government of india india meteorological department...

29
1 Government of India India Meteorological Department Central Seismological Observatory, Shillong -793005. PROGRESS REPORT FOR THE MONTH OF SEPTEMBER, 2009 1. CHEIF FEATURES 1.1. Shri.A.C.Lyngdoh, Meteorologist incharge, CSO, Shillong was on tour to Saiha, Mizoram in connection with supervision of construction of Seismic Pillar from 20 th – 25 th September 2009. 1.2. Hindi day was observed on 16 /9/2009. Dr.N.Hazarika and Shri.M.Nongkhlaw of IIGM, Shillong were the chief guest at the function. 2. DATA MANAGEMENT. A. SEISMOLOGY. 2.A1 Number of felt shocks recorded during the month : 4 Nos. 2.A2 Number of Earthquake magnitude 5.0 and above recorded during the month : 15 Nos. 2.A3 Significant earthquake messages were transmitted over MES/FA regularly to DGM(Seismo.), New Delhi for onward transmission to USGS, USA. 2.A4 Seismological Bulletin and near shock data for AUGUST, 2009 sent to DGM (Seismo.), New Delhi. 2.A5 BBS Data in prescribed format in CDR for AUGUST, 2009 sent to DGM (Seismo), New Delhi. 2.A6 Near earthquake data (5 ° )for AUGUST, 2009 supplied to RRL, Jorhat 2.A7 Near earthquake data (10°)for AUGUST, 2009 supplied to NGRI, Tezpur 2.A8 Monthly technical information for the month of AUGUST, 2009 was sent to DGM (Seismo.), New Delhi. 2.A9 Recording of BBS is continuing. 2.A10 Recording of GPS at permanent station of CSO. Shillong is continuing. 2.A11 Monthly statement of consumable items for the month of AUGUST, 2009 was sent to DGM(Seismo), New Delhi. 2.A12. Recording of RTSMN is continuing. 2.A13. Recording of MEQ is continuing.

Upload: vuongdiep

Post on 10-Mar-2018

222 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

1

Government of India

India Meteorological Department Central Seismological Observatory,

Shillong -793005.

PROGRESS REPORT FOR THE MONTH OF SEPTEMBER, 2009

1. CHEIF FEATURES 1.1. Shri.A.C.Lyngdoh, Meteorologist incharge, CSO, Shillong was on tour to Saiha, Mizoram in connection with supervision of construction of Seismic Pillar from 20th – 25th September 2009. 1.2. Hindi day was observed on 16 /9/2009. Dr.N.Hazarika and Shri.M.Nongkhlaw of

IIGM, Shillong were the chief guest at the function. 2. DATA MANAGEMENT. A. SEISMOLOGY. 2.A1 Number of felt shocks recorded during the month : 4 Nos. 2.A2 Number of Earthquake magnitude 5.0 and above recorded during the month : 15 Nos. 2.A3 Significant earthquake messages were transmitted over MES/FA regularly to

DGM(Seismo.), New Delhi for onward transmission to USGS, USA. 2.A4 Seismological Bulletin and near shock data for AUGUST, 2009 sent to DGM

(Seismo.), New Delhi. 2.A5 BBS Data in prescribed format in CDR for AUGUST, 2009 sent to DGM (Seismo),

New Delhi. 2.A6 Near earthquake data (∆ ≤ 5 °)for AUGUST, 2009 supplied to RRL, Jorhat 2.A7 Near earthquake data (∆ ≤ 10°)for AUGUST, 2009 supplied to NGRI, Tezpur 2.A8 Monthly technical information for the month of AUGUST, 2009 was sent to DGM

(Seismo.), New Delhi. 2.A9 Recording of BBS is continuing. 2.A10 Recording of GPS at permanent station of CSO. Shillong is continuing. 2.A11 Monthly statement of consumable items for the month of AUGUST, 2009 was sent

to DGM(Seismo), New Delhi. 2.A12. Recording of RTSMN is continuing. 2.A13. Recording of MEQ is continuing.

Page 2: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

2

B. METEOROLOGY & RADIATION. 2.B1 Synop data of 03z and 12z were transmitted over VSAT/ PHONE/ PHONOGRAM to

RMC, Guwahati / DDGM(WF), Pune / NHEC, New Delhi regularly . 2.B2 Monthly Meteorological data for AUGUST, 2009 were sent to RMC, Guwahati. 2.B3 Minimum and Maximum temperatures of Shillong were sent to AIR, Shillong and

Doordarshan – Guwahati & Shillong daily. 2.B4 Weekly rainfall data of Shillong were sent to RMC, Guwahati on regular basis. 2.B5 Weekly synop data were sent to DDGM(WF) Pune / RMC, Guwahati on regular

basis. 2.B6 Some cases of Met. enquiries / data have been forwarded to RMC, Guwahati for

further necessary action. 2.B7 Weekly visibility reports were sent to RMC, Guwahati on regular basis. 2.B8 Monthly flood damage & disaster events report for AUGUST, 2009 sent to RMC,

Guwahati. 2.B9 The following observations took place during the month :- (a). Pyrgeometer : NIL (b). Pyrheliometer : NIL 2.B10 Number of print out from Data logger for global and diffuse solar radiation :30 2.B11 Monthly radiation data for AUGUST, 2009 sent to ADGM ® Pune. 2.B12. Weekly original MMR were sent to RMC, Guwahati on regular basis. 3. BUDGET & PLANNING. 3.1 O.E. bills, Medical bills and Contingent bills etc. 4. RECEIPTS & DESPATCHED. 4.1 Number of letters receipts during the month = 134 4.2 Number of letter dispatched during the month = 129 5. RECEIPTS / PAYMENTS. 5.1 OTA bills, and O.E. bills, Contingent bills etc.

Page 3: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

3

6. VISITORS. 6.1. A group of 20 Students Msc from Department of Environmental Science,

N.E.H.University visited the observatory on 30/9/09. Sd/- ( A.C.Lyngdoh ) Meteorologist-in-charge. Copy to: DGM(G/S), New Delhi / DDGM(Seismo), New Delhi / DDGM(Telecom), NEW DELHI/ DDGM(Sat.Met),NEW DELHI/ DDGM (UI), New Delhi / ADGM®, Pune / DDGM(WF), Pune / DDGM (SI), Pune / DDGM (Agrimet), Pune. RMCs : New Delhi / Mumbai / Nagpur / Chennai / Kolkata / Guwahati. Directors : PAC, Kolkata / Seismo. New Delhi / M.O. Kolkata.

