Gradual re-start of the accelerator complex
and main accelerator projects
Online information meeting: Plan for CERN’s gradual re-start
Frédérick Bordry
5th May 2020
2
Gradual re-start of the accelerator complex and main accelerator projects
Online information meeting: Plan for CERN’s gradual re-start
Frédérick Bordry
5th May 2020
LS2 schedule: 13th March 2020
Master Schedule (v.2.4)
3
Gradual re-start of the accelerator complex and main accelerator projects
Online information meeting: Plan for CERN’s gradual re-start
Frédérick Bordry
5th May 2020
Phase 0
Safe Mode
Safe-mode and other
urgent activities
Week of 13 March: safe stop
all maintenance,
consolidation and upgrading
work in progress.
CERN open
in virtual mode
Massive telework
Preparation of
gradual re-start plans
From LS2 activities to safe-mode
4
Gradual re-start of the accelerator complex and main accelerator projects
Online information meeting: Plan for CERN’s gradual re-start
Frédérick Bordry
5th May 2020
Phase 0 Phase 1 Phase 2
Today 18th
May+ ~16 weeks
+ ~500 people
on site per week
Safe-mode and other
urgent activities
Up to 600
persons on site
Ramp-up to unlimited
access may be completed
by mid-September
“Unlimited”
access to
sites
to
Gradual and cautious re-start plan
Resume gradually, starting
with LS2, accelerator and
detector upgrades, urgent site
and building work.
- Number of people on sites include CERN’s personnel as well as contractors.
- Personnel involved in LS2, accelerator and detector upgrades, urgent site and building work
will come back gradually as of 18th May.
- The rest of personnel will come back gradually as of 2nd week of June.
- Personnel will be called by supervisors
5
Gradual re-start of the accelerator complex and main accelerator projects
Online information meeting: Plan for CERN’s gradual re-start
Frédérick Bordry
5th May 2020
LS2 and Projects structures are maintained
- Using an identical scheme as for Safety coordination since have
demonstrated efficiency.
- All meetings will continue as before the partial CERN closure, remote
connection will be systematically proposed.
WITH, additional measures linked to COVID-19
- Health & Safety protection of workers according to COVID-19 directives.
- To be taken as an additional hazard managed by line management.
- LS2 Committee to indicate eligible activities which could resume.
- Based on indications by the LS2 Coordination, projects priorities and
requests from Groups and Subcontractors.
Re-start under LS2 Coordination
6
Gradual re-start of the accelerator complex and main accelerator projects
Online information meeting: Plan for CERN’s gradual re-start
Frédérick Bordry
5th May 2020
Phase 0: evaluating CERN readiness for re-start after Safe-mode and urgent activities
Selection of activities based on priority for the Organisation
Resume the technical services/workshops to nominal performance where needed.
Cap the number of persons permanently at CERN to 600 during Phase 0.
Limit the working places to allow best Safety follow-up: sites inspections, (mini)VICs,
logistics, etc.
Avoid whenever possible to recall personnel from Contractors before Host States
deconfinement.
Management of activities by line management in the departments in
collaboration with LS2 coordination.
Phase 1: Resume gradually. Guidelines for personnel ramping-up ~+500 every week
LS2 rules & guidelines stay valid: new activities announced at LS2C with
relevant PLAN item for validation.
QA efforts be maintained particularly configuration management, integrations, ECRs,
layout database, etc.
Resuming activities going on before going on Safe mode.
Starting new activities shall be discussed with LS2C after checks with line
management of the departments.
Set a priority list of activities needed for LS2 Stage 2 period, including all
experimental areas and projects.
Evaluation of resources from support groups to define their ramping-up schemes.
Compatibility with Groups activities, solving coactivity issues and prioritisation.
