Gravity Pipeline Outreach Meeting
March 22, 2017
Regional Environmental
Sewer Conveyance Upgrade
![Page 2: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/2.jpg)
Agenda
• Introduction (Teresa)
• Gravity Pipeline Project – Overview (Bruce)
• Procurement Process and Stages (Teresa)
• Key Parts of the RFQ (Bruce)
• Estimates, Budgets and Pricing (Teresa)
• Early Focus Areas (Stage 1) (Bruce)
• Available Information (Teresa)
• Questions (Please ask anytime)
![Page 3: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/3.jpg)
Gravity Pipeline Project – Overview
• Background
• Virtual tour of alignment and shafts
– Horizontal
– Vertical
• Hydraulics
– Diurnal and Seasonal Equalization
• Status of EIR, Permits and Easements
• Availability of SVCW Funding
![Page 4: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/4.jpg)
WEST BAY SANITARY DISTRICT
SAN CARLOS
BELMONT
MENLO PARK
WOODSIDE
EMERALD HILLS
REDWOOD CITY
![Page 5: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/5.jpg)
Problem we need to Solve
Joints every 12’ in RCP Force Main thru YBM
Design useful life = 25 to 50 years (ASCE; EPA)
Pipe is 45 years old
Originally designed for gravity flow (low pressure)
Currently operating at 2.5 times design pressure
64 leaks so far; rate of failure is increasing
Leaks are time-consuming, disruptive and expensive to
repair . . . potentially catastrophic.
![Page 6: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/6.jpg)
Pipe cracked
(not a joint separation)
Raw sewage flowing from
separated and offset joint
![Page 7: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/7.jpg)
Adjacent to airport . . .
valve bonnet blew off . . .
. . . raw sewage into the air
![Page 8: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/8.jpg)
Major Failures Corrosion + Surge
![Page 9: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/9.jpg)
Numerous Alternatives Considered
2013/2014 Open Cut in Street Open Cut in Levee Lay in Slough Lay in Lagoon Microtunnel (shallow)
2014/2015 Microtunnel (deep) Tunnel Boring Machine (deep) From SVCW Plant From near Airport
Sliplining (w/ bypass) Parallel Smaller Pipes Pipe Bursting (w/ bypass) Pipe Splitting (w/bypass) Swege (w/bypass) Replace in place (w/bypass)
![Page 10: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/10.jpg)
![Page 11: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/11.jpg)
![Page 12: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/12.jpg)
Current Project
• SVCW will share all of the studies and alternatives developed to-date
• We expect to work collaboratively with the PDB during Stage 1 to refine, revise or change these concepts to best meet SVCW objectives
![Page 13: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/13.jpg)
Virtual Tour
![Page 14: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/14.jpg)
“60% Permit Plans” – RLS Shaft
![Page 15: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/15.jpg)
RLS Shaft
![Page 16: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/16.jpg)
RLS Shaft
![Page 17: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/17.jpg)
RLS Shaft
![Page 18: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/18.jpg)
Airport Access Shaft
![Page 19: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/19.jpg)
Airport Access Shaft
![Page 20: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/20.jpg)
San Carlos Drop Structure
![Page 21: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/21.jpg)
San Carlos Drop Structure
![Page 22: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/22.jpg)
“60% Permit Plans” – Bair Island Inlet
![Page 23: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/23.jpg)
Bair Island Inlet Structure
![Page 24: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/24.jpg)
Bair Island Inlet Structure
![Page 25: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/25.jpg)
Alignment
![Page 26: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/26.jpg)
Governors Bay Alignment
![Page 27: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/27.jpg)
Easement Acquisition
![Page 28: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/28.jpg)
Pulgas Creek
![Page 29: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/29.jpg)
Geologic Profile
![Page 30: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/30.jpg)
![Page 31: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/31.jpg)
Hydraulics
San Carlos Drop Structure
Design Storm Equalization
Diurnal Equalization
![Page 32: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/32.jpg)
EIR Status
• Draft EIR November 2016
• Comments Due January 2017 (very few comments)
• Adoption expected April 2017
![Page 33: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/33.jpg)
Environmental Permits
• Environmental Permit Applications submitted December 2016
– COE under Pulgas Creek
– BCDC
– California F&WS
• Expected October 2017
![Page 34: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/34.jpg)
Easements
• Affected along 3.3 miles:
– Four private owners
– Three public agencies
• Legal Descriptions being prepared
• Private acquisitions to start upon approval of EIR
• Two of public agencies are members of SVCW
• Currently leasing Airport Access Shaft staging area
![Page 35: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/35.jpg)
Funding
• Currently have bond capacity to obtain bonds for entire program
• Pursuing less expensive funding
– SRF
– WIFIA
![Page 36: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/36.jpg)
Procurement Process and Stages of Design-Build
• Why Progressive Design Build
• RFQ/RFP
• Stage 1/Stage 2 with Phases
• Schedule
![Page 37: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/37.jpg)
Why Progressive Design Build
• Accelerate completion of overall Project relative to DBB delivery
• Promote a cooperative and collaborative relationship between SVCW and the PDB team
• Incorporate ongoing cost modeling and take a “design-to-budget” approach
• Flexibility for phased design and construction
• Early and ongoing staff involvement and training
![Page 38: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/38.jpg)
RFQ/RFP Process
• Step 1: – RFQ issuance, – Pre-submittal meeting – Interviews with selected Respondents, – Shortlisting of three (or up to four) Respondents.