Sd/- ( A.C.Lyngdoh ) Meteorologist-in-charge. CSO.SHL.UOI.NO. A-47011/1/2001/ Dt . 10. 2009

Page 4: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

4

Government of India

India Meteorological Department Central Seismological Observatory,

Shillong -793005.

PROGRESS REPORT FOR THE MONTH OF OCTOBER, 2009

1. CHEIF FEATURES 1.1 Shri.A.C.Lyngdoh, Meteorologist incharge, CSO, Shillong was promoted to

Meteorologist-I on 13/10/09. 1.2 Shri.A.C.Lyngdoh, Meteorologist incharge, CSO, Shillong attended meeting at DC,

East Khasi Hillls District, Shillong in connection with the setting up of Emergency Control Room for Disaster Management.

1.3 Shri.A.C.Lyngdoh, Meteorologist incharge, CSO, Shillong attended the H.J.Babha,

Centenary Programme at AMD, Shillong. 2. DATA MANAGEMENT. A. SEISMOLOGY. 2.A1 Number of felt shocks recorded during the month : 3 Nos. 2.A2 Number of Earthquake magnitude 5.0 and above recorded during the month : 25 Nos. 2.A3 Significant earthquake messages were transmitted over MES/FA regularly to

DGM(Seismo.), New Delhi for onward transmission to USGS, USA. 2.A4 Seismological Bulletin and near shock data for SEPTEMBER, 2009 sent to DGM

(Seismo.), New Delhi. 2.A5 BBS Data in prescribed format in CDR for SEPTEMBER, 2009 sent to DGM

(Seismo), New Delhi. 2.A6 Near earthquake data (∆ ≤ 5 °)for SEPTEMBER, 2009 supplied to RRL, Jorhat 2.A7 Near earthquake data (∆ ≤ 10°)for SEPTEMBER, 2009 supplied to NGRI, Tezpur 2.A8 Monthly technical information for the month of SEPTEMBER, 2009 was sent to DGM

(Seismo.), New Delhi. 2.A9 Recording of BBS is continuing. 2.A10 Recording of GPS at permanent station of CSO. Shillong is continuing. 2.A11 Monthly statement of consumable items for the month of SEPTEMBER, 2009 was

sent to DGM(Seismo), New Delhi. 2.A12. Recording of RTSMN is continuing. 2.A13. Recording of MEQ is continuing.

Page 5: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

5

B. METEOROLOGY & RADIATION. 2.B1 Synop data of 03z and 12z were transmitted over VSAT/ PHONE/ PHONOGRAM to

RMC, Guwahati / DDGM(WF), Pune / NHEC, New Delhi regularly . 2.B2 Monthly Meteorological data for SEPTEMBER, 2009 were sent to RMC, Guwahati. 2.B3 Minimum and Maximum temperatures of Shillong were sent to AIR, Shillong and

Doordarshan – Guwahati & Shillong daily. 2.B4 Weekly rainfall data of Shillong were sent to RMC, Guwahati on regular basis. 2.B5 Weekly synop data were sent to DDGM(WF) Pune / RMC, Guwahati on regular

basis. 2.B6 Some cases of Met. enquiries / data have been forwarded to RMC, Guwahati for

further necessary action. 2.B7 Weekly visibility reports were sent to RMC, Guwahati on regular basis. 2.B8 Monthly flood damage & disaster events report for SEPTEMBER, 2009 sent to RMC,

Guwahati. 2.B9 The following observations took place during the month :- (a). Pyrgeometer : NIL (b). Pyrheliometer : NIL 2.B10 Number of print out from Data logger for global and diffuse solar radiation :31 2.B11 Monthly radiation data for SEPTEMBER, 2009 sent to ADGM ® Pune. 2.B12. Weekly original MMR were sent to RMC, Guwahati on regular basis. 3. RESEARCH/PUBLICATION 3.1. An abstract entitled “Response time for earthquake preparedness from Seismic alert

system in Shillong and Guwahati” authored by Shri.A.C.Lyngdoh and Shri.M.Taid was accepted for publication in the “ Second India Disaster Management Congress, 4th – 6th Nov’09, NIDM, New Delhi.

4. TRAINING. 4.1. Shri.A.Kharshong, MA attended Modular Course training for LA/MA at RMC,

Kolkata. 4. BUDGET & PLANNING. 4.1 O.E. bills, Medical bills and Contingent bills etc.

Page 6: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

6

5. RECEIPTS & DESPATCHED. 5.1 Number of letters receipts during the month = 141 5.2 Number of letter dispatched during the month = 163 6. RECEIPTS / PAYMENTS. 6.1 OTA bills, and O.E. bills, Contingent bills etc. 7. VISITORS. 1.1. 80 Students (class XI-XII) Arts Stream from BSF Senior Secondary School visited

the observatory on 06/10/2009. 1.2. 90 Students (class XI-XII) Science Stream from BSF Senior Secondary School

visited the observatory on 07/10/2009. Sd/- ( A.C.Lyngdoh ) Meteorologist-in-charge. Copy to: DGM(G/S), New Delhi / DDGM(Seismo), New Delhi / DDGM(Telecom), NEW DELHI/ DDGM(Sat.Met),NEW DELHI/ DDGM (UI), New Delhi / ADGM®, Pune / DDGM(WF), Pune / DDGM (SI), Pune / DDGM (Agrimet), Pune. RMCs : New Delhi / Mumbai / Nagpur / Chennai / Kolkata / Guwahati. Directors : PAC, Kolkata / Seismo. New Delhi / M.O. Kolkata.

Sd/- ( A.C.Lyngdoh ) Meteorologist-in-charge. CSO.SHL.UOI.NO. A-47011/1/2001/ Dt . 11. 2009

Government of India

Page 7: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

7

India Meteorological Department Central Seismological Observatory,

Shillong -793005.

