Engineering Systems
Conference on Power Engineering, 2004, pp. 53-56.
15. Kejariwal, et al. Fault Detection and Location System for Power Transmission and
Distribution Lines. The Research and Development Institute, Inc. at Montana State
University. Patent 5,343,155. 30 August 2014.
16. M. Vintan, “Fault Current Distribution Computation on Overhead Transmission Lines,” in
Proceedings of the Fifth International World Energy System Conference, vol. II, 2004,
Oradea, Romania, pp. 273-279.
17. J. Jiang, Y. Lin, J. Yang, T. Too, C. Liu, “An Adaptive PMU Based Fault
Detection/Location Technique for Transmission Lines—Part II: PMU Implementation and
Performance Evaluation,” in IEEE Transactions on Power Delivery, Vol. 15, No. 4,
October 2000, pp. 1136-1146.
18. J. Jiang, Y. Lin, J. Yang, T. Too, C. Liu, “An Adaptive PMU Based Fault
Detection/Location Technique for Transmission Lines—Part II: PMU Implementation and
Performance Evaluation,” in IEEE Transactions on Power Delivery, Vol. 15, No. 4,
October 2000, pp. 1136-1146.
19. M.B. Djuri6, Z.M. Radojevi6 and V.V. Terzija, Member IEEE, “Distance Protection and
Fault Location Utilizing Only Phase Current Phasors”, October 1998
20. Javad Sadeh, N. Hadjsaid, A. M. Ranjbar, and R. Feuillet, “Accurate Fault Location
Algorithm for Series Compensated Transmission Lines”, July 2000
21. Mokhlis1, Hasmaini Mohamad, A. H. A. Bakar1, H. Y. Li, “Evaluation of Fault Location
Based on Voltage Sags Profiles: a Study on the Influence of Voltage Sags Patterns”, 2011
22. D. A. Tziouvaras, J. B. Roberts, and G. Benmouyal, “New multi-ended fault location
design for two- or three-terminal lines,” in Proc. Inst. Elect. Eng. Developments in Power
System Protection, Amsterdam, the Netherlands, 2001, pp. 395–398, Conf. publ. no.
479.Shi J. and Malik J., „Normalized Cuts and Image Segmentation‟, IEEE Transactions
on Pattern Analysis and Machine Learning, 888-905, 2000.
23. Tumanski, S., Induction Coil Sensors – a Review, Meas. Sci. Technol. 2007 18 R31.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 80 of 108
24. S. Sajedi, F. Khalifeh, Z. Khalifeh, T. karimi, “Application of Wavelet Transform for
Identification of Fault Location on Transmission Lines,” 2011
25. M. Dewe, S. Sankar, J. Arrillaga, “The Application of Satellite Time References to HVDC
Fault Location”, IEEE Transactions on Power Delivery, 8, 1295-1302 (1993)
26. F. H. Magnago, A. Abur, “Fault location using wavelets ,” IEEE Transactions on Power
Delivery, 13, 14750-1480 (2016)
27. Emmanouil Styvaktakis, Mathias H.J. Bollen, Irene Y.H. Gu , “A Fault Location
Technique Using High Frequency Fault Clearing Transients”, 1999
28. S.M. Kay, S.L. Marple, “Spectrum Analysis: A Modem Perspective,” Proceedings of the
ZEEE, vol. 69, no. 11, hov. 1981, pp. 1380- 14 1 9
29. D. C. Robertson, 0. I. Camps, J. S. Mayer, and W. B. Gish, “Wavelets and Electromagnetic
Power System Transients”, IEEE Transactions on Power Delivery, Vol.11, No.2, pp. 1050-
1058, April 1999
30. H. Mokhlis1, Hasmaini Mohamad, A. H. A. Bakar1, H. Y. Li, “Evaluation of Fault
Location Based on Voltage Sags Profiles: a Study on the Influence of Voltage Sags
Patterns”, 2011
31. M.S Sachdev, FIEEE, R.Agarwal, St. MIEEE, “ A Technique for estimating transmission
line fault locations from digital impedance relay measurements”,2009
32. M. KezunoviC, B. PeruniEiC, “Automated Transmission line fault analysis using
synchronized sampling at two ends ", 2012
33. Joe-Air Jiang, Jun-Zhe Yang, Ying-Hong Lin, Chih-Wen Liu,” An Adaptive PMU Based
Fault Detection/Location Technique for Transmission Lines”, 2015
34. A. A. Girgis, D. G. Hart, and W. L. Peterson, “A New Fault Location Technique For Two-
and Three-Terminal Lines,” IEEE Transactions on Power Delivery, vol. 7, no. 1, pp. 98–
107, January 1992
35. D. Novosel, D. G. Hart, E. Udren, and J. Garitty, “Unsynchronized Two- Terminal Fault
Location Estimation,” IEEE Transactions on Power Delivery, vol. 11, no. 1, pp. 130–137,
January 1996
36. Javad Sadeh, N. Hadjsaid, A. M. Ranjbar, and R. Feuillet, “Accurate Fault Location
Algorithm for Series Compensated Transmission Lines”, July 2012
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 81 of 108
37. A. Gopalakrishnan, M. Kezunovic, S. M. McKenna, and D. M. Hamai, “Fault Location
Using the Distributed Parameter Transmission Line Model”, October 2000
38. Erikson, L., Saha,M.M and Rockfeller, “An accurate fault locator with compensation for
