GNSS PROJECT (PHASE-I) With the completion of the above packages, an Irrigation Potential 35,000 Ac will be created in Kadapa District in Phase-I. GORAKALLU RESERVIOR Capacity: 10.29 TMC FRL : +261 M Package: Open Category POTHIREDDYPADU HEAD REGULATOR Sill : +841’ BANAKACHERLA CROSS REGULATOR OWK RESERVOIR 4.31TMC GANDIKOTA RESERVOIR FRL + 209 M CAP: 11.943 TMC(Live) 16.840 TMC (Gross) KM 0.00 KM 32.64 SRMC SRBC VAMIKONDA SAGAR (3.249 TMC) SARVARAJA SAGAR (3.059 TMC) KM 24.33 KM 52.875 KM 34.80 KM 16.50 PKG 89 PKG 47 PKG 1 PKG 2 PKG 48 PKG 49 SRBC Bypass canal (5 M dia) 16.225 KM 56.775 KM 57.700 KM GNSS Flood Flow Canal GNSS FFC Tunnel 5.25 Km Completed Work in Progress Tender Stage LEGEND

Upload: lynn-powers

Post on 03-Jan-2016

227 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: GNSS PROJECT (PHASE-I) With the completion of the above packages, an Irrigation Potential 35,000 Ac will be created in Kadapa District in Phase-I. GORAKALLU

GNSS PROJECT (PHASE-I)

With the completion of the above packages, an Irrigation Potential 35,000 Ac will be created in Kadapa District in Phase-I.

GORAKALLU RESERVIORCapacity: 10.29 TMC FRL : +261 MPackage: Open Category

PO

TH

IRE

DD

YP

AD

U H

EA

D R

EG

ULA

TO

RS

ill :

+84

1’

BA

NA

KA

CH

ER

LA

CR

OS

S R

EG

ULA

TO

ROWK

RESERVOIR4.31TMC

GANDIKOTA RESERVOIRFRL + 209 MCAP: 11.943 TMC(Live) 16.840 TMC (Gross)

KM

0.0

0

KM

32.

64

SRMC SRBC

VA

MIK

ON

DA

S

AG

AR

(3.2

49 T

MC

)

SA

RV

AR

AJA

SA

GA

R(3

.059

TM

C)

KM

24.

33

KM

52.

875

KM

34.

80

KM

16.

50

PKG 89

PK

G 4

7

PKG 1 PKG 2

PK

G 4

8

PK

G 4

9

SRBC Bypass canal (5 M dia)

16.225 KM 56.775 KM 57.700 KM

GNSS Flood Flow Canal GNSS FFC

Tunnel 5.25 Km

Completed

Work in Progress

Tender Stage

LEGEND

Page 2: GNSS PROJECT (PHASE-I) With the completion of the above packages, an Irrigation Potential 35,000 Ac will be created in Kadapa District in Phase-I. GORAKALLU

1 PROJECT PROFILELocation of Head works : Pothireddypadu Head regulator, foreshore of Srisailam Reservoir

2 Admn. Sanction : G. O. Ms. No. 53, Dt: 1-6-04 for Rs. 560.00 Crs.G. O. Ms. No. 5, Dt: 11-1-05 for Rs. 271.00 Crs.G. O. Ms. No. 108, Dt: 2-3-05 for Rs. 340.00 Crs.

3 No. of Packages (EPC) : 6

4 Agreement value of packages

: Rs. 1055.84 Crs.

5 Budget Provision :

Rs. 330.00 Crs.

6 Expenditure

2004-05 : Rs. 67.09 Crs.

2005-06 : Rs. 222.57 Crs.

Cum. Exp. : Rs. 289.66 Crs.

7 Utilisation : 38 TMC

8 Ayacut Ultimate : 2.6 Lakh acres (Cuddapah: 1,55,000 Acres, Chittoor: 1,03,500 Acres, Nellore: 1500 Acres)

Phase-I : 35,000 Acres in Kadapa District

GNSS PROJECT (PHASE-I)

Page 3: GNSS PROJECT (PHASE-I) With the completion of the above packages, an Irrigation Potential 35,000 Ac will be created in Kadapa District in Phase-I. GORAKALLU

9 Land Acquisition (Ultimate)

Required : 26,284 acres

Requisitioned : 22,223 acres

Acquired : 4,082 acres

10 Mob. Advance. Paid Recovered

2004-05 : Rs. 67.09 Crs. --

2005-06 : Rs. 11.26 Crs. Rs. 30.64 Crs

Total : Rs. 78.35 Crs. Rs. 30.64 Crs.

11 Target Date : 3/2008

GNSS PROJECT (PHASE-I)

Page 4: GNSS PROJECT (PHASE-I) With the completion of the above packages, an Irrigation Potential 35,000 Ac will be created in Kadapa District in Phase-I. GORAKALLU

PKG No.

DescriptionName of

Contractor

Bid /Agreement

AmountRs in Crs.