PROGRESS REPORT FOR THE MONTH OF NOVEMBER, 2009

1. CHEIF FEATURES 1.1. Shri.A.C.Lyngdoh, Meteorologist incharge, CSO, Shillong was on tour to Imphal,

Manipur in connection with supervision of Seismic pillar from 15th-17th November’09. 1.2 . Vigilance Observance week was observed in the office from 3rd-7th November’09.

Pledge was taken on 3rd November’09. 2. DATA MANAGEMENT. A. SEISMOLOGY. 2.A1 Number of felt shocks recorded during the month : 01 Nos. 2.A2 Number of Earthquake magnitude 5.0 and above recorded during the month : 17 Nos. 2.A3 Significant earthquake messages were transmitted over MES/FA regularly to

DGM(Seismo.), New Delhi for onward transmission to USGS, USA. 2.A4 Seismological Bulletin and near shock data for OCTOBER, 2009 sent to DGM

(Seismo.), New Delhi. 2.A5 BBS Data in prescribed format in CDR for OCTOBER, 2009 sent to DGM (Seismo),

New Delhi. 2.A6 Near earthquake data (∆ ≤ 5 °)for OCTOBER, 2009 supplied to RRL, Jorhat 2.A7 Near earthquake data (∆ ≤ 10°)for OCTOBER, 2009 supplied to NGRI, Tezpur 2.A8 Monthly technical information for the month of OCTOBER, 2009 was sent to DGM

(Seismo.), New Delhi. 2.A9 Recording of BBS is continuing. 2.A10 Recording of GPS at permanent station of CSO. Shillong is continuing. 2.A11 Monthly statement of consumable items for the month of OCTOBER, 2009 was

sent to DGM(Seismo), New Delhi. 2.A12. Recording of RTSMN is continuing. 2.A13. Recording of MEQ is continuing. B. METEOROLOGY & RADIATION.

Page 8: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

8

2.B1 Synop data of 03z and 12z were transmitted over VSAT/ PHONE/ PHONOGRAM to

RMC, Guwahati / DDGM(WF), Pune / NHEC, New Delhi regularly . 2.B2 Monthly Meteorological data for OCTOBER, 2009 were sent to RMC, Guwahati. 2.B3 Minimum and Maximum temperatures of Shillong were sent to AIR, Shillong and

Doordarshan – Guwahati & Shillong daily. 2.B4 Weekly rainfall data of Shillong were sent to RMC, Guwahati on regular basis. 2.B5 Weekly synop data were sent to DDGM(WF) Pune / RMC, Guwahati on regular

basis. 2.B6 Some cases of Met. enquiries / data have been forwarded to RMC, Guwahati for

further necessary action. 2.B7 Weekly visibility reports were sent to RMC, Guwahati on regular basis. 2.B8 Monthly flood damage & disaster events report for OCTOBER, 2009 sent to RMC,

Guwahati. 2.B9 The following observations took place during the month :- (a). Pyrgeometer : NIL (b). Pyrheliometer : NIL 2.B10 Number of print out from Data logger for global and diffuse solar radiation :30 2.B11 Monthly radiation data for OCTOBER, 2009 sent to ADGM ® Pune. 2.B12. Weekly original MMR were sent to RMC, Guwahati on regular basis. 3. BUDGET & PLANNING. 3.1 O.E. bills, Medical bills and Contingent bills etc. 4. RECEIPTS & DESPATCHED. 4.1 Number of letters receipts during the month = 164 4.2 Number of letter dispatched during the month = 129 5. RECEIPTS / PAYMENTS. 5.1 OTA bills, and O.E. bills, Contingent bills etc. 6. VISITORS. 6.1. 18 teachers and 72 Students from Langtor Higher Secondary School visited the

observatory on 06/11/2009.

Page 9: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

9

Sd/- ( A.C.Lyngdoh ) Meteorologist-in-charge. Copy to: DGM(G/S), New Delhi / DDGM(Seismo), New Delhi / DDGM(Telecom), NEW DELHI/ DDGM(Sat.Met),NEW DELHI/ DDGM (UI), New Delhi / ADGM®, Pune / DDGM(WF), Pune / DDGM (SI), Pune / DDGM (Agrimet), Pune. RMCs : New Delhi / Mumbai / Nagpur / Chennai / Kolkata / Guwahati. Directors : PAC, Kolkata / Seismo. New Delhi / M.O. Kolkata.

Sd/- ( A.C.Lyngdoh ) Meteorologist-in-charge. CSO.SHL.UOI.NO. A-47011/1/2001/ Dt . 12. 2009

Government of India India Meteorological Department

Page 10: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

10

Central Seismological Observatory, Shillong -793005.

PROGRESS REPORT FOR THE MONTH OF DECEMBER, 2009

1. DATA MANAGEMENT. A. SEISMOLOGY. 1.A1 Number of felt shocks recorded during the month : 02 Nos. 1.A2 Number of Earthquake magnitude 5.0 and above recorded during the month : 17Nos. 1.A3 Significant earthquake messages were transmitted over MES/FA regularly to

DGM(Seismo.), New Delhi for onward transmission to USGS, USA. 1.A4 Seismological Bulletin and near shock data for NOVEMBER, 2009 sent to DGM

(Seismo.), New Delhi. 1.A5 BBS Data in prescribed format in CDR for NOVEMBER, 2009 sent to DGM

(Seismo), New Delhi. 1.A6 Near earthquake data (∆ ≤ 5 °)for NOVEMBER, 2009 supplied to RRL, Jorhat 1.A7 Near earthquake data (∆ ≤ 10°)for NOVEMBER, 2009 supplied to NGRI, Tezpur 1.A8 Monthly technical information for the month of NOVEMBER, 2009 was sent to DGM

(Seismo.), New Delhi. 1.A9 Recording of BBS is continuing. 1.A10 Recording of GPS at permanent station of CSO. Shillong is continuing. 1.A11 Monthly statement of consumable items for the month of NOVEMBER, 2009 was

sent to DGM(Seismo), New Delhi. 1.A12. Recording of RTSMN is continuing. 1.A13. Recording of MEQ is continuing. B. METEOROLOGY & RADIATION. 1.B1 Synop data of 03z and 12z were transmitted over VSAT/ PHONE/ PHONOGRAM to

RMC, Guwahati / DDGM(WF), Pune / NHEC, New Delhi regularly . 1.B2 Monthly Meteorological data for NOVEMBER, 2009 were sent to RMC, Guwahati.

