grid connection of wind farms - mpoller
TRANSCRIPT
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Grid Connection of Wind FarmsMarkus Pöller and Oscar Amaya/DIgSILENT GmbH
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Grid Connection
• Impact on thermal loading of lines/transformers• Impact on voltage during normal operation• Short circuit currents• Power Quality Aspects
– Voltage dips because of WTG switching
– Voltage dips because of transformer inrush– Continuous Flicker
– Harmonics
• Behaviour during grid faults/Fault ride through requirements
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Impact on Thermal Loading
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Options for network connection
HV
MV
AB
C
A Distributed/Embedded
B MV Substation
C HV Substation
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Impact on Thermal Loading of Lines/Transformers
• Additionally required transmission lines must be planned based on well defined scenarios, considering size and location of planned wind farms.
• Load flow studies required for combinations of:– Load level (High-/Low-load)
– Wind speed level (High-/Medium-/Low wind)
• For avoiding investments in new transmission lines which are only required for a few hours per year, probabilities should be assigned to the studied cases.
• Assessment of potential of dynamic line rating recommended because of the good correlation of transmission line capacity and wind speed.
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Impact on Thermal Limits – Example
To DROERIVIER
Voltage Levels
400, kV220, kV132, kV66, kV33, kV
Wind Park
150 MW
Continued onBacchus 132kV diagram
BOSKLOOF 1
BOSKLOOF 2
LAINGSBURG
LAIN132 WF
LAIN0.69 WF
LAIN33 WF
LAIN132B1
LADIS13
WELTV1_2
SWART22
SWART1
BUFPT22
WELTV1_1
BUFPT1
QUARY1_2
QUARY1_1
PIETM1_2
BAVIANSK
BANTM2_2
BANTM1_1
WHITH1_2
WHITH1_1
BAVIN1_2
LEEUG22
BAVIN1_1
LEEUG1_2
LEEUG1_1
PIETM1_1
GEELBEK
GEELB1_2
GEELB1_1
RUITK1_2
RUITK1_1
ANTJIESKKOUP
LAIN132B2
KOUP1_2
KOUP1_1
GEMSB1_2
GEMSB1_1
BANTAM
ANTJK1_2
ANTJK1_1
BOTES_2
BOTES_1
Laingsburg WF
LAIN
WF
Tr
1LA
IN W
F T
r 2
2181
WO
LF12
,41
2181WOLF9,40
lod_
7089
2..
Ladismith
M1311CH28,11
2161WOLF6,12
WP51WOLF6,00
2161
WO
LF14
,45
lod_72962_1 lod_72932_1
trf_
7068
2..
lod_70686_1
lod_72852_1
lod_70732_1
lod_
7096
2_1
lod_70922_1
lod_
7089
2_1
lod_70842_1 lod_70762_1
2181WOLF12,93
2181WOLF12,93
2181WOLF11,05
lod_70682_1
2181WOLF11,05
2181WOLF13,16
2181WOLF13,16
2181WOLF9,64
2181
WO
LF9,
40
2181WOLF9,64
2181WOLF14,20
2181WOLF14,20
2181WOLF24,09
2181WOLF24,09
2181WOLF21,81
2181WOLF21,81
lod_
7280
2_1
2181
WO
LF12
,40
lod_
7288
2_1
2181WOLF9,96
2181
WO
LF11
,45
2181
WO
LF11
,45
2181
WO
LF2,
08
2181
WO
LF3,
87
2181
WO
LF0,
51
2181WOLF74,80
WP
51W
OLF
14,4
5
2181
WO
LF2,
63
2181
WO
LF2,
07
2181WOLF11,41
2181WOLF11,41
2181WOLF9,96
2181WOLF22,49
2181WOLF22,49
2181WOLF11,17
2181WOLF11,17
lod_74006_1lod_73006_1
trf_
7400
2..
trf_
7300
2..