7
Gradual re-start of the accelerator complex and main accelerator projects
Online information meeting: Plan for CERN’s gradual re-start
Frédérick Bordry
5th May 2020
► 68 x BE department with 53 with interpersonal distancing► ABP (4), BI (11), CO (5), OP(1), RF (29), ICS (18)
► 28 x EN department, all with full distancing► CV (8), EA (4), EL (5), HE (3), MME (4), SMM (4)
► 129 x TE department with 80 with interpersonal distancing.► ABT (12), CRG (9), EPC (15), MPE (4), MSC (45), VSC (44)
included DISMAC (14), HL-LHC (22)
Staff
CERN
[FTE]
Staff
Contractor
[FTE]
Staff
CERN
[FTE]
Staff
Contractor
[FTE]
L3 3 1
L4 8 2 5
PSB 25 19 8 8
PS 29 17 12 3
SPS 29 16 11 9
LHC 29 15 25 13
EXP 25 13 15 10
HL-LHC 46 29 43 28
INFRAS 21 16 19 14
SUPPORT 2 1 3 2
Grand Total 217 128 142 87
On-site AM On-site PM
36% Injectors/LIU
14% LHC
11% Host Lab
25% HL-LHC
14% Dept Infras
Phase 0: activities before to
Courtesy Miguel Jimenez
8
Gradual re-start of the accelerator complex and main accelerator projects
Online information meeting: Plan for CERN’s gradual re-start
Frédérick Bordry
5th May 2020
L3 L4 PS PSB SPS LHC Grand Total
BE-ABP 14 1 15
BE-ASR 1 1 1 3
BE-BI 4 7 6 15 118 150
BE-BI-TE-MSC 4 4
BE-CO 1 2 3
BE-ICS 1 1
BE-ICS 1 5 1 13 188 208
BE-OP 52 52
BE-RF 1 1
BE-RF 8 9 5 18 8 48
Total BE 20 11 23 15 50 366 485
EN-ACE 3 3
EN-CV 5 12 2 20 58 97
EN-EA 3 3 6
EN-EL 1 1 16 14 90 122
EN-EL-EPM 16 16
EN-EL-FC 14 14
EN-EL-FC-EPM 4 4
EN-HE 2 3 2 74 81
EN-SMM 1 2 15 13 149 180
EN-STI 2 2
EN-STI 1 3 1 8 51 64
Total BE 11 4 52 3 60 459 589
TE-ABT 6 11 15 20 52
TE-CRG 2 196 198
TE-EPC 1 1
TE-EPC 1 9 1 8 48 67
TE-EPC EN-CV 2 2
TE-EPC TE-MPE 1 1
TE-MPE 1 1
TE-MPE 2 2 2 85 91
TE-MSC 1 1
TE-MSC 1 1 12 10 13 47 84
TE-VSC 1 3 6 15 280 305
Total TE 8 1 32 33 53 676 803
SMB-SE 1 1
SMB-SE 11 7 18
SMB-SE 33 33
SMB-SIS 1 6 7
Total TE 1 1 11 0 13 33 59
HSE-HH 1 1
HSE-OHS 1 1
HSE-OHS, BE-BI 2 2
HSE-RP 1 1
Total HSE 2 3 0 0 0 0 5
IR-ECO 1 1
IT-CS 1 1 4 6
Grand Total 42 22 119 51 180 1534 1948
~1950 activities
planned during LS2
Number of declared activities in LS2 PLAN tool
Activities after to
Courtesy Miguel Jimenez
9
Gradual re-start of the accelerator complex and main accelerator projects
Online information meeting: Plan for CERN’s gradual re-start
Frédérick Bordry
5th May 2020
~17,000 days of work
still for the LS2 !
Working days declared in LS2 PLAN toolGroups L3 L4 LHC PS PSB SPS Grand TotalBE-ICS 2 2
BE-RF 5 5
BE-ABP 240 25 265
BE-ASR 2 2 2 6
BE-BI 13 357 44 6 64 484
BE-BI 41 41
BE-CO 125 88 213
BE-ICS 2 222 13 2 425 664
BE-OP 400 400
BE-RF 6 135 515 245 548 1,449
EN-STI 7 7
EN-ACE 330 330
EN-CV 14 778 2 0 200 994
EN-EA 80 25 105
EN-EL 2 0 393 205 265 865
EN-EL-EPM 4 4
EN-EL-FC 65 65
EN-EL-FC-EPM 8 8
EN-HE 3 175 10 110 298
EN-SMM 2 0 719 11 55 787
EN-STI 0 797 0 0 157 954
SMB-SE 3 3
SMB-SE 52 155 207
SMB-SE 171 171
SMB-SIS 3 60 63
TE-EPC 1 1
TE-MPE 1 1
TE-MSC 5 5
TE-ABT 545 0 0 322 867
TE-CRG 3,101 70 3,171
TE-EPC 2 200 9 0 300 511
TE-EPC 0 0
TE-EPC 0 0
TE-MPE 11 475 0 0 486
TE-MSC 2 0 453 10 10 65 540
TE-VSC 1 2,359 15 0 476 2,850
Other Dpts 3 1 0 0 0 25 29
Grand Total 313 38 11,435 1,038 353 3,643 16,819
Activities after to
Courtesy Miguel Jimenez
10
Gradual re-start of the accelerator complex and main accelerator projects
Online information meeting: Plan for CERN’s gradual re-start
Frédérick Bordry
5th May 2020
St art of Linac3 Source
LH C P R OB E beam ready fo r LH C
Start B eam
C o mmissio ning
# ## # # # # ## # # # # ## #
APR M AY JUNE JULYOCT NOV DEC JAN FEB M ARAPR M AY JUNE JULY AUG SEPTOCT NOV DEC JAN FEB M ARAPR M AY JUNE JULY AUG SEPT
# # # #
OCT NOV DEC JAN FEB M AR
# # # # # ## # # # # #9 # # # # #3 4 5 6 7 8# # # # 1 2# # # # # ## # # # # ## # # # # ## # # # # ## # # # # ## # # # # #8 9 # # # #2 3 4 5 6 7# # # # # 1# # # # # ## # # # # ## # # # # ## # # # # ## # # # # ## # # # # #6 7 8 9 # ## 1 2 3 4 5# # # # # #
LHC 3, 7, IT
SM 18
# # # # # #
LEIR
Linac2
Linac4
P SB
P S
T T 2
SP S
LH C
# # # #
OP
EN
DA
YS
Linac3
# # # # # ## # # # # #9 # # # # #3 4 5 6 7 8# # # # 1 2# # # # # ## # # # # ## # # # # ## # # # # ## # # # # ## # # # # #8 9 # # # #2 3 4 5 6 7# # # # # 1# # # # # ## # # # # ## # # # # ## # # # # ## # # # # ## # # # # #6 7 8 9 # ## 1 2 3 4 5# # # # # ## # # # # #
LEIR Shutdown
Linac3 Shutdown
COVID-19 Safe Mode
COVID-19 Safe Mode
PS&TT2 HT12
weeks
Co
ntr
ol M
ain
t.