Page 11: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

11

1.B3 Minimum and Maximum temperatures of Shillong were sent to AIR, Shillong and Doordarshan – Guwahati & Shillong daily.

1.B4 Weekly rainfall data of Shillong were sent to RMC, Guwahati on regular basis. 1.B5 Weekly synop data were sent to DDGM(WF) Pune / RMC, Guwahati on regular

basis. 1.B6 Some cases of Met. enquiries / data have been forwarded to RMC, Guwahati for

further necessary action. 1.B7 Weekly visibility reports were sent to RMC, Guwahati on regular basis. 1.B8 Monthly flood damage & disaster events report for NOVEMBER, 2009 sent to RMC,

Guwahati. 1.B9 The following observations took place during the month :- (a). Pyrgeometer : NIL (b). Pyrheliometer : NIL 1.B10 Number of print out from Data logger for global and diffuse solar radiation :31 1.B11 Monthly radiation data for NOVEMBER, 2009 sent to ADGM ® Pune. 1.B12. Weekly original MMR were sent to RMC, Guwahati on regular basis. 2. TOUR. 2.1 Shri.J.Tamil, Mech Gr-I and shri.A.K.Sunar,MA were on tour to Seismo Agartala for rectification of CSIO Recorder/Sensor from 18/12/09 to 22/12/2009. 3. BUDGET & PLANNING. 3.1 O.E. bills, Medical bills and Contingent bills etc. 4. RECEIPTS & DESPATCHED. 4.1 Number of letters receipts during the month = 224 4.2 Number of letter dispatched during the month = 146 5. RECEIPTS / PAYMENTS. 5.1 OTA bills, and O.E. bills, Contingent bills etc. 6. VISITORS. 6.1 A group of 50 students with teachers from different schools of Meghalaya under DST programme INSPIRE conducted by NEHU, Shillong visited the Observatory on

Page 12: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

12

15/12/2009. 6.2. A group of 10 BSc (Geology) students with lecturers and Associate Prof.D.Walia

NEHU, Shillong visited the Observatory on 08/12/2009. ( A.C.Lyngdoh ) Meteorologist-in-charge. Copy to: DGM(G/S), New Delhi / DDGM(Seismo), New Delhi / DDGM(Telecom), NEW DELHI/ DDGM(Sat.Met),NEW DELHI/ DDGM (UI), New Delhi / ADGM®, Pune / DDGM(WF), Pune / DDGM (SI), Pune / DDGM (Agrimet), Pune. RMCs : New Delhi / Mumbai / Nagpur / Chennai / Kolkata / Guwahati. Directors : PAC, Kolkata / Seismo. New Delhi / M.O. Kolkata.

( A.C.Lyngdoh ) Meteorologist-in-charge. CSO.SHL.UOI.NO. A-47011/1/2001/ Dt . 01.2010

Government of India India Meteorological Department

Central Seismological Observatory, Shillong -793005.

PROGRESS REPORT FOR THE MONTH OF JANAURY 2010

Page 13: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

13

1. CHEIF FEATURES 1.1 Republic Day was celebrated on 26th Janaury 2010. Shri.A.C.Lyngdoh, Meteorologist in charge hoisted the National flag. 1.2 DPC meeting for MA was convened on 22nd Janaury 2010. . 2. DATA MANAGEMENT. A. SEISMOLOGY. 2.A1 Number of felt shocks recorded during the month : 1 Nos. 2.A2 Number of Earthquake magnitude 5.0 and above recorded during the month : 12 Nos. 2.A3 Significant earthquake messages were transmitted over MES/FA regularly to

DGM(Seismo.), New Delhi for onward transmission to USGS, USA. 2.A4 Seismological Bulletin and near shock data for DECEMBER, 2009 sent to DGM

(Seismo.), New Delhi. 2.A5 BBS Data in prescribed format in CDR for DECEMBER, 2009 sent to DGM

(Seismo), New Delhi. 2.A6 Near earthquake data (∆ ≤ 5 °)for DECEMBER, 2009 supplied to RRL, Jorhat 2.A7 Near earthquake data (∆ ≤ 10°)for DECEMBER, 2009 supplied to NGRI, Tezpur 2.A8 Monthly technical information for the month of DECEMBER, 2009 was sent to DGM

(Seismo.), New Delhi. 2.A9 Recording of BBS is continuing. 2.A10 Recording of GPS at permanent station of CSO. Shillong is continuing. 2.A11 Monthly statement of consumable items for the month of DECEMBER, 2009 was

sent to DGM(Seismo), New Delhi. 2.A12. Recording of RTSMN is continuing. 2.A13. Recording of MEQ is continuing. B. METEOROLOGY & RADIATION. 2.B1 Synop data of 03z and 12z were transmitted over VSAT/ PHONE/ PHONOGRAM to

RMC, Guwahati / DDGM(WF), Pune / NHEC, New Delhi regularly . 2.B2 Monthly Meteorological data for DECEMBER, 2009 were sent to RMC, Guwahati.

Page 14: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

14

2.B3 Minimum and Maximum temperatures of Shillong were sent to AIR, Shillong and Doordarshan – Guwahati & Shillong daily.

2.B4 Weekly rainfall data of Shillong were sent to RMC, Guwahati on regular basis. 2.B5 Weekly synop data were sent to DDGM(WF) Pune / RMC, Guwahati on regular

basis. 2.B6 Some cases of Met. enquiries / data have been forwarded to RMC, Guwahati for

further necessary action. 2.B7 Weekly visibility reports were sent to RMC, Guwahati on regular basis. 2.B8 Monthly flood damage & disaster events report for DECEMBER, 2009 sent to RMC,

Guwahati. 2.B9 The following observations took place during the month :- (a). Pyrgeometer : NIL (b). Pyrheliometer : NIL 2.B10 Number of print out from Data logger for global and diffuse solar radiation :31 2.B11 Monthly radiation data for DECEMBER, 2009 sent to ADGM ® Pune. 2.B12. Weekly original MMR were sent to RMC, Guwahati on regular basis. 3. BUDGET & PLANNING. 3.1 OTA bills, O.E bills, Medical bills and Contingent bills etc. 4. RECEIPTS & DESPATCHED. 4.1 Number of letters receipts during the month = 117 4.2 Number of letter dispatched during the month = 121 5. RECEIPTS / PAYMENTS. 5.1 Medical bills, and O.E. bills, Contingent bills etc. 6. VISITORS.