2181WOLF74,80
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Impact on Thermal Limits – Example
Wind Park
150 MW
To DROERIVIER
Continued onBacchus 132kV diagram
BOSKLOOF 1
BOSKLOOF 2
LAINGSBURG
LAIN132 WF
LAIN0.69 WF
LAIN33 WF
LAIN132B1
LADIS13
SWART22
SWART1
BUFPT22
BUFPT1
QUARY1_2
QUARY1_1
PIETM1_2 BANTM2_2
BANTM1_1
WHITH1_2
WHITH1_1
BAVIN1_2
BAVIN1_1PIETM1_1
GEELB1_2
GEELB1_1
RUITK1_2
RUITK1_1
LAIN132B2
KOUP1_2
KOUP1_1
GEMSB1_2
GEMSB1_1
ANTJK1_2
ANTJK1_1
BOTES_2
BOTES_1
180,
00 M
VA
86,0
1 %
2,50
MV
A81
,36
%
2181
WO
LF
12,4
1 km
0,00
%
2181WOLF 9,40 km31,04 %
Ladismith
M1311CH 28,11 km7,06 %
2161WOLF 6,12 km14,59 %
WP51WOLF 6,00 km14,48 %
2161
WO
LF
14,4
5 km
15,9
7 %
lod_72962_1 lod_72932_1
lod_72852_1
lod_70922_1 lod_70842_1
2181WOLF 12,93 km20,17 %
2181WOLF 12,93 km22,62 %
2181WOLF 11,05 km19,67 %
2181WOLF 11,05 km20,68 %
2181WOLF 13,16 km18,27 %
2181WOLF 13,16 km20,32 %
2181WOLF 9,64 km17,76 %
2181
WO
LF
9,40
km
31,0
4 %
2181WOLF 9,64 km17,88 %
2181WOLF 14,20 km17,12 %
2181WOLF 14,20 km17,53 %
2181WOLF 24,09 km16,59 %
2181WOLF 24,09 km16,33 %
2181
WO
LF
12,4
0 km
120,
99 %
2181WOLF 9,96 km115,69 %
2181
WO
LF
11,4
5 km
20,8
3 %
2181
WO
LF
11,4
5 km
22,9
7 %
2181
WO
LF
2,08
km
0,95
%
2181
WO
LF
3,87
km
1,37
%
2181
WO
LF
0,51
km
0,39
%
2181WOLF 74,80 km0,00 %
WP
51W
OLF
14
,45
km15
,72
%
2181
WO
LF
2,63
km
6,05
%
2181
WO
LF
2,07
km
3,36
%
2181WOLF 11,41 km0,00 %
2181WOLF 11,41 km112,44 %
2181WOLF 9,96 km0,00 %
2181WOLF 22,49 km111,37 %
2181WOLF 22,49 km0,00 %
2181WOLF 11,17 km115,48 %
2181WOLF 11,17 km0,00 %
10,0
0 M
VA
60,6
8 %
10,0
0 M
VA
14,0
0 %
2181WOLF 74,80 km110,86 %
• 120% overload off
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Impact on Thermal Limits - Example
General mitigation options if thermal limits are ex ceeded:
• Build a new line
• Limit wind farm output to 80% during all times (80% of rated output)
• Limit wind farm output in case of actual line failure (manual or automatic inter-trip).
• Consider dynamic line rating systems.
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Violation of Thermal Limits – Cap Wind Farm Output
0,500 1,500 2,500 3,500 4,500 5,500 6,500 7,500 8,500 9,500 10,50 11,50 12,50 13,50 14,50 15,50 16,50 17,50 18,50 19,50 20,50
12,50
10,00
7,50
5,00
2,50
-2,50
0,000
x-Axis: Windpark Analysis: Wind Speed in m/sWindpark Analysis: Probability in %
100,0380,0360,0340,0320,030,03
160,00
120,00
80,00
40,00
0,00
-40,00
x-Axis: Windpark Analysis: Cummulative Probability in %Windpark Analysis: Generated Power in MW
Y =120,000 MW16.624 %
DIGSILENT High Load Plots
Voltage at Laingsburg Wind Farm Connection Point PV-Curve
Date: 7/23/2009
Annex: 1 /3
DIg
SIL
EN
T
1454 h/year
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Violation of Thermal Limits – Cap Wind Farm Output
Not Delivered Energy depends on:• Wind conditions (average wind speed)• Site-specific aspects• Power curve of turbines
Rough cost estimates (example):• vw=7m/s:
– Energy not delivered around 5% of potential energy– 150 MW wind-farm: 19 000MWh not delivered -> 23 750 000 R/year
• vw=8m/s: – Energy not delivered around 7,5% of potential energy– 150 MW wind-farm: 37 000 MWh not delivered -> 46 250 000 R/year
• Must be compared to annualized costs of required line upgrade
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Violation of Thermal Limits – Cap Wind Farm Output u nder Contingency Situations
More cost effective solution:
• Limitation of wind farm output only in situations in which one circuit is available (planned outage, unplanned outage)
• In case of minor overloads (below emergency rating): – Manual action of system operator
• In case of major overloads (above emergency rating):– Automatic inter-trip scheme
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Dynamic Line Rating - Potential
• Thermal loading of overhead lines depends on:– Ambient temperature
– Wind speed -> correlation with wind generation
• Wind-generators:– cut-in wind-speed: 2.5...4m/s, rated: 12...16m/s– But: height, environment etc. must be considered too!