apparent reactance in the fault resistance resulting from remote end infeed”, IEEE Trans.,
PAS104, 1985, pp. 424435
39. Scheweitzer, E.O., 111, “Evaluation and development of transmission line fault locating
techniques which use sinusoidal steady state information”, Computers & Elec. Engng
USA, 1983, IO, (4), pp. 269-218
40. Cook,V,“Fundamental aspects of fault location algorithms used in distance protection”,
IEE Proc. C, 1986, 133, (6), pp. 359-368
41. Jeyasurya, B., Rahman,M.A, “Accurate fault location of transmission line using
microprocessors”, IEE Conf. Publ. 302, 1989
42. Lawrence, D.J., and Waser, D.L, “Transmission line fault location using digital fault
recorder”, IEEE Trans., 1988, PWRD-3, (2). pp. 496-502
43. M. Kezunovit, J. Mrkic, B. PeruniEiC, “An Accurate Fault Location Algorithm Using
Synchronized Sampling,” May 1994
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 82 of 108
APPENDIX A
Title – G.S.M based three phase fault analysis with auto-reset on temporary fault or remained
trip otherwise.
Description- fault in power system is deviation of voltage or current from its nominal value and
state which happens more often leading to the failure of many equipment or may even be life
threatening to the operating personal, so to overcome this engineers have developed a system to
analysis the fault in power system. The fault analysis of power system is required in order to
provide information to selection of safety gear.
Faults usually occur in a power system due to either insulation failure, flashover, physical
damage or human error. These faults, may either be three phase in nature involving all three
phases in a symmetrical manner, or may be asymmetrical where usually only one or two phases
may be involved.
Fault analysis usually carried out in per-unit quantities (similar to percentage quantities) as they
give solutions which are somewhat consistent over different voltage and power ratings, and
operate on values of the order of unity. Relating to one single phase gives information related to
two or three phase as well so it is more obvious & sufficient to do calculation in one phase.
This project system will be designed to develop an automatic griping mechanism for three phase
supply system. The output will reset automatically when there is brief interruption (temporary
fault) or remain tripped otherwise in case of permeant fault.
Function
Automatic reset in case of temporary fault
Trip when permeant fault.
Send message to the operating personal when fault encountered.
Requirement to make such system-
This system will be built using three single phase transformers which are wired in star input and
star output, and 3 transformers are connected in delta connections, having input 220 volt and
output at 12 volt. This concept low voltage testing of fault conditions is followed as it is not
advisable to create on mains line. 555 timers are used for handling short duration and long
duration fault conditions.
1. Three single phase transformer ( wired star input and star output)
2. Three transformer ( delta connection, input 220V & output 12V)
3. 555 ( for handling short duration and long duration fault)
4. Switch set to create fault
I. Line to line fault (LL occurring 5-10%)
II. Line to ground fault (LG major of all fault occurring 60-65%)
III. Double line to ground fault (LLG occurring 15-20%)
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 83 of 108
IV. Line to line to line fault (LLL kind of symmetrical fault occurring 2-5% but
results in damaging major equipment’s )
5. OP-amps
6. Resistor
7. Diode
8. Capacitor
9. LED
10. Relay
11. G.S.M technology to send SMS to operating personal
Targeted audience –
this system is designed to save life of the operating personal operating the power system
moreover it can be a life saver when there is wrath of nature like thunder storm, lightning which
result in damaging the power system by uprooting the transmission line as a result of which live
wire comes in contact with the ground.it can save many important costly equipment of power
system.
Research area
Power flow analysis
Power system fault
Power system stability
Matlab to simulate the system design
G.S.M technology
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 84 of 108
APPENDIX B
PROJECT PROPOSAL FORM
Pritesh Kumar, Electrical & Electronics Engineering
Supervisor- Vijyendra Sharama
Title-
G.S.M interfaced three phase fault analysis tool with auto-reset on temporary fault or remained
trip otherwise.
