    1st Global Workshop Plan

    2010.05.27

    Global ERP Project TFT

  • 8/4/2019 Global Workshop Plan en v.2.5

    2/10

    1. Global Workshop Overview

    To share the current status and future plan of LOTTE Conf. Global ERP project

    To introduce SAP ERP for global members To share the candidates for global common processes

    To find gaps between Korea and overseas companies

    To draw action items based on the gaps discussed and establish the future plan

    Objectives

    Period : 2010.08.16 ~ 2010.08.20

    Venue : LOTTE Conf., Korea

    Venue

    Before the 1st global workshop, overseas PI members must prepare the following(Refer to theattached files on page 2 :

    - As-Is Process Model- Business Requirement- Master Data- Organization Structure- System Structure- Application Menu List

    Assignment

  • 8/4/2019 Global Workshop Plan en v.2.5

    3/10

  • 8/4/2019 Global Workshop Plan en v.2.5

    4/10

    21 22 23 24 25 28 29 30 1 2 5 6 7 8 9 12 13 14 15 16 19 20 21 22 23 26 27 28 29 30 2 3 4 5 6 9 10 11 12 13 16 17 18 19 20

    Distribute W/S Plan and Template

    Define To-Be Processes

    Review As-Is Status

    for Overseas Company

    Decide candidates for

    global common process

    Prepare As-Is Status i.e. process flow, master data, etc.

    Review Material from LOTTE

    (i.e. Candidates for Global)

    2010.06 2010.07 2010.08

    LOTTE

    Conf.

    China

    India

    Belgium

    Vietnam

    2. Global Workshop Plan

    1st GlobalWorkshop

    Prepare As-Is Status As-Is Process Model Org. Structure Master Data System Business Requirement

    Review W/S material Review the candidates for global common

    processes defined by LOTTE Conf.

    1st Global W/S Review the candidates for global

    process and find FIT/GAPs

    Define action items and plan

    Global Common Processes

    Review As-Is Status fromoverseas companies

    Decide candidates for globalcommon processes

  • 8/4/2019 Global Workshop Plan en v.2.5

    5/10

    3. Workshop Plan(Day 1)

    Date Time Slot Room No. Subject Responsibility Remarks

    2010-0

    8-

    16(M

    on)

    10:00 - 10:30GreetingIntroduction to 1st Global Workshop

    10:30 - 10:45 Introduce PI and Consultants

    10:45 - 12:00

    Introduction to LOTTE Conf. Global ERP Project- Project Status- Roll-Out Plan- Project Scope

    12:00 - 13:00 Lunch

    13:00 - 14:00 [COMMON SESSION]SAP Overview

    14:00 - 14:10 Break

    14:10 - 15:40 [BREAKOUT SESSION]Training - FI, CO, MM, SD, PP

    15:40 - 16:00 Break

    16:00 - 17:30 [BREAKOUT SESSION]Training - FI, CO, MM, SD, PP

    17:30 - 18:00 Wrap Up

  • 8/4/2019 Global Workshop Plan en v.2.5

    6/10

    3. Workshop Plan(Day 2)

    Date Time Slot Room No. Subject Responsibility Remarks

    2010-08-17(Tue)

    09:00 - 10:30

    [BREAKOUT SESSION]Discuss ion on candidates for global common process and AS-ISprocesses of overseas companies FI, CO, MM, PP, SD

    Find fit and gap Draw action Item s and establish plan

    10:30 - 12:00

    12:00 - 13:00 Lunch

    13:00 - 16:45

    [BREAKOUT SESSION]Discuss ion on candidates for global common process and AS-ISprocesses of overseas companies FI, CO, MM, SD, PP

    Find fit and gap

    Draw action Item s and establish plan

    13:00 - 16:30

    17:30 - 18:00 Wrap Up

  • 8/4/2019 Global Workshop Plan en v.2.5

    7/10

    3. Workshop Plan(Day 3)

    Date Time Slot Room No. Subject Responsibility Remarks

    2010-08-18(Tue)

    09:00 - 10:30

    [BREAKOUT SESSION]Discuss ion on candidates for global common process and AS-ISprocesses of overseas companies FI, CO, MM, SD, PP Find fit and gap

    Draw action Item s and establish plan

    10:30 - 12:00

    12:00 - 13:00 Lunch

    13:00 - 16:45

    [BREAKOUT SESSION]Discuss ion on candidates for global common process and AS-IS

    processes of overseas companies FI, CO, MM, SD, PP

    Find fit and gap

    Draw action Item s and establish plan13:00 - 16:30

    17:30 - 18:00 Wrap Up

  • 8/4/2019 Global Workshop Plan en v.2.5

    8/10

    3. Workshop Plan(Day 4)

    Date Time Slot Room No. Subject Responsibility Remarks

    2010-08-19(Tue)

    09:00 - 10:30

    [BREAKOUT SESSION]Discuss ion on candidates for global common process and AS-ISprocesses of overseas companies FI, CO, MM, SD, PP

    Find fit and gap Draw action Item s and establish plan

    10:30 - 12:00

    12:00 - 13:00 Lunch

    13:00 - 16:45

    [BREAKOUT SESSION]Discuss ion on candidates for global common process and AS-ISprocesses of overseas companies FI, CO, MM, SD, PP

    Find fit and gap

    Draw action Item s and establish plan13:00 - 16:30

    17:30 - 18:00 Wrap Up

  • 8/4/2019 Global Workshop Plan en v.2.5

    9/10

    3. Workshop Plan(Day 5)

    Date Time Slot Room No. Subject Responsibility Remarks

    2010-0

    8-

    20(Fri)

    09:00 - 12:00 M1

    [BREAKOUT SESSION]Prepare deliverables FI, CO, MM, PP, SD- Fit and Gap List- Action Items and Plan

    12:00 - 13:00 Lunch

    13:00 - 13:40

    M1

    [COMMON SESSION]Presentation CO

    13:40 - 14:20 [COMMON SESSION]Presentation FI

    14:20 - 14:30 Break

    14:30 - 15:10 [COMMON SESSION]Presentation MM

    15:10 - 15:50 [COMMON SESSION]Presentation PP

    15:50 - 16:00 Break

    16:00 - 16:40 [COMMON SESSION]Presentation - SD

    16:40 - 17:30 Wrap Up

  • 8/4/2019 Global Workshop Plan en v.2.5

    10/10

    3. Participants for the 1st Global Workshop

    Korea China India Vietnam Belgium

    FI () Subramanian

    CO Subramanian

    MM Vincent Prabhaka Kurt Tollenaere

    PP Sundararajan Marleen Brijs

    SD Ranganathan Vicky Altruye

    IT () R Prakash Petra Hillaert

    Program

    Manager Kim Kyo Hee Paul Bevers

    ()