Ambient Temperature
Line Rating expressed in MVA at 66 kV*
Wind Speed = 0.5 m/s Wind Speed = 3.0 m/s Wind Speed = 5.0 m/s
30 ºC 22.6 39.9 49.5
35 ºC 16.5 32.9 41.5
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Impact on Voltage Variations
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Voltage Variations
• Distribution Grids: Considerable voltage variations for varying MW because of low X/R ratios (large R)
• Transmission Grids: Substantially less voltage variations for varying MW becaus of high X/R ratios (low R). Contingency cases are more relevant.
• Mitigation Options: – Q(P)-Characteristic (open-loop voltage compensation)
– Voltage control (voltage feed-back)
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Voltage Variations - Procedure
• Step 1 - System Operator: Identify required reactive power range at connection point
• Step 2 – Wind farm planner: Design the reactive power capability for complying with reactive capability requirements.
- Step 1 might be defined by a general Grid Code requirement -
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Example 1: Connection to Distribution/Subtransmission Gri d
To DROERIVIER
Voltage Levels
400, kV220, kV132, kV66, kV33, kV
Wind Park
150 MW
Continued onBacchus 132kV diagram
BOSKLOOF 1
BOSKLOOF 2
LAINGSBURG
LAIN132 WF
LAIN0.69 WF
LAIN33 WF
LAIN132B1
LADIS13
WELTV1_2
SWART22
SWART1
BUFPT22
WELTV1_1
BUFPT1
QUARY1_2
QUARY1_1
PIETM1_2
BAVIANSK
BANTM2_2
BANTM1_1
WHITH1_2
WHITH1_1
BAVIN1_2
LEEUG22
BAVIN1_1
LEEUG1_2
LEEUG1_1
PIETM1_1
GEELBEK
GEELB1_2
GEELB1_1
RUITK1_2
RUITK1_1
ANTJIESKKOUP
LAIN132B2
KOUP1_2
KOUP1_1
GEMSB1_2
GEMSB1_1
BANTAM
ANTJK1_2
ANTJK1_1
BOTES_2
BOTES_1
Laingsburg WF
LAIN
WF
Tr
1LA
IN W
F T
r 2
2181
WO
LF12
,41
2181WOLF9,40
lod_
7089
2..
Ladismith
M1311CH28,11
2161WOLF6,12
WP51WOLF6,00
2161
WO
LF14
,45
lod_72962_1 lod_72932_1
trf_
7068
2..
lod_70686_1
lod_72852_1
lod_70732_1
lod_
7096
2_1
lod_70922_1
lod_
7089
2_1
lod_70842_1 lod_70762_1
2181WOLF12,93
2181WOLF12,93
2181WOLF11,05
lod_70682_1
2181WOLF11,05
2181WOLF13,16
2181WOLF13,16
2181WOLF9,64
2181
WO
LF9,
40
2181WOLF9,64
2181WOLF14,20
2181WOLF14,20
2181WOLF24,09
2181WOLF24,09
2181WOLF21,81
2181WOLF21,81
lod_
7280
2_1
2181
WO
LF12
,40
lod_
7288
2_1
2181WOLF9,96
2181
WO
LF11
,45
2181
WO
LF11
,45
2181
WO
LF2,
08
2181
WO
LF3,
87
2181
WO
LF0,
51
2181WOLF74,80
WP
51W
OLF
14,4
5
2181
WO
LF2,
63
2181
WO
LF2,
07
2181WOLF11,41
2181WOLF11,41
2181WOLF9,96
2181WOLF22,49
2181WOLF22,49
2181WOLF11,17
2181WOLF11,17
lod_74006_1lod_73006_1
trf_
7400
2..
trf_
7300
2..