Objective –
To reach the aim following are the field to work on
A perfect fault analysis tool should be able to perform the following task
6. Fault detection in three phase transmission line.
7. Fault classification in three phase transmission line.
8. Fault location in three phase transmission line.
Interfacing two technology
9. Interfacing G.S.M technology with transmission line to alert the operating personal.
Explanation of the project:
Fault detection on transmission line are important task to safeguard electrical power
system. Fault detection is essential to the safe operation of electric power transmission and
distribution systems. Without some sort of fault detection, the automated removal of short
circuits from a transmission system would be impossible. As a result, these faults might
persist until essential electrical equipment is damaged or destroyed so it is a must process
for fault analysis in transmission line, result is clear protection of power system equipment.
Transmission line protection is an important issue in power system engineering because
85~87% fault occur in transmission line. Seeing from other prospective it’s a must process
to save people & governments money.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 85 of 108
Technology to be used:
G.S.M
Artificial neural network.
Artificial Intelligence can be used if system has more complexity.
K-Nearest Algorithm for fault calculation.
Or synchronized sampling for fault calculation.
Wavelet approach
It is important to note that K-nearest algorithm, synchronized sampling & Wavelet approach are
different technology for fault calculation.
Software to be used
Matlab/ Simulink
GSM module software depending upon GSM module used while implementation of
technology on board.
Hardware to be implemented:
Transformer
Op-amp
Switches
Resistor’s
555 timer
Diode
Capacitor
LED’s
Relay
GSM module
Block diagram of proposed device
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 86 of 108
START
VOLTAGE & CURRNET
SIGNAL
WAVELE/A-NN/L-NEAREST NEIGHOUR
TOOLBOX
COMPONENT FILTERING BOTH VOLATAGE &
CURRNET SIGNAL
WEATHER
FAULT
OCCURRED OR
NOT?
SELECT Z
depending
on fault
Calculate z
Stop
Show distance
Calculate “distance”
Print no fault
Stop
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 87 of 108
How analysis will be done?
A typical fault analysis tool should be able to perform fault classification, fault detection fault
location.
Fault detection
Various method is there for fault detection gathering information will be viable to achieve
the final output. Some of the proposed method for fault location are proposed below:
Impedance- based method
Travelling Wave based method
Detection using magnetic field sensor
Fault detection will perform the following operation:
Record the time at which fault occurred.
If some abnormality is recorded at both ends of the transmission line, then the
location of the fault is computed based on the difference in detection times.
If the abnormality is recorded at only one end of the transmission line, then the
possibility that an error might have occurred is recorded in the memory.
Fault classification
Many method are there for classification of fault such as
Wavelet method can again be used
K-nearest Neighbor Algorithm
Fault location
The current fault location methods for cables can be divided into offline and online
methods. The offline methods require special equipment, trained personnel and that the
faulted cable is out of service before the methods can be used. The online methods utilize
information in the current and voltage measured at the fault locator terminal (FLT) between
fault incipience and fault clearance
On-line method- The online fault location methods can be subdivided into two
primary categories;
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 88 of 108
Impedance method.-The impedance-based fault location methods compares
most often pre-known line parameters to the impedance measured in the
case of fault. Based on this comparison the fault location can be estimated.
Travelling wave method. When a fault occurs on a cable system, transient
voltage and current waves will travel from the fault location in both
directions towards the terminals to where the cable is connected
Of-line method- The offline methods can be divided into two categories—
terminal methods and tracer methods. The terminal methods do, as the name
indicates, rely on analyzing measurements performed from one or both ends
of the cable. The tracer methods rely on the other hand on measurements
performed by a trained person walking the cable route.
Literature review
Inspiration for working on this project come when observing a transmission line (long) which
almost resemble like a clan carrying wire with bended hand through which a quest was developed
how whole system work, later while searching this topic a fact appeared which shows major ~80-
85% of fault in transmission line occur in transmission line. While searching for previous research
fault analysis in transmission line several interesting fact was known such as:
(Yadav 2014)”Fault analysis in three phase transmission line using K-Nearest
neighbor algorithm “discusses “ in K-NN algorithm method K-NN uses the nearest
neighbor to calculate the fault. This method compares the value from nominal value
and henceforth decision is taken, it is important to mention that detection time is
within half to one cycle and of the proposed method is 99%.”