Agreement

concluded date

Mobilisation Advanace Rs. in Crs.

1

Construction of Gandikota Reservoir across river Pennar and Head regulator. Excavation of Main canal from KM 0.00 to KM 24.33, including CM & CD works, distributories, field channels etc.,

M/s Mythas – NCC, Hyderabad

250.20 3 / 2005 12.51

2

Excavation of Main canal from KM 24.33 to KM 32.64, formation of Vamikonda and Sarvaraja sagar reservoirs including CM & CD works, distributories, field channels complete

M/s Gammon India Ltd.

294.45 3/2005 13.72

OCGadikota LI Scheme (Gandikota Reservoir to Pulivendula Branch Canal)

M/s KBLM – CCL (JV)

286.00 3/2005 14.30

47

Excavation of GNSS Flood flow canal from Owk Reservoir to Gandikota Reservoir from 0.00 KM to 16.50 KM, including Head regulator, CM & CD works

Engineers & Contractors,

Hyd72.997 28-2-2005 3.65

48

Excavation of GNSS Flood flow canal from Owk Reservoir to Gandikota Reservoir from 16.50 KM to 34.80 KM including Head regulator, CM & CD works

Coramandal Prestcerte

(P) Ltd, Hyd.78.559

28-2-2005 3.927

49

Excavation of GNSS Flood flow canal from Owk Reservoir to Gandikota Reservoir from 34.80 KM to 52.87 KM including Head regulator, CM & CD works

Coramandal Prestcerte(P

)Ltd, Hyd 73.65 28-2-2005 3.682

1055.84

GNSS PROJECT (PHASE-I)

Page 5: GNSS PROJECT (PHASE-I) With the completion of the above packages, an Irrigation Potential 35,000 Ac will be created in Kadapa District in Phase-I. GORAKALLU

Package No.1 [EPC System]

i. Construction of Gandikota dam across Penna river.

ii. Earth work excavation of main canal from Km. 0.000 to Km.24.330, fabrication and erection of radial crest gates, stop log gates and its accessories, river sluice gates, gantry crane etc.

iii. Construction of Head Regulator.

GALERU NAGARI SUJALA SRAVANTHI

Name of the Contractor : M/s MAYTAS-NCC (JV), Hyd. Agreement Amount : Rs. 250.20 Crs.

Agreement Date : 25-10-2004

Period of Completion : 30 Months

Target date of Completion : 4/2007

Investigation : Completed

Design (Canal) : 12 Km length approved against 24.33 Kms. Completed

Execution (Canal) : 12 Km length completed against 24.33 Kms.

Execution (Dam) : Exploring drilling completed.

Qty. of earth work done : 52,93,972 cum against 81,98,000 cum

Qty. of concrete work done : 2,807 cum against 3,04,000 cum

Expenditure : Rs. 78.21 Crs. (Inc. Mob. Adv. Rs. 12.51 Crs.) against Rs. 250.20 Crs.

2004-05 : Rs. 12.51 Crores (mob. Adv. Only)

2005-06 : Rs. 65.7 Crores.

Land Acquisition : Required 16397 Ac. Acquired 3398 Ac. Requisitioned:16398 Acs

R & R : Estimate under preparation

Page 6: GNSS PROJECT (PHASE-I) With the completion of the above packages, an Irrigation Potential 35,000 Ac will be created in Kadapa District in Phase-I. GORAKALLU

Package No. 2

i. Excavation of main canal from Km. 24.33 to Km. 32.64.

ii. Formation of Vamikonda Sagar and Sarvaraya Sagar reservoir and leading channels to reservoirs and its distributaries etc.

Name of the Contractor : M/s Gammon India Ltd., Mumbai

Agreement Amount : Rs. 294.45 Crs.

Agreement Date : 25-10-2004

Period of Completion : 30 Months

Target date of completion : 4/2007

Investigation : Completed

Design : 5 Km length approved against 10 Km

Structures : Under Approval

Execution : 6.5 Km length in progress against 10 Km

Qty. of earth work done: 6 T cum against 7.73 T cum

Expenditure : Rs. 43.78 Crs. (inc. mob. adv. Rs. 14.72 Crs)

against Rs. 394.45 Crs.

2004-05 : Rs. 14.72 Crs. (Mob. Adv.)

2005-06 : Rs. 29.06 Crs.

Land Acquisition : Required – 5253 Ac. Requisitioned : 5053 Acres

Acquired : 419 Acres.

R & R : Estimate under preparation

GALERU NAGARI SUJALA SRAVANTHI

Page 7: GNSS PROJECT (PHASE-I) With the completion of the above packages, an Irrigation Potential 35,000 Ac will be created in Kadapa District in Phase-I. GORAKALLU

Package No.47 / Cat – II

i. Flood Flow Canal from Owk Reservoir to

Gandikota Reservoir including

construction of Head Regulator from

Km.0.000 to Km. 16.500..

Name of the Contractor : Engineers & Contractors, Hyd.