2181WOLF74,80
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Voltage Variations/Step 1 – Example 1: cosphi constant (= 1)
207,50167,50127,5087,5047,507,50
1,08
1,05
1,02
0,99
0,96
0,93
x-Axis: Laingsburg WF: Active Power in MWLAIN132 WF: Voltage in p.u. - Base CaseLAIN132 WF: Voltage in p.u. - Lain132kV_Laingsburg_OffLAIN132 WF: Voltage in p.u. - Laingsburg_Boskloof_OffLAIN132 WF: Voltage in p.u. - Laingsburg_Droerivier_Off
Y = 1,050 p.u.47.697 MW58.375 MW
66.198 MW
X =150,000 MW
1.065 p.u.
1.070 p.u. 1.074 p.u.
1.050 p.u.
136.500 MW 1.074 p.u.
DIGSILENT High Load Voltage
Voltage at Laingsburg Wind Farm Connection Point PV-Curve
Date: 7/24/2009
Annex: 1 /2
DIg
SIL
EN
T
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Voltage Variations/Step 1 – Example 1:cosphi(P)-characteristic
200,00160,00120,0080,0040,000,00
1,075
1,050
1,025
1,000
0,975
0,950
x-Axis: Laingsburg WF: Active Power in MWLAIN132 WF: Voltage in p.u. - Base CaseLAIN132 WF: Voltage in p.u. - Lain132kV_Laingsburg_OffLAIN132 WF: Voltage in p.u. - Laingsburg_Boskloof_OffLAIN132 WF: Voltage in p.u. - Laingsburg_Droerivier_Off
Y = 1,050 p.u.
X =150,000 MW
1.037 p.u. 1.038 p.u. 1.044 p.u.
1.050 p.u.
DIGSILENT High Load Voltage
Voltage at Laingsburg Wind Farm Connection Point PV-Curve - cosphi(P)-characteristic
Date: 7/24/2009
Annex: 1 /2
DIg
SIL
EN
T
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Voltage Variations- Example 1: Summary
• High voltages in case of cos(phi)=1
• Small voltage variations if cos(phi) adjusted to actually generated power (absorbing vars for compensating increasing voltage)
• Voltage control (with voltage feed-back) at wind farm connection point is possible but not required in this particular case because:– Only small voltage steps in case of contingencies– Only small voltage variations in case of different operational scenarios
(high/low load)– No voltage stability issue
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Example 2: Large Wind Farms at Transmission Level
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Voltage vs. Reactive Power – Voltage Stability
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Voltage Variations- Example 2: Summary
• Small Voltage Variations in function of active power variations (large X/R ratios)
• High Voltage Variations in case of critical contingencies
• Voltage control (with voltage feed-back) at wind farm connection point is required for maintaining voltage stability
• Required reactive power range can be determined by analyzing QV-curves
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Voltage Variations/Step 2 – Wind Farm Design
• Wind farm design must consider reactive power requirements.
• Reactive power capability at grid connection point is limited by:– Reactive power capability of wind turbine generators (WTGs)– Thermal ratings of cables in the wind farm collector system.
– Voltage variations at the LV-nodes (voltage range of operation of WTGs)
• Requirement for additional reactive power compensation devices (STATCOM, switched shunts) must be taken based on:– Required reactive power capability– Required dynamic performance of voltage/reactive power control.
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Reactive Power – Voltage Control
p
q
power factor limit
q
const var limit (recommended)
cos(phi)=0,95cos(phi)=0,95
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Voltage Variations - Wind Farm Design
• Wind farm design must consider grid requirements
• Reactive power capability at grid connection point is limited by:– Reactive power capability of wind turbine generators (WTGs)
– Thermal ratings of cables in the wind farm collector system.– Voltage variations at the LV-nodes (voltage range of operation of WTGs)
• Requirement for additional reactive power compensation devices (STATCOM, switched shunts) must be taken based on:– Required reactive power capability
– Required dynamic performance of voltage/reactive power control.
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Voltage Variations – Wind Farm Planning Studies
DIGSILENT
PowerFactory 14.0.513
Windfarm Red Sunset
CFE/GTZ/DIgSILENT
Project: Example
Graphic: Red Sunset
Date: 7/27/2009
Annex:
/115 kV
/20 kV
Windpark Analysis
PVUset=1,12
Tr
Tra
fo-T
yp
0
Shunt/Filter max. no.: 3 act. no.: 3 7,00 Mvar
3
Line
(4)
N
2XS
2Y 1
x..
0,80
km
Line
(3)
N
2XS
2Y 1
x..