(Singh & Pnaighari, 2011)”Transmission line fault detection classification by
“discusses” proposed method uses the sample of current & voltage extracted from
the fault point. Wavelet transform is used to extract transient energy from the
sample moreover it is free from tradition neural network approach such as
genralizarion”
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 89 of 108
(Jung,Choi ,Cho & chung,2012) “Analysis of the unbalanced fault in transmission
line in Three-Phase Flux coupling type SFCL using the symmetrical coordinate
method” discusses “ in unsymmetrical or unbalanced fault in power system when
flux coupling type SFCL was applied , use of SFCL limit the fault current using the
symmetrical co-ordinate method in case of fault state by changing the primary
secondary turn ratio of the flux coupling type SFCL(superconducting fault current
limiter).”
(Hagh,Razi,Taghizadeh ,2007) “Fault classification & location of power
transmission line using Artificial Neural Network” discusses “the present method
is not dependent on fault inception angel. Modular ANNs are considered with
three hidden layer and then those are tested with various distance & resistance of
fault for each type of fault. Line to ground, double line to ground & line to line
fault are considered. Maximum absolute error for line to ground fault was
0.3324%, for double line to ground it was 0.4926% & for line to line 0.348% for
three phase fault.”
(Dutta,Kezunovic,2014)”Transmission line fault analysis using synchronized
sampling” discusses “ synchronized sampling of both voltage and current is one of
the simple yet most efficient fault analysis method by using prevent & post event
sample to detect fault moreover it does not require elaborated parameter setting for
detecting threshold, since method depends on accurate representation of a
transmission line model &, therefore produce very accurate fault location method
because of modern circuit breaker fault is detected within two cycle.”
(Yadav, Swerpadama,2015)”Improved fault location algorithm for multi-location
fault , transforming fault & shunt fault in Thyristor controlled series capacitor
compensated transmission line” discusses “combining two method discreet WT &
ANN fault method reduces the fault classification( fault type & faulty phase(s)
information for fault location estimation most important significance is that it not
only locate shunt fault but also find location of multi-location fault & transforming
fault that too using single terminal data.”
(Singh,Tripathi,Vekataramana,2013)”Recent techniques used in transmission line
protection: a review “discusses “The ANN, fuzzy logic, genetic algorithm, SVM
and wavelet based techniques have been quite successful but are not adequate for
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 90 of 108
the present time varying network configurations, power system operating
conditions and events. Therefore, it seems that there is a significant scope of
research in AI techniques which can simplify the complex nonlinear systems,
realize the cost effective hardware with proper modification in the learning
methodology and preprocessing of input data and which are computationally much
simpler. Also development of reliable software and communication system will
pave the way”
(0. Dag & Ucak, 2003) “A Combined Wavelet-ANN based fault classifier has been
investigated for electrical distribution systems “discusses “Some fault condition
wore taken to identify by this the proposed approach. It is shown that the technique
correctly recognizes and discriminates the fault type and faulted phases with a high
degree of accuracy”.
Methodology most probably to be used
Faulted transmission line
Fault analysis is carried out in per unit quantity. Since information related to single phase gives
the information related to three or two phase as well so it more than sufficient to do calculation in
one phase only as it will give information related to other two phase as well.
The proposed system will be built using three single phase transformers which will be wired in
star input and star output, and 3 transformers are connected in delta connections, having input 220
volt and output at 12 volt. The concept of low voltage testing on fault conditions is followed as it
is not advisable to create on mains line. 555 timers shall be used for handling short duration and
long duration fault conditions.
A set of switches will be used to create the fault stress will be more on LL, LG and 3L fault in as
LG fault has maximum fault condition nearly 65% of overall fault in transmission line followed
~ ~
B
U
S
B
U
S
mZ (1-m)Z Ia
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 91 of 108
LL, 3L.( more symmetrical and unsymmetrical fault condition can be implanted on the device if it
is not followed by time constrain. Low voltage side, for activating the tripping mechanism. Short
duration fault will returns the supply to the load immediately called as temporary trip while long
duration shall result in permanent trip.
GSM technology will be used to send message to the authorities via SMS by interfacing a GSM
modem.
Earlier work done on the topic:
Traditional way of analyzing fault in transmission line was based on change on voltage current
1and impudence with respect to present value to identify the fault. Many technology has overtaken
the traditional approach such as
ANN (artificial neural network) which would be used in the project for calculating fault.
This ANN technology need huge amount of training cases to achieve good performance.
Synchronized sampling-method depends on accurate representation of transmission line
model & therefore produces a very accurate fault location result.