Page 15: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

15

6.1 WO RC Lal, JWO S.K.Bhart and Sgt B.P.Yadav of EAC, Shillong visited the Observatory on 14/01/2010. ( A.C.Lyngdoh ) Meteorologist-in-charge. Copy to: DGM(G/S), New Delhi / DDGM(Seismo), New Delhi / DDGM(Telecom), NEW DELHI/ DDGM(Sat.Met),NEW DELHI/ DDGM (UI), New Delhi / ADGM®, Pune / DDGM(WF), Pune / DDGM (SI), Pune / DDGM (Agrimet), Pune. RMCs : New Delhi / Mumbai / Nagpur / Chennai / Kolkata / Guwahati. Directors : PAC, Kolkata / Seismo. New Delhi / M.O. Kolkata.

( A.C.Lyngdoh ) Meteorologist-in-charge. CSO.SHL.UOI.NO. A-47011/1/2001/ Dt . 02. 2010

Government of India India Meteorological Department

Central Seismological Observatory, Shillong -793005.

PROGRESS REPORT FOR THE MONTH OF FEBRUARY 2010

1. CHEIF FEATURES

Page 16: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

16

1.1 SHRI A.LYNGRAH, MECH GR-I EXPIRED ON 10/02/2010 WHILE IN SERVICE. Condolence meeting was held on 10/02/2010 and copy of condolence message was delivered to the family. Shri.A.C.Lyngdoh, Meteorologist in charge attended the funeral and laid wreath of flowers on behalf of India Meteorological Department.

1.2 Dr.A.K.Shukla, Scientist ‘E’, EREC, New Delhi and Shri B.S.Rani, AM-I attended meeting on 03-02-2010 at CSO, Shillong with Engineers of CPWD (Civil & Electrical), Shillong regarding status of CRS Building at CSO, Shillong. . 2. DATA MANAGEMENT. A. SEISMOLOGY. 2.A1 Number of felt shocks recorded during the month : 03 Nos. 2.A2 Number of Earthquake magnitude 5.0 and above recorded during the month : 07 Nos. 2.A3 Significant earthquake messages were transmitted over MES/FA regularly to

DGM(Seismo.), New Delhi for onward transmission to USGS, USA. 2.A4 Seismological Bulletin and near shock data for JANAURY, 2010 sent to DGM

(Seismo.), New Delhi. 2.A5 BBS Data in prescribed format in CDR for JANAURY, 2010 sent to DGM (Seismo),

New Delhi. 2.A6 Near earthquake data (∆ ≤ 5 °)for JANAURY, 2010 supplied to RRL, Jorhat 2.A7 Near earthquake data (∆ ≤ 10°)for JANAURY, 2010 supplied to NGRI, Tezpur 2.A8 Monthly technical information for the month of JANAURY, 2009 was sent to DGM

(Seismo.), New Delhi. 2.A9 Recording of BBS is continuing. 2.A10 Recording of GPS at permanent station of CSO. Shillong is continuing. 2.A11 Monthly statement of consumable items for the month of JANAURY, 2010 was sent

to DGM(Seismo), New Delhi. 2.A12. Recording of RTSMN is continuing. 2.A13. Recording of MEQ is continuing. B. METEOROLOGY & RADIATION. 2.B1 Synop data of 03z and 12z were transmitted over VSAT/ PHONE/ PHONOGRAM to

RMC, Guwahati / DDGM(WF), Pune / NHEC, New Delhi regularly . 2.B2 Monthly Meteorological data for JANAURY, 2010 were sent to RMC, Guwahati. 2.B3 Minimum and Maximum temperatures of Shillong were sent to AIR, Shillong and

Doordarshan – Guwahati & Shillong daily. 2.B4 Weekly rainfall data of Shillong were sent to RMC, Guwahati on regular basis.

Page 17: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

17

2.B5 Weekly synop data were sent to DDGM(WF) Pune / RMC, Guwahati on regular basis.

2.B6 Some cases of Met. enquiries / data have been forwarded to RMC, Guwahati for further necessary action.

2.B7 Weekly visibility reports were sent to RMC, Guwahati on regular basis. 2.B8 Monthly flood damage & disaster events report for JANAURY, 2010 sent to RMC,

Guwahati. 2.B9 The following observations took place during the month :- (a). Pyrgeometer : NIL (b). Pyrheliometer : NIL 2.B10 Number of print out from Data logger for global and diffuse solar radiation :28 2.B11 Monthly radiation data for JANAURY, 2010 sent to ADGM ® Pune. 2.B12. Weekly original MMR were sent to RMC, Guwahati on regular basis. 3. TOUR. 3.1 Shri.J.Tamil, Mech Gr-I and Shri.L.B.Chetri,MA were on tour to Seismo Agartala for installation of MEQ Recorder during the month. 4. BUDGET & PLANNING. 4.1 OTA bills, O.E bills, Medical bills and Contingent bills etc. 5. RECEIPTS & DESPATCHED. 5.1 Number of letters receipts during the month = 112 5.2 Number of letter dispatched during the month = 160 6. RECEIPTS / PAYMENTS. 6.1 Medical bills, and O.E. bills, Contingent bills etc. 7. VISITORS. 7.1 Some people visited the Observatory during the month and were explained the

functions of Meteorology, Seismology and Radiation.

Page 18: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

18

( A.C.Lyngdoh ) Meteorologist-in-charge. Copy to: DGM(G/S), New Delhi / DDGM(Seismo), New Delhi / DDGM(Telecom), NEW DELHI/ DDGM(Sat.Met),NEW DELHI/ DDGM (UI), New Delhi / ADGM®, Pune / DDGM(WF), Pune / DDGM (SI), Pune / DDGM (Agrimet), Pune. RMCs : New Delhi / Mumbai / Nagpur / Chennai / Kolkata / Guwahati. Directors : PAC, Kolkata / Seismo. New Delhi / M.O. Kolkata.