1,00
km
WTG 13
WTG 5
WTG 12
WTG 11
WTG 10
WTG 4
WTG 3
WTG 2
WTG 1
WTG 14
WTG 15
WTG 16
WTG 6
WTG 7
WTG 8
S4 NA2XS(F)2Y 1x185RM 12/20kV ir
1,00 km
S3 NA2XS(F)2Y 1x185RM 12/20kV ir
1,00 km
S2 NA2XS(F)2Y 1x185RM 12/20kV ir
1,00 km
S1
N
A2X
S(F
)2Y
1x1
85R
M 1
2/20
kV ir
2,
00 k
m
S13
N
A2X
S(F
)2Y
1x1
85R
M 1
2/20
kV ir
0,
80 k
m
S14 NA2XS(F)2Y 1x185RM 12/20kV ir
0,80 km
S15 NA2XS(F)2Y 1x185RM 12/20kV ir
0,80 km
S16 NA2XS(F)2Y 1x185RM 12/20kV ir
0,80 km
S5
N
A2X
S(F
)2Y
1x1
85R
M 1
2/20
kV ir
2,
50 k
m
S6 NA2XS(F)2Y 1x185RM 12/20kV ir
0,80 km
S7 NA2XS(F)2Y 1x185RM 12/20kV ir
0,80 km
S8 NA2XS(F)2Y 1x185RM 12/20kV ir
0,80 km
S12 NA2XS(F)2Y 1x185RM 12/20kV ir
0,80 km
S11 NA2XS(F)2Y 1x185RM 12/20kV ir
0,80 km
S9 NA2XS(F)2Y 1x185RM 12/20kV ir
1,60 km
Tr1
0LV
-Trf
0
Tr5
LV-T
rf0
Tr6
LV-T
rf
0
Tr7
LV-T
rf
0
Tr8
LV-T
rf
0
Tr4
LV-T
rf
0
Tr3
LV-T
rf
0T
r13
LV-T
rf
0
Tr1
4LV
-Trf
0
Tr1
5LV
-Trf
0
Tr1
6LV
-Trf
0
Tr1
2LV
-Trf
0
Tr1
1LV
-Trf
0
Tr2
LV-T
rf
0
Tr1
LV-T
rf
0
DIg
SIL
EN
T
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Voltage Variations – Wind Farm Design Studies
-5
0
5
10
15
20
25
30
35
40
45
50
-30 -20 -10 0 10 20 30
P [MW]
Q [Mvar]
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Short Circuit Contribution
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Short Circuit Contribution of Wind Farms
• Calculation of max. short circuit currents:
– Impact on short circuit ratings of existing components (substations, CB-ratings, cable-/line ratings, transformers etc.)
– Impact on new components, inside the wind farm
• Calculation of min. short circuit currents:
– Verification of protection settings
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Short Circuit Contribution of Wind Farms
0,300,200,100,00-0,10 [s]
0,30
0,20
0,10
0,00
-0,10
-0,20
-0,30
Tr2: Phase Current A/HV-Side in p.u.Tr2: Phase Current B/HV-Side in p.u.Tr2: Phase Current C/HV-Side in p.u.
Fault Clearedip
DIg
SIL
EN
T
Fault Current of DFIG with Crow-bar protection
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Short Circuit Contribution - Modelling
• DFIG and WTGs with fully rated converter are devices with controlled currents.
• DFIG is usually equipped with protection mechanisms (Crow-bar, Chopper), which make short circuit behavior highly non-linear.
• Difficult to model for steady state short circuit analysis, which is typically based on Thevenin-equivalents.
• No special consideration of WTGs given in IEC 60909.
• Proposed approach:– „Equivalent Synchronous generator“ approach: Characterizing WTG short
circuit currents by subtransient and transient parameters.– Approach suitable for planning studies but not for highly accurate studies.