ANFIS network- adaptive neuro fuzzy interface system
Wavelet transform- this method utilizes sample of current & voltage extracted from the
fault point. This technology is free from tradition neural network approach such as
“generalization”.
Symmetrical coordinate method- this technology uses a device called SFCL
(superconducting fault current limiter). SFCL uses symmetrical coordinate method in case
of unbalanced fault
Possible enhancement to be done in the existing topic
A deep research will be done by the researcher for understanding the fault analysis perfectly, a
perfect fault analysis tool perform the following important function
Fault detection
Fault classification
Fault location
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 92 of 108
All the above described method need huge amount of calculation so, Artificial intelligence
technique can be used to solve the complex non –linear system for ease of the calculation.
Interfacing the viable GSM technology with the fault analysis tool would be helpful in
many ways such as in case of fault occur the GSM technology will automatically inform
the operating personal via sort message service (SMS), moreover interfacing this
technology could be life savior to many for human’s & animals too.
Target audience:
this system is designed to save life of the operating personal operating the power system
moreover it can be a life saver when there is wrath of nature like thunder storm, lightning which
result in damaging the power system by uprooting the transmission line as a result of which live
wire comes in contact with the ground.it can save many important costly equipment of power
system.
Feasibility:
Cost feasibility:
To complete the project various electrical component such as transformer and electronics
component such as diode will be used, so the final cost cannot be accurately predicted at this stage
but an average cost of the component to make hardware can be predicted which is described below
S.no Equipment Average
Equipment cost
No. of
component
required
Average cost in
RS
1. Transformer Rs.120~150 6 720~900
2. Op-amp Rs.50~100 6 300~600
3. Switches Rs.30~50 4~6 180~300
4. Resistor’s Rs.1~2 8~10 20
5. Diode Rs.1~2 10~12 10~20
6. Capacitor Rs.20~40 8~10 200~400
7. LED’s Rs.5~10 6 30~60
8. Relay Rs.30~50 6 200
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 93 of 108
9. GSM module Rs.900~1200 1 900~1200
10 555 Timer Rs.40~50 2 100~
555 timer Rs.3100~
Minimum cost will be ~ Rs.3100.
Time feasibility:
After background research, literature review will be done which is basis of any research &
then technical research.
Questionnaire & interview will be done.
And will be followed by implementation on hardware.
At last documentation will be done.
Gant chart
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 94 of 108
APPENDIX D
PERT CHART1
0
0
Requirement
Analysis and
Research
1
54
61
267
74
3
13
6
74
74
4
95
102
Literature Review
5
Programming
Implementation
Testing and
Evaluation
FYP
Documentation
and Submission
Project
Commencement
Data Gathering
Techniques
54
74
1513
37
62
28
19
898
89
21610
154
154
9
117
117
216
12
244
244
11
263
263
Proposed
Methodology6
Project Management
7
102
102
Analysis &Mid-point
documentation
15
FIGURE 1: PERT CHART
For this project, the researcher has used activity on arrow pert chart to evaluate the time
management of the project. The Earliest Completion Time (ECT) i.e. the minimum amount of time
needed to complete all the activities that precedes every event is mention in the upper part of the
circle and the Latest Completion Time (LCT) which is the latest time needed at which the event
can occur without delaying the overall project is mention in the lower part of the circle. The critical
path is the path of the tasks which cannot be delayed and project will not move forward without
completing these tasks. In the pert chart drawn below, black lined tasks which are from task 1, 4,
5, 8, 9, 10, 11, 12, 13, 14 and 15 indicates the critical path and these task cannot be delayed. Task
4 is dependent upon task 2 and 3 and task 8 depends upon 6 and 7. It means task 8 cannot be
starting before task 6 and 7 is not completed. Critical path is that when the earliest completion time
and the latest completion time is same for a particular task.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 95 of 108
TIMELINE
S. No Contents Starting Date Deadline Supervisee
Signature
Supervisor
signature
1 Conduct background
research work
26-8-2015 1-9-2015
2 Literature review
from 10 research
paper , journal ,etc.
related to project
2-9-2015 10-92015
3 Read concept of
basics of fault
analysis in three
phase transmission
line.
13-9-2015 20-9-2015
4 Preparing project
proposal form.
28-9-2015 1-102015
5 Go through Reach of
Circuit breaker &
read the concept of
Relay
4-10-2015 13-10-2015
6 Concept of
Calculation of fault
14-10-2015 19-10-2015
7 Read basics of GSM
module & go through
some research paper
related to it.
20-10-2015 28-10-2015
8 Finding of Secondary
research.