( A.C.Lyngdoh ) Meteorologist-in-charge. CSO.SHL.UOI.NO. A-47011/1/2001/ Dt . 03. 2010

Page 19: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

19

Government of India

India Meteorological Department Central Seismological Observatory,

Shillong -793005.

PROGRESS REPORT FOR THE MONTH OF MARCH 2010

1. CHEIF FEATURES 1.1. W.M.O day was observed on 23/3/2010. 2. DATA MANAGEMENT. A. SEISMOLOGY. 2.A1 Number of felt shocks recorded during the month : 17 Nos. 2.A2 Number of Earthquake magnitude 5.0 and above recorded during the month : 01 Nos. 2.A3 Significant earthquake messages were transmitted over MES/FA regularly to

DGM(Seismo.), New Delhi for onward transmission to USGS, USA. 2.A4 Seismological Bulletin and near shock data for FEBRUARY, 2010 sent to DGM

(Seismo.), New Delhi. 2.A5 BBS Data in prescribed format in CDR for FEBRUARY, 2010 sent to DGM

(Seismo), New Delhi. 2.A6 Near earthquake data (∆ ≤ 5 °)for FEBRUARY, 2010 supplied to RRL, Jorhat 2.A7 Near earthquake data (∆ ≤ 10°)for FEBRUARY, 2010 supplied to NGRI, Tezpur 2.A8 Monthly technical information for the month of FEBRUARY, 2009 was sent to DGM

(Seismo.), New Delhi. 2.A9 Recording of BBS is continuing. 2.A10 Recording of GPS at permanent station of CSO. Shillong is continuing. 2.A11 Monthly statement of consumable items for the month of FEBRUARY, 2010 was

sent to DGM(Seismo), New Delhi. 2.A12. Recording of RTSMN is continuing. 2.A13. Recording of MEQ is continuing.

Page 20: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

20

B. METEOROLOGY & RADIATION. 2.B1 Synop data of 03z and 12z were transmitted over VSAT/ PHONE/ PHONOGRAM to

RMC, Guwahati / DDGM(WF), Pune / NHEC, New Delhi regularly . 2.B2 Monthly Meteorological data for FEBRUARY, 2010 were sent to RMC, Guwahati. 2.B3 Minimum and Maximum temperatures of Shillong were sent to AIR, Shillong and

Doordarshan – Guwahati & Shillong daily. 2.B4 Weekly rainfall data of Shillong were sent to RMC, Guwahati on regular basis. 2.B5 Weekly synop data were sent to DDGM(WF) Pune / RMC, Guwahati on regular

basis. 2.B6 Some cases of Met. enquiries / data have been forwarded to RMC, Guwahati for

further necessary action. 2.B7 Weekly visibility reports were sent to RMC, Guwahati on regular basis. 2.B8 Monthly flood damage & disaster events report for FEBRUARY, 2010 sent to RMC,

Guwahati. 2.B9 The following observations took place during the month :- (a). Pyrgeometer : NIL (b). Pyrheliometer : NIL 2.B10 Number of print out from Data logger for global and diffuse solar radiation :31 2.B11 Monthly radiation data for FEBRUARY, 2010 sent to ADGM ® Pune. 2.B12. Weekly original MMR were sent to RMC, Guwahati on regular basis. 3. TOUR. 3.1 Shri.J.Tamil, Mech Gr-I and Shri.A.Kharshong, MA were on tour to Seismo Lekhapani to rectify / install CSIO Recorder from 6/3/2010 to 10/3/2010. 4. BUDGET & PLANNING. 4.1 OTA bills, O.E bills, Medical bills and Contingent bills etc. 5. RECEIPTS & DESPATCHED. 5.1 Number of letters receipts during the month = 80 5.2 Number of letter dispatched during the month = 165

Page 21: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

21

6. RECEIPTS / PAYMENTS. 6.1 Medical bills, and O.E. bills, Contingent bills etc. 7. VISITORS. 7.1 School students from different schools of Meghalaya visited the Observatory on 05/03/2010 as part of National Science Day celebration organized by State Council for Science,Technology and Environment, Government of Meghalaya. 7.2 Headmistress from different schools in Assam visited the Observatory on 19/03/2010 7.3 Trainees as part of training organized by Meghalaya Rural Development Society visited the Observatory on 24/3/2010. ( A.C.Lyngdoh ) Meteorologist-in-charge. Copy to: DGM(G/S), New Delhi / DDGM(Seismo), New Delhi / DDGM(Telecom), NEW DELHI/ DDGM(Sat.Met),NEW DELHI/ DDGM (UI), New Delhi / ADGM®, Pune / DDGM(WF), Pune / DDGM (SI), Pune / DDGM (Agrimet), Pune. RMCs : New Delhi / Mumbai / Nagpur / Chennai / Kolkata / Guwahati. Directors : PAC, Kolkata / Seismo. New Delhi / M.O. Kolkata.

( A.C.Lyngdoh ) Meteorologist-in-charge. CSO.SHL.UOI.NO. A-47011/1/2001/ Dt . 04 2010

Page 22: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

22

Government of India India Meteorological Department

Central Seismological Observatory, Shillong -793005.

PROGRESS REPORT FOR THE MONTH OF APRIL 2010

1. DATA MANAGEMENT. A. SEISMOLOGY. 1.A1 Number of felt shocks recorded during the month : 08 Nos. 1.A2 Number of Earthquake magnitude 5.0 and above recorded during the month : 03 Nos. 1.A3 Significant earthquake messages were transmitted over MES/FA regularly to

DGM(Seismo.), New Delhi for onward transmission to USGS, USA. 1.A4 Seismological Bulletin and near shock data for MARCH, 2010 sent to DGM

(Seismo.), New Delhi. 1.A5 BBS Data in prescribed format in CDR for MARCH, 2010 sent to DGM (Seismo),

New Delhi. 1.A6 Near earthquake data (∆ ≤ 5 °)for MARCH, 2010 supplied to RRL, Jorhat 1.A7 Near earthquake data (∆ ≤ 10°)for MARCH, 2010 supplied to NGRI, Tezpur 1.A8 Monthly technical information for the month of MARCH, 2009 was sent to DGM

(Seismo.), New Delhi. 1.A9 Recording of BBS is continuing. 1.A10 Recording of GPS at permanent station of CSO. Shillong is continuing. 1.A11 Monthly statement of consumable items for the month of MARCH, 2010 was sent

to DGM(Seismo), New Delhi. 1.A12. Recording of RTSMN is continuing. 1.A13. Recording of MEQ is continuing. B. METEOROLOGY & RADIATION. 1.B1 Synop data of 03z and 12z were transmitted over VSAT/ PHONE/ PHONOGRAM to

RMC, Guwahati / DDGM(WF), Pune / NHEC, New Delhi regularly . 1.B2 Monthly Meteorological data for MARCH, 2010 were sent to RMC, Guwahati. 1.B3 Minimum and Maximum temperatures of Shillong were sent to AIR, Shillong and

Doordarshan – Guwahati & Shillong daily. 1.B4 Weekly rainfall data of Shillong were sent to RMC, Guwahati on regular basis. 1.B5 Weekly synop data were sent to DDGM(WF) Pune / RMC, Guwahati on regular

basis.