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Power Quality
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Power Quality
• Impact on Flicker– Continuous flicker– Flicker following switching actions (WTGs, Inrush)
• Impact on Harmonics– Harmonic injections
– Impact on harmonic impedance
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Continuous Flicker
Caused by
• Turbulences
• “Rotational sampling”:turbulence variation across the rotor
• Tower Shadow
• Torsional oscillation
Applicable Standards:
• IEC 61000-3-6, IEC 61400-21
Mexican Grid Code: Pst<0,35Plt<0,25
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Continuous Flicker - Example
70.60656.46542.32328.18214.041-0.1000 [s]
4.00
2.00
-0.00
-2.00
-4.00
-6.00
Rotor-Turbulence: vt0
70.60656.46542.32328.18214.041-0.1000 [s]
-3.20
-3.60
-4.00
-4.40
-4.80
-5.20
T3WT1: Total Active Power/HV-Side in MW
6.255.003.752.501.250.00 [Hz]0.001
0.01
0.1
1
10
100
T3WT1: Total Active Power/HV-Side, Magnitude in MW
DIgSILENT Turbulence, Electrical Power and Spectrum of a 5MW Variable Speed Turbine Plots(3)
V0=13.6 m/s
Date: 10/5/2003
Annex: /1
DIg
SIL
EN
T
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Flicker due to Switching Actions
• WTGs automatically synchronize to the grid if vw>vcutin
• Variable speed WTGs: Very smooth synchronisation• Fixed speed WTGs: Considerable voltage dip. Mitigation: soft cut-in
• Wind farm energization causes more considerable voltage dips:– Switching of WTG step-up transformers
– Switching of main transformer– > only during wind farm energization, not repeting events.
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Switching of Fixed Speed Induction Generator
ASM
Typical start-up procedure
• Turbine pulls up the rotor to0.9 ..1.1 nnominal
• Breaker is closed
V0
Z’’n
X’’
IG’’ • Approximate Formula
''''''
n
rGiGn
S
SkIZu ==∆
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Switching
0.200.150.100.05-0.00-0.05 [s]
1.025
1.000
0.975
0.950
0.925
0.900
0.875
415V Machines: Voltage Phasor, Magnitude in p.u.
0.200.150.100.05-0.00-0.05 [s]
6000.00
4000.00
2000.00
0.00
-2000.00
-4000.00
-6000.00
WG 315kW: Phase Current A in AWG 315kW: Phase Current B in AWG 315kW: Phase Current C in A
0.200.150.100.05-0.00-0.05 [s]
1.003
1.000
0.997
0.994
0.991
0.988
WG 315kW: Speed
0.200.150.100.05-0.00-0.05 [s]
0.90
0.60
0.30
-0.00
-0.30
-0.60
-0.90
415V Machines: Line-Line Phase Voltage A in kV415V Machines: Line-Line Phase Voltage B in kV415V Machines: Line-Line Phase Voltage C in kV
DIgSILENT Wind Power Integration Training WG
Asm cut-In, directly on line EMT-simulation
Date: 10/5/2003
Annex: 1 /1
DIg
SIL
EN
T
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
With Soft Cut-In
0.210.170.130.090.05 [s]
0.90
0.60
0.30
-0.00
-0.30
-0.60
-0.90
415V Machines: Line-Line Phase Voltage A in kV415V Machines: Line-Line Phase Voltage B in kV415V Machines: Line-Line Phase Voltage C in kV
0.210.170.130.090.05 [s]
1.0250
0.995
0.965
0.935
0.905
0.875
415V Machines: Voltage Phasor, Magnitude in p.u.
0.210.170.130.090.05 [s]
1.0100
1.0040
0.998
0.992
0.986
0.980
Motor 315kW: Speed
0.210.170.130.090.05 [s]
200.00
100.00
0.00
-100.00
-200.00
Motor 315kW: Phase Current A in AMotor 315kW: Phase Current B in AMotor 315kW: Phase Current C in A
DIgSILENT Wind Power Integration Seminar Motor
Soft cut-in
Date: 10/5/2003
Annex: 1 /1
DIg
SIL
EN
T
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Switching of Variable Wind Generators
DASM
1
2
SynM
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Connection of Variable Speed WTG
0.060.040.02-0.00 [s]
0.20
0.10
0.00
-0.10
-0.20
PWM Grid Side: Current, d-Axis in p.u.PWM Grid Side: d-Axis Current Reference in p.u.
0.060.040.02-0.00 [s]
1.025
1.000
0.975
0.950
0.925
0.900
Point of Interconnection: Voltage Phasor, Magnitude in p.u.
0.060.040.02-0.00 [s]
0.04
0.02
0.00
-0.02
-0.04
2-Winding Transformer: Phase Current A/HV-Side in kA2-Winding Transformer: Phase Current B/HV-Side in kA2-Winding Transformer: Phase Current C/HV-Side in kA
DIgSILENT Wind Power Training Plots
Cut-In of Variable Converter driven synchronous machine
Date: 10/5/2003
Annex: 1 /3
DIg
SIL
EN
T
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Connection of Variable Speed WTG
0.060.040.02-0.00 [s]
0.20
0.10
0.00
-0.10
-0.20
PWM Grid Side: Current, d-Axis in p.u.PWM Grid Side: d-Axis Current Reference in p.u.