29-10-2015 2-11-2015
9 Read
MATLAB/Simulink
for implementing
proposed topic.
3-11-2015 -11-2015
10 Preparation &
distribution of
questioner for
primary research.
-11-2015 -11-2015
11 Analysis of data -11-2015 13-11-2015
12 Interview for primary
research
-11-2015 -11-2015
13 Focused group
research for primary
research.
14-11-2015 17-11-2015
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 96 of 108
14 Documentation of
mid-point submission
17-11-2015 23-11-2015
QUESTTIAIRE ANALYSIS
This questionnaire is regarding the transmission lines fault analysis and tool used in doing
so. The answers are expected for an academic project on ‘G.S.M based three phase fault
analysis with auto-reset on temporary fault or remained trip otherwise’. The answers shall
only be used for academic purpose and the identity of the interviewee shall be disclosed
only by his/her consent.
If any question is unanswerable by the participant, he/she may skip it.
PERSONAL INFORMATION
Name: …………………………………………………………………………………….
Working Place: …………………………………………………………………………...
Designation: ……………………………………………………………………………....
E mail: …………………………………………………………………………………….
TECHNICAL INFORMATION
1. The highest transmission voltage used by this substation?
a) 220Kv
b) 400Kv
c) 765Kv
ANALYSIS: highest transmission voltage used by the substation is 400Kv. In fact major of the
substation in India voltage transmission is 400Kv.
2. Which of the following factor is major concern for the substation.
a) Over-load
b) Lightning
c) Faulty equipment
d) Insulation failure
e) Short circuit current
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 97 of 108
Analysis: from the above figure it is clear that major of the fault in transmission line occur due to
overload & short-circuit 58% to be exact.
23% time fault is due to Lightning causing many type of fault like earth to ground fault and line
to line or triple line to line fault.
19% of the fault in the substation was due to faulty equipment.
3. Which fault limiting device is used in system?
a) Relay
b) Circuit breaker
c) Fuse
d) Lightning power protection device
e) If any other please specify…………………………………………………….
Analysis: when asked about which fault limiting device is used in system the answer was relay
and circuit breaker.
4. Dose the system has any device installed to detect fault?
a) Yes
b) No
Analysis: yes, system had automatic device to detect fault in this case when the fault is
encountered in the system there is a buzzer sound so that it can be restored properly.
5. Dose the system has any device installed to classify fault?
a) Yes
58% overload &short circuit
23%Lightning
10%
9%
19%faulty
equipment
Sales
1st Qtr
2nd Qtr
3rd Qtr
4th Qtr
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 98 of 108
b) No
Analysis: yes, the system was installed with device to classify fault automatically like which
type of fault it is, where it occurred, nature of fault etc.
6. Dose the system has installed any automation device to detect and classify fault
automatically?
a) Yes
b) No
Analysis: yes the system was installed with automated device to detect and classify fault.
(If answer to question 6th is ‘yes’ then please proceed.)
7. In which year the automation device was installed in the system?
……………………………………………………………………………………………
Analysis: the fault automated device was installed in the system in the year 2012. So it can be
clearly visualized that in India almost all system must have been installed with automated device
in near 2010.
8. Was the automation device installed useful?
a) Very useful
b) Useful
c) Moderately useful
d) Less useful
e) Not useful
Analysis: yes the automated device installed in the system was found to be very useful for the
operating personal.
9. What is the reach of fault protection device used in the system?
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
Analysis: the reach of the device is device into zones namely: zone 1, zone 2, zone 3, depending
upon the location of fault zone is categorized and subsequently operation is performed.
10. What is the reaction time of fault protection device to detect and classify fault?
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
Analysis: the time taken by the fault limiting device to respond is in mille seconds and either the
buzzer is alarmed and subsequent operation is performed by the relay depending upon the fault.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 99 of 108
11. Which method is used for calculation of fault?
a) DWT
b) SFCL
c) Synchronized sampling
d) Time domain using K-NN nearest neighbor algorithm
e) If any other please specify…………………………………………………….
Analysis: the operating personal do not know the technical specification of relay how it performs
and how it takes the fault, it was being said by the recipient that all calculating is done by relay
(numerical relay).
12. Dose the installed automated device send message to the operating personal when
fault encountered?
a) Yes
b) No
Analysis: major system installed in power system does not send notification.
13. Give a brief detail about installed automated device
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
Analysis: fault encountering device installed in the system are basically relay some of them are
MI com P-422, P-141, P-632, P-142
Alstom- REL 670
L&T- Sem special energy T141
All of the above mentioned are numerical relay.