Page 23: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

23

1.B6 Some cases of Met. enquiries / data have been forwarded to RMC, Guwahati for further necessary action.

1.B7 Weekly visibility reports were sent to RMC, Guwahati on regular basis. 1.B8 Monthly flood damage & disaster events report for MARCH, 2010 sent to RMC,

Guwahati. 1.B9 The following observations took place during the month :- (a). Pyrgeometer : NIL (b). Pyrheliometer : NIL 1.B10 Number of print out from Data logger for global and diffuse solar radiation :30 1.B11 Monthly radiation data for MARCH, 2010 sent to ADGM ® Pune. 1.B12. Weekly original MMR were sent to RMC, Guwahati on regular basis. 2. BUDGET & PLANNING. 2.1 OTA bills, O.E bills, Medical bills and Contingent bills etc. 3. RECEIPTS & DESPATCHED. 3.1 Number of letters receipts during the month = 84 3.2 Number of letter dispatched during the month = 145 4. RECEIPTS / PAYMENTS. 4.1 Medical bills, and O.E. bills, Contingent bills etc. ( A.C.Lyngdoh ) Meteorologist-in-charge. Copy to: DGM(G/S), New Delhi / DDGM(Seismo), New Delhi / DDGM(Telecom), NEW DELHI/ DDGM(Sat.Met),NEW DELHI/ DDGM (UI), New Delhi / ADGM®, Pune / DDGM(WF), Pune / DDGM (SI), Pune / DDGM (Agrimet), Pune. RMCs : New Delhi / Mumbai / Nagpur / Chennai / Kolkata / Guwahati. Directors : PAC, Kolkata / Seismo. New Delhi / M.O. Kolkata.

( A.C.Lyngdoh ) Meteorologist-in-charge. CSO.SHL.UOI.NO. A-47011/1/2001/ Dt . 05 2010

Page 24: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

24

Government of India

India Meteorological Department Central Seismological Observatory,

Shillong -793005.

PROGRESS REPORT FOR THE MONTH OF MAY 2010

1. CHEIF FEATURES 1.1 Antiterrorism day observed on 21/5/2010. 1.2. Dr.A.K.Bansal,Scientist-G, Dr.Verma from MoES and Dr.D.Walia, Associate

professor, NEHU visited the observatory on 21/5/2010. 2. DATA MANAGEMENT. A. SEISMOLOGY. 2.A1 Number of felt shocks recorded during the month : 01 Nos. 2.A2 Number of Earthquake magnitude 5.0 and above recorded during the month : 09 Nos. 2.A3 Significant earthquake messages were transmitted over MES/FA regularly to

DGM(Seismo.), New Delhi for onward transmission to USGS, USA. 2.A4 Seismological Bulletin and near shock data for APRIL, 2010 sent to DGM

(Seismo.), New Delhi. 2.A5 BBS Data in prescribed format in CDR for APRIL, 2010 sent to DGM (Seismo), New

Delhi. 2.A6 Near earthquake data (∆ ≤ 5 °)for APRIL, 2010 supplied to RRL, Jorhat 2.A7 Near earthquake data (∆ ≤ 10°)for APRIL, 2010 supplied to NGRI, Tezpur 2.A8 Monthly technical information for the month of APRIL, 2009 was sent to DGM

(Seismo.), New Delhi. 2.A9 Recording of BBS is continuing. 2.A10 Recording of GPS at permanent station of CSO. Shillong is continuing. 2.A11 Monthly statement of consumable items for the month of APRIL, 2010 was sent to

DGM(Seismo), New Delhi. 2.A12. Recording of RTSMN is continuing. 2.A13. Recording of MEQ is continuing.

Page 25: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

25

B. METEOROLOGY & RADIATION. 2.B1 Synop data of 03z and 12z were transmitted over VSAT/ PHONE/ PHONOGRAM to

RMC, Guwahati / DDGM(WF), Pune / NHEC, New Delhi regularly . 2.B2 Monthly Meteorological data for APRIL, 2010 were sent to RMC, Guwahati. 2.B3 Minimum and Maximum temperatures of Shillong were sent to AIR, Shillong and

Doordarshan – Guwahati & Shillong daily. 2.B4 Weekly rainfall data of Shillong were sent to RMC, Guwahati on regular basis. 2.B5 Weekly synop data were sent to DDGM(WF) Pune / RMC, Guwahati on regular

basis. 2.B6 Some cases of Met. enquiries / data have been forwarded to RMC, Guwahati for

further necessary action. 2.B7 Weekly visibility reports were sent to RMC, Guwahati on regular basis. 2.B8 Monthly flood damage & disaster events report for APRIL, 2010 sent to RMC,

Guwahati. 2.B9 The following observations took place during the month :- (a). Pyrgeometer : NIL (b). Pyrheliometer : NIL 2.B10 Number of print out from Data logger for global and diffuse solar radiation :31 2.B11 Monthly radiation data for APRIL, 2010 sent to ADGM ® Pune. 2.B12. Weekly original MMR were sent to RMC, Guwahati on regular basis. 3. BUDGET & PLANNING. 3.1 OTA bills, O.E bills, Medical bills and Contingent bills etc. 4. RECEIPTS & DESPATCHED. 4.1 Number of letters receipts during the month = 112 4.2 Number of letter dispatched during the month = 130 5. RECEIPTS / PAYMENTS. 5.1 Medical bills, and O.E. bills, Contingent bills etc. 6. RESEARCH & PUBLICATION. 6.1 Shri.A.C.Lyngdoh, Meteorologist Gr-I took part in the poster session and as co author of the paper entitled Radon Concentration in Drinking water of Eastern part of Shillong at the National Seminar on Applications of Radiation Technology in Medical Sciences (ARTMS) on May 15th, 2010 at North East Indira Gandhi Regional Institute of Health and Medical Sciences(NEIGRIHMS), Shillong-18 organized by: NEIGRIHMS and Department of Atomic Energy (DAE), GOI, Mumbai