• Step 2: – RFP issuance to short-listed Respondents, – Pre-Proposal Meeting – Confidential Meetings with each short-listed Respondent – Reference checking – Interviews – Selection of winning Respondent – Negotiation of Stage 1 Preconstruction contract
![Page 39: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/39.jpg)
Stage 1/Stage 2 with Phases
• Stage 1 – Collaboratively bring the design from a 5% to 10%
level to a 60% to 70% level
– Negotiate Stage 2 Contract Pricing and Schedule
• Stage 2 – Final design (100%)
– Construction
– Testing and Start-up
• Phases – As needed to move project forward
![Page 40: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/40.jpg)
Schedule
• Issue RFQ Shortly after April 13
• SOQ Submission End of May
• Shortlist and RFP Early June
• Proposals Due Late August
• Stage 1 Approval September or October
• Stage 2 Approval 2018
Construction: Two to three years
![Page 41: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/41.jpg)
Key Parts of the RFQ
• RESCU Success Factors
• Gravity Pipeline Project Objectives
• Risk Responsibility Matrix
• Required elements of SOQ
![Page 42: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/42.jpg)
RESCU Success Factors “Success” - collaboratively implementing an appropriate balance of the following: • Cost: Provide a complete functional conveyance system that meets
the goals of the Program at the lowest practical capital and lifecycle cost.
• Operations: Produce projects that are easy, efficient, and effective to operate.
• Maintenance: Produce projects that minimize required maintenance. • Safety: Implement projects that are safe to construct, operate, and
maintain. • Schedule: Place new wastewater conveyance system projects into
operation with best practical safe speed, while maintaining the present level of service with existing facilities.
• Stakeholder Impacts: Solicit, evaluate, and respond to stakeholder’s concerns, and implement a Program that best meets the combined needs of stakeholders while reaching the Program’s goals.
![Page 43: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/43.jpg)
Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will reliably
receive, convey and equalize wastewater flows ranging from 2 mgd to 103 mgd in full compliance with environmental requirements.
• Cost: Provide a complete functional gravity pipeline and inlet facilities that meet the goals of the Project at the lowest practical capital and lifecycle cost. Provide early and ongoing total Gravity Pipeline cost predictability.
• Schedule: Achieve the best practical safe speed to complete the tunnel and inlet structures so that the existing failing pipeline and pump stations can be taken out of operation as early as reasonably possible.
• Risk: Generally assign to the Design-Builder the risks that the Design-Builder can reasonably anticipate and control. Assign to SVCW the risks that the Design-Builder cannot reasonably anticipate and control.
• Safety: Implement an effective safety program incorporating better than industry practices. • Accountability: Design-Builder to provide for a single point of accountability for
performance of all services under Stage 1 and Stage 2. SVCW to provide a single point of accountability for all direction to the Design-Builder.
• Collaboration: Implement an integrated design process that collaboratively includes SVCW management, engineering, operations and maintenance as well as the Design-Build contractor and engineer to develop a design that optimally achieves SVCW success factors and Gravity Pipeline requirements.
• Innovation: Apply proven technology from other locations to uniquely achieve Gravity Pipeline goals.
![Page 44: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/44.jpg)
Risk Responsibility Matrix
• Approach: Collaboratively reduce risk and then assign to PDB what the PDB can best control
• Built from a thorough Risk Register prepared during project planning (biggest risk was cost over budget)
![Page 45: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/45.jpg)
Required Elements of SOQ
• Team structure (including parties responsible for shafts, tunnel,
concrete segments)
• Key personnel
• Experience collaborating with owners
• Similar projects
• Safety
Pass fail items, financial, insurance, bonding, etc.
![Page 46: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/46.jpg)
Estimates, Budgets and Pricing
• Budget vs Current Cost Estimate – design to budget
• Indicative Pricing
![Page 47: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/47.jpg)
Focus Areas during early PDB Preconstruction Services (Stage 1)
• RLS shaft – coordination with FoP
• Pipe in tunnel
• Shaft construction
• Benefit of Bair Island start vs environmental/permitting delay risks
• Project cost and schedule
![Page 48: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/48.jpg)
RLS shaft – coordination with FoP
![Page 49: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/49.jpg)
Pipe in Tunnel – Alternatives
• Two Pass – FRP in tunnel – HDPE lining
• One Pass – HDPE lined segments
• Field weld • Combisegments
– Multiple layers of defense • Upstream dosing • Water and air flow • Special concrete • Monitoring
![Page 50: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/50.jpg)
Shaft Construction - Constraints
• Geotech – YBM, Sand, Groundwater • Airport Height limits – ~55’, ~45’, ~25’ • Protected species – Rail and Mouse • Traffic – Redwood Shores Parkway
![Page 51: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/51.jpg)
Benefit of Bair Island start vs environmental/permitting delay risks
Risks • Ridgeway Rail – no night work • Mouse – no work during high
tides • New Biological opinion – 9 to
12 months • EIR amendment Benefits • Eliminate airport access shaft • No TBM relocation – one
launch • Muck spoil on site
![Page 52: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/52.jpg)
Project Cost and Schedule
• Reduce GP cost by more than $40 million
• Reduce GP schedule by more than a year
• Achieve 100 year service life
• Achieve diurnal and wet weather equalization
![Page 53: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/53.jpg)
Available Information
• Current
• Future (at RFQ Issuance)
• Self-Guided Tour Maps
![Page 54: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/54.jpg)
![Page 55: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/55.jpg)
![Page 56: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/56.jpg)
![Page 57: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/57.jpg)
![Page 58: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/58.jpg)
![Page 59: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/59.jpg)
![Page 60: Gravity Pipeline Outreach Meeting inch pipeline... · Gravity Pipeline Project Objectives • Quality: Provide a gravity pipeline that will be sustainable over 100 years and will](https://reader034.vdocuments.us/reader034/viewer/2022050315/5f776e5525d6c40e7b72939d/html5/thumbnails/60.jpg)
More questions?
Thank you for your interest!
Regional Environmental
Sewer Conveyance Upgrade