gotland power-to-gas feasibility study (sweco)
TRANSCRIPT
POWER TO GAS GOTLAND – OVERVIEW AND PARTIAL RESULTS 2016-06-22
2016-06-29 1
Sweden 2025 Lindfeldt, Saxe, Magnusson, Mohseni
Applied Energy, 2010
Sweden 2030 Fossilfrihet på väg, Prof. Thomas B Johansson, 2013
Europe 2030 (total 5000 TWh) Audi, Dr. Hermann Pengg, 2016 BULK!!!
Feasibility study
• Feasibility study for the first MW-scale PtG plant in Sweden • Location • Technology • Economical aspects • Regulatory issues
• Continuation of the previous ”location study”
• Many local actors interested • Broad project group involved – Gas grid
owners, Electricity grid owners, Industry, Energy Companies, Component manufacturers, Gotland Municipality etc. Malmö
Göteborg
Stockholm
Current situation on Gotland
• Existing main land cable connection 200 MW
• New 300 MW cable in 2021 at the earliest
• Visions of 1000 MW in 2030
• PtG as seasonal energy storage and/or for fuel production
• Possible CO2-sources • Existing biogasproduction
• Industry (e.g Cementa)
• Spendrups beer production
Malmö
Göteborg
Stockholm
Wind Power vs Main land cable connection
0
200
400
600
800
1000
1200
Nuvarande utrymmeför vindkraft (2014)
Vision om vindkraft till2020
Planeradfastlandskabel i drift
2021
Vision om vindkraft till2025
Vision om nyfastlandskabel under
2020-talet
Kap
acit
et (
MW
)
Business case PtG (SNG) • System efficiency electricity to methane roughly 50 %
• Hence methane must be sold 2 x electricity price (per kWh) to cover only the electricity cost
• Additional spread needed to cover investment costs, operational costs, m.m.
• CO2 source and electricity production close to eachother
• Free CO2
• Spread between electricity price and biogas price per kWh • If possible, be able to use added value of electrolyser eg. balancning, lowering feed
in-costs etc.
• Existing infrastructure for methane
• Possibility to sell heat
• Possibility to sell oxygen
Digestion process
Förnybar el Elektrolys
Power to Gas vs. Conventional biogas production
CO₂- separation
60m³ CH₄ 40m³ CO₂
40m³ CO₂
60m³ CH₄ (=vehicle gas)
> 95 m³ CH₄
H₂
CO₂- methanation
Via Power to Gas - CO2 används som råvara för ytterligare metanproduktion
+60%
Visby
Klintehamn
22 GWh
4-5 GWh?
Crude gas production
Wind Power >20 MW
2 - 3 MW
Pipeline
Scene Gotland
Slite (Cementa)
Upgrading facility
0
200
400
600
800
1000
1200
1400
1600
0 1000 2000 3000 4000 5000 6000 7000 8000
SEK
/MW
h
Timme
Price duration curve 2015 - SE3
Elpris Medelpris el
Ca 2 €cent/kWh + grid fees
Vehicle gas Ca 8-12 €cent/kWh
Hydrogen price Ca 25-30 €cent/kWh
Upgrading
Crude gas production
PtG incl electrolysis
CH4/CO2 ≈ 60/40
Gas cleaning
PtG + Electrolysis at upgrading
Visby
Brogas
Advantages • Have good possibilities to sell heat to
surrounding processes eg. district heating grid or Arla
• Miminum distribution needs of H2, CO2 or CH4
• Existing storage for end product Disadvantages • Grid fees are relatively high
Electricity [PROCENT]
Grid fees [PROCENT]
Water [PROCENT]
Employment costs
[PROCENT]
OPERATIONAL COSTS
Synthetic methane
[PROCENT]
Oxygen [PROCENT]
District heating
[PROCENT]
REVENUES
Fördelning av kostnader och Intäkter
Brogas
Everything in Klintehamn - if biogas production plans are executed
• Local grid use (IKN) • Heat needs in the surroundig • Minimal transportation of H2 required
Visby
Klintehamn
Upgrading
Crude gas production
PtG incl electrolysis
Gas cleaning