0.060.040.02-0.00 [s]
1.025
1.000
0.975
0.950
0.925
0.900
Point of Interconnection: Voltage Phasor, Magnitude in p.u.
0.060.040.02-0.00 [s]
0.04
0.02
0.00
-0.02
-0.04
2-Winding Transformer: Phase Current A/HV-Side in kA2-Winding Transformer: Phase Current B/HV-Side in kA2-Winding Transformer: Phase Current C/HV-Side in kA
DIgSILENT Wind Power Training Plots
Cut-In of Variable Converter driven synchronous machine
Date: 10/5/2003
Annex: 1 /3
DIg
SIL
EN
T
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Harmonic injections caused by:
• Power electronics converters
• modern PWM converters produce high order harmonics
• Saturation effects (Generator, Transformer)
Inter-Harmonic injections caused by:
• PWM with switching frequency different from multiples of networkfrequency
Effect
• Voltage distortion depending on network impedance
• Resonance problems
Standards: IEC 61000-3-7, IEC 61400-21
Harmonic and Inter-Harmonic Injections
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Self Commutated Converter
Udc Uac
ACUDCU
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Self Commutated PWM Converter
0.080.060.040.02-0.00 [s]
0.20
0.10
0.00
-0.10
-0.20
2-Winding Transformer: Phase Current A/HV-Side in kA
6400.5120.3840.2560.1280.0.00 [Hz]
0.15
0.12
0.09
0.06
0.03
0.00
2-Winding Transformer: Phase Current A/HV-Side, Magnitude in kA
900.000 Hz 0.004 kA
1100.000 Hz 0.003 kA
1950.000 Hz 0.004 kA
2050.000 Hz 0.004 kA
DIgSILENT Wind Power Training Currents
PWM-converter
Date: 10/5/2003
Annex: 1 /4
DIg
SIL
EN
T
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Impact on Harmonic Impedance
• Voltage source converters:– define a path via the coupling reactance to earth for high frequency
harmonics.
– At low frequency harmonics: Controller transfer function needs to be considered too.
• Effect: – Shift of resonance frequencies (towards higher order).
– Increased harmonic damping
• Cable capacitance of wind farm-internal cables.• Effect:
– Shift of resonance frequencies (towards lower order)
– Amplification of harmonic background distortion.
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Impact on Flicker and Harmonics - Summary
• Analysis of Flicker and Harmonics using IEC 61400-21 data sheet of a typical variable-speed wind generator.
• Flicker generally low in case of large wind farms because Flicker-relevant turbulences within a wind farm are only weekly correlated
• Harmonics of modern wind turbines (with IGBT-converters) very low. Almost no harmonic current injections.
• WTGs can have a positive influence on harmonic impedance characteristics (improved damping, increased resonance frequencies)
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Behaviour During Grid Faults – FRT Requirements
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Example: Converter Driven Synchronous Genenrator
0.600.400.200.00 [s]
60.00
40.00
20.00
0.00
-20.00
Cub_1\PCC PQ: Active Power in p.u.Cub_1\PCC PQ: Reactive Power in p.u.
0.600.400.200.00 [s]
1.20
1.00
0.80
0.60
0.40
0.20
HV: Voltage, Magnitude in p.u.MV BusBar: Voltage, Magnitude in p.u.
0.600.400.200.00 [s]
1.15
1.10
1.05
1.00
0.95
0.90
Generator: speed
DIg
SIL
EN
T
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
FRT Requirements: Summary
Basic FRT-Requirements:
• WTGs must not disconnect in case of voltage dips
• WTGs must deliver active power shortly after a voltage dip
Advanced FRT-Requirements:
• WTGs must inject reactive current during a fault (voltage support, protection excitation)
• WTGs must not absorb reactive power during voltage recovery
GTZ-TERNA Expert Workshop 2009: Grid and System Integration of Wind Energy, 10.11.2009-12.11.2009, Berlin/Germany
Thank You
Markus Pöller Oscar Amay
[email protected] [email protected]
DIgSILENT GmbH
Heinrich-Hertz-Str. 9
72810 Gomaringen
www.digsilent.de