Co
ntr
ol M
ain
t.
PS&TT2 Surface work
PS&TT2 Shutdown
RP
RP cooling
Linac4 connection - Linac2 Underground
RP cooling
Linac2 Surface work
PSB Surface work
RP cooling
Beam commissi
oning6 weeks
Beamcommission
ing6 weeks
Ions to LHC
L4
Main
Du
mp
Cold check-out1 month
SPS Hardware
tests2 months
PSB Shutdown
Linac4 Connection - Linac4 Transfer tunnel
HT
Linac4 ShutdownNO WORKNew LBE line - PS Switch Yard
RP cooling
Modification on LBS line - PS Switch
Start of work in the high radiological risk areas
PSB Hardware tests
4 months
PS Switch Yard CLOSED
PS Switch YardCLOSED
SPS Surface work
LHC Surface work
SPS Shutdown
LHC Shutdown
LHC Cool-downwhole machine
LHC Hardware CommissioningPowering tests + Magnet trainingLHC Cool-down
Coldcheck-
out6 weeks
Linac4 Beam Tests to LBE
line8 weeks
PSB
Ions to NA
and EA
Xm
as b
reak 2
01
8-2
01
9
Xm
as b
reak 2
01
9-2
02
0
SPS tests3 wks
PS tests
LHC Tests + Warm-Up4 months + 2 weeks of xmas break
2018-2019
IST
BA1 7 weeks
3M
eV
HT
2w
Stop for infras.
HT
IS
IS
ISTs Period10 weeks
Cold check-out
4wksISTs Period6 weeks
IST Linac3 Beam testing
( ITFSTP12)
HWC
IST HW
CLEIR Beam commissioning
Linac3 Beam
testing (Transfer lines)
IST
tra
ns
fer
lin
es
Xm
as b
reak 2
02
0-2
02
1
HW
C Linac3 Beam commissioning
Co
ld c
he
ck-
ou
t
Co
ntr
ol
IST 1
w
Start of ISTs
Start of ISTs
Start of ISTs
Start of ISTs
Start of ISTs
Start of ISTs POPS-B
POP
PO
PS
LEB
T(3
MeV
)
Ch
eck-o
ut
BA2 7 weeks
BA4 7 weeks
BA6 7 weeks
BA3 20 weeks
BA5 7 weeks
COVID-19 Safe Mode
ISTs Period
5 weeks
PSB Beam commissioning
2.5 months
COVID-19 Safe Mode
COVID-19 Safe Mode
COVID-19 Safe Mode
COVID-19 Safe Mode
Linac4 Beam Setup(LBE dump)
2.5 months
Prospective new LS2 schedule
3 months
Special LS2 Committee (8th May): prioritization review of Phase 1 re-start
LHC accelerator and experiments Meeting (8th June) : L2 status and Run 3
LS2 Day (12th June): Consolidate the LHC Experiments timeline and LS2 Master schedules.
Update on resources availabilities including Support’s group and General Services.
LHC workshop (“Chamonix”, 28th Sept to 1st Oct) to review and optimize the LS2 schedule and the Run 3
11
Gradual re-start of the accelerator complex and main accelerator projects
Online information meeting: Plan for CERN’s gradual re-start
Frédérick Bordry
5th May 2020
Safety first
- To respond to all safety hazards and maintain
the highest standards of safety as demonstrated
since the start of the LS2.
- COVID-19 will be addressed as an additional
hazard with all the necessary adjustments that
may be needed following feedback and
recommendations by experts and the Host States.
12
Gradual re-start of the accelerator complex and main accelerator projects
Online information meeting: Plan for CERN’s gradual re-start
Frédérick Bordry
5th May 2020
CERN now has a better vision of the situation, thank you all for your contribution
to the development of this plan.
A gradual re-start is possible, providing a strict respect of the safety rules
and the sanitary measures in place by HSE and the local authorities.
We have to be patient as we are all recovering from an unexpected period and a
unique long safe-mode
Take care and don’t forget our successful slogan:
Safety first, Quality second and Schedule third
Work on the CERN sites will resumegradually. The presence on site of everymember should be limited to the timerequired to carry out the approvedactivity/ies.