Page 26: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

26

Sd/- ( A.C.Lyngdoh ) Meteorologist-in-charge. Copy to: DGM(G/S), New Delhi / DDGM(Seismo), New Delhi / DDGM(Telecom), NEW DELHI/ DDGM(Sat.Met),NEW DELHI/ DDGM (UI), New Delhi / ADGM®, Pune / DDGM(WF), Pune / DDGM (SI), Pune / DDGM (Agrimet), Pune. RMCs : New Delhi / Mumbai / Nagpur / Chennai / Kolkata / Guwahati. Directors : PAC, Kolkata / Seismo. New Delhi / M.O. Kolkata.

Sd/- ( A.C.Lyngdoh ) Meteorologist-in-charge. CSO.SHL.UOI.NO. A-47011/1/2001/ Dt . 06 2010

Page 27: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

27

Government of India India Meteorological Department

Central Seismological Observatory, Shillong -793005.

PROGRESS REPORT FOR THE MONTH OF SEPTEMBER 2010

1. CHEIF FEATURES 1.1 Shri.A.C.Lyngdoh, Meteorologist in charge, CSO, Shillong was on tour to IIT Guwahati in connection with Supervision of construction of Seismic pillar in connection with North East Seismic Telemetry Network. 1.2 Hindi day was observed on 20/9/2010 and various activities were engaged to promote Hindi language. 2. DATA MANAGEMENT. A. SEISMOLOGY. 2.A1 Number of felt shocks recorded during the month : 02. 2.A2 Number of Earthquake magnitude 5.0 and above recorded during the month : 13 Nos. 2.A3 Significant earthquake messages were transmitted over MES/FA regularly to

DGM(Seismo.), New Delhi for onward transmission to USGS, USA. 2.A4 Seismological Bulletin and near shock data for August, 2010 sent to DGM

(Seismo.), New Delhi. 2.A5 BBS Data in prescribed format in CDR for August, 2010 sent to DGM (Seismo),

New Delhi. 2.A6 Near earthquake data (∆ ≤ 5 °)for August, 2010 supplied to RRL, Jorhat 2.A7 Near earthquake data (∆ ≤ 10°)for August, 2010 supplied to NGRI, Tezpur 2.A8 Monthly technical information for the month of August, 2010 was sent to DGM

(Seismo.), New Delhi. 2.A9 Recording of BBS is continuing. 2.A10 Recording of GPS at permanent station of CSO. Shillong is continuing. 2.A11 Monthly statement of consumable items for the month of August, 2010 was sent to

DGM(Seismo), New Delhi. 2.A12. Recording of RTSMN is continuing. 2.A13. Recording of MEQ is continuing.

Page 28: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

28

B. METEOROLOGY & RADIATION. 2.B1 Synop data of 03z and 12z were transmitted over VSAT/ PHONE/ PHONOGRAM to

RMC, Guwahati / DDGM(WF), Pune / NHEC, New Delhi regularly . 2.B2 Monthly Meteorological data for August, 2010 were sent to RMC, Guwahati. 2.B3 Minimum and Maximum temperatures of Shillong were sent to AIR, Shillong and

Doordarshan – Guwahati & Shillong daily. 2.B4 Weekly rainfall data of Shillong were sent to RMC, Guwahati on regular basis. 2.B5 Weekly synop data were sent to DDGM(WF) Pune / RMC, Guwahati on regular

basis. 2.B6 Some cases of Met. enquiries / data have been forwarded to RMC, Guwahati for

further necessary action. 2.B7 Weekly visibility reports were sent to RMC, Guwahati on regular basis. 2.B8 Monthly flood damage & disaster events report for August, 2010 sent to RMC,

Guwahati. 2.B9 The following observations took place during the month :- (a). Pyrgeometer : NIL (b). Pyrheliometer : NIL 2.B10 Number of print out from Data logger for global and diffuse solar radiation :30 2.B11 Monthly radiation data for August, 2010 sent to ADGM ® Pune. 2.B12. Weekly original MMR were sent to RMC, Guwahati on regular basis. 3. BUDGET & PLANNING. 3.1 Macp arrear bills, OTA bills, O.E bills, Medical bills and Contingent bills etc. 4. RECEIPTS & DESPATCHED. 4.1 Number of letters receipts during the month = 120 4.2 Number of letter dispatched during the month = 118 5. RECEIPTS / PAYMENTS. 5.1 Medical bills, and O.E. bills, Contingent bills etc.

Page 29: Government of India India Meteorological Department ...metnet.imd.gov.in/progressreports/1111992010-09PROGRESS REPORT FOR...India Meteorological Department Central Seismological Observatory,

29

6. RESEARCH & PUBLICATION. 6.1 A paper entitled “ Recent trends in Meteorological Parameters indicating tendencies in climate change in and around Shillong and Sohra (Cherrapunjee)” authored by Shri.A.C.Lyngdoh, I.Panda, M.Taid and B.Sinha was submitted for National conference on climate change-Environmental Apocalypse- Human ethics in question at Synod College, Shillong.

Sd/- ( A.C.Lyngdoh ) Meteorologist-in-charge. Copy to: DGM(G/S), New Delhi / DDGM(Seismo), New Delhi / DDGM(Telecom), NEW DELHI/ DDGM(Sat.Met),NEW DELHI/ DDGM (UI), New Delhi / ADGM®, Pune / DDGM(WF), Pune / DDGM (SI), Pune / DDGM (Agrimet), Pune. RMCs : New Delhi / Mumbai / Nagpur / Chennai / Kolkata / Guwahati. Directors : PAC, Kolkata / Seismo. New Delhi / M.O. Kolkata.