Agreement Amount : Rs. 72.99 Crs.

Agreement Date : 28-2-2005

Period of Completion : 24 Months

Target date of completion : 2/2007

GALERU NAGARI SUJALA SRAVANTHI

Investigation : Length in 17.954 KMs against 17.954 KMs – Completed

a) Designs approved length 17.954 in KMS against 17.954 KMS - Approved

b) Structures approved 17 Nos. against total 17 Nos. of Structures – Approved

a) Execution: Length in 8.00 KM in progress against total length of 17.954 KM

b) Structures approved - Nil - Nos. against total 17 Nos. of Structures

a) Qty. of earth work done : 20,25,000 Cum against 49,36,500 Cum.

b) Qty. of Concrete works done - Nil - Cum against 46,000 cum.

No. of Machinery (Machinery wise) deployed.Excavaters - 11,Tippers-45,Dozers-3,Compressers-8,Wagon Drills -8, Water Tankers-3

Expenditure : Rs 28.97 Crs. (including Mob. Adv. Rs. 7.30 Crs.) against Rs. 72.999 Crores 2004-05 : Rs. 3.65 Crs (Mob. Adv. Only) 2005-06 : Rs. 25.32 Crs. (Inc. Mob. Adv. Rs. 3.65 Crs.) Mob. Adv. Recovered : Rs. 3.63 Crores Land Acquisition : Required : 640 Acres; Acquired : Nil, Requisitioned 640 Acres.

Page 8: GNSS PROJECT (PHASE-I) With the completion of the above packages, an Irrigation Potential 35,000 Ac will be created in Kadapa District in Phase-I. GORAKALLU

Package No.48 / Cat – II

i. Flood Flow Canal from Owk Reservoir to Gandikota Reservoir including construction of CM & CD works from Km.16.500 to Km. 34.800.

Name of the Contractor : Coramandal Prestcerte(P)Ltd, Hyd.

Agreement Amount : Rs. 78.55 Crs.

Agreement Date : 28-2-2005

Period of Completion : 24 Months

Target date of Completion: 2/2007

GALERU NAGARI SUJALA SRAVANTHI

Investigation : Length in 16.02 KMs against 16.02 KMs – Completed

a) Designs approved length 16.02 in KMS against 16.02 KMS – Approved

b) Structures approved Nil. against total 19 Nos. of Structures

a) Execution: Length in 7 KM in progress against total length of 16.02 KM

b) Structures approved - 9 Nos. against total 19 Nos. of Structures

a)Qty. of earth work done 25,50,000 Cum Against 50,15,000 cum

No of Machinery deployed. (Excavators – 5, Tippers – 15, Dozer – 3, Compressors – 13, Wagon drills -13)

Expenditure: Rs. 48.78 Crs. (inc. mob. Adv. of Rs. 7.86 Crs. against Rs. 78.56

Crs.2004-05 : Rs. 3.93 Crs (Mob. Adv.)2005-06 : Rs. 44.85 Crs. (Inc. Mob. Adv. Rs. 3.93 Crs) Mob. Advance Recovered : Rs. 7.86 Crores Land Acquisition : Required : 576 Acres ; Acquired : Nil, Requisitioned –

576 Acres

Page 9: GNSS PROJECT (PHASE-I) With the completion of the above packages, an Irrigation Potential 35,000 Ac will be created in Kadapa District in Phase-I. GORAKALLU

Package No.49 / Cat – II

i. Flood Flow Canal from Owk Reservoir to Gandikota Reservoir including construction of CM & CD works from Km.34.800 to Km. 52.300.

Name of Contractor : Coramandal Prestcerte (P)Ltd

Agreement Amount : Rs. 73.658 Crs.

Agreement Date : 28-2-2005

Period of Completion : 24 Months

Target date of Completion: 2/2007

GALERU NAGARI SUJALA SRAVANTHI

1 Investigation : Length in 17.4 KMs against 17.4 KMs - Completed

2 a) Designs approved length 17.4 in KMS against 17.4 KMS – Approved

3 a) Execution: Length in 13 KMs in progress against total length of 17.4 KM

4 a) Qty. of earth work done 43.8 Lakhs Cum against 57.26 Lakhs Cum.

b) Qty. of Concrete works done - Nil - Cum against 13 Nos of Structure Concrete.

5No. of Machinery (Machinery wise) deployed ; Excavators -8,Tippers-12, Dozers-6, Compressors-10, Wagon Drill-10.

6 Expenditure : Rs. 50.60 Crs. (including advances Rs. 7.36 Crs. against Rs. 73.66 Crs.

2004-05 : Rs. 3.68 Crs. (Mob. Adv)2005-06 : Rs. 46.92 Crs. (Inc. Mob. Adv. Rs. 3.68 Crs)Mob. Advance Recovered : Rs. 7.36 Crores

Land Acquisition : Required : 737 Acres ; Acquired : Nil, Acquired – 737 Acres