14. In what ways dose the installed automated device in the system has been useful?
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
Analysis: when asked about what ways the device was useful it was mentioned that it was
because it can encounter and automatically respond to the fault.
15. Is there any possible upgradation required in system?
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 100 of 108
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
Analysis: At present operation of CBE is to be done, it is the reason why many fault are missed
by the automatic device.
(Thank you very much for sparing your precious time. The answers given are of great
value for this project. It is assured that the answers given here shall be used only for
academic purpose and following all the ethical rights of participants.)
For question number 11
SFCL-symmetrical coordinate method
DWT-discreet wavelet transform.
K-NN (nearest neighbor) algorithm
Interview question analysis:
The interview was conducted by the operating personal at BBMB Hariender Kumar Deshwal
posted in executive engineering post.
Below are the question that was asked by the interviewer along with the analysis based on
answer:
Video has been include in the C.D attached with the document.
Technical question
1. Why fault detection & classification is important in power system?
Analysis : when asked it was responded with a very simple but obvious answer i.e.
that knowing the fact that major of the fault occur in power system in transmission
line nearly 80%~ it should be a continuous running process to get the continuous
supply and keep the power system running .
2. What is the approach of operating personal find there is fault in the system?
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 101 of 108
Analysis: whenever there is any fault in the system the device gives the alarm and the
person checks the fault and trips the connection & later some person is send to operate
the faulty area or to restore it.
3. What better method could be used to improve fault detection & classification?
4. Why automated device has upper hand than manual calculation?
Analysis: in case of automated device chances of error are less as it is done by the
computer program so computer takes the value up to decimal place living less space
for error while when human operate chances of error are more. Response time is less
for the computer case.
5. Which is the more conventional way of calculating fault?
Analysis: substation has nothing to do with the fault current they do not calculate
the fault current only prime focus is to restore the faulty equipment as soon as
possible.
6. What are your views on automated fault detection & classification installed in
system?
Analysis: numerical relay perform an extra vital role in maintaining the power
system error free so that it can run smoothly, there are various numerical relay
available.
7. Could you please share what are the problem faced while handling fault scenario?
Analysis: common error faced is that as it is substation there are various line and
fault may occur at any line making it difficult to classify so major problem is to
classify in which section the fault occurred as there are many relay (numerical )
installed depending upon the zone type.
8. Are you satisfied with fault detection & classification device installed in system?
Analysis: yes the operating personal was satisfied with the fault limiting device.
9. How does the operating personal (if manual) or computer detect which type of fault
it is?
Analysis: all fault are scenario are dealt by numerical relay and the substation has
nothing to do with fault current calculation.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 102 of 108
10. In which season dose the fault occur the most?
Analysis: most fault cases are encountered in the winter season as because of corona
effect major fault occur in the system ionized by the charge particle present in the air.
11. Which was the most severe fault encountered by this substation in near past?
Analysis: recent fault encountered by the system was due to the human error as some
person taped the wire cause of short circuit it worked for a while and later it again
burnet causing more problem had the case been dealt the very time with serious
intension serious fault could not have encountered.
12. BBMB dose provide supply to Indian railway which is traction in nature if fault
occur in that line how it is resolved?
Analysis: there is separate section for the railway line as it traction is nature had
the same line given to the public commercial line it would provide a uneven load.
13. What is the approach when multiple fault is encountered in the system?
Analysis: when multiple fault is encountered by the system numerical relay take
care of it by dealing with the zone case if the first fault is in zone 1 it clears the fault
and the remaining fault is dealt by zone 2 & zone 3.
14. In a recent report published it has been mentioned that BBMB has replaced
Porcelain insulators with Polymers insulators why it is done so?
Analysis: reason behind the replacement was because porcelain insulator punchers
to quickly while
15. After what interval of time all fault detection devices are tested?
Analysis: all fault detection device is tested once every four month and is
mandatory check.
16. Is there any auxiliary fault detection tool when the primary one fails?
Analysis: yes there is auxiliary device installed in case the primary device fails.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 103 of 108
Appendix B
Transmission line in power system model in Simulink is represented by distributed parameters
line. It implements an N-phases distributed parameter line model. The R, L, and C line parameters
are specified by [N x N] matrices. Resistance presented by: resistance per unit length (Ohms/km)
with [N x N matrix] - [0.01273 0.3864].
Inductance presented by: inductance per unit length (H/km) with [N x N matrix] - [0.9337e-3
4.1264e-3]. Capacitance presented by: capacitance per unit length (F/km) with [N x N matrix] -
[12.74e-9 7.751e-9]. Three-phase transformer model in Simulink was built by specifying
parameters for winding 1 and winding 2, and also magnetization characteristics which are the
following:
Winding 1 parameters [V1 Ph-Ph(Vrms), R1(pu), L1(pu)]: [735e3, 0.15/30/2, 0.15*0.7].
Winding 2 parameters [V2 Ph-Ph(Vrms), R2(pu), L2(pu)]: [ 16e3, 0.15/30/2, 0.15*0.3].
Magnetization resistance Rm (pu): 500; magnetization inductance Lm (pu): 500.
AC voltage source model in Simulink was presented by three-phase ideal sinusoidal voltage source
With amplitude.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 104 of 108
APPENDIX C: HEATH SAFETY AND ETHICAL ASSESSMENT
Risk Area: Implementation
Soldering Iron Burn
Burning of Components
Risk Area: Fabrication
Itching of PCB
Risk Area: testing
Electric Shock
There are several risks involved in the proposed project ‘G.S.M based three phase fault analysis
with auto reset on transient fault or remain tripped otherwise ‘which were mentioned in the risk
assessment form which is attached in the appendices section of the document along with the level
of risk involved.
Risk area: Implementation
In the implementation phase there are two types of risks involved for the researcher himself while
implementing the hardware design.
Soldering Iron Burn
Soldering process is used to connect the components on PCB on the traces provided. It is done to
make the two wires short and connect them with each other. While doing the soldering of
components on the PCB, the researcher may encounter the soldering iron burn if the soldering iron
is not handled with care or if the hot part of the soldering iron is touched with bare hands. This
process may lead to minor injury to the researcher, so it is recommended to carefully do the
soldering of the components.
Burning of Components
The component such as transformer can burn any time if proper connection is not done to the
transformer resulting in damaging the transformer and other component as well.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 105 of 108
If two wire are connected to terminal then it might result in short circuiting and burning of
equipment.
Risk Area: Fabrication
Itching of PCB
In the fabrication process, the risk involved is in the Itching of PCB. PCB itching involves the
contact with the Ferric Chloride Acid at to draw the layout on the copper PCB, it should be kept
dipped in the solution for about 4-5 hours. When the layout is complete the PCB should be taken
out from the solution and unwanted copper should be removed from the PCB. Sometimes this
solution may burn the skin of the researcher and may lead to minor injury. This injury is caused
when the hand comes in direct contact with the chemical. It is recommended to use gloves while
inserting and removing the PCB from the chemical so that the injury can be minimized up to some
extent.
Electric Shock
All the components mainly used to in the circuit operates either at 12 V or at 5 V but the AC which
is supplied to the circuit is 230 V. it should be firstly converted to 12 volts using step down
transformer and then using voltage regulator it is converted to 5V. But there are electric shock
hazard if the ac is directly touched with bare hands or somewhere the contact is developed with
direct AC supply. The electric shock may occur sue to this direct AC supply so it is recommended
to use gloves while connecting AC and not to touch it with bare hands or feet.
But the risks involved in the project are minor risks and can be adequately controlled if necessary
measures are taken. The level of risks is described in the risk assessment form which is attached
in the appendices section. There are no serious health issues involved in the project so the
researcher is performing it as per ethical guidelines.
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 106 of 108
APPENDIX D: USER MANUAL
A user guide or user's guide, also commonly known as a manual, is a technical communication
document intended to give assistance to people using a particular system
Since this is a three phase analysis so electrical lab is required to provide the hardware three phase
source through which analysis will be done.
The hardware has to be powered from three phase source, if given single phase or DC input
hardware will not work.
Figure 63: Powering hardware from three phase source
When push button will be pressed which is connected across relay it disconnects that relay
and in the process in common contacts moves to the NC position to provide a logic low at
trigger pin of 555 timer to develop an output that brings the U3 555 timer which is used in
astable mode for its reset pin to high such that the astable operation takes place at its output
which is also indicated by flashing D11 LED. Pushing the switch for a long time will trip
the circuit permanently
G.S.M Based Three Phase Fault Analysis with Auto Reset
FYP-2016 PT1284410 Page 107 of 108
If the fault is off temporary in nature i.e. if the push button pressed is released immediately
the U1 monostable disables U3 the output of which goes to zero in the event of any push
button kept pressed for a longer duration the monostable output provides a longer duration
active situation for U3 the astable timer the output of which charges capacitor C13 through
R11 such that the output of the comparator goes high that drives the relay to switch off
three phase load.
If system encounter any type of fault LED Will glow weather it is line to ground or line to
line depending upon the push button being pushed